Overview Balance Management project

Size: px
Start display at page:

Download "Overview Balance Management project"

Transcription

1 Overview Balance Management project Ove S. Grande WS Gardermoen 26 January 11 SINTEF Energy Research 0

2 The Balance Management Project Competence building project in the framework of The Norwegian Research Council - Renergi Program. Project period Project partners: TSOs (Statnett, TenneT), regulator (NVE), 4 Norwegian producers, GDF Suez, Delft University of Technology, The Norwegian University of Science and Technology (NTNU) 2 Norwegian and 2 Dutch PhDs PhD funding from The Norwegian Research Council, Next Generation Infrastructure (NGI) NL and GDF Suez, Belgium SINTEF Energy Research 1

3 The Balance Management Project Motivation Optimal use of reserves over national borders Reduce reserve costs Exploit the favorable properties of hydro power plants as balancing resources Increased need for reserves due to a growing share of RES with less predictable output. Market coupling of European day ahead markets and the ongoing integration process in Europe SINTEF Energy Research 2

4 Balance management project Results Overview Balancing Mechanisms Northern Europe Analyses of present costs (incl. database marginal costs thermal prod) General market design aspects Potential exchange schemes between the Nordic and the Central European synchronous systems PhD work: Market design and regulatory aspects (TU Delft) Market models and simulations (NTNU) 4 seminars / WS: Arnhem, NL, Feda, N, Schiphol, NL, Gardermoen, N List of publications Dec 10: 4 TRs, 15 papers, database regulation costs thermal production, presentations/lectures Open documents downloadable at SINTEF Energy Research 3

5 Balancing Areas in Northern Europe SINTEF Energy Research 4

6 Future picture (?): The Nordic synchrounous region and the merged Norhtern Central European control area SINTEF Energy Research 5

7 Integration of balance management Main challenges Use of terminology Harmonization of market and rules Procurement and prioritization Timing market gate closure Settlement procedures Technical Exchange between separate synchronous systems via HVDC links Different production technologies Different control strategies SINTEF Energy Research 6

8 Definitions Imbalance Power Deviation: Difference between production output and consumption that will cause a rise or fall in frequency leading to activation of the primary control Regional/Area imbalance: Deviations from exchange plan for the defined balancing region/area. Area Control Error: ACE = Pexc + R f Settlement imbalance: Deviations from exchange plans for the balance responsible parties (BRP), in average over the settlement period (MWh/period) where the settlement period can be 60, 30 or 15 min. SINTEF Energy Research 7

9 Definitions Balancing control Primary Control: Automatic droop based frequency control Secondary Control: Automatic LFC/AGC Tertiary Control: Manual set point control Time Control: Manual set point control to eliminate the deviation between synchronous and universal time SINTEF Energy Research 8

10 Definitions Reserves (ETSO reference model) Frequency Containment Reserves (FCR) Operating reserves necessary for constant containment of frequency deviations (fluctuations) from nominal value Frequency Restoration Reserves (FRR) Operating reserves necessary to restore frequency to the nominal value after sudden system disturbance occurrence and consequently replace FCR Replacement Reserves (RR) Operating reserves necessary to restore the required level of operating reserves (FCR and FRR) SINTEF Energy Research 9

11 Definitions Balancing reserves Category Nordel Netherlands Germany Frequency Containment Reserves (FCR) Frequency Controlled Normal Operation Reserve (FCNOR) Primary reaction Primary Control capacity Frequency Controlled Disturbance Reserves (FCDR) Frequency Restoration Fast Active Regulation Capacity Secondary Control Reserves (FRR) Disturbance Reserves Reserve Capacity capacity (FADR) (Emergency Capacity) (Manually activated) Reserve Replacement Reserve Capacity Minutes reserves (RR) (Emergency Capacity) SINTEF Energy Research 10

12 Transition from market to physical operation in the Nordic region SINTEF Energy Research 11

13 Imbalance settlement Definitions Active balancing: Change in production or consumption on a request from the TSO to activate their bid in the balance market. Passive balancing: Contribution to regulation without having been requested to do so by the TSO. Two price settlement is used when different prices are used for active and passive balancing. Single and dual pricing: Only one or both of the up- and down prices within the hour SINTEF Energy Research 12

