4 Description of the Development
|
|
- Scott O’Neal’
- 5 years ago
- Views:
Transcription
1 Inverclyde Wind Farm Environmental Statement Inverclyde Renewables LLP 4 Description of the Development Introduction Table 4.1: Drawings 4.1 This chapter provides a description of the physical characteristics of the proposed Inverclyde Wind Farm for the purposes of informing the identification and assessment of the likely potential significant environmental effects. Information is provided in accordance with the requirements of the EIA regulations. A description of the layout and land-take associated with the proposed turbines and the associated infrastructure is provided. In addition, this chapter provides a description of the typical details of the type of turbines proposed, along with typical details for turbine foundations, hardstanding, access tracks, the combined welfare, substation and control building, and other associated infrastructure. Application for Planning Consent Drawing no. Figure 1.1 Figure 1.2 Figure 4.1 Figure 4.2 Figure 4.3 Figure 4.4 Figure 4.5 Figure 4.6 Drawing title Site Location Site Layout Turbine and Infrastructure Layout Typical Wind Turbine Elevation Typical Power Performance Calibration Mast Typical Turbine Foundation and Hardstanding Typical Access Track Cut and Floating Road Design Welfare, Substation and Control Building Plan 4.2 The Applicant is seeking consent under the Town and Country Planning (Scotland) Act 1997 (as amended) for a wind farm comprising the following: 10, three bladed, horizontal axis wind turbines, each up to a maximum blade tip height of 110 m (above ground level), rated at between 2 MW and 3 MW each, and with a maximum hub height of 65 m; external turbine transformers and turbine switchgear adjacent to each turbine; a hardstanding area at each turbine location for use by the cranes erecting each turbine; one temporary (mobile) power performance calibration mast; a combined welfare and control building, which would provide site welfare facilities for operational staff; an electrical substation and network of buried electrical and control cables linking the control building, substation and turbines; a temporary construction compound; drainage works and watercourse crossings; a borrow pit; a network of access tracks and turning areas linking the turbines and the substation/ control building; an access track linking Dougliehill Road, crossing Devol Moor, to the B788 adjacent to the Devol Moor 132/33 kv substation; and associated ancillary works and engineering operations. 4.3 The elements that form the proposed Inverclyde Wind Farm are described in a series of drawings, which are listed in Table 4.1. Figure 4.7 Figure 4.8 Figure 5.1 Welfare, Substation and Control Building Elevation Typical Cable Trench Detail Construction Compound Layout 4.4 The EIA is based on the drawings listed in Table 4.1 and the description of the development set out in this chapter. 4.5 The locations of the proposed turbines and other infrastructure would be subject to micrositing. This process allows for minor changes in turbine or infrastructure location to respond to possible variations in ground conditions across the site, which would only be confirmed following detailed site investigation work carried out immediately prior to construction. This process also provides scope for further mitigation of localised potential environmental effects through avoidance of sensitive features. It is anticipated that the agreed tolerance micrositing distance of 50 m would form a condition accompanying any consent. Any repositioning would be carried out under the supervision of an ecological clerk of works. Further description of the application of micrositing is provided in Chapter 5: Construction and Environmental Management. Site Layout Turbine Layout 4.6 The proposed locations for all infrastructure including, wind turbines, tracks, welfare buildings, the substation and borrow pits, are shown on Figure 1.2. The turbine grid reference locations are listed in Table 4.2. Volume 2: Main Report Chapter 4: Description of the Development 4-1 ENVIRON
2 Inverclyde Renewables LLP Inverclyde Wind Farm Environmental Statement Table 4.2: Turbine Locations (British National Grid, OS GB 1936 Datum) Name Easting Northing Turbine Turbine Turbine Turbine Turbine Turbine Turbine Turbine Turbine Turbine Land Take 4.7 The permanent land take from the proposed Inverclyde Wind Farm would be 2.49 % of the total site area (209.8 hectares). The permanent land take would be limited to the area of the towers (supporting the turbines), the hardstanding area immediately around the towers, the substation and welfare buildings, the access tracks linking these elements and the link tracks to the core path network. 4.8 In constructing the wind farm there would be a requirement for temporary disturbance of land, to allow for, for example, temporary construction compounds and borrow pit excavation. This land would be restored following the completion of the construction works. 4.9 Table 4.3 sets out the approximate permanent and temporary land take associated with each element of the proposed Inverclyde Wind Farm, and provides an estimate of the total areas of land take. Table 4.3: Land Take Calculations Wind Farm Element Temporary Land Take Permanent Land Take Temporary construction compound/ Permanent car park Welfare, control building and substation Turbine and transformer (based on maximum extent of gravity base foundation for turbine of 20 m x 20 m, and transformer switchgear housing of 7 m x 4 m) Permanent crane pad hardstanding Turbine working area (excavation area for foundation assuming 40 m x 40 m) Less 430 m 2 per turbine due to turbine and transformer area being located within the turbine working area. Temporary turbine installation area (rotor hub assembly, laydown areas and crane boom assembly area). Access track and passing places (permanent 7 km) Temporary access track to borrow pit (plus shoulder areas on permanent tracks) Total Area During Construction 50m x 60 m = 3,000 m 2 50 m x 20 m = 1,000 m 2 3,000 m 2 N/A 30 m x 30 m = 900 m m 2 N/A 430 m 2 per turbine = 4,300 m 2 4,300 m 2 N/A 896 m 2 per turbine = 8,960 m 2 8,960 m 2 16,000 m m 2 = N/A 11,700 m 2 11,700 m m 2 per turbine = N/A 5,130 m 2 5,130 m 2 N/A 35,615 m 2 35,615 m 2 8,318 m 2 N/A 8,318 m 2 Link tracks to core path network N/A 1,356 m 2 1,356 m 2 Borrow pits 7,234 m 2 N/A 7,662 m 2 TOTAL 35,382 m 2 52,131 m 2 86,941m 2 % of site area 1.67% 2.49% 4.14% Description of the Proposed Inverclyde Wind Farm Wind Turbines 4.10 The proposed Inverclyde Wind Farm would consist of 10 three bladed, horizontal axis wind turbines (see Figure 4.2). The proposed turbines would be multi-megawatt class machines, each with an installed electrical capacity of between 2 and 3 MW The maximum turbine parameters selected for the purposes of this EIA is a 3 MW turbine, with a rotor diameter of up to 93 m, a hub height of up to 65 m and a maximum ground to tip height of 110 m. ENVIRON 4 2 Volume 2: Main Report Chapter 4: Description of the Development
