THERMAL ASSESSMENT OF PASSIVE COOLED FOUNDATION SOILS BENEATH THE TRANS-ALASKA PIPELINE AT ATIGUN PASS

Size: px
Start display at page:

Download "THERMAL ASSESSMENT OF PASSIVE COOLED FOUNDATION SOILS BENEATH THE TRANS-ALASKA PIPELINE AT ATIGUN PASS"

Transcription

1 THERMAL ASSESSMENT OF PASSIVE COOLED FOUNDATION SOILS BENEATH THE TRANS-ALASKA PIPELINE AT ATIGUN PASS Keith F. Mobley 1, Mike R. Fitzpatrick. 2, John E. Ferrell 3 1. Shannon & Wilson, Inc Fairbanks Street, Suite 3 Anchorage, Alaska Michael Baker, Jr., Inc Business Park Blvd Anchorage, Alaska Alyeska Pipeline Service Co S. Bragaw Anchorage, Alaska Introduction The Trans-Alaska Pipeline crosses the Brooks Range in northern Alaska at Atigun Pass (See Figure 1). The upper portions of the pass consist of steep sided valleys with rock slopes rising about 800 to 1000 meters above the bottom. Due to avalanche and rock fall hazard, the pipeline was constructed in the below-ground mode, despite the presence of thaw unstable permafrost. To mitigate the stability issues, the pipeline was constructed within insulated boxes to protect two thaw unstable permafrost zones. In 1979, it was discovered that portions of the soil beneath the insulated boxes had begun to thaw. Thermosyphons were installed as a part of the effort to restore the permafrost. Abstract The foundation of a section of the Trans-Alaska Pipeline was stabilized in 1981 using thermosyphons. Over the past 16 years, some of the thermosyphon radiators were damaged from avalanches and rock fall. A large avalanche in 1994 did significant damage to about 1/3 of the array. This potential reduction in the cooling capacity of the array raised concern about the long-term stability of the pipeline in this area. A field and modeling study was conducted to assess the current cooling capacity of the array and to predict the future thermal environment of the foundation soils. Thermistor strings were installed in existing vacant cased borings. A twodimensional finite element thermal analysis was done, with the soil parameters calibrated to match the known temperatures. A multi-year model was run to help predict the future performance of the remaining portion of the array. Results of the modeling indicate that the remaining thermosyphons have sufficient capacity to maintain the foundation in a frozen state. The heat pipes located on the south side of Atigun Pass have been damaged as a result of several avalanches, rock falls, and ice expansion within the casings. The damage has reduced the cooling capacity of the system. The purpose of this study was to evaluate the current conditions and to determine if the stability Figure 1. Location of Atigun Pass. Keith F. Mobley, et al. 739

2 of the pipeline in this area was at risk, and to provide recommendations for further work, if necessary. The scope of work included a limited field effort to determine current temperature conditions and inventory of the heat pipe physical conditions, and a thermal analysis via finite element computer modeling. Two different scenarios representing full and partial heat pipe capacity were run. History During construction of the pipeline in Atigun Pass, two portions of the alignment, one each on the north and south sides of the pass, were recognized as being thaw unstable. However, the pipeline was constructed below ground based on the assessment of avalanche and rockfall hazards. To mitigate the thaw unstable foundation, each thaw unstable portion of the pipe was placed in an insulated box that rests on a continuous 3 m wide, 0.3-m thick concrete slab. The box on the north side of the pass is about 550 meters long, and the south side box is about 1300 meters long. In 1979, about 2 years after oil flow commenced, an oil leak was discovered on the north side of the pass. Investigation revealed that ice within a predominately rock rubble matrix had melted, allowing the pipe to settle. The investigation was expanded to look at the entire Atigun Pass section of the pipeline to see if other areas had experienced similar settlements. Several other portions of the pipe had settled, including a 122-m section near the north end of the southern insulated box, which settled up to 1.5 m. Field studies conducted from 1979 through 1981 (WCC, 1981) indicated that the major reason for the settlement was the presence of warm water flowing along the pipeline trench backfill and creating a large thaw bulb below the insulated box. In addition, the groundwater infiltrated into the insulated box, degrading the pipe coating, the grout sleeve and the insulation. Degradation of the insulation further exacerbated the thaw problems. Repair work for the south side insulated box included two grout curtains to control the water flow under the insulated box, pressure grouting to lift the pipe into a better curvature condition, construction of two surface drainage channels to divert runoff away from the pipe, drilling wells to remove existing groundwater along the pipeline corridor; and mechanical and passive ground freezing to restore the thermal regime, thereby restabilizing the foundation soils. The mechanical freezing was accomplished by drilling 268 refrigeration casings at about 1 m on centers on both sides of the insulated box to a depth of about 10 m, generally about 1.5 to 2.1 m from the pipe centerline. Once all of the casings were in place, refrigeration piping was placed in each, manifolded together and a brine coolant circulated through a refrigeration plant. At the conclusion of the mechanical refrigeration in October 1980, all of the refrigeration piping was removed from the casings. Ammonia (NH 3 ) filled, free standing heat pipes were installed in mid to late October 1980 to the bottom of about 1/2 of the mechanical refrigeration casings, generally alternating in the existing refrigeration casings. The heat pipes were designed to cool the ground enough to maintain frozen ground above the thaw unstable portion of the foundation. The remaining refrigeration casings were left open at the ground surface and were filled with a glycol, water and rust inhibitor mixture. Since 1980, there have been several avalanches and rock falls that have damaged a number of the heat pipes. In addition, ice expansion, jacking and splitting have damaged other heat pipes and casings. Field work In October 1996, one set of ground temperature profiles extending to 5 to 10 m were obtained by inserting a 12-point thermistor string to the bottom of an open refrigeration casing. The casings used still contained the antifreeze and corrosion inhibitor solution that was added at the end of the 1980 construction season. The thermosyphon array was inventoried to determine the approximate portion of cooling capacity remaining. In January 1997, an infrared study was conducted by Alyeska to assess the performance of the thermosyphons. Infrared readings were taken of each radiator for qualitative indications of heat transfer. Thermal analysis A finite element computer program titled TEMP/W was used to analyze ground thermal conditions with the heat pipe array at full, undamaged capacity and to simulate conditions with only one-third of the heat pipe capacity operating. TEMP/W is a two-dimensional finite element, geothermal computer program developed by Geo-Slope International to model ground thermal responses to environmental or physical changes. The governing set of equations used in TEMP/W states that the difference between the heat flux entering and leaving an elemental volume of soil at a point in time is equal to the change in the stored heat energy. The program allows for complete modeling of material types; properties such as thermal conductivity, heat capacity and volu- 740 The 7th International Permafrost Conference

