1 SECTION EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Contractor shall be held to have read all Bidding Requirements; all of the General Conditions and Supplementary General Conditions and all Divisions of the Technical Specifications before submitting a bid for the proposed work, and in the execution of the work, they will be bound by all of the conditions and requirements therein. 1.2 SUMMARY A. Temporary Sediment Controls: Water control, dust control, erosion and sediment control. B. Requirements set forth in the Storm Water Pollution Prevention Plan (SWPPP) to be provided to the Contractor by the Owner prior to the start of construction. 1.3 COORDINATION A. General Conditions of the Contract for Construction. 1.4 SUBMITTALS A. Submit product specifications for all packaged materials. B. Submit gradation reports for all bulk aggregate and infiltration materials. C. Submit percolation+testing results for all infiltration materials. 1.5 PRODUCT HANDLING A. Store materials properly to prevent damage, deterioration, and contamination. 1. Aggregates shall be stockpiled in a well+drained location. 2. Packaged materials shall be delivered in their original unopened containers and stored in a weatherproof enclosure. 1.6 JOB CONDITIONS A. At all locations of temporary sedimentation basins, stake out all existing and proposed utilities to check for conflicts, prior to excavation. B. During excavation if any existing utilities, either know or unknown are encountered, it shall be immediately reported to the Owner s 1.7 APPLICABLE CODES, STANDARDS AND SPECIFICATIONS A. New York State Standards and Specifications for Erosion and Sedimentation Control, August,

2 B. New York State Stormwater Management Design Manual (January 2015). C. New York State Department of Environmental Conservation SPDES General Permit for Stormwater Discharges from Construction Activities (Permit No. GP ). D. New York State Department of Transportation Standard Specifications of May 1, 2008 and all Addenda. 1.8 WATER CONTROL A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment as required. B. Protect site from ponding, puddling, or running water. Provide control measures as required to protect site from water erosion. 1.9 DUST CONTROL A. Execute work by methods to minimize dust from construction operations. B. Provide positive means to prevent air+borne dust from dispersing into atmosphere EROSION AND SEDIMENT CONTROL A. The Contractor is responsible for the implementation and maintenance of erosion control measures and structures as set forth in the SWPPP. The Contractor shall exercise diligence to continuously monitor and evaluate erosion control measures on a regular basis, including after rainfall events, and maintain and modify erosion control measures as necessary. B. Plan and execute construction by methods to control surface drainage from cuts and fills, from borrow and waste disposal areas. C. The contractor shall confine grading operations and ground disturbance inside the designated project limits. Disturbance of areas outside project limits shall not be permitted without prior approval from the Owner. D. Install temporary erosion control measures prior to the start of construction activities. E. Minimize amount of bare soil exposed at one time. The Contractor shall also minimize the disturbance of any perimeter buffer areas or areas designated as to remain undisturbed, if any, as delineated on the plans. F. Provide temporary measures such as berms, dikes, silt fencing, straw bales, inlet sediment traps, and drains. The Contractor shall install and maintain all erosion control and sedimentation measures in accordance with this section and the requirements specified in the NYSDOT Standard Specifications, Section G. Storm drain inlet protection shall be installed at all catch basins, receivers and yard drains unless directed otherwise by the Architect/Engineer

3 H. Construct fill and waste areas by selective placement to avoid erosive surface silts or clays. I. The Contractor shall remove sediment accumulated in the structures periodically as necessary and at the end of construction and dispose off+site in a stable location as approved by the Architect/Engineer. J. Periodically inspect earthwork to detect evidence of erosion and sedimentation; promptly apply corrective measures. Additional measures may be necessary to correct deficiencies and provide adequate control for unforeseen site conditions and extreme weather. K. All temporary erosion control measures shall remain in place and maintained until all disturbed areas have become stabilized CONSTRUCTION SEQUENCE A. Construction activities shall be scheduled by the Contractor with the intent to minimize the amount of disturbed area at any one time as well as the length of exposure. In general, once work has been started on a particular phase or structure, this work shall be completed, to the extent possible, before work on another phase or structure is started. It will be the Contractor s responsibility to evaluate potential hazards and to use temporary measures to stabilize any areas of incomplete work. Specific scheduling of critical construction events and erosion control measures shall be as follows: 1. Field stakeout drainage structures, and erosion control measures by qualified personnel. 2. Install perimeter controls, silt fencing, and stabilized construction entrance. 3. Strip topsoil inside clearing limits as necessary. Stockpile topsoil if uncontaminated in stable areas and stabilize with temporary seed and mulch as required. 4. Perform excavations for demolitions and new constructions. Seed and mulch all new work as required. 5. Install protection around existing catch basins and new yard drains. Perform final grading and construct road subbase. 6. Maintain erosion control measures, re+seed and mulch remaining areas as necessary until vegetation is fully established POLLUTION CONTROL A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations. PART 2 MATERIALS 2.1 MATERIALS A. Silt Fence: Mirafi Envirofence, prefabricated silt fence, incorporating Mirafi 100X woven fabric, 1+1/4 square hardwood posts (spacing of 8.3 linear feet), plastic net backing for additional reinforcement