3 Inverclyde Wind Farm Environmental Statement Inverclyde Renewables LLP 4.12 The turbines would generate electricity from wind speeds between approximately 4 m/s to 25 m/s. The rotor would be 'upwind', and all rotors would turn in the same direction. The proposed turbines would operate using variable speed rotor technology, and hence operate at different rotational speeds depending on the wind speed. Rotor speeds would vary depending on the wind speed, from approximately 10 rpm (revolutions per minute) at the cut in wind speed up to a full rotor speed of approximately 20 rpm at full power output Above ground, each turbine would comprise: a tubular tower, up to 65 m high, with door and internal access systems; a nacelle housing generator, gearbox, hydraulic and electrical control systems, and externally mounted anemometry instruments; and a rotor comprising a central hub and three blades, with an overall diameter of up to 93 m Wind turbines are available in a variety of colours, the most common being white, off white or light grey. The finish is normally semi-matt. The colour of the turbines would be agreed in consultation with the planning authority, however it is anticipated that light grey turbines would be used The blades of modern turbines are generally made from reinforced composite materials (e.g. fibreglass or wood epoxy), with towers normally constructed from steel The wind turbines have a requirement to be spaced apart, so as not to interfere aerodynamically with one another. Figure 1.2: Site layout illustrates the spacing of the turbines. Turbine Transformers and Switchgear 4.17 The transformer and switchgear would be provided adjacent to each turbine, connected by a length of buried cable, to raise the generation voltage to the higher level of 33 kv to connect with the electricity transmission network. In order to manage health and safety of operatives during maintenance, the transformer and switchgear would be located externally, at the base of the turbine, within an enclosure which can be provided in various colours to suit the landscape context. The transformer and switchgear enclosure dimension would be approximately 2.5 x 2.5 m in plan and 3 m in height. Power Performance Calibration Masts 4.18 A temporary guyed mast, known as power performance calibration mast, of up to 70 m height would be erected to confirm the detailed wind flow of the site. The mast would be raised prior to turbine erection and the data gathered would be used in the acceptance tests on the turbines. Figure 4.3 shows an example of a power performance calibration mast The mast would be removed 6-12 months into the Development s operation, once sufficient data across the full range of wind conditions is gathered to prove the performance of the turbines. Foundations and Hardstanding 4.20 The wind turbines would be sited on steel reinforced concrete foundations. It is anticipated that these would be of gravity base design. Final base designs would be determined after a full geotechnical evaluation of each turbine site. Figure 4.4 gives an illustration of typical wind turbine foundation construction. Typical permanent landtake associated with the foundations for the turbine and transformer would be approximately 430 m 2. During the erection of the turbines, crane hard-standing areas would be required at each turbine base. Typically, these consist of a main crane hard-standing area adjacent to the turbine position where the main turbine erection crane would be located, plus additional areas of land required during the assembly of the main crane jib and assembly of the rotor. The hard-standing provides a hardcore platform with a total permanent land-take estimated at approximately 896 m 2 per turbine for the crane pads There would be a need to use cranes from time to time during the operational phase of the proposed Inverclyde Wind Farm; therefore the main crane hard-standing would be left uncovered to ease maintenance activities. On-site Access Tracks, Turning Heads and Passing Bays 4.22 Tracks would be required to enable the turbine components and construction materials to be transported to their locations, and to enable on-going access for subsequent maintenance visits, as illustrated in Figure 1.2. The proposed Inverclyde Wind Farm application includes for the construction of a 2.1 km access track from Dougliehill Road, across Devol Moor, to the B788 at Harelaw adjacent to the north of Devol Moor substation and a network of approximately 4.9 km of new site tracks on the west side of the B788 linking the turbines for construction, operation and decommissioning. Vehicular access would be restricted by padlocked gates to authorised vehicles only. The track across Devol Moor from Dougliehill Road to the B788 would be maintained for the duration of the operational life of the proposed Inverclyde Wind Farm to allow for any abnormal loads access; however, routine maintenance and operational staff visits in light goods vehicles or passenger vehicles would use the B788 to reach the site entrance Based on the ground conditions at the site, it is anticipated that only 'cut' track would be required. Cut tracks would be used on hard ground, typically less than 1 m depth of peat, or on steeper gradients. Short sections of floating track may be used on areas of soft ground, typically with peat depths > 1 m, although these areas have mostly been avoided through design. The need for floating tracks would be determined through detailed site investigation at the pre-construction stage. Figure 4.5 illustrates typical cut and floating track constructions All turbine access tracks would be designed to carry the same maximum loads, and each track must be capable of supporting the weight of the mobile crane and the turbine components. Nominal track running width would be approximately 5 m, plus a 0.5 m shoulder on either side (i.e. 6 m wide in total) subject to local ground conditions, and would be designed to carry an Volume 2: Main Report Chapter 4: Description of the Development 4-3 ENVIRON
