1 TECHNICAL SPECIFICATION ITEM TEMPORARY VEHICLE AND EQUIPMENT FUELING AREA PART 1 - GENERAL 1.01 Description Installation of erosion and sediment control for a temporary vehicle and equipment fueling area for aboveground fuel storage tank, which will be on site for more than 48 hours, or as directed or as directed by the Engineer Related Work Related work as called for on PLANS or specified elsewhere in this or other TECHNICAL SPECIFICATIONS Submittals A. Submit manufacturer s catalog sheets and other product data on dispensing equipment, pump, and aboveground fuel storage tanks, indicating the capacity and dimensions of the tank. B. Submit drawings to show the location of tank protection area and driveway. Indicate the nearest inlet or channelized flow area. Clearly dimension all distances and measurements. C. Submit a list of spill containment equipment, and quantities thereof, located at the fueling area. D. Submit manufacturer s catalog sheets and other product data on geotextile fabric Quality Assurance Person conducting visual examination for pollutant shall be fully knowledgeable about the NPDES Construction General Permit, detecting sources of storm water contaminants, inspection of aboveground storage tank and appurtenances for leakage, and the day-to-day operations that may cause unexpected pollutant releases. PART 2 - PRODUCTS 2.01 Aboveground Storage Tank A. Tank Assembly: Must be listed with UL 1709 and UL B. Inner Steel Storage Tank: Follow UL 142, with minimum thickness of 1/8-inch all welded construction

2 C. Tank Encasement: Either concrete or steel to provide a minimum of 110 percent containment of the inner tank capacity. Provide 5-gallon overspill containment pan for tank refueling. D. Dispenser Pump: For submersible pump, UL listed emergency shut-off valve to be installed at each dispenser. For suction pump, UL listed vacuum-activated shut-off valve, with a shear section, is to be installed at each dispenser. Fuel may not be dispensed from a tank by gravity flow or by pressurization of the tank. Means must be provided to prevent release of fuel by siphon flow. E. Representative Manufacturers: Convault, Fireguard, Ecovault, SuperVault, or equal Concrete Provide concrete with a minimum strength of 4,000 psi at 28 days Aggregates A. Coarse aggregate shall consist of crushed stone, gravel, crushed blast furnace slag, or a combination of these materials. Aggregate shall be composed of clean, hard, durable materials, free from adherent coatings, salt, alkali, dirt, clay, loam, shale, soft or flaky materials, or organic and injurious matter. B. Coarse aggregate shall conform to the following graduation requirements. Sieve Size (Square Mesh) Percent Retained (By Weight) 2½ ½ ¾ No Geotextile Fabric A. Woven or non-woven geotextile filter fabric made of either polypropylene, polyethylene, ethylene, or polyamide material, in continuous rolls of longest practical length. B. Grab Strength: 270 psi in any principal direction (ASTM D4632), Mullen burst strength exceeding 200 psi (ASTM D-3786), and the equivalent opening size between 50 and 70. C. Furnish ultraviolet inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 F to 120 F. D. Representative Manufacturers: Mirafi, Inc., Synthetic Industries, or equal