3 Table 1 Model Input Parameters metric water content; and boundary conditions including changes of temperature with time, nodal heat fluxes and heat flux changes with time. See Table 1 for input parameters. A near step function was employed to model the latent heat removal or addition during the phase change of water within the material matrix. A finite element mesh was created and the various material properties and boundary conditions applied. The model does not take into account convective heat transfer. Because the subsurface water flow was controlled during the 1980 repair efforts, eliminating the convective portion of the heat transfer was considered acceptable. monthly temperature profile from the 1 day time steps of the model for one year to bring the model into equilibrium, then for an additional 18 months, for a total of 2.5 years of modeling. Each individual heat pipe was determined to have a heat extraction capacity of 0.56 kcal/min-m of evaporator embedment when there was a 1.7 C temperature differential between the radiator fins and the condenser pipe (WCC, 1980). For the model, we assumed that when the temperature differential was less than 1.7 C, the heat pipe had no cooling capacity over the portion The initial values for thermal properties of the soil were obtained from published data (Andersland and Anderson, 1978; Lunardini, 1981). The thermal conductivity for wet insulation was based on previously completed experimental data (Shannon and Wilson, 1994). ANALYTICAL MODEL The physical conditions of the model include the finite element geometry and boundary conditions, the infinite boundary, pipeline, wet insulation, nodes that represent the heat pipes, and the soil types. A half space (axis-symmetric) model was used in the analysis in order to reduce the calculation time required by the computer, see Figure 2. An infinite boundary was placed at the left edge. Input parameters for the pipeline, soil, heat pipe and air were developed based on our knowledge of the surrounding conditions, ground temperature profiles, and pipeline operating conditions. The model was developed to output a Figure 2. Finite Element Half-Space Model Keith F. Mobley, et al. 741

4 of the evaporator that failed the temperature differential criteria. It is possible for the heat pipe to be functional even if only the bottom foot of the heat pipe has a 1.7 C temperature differential. The heat flux functions were determined by trial and error. Trial and error was required as the heat removal capacity of the heat pipes is a function of the ground temperature and the air temperature, while the ground temperature is a function of the heat removed by the heat pipes. This results in one equation and two unknowns. The heat pipes generally begin to function at air temperatures of Ð2 C and below. These values are dependent on the pressure and concentration of the NH 3 in the heat pipe. It was also assumed that only 5 m of the 6 m of heat pipe length was active in extracting heat, with the top meter of the pipe in the ground maintaining very close to the air temperature. Results Temperatures read during the October 1996 fieldwork were mostly below freezing, with a range from about -8 to just above 0 C. Only one thermistor point recorded a temperature above freezing. The heat pipes had probably been operational for two to three weeks. Based on the model, the ground temperatures get so cold that thawing at the bottom of the concrete support slab probably does not begin until late May or June. Thaw does not reach the bottom of the thermosyphons until late August or September, just before the thermosyphons will again become active. The thermal model was adjusted to provide results at the end of the first year equilibrating run that closely matched the temperatures measured during the fieldwork. The assumptions used for the adjusted air temperature, soil parameters and heat pipe capacity, although most likely not equal to actual conditions, are close enough that individual errors are for the most part canceling each other. At 100% heat pipe capacity, the ground around the oil pipeline within the heat pipe array would be getting colder each year, as shown in Figure 3. Our model indicates that at 1/3 of the installed heat pipe capacity, it is marginal to keep the ground beneath the pipeline in frozen thermal equilibrium. See Figure 4. With approximately 2/3 of the original installed capacity still available, the heat pipe array in its current condition is more than sufficient to keep the ground frozen, even during extreme weather event years where there is a warm, snowy winter followed by a warm, wet summer. Conclusion The Trans-Alaska Pipeline within the south side insulated box is not in danger of settling due to thawing of the foundation soils. With the reduced oil temperatures (47¼C in 1980 and 34¼C in 1996) and the groundwater and surface water flow diverted away from the warm pipe upstream of the insulated box, the reduced capacity of the heat pipes is keeping the soil temperature in equilibrium. Approximately 1/2 of the heat pipes are physically damaged. The infrared study conducted by Alyeska in January 1997 indicates that most of the damaged heat pipes are still nearly fully functional. The north half of the array is in excellent condition with about 94% of the pipes still intact. Some of the pipes are bent and a few may have leaked ammonia, but it is likely that the cooling capacity is at or above 80% of the original installed capacity. The south half of the array is in much worse condition, with only about 57% of the heat pipes likely functional. Again some of the remaining pipes are bent and a few may have leaked ammonia, so the cooling capacity is probably near 50% of the original capacity. The average capacity of the entire array is therefore likely at or above 65% of the original installed capacity. The most important area to keep frozen is the north half, where the heat pipes are in good condition. Keeping the northern edge frozen effectively diverts any upstream groundwater away from the thaw unstable zones. Without moving water, even with greatly reduced cooling capacity, the ground will likely not thaw very much, and remain cooled due to the ambient air temperatures. If the annual, late summer thermal monitoring in the future shows a trend of increasing thaw, Alyeska would have time to implement a repair to refreeze the ground. Over most of the array, more than 7 m of ground below the concrete slab has to rethaw (the first time was in 1979 and 1980) before reaching new thaw unstable (never thawed) ground. Based on the model, replacement of most of the damaged, non-functional heat pipes would refreeze the ground in one winter. Acknowledgments The authors wish to express their appreciation to Alyeska Pipeline Service Company for their permission to present this information. 742 The 7th International Permafrost Conference