4 Inverclyde Renewables LLP axle load of approximately 16 tonnes. Track widths may be slightly wider in some sections to accommodate bend radius and to make provision for passing bays and turning heads Site track routes have been designed to minimise watercourse crossings. The proposed site access tracks would include a total of seven watercourse crossings, comprising a mixture of natural and artificial drains. The type and design of stream crossing would be dependent on the stream morphology, peak flows, local topography and ecological requirements, and would be chosen so as to avoid or minimise potential environmental effects. The watercourse crossings are considered in further detail within Chapter 10: Hydrology, Hydrogeology and Geology. Access for Recreation 4.26 The site track network has been designed to make connections with the existing local path network, providing new opportunities for walking routes around Corlic Hill, linking in with existing routes from Whinhill Golf Course, the Gryfe reservoirs and Old Largs Road. 450 m of link paths would be constructed to link the site access tracks to the existing core path network. A car park providing approximately 24 parking spaces for members of the public would also be provided off the B788, opposite the existing Devol Moor substation, as shown in Figure 1.2. Suitable gates would be provided to allow pedestrian/cyclist access to the track network from the car park. Welfare, Substation and Control Building 4.27 The welfare, substation and operational control facilities would be located in a single building and associated compound adjacent to the site access on the west side of the B788, as depicted in Figure The building would be located within a compound with dimensions of 30 m x 30 m, surrounded by a perimeter security fence with gated access. The building would be configured in an L- shape with dimensions of 20 m x 6 m. Figure 4.6 provides a plan illustration of the building, with elevation drawings shown in Figure 4.7. The location of the building would require the diversion of a small drain. Further details are provided in Chapter 10: Hydrology, Hydrogeology and Geology The primary purpose of the substation would be to provide an electrical connection point for the incoming 33 kv cables from the turbine transformers. The facility would accommodate the 33 kv switchgear and provide a central metering point for measuring the energy generated by the proposed Inverclyde Wind Farm The welfare and control building would be utilised periodically by visiting maintenance staff. The facility would contain emergency first-aid equipment, a flammables/chemical store; workshop/store; storage space for tools and spares and office space for monitoring equipment; drying/changing rooms; toilets; washroom facilities and kitchen facilities. Foul wastewater would either be discharged via a septic tank and soakaway, or by tankering and off-site disposal, depending on the suitability of the site for a soakaway and prior agreement with SEPA. Underground Cable Network Inverclyde Wind Farm Environmental Statement 4.31 Electrical connection from the turbines to the on-site substation would be via a network of underground 33 kv cables. As far as possible cables would follow the routes of the site tracks to minimise ground disturbance. The cables would be laid in trenches of approximately 450 mm wide to a depth of around 1 m. The temporary land disturbance associated with the cable trenches are covering in the land take figure presented for access tracks in Table 4.3. The distance of the trench from the track would be dependent on the ground conditions Figure 4.8 illustrates the typical cable trench detail that would be used. Connection to Electricity Grid 4.33 The grid connection does not form part of the planning application for the proposed Inverclyde Wind Farm. Any required consent for the grid connection would be typically be sought by the relevant owner of the local distribution or transmission network. The grid connection proposals would be subject to a separate consent process Nevertheless it is anticipated that the most likely connection point would be into the electricity grid at the Devol Moor 33 kv/132 kv substation via an underground cable. Devol Moor substation is located approximately 60 m east of the proposed Inverclyde Wind Farm substation, on the opposite side of the B788. Temporary Construction Compounds 4.35 A temporary construction compound would be required to enable construction of the proposed Inverclyde Wind Farm. The compound would include: temporary portable office accommodation; toilet and welfare facilities; storage for tools, small plant and parts; parking; a receiving area for incoming vehicles; and a bunded area for storage of fuels and oils The temporary construction compound would have dimensions of approximately 50 m x 60 m (3,000 m 2 in total). The indicative layout of the temporary construction compound is shown in Figure 5.1. In addition, a satellite compound for material laydown during track construction would be required within the site area to the east of the B788. Borrow Pits 4.37 To minimise the volume of stone brought onto the site and any associated environmental effect, a borrow pit located within the site would be used to source the majority of the necessary material for track construction A borrow pit search area has been identified, shown on Figure 4.1 and detailed in Technical Appendix 5.1, including illustrative layouts. The extent of the proposed borrow pit area is ENVIRON 4 4 Volume 2: Main Report Chapter 4: Description of the Development
5 Inverclyde Wind Farm Environmental Statement Inverclyde Renewables LLP 7,662 m 2. It is anticipated that approximately 35,000 m 3 of stone would be extracted from the borrow pit. The exact location of the borrow pit and its dimensions would be established following detailed geotechnical investigation for the borrow pit search area. The borrow pit would be restored following extraction of stone. Details of the borrow pit restoration proposals are provided in Chapter 5: Construction and Environmental Management and Chapter 7: Ecology. Operation and Management Life of the Project 4.39 The expected operational life of the proposed Inverclyde Wind Farm is 25 years from the date of commissioning. At the end of this period, a decision would be made as to whether to refurbish, remove, or replace the turbines. If refurbishment or replacement were to be chosen, relevant planning applications would be made. If a decision were to be taken to decommission the proposed Inverclyde Wind Farm, this would entail the removal of all the turbine components, transformers, the substation and associated buildings. The access tracks would be left on the site to ensure the continued benefit of improved access for the landowner, tenant farmer and the public for recreation or they could be reinstated. It is not currently best practice to remove the concrete foundations from the site as this would cause more damage than leaving them in situ. The exposed concrete plinth would be removed to a suitable depth below ground level and the entire foundation would be graded over with soil and would be replanted. This follows advice originally given in PAN 45, which advises in paragraph 33 that concrete foundations may be best left in place and covered over. This advice is also repeated in the Scottish Government's web-based renewables advice. Health and Safety 4.40 The health and safety of staff and the public is of paramount importance to the Applicant. Strict health and safety procedures would be applied during the construction and subsequent operation of the proposed Inverclyde Wind Farm and would be in compliance with prevailing legislation and best practice, currently set out in: the Construction (Design and Management) Regulations 2007 (HSE, 2007); the Health and Safety at Work Act 1975 (HMSO, 1974); the Construction (Health, Safety and Welfare) Regulations 1996 (HMSO, 1996); the revised