3 PART 3 - EXECUTION 3.01 General A. Do not clear, grub, or rough cut until erosion and sedimentation control systems are in place, unless otherwise approved by Engineer. B. Maintain existing erosion and sedimentation control systems located within the project site installed by others prior to start of construction under this contract until acceptance of the project or until directed by the Engineer to remove and dispose the existing systems. C. Inspect and repair or replace components of all erosion and sedimentation control systems as specified for each type of system. Unless otherwise directed, maintain the erosion and sedimentation control systems until acceptance of the project. Remove erosion and sedimentation control systems promptly when directed by the Engineer and dispose of removal materials offsite. D. Remove and dispose of sediment deposits at the project spoil site. If a project spoil site is not designated on Drawings, dispose sediment at an offsite location. Contractor assumes responsibility for offsite disposal location. Sediment shall be disposed of at an offsite location not in or adjacent to a stream or floodplain. Spread, compact, and stabilize sediment placed at the project site in accordance with the directions of the Engineer. Do not allow sediment to flush into a stream or drainage way. If sediment is contaminated, dispose of sediment in accordance with federal, state and local regulations. E. Do not maneuver equipment or vehicles on areas outside of dedicated rights-of-way and easements for construction. Immediately repair damages caused by construction traffic to erosion and sedimentation control systems. F. Employ protective measures to avoid damage to existing trees to be retained on the project site. Conduct all construction operations under this Contract in conformance with the erosion control practices described in Item General Source Controls. G. Contractor to prepare spill response and containment procedures to be implemented in the event of a significant materials spill. Significant materials include but are not limited to: raw materials; fuels; materials such as solvent, detergents, and plastic pellets; finished materials such as metallic products; raw materials used in food processing or production; hazardous substances designated under section 101(14) of CERCLA; any chemical required to be reported pursuant to Section 313 of Title III of SARA; fertilizers; pesticides, and waste products such as slag, ashes and sludge that have the potential to be released with storm water discharges. Spill containment procedures shall be kept on-site or in construction field office. H. Spill containment equipment appropriate to the size of operation is to be located in close proximity of the fueling area. Such equipment includes, but not limited to, suitable waste containers for significant materials, drip pans, booms, inlet covers, or absorbent

4 I. All significant materials or waste containers used for construction activities and stored on-site overnight are to be properly labeled Construction Methods A. Provide fuel tank protection area and driveway as shown on the Drawings. B. Do not locate fueling area in or near a channelized flow area or close to a storm sewer conveyance system. Sufficient space must be provided to allow installation of other erosion and sediment controls to protect those areas. C. Clear and grub the fueling area to remove unsuitable materials. Place geotextile fabric as permeable separator to prevent mixing of coarse aggregate with underlying soil. Overlap fabric a minimum of 6 inches. Place coarse aggregate on top of the geotextile fabric to minimum depth of 8 inches. D. Grade protection area and driveway to provide sufficient drainage away from stabilized areas. Use sandbags, gravel, boards, or similar methods to prevent sediment from entering public right-of-way, receiving stream or storm water conveyance system. The driveway to the fuel tank area shall have a minimum width of 15 feet for one-way traffic and 30 feet for two-way traffic. E. Place the aboveground storage tank on top of the cast-in-place or pre-cast foundation. The size and thickness of the foundation shall based on the size and weigh of the tank to be used, with a minimum thickness of 6 inches. The concrete foundation shall be enclosed by a 5-inch by 5-inch concrete curb and shall extend a minimum of 1 foot beyond the tank and dispenser assemblies, so that leak and drip can be contained within the concrete foundation. F. Slope the concrete foundation a minimum of 1 percent toward a 6-inch wide by 12- inch long by 4-inch deep sump pit. Install a minimum of 2-inch pipe inside the sump pit with a valve on the outside of the curb to allow draining of the concrete foundation. G. Install a portable concrete Jersey Barrier around the concrete foundation. Provide a minimum clearance of 2 feet from the edge of the foundation. In lieu of the jersey barrier, Contractor can install 4-inch diameter steel pipe bollards around the foundation. The bollards shall be buried a minimum of 3 feet deep, 3 feet aboveground, and 4 feet on center, encased in a 12-inch wide concrete foundation Maintenance A. Inspections shall be conducted by the designated health and safety officer qualified to conduct heath and safety inspections. B. Inspect stabilized areas after every storm event and at least once a week. Provide periodic top dressing with additional coarse aggregate to maintain the required depth. Repair and clean out damaged control measures used to trap sediment. C. Inspect fuel tank foundation s bermed area after every storm event and at least once a week. Visually examine storm water contained in the tank s bermed foundation area