14 Alternatives for imbalance pricing: Marginal price. The price of the last balancing unit used. Average price of the energy balance actions.. Pay-as-bid. Each activation is paid the bid price. Elspot area price Incentive component (NL): Added to or subtracted from the imbalance price in the case of upward or downward regulation respectively SINTEF Energy Research 13

15 New Nordic model for BM settlement The Nordic TSOs have harmonised the pricing model based on two separate balances: Balance for production Balance for consumption The pricing of production imbalances is based on twoprice settlement and the pricing of consumption imbalances would be based on one-price settlement. SINTEF Energy Research 14

16 Overview imbalance settlement Settlement period [minutes] Balance definition Single/dual BM pricing Payment Mechanism Norway Consumption Dual (all Two prices Sweden Denmark 60 (Total) + Production countries from 2009) Marginal price Finland Netherlands 15 Total Dual One price Marginal price Germany 15 Total Single Two prices * Pay as bid / Average price SINTEF Energy Research 15

17 Balancing costs Technical report (ADAPT-consulting) : Documentation of present cost covering production and industrial consumption Spread sheet with cost data for 418 thermal production units (S, DK, GE, NL, B) Plan type Heat delivery Primary and secondary fuel Marginal fuel and CO2 costs Start/stop costs Efficiency SINTEF Energy Research 16

18 TR Balancing Market Design Role of Balancing Exchange of Balancing Services between control areas Design Variables Multi control area Balancing Market design proposals Performance criteria Evaluation of multinational balancing market designs SINTEF Energy Research 17

19 TR Exchange of Balancing resources between separate synchronous systems in Northern Europe Background Key principles for balance market integration The France-UK inititiative Merging of control areas in Northern Central Europe Exchange of reserves to/from the Nordic system System Characteristics Reserve requirements related to forecast uncertainties Balancing resources control objects Reservation of transmission capacity Pricing principles Alternative schemes for exchange (6 models proposed) Modeling of balance market integration in Northern Europe SINTEF Energy Research 18

20 Key principles BM integration (ERGEG) Security of supply Market based Mechanisms Effective Competition Impact of Cross-Border Trade reservation of transmission capacity Compatibility of balancing mechanisms SINTEF Energy Research 19

21 Nordic characteristics Balancing: Common merit order list Control criteria: f and t Restrictions: Bottlenecks, other opertional Automatic secondary control Balancing resources Hydro, Thermal, reducible loads Optimal choice of regulation objects Reserve requirements Allocation of HVDC transmission capacity SINTEF Energy Research 20

22 Optimal choise of control objects Efficiency of control actions is dependent of geographic location of control object Example: Loss of 100 MW production in Northern Norway in a situation with full utilization of the grid from north to south can be replaced by 60 MW load reduction in the Stockholm area due to reduction in marginal losses SINTEF Energy Research 21

23 Reserve requirements Update of Nordic requirements referring to congested corridors, not country borders Dynamic reservation related to wind and consumption forecast uncertainty SINTEF Energy Research 22

24 Allocation of HVDC transmission capacity P[MW] P ATC Balancing trade Intraday trade P BM P ID Day Ahead trade P DA ptu time SINTEF Energy Research 23

25 Sum up Main contributions Overview of balancing mechanisms in NE Regulation costs database thermal production Evaluation of market design Exchange with a merged N-CE control area parallel utilization of HVDC links Alternative exchange schemes between the Nordic and CE systems PhD work: Market design and regulatory aspects Modeling and analyses SINTEF Energy Research 24

Regulating Power Market (RPM) Review Study

Regulating Power Market (RPM) Review Study Regulating Power Market (RPM) Review Study High-level Summary Bonn / Oosterbeek 07.10.2013 PURPOSE AND SCOPE OF STUDY ANALYSIS OF CURRENT RPM DESIGN REGARDING ATTRACTIVENESS AND EFFICIENCY ANALYSIS OF

More information

Explanatory document for the Nordic synchronous area proposal for the FRR dimensioning rules in accordance with Article 157(1) of the Commission

Explanatory document for the Nordic synchronous area proposal for the FRR dimensioning rules in accordance with Article 157(1) of the Commission Explanatory document for the Nordic synchronous area proposal for the FRR dimensioning rules in accordance with Article 157(1) of the Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing

More information

TABLE OF CONTENTS. Page

TABLE OF CONTENTS. Page 3 TABLE OF CONTENTS Page TERMS AND ABBREVIATIONS... 5 1 INTRODUCTION... 7 