4 B. Bank Run Gravel: Clean, Durable, sharp+angled fragments of rock of uniform quality. The gradation shall be as follows: Type 2: Sieve Size Percentage Passing Designation By Weight 1 ½ inch inch ½ inch C. #1 Stone: Crushed stone conforming to NYSDOT Sharp, angular fragments of crushed limestone or other approved crushed rock. Uniform quality throughout, well graded and free from dirt, clay and debris. The gradation shall be as follows: Sieve Size Percentage Passing Designation By Weight 2 inch 100 1/4 inch No No D. Rip+Rap: Hard, sound, angular stones, with a minimum weight of 100 pounds per stone, conforming to NYSDOT , Stone Filling Medium. E. Geotextile Fabric: material shall conform to Section Geotextile fabric and to Section of the NYSDOT Standard Specifications PART 3 EXECUTION 3.1 INSTALLATION A. Install silt fence or stone check dams as necessary to prevent sediment from leaving the construction area in accordance with NYSDOT Standard Specification Section B. Install catch basin inserts at all receivers within 200 feet of construction area or as ordered by Architect. Install catch basin inserts according to manufacturer s recommendations. Replace catch basin inserts when oil or sediment capacity is reached. Dispose of used inserts appropriately. C. All temporary erosion control measures will be maintained throughout the course of the site construction activities. D. Install stabilized construction entrance in accordance with details shown in the Contract Plans. E. The Architect or Owner may order additional erosion and sediment controls to be installed. The Contractor shall comply with the Architect s or Owner s request and immediately install the required controls

5 3.2 MAINTENANCE A. Silt fences shall be maintained and sediment materials removed when bulges develop in the silt fence, and as directed by the SWPPP Inspection personnel or the Owner s B. Catch basin inserts shall be inspected frequently and cleaned and/or replaced promptly when necessary and as directed by the SWPPP Inspection personnel or the Owner s C. Stone check dams shall be inspected frequently and cleaned and/or replaced promptly when necessary and as directed by the SWPPP Inspection personnel or the Owner s END OF SECTION

Stormwater Pollution Prevention Plan Engineering Department Requirements

Stormwater Pollution Prevention Plan Engineering Department Requirements Stormwater Pollution Prevention Plan Engineering Department Requirements The following are the stormwater pollution prevention plan requirements for the above referenced project. If you have any questions

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL Section Number Title 801 GENERAL 802 STANDARD METHODS OF EROSION AND SEDIMENT

More information

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01. Description. This work consists of installing and maintaining erosion and sedimentation controls to minimize soil erosion and control

More information

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment

More information

Single Family Residential Construction Erosion/Sediment Control Standards

Single Family Residential Construction Erosion/Sediment Control Standards Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended

More information

CONSTRUCTION SPECIFICATION MANUAL TECHNICAL STANDARDS FOR STORMWATER

CONSTRUCTION SPECIFICATION MANUAL TECHNICAL STANDARDS FOR STORMWATER CONSTRUCTION SPECIFICATION MANUAL TECHNICAL STANDARDS FOR STORMWATER Tavares, Florida Jones Edmunds & Associates, Inc. Project No. 06806-012-01 CONSTRUCTION SPECIFICATION MANUAL TECHNICAL STANDARDS FOR

More information

SECTION TRENCHING, BACKFILL AND COMPACTION

SECTION TRENCHING, BACKFILL AND COMPACTION SECTION 312333 TRENCHING, BACKFILL AND COMPACTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. Native Backfill Material 2. Crushed Stone Bedding 3. Select Backfill Material 4. Shoring and Bracing