5 for oil sheen or other obvious indicators of storm water pollution. Properly dispose of the storm water when pollutant is present. Record visual examination of storm water discharge in a Report noting the date and time of examination, name of examiner, observations of water quality, and volume of storm water discharged from the bermed area. The Report shall be kept together with all other storm water pollution control inspection reports on the site, in a readily accessible location Temporary Fueling Area Closure The temporary vehicle and equipment fueling area shall be disposed of by removal of all sediment and erosion controls properly offsite. Engineer will inspect the top soils in the fueling area and immediate vicinity for evidence of fuel leaks. If the Engineer determines that sufficient pollutants have been released, the soil shall be removed and properly disposed offsite. Other remediation method may be required Measurement and Payment A. Unless indicated in Document Bid Tabulation Form, the Temporary Vehicle and Equipment Fueling Area is incidental to the Work. Include costs for Temporary Vehicle and Equipment Fueling Area in the cost of work for which it is required. B. When indicated in Document Bid Tabulation Form, measurement and payment for Temporary Vehicle and Equipment Fueling Area will be on a lump sum basis. The Temporary Vehicle and Equipment Area measured as stated, will be paid for at the unit price bid for Temporary Vehicle and Equipment Fueling Area, Complete in Place. Payment for Temporary Vehicle Fueling Area will include and be full compensation for all labor, equipment, materials, supervision, and all incidental expenses for construction of these items, complete in place, including, but not limited to, embankment and excavation, concrete foundation and curbs, protection barrier, driveway, maintenance requirements, repair and replacement of damaged sections, removal of sediment deposits, redressing of aggregates and stones, and removal of erosion and sedimentation control systems at the end of construction

ITEM 706 PIPE SLOPE DRAIN

ITEM 706 PIPE SLOPE DRAIN AFTER NOVEMBER 1, 2008 ITEM 706 PIPE SLOPE DRAIN 706.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control pipe slope drains, utilized during construction

More information

ITEM 750 ROCK FILTER DAMS

ITEM 750 ROCK FILTER DAMS AFTER MARCH 1, 2012 ITEM 750 ROCK FILTER DAMS 750.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control rock filter dams utilized during construction

More information

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL Section Number Title 801 GENERAL 802 STANDARD METHODS OF EROSION AND SEDIMENT

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

REGIONAL CONSTRUCTION STANDARDS

REGIONAL CONSTRUCTION STANDARDS REGIONAL CONSTRUCTION STANDARDS SIXTH EDITION Publication Update 6.5 (Full Committee Approved Proposed Revision 6.5 Storm Sewer Joint Wrap - Section 302 As Publication Update 6.5) March 27, 2018 Copyright

More information

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

Water Pollution Control for Work in Sensitive Areas

Water Pollution Control for Work in Sensitive Areas Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed

More information

DIVISION 4100 SITEWORK

DIVISION 4100 SITEWORK DIVISION 4100 SITEWORK SECTION 4115 EARTHWORK PART 1 - GENERAL 1.01 SCOPE This section covers the grading and compaction of excavations, embankments, structural foundations, and planted areas. 1.02 REFERENCES

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS TEXAS STANDARD CONSTRUCTION NOTES DRWN. BY: DSGN. BY: KJW 1 of 2 *Place geotextile fabric as a permeable seperator to prevent mixing of coarse aggregate and underlying soil. (as needed). 1. GEOTEXTILE

More information

SECTION GENERAL EXCAVATION

SECTION GENERAL EXCAVATION 02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,

More information

Fabric Drop Inlet Protection

Fabric Drop Inlet Protection Fabric Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Block

More information

REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form

REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form Proposed Revision To: REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form General Provisions (Division 1) Technical Specifications (Divisions 2-8) Standard Details Change No. Hampton Roads Planning

More information

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING SECTION 334701 - WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. The Contractor shall provide all labor, materials, tools, and equipment required

More information

SECTION STORMWATER POLLUTION PREVENTION

SECTION STORMWATER POLLUTION PREVENTION PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02133 STORMWATER POLLUTION PREVENTION A. Prohibit illicit discharge (non-rainwater) into the storm drain system. B. Construct any and all necessary systems to

More information

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING Section Number Title 301 GENERAL 302 MATERIALS SPECIFICATIONS 303 CLEARING

More information

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS. SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract

More information

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1 1.01 GENERAL A. The Contractor shall perform all excavation, backfilling, grubbing and grading required for construction and installation of pipelines, structures and appurtenances. Excavation shall include

More information

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Materials and Waste Management - WM DESCRIPTION AND PURPOSE A gravel

More information

ACTIVITY: Dewatering Operations AM 12

ACTIVITY: Dewatering Operations AM 12 Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients Toxic Materials Oil & Grease Bacteria &

More information

This silt fence system is composed of geotextile filter fabric and steel posts.