edition of the Renewable UK Health and Safety in the Wind Energy Industry Guidelines; and the Management of Health and Safety at Work Regulations 1999 (HMSO, 1999) A sign would be placed at the entrance to the proposed Inverclyde Wind Farm giving details of emergency contacts. This information would also be made available to the local police station and the grid operator. Environmental Management Systems (EMS) 4.42 The Applicant has confirmed that the proposed Inverclyde Wind Farm would operate under an ISO accredited Environmental Management System (EMS). The EMS would ensure an environmental monitoring and maintenance programme is in place to ensure continued monitoring of environmental conditions on site and to prevent any adverse effects arising during the operation of the proposed wind farm Further details of the environmental management systems that would be in place during the construction of the proposed Inverclyde Wind Farm are detailed within Chapter 5: Construction and Environmental Management. Operational Residues and Emissions 4.44 This section provides an estimate, by type and quantity, of the expected residues and emissions resulting from the operation of the development. Water 4.45 Water emissions resulting from the operational wind farm are anticipated to be limited to surface water, and very small quantities of waste water from the site welfare facilities The site would be designed to ensure that surface water runoff does not exceed the predevelopment volume or rate of run-off. Access tracks would be designed to be semi-permeable and to act in a similar manner to a Sustainble Drainage System (SUDS), allowing some infiltration of surface water through the track surface. In addition, there would be a trackside drainage system installed during construction incorporating measures to attenuate the flow and provide for physical filtration and infiltration of surface water. Runoff from areas of impermeable hardstanding such as crane pads and foundations is expected to infiltrate locally on unsurfaced areas. Water quality monitoring during the operational phase would allow early detection of potential pollution incidents and assurance as to the on-going performance of the SUDS. Further detail on the surface water management proposed during construction is provided in Chapter 5: Construction and Environmental Management Small volumes of foul wastewater would either be discharged via a septic tank and soakaway, or by tankering and off-site disposal, depending on the suitability of the site for a soakaway and prior agreement with SEPA. Air 4.48 Due to the nature of the development no significant point source air emissions would be produced during the operation of the proposed Inverclyde Wind Farm. The proposed Inverclyde Wind Farm would generate renewable electricity and would therefore displace carbon dioxide (CO 2 ) emissions associated with electricity generation, which would otherwise be supplied via other forms of power generation requiring the combustion of fossil fuels. CO 2 Volume 2: Main Report Chapter 4: Description of the Development 4-5 ENVIRON
6 Inverclyde Renewables LLP Inverclyde Wind Farm Environmental Statement Waste savings of approximately 27,000 tonnes per year are predicted compared to using a grid mix of electricity generation The power generation aspect of the proposed Inverclyde Wind Farm would not produce any waste emissions or pollutants. The general operation and maintenance of the development has the potential to produce a small amount of waste. This is likely to be restricted to waste associated with the welfare building from employees and visiting contractors and the storage of oils and lubricants. Further details are provided in Chapter 5: Construction and Environmental Management. Noise and Vibration 4.50 The wind turbines would generate noise during operation, and the noise levels would vary according to the wind speed. The location of residential receptors in relation to the wind farm was one of the key considerations in the design development process. Full details of the noise impact assessment are presented in Chapter 13: Noise and Vibration. Light 4.51 Security lighting would be provided for the combined substation/ control building/ welfare building; however this would only be in use when personnel are present on site. No lighting would be provided on the proposed turbines. ENVIRON 4 6 Volume 2: Main Report Chapter 4: Description of the Development
7 Crown copyright, All rights reserved Licence number Legend Site Boundary Turbine Layout Turbine Installation Area Access Track Temporary track to substation Temporary Construction Compound Temporary Borrow Pit Track Link track (to core paths network) Passing Place Permanent Crane Hardstanding Borrow Pit Area Substation / Control Building Hardstanding Permanent Car Parking ± 8 9 A3 1:7,500 Figure 4.1: Turbine and Infrastructure Layout 10 Site: Proposed Inverclyde Wind Farm Client: Inverclyde Wind Farm Ltd DD/PB UK Walker Street, Edinburgh EH3 7JY Meters Tel: +44 (0) Fax: +44 (0)
8 Key 110m max TIP HEIGHT HUB ROTOR NACELL 65m max HUB HEIGHT 93m max ROTOR DIA TOWER SIDE ELEVATION TRANSFORMER KIOSK (2.5mX2.5x3m) FRONT ELEVATION TRANSFORMER KIOSK (2.5mX2.5x3m) Title Site Client Scale Figure 4.2: Typical Wind Turbine Elevation NTS B UK Proposed Inverclyde Wind Farm Inverclyde Renewables LLP CH/KG
9 65m Key Typical Meteorological Mast Details NOTES: 1. All dimensions shown are approximate and may vary further to final design. Do not scale from this drawing. Title Site Figure 4.3: Typical Power Performance Calibration Mast UK Proposed Inverclyde Wind Farm Client Scale Inverclyde Renewables LLP NTS A KG
10 Key TYPICAL PLAN OF CRANE HARDSTANDING AND TURBINE ASSEMBLY AREAS Area Description Max Area Dimension Bearing Capacity fall (%) (m 2 ) axb(m) kn/m 2 Axel load Maintenance q1 Construction area x T Permanent q2 Lay down area x T Temporary q3 Assembly area x Temporary C-C 15 E-F 22 B 5 Units in meter NOTES 1. ALL DIMENSIONS SHOWN ARE APPROXIMATE 2. LAYOUT AS SHOWN IS INDICATIVE ONLY Title Site Figure 4.4: Typical Turbine Foundation and Hardstanding UK Proposed Inverclyde Wind Farm Client Scale Inverclyde Renewables LLP NTS B CC
11 Key TOP SURFACE OF SLOPES FINISHED WITH EXCAVATED PEAT TURFS MINIMUM USABLE RUNNING WIDTH (1:40) Nom (1:40) Nom UPPER LAYER OF GEOGRID 150 TYPICAL COMPACTED STONE TYPICAL FLOATING ROAD SCALE 1:50 LOWER LAYER OF GEOGRID LAID ON EXISTING GROUND SURFACE EXISTING GROUND LEVEL EXCAVATED SUBSOIL SPREAD UP TO 5m FROM ROAD EDGE AND COVERED WITH LOCAL TOPSOIL MINIMUM USABLE RUNNING WIDTH (1:40) Nom (1:40) Nom SUBSOIL COMPACTED STONE TYPICAL SECTION OF ROAD ON FORMATION SCALE 1:50 ROAD FOUNDED ON SUITABLE LOAD BEARING STRATA DRAINAGE DITCH. DEPTH SIZED FOR HYDROLOGICAL CONDITIONS ,000 NTS PROPOSED PASSING PLACE Title Figure 4.5: Typical Access Track Cut and Floating Road 5500 ACCESS ROAD Site UK Proposed Inverclyde Wind Farm TYPICAL PASSING PLACES ON WINDFARM SCALE 1:250 Client Scale Inverclyde Renewables LLP NTS B CH/KG