5 Figure % heat pipe capacity 0¼C Isotherm Figure 4. 33% heat pipe capacity 0¼C Isotherm References Andersland, O.B. and Anderson, D.M. (1978). Geotechnical Engineering for Cold Regions. McGraw Hill Inc., New York ( Lunardini, Virgil J. (1981). Heat Transfer in Cold Climates. Van Nostrand Reinhold Inc., New York (731 pp) Shannon & Wilson, Inc. (1994). Insulation Conductivity Study. Report to Alyeska Pipeline Service Co. Woodward Clyde Consultants, Inc. (1980). Atigun Pass, MP Pipe Stabilization and Instrumentation Volumes 1 and 2. Report to Alyeska Pipeline Service Company Woodward Clyde Consultants, Inc. (1981). Atigun Pass, MP Pipe Stabilization and Instrumentation, Report to Alyeska Pipeline Service Company Keith F. Mobley, et al. 743

Analysis of flooding effects on a landfill permafrost containment system

Analysis of flooding effects on a landfill permafrost containment system Permafrost, Phillips, Springman & Arenson (eds) 2003 Swets & Zeitlinger, Lisse, ISBN 90 5809 582 7 Analysis of flooding effects on a landfill permafrost containment system A.K.F. Mobley Principal, Northern

More information

Thermosyphon in End View

Thermosyphon in End View GEO-SLOPE International Ltd, Calgary, Alberta, Canada www.geo-slope.com 1 Introduction Thermosyphon in End View Thermosyphons and heat pipes are a passive form of artificial ground freezing in which heat

More information

UPDATE OF PERFORMANCE OF SLOPES ON THE NORMAN WELLS PIPELINE PROJECT

UPDATE OF PERFORMANCE OF SLOPES ON THE NORMAN WELLS PIPELINE PROJECT UPDATE OF PERFORMANCE OF SLOPES ON THE NORMAN WELLS PIPELINE PROJECT Introduction In April, 1985 the Interprovincial Pipeline (NW) Limited began transporting crude oil from Norman Wells N.W.T. to Zama,

More information

Trans-Alaska Pipeline System

Trans-Alaska Pipeline System Trans-Alaska Pipeline System Low Flow Plan Summary A Report on Low Flow Issues Through 2030 Prepared by the TAPS Owners 3 June 2009 Report Contents 1.0 Executive Summary...4 2.0 Background Information...6

More information

John Thornley, PE & Brenton Savikko, PE Golder Associates, Inc.

John Thornley, PE & Brenton Savikko, PE Golder Associates, Inc. Geotechnical Implications of Climate Impacts in Permafrost John Thornley, PE & Brenton Savikko, PE Golder Associates, Inc. What is Permafrost? How Do Changes in Permafrost Affect Geotechnical Engineering?

More information

Unique Thermosyphon Roadway Test Site Spanning 11 years

Unique Thermosyphon Roadway Test Site Spanning 11 years Unique Thermosyphon Roadway Test Site Spanning 11 years Anna M. Wagner US Army Cold Regions Research and Engineering Laboratory, Ft. Wainwright, AK, USA John P. Zarling Department of Civil and Environmental

More information

Thermosyphon Foundations in Warm Permafrost

Thermosyphon Foundations in Warm Permafrost Thermosyphon Foundations in Warm Permafrost Igor Holubec, Ph.D., P.Eng. I. Holubec Consulting Inc. March 13 & 14, 2008 Project Definition Sponsor - Government of Northwest Territories, Public Works and

More information

The Diavik Waste Rock Project: Heat Transfer in a Large Scale Waste Rock Pile Constructed in a Permafrost Region

The Diavik Waste Rock Project: Heat Transfer in a Large Scale Waste Rock Pile Constructed in a Permafrost Region The Diavik Waste Rock Project: Heat Transfer in a Large Scale Waste Rock Pile Constructed in a Permafrost Region Nam Pham, Richard Amos, David Blowes, Leslie Smith and Dave Sego 1 2 2 3 1 1. Department

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

Northern Built Infrastructure Program

Northern Built Infrastructure Program Northern Built Infrastructure Program Introducing A New CSA Standard for: Moderating the effects of permafrost degradation on existing building foundations Richard Trimble, P.Eng., FEC Working Group Member

More information

Permafrost Engineering

Permafrost Engineering First Circular International Short Course on Permafrost Engineering Effective Design and Construction in Permafrost Regions December 5 to December 10, 2013 Edmonton, Alberta Department of Civil and Environmental

More information

The basic elements of the system include: Buried loops of piping (the ground loop); A biodegradable liquid antifreeze;

The basic elements of the system include: Buried loops of piping (the ground loop); A biodegradable liquid antifreeze; GeoThermal Welcome to the new era of home comfort otherwise known as GeoThermal heating and cooling. While the name may sound space-age, the technology is very well, down-to-earth. Read on to find out

More information

Permafrost Engineering

Permafrost Engineering First Circular International Short Course on Permafrost Engineering Effective Design and Construction in Permafrost Regions May 8 13, 2015 Edmonton, Alberta Department of Civil and Environmental Engineering

More information

is a possibility of the existence of permafrost as a result

is a possibility of the existence of permafrost as a result 111.2 CERTAIN ASPECTS OF ALASKA DISTRICT ENGINEERS EXPERIENCE IN AREAS OF MARGINAL PERMAFROST E. L. Long In nearly twenty years of engineering and construction experience in Alaska, the Alaska District

More information

White Paper. Geothermal Heating and Cooling

White Paper. Geothermal Heating and Cooling White Paper Geothermal Heating and Cooling The fundamentals of a geoexchange system (geothermal heating and cooling system) are well understood and although many factors need to be considered when designing

More information

Permafrost Engineering

Permafrost Engineering International Short Course on Permafrost Engineering Effective Design and Construction in Permafrost Regions November 29 th December 4, 2018 Edmonton, Alberta Department of Civil and Environmental Engineering