This silt fence system is composed of geotextile filter fabric and steel posts. Supplemental Technical Specification for SILT FENCE SYSTEMS SCDOT Designation: SC-M-815-2 (03/08) 1.0 Silt Fence Systems This Supplemental Specification replaces Sections 815.2.5 and 815.4.6, Silt Fences,

More information

This silt fence system is composed of geotextile filter fabric and steel posts.

This silt fence system is composed of geotextile filter fabric and steel posts. Supplemental Technical Specification for SILT FENCE SYSTEMS SCDOT Designation: SC-M-815-2 (7/18) 1.0 Silt Fence Systems This Supplemental Specification replaces Sections 815.2.5 and 815.4.6, Silt Fences,

More information

SC-07 STORM DRAIN INLET PROTECTION

SC-07 STORM DRAIN INLET PROTECTION Greenville County Technical Specification for: SC-07 STORM DRAIN INLET PROTECTION 1.0 Storm Drain Inlet Protection 1.1 Description Provide Storm Drain Inlet Protection at all existing and newly installed

More information

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete. SECTION 02720 STORM DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-place Concrete. 1.02 REFERENCES

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

SECTION 18 - EARTHWORK TABLE OF CONTENTS

SECTION 18 - EARTHWORK TABLE OF CONTENTS SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL... 18.1 18-2 ROADWAY EXCAVATION... 18.1 18-2.01 General... 18.1 18-2.02 Unsuitable Roadway Excavation and Backfill... 18.1 18-2.03 Surplus

More information

INLET STRUCTURE FILTERS

INLET STRUCTURE FILTERS Supplemental Technical Specification for INLET STRUCTURE FILTERS SCDOT Designation: SC-M-815-8 (04/11) 1.0 Inlet Structure Filters This Supplemental Specification replaces sections 815.1.1.3, 815.2.4,

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01. Description. This work consists of installing and maintaining erosion and sedimentation controls to minimize soil erosion and control

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

902 TEMPORARY EROSION AND SEDIMENT CONTROL SECTION 902 TEMPORARY EROSION AND SEDIMENT CONTROL

902 TEMPORARY EROSION AND SEDIMENT CONTROL SECTION 902 TEMPORARY EROSION AND SEDIMENT CONTROL SECTION 902 TEMPORARY EROSION AND SEDIMENT CONTROL 902.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

SECTION 1 GENERAL NOTES

SECTION 1 GENERAL NOTES ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS

More information

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm

More information

INLET STRUCTURE FILTERS

INLET STRUCTURE FILTERS Supplemental Technical Specification for INLET STRUCTURE FILTERS SCDOT Designation: SC-M-815-8 (07/17) 1.0 Inlet Structure Filters This Supplemental Specification replaces sections 815.1.1.3, 815.2.4,

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

SECTION EROSION AND SEDIMENTATION CONTROL

SECTION EROSION AND SEDIMENTATION CONTROL SECTION 02160 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Contractor shall be held to have read all Bidding Requirements; all of the General Conditions and Supplementary

More information

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT 06045-0191 HILLIARD S POND DAM REMOVAL AND BIGELOW BROOK STREAM CHANNEL RESTORATION BID NO. 14/15-74

More information

Section 14 EARTHWORK, EXCAVATION, EMBANKMENT AND SUB-GRADE

Section 14 EARTHWORK, EXCAVATION, EMBANKMENT AND SUB-GRADE Section 14 EARTHWORK, EXCAVATION, EMBANKMENT AND SUB-GRADE 14-1 ROADWAY EXCAVATION AND BACKFILL In the Contract this item shall consist of excavating, removing, and satisfactory disposal of all material