12 BUFFER PLANTING (NATIVE SHRUBS, GRASS AND WILDFLOWERS SEED MIX) B782 - PUBLIC ROAD ACCESS / EGRESS 6000mm GATE Key PALISADE FENCE BUFFER PLANTING - Detail to be agreed by condition with Inverclyde Council HARDSTANDING 5000mm 5000mm SEWAGE DISPOSAL NOTES 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS STATED OTHERWISE. 5000mm 2. LAYOUT OF CONTROL BUILDING AS SHOWN IS INDICATIVE ONLY. 3. HARDSTANDING AREA TO BE MIN WIDTH OF 5m FORMED AROUND PERIMETER FO THE CONTROL BUILDING. 5500mm Title Figure 4.6: Welfare, Substation and Control Building - Plan Site UK Proposed Inverclyde Wind Farm 5000mm Client Scale Inverclyde Renewables LLP NTS A CH
13 Key EAST ELEVATION Roller Shutters on all windows SOUTH ELEVATION NORTH ELEVATION NOTES 1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS STATED OTHERWISE 2. LAYOUT OF CONTROL BUILDING AS SHOWN IS INDICATIVE ONLY. 3. HARDSTANDING AREA TO BE MINWIDTHOF5mFORMED AROUND PERIMETER OF THE CONTROL BUILDING 4606mm Title Site Figure 4.7: Welfare, Substation and Control Building - Elevation UK Proposed Inverclyde Wind Farm Client Inverclyde Renewables LLP Roller Shutter Door WEST ELEVATION Roller Shutters on all windows Scale NTS A CC
14 Key GRANULAR BACKFILL TOPSOIL GROUND LEVEL COMPACTED STONE GROUND LEVEL MARKER TAPE 200 MARKER TAPE 200 TELECOMMUNICATION CABLE GRANULAR BACKFILL APPROVED CABLE COVER 6 APPROVED CABLE COVER 1000 EQ COPPER EARTH TAPE COPPER EARTH TAPE TELECOMMUNICATION CABLE SAND/RIDDLED EARTH BEDDING EQ SAND/RIDDLED EARTH BEDDING 5No. 125mm DIAMETER PLASTIC RIGIDUCTS 95 3-CABLES IN TREFOIL FORMATION SCALE 1:25 CABLES ROAD CROSSING SCALE 1:25 NOTE : GROUND TO BE REINSTATED WITHIN 2 MONTHS OF WIRE AND CABLE INSTALLATION NOTES: 1. ALL DIMENSIONS SHOWN ARE APPROXIMATE AND MAY VARY FURTHER TO FINAL DESIGN. DO NOT SCALE FROM THIS DRAWING. Title Figure 4.8: Cable Trenching - Section Site UK Proposed Inverclyde Wind Farm Client Scale Inverclyde Renewables LLP NTS A CH
Linfairn Wind Farm Addendum Chapter A3: Project Description
A3. PROJECT DESCRIPTION 3.1 Introduction This chapter provides a description of the changes to the Project since the ES was published. An outline Construction Environmental Management Plan (CEMP) is included
More information5 Construction and Environmental Management
Inverclyde Wind Farm Inverclyde Renewables LLP 5 Construction and Environmental Management Introduction 5.1 In order to inform the prediction of environment effects set out in the technical chapters, this
More informationOweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B
Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International
More informationDESIGN & ACCESS STATEMENT
DESIGN & ACCESS STATEMENT IN SUPPORT OF THE PROPOSED ERECTION OF A SINGLE WIND TURBINE WITH MAXIMUM BLADE TIP HEIGHT OF 67M, FORMATION OF NEW VEHICULAR ACCESS, ACCESS TRACK AND ASSOCIATED INFRASTRUCTURE
More informationToddleburn Wind Farm. Environmental Statement Non-technical Summary. I & H Brown Toddleburn Ltd
Toddleburn Wind Farm Environmental Statement Non-technical Summary I & H Brown Toddleburn Ltd July 2004 Introduction I & H Brown Toddleburn Ltd proposes to develop a wind farm near Oxton, in the Scottish
More informationStrathy Wood Wind Farm Peat Volume Calculations
22 nd July 2015 Nikki Anderson Energy Consents & Deployment Unit Scottish Government 4th Floor, 5 Atlantic Quay 150 Broomielaw Glasgow G2 8LU Dear Nikki Strathy Wood Wind Farm Volume Calculations I am
More informationSgurr Energy Ltd. Linfairn Wind Farm Appendix 9.3 Outline Peat Management Plan. September This Document is of UK Origin
Sgurr Energy Ltd Linfairn Wind Farm Appendix 9.3 Outline Peat Management Plan September 2013 This Document is of UK Origin EnviroCentre Document No. 5614 EnviroCentre Project No. 161766j Status Final Project
More informationCONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5
CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey
More information14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER
Knockskae Wind Farm Environmental Statement Volume 2 Main Report 14-1 14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER 14.1 Introduction 14.1.1 This Chapter has been prepared by. It identifies and
More informationProposed Blackhillock Substation Expansion. Public Exhibition
Proposed Blackhillock Substation Expansion Public Exhibition 9 February 2012 Blackhillock Substation Expansion: Pre Application Consultation The proposals are for the redevelopment of the existing substation
More informationTullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT
HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,
More informationOrkney Sustainable Energy Document OSE/2881 Chapter 7 October 2012
Orkney Sustainable Energy Document OSE/2881 Chapter 7 October 2012 Orkney Sustainable Energy Limited 6 North End Road Stromness Orkney KW16 3AG Telephone 01856 850054 Email info@orkneywind.co.uk Web www.orkneywind.co.uk
More informationHarryburn Wind Farm. Technical Appendix Peat Management Plan Innogy Renewables UK Ltd
Harryburn Wind Farm Technical Appendix 11.2 Peat Management Plan Innogy Renewables UK Ltd SLR Ref: 405.06521.00001 Version No: Final April 2017 Harryburn Wind farm 405.06521.00001 CONTENTS 1.0 NON TECHNICAL
More informationORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity.
ORDINANCE NO. AN ORDINANCE AMENDING ORDINANCE NO. 1060 KNOWN AS THE WILLMAR ZONING ORDINANCE BY ADDING SECTION 11 RELATING TO WIND ENERGY CONVERSION SYSTEMS (WECS) The City of Willmar does ordain as follows:
More informationGROUSEMOUNT WIND FARM County Kerry
GROUSEMOUNT WIND FARM County Kerry ENVIRONMENTAL IMPACT STATEMENT VOLUME 1 - NON-TECHNICAL SUMMARY & EIS TEXT ESB WIND DEVELOPMENT Report No. QR-320171-11-GK0715-R01 ESB WIND DEVELOPMENT LIMITED GROUSEMOUNT
More informationBig Thunder Wind Park
Construction Plan Report DRAFT Prepared by: M.K. Ince and Associates Ltd. May 18, 2010 TABLE OF CONTENTS BIG THUNDER WIND PARK... 1 1 PROJECT OVERVIEW... 1 1.1 PROJECT SCHEDULE... 2 2 CONSTRUCTION ACTIVITIES...
More informationAppendix D: A selection of slides from presentations at local Community Council meetings
Appendix D: A selection of slides from presentations at local Community Council meetings Hill of Ochiltree Wind Farm Public Consultation Pre-Application Consultation Report Facilitating Change (UK) Limited
More informationAppendix 6.D Enoch Hill Wind Farm FEI - Justification for Values Used in Carbon Calculator
6.D1 Appendix 6.D Enoch Hill Wind Farm FEI - Justification for Values Used in Carbon Calculator Wind Farm Characteristics Dimensions No. of turbines 16 16 16 Number of turbines included in Proposed Development.
More informationMohawk College Hamilton, ON. Project Description Report. Fennell Campus Wind Project
Mohawk College Hamilton, ON Fennell Campus Wind Project H336493-0000-07-124-0001 Rev. C September 24, 2010 Project Report Mohawk College Fennell Campus Wind Project September 24, 2010 Table of Contents
More informationINTRODUCTION Purpose of this EIA Report The Applicant Site Description Overview of the Proposed Development...