More information

Developing and Managing Transportation Infrastructure in Permafrost Regions

Developing and Managing Transportation Infrastructure in Permafrost Regions Transportation Association of Canada Primer on Developing and Managing Transportation Infrastructure in Permafrost Regions Permafrost underlies about half of the landmass of Canada and our northern road,

More information

Available online at ScienceDirect. Procedia Engineering 113 (2015 )

Available online at   ScienceDirect. Procedia Engineering 113 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 113 (2015 ) 282 286 International Conference on Oil and Gas Engineering, OGE-2015 Ground heat stabilizer work research in year-round

More information

Index. STP779-EB/Jul. 1982

Index. STP779-EB/Jul. 1982 STP779-EB/Jul. 1982 Index A Absorption of moisture (see Moisture absorption) Adsorption, 191 Capillary versus time, 197 Isotherms For glass fiber, 194, 195 For various materials, 196 Air leakage (exfiltration,

More information

Grouting for Freezing

Grouting for Freezing Grouting for Freezing Joseph A. Sopko, Ph.D., P.E. M.ASCE 1, Adam T. Curry, P.E. M.ASCE, 2 and Gregory T. Ziegler, P.E., M.ASCE 3 1 Moretrench American Corporation, 100 Stickle Ave., Rockaway, NJ 07866;

More information

Thermal Cover Design for Mine Waste Facilities in Cold Regions

Thermal Cover Design for Mine Waste Facilities in Cold Regions Thermal Cover Design for Mine Waste Facilities in Cold Regions Christopher W. Stevens SRK Consulting (U.S.) Inc., Anchorage, Alaska, USA Tia Shapka-Fels SRK Consulting (Canada) Inc., Vancouver, British

More information

TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada

TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada INTRODUCTION The Historic Turner Valley Gas Plant is located

More information

A Case Study Approach for Engineering & Economic Analysis for Climate Change Adaptation: Alaska s Dalton Highway

A Case Study Approach for Engineering & Economic Analysis for Climate Change Adaptation: Alaska s Dalton Highway A Case Study Approach for Engineering & Economic Analysis for Climate Change Adaptation: Alaska s Dalton Highway First International Conference on Surface Transportation System Resilience to Climate Change

More information

Permafrost Engineering

Permafrost Engineering First Circular International Short Course on Permafrost Engineering Effective Design and Construction in Permafrost Regions April 24-29, 2008 Edmonton, Alberta Department of Civil and Environmental Engineering

More information

Review of Current Practice of Building Foundations in the Canadian North

Review of Current Practice of Building Foundations in the Canadian North Review of Current Practice of Building Foundations in the Canadian North Christine Harries 1 1 SNC-Lavalin, Montreal QC, Canada christine.harries@snclavalin.com Abstract. The Canadian North is experiencing

More information

Surface Layer. Surfa c e layer. Active layer. Pe rm a fro st

Surface Layer. Surfa c e layer. Active layer. Pe rm a fro st Permafrost Permafrost is soil that is always frozen. Because the Arctic and sub-arctic are so cold and dark for much of the year, soil under the surface doesn t receive enough warmth through the sun to

More information

The Hydrosphere The hydrosphere is the Earth s outer layer of water The distribution of water on Earth:

The Hydrosphere The hydrosphere is the Earth s outer layer of water The distribution of water on Earth: The Hydrosphere The Hydrosphere The hydrosphere is the Earth s outer layer of water The distribution of water on Earth: 2.5 97.5 21 79 Catchment Areas Catchment: All the area of land from which water empties

More information

Snow-Melting on Sidewalks with Ground-Coupled Heat Pumps in a Heavy Snowfall City

Snow-Melting on Sidewalks with Ground-Coupled Heat Pumps in a Heavy Snowfall City Proceedings World Geothermal Congress 2005 Antalya, Turkey, 24-29 April 2005 Snow-Melting on Sidewalks with Ground-Coupled Heat Pumps in a Heavy Snowfall City Koji Morita 1 and Makoto Tago 2 1 National

More information

Application of Thermal Piles in Thawing a Frozen Ground

Application of Thermal Piles in Thawing a Frozen Ground NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Application of Thermal Piles in Thawing a Frozen Ground G. Sinnathamby* *Geoengineering,

More information

LARGE STORAGE TANK PROJECT

LARGE STORAGE TANK PROJECT INTRODUCTION The Fairbanks Large Storage Tank is part of the Interior Energy Project (IEP) designed to expand natural gas distribution in Fairbanks and Interior Alaska. A tank with a capacity of 0.44 Bcf

More information

FULL YEAR PERFORMANCE SIMULATION OF A DIRECT-COOLED THERMAL STORAGE ROOF (DCTSR) IN THE MIDWEST

FULL YEAR PERFORMANCE SIMULATION OF A DIRECT-COOLED THERMAL STORAGE ROOF (DCTSR) IN THE MIDWEST FULL YEAR PERFORMANCE SIMULATION OF A DIRECT-COOLED THERMAL STORAGE ROOF (DCTSR) IN THE MIDWEST Richard C. Bourne Davis Energy Group, Inc. 123 C Street Davis, CA 95616 and Dr. Bing Chen Passive Solar Research

More information

and Engineering Laboratory Cold Regions Research Demonstration of an Artificial Frozen Barrier ERDC/CRREL TR-12-12

and Engineering Laboratory Cold Regions Research Demonstration of an Artificial Frozen Barrier ERDC/CRREL TR-12-12 ERDC/CRREL TR-12-12 Installation Technology Transfer Program Demonstration of an Artificial Frozen Barrier Anna M. Wagner and Edward Yarmak, Jr. November 2012 Cold Regions Research and Engineering Laboratory

More information

[5] SA1.2 The student demonstrates an understanding of the processes of science by using

[5] SA1.2 The student demonstrates an understanding of the processes of science by using Levels Overview: In this lesson, students explore the active layer above permafrost and investigate various factors on the insulation value of the active layer. (NOTE: This lesson will require more than

More information

Novel Modeling Approach to Understand the Fate of Infiltrated Water at Green Stormwater Infrastructure in Philadelphia, PA

Novel Modeling Approach to Understand the Fate of Infiltrated Water at Green Stormwater Infrastructure in Philadelphia, PA Novel Modeling Approach to Understand the Fate of Infiltrated Water at Green Stormwater Infrastructure in Philadelphia, PA Matt Gamache 1*, Daniel O Rourke 2, and Mark Maimone 3 1 CDM Smith, Boston, Massachusetts

More information

COLD WEATHER CONCRETING

COLD WEATHER CONCRETING When placing concrete in cold climates, certain precautions should be taken to avoid damage from freezing. Freezing can cause ice crystals to form in the paste of freshly placed concrete, which can retard

More information

Subject: Geotechnical consultation Permafrost foundation Plate Boundary Observatory (PBO), Alaska DMA Job No , UNAVCO P.O. No.