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

New Administration Building

New Administration Building New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180

More information

Performance Standards Compliance Checklist

Performance Standards Compliance Checklist Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

VILLAGE OF HODGKINS 8990 LYONS STREET, HODGKINS, ILLINOIS OFFICE: FAX:

VILLAGE OF HODGKINS 8990 LYONS STREET, HODGKINS, ILLINOIS OFFICE: FAX: VILLAGE OF HODGKINS 8990 LYONS STREET, HODGKINS, ILLINOIS 60525 OFFICE: 708.579.6700 FAX: 708.579.6707 Village Ordinance #07-10 Soil Erosion & Sedimentation Control The Village of Hodgkins is responsible

More information

Diversion Dikes. Fe=0.95

Diversion Dikes. Fe=0.95 2.2 Diversion Dike Erosion Control Description: A diversion dike is a compacted soil mound, which redirects runoff to a desired location. The dike is typically stabilized with natural grass for low velocities

More information

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture

More information

ITEM 750 ROCK FILTER DAMS

ITEM 750 ROCK FILTER DAMS AFTER MARCH 1, 2012 ITEM 750 ROCK FILTER DAMS 750.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control rock filter dams utilized during construction

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 8 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Note: This Special Provision is generally written in the imperative mood. The subject, the

More information

SECTION EROSION CONTROLS

SECTION EROSION CONTROLS SECTION 31 25 13 EROSION CONTROLS PART 1 GENERAL 1.1 SUMMARY A. Section Includes installing, maintaining and removing: 1. Silt Fence. 2. Temporary Construction Entrances. 3. Diversion Channels. 4. Sediment

More information

902 TEMPORARY EROSION AND SEDIMENT CONTROL SECTION 902 TEMPORARY EROSION AND SEDIMENT CONTROL

902 TEMPORARY EROSION AND SEDIMENT CONTROL SECTION 902 TEMPORARY EROSION AND SEDIMENT CONTROL SECTION 902 TEMPORARY EROSION AND SEDIMENT CONTROL 902.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

City of Thomasville Water, Sewer & Natural Gas Specifications

City of Thomasville Water, Sewer & Natural Gas Specifications SECTION 02125 EROSION, SEDIMENTATION AND POLLUTION CONTROL PART 1 GENERAL 1.01 SCOPE A. The work specified in this Section consists of providing, maintaining and removing temporary erosion, sedimentation

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement. SECTION 31 25 13 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the provisions for the control of erosion in the construction area and in stockpile areas

More information

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering) Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.) Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,

More information

ACTIVITY: Dewatering Operations AM 12

ACTIVITY: Dewatering Operations AM 12 Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients Toxic Materials Oil & Grease Bacteria &

More information

Appendix B Construction SWPPP Short Form

Appendix B Construction SWPPP Short Form Appendix B Construction SWPPP Short Form Projects falling within the thresholds listed below may use this short form instead of preparing a formal Construction Stormwater Pollution Prevention Plan (SWPPP).

More information

Construction Site Inspections

Construction Site Inspections Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some

More information

ADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows:

ADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows: DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION 00 91 11.02 ADDENDUM NUMBER TWO June 22, 2016 TO: PLANHOLDERS SUBJECT: PCT TRUCK STAGING PROJECT PROJECT NO. 091606 CONTRACT NO. 070287 This

More information

SECTION 903 EROSION CONTROL

SECTION 903 EROSION CONTROL SECTION 903 EROSION CONTROL Delete this Section in its entirety and replace with the following: SECTION 903 EROSION CONTROL 903-1 DESCRIPTION: This work consists of providing all; administrative, labor,

More information

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities. SECTION 01 5713 TEMPORARY EROSION AND SEDIMENT CONTROL PART 1 GENERAL 1.01 SECTION INCLUDES A. Prevention of erosion due to construction activities. B. Prevention of sedimentation of waterways, open drainage

More information

Storm Water Pollution Prevention Plan for CES Gravel #3800

Storm Water Pollution Prevention Plan for CES Gravel #3800 David Lewis Cell: (870) 310-2757 Rickey Vaughn Cell: (870) 310-9602 Buddy McAdams Cell: (870) 310-8733 Local (870) 881-8830 Fax: (870) 881-8809 LICENSED, BONDED & INSURED Howard Cupp, Jr. Cell: (870) 314-2877