1. INTRODUCTION Purpose of this... 1-2 The Applicant... 1-2 Site Description... 1-3 Overview of the Proposed Development... 1-3 EIA Process... 1-5 Structure of the... 1-6 The Environmental Impact Assessment
More information8 Geology, Hydrology & Hydrogeology
Inverneill Wind Farm Scoping Report Page 42 8 Geology, Hydrology & Hydrogeology 8.1 Introduction The EIA will consider the potential issues arising from the construction, operation and decommissioning
More informationAppendix 6.A Peat Management Plan
Appendix 6.A Peat Management Plan Amec Foster Wheeler Environment & Infrastructure UK Limited Amec Foster Wheeler Environment & Infrastructure UK Limited E.ON Climate & Renewables UK Developments Ltd Lorg
More informationApplications. 5 reasons why you should choose Hebden X Grid cellular paving
5 reasons why you should choose Hebden X Grid cellular paving The British-made Hebden X Grid cellular paving system can be filled with grass or gravel, then driven over, parked on and walked on whilst
More informationSTATE OF VERMONT PUBLIC SERVICE BOARD PREFILED TESTIMONY AND EXHIBITS OF IAN A. JEWKES
STATE OF VERMONT PUBLIC SERVICE BOARD Docket No. Petition of Dairy Air Wind, LLC for a certificate of public good, pursuant to 0 V.S.A., for the installation of a single turbine,. MW wind-powered electric
More informationAnnex F Scoping Checklist
Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve
More informationLow Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]
Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent
More informationManagement Plan: Hazardous Materials Removal & Demolition
Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council
More informationGarvagh Glebe Wind Energy Project County Leitrim
HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's
More informationDecommissioning Report East Durham Wind Energy Centre
NextEra Energy Canada, ULC East Durham Wind Energy Centre Prepared by: GENIVAR Inc. 500 600 Cochrane Drive 905-475-7270 tel Markham, ON, Canada L3R 5K3 905-475-5994 fax www.genivar.com Project Number:
More informationBackground and Project Description. Chapter 05: Description of Development
Background and Project Description Chapter 05: Description of Development Background and and Project Project Description Description DESCRIPTION OF DEVELOPMENT OF Chapter Chapter Contents Contents...
More informationSOUTH BRANCH WIND FARM DECOMMISSIONING REPORT
SOUTH BRANCH WIND FARM DECOMMISSIONING REPORT Report 7 of 9 March 26, 2012 South Branch Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario L8R 2L3 Tel: 905-528-1747 Fax: 866-203-6516 Email:
More informationEnergy 3 Frequently Asked Questions
Energy 3 Frequently Asked Questions What is wind energy? Wind energy is a converted form of solar energy. The sun's radiation heats different parts of the earth at different rates, most notably during
More informationK2 WIND POWER PROJECT DECOMMISSIONING PLAN REPORT. Prepared by: K2 Wind Ontario Limited Partnership Suite 105, 100 Simcoe Street Toronto, ON M5H 3G2
K2 WIND POWER PROJECT DECOMMISSIONING PLAN REPORT Prepared by: K2 Wind Ontario Limited Partnership Suite 105, 100 Simcoe Street Toronto, ON M5H 3G2 In association with: Stantec Consulting Ltd.; SENES Consultants
More informationABERARDER WIND FARM. Environmental Statement Volume I Non-Technical Summary
ABERARDER WIND FARM Environmental Statement 2014 Volume I CONTENTS Preface... 2 Introduction... 4 Site Location... 5 Development Plan Policy... 7 Environmental Sensitivity... 9 Site Construction & Decommissioning...
More informationCF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE
CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document
More informationOverview. Tangy III Wind Farm Proposal. SSE Renewables. Site location. This exhibition
Overview SSE Renewables SSE Renewables is the renewable energy division of SSE plc. It is responsible, on behalf of SSE Generation Limited, for the development and construction of SSE group s renewable
More informationClachaig Glen. Design and Access Statement. May 2016
Clachaig Glen Design and Access Statement May 2016 Clachaig Glen Wind Farm Design and Access Statement 1 1 INTRODUCTION 1.1 Introduction 1.1.1 This Design and Access Statement (DAS) has been prepared
More information11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...
Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3
More informationGores Wind Farm. Environmental Statement. Volume 1 - Written Text
Gores Wind Farm Environmental Statement Volume 1 - Written Text Prepared By West Coast Energy Limited Mynydd Awel Mold Business Park Maes Gwern Mold CH7 1XN VOLUME ONE - WRITTEN TEXT CHAPTER ONE - INTRODUCTION
More informationWelcome to Hoolan Energy s public exhibition for our wind farm proposal
WELC ME Welcome to Hoolan Energy s public exhibition for our wind farm proposal This exhibition contains information about our plans for a wind development, including visualisations, potential access routes
More informationChapter 750 WIND POWER GENERATION FACILITIES
Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements
More informationFinal Construction Plan Report Belle River Wind Project
Prepared by: AECOM 105 Commerce Valley Drive West, Floor 7 905 886 7022 tel Markham, ON, Canada L3T 7W3 905 886 9494 fax www.aecom.com Project Number: 60321891 Date: May, 2015 Table of Contents 1. Introduction...
More information19. INTERACTION OF IMPACTS
19. INTERACTION OF IMPACTS 19.1 INTRODUCTION In addition to the requirement to describe the likely significant effects of the proposed development on the different elements of the environment, it is also
More informationTechnical Data
4906-17-05 Technical Data (A) PROJECT AREA SITE have occurred in this section. (1) Geography and Topography have occurred in this section. (2) Aerial Photography have occurred in this section. (3) Site
More informationGRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION
CHAPTER 23.105 GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION Sections 23.105.101 General... 1 23.105.102 Definitions... 1 23.105.103 Permits required... 3 23.105.104 Hazards.... 4 23.105.105 Permit
More informationCHAPTER 8 Energy Efficiency, and Renewable Energy. Kildare County Development Plan , Volume 1
Chapter 6 Rural Housing Strategy CHAPTER 8 Energy Efficiency, and Renewable Energy 157 8 ENERGY EFFICIENCY AND RENEWABLE ENERGY 8.1 Background The development of renewable energy sources is a priority
More informationKentish Flats Offshore Wind Farm
Kentish Flats Offshore Wind Farm A pure spot on the Map of the World Kentish Flats Offshore Wind Farm features 30 wind-powered turbines each with a nominal rated capacity of 3 MW making a net capacity
More informationAPPENDIX A3. Outline Construction Environmental Management Plan. 1 Introduction Background Project Description...