Subject: Geotechnical consultation Permafrost foundation Plate Boundary Observatory (PBO), Alaska DMA Job No , UNAVCO P.O. No. July 14, 2006 UNAVCO PBO 1200 East 76th Ave Suite 1210 Anchorage, AK 99518 Attention: Benjamin A. Pauk (pauk@unavco.org) cc: Chuck Kurnik (kurnik@unavco.org) Subject: Geotechnical consultation Permafrost

More information

geoexchange as an alternative energy source DESIGN APPROACHES

geoexchange as an alternative energy source DESIGN APPROACHES geoexchange as an alternative energy source DESIGN APPROACHES GEOEXCHANGE AN ALTERNATIVE ENERGY SOURCE T The earth provides the perfect heat exchange medium: harnessing constant, year-round temperatures

More information

Chapter Six{ TC "Chapter Six" \l 1 } System Simulation

Chapter Six{ TC Chapter Six \l 1 } System Simulation Chapter Six{ TC "Chapter Six" \l 1 } System Simulation In the previous chapters models of the components of the cooling cycle and of the power plant were introduced. The TRNSYS model of the power plant

More information

Walking on Frozen Ground

Walking on Frozen Ground Levels Overview: A local Elder visits the classroom to share information on permafrost in the local area. I-II Teacher s Note: This activity is repeated in the Level III-IV lesson Tour of the Grades K-4

More information

Comparison of Borehole Heat Exchangers (BHEs): State of the Art vs. Novel Design Approaches

Comparison of Borehole Heat Exchangers (BHEs): State of the Art vs. Novel Design Approaches Comparison of Borehole Heat Exchangers (BHEs): State of the Art vs. Novel Design Approaches P. Oberdorfer * F. Maier and E. Holzbecher University of Göttingen Geoscience Centre Applied Geology *Corresponding

More information

International Forum on Energy, Environment Science and Materials (IFEESM 2015)

International Forum on Energy, Environment Science and Materials (IFEESM 2015) TRNSYS Simulation of Hybrid Ground Source Heat Pump System Based on Cooling Conditions Jun Zhang1, a *, Shunyu Su1, b*, Lamei Liu1,c, Chuanhui Zhou1,d, Lei Shi2,e 1 College of Urban Construction, Wuhan

More information

Simulation of a Thermal Environment for Chilled Foods during Transport

Simulation of a Thermal Environment for Chilled Foods during Transport Simulation of a Thermal Environment for Chilled Foods during Transport D.Stubbs, S.H.Pulko, A.J.Wilkinson + Abstract Here we describe a modification of the existing treatments for thermal effects associated

More information

Presentation Outline

Presentation Outline St. John s Tunnel Rehabilitation A Demonstration of Successful Fast- Track Design and Construction Christopher P. Russell, P.E. Shannon & Wilson Inc., Staff Engineer Gregory R. Fischer, Ph.D., P.E. Shannon

More information

New Large Geothermal Storage Project in Zurich/Switzerland for Heating and Cooling

New Large Geothermal Storage Project in Zurich/Switzerland for Heating and Cooling Proceedings World Geothermal Congress 25 Antalya, Turkey, 24-29 April 25 New Large Geothermal Storage Project in Zurich/Switzerland for Heating and Cooling E. Rohner, S. Bassetti and T. Kohl GEOWATT AG,

More information

Endless Possibilities Use of Heat Pipe for Global Warming Reduction

Endless Possibilities Use of Heat Pipe for Global Warming Reduction 10th IHPS, Taipei, Taiwan, Nov. 6-9, 2011 Endless Possibilities Use of Heat Pipe for Global Warming Reduction Masataka Mochizuki, Thang Nguyen, Koichi Mashiko, Yuji Saito, Tien Nguyen and Vijit Wuttijumnong

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

Part 1 Review Questions on material covered in Midterms I & II

Part 1 Review Questions on material covered in Midterms I & II 1 Arch 463 ECS Fall 2001 Name FINAL 40 Multiple Choice Questions Part 1 Review Questions on material covered in Midterms I & II 1. Passive systems for environmental control A. can enhance human comfort

More information

CHAPTER 18 FOUNDATIONS IN AREAS OF SIGNIFICANT FROST PENETRATION

CHAPTER 18 FOUNDATIONS IN AREAS OF SIGNIFICANT FROST PENETRATION CHAPTER 18 FOUNDATIONS IN AREAS OF SIGNIFICANT FROST PENETRATION 18-1. Introduction. a. Types of areas. For purposes of this manual, areas of significant frost penetration may be defined as those in which

More information

PERMAFROST ENGINEERING APPLIED TO TRANSPORTATION INFRASTRUCTURE

PERMAFROST ENGINEERING APPLIED TO TRANSPORTATION INFRASTRUCTURE NVS stipend 2016 PERMAFROST ENGINEERING APPLIED TO TRANSPORTATION INFRASTRUCTURE ABSTRACT This report covers the course outline and detailed description of field trips during the course in May 2016 in

More information

An Introduction to Road Design for Cold Regions

An Introduction to Road Design for Cold Regions An Introduction to Road Design for Cold Regions J. Paul Guyer 2013 1 CONTENTS 1. GENERAL 2. BASE COURSE AND PAVEMENT COMPOSITION 3. BASE COURSE DESIGN IN AREAS OF NON-FROST- SUSCEPTIBLE SOILS 4. BASE COURSE