More information

Base Course Design and Construction

Base Course Design and Construction Part I General A. This information is to be used as a guideline in construction a dynamic aggregate base and drainage system. Project conditions may vary based on overall scope of work and location. Any

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP INFRASTRUCTURE SERVICES Page 1 of 7 1.0 GRANULAR BASE AND SUB-BASE 1.1 DESCRIPTION.1 This section specifies requirements for supplying, producing, hauling placing and compacting processed gravel or quarried

More information

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS SECTION 13100 MECHANICALLY STABILIZED EARTH RETAINING WALLS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. Includes all labor, material, equipment, testing and submittals required to design and complete construction

More information

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SPECIAL SPECIFICATION 4653 Polypropylene Pipe 2004 Specifications CSJ 2158-01-013, Etc. SPECIAL SPECIFICATION 4653 Polypropylene Pipe 1. Description. Furnish and install polypropylene pipe for constructing polypropylene pipe culverts or polypropylene

More information

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment

1993 Specifications CSJ'S & SPECIAL SPECIFICATION ITEM Tree Preservation and Treatment 1993 Specifications CSJ'S 0912-71-554 & 0912-71-555 SPECIAL SPECIFICATION ITEM 1016 Tree Preservation and Treatment 1. Description. This section specifies the requirements for protecting trees and related

More information

CITY OF FARGO SPECIFICATIONS GEOTEXTILES AND GEOGRIDS

CITY OF FARGO SPECIFICATIONS GEOTEXTILES AND GEOGRIDS GEOTEXTILES AND GEOGRIDS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, accessories, and equipment necessary

More information

Construction Specification for General Excavation

Construction Specification for General Excavation Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03

More information

SECTION EROSION CONTROL DEVICES

SECTION EROSION CONTROL DEVICES SECTION 02374 PART 1 GENERAL EROSION CONTROL DEVICES 1.1 SUMMARY A. Section Includes: 1. Diversion Channels. 2. Rock Energy Dissipator. 3. Paved Energy Dissipator. 4. Rock Basin. 5. Rock Barriers. 6. Sediment

More information

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section 02670-1 of 6 SECTION 02670 CURB, COMBINATION CURB AND GUTTER, AND 02670.01 GENERAL A. Description This work shall include, but not necessarily be limited to, the construction of concrete curb, concrete

More information

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 1. Description This work shall consist of the design, manufacture and construction of a T-WALL structure

More information

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement. SECTION 31 25 13 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the provisions for the control of erosion in the construction area and in stockpile areas

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018

ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018 CBBEL PROJECT NO. 02-0065.H0226 ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018 Modification No. 1 In regards to the COBBLESTONE PAVERS specification,

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 8 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Note: This Special Provision is generally written in the imperative mood. The subject, the

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO.

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. 2017-1 43 SOUTH GRANVILLE WATER AND SEWER AUTHORITY H STREET BY-PASS

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

Nantasket Beach Revetment Design

Nantasket Beach Revetment Design Nantasket Beach Revetment Design A design concept for a stone revetment was developed for the conditions reported in the 20 May 2008 Draft Nantasket Beach Coastal Engineering Appendix. This revetment design

More information

IN T R A / M IN T R A M

IN T R A / M IN T R A M SPRING MESA SUBDIVISION CONSTRUCTION PLANS A PART OF SECTION 35, TOWNSHIP 2 SOUTH, RANGELINE 70 WEST, 6th. PRINCIPAL MERIDIAN. CITY OF ARVADA, COUNTY OF JEFFERSON, STATE OF COLORADO COVER SHEET MARTIN

More information

SECTION MINOR CONCRETE

SECTION MINOR CONCRETE SECTION 03300 - MINOR CONCRETE CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And Payment...

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 31 23 33 TRENCHING AND BACKFILL PART 1 GENERAL... 3 1.1 Description... 3 A. Excavation for Utilities Includes... 3 B. Suitable Fill Material...

More information

SECTION 28 AGGREGATE BASE COURSE (FAA P-208) [For base course under runway and taxiway surfaces, use Section 29, FAA Item P-209.]