APPENDIX A3. Outline Construction Environmental Management Plan Contents 1 Introduction... 3 1.1 Background... 3 1.2 Project Description... 3 1.3 Aims and Objectives... 4 1.4 Structure of Outline CEMP...
More informationCrowlands Wind Farm. Project construction information and update
Crowlands Wind Farm Project construction information and update About the Project Crowlands wind farm is a renewable energy project currently under construction. Located in Western Victoria s Pyrenees
More informationRampion Offshore Wind Farm Frequently Asked Questions (FAQs)
Rampion Offshore Wind Farm Frequently Asked Questions (FAQs) February 2012 Q: Why renewable energy? A: Renewable energy involves generating electricity from natural sustainable energy sources, which do
More informationWind Power Development on Port of Corpus Christi Authority Property
Wind Power Development on Port of Corpus Christi Authority Property Prepared for American Association of Port Authorities Harbors, Navigation and Environment Committees Seminar May 1, 2012 San Francisco,
More informationRefer to Chapter 3.0 (Description of Development) for a detailed site and development description.
7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT
Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,
More informationNOVEMBER 2016 GRANDWALL. retaining walls installation guide
NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining
More informationPROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL BACKGROUND INFORMATION DOCUMENT April 2014 (2 nd Edition) Project developer: South Africa Mainstream
More informationOverview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition
and Stronelairg s Overview SSE Renewables SSE Renewables is the renewable energy development division of SSE. The company is responsible for the development of onshore and offshore wind farms in the UK,
More information21 July Anthony Yeates RATCH-Australia Corporation Limited Level 7, 111 Pacific Highway North Sydney NSW 2060
AECOM Australia Pty Ltd Level 21, 420 George Street Sydney NSW 2000 PO Box Q410 QVB Post Office NSW 1230 Australia www.aecom.com +61 2 8934 0000 tel +61 2 8934 0001 fax ABN 20 093 846 925 21 July 2015
More informationSandy Knowe Wind Farm. Non-Technical Summary Addendum
Sandy Knowe Wind Farm Non-Technical Summary Addendum Sandy Knowe Wind Farm Ltd November 2013 SANDY KNOWE WIND FARM ii NON-TECHNICAL SUMMARY Contents 1 Background 1 2 Availability of the ES Addendum 2 3
More informationKnockendurrick Wind Farm Proposal
Knockendurrick Wind Farm Proposal Planning Application and Environmental Statement Non Technical Summary September 2013 Energy for everyone s benefit of the proposed site showing 132m turbines. View from
More informationAnnex L. Project Risk Analysis Matrix
Annex L Project Risk Analysis Matrix L1 Table L1 Project Environmental Risk Analysis Local Road upgrades: Loss/damage cultural heritage values Low Acceptable Loss/damage of biodiversity value, EEC Construction
More informationNatural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).
Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...
More informationSeneca Wind Cluster. Non Technical Summary May 2013 SENECA GLOBAL ENERGY
Seneca Wind Cluster Non Technical Summary May 2013 SENECA GLOBAL ENERGY Non-Technical Summary This document presents a Non Technical Summary (NTS) of the Environmental Statement (ES), which has been submitted
More informationReport on Archaeological Testing of Luas Line A1 Belgard to Saggart, Co.Dublin.
Project code: RPLT08 Client: Railway Procurement Agency Date: October, 2008. Report on Archaeological Testing of Luas Line A1 Belgard to Saggart, Co.Dublin. Director: Liam Hackett. Author : Liam Hackett.
More informationORDINANCE BE IT ORDAINED BY THE MAYOR AND COUNCIL OF THE CITY OF NORTH MYRTLE BEACH, SOUTH CAROLINA, IN COUNCIL DULY ASSEMBLED, THAT:
Section 1: ORDINANCE AN ORDINANCE OF THE CITY OF NORTH MYRTLE BEACH PROVIDING THAT THE CODE OF ORDINANCES, CITY OF NORTH MYRTLE BEACH, SOUTH CAROLINA, BE AMENDED BY ADDING ARTICLE VII.1 TO CHAPTER 23.
More informationManagement of Design and Construction for Civil Works under EPC contract in one Oversea Wind Farm Project
ORIGINAL ARTICLE Management of Design and Construction for Civil Works under EPC contract in one Oversea Wind Farm Project Wu Zheng Power China Chengdu Engineering Corporation LTD, Chengdu 610072 Abstract:
More informationEIGHT POINT WIND ENERGY CENTER
EIGHT POINT WIND ENERGY CENTER Case No. 16 F 0062 1001.11 Exhibit 11 Preliminary Design Drawings Contents Exhibit 11: Preliminary Design Drawings... 1 11(a) Site Plan... 1 11(b) Construction Operations
More informationlegend. #1 is a gas relief valve? If so does Enbridge supply with station?
Michael Pacholok, Director Purchasing and Materials Management Division City Hall, 8 th Floor, West Tower 00 Queen Street West Toronto, Ontario M5H N Joanne Kehoe Manager Construction Services May 4, 06
More informationWhite Rock Wind Farm. Traffic and Transport Impact Assessment
White Rock Wind Farm Traffic and Transport Impact Assessment November 2010 Page 2 of 19 Contents 1. Introduction...3 1.1 Project location...3 1.2 Project description...3 2. Key Issues and their Assessment...4
More informationSECTION A1 EXCAVATION AND BACKFILL GENERAL
SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such
More informationLINE ONE LINE TWO LINE THREE
LINE ONE LINE TWO LINE THREE Environmental Statement Volume 1: Non-Technical Summary Prepared by This document has been prepared by Limited for the sole use of our client (the Client ) and in accordance
More informationOvercoming Ecological Challenges and Exploring Biodiversity Opportunities Associated with Energy Infrastructure Projects in Scotland
Overcoming Ecological Challenges and Exploring Biodiversity Opportunities Associated with Energy Infrastructure Projects in Scotland Kathy Dale EnviroCentre Limited Summary Scotland s renewables targets
More informationMarble River Wind Farm: Contact Information
: Contact Information For more information on the, please contact the project developers at www.horizonwind.com, www.acciona.es or www.aes.com. Our current Marble River office is located at the Adirondack
More informationFeatures Include: Near Vertical Walls Do it Yourself No Concrete Footings Required
Features Include: Near Vertical Walls Do it Yourself No Concrete Footings Required Tel: Office: +27 (0)11 964 2995 Fax number: +27 (0)86 601 6692 info@dsmmasonry.co.za www.dsmmasonry.co.za Range three
More informationSeparation between Wind Turbines and Overhead Lines Principles of Good Practice
PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation L44 Separation between Wind Turbines and Overhead Lines Principles of Good Practice www.energynetworks.org
More informationPrimary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane.