More information

MONTREAL AT WORK New tunnel construction starts across the city. NORTH AMERICAN EDITION October ~ November 2017

MONTREAL AT WORK New tunnel construction starts across the city. NORTH AMERICAN EDITION October ~ November 2017 The official publication of the Tunnelling Association of Canada NORTH AMERICAN EDITION October ~ November 2017 MONTREAL AT WORK New tunnel construction starts across the city TECHNICAL / GEOTECHNICAL

More information

Enhancement of Heat Exchange Capacity of Ground Heat Exchangers by Injecting Water into Wells

Enhancement of Heat Exchange Capacity of Ground Heat Exchangers by Injecting Water into Wells PROCEEDINGS, Thirty-Ninth Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, February 24-26, 2014 SGP-TR-202 Enhancement of Heat Exchange Capacity of Ground Heat Exchangers

More information

Thermal Control in Buildings by John Straube (updated )

Thermal Control in Buildings by John Straube (updated ) building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Building Science Digest 011 Thermal Control in Buildings 2006-11-02 by John Straube (updated 2011-12-12)

More information

Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park

Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park Prepared for: City of Bellingham Public Works Department Environmental Resource Division 210 Lottie St.

More information

DEALING WITH PERMAFROST DEGRADATION UNDER AIRPORT PAVEMENTS

DEALING WITH PERMAFROST DEGRADATION UNDER AIRPORT PAVEMENTS DEALING WITH PERMAFROST DEGRADATION UNDER AIRPORT PAVEMENTS Ludomir Uzarowski, Rabiah Rizvi, Mark Musial, Golder Associates Ltd. Susan Tighe, University of Waterloo SWIFT, CAPTG Niagara Falls, September

More information

What is a ground source heat pump?

What is a ground source heat pump? What is a ground source heat pump? Ground source heat pumps (GSHPs) are electrically powered systems that tap the stored energy of the greatest solar collector in existence: the earth. These systems use

More information

RECENT APPLICATIONS OF GEOTHERMAL ANALYSIS IN NORTHERN ENGINEERING

RECENT APPLICATIONS OF GEOTHERMAL ANALYSIS IN NORTHERN ENGINEERING RECENT APPLICATIONS OF GEOTHERMAL ANALYSIS IN NORTHERN ENGINEERING J.F. (Derick) Nixon Nixon Geotech Ltd Box 9, Site 9, RR6, Calgary, Alberta T2M 4L5 e-mail: derickn@cadvision.com Abstract Geothermal analysis

More information

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No 000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

Dynamic groundwater-river interaction model for planning water allocation in a narrow valley aquifer system of the Upper Motueka catchment

Dynamic groundwater-river interaction model for planning water allocation in a narrow valley aquifer system of the Upper Motueka catchment Dynamic groundwater-river interaction model for planning water allocation in a narrow valley aquifer system of the Upper Motueka catchment Timothy Hong t.hong@gns.cri.nz Gilles Minni g.minni@gns.cri.nz

More information

Re: Information Request Submission for the NIRB s Review of AEM s Whale Tail Pit Expansion Project Proposal

Re: Information Request Submission for the NIRB s Review of AEM s Whale Tail Pit Expansion Project Proposal February 21, 2019 NIRB file # - 16MN056 NRCan # - NT- 099 Sophia Granchinho Manager, Impact Assessment Nunavut Impact Review Board PO Box 1360 Cambridge Bay, NU, X0B 0C0 Via electronic mail to: info@nirb.ca

More information

Figure 4-8. horizontal trench loops single-pipe, single-trench loops

Figure 4-8. horizontal trench loops single-pipe, single-trench loops Figure 4-8. Pulling back loop lines Horizontal Trench Loops As drilling progresses to the design length, the bit is directed from its 10-ft depth back up to the surface. At the surface, a pulling shackle

More information

2006 Building Science Press All rights of reproduction in any form reserved.

2006 Building Science Press All rights of reproduction in any form reserved. building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Building Science Digest 011 Thermal Control in Buildings 2006-11-07 by John Straube Abstract: Providing

More information

Reducing running costs, whilst benefiting the environment and the future

Reducing running costs, whilst benefiting the environment and the future Reducing running costs, whilst benefiting the environment and the future The Danfoss DHP-R produces heating and hot water using stored solar energy from the bedrock, surface ground, groundwater or exhaust

More information

INCREASING THE UNDER-GROUND CABLES AMPACITY BY USING ARTIFICIAL BACKFILL MATERIALS

INCREASING THE UNDER-GROUND CABLES AMPACITY BY USING ARTIFICIAL BACKFILL MATERIALS I J E E S R Vol. 3 No. 2 July-December 2013, pp. 79-85 INCREASING THE UNDER-GROUND CABLES AMPACITY BY USING ARTIFICIAL BACKFILL MATERIALS Ossama E. Gouda 1, Adel Z. El Dein 2 & Ghada M. Amer 3 1 Faculty

More information

National Research Council Canada. Conseil national de recherches Canada. Canada

National Research Council Canada. Conseil national de recherches Canada. Canada National Research Council Canada Conseil national de recherches Canada In-situ Performance Evaluation of Exterior Insulation Basement System (EIBS) Spray Polyurethane Foam Summary Report M.C. Swinton,

More information

Investigations on the mechanical behaviour of a Heat Exchanger Pile

Investigations on the mechanical behaviour of a Heat Exchanger Pile Deep Foundations on Bored and Auger Piles Van Impe & Van Impe (eds) 29 Taylor & Francis Group, London, ISBN 978--415-47556-3 Investigations on the mechanical behaviour of a Heat Exchanger Pile L. Laloui