More information

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

Construction Site Erosion Control and Phase II of the Stormwater Permit Program Construction Site Erosion Control and Phase II of the Stormwater Permit Program Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Some Features of Phase

More information

Page 1 of 6 Permit No: MN R J. Mineral Mining and Dressing

Page 1 of 6 Permit No: MN R J. Mineral Mining and Dressing Page 1 of 6 J. Mineral Mining and Dressing 1. Authorized Stormwater Discharges The requirements in Sector J apply to stormwater discharges associated with industrial activity from active, temporarily inactive

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

STANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018

STANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018 STANDARD CONSTRUCTION DETAILS REVISED - JANUARY 2018 TABLE OF CONTENTS STORM WATER POLLUTION PLAN NOTES - - - - - - - - - - - - - - - - - - - - - - - - - SD-EC01 SILT FENCE NOTES - - - - - - - - - - -

More information

Tips with Creation of your Erosion and Sediment Control Plan

Tips with Creation of your Erosion and Sediment Control Plan Tips with Creation of your Erosion and Sediment Control Plan By Chris Droste, CESCO Senior Erosion Control Specialist Westmoreland Conservation District Forming Your Narrative Use the DEP checklist. Page

More information

The Good, The Bad, and The Ugly

The Good, The Bad, and The Ugly Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

Construction Phasing Bad

Construction Phasing Bad Construction Entrances Construction Phasing Remove mud and dirt from the tires of construction vehicles before they enter a paved roadway. Propoerly size entrance BMP's for all anticipated vehicles. Make

More information

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control

More information

A. Each Contractor shall comply with the requirements outlined in these documents.

A. Each Contractor shall comply with the requirements outlined in these documents. Section 000700 Stormwater Management Plan for Aurora Public Schools PART 1 GENERAL 1.0 DESCRIPTION A. Each Contractor shall comply with the requirements outlined in these documents. PART 2 PRODUCTS Not

More information

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Materials and Waste Management - WM DESCRIPTION AND PURPOSE A gravel

More information

Common Construction-Site BMPs Quick Reference Guide

Common Construction-Site BMPs Quick Reference Guide Common Construction-Site BMPs Quick Reference Guide Installation and Inspection Requirements For more information visit the Town of Truckee Clean Water Program Website: http://www.townoftruckee.com/engineering/clean-water-program

More information

Erosion Control Inspection Form

Erosion Control Inspection Form Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

Please print or type.

Please print or type. SOIL EROSION AND SEDIMENTATION CONTROL PERMIT APPLICATION 6-18-07 Ann kjjkjkff- ANN ARBOR CHARTER TOWNSHIP 3792 Pontiac Trail, Ann Arbor, Michigan 48105-9656 Phone (734) 663-3418 Website: www.aatwp.org

More information

Construction Site Runoff (CSR) Permit Application Permit Fee $150.00

Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Site Address or Lot and Subdivision: Applicant Name: Applicant s E-Mail: Applicant s Address: Telephone: (office) City, State, ZIP (cell)

More information

Section 1I-3 - Bioswales

Section 1I-3 - Bioswales BIOSWALES (Numbering pending) These specifications compliment the bioswale design portion of the Iowa Stormwater Management Manual in Chapter 2, Section 2I-3. Sections of the following documents, as referenced

More information

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

Flow Diversion Banks: General

Flow Diversion Banks: General Flow Diversion Banks: General DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Flow diversion

More information

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until

More information

Rock Sock (RS) Rock Sock height.

Rock Sock (RS) Rock Sock height. Rock Sock (RS) SC-5 Description A rock sock is constructed of gravel that has been wrapped by wire mesh or a geotextile to form an elongated cylindrical filter. Rock socks are typically used either as

More information

LOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE

LOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE TITLE: NUMBER: ISSUER: Storm Water Discharges Associated with Construction and Land Disturbance Activities REF-6286.0 John Sterritt, Director Enrique G. Boull t, Chief Operating Officer Office of the Chief

More information

City of Glendale Stormwater Management Plan Checklist

City of Glendale Stormwater Management Plan Checklist City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP

More information

Figure Inlet protection (Source: Minnesota DOT)

Figure Inlet protection (Source: Minnesota DOT) 3.9 INLET PROTECTION Figure 3.14. Inlet protection (Source: Minnesota DOT) Overview Description: A manufactured protective device or barrier used to trap sediment at a storm drain surface or curb inlet.