17. SERVICES 17.1 Introduction 17.1.1 WSP Development Limited has been appointed by CALA Homes to investigate and appraise the availability of services to serve a proposed mix-use development of approximately
More informationLANDSCAPE RETAINING WALLS
SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls
More informationBirneyknowe Wind Farm Proposal
Birneyknowe Wind Farm Proposal Planning Application and Environmental Statement Non Technical Summary April 2014 Energy for everyone s benefit Image shows 100m to tip turbines at West Durham Wind Farm
More informationLOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989
DOCUMENT 8b LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989 DIRECTION UNDER SECTION 90(2ZA) OF THE TOWN AND COUNTRY PLANNING ACT 1990 TO VARY THE CONDITIONS
More informationArticle 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS
Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS SECTION 57.010, PURPOSE: The purpose of this article is to establish wind generation and wireless communication tower (Hereafter referred to
More informationTABLE OF CONTENTS PAGE SECTION
TABLE OF CONTENTS SECTION PAGE 1.0 EXECUTIVE SUMMARY... 1 1.1 Project Description... 1 1.2 Project Applicant... 1 1.3 Summary of Project Purpose and Need... 2 1.4 Summary of Proposed Alternative... 2 1.5
More informationPermeability across the entire site within the General Residential Zone is a minimum of 30%.
Partly Operative District Plan Rule Assessment The following assessment is to demonstrate compliance or non-compliance with the rules of the Partly Operative District Plan. The proposed duplex dwellings,
More informationCity of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING
January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01
More information9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:
SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities
More informationLOT GRADING GUIDELINES FOR LOW DENSITY RESIDENTIAL PROPERTIES
LOT GRADING GUIDELINES FOR LOW DENSITY RESIDENTIAL PROPERTIES Contents LOT GRADING GUIDELINES... 3 LOW DENSITY RESIDENTIAL PROPERTIES... 3 Introduction... 3 Definitions:... 3 Purpose... 3 LOT GRADING APPROVAL
More informationSITE ENVIRONMENTAL MANAGEMENT PLAN VIKING WIND FARM TECHNICAL SCHEDULE 2 POLLUTION PREVENTION PLAN
Document No. TS2 Page i VIKING WIND FARM TECHNICAL SCHEDULE 2 SEMP Version: 1.0 Rev No. Revision Description: Date : 0.0 Addendum ES, Appendix A14.6 Sept 2010 Name : Position : Signature : Prepared by
More informationKENT BREEZE WIND FARMS
Decommissioning Plan Report MAY 2010 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. DECOMMISSIONING PROCESS DESCRIPTION... 2 3. SITE RESTORATION... 3 4. EXCESS MATERIALS AND WASTE MANAGEMENT... 4 5. MANAGING
More informationTHE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT
THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT Welcome Eggborough Power Ltd (EPL) is proposing to develop a new gas-fired power station on the site of its existing coal-fired
More informationWillow Ridge Wind Project Frequently Asked Questions. Popular Questions Who is the developer of the proposed project?
Willow Ridge Wind Project Frequently Asked Questions Popular Questions Who is the developer of the proposed project? Algonquin Power Co./ Liberty Power Co. is the company proposing the project and, if
More information8 Geology, Hydrology, Hydrogeology
Camster II Wind Farm Scoping Report 50 8 Geology, Hydrology, Hydrogeology 8.1 Introduction The EIA will consider the potential issues arising from the construction, operation and decommissioning of the
More informationCity of Doral 8401 NW 53 rd Ter. Doral, FL 33166
City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control
More informationAMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for:
PROPERTY LINE SETBACK ASSESSMENT REPORT File No. 160960595 April 2013 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L6H 7H7 Prepared by: Stantec Consulting Ltd. Suite 1 70 Southgate Drive
More information5.6 Details of Other Consents and Licenses
The Millbrook Power (Gas Fired Power Station) Order 5.6 Details of Other Consents and Licenses Planning Act 2008 The Infrastructure Planning (Applications: Prescribed Forms and Procedure) 2009 PINS Reference
More informationAPPENDIX 4.1 OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN FOR SHEPHERDS RIG WIND FARM INFINERGY
APPENDIX 4.1 OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN FOR SHEPHERDS RIG WIND FARM INFINERGY Prepared By: 7th Floor 144 West George Street Glasgow G2 2HG T +44 (0)141 221 9997 l E info@arcusconsulting.co.uk
More informationBRITISH CONSTRUCTIONAL STEELWORK ASSOCIATION LIMITED
SAFE SITE HANDOVER CERTIFICATE AND CHECKLIST 2008 Introduction Safety during steelwork erection is a key focus of BCSA and its member companies; issues such as safety when working at height, personal protective
More informationGE Power & Water Renewable Energy. Introducing GE s 2.75 MW Wind Turbines Increased customer value through product evolution
GE Power & Water Renewable Energy Introducing GE s 2.75 MW Wind Turbines 2.75-100 2.75-103 Increased customer value through product evolution Introducing GE s 2.75-100 and 2.75-103 Product evolution. It
More informationEmergency Management Guidelines For Wind Energy Facilities. Emergency Management Guidelines for Wind Energy Facilities
Emergency Management Guidelines For Wind Energy Facilities Emergency Management Guidelines for Wind Energy Facilities MAY 2015 Emergency Management Guidelines For Wind Energy Facilities 1 Emergency Management
More informationNational Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance
National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and Guidance NSI 6 DEMARCATION IN SUBSTATIONS Copyright National Grid plc 2016, all rights reserved. No part of this publication
More informationAppendix 7.B Private Water Supply Risk Assessment
Appendix 7.B Private Water Supply Risk Assessment E.on Climate and Renewables (EC&R) Kelmarsh Wind Farm Risk Assessment of Private Water Supplies Entec UK Limited Copyright and Non-Disclosure Notice
More informationKlickitat County. On-Site Sewage System. Construction Manual
Homeowner OSS Design and Construction Guide Klickitat County On-Site Sewage System Construction Manual Minimum standards and recommendations expected for the construction of on-site wastewater treatment
More informationIf a new residence s electrical service is not located within 200 feet of existing
Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close
More information