More information

PERFORMANCE OF AN ENGINEERED COVER SYSTEM FOR A URANIUM MINE WASTE ROCK PILE IN NORTHERN SASKATCHEWAN AFTER SIX YEARS

PERFORMANCE OF AN ENGINEERED COVER SYSTEM FOR A URANIUM MINE WASTE ROCK PILE IN NORTHERN SASKATCHEWAN AFTER SIX YEARS PERFORMANCE OF AN ENGINEERED COVER SYSTEM FOR A URANIUM MINE WASTE ROCK PILE IN NORTHERN SASKATCHEWAN AFTER SIX YEARS B. Ayres, P.Eng. 1 M. O Kane, P.Eng. 1 L. Barber 1 D. Hiller 2 D. Helps 2 ABSTRACT

More information

Cambridge International Examinations Cambridge International General Certificate of Secondary Education

Cambridge International Examinations Cambridge International General Certificate of Secondary Education Cambridge International Examinations Cambridge International General Certificate of Secondary Education *1007469920* ENVIRONMENTAL MANAGEMENT 0680/21 Paper 2 October/November 2016 1 hour 45 minutes Candidates

More information

Effects of flow behavior on the design of transient operation scenarios

Effects of flow behavior on the design of transient operation scenarios Effects of flow behavior on the design of transient operation scenarios *Jakyung Kim 1) and Yutaek Seo 2) 1), 2) Division of Ocean Systems Engineering, KAIST, Daejeon 305-600, Korea 1) kjkwkrud@kaist.ac.kr

More information

Public Works Manual. Revised September Concrete & Asphalt

Public Works Manual. Revised September Concrete & Asphalt Public Works Manual Revised September 2015 Concrete & Asphalt Where it must cross domestic it must cross above and with a 1 minimum separation. Nonpotable water tape. 10.00 PORTLAND CEMENT CONCRETE 10.01

More information

Appendix D. Erosion Management Sub- Plan

Appendix D. Erosion Management Sub- Plan Appendix D Erosion Management Sub- Plan DRENNAN SOLAR ENERGY FACILITY EROSION MANAGEMENT PLAN PRODUCED FOR ERM ON BEHALF OF SOLAIREDIRECT BY Simon.Todd@3foxes.co.za JUNE 2013 PURPOSE The purpose of the

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 2 SPECIAL BENCHING AND SIDEHILL EMBANKMENT FILLS Geotechnical Bulletin GB2

More information

Coupled Hydrological and Thermal Modeling of Permafrost and Active Layer Dynamics: Implications to Permafrost Carbon Pool in Northern Eurasia

Coupled Hydrological and Thermal Modeling of Permafrost and Active Layer Dynamics: Implications to Permafrost Carbon Pool in Northern Eurasia Coupled Hydrological and Thermal Modeling of Permafrost and Active Layer Dynamics: Implications to Permafrost Carbon Pool in Northern Eurasia Sergey Marchenko & Vladimir Romanovsky University of Alaska

More information

Suez Water Westchester. Storer Avenue Bridge Water Main Replacement

Suez Water Westchester. Storer Avenue Bridge Water Main Replacement Suez Water Westchester Storer Avenue Bridge Water Main Replacement Edwin C. Tifft Jr. Water Supply Symposium Thursday September 20 th, 2016 Intro/Welcome Agenda Welcome & Thank you Gerard Moreno, P.E.

More information

Review on Numerical Simulation of frosting behavior on Ambient air vaporizer

Review on Numerical Simulation of frosting behavior on Ambient air vaporizer Review on Numerical Simulation of frosting behavior on Ambient air vaporizer Lokesh Shivrajsingh Thakur Masters in Thermal Engineering, Mechanical Engineering Department, A.D. Patel institute of technology,

More information

Design of a New Ice Thermal Energy Storage System

Design of a New Ice Thermal Energy Storage System Union College Union Digital Works Honors Theses and Student Projects 6-2017 Design of a New Ice Thermal Energy Storage System Andrew Fontaine Union College - Schenectady, NY Follow this and additional

More information

Permafrost, climate change and northern communities. Steve Kokelj and Steve Wolfe INAC & NRCan

Permafrost, climate change and northern communities. Steve Kokelj and Steve Wolfe INAC & NRCan Permafrost, climate change and northern communities Steve Kokelj and Steve Wolfe INAC & NRCan Outline What is permafrost? Climate change and permafrost Landscape change Permafrost and communities What

More information

Introduction to Utilidors, Power Distribution and Communication Systems in Cold Regions

Introduction to Utilidors, Power Distribution and Communication Systems in Cold Regions Introduction to Utilidors, Power Distribution and Communication Systems in Cold Regions Course No: E01-003 Credit: 1 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development,

More information

NANISIVIK MINE Closure Design and Performance Monitoring

NANISIVIK MINE Closure Design and Performance Monitoring NANISIVIK MINE Closure Design and Performance Monitoring Jim Cassie, M.Sc., P.Eng. Principal Geotechnical Engineer BGC Engineering Inc. 2015 RPIC FEDERAL CONTAMINATED SITES REGIONAL WORKSHOP OUTLINE SITE

More information

Impact of Frost Heaving on Catch Basin and Road Infrastructure. Presented By: Kurtis Anketell, EIT Public Works Department

Impact of Frost Heaving on Catch Basin and Road Infrastructure. Presented By: Kurtis Anketell, EIT Public Works Department Impact of Frost Heaving on Catch Basin and Road Infrastructure Presented By: Kurtis Anketell, EIT Public Works Department Outline Introduction Heaved Catch Basin Problem in Red Deer Frost Heave Indicators

More information

Science SC Records, collects and explains data. SC Applies and accurately reads appropriate scientific instruments.

Science SC Records, collects and explains data. SC Applies and accurately reads appropriate scientific instruments. Overview: Students analyze soil temperature data to determine which soil sample is permafrost and explore the affect the active layer plays on permafrost structure. Levels III-IV Objectives: The student

More information

Mechanical Redesign. Existing System: The following schematic was devised below.