More information

Intended Construction Sequence East Brine Pond

Intended Construction Sequence East Brine Pond Intended Construction Sequence East Brine Pond 1) Stabilize Construction Entrance 1 Use Existing < 1.0 2) Install Silt Fence Around Planned Disturbance 1 < 1.0 3) Construct Sediment Trap 1 < 1.0 4) Construct

More information

SECTION UTILITY BACKFILL MATERIALS

SECTION UTILITY BACKFILL MATERIALS SECTION 31 23 23 UTILITY BACKFILL MATERIALS PART 1: GENERAL 1.01 SECTION INCLUDES A. Material Classifications B. : 1. Concrete sand 2. Gem sand 3. Pea gravel 4. Crushed stone 5. Crushed concrete 6. Bank

More information

2010 California Green Building Standards Code. Residential and Non-Residential Development

2010 California Green Building Standards Code. Residential and Non-Residential Development 2010 California Green Building Standards Code Residential and Non-Residential Development Stormwater Management (Site Development) Requirements Engineering, Surveying & Permit Services Department 2700

More information

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE STORM WATER POLLUTION PREVENTION PLAN TEMPLATE Cover Page Certifications Project, Owner, Operator, SWPPP Preparer, Date, Project Dates Signed by RIDOT (Owner) and CONTRACTOR (as Operator) of Contents Introduction

More information

STORMWATER POLLUTION PREVENTION PLAN

STORMWATER POLLUTION PREVENTION PLAN STORMWATER POLLUTION PREVENTION PLAN PART I GENERAL PROJECT INFORMATION - To be completed by Owner or Consultant PROJECT NAME: PROPERTY OWNER S NAME: ADDRESS: CITY: STATE: ZIP: PHONE #: FAX #: MOBILE #:

More information

APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS

APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS City of Bradenton January 2017 1 INTRODUCTION This appendix to the City of Bradenton Department of Public Works and Utilities Utility Specifications

More information

Planning & Building Department. Requirements for Erosion and Sediment Control

Planning & Building Department. Requirements for Erosion and Sediment Control Planning & Building Department 455 County Center, 2nd Floor Redwood City, California 94063 Tel: 540/863-4161/Fax: 650/363-4849 Mail Drop PLN122 plngbldg@smcgov.org http://planning.smcgov.org Requirements

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER FOR SPECIAL CONDITIONS AND PERMIT NUMBERING GENERAL NOTES: HOUSE GREEN HOUSE 1900 S. NORFOLK ST. SUITE 350 GARAGE GRADING

More information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

WAKULLA SITE PLANNING

WAKULLA SITE PLANNING WAKULLA CIVIL SURVEYING SITE PLANNING TRAFFIC CONTROL PLAN WAKULLA ARRAN ROAD WIDENING & RESURFACING UTILITY CONTACT LIST NO. DATE: APPR. REVISION: DATE: CIVIL SURVEYING SITE PLANNING GENERAL NOTES WAKULLA

More information

D EROSION AND SEDIMENT CONTROL. Table of Contents

D EROSION AND SEDIMENT CONTROL. Table of Contents Table of Contents D1. GENERAL... 1 D2. OBJECTIVE... 1 D3. REFERENCE MATERIAL... 1 D4. REGULATORY REQUIREMENTS... 1 D5. EROSION AND SEDIMENT CONTROL (ESC) PLANS... 2 D5.1 Goals and Objectives:... 2 D5.2

More information

PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR. Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL

PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR. Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL Reader Notes (1/18/17 draft) CWS has drafted proposed changes to Chapter 6 to incorporate

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

APPENDIX C DURING CONSTRUCTION BMP TABLES

APPENDIX C DURING CONSTRUCTION BMP TABLES APPENDIX C DURING CONSTRUCTION BMP TABLES Table C.1 Table C.2 Table C.3 Erosion Prevention BMPs Sediment Control BMPs Stormwater Runoff and Ground Control Measures STORM WATER QUALITY DESIGN MANUAL Appendix

More information

DESIGN AND CONSTRUCTION STANDARDS. Section 3: Standards by CSI Divisions. Storm Water Permit and Monitoring

DESIGN AND CONSTRUCTION STANDARDS. Section 3: Standards by CSI Divisions. Storm Water Permit and Monitoring Storm Water Permit and Monitoring GENERAL It is the Contractor s responsibility to obtain a National Pollutant Discharge Elimination System (NPDES) permit coverage under ADEM Administrative Code Chapter

More information

Storm Water Pollution Prevention Plan (SWP3) Checklist

Storm Water Pollution Prevention Plan (SWP3) Checklist . Summit Soil and Water Conservation District Storm Water Pollution Prevention Plan (SWP3) Checklist Modified from the Ohio EPA SWP3 Checklist (Revised January 2017) SITE NAME: REVIEWER: DATE RECEIVED:

More information

Homeowner Incentive Program

Homeowner Incentive Program Homeowner Incentive Program Lake Whatcom Watershed Stormwater Considerations Applicable to HIP-Eligible projects within Basin One of the Lake Whatcom Watershed, under the jurisdiction of the City of Bellingham

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY

SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY 1. PURPOSE: SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY The purpose of this policy is to establish procedures to facilitate compliance with federal, state and local stormwater regulations

More information

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities Development Services 1775 12 th Ave. NW P.O. Box 1307 Issaquah, WA 98027 425-837-3100 issaquahwa.gov Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction

More information

EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ

EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE EXAMPLES OF COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR

More information

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods SECTION 2000- EARTHWORK PART 1- GENERAL 1.01 SCOPE: This Section covers excavation, fill, and compaction of earth and rock for roadway, embankments, structural foundations, and planted areas. Topics include

More information

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site.

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site. INLET PROTECTION From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.state.ma.us/dep/brp/stormwtr/files/esfull.pdf Definition: A sediment filter or an excavated

More information

GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ

GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR PROJECT BEING DEVELOPED

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 04821 TEMPORARY VEHICLE AND EQUIPMENT FUELING AREA PART 1 - GENERAL 1.01 Description Installation of erosion and sediment control for a temporary vehicle and equipment fueling

More information

SWPPP Inspection Procedures and Form 247 Instructions

SWPPP Inspection Procedures and Form 247 Instructions SWPPP Inspection Procedures and Form 247 Instructions 1. Pre-Construction Conference a. A stormwater pollution pre-construction conference shall be held prior to beginning work on each project. b. The

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information

ITEM 706 PIPE SLOPE DRAIN

ITEM 706 PIPE SLOPE DRAIN AFTER NOVEMBER 1, 2008 ITEM 706 PIPE SLOPE DRAIN 706.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control pipe slope drains, utilized during construction

More information

Tina R. Evans, PE, CISEC HydroDynamics Incorporated Parker, CO HDI

Tina R. Evans, PE, CISEC HydroDynamics Incorporated Parker, CO HDI Tina R. Evans, PE, CISEC HydroDynamics Incorporated Parker, CO 303-841-0377 PREPARING FOR THE START OF CONSTRUCTION Environmental Regulatory Tasks Remain compliant Steps to Consider Know the Rules and

More information

Town of Fortville Utility Street Standards

Town of Fortville Utility Street Standards Town of Fortville Utility Street Standards SECTION 02101 - TEMPORARY EROSION AND DUST CONTROL PART 1 - GENERAL 1.1 DESCRIPTION A. Temporary Erosion and Dust Control measures must meet the current Town

More information

Appendix K: Soil Erosion and Sedimentation Control Plan Check List

Appendix K: Soil Erosion and Sedimentation Control Plan Check List Appendix K: Soil Erosion and Sedimentation Control Plan Check List Drain Commissioner 46 February 2005 SOIL EROSION AND SEDIMENTATION CONTROL PLAN CHECK LIST Items listed below must be clearly depicted

More information

Fabric Drop Inlet Protection

Fabric Drop Inlet Protection Fabric Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Block

More information

C-1. Infiltration System

C-1. Infiltration System C-1. Infiltration System Design Objective An infiltration system captures surface stormwater runoff and allows it to infiltrate into the soil. This SCM is typically the work horse of a runoff volume match

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre

CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre Approved by: City of Camarillo Stormwater Program Manager Date: CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre Project Name: Project #: Project Location:

More information