SECTION 28 AGGREGATE BASE COURSE (FAA P-208) [For base course under runway and taxiway surfaces, use Section 29, FAA Item P-209.] 28-1 GENERAL SECTION 28 AGGREGATE BASE COURSE (FAA P-208) The Contractor shall perform all work required by the plans and specifications for construction of aggregate base course for, use under runway

More information

SECTION UNDERDRAINS. 1. Protection of the environment; Section Trench excavation, backfill, and compaction; Section

SECTION UNDERDRAINS. 1. Protection of the environment; Section Trench excavation, backfill, and compaction; Section 02510-1 of 7 SECTION 02510 UNDERDRAINS 02510.01 GENERAL A. Description Underdrain installation shall include, but not necessarily be limited to, constructing underdrains using pipe, filter fabric, and

More information

Inlet Protection. Fe= (Depends on soil type)

Inlet Protection. Fe= (Depends on soil type) 3.4 DESIGN CRITERIA: KEY CONSIDERATIONS Evaluate drainage patterns to ensure inlet protection will not cause flooding of roadway, property or structures Never block entire inlet opening Size according

More information

SECTION 18 - EARTHWORK TABLE OF CONTENTS

SECTION 18 - EARTHWORK TABLE OF CONTENTS SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL...18.1 18-2 ROADWAY EXCAVATION...18.1 18-2.01 General...18.1 18-2.02 Unsuitable Roadway Excavation and Backfill...18.1 18-2.03 Surplus

More information

SECTION 503 TEMPORARY PAVEMENT RESTORATION

SECTION 503 TEMPORARY PAVEMENT RESTORATION SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

Construction Specification 62 Grouted Rock Riprap

Construction Specification 62 Grouted Rock Riprap Construction Specification 62 Grouted Rock Riprap 1. Scope The work consists of furnishing, transporting, and the installation of grouted rock riprap revetments and blankets, including filter or bedding

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 9/17/18)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 9/17/18) Page 1 of 8 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

BMP-5. A temporary sediment barrier consisting of a synthetic filter fabric stretched across and attached to supporting posts and entrenched.

BMP-5. A temporary sediment barrier consisting of a synthetic filter fabric stretched across and attached to supporting posts and entrenched. BMP-5 BMP: SILT FENCE Definition A temporary sediment barrier consisting of a synthetic filter fabric stretched across and attached to supporting posts and entrenched. Purposes To intercept and detain

More information

Suggested Best Management Practices (BMPs)

Suggested Best Management Practices (BMPs) Suggested Best Management Practices (BMPs) Preface The purpose of this Best Management Practices (BMP) Manual is to help educate and instruct on ways to reduce stormwater pollution and help prevent it

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract

More information

55.3 AGGREGATE PRODUCTION AND STOCKPILING

55.3 AGGREGATE PRODUCTION AND STOCKPILING 55.3 AGGREGATE PRODUCTION AND STOCKPILING 55.3.1 GENERAL The Work covers the general requirements for production, gradation, stockpiling, and pit operations for specified aggregate materials. 55.3.2 AGGREGATE

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater

More information

SECTION EARTHWORK

SECTION EARTHWORK SECTION 310000 PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and perform all excavation, backfill, fill and grading required to complete the work

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

SECTION SUBDRAINAGE

SECTION SUBDRAINAGE SECTION 33 46 00 SUBDRAINAGE PART 1 GENERAL 1.01 SECTION INCLUDES A. CONTRACTOR shall furnish all labor, tools, and equipment and perform all Work necessary for, or incidental to, the supply and installation

More information

SECTION 14 EMBANKMENT

SECTION 14 EMBANKMENT SECTION 14 EMBANKMENT 14.1 DESCRIPTION A. General: This work consists of constructing roadway embankments, including preparation of the areas upon which embankments are to be placed; the construction of

More information

SECTION 500 STRUCTURES

SECTION 500 STRUCTURES SECTION 500 STRUCTURES 500.1 GENERAL This section defines the various construction items that are associated with the completion of a concrete, steel, timber, or masonry unit structures, or a combination

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL 13.01 GENERAL The work included in this section shall consist of furnishing all materials and equipment and performing all labor

More information