Mechanical Redesign. Existing System: The following schematic was devised below. Mechanical Redesign Existing System: The mechanical system explained in the existing conditions was simulated on an energy modeling system call equest. This program was used because of its strong detailed

More information

Numerical Modeling of Slab-On-Grade Foundations

Numerical Modeling of Slab-On-Grade Foundations Numerical Modeling of Slab-On-Grade Foundations M. D. Fredlund 1, J. R. Stianson 2, D. G. Fredlund 3, H. Vu 4, and R. C. Thode 5 1 SoilVision Systems Ltd., 2109 McKinnon Ave S., Saskatoon, SK S7J 1N3;

More information

Simulations of a New Double U-tube Borehole Configuration with Solar Heat Injection and Ground Freezing

Simulations of a New Double U-tube Borehole Configuration with Solar Heat Injection and Ground Freezing Simulations of a New Double U-tube Borehole Configuration with Solar Heat Injection and Ground Freezing Parham Eslami Nejad 1 and Michel Bernier 2 1 Canmet Energy Technology Center, Varennes, Québec 2

More information

STATE OF ALASKA ALASKA OIL AND GAS CONSERVATION COMMISSION 333 West Seventh Avenue Anchorage, Alaska ) ) ) ) ) )

STATE OF ALASKA ALASKA OIL AND GAS CONSERVATION COMMISSION 333 West Seventh Avenue Anchorage, Alaska ) ) ) ) ) ) STATE OF ALASKA ALASKA OIL AND GAS CONSERVATION COMMISSION 333 West Seventh Avenue Anchorage, Alaska 99501 Re: Mechanical Integrity of Prudhoe Bay Wells Docket Number: OTH-18-064 Prudhoe Bay Field IT APPEARING

More information

GEOTHERMAL HEAT PUMPS CONFIGURATIONS/INSTALLATION

GEOTHERMAL HEAT PUMPS CONFIGURATIONS/INSTALLATION GEOTHERMAL HEAT PUMPS CONFIGURATIONS/INSTALLATION There are three main categories when dealing with geothermal heat pumps; open-loop, closed-loop, and direct-exchange. The closed-loop and direct-exchange

More information

The Art of Thermal Mass Modeling for Energy Conservation in Buildings, Part 2

The Art of Thermal Mass Modeling for Energy Conservation in Buildings, Part 2 The Art of Thermal Mass Modeling for Energy Conservation in Buildings, Part 2 Linda Lam is a Project Engineer at Transsolar, Inc. She has a traditional mechanical engineering background with an energetic

More information

Flat Loop Thermosyphon Foundations in Warm Permafrost

Flat Loop Thermosyphon Foundations in Warm Permafrost Flat Loop Thermosyphon Foundations in Warm Permafrost Prepared for Government of the NT Asset Management Division Public Works and Services and Climate Change Vulnerability Assessment Canadian Council

More information

Geothermal Heating & Cooling in Health Care Applications

Geothermal Heating & Cooling in Health Care Applications Geothermal Heating & Cooling in Health Care Applications Sergio Almeida, P.Eng. sergio@geoxergy.com (204) 255 5959 May 18, 2017 Intro to Geo Why Geothermal? Future outlook for Geothermal in Ontario What

More information

Introduction Retrofit interior insulation of masonry buildings Exterior insulation ideal solution Interstitial condensation, freeze thaw issues

Introduction Retrofit interior insulation of masonry buildings Exterior insulation ideal solution Interstitial condensation, freeze thaw issues Introduction Retrofit interior insulation of masonry buildings Exterior insulation ideal solution Interstitial condensation, freeze thaw issues Kohta Ueno, Building Science Corporation Masonry Wall Interior

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

Category 1 Waste Rock Stockpile Groundwater Containment System

Category 1 Waste Rock Stockpile Groundwater Containment System Memorandum To: Jennifer Saran, Poly Met Mining Inc. Project: 23690862.00-042-008 1.0 Introduction The Co-Lead Agencies have requested a summary of the four containment systems that are planned for the

More information

OPERATION AND CONTROL OF THERMALLY ACTIVATED SLAB HEATING AND COOLING SYSTEMS

OPERATION AND CONTROL OF THERMALLY ACTIVATED SLAB HEATING AND COOLING SYSTEMS OPERATION AND CONTROL OF THERMALLY ACTIVATED SLAB HEATING AND COOLING SYSTEMS Bjarne W. Olesen Ph. D, International Centre for Indoor Environment and Energy, Department of Mechanical Engineering, Technical

More information

A Comparative Study of the Thermal Comfort of Different Building Materials in Sana a

A Comparative Study of the Thermal Comfort of Different Building Materials in Sana a American Journal of Engineering and Applied Sciences, 6 (1): 20-24, 2013 ISSN: 1941-7020 2014 Alhaddad and Jun, This open access article is distributed under a Creative Commons Attribution (CC-BY) 3.0

More information

Geothermal Heat Pump Systems Efficiency in Russia

Geothermal Heat Pump Systems Efficiency in Russia Proceedings World Geothermal Congress 2010 Bali, Indonesia, 25-29 April 2010 Geothermal Heat Pump Systems Efficiency in Russia Grigoriy Vassiliev, Victor Gornov 32 build 3, Bolshaya Filevskaya str., Moscow,

More information

Chapter 10. Pipeline Installation

Chapter 10. Pipeline Installation Chapter 10 CHAPTER 10 STOCKWATER PIPELINE INSTALLATION TABLE OF CONTENTS PART 10.1 TRENCHING 10-1 10.1.1 Backhoe Constructed Trench 10-1 10.1.2 Trencher Constructed Trench 10-1 10.1.3 Backfilling and Maintenance

More information

VADOSE/W 2D Tutorial

VADOSE/W 2D Tutorial 1 Introduction VADOSE/W 2D Tutorial This example illustrates the basic methodology for simulating soil-climate interaction of an engineered soil cover system placed over a waste. The primary objective

More information

Active Geotechnical Treatment Technology for Permafrost Embankment of Qinghai-Tibet Railway

Active Geotechnical Treatment Technology for Permafrost Embankment of Qinghai-Tibet Railway Active Geotechnical Treatment Technology for Permafrost Embankment of Qinghai-Tibet Railway Xue-qin Chen Department of Civil Engineering, Shaoxing University, Shaoxing 312000, China Cui-hong Li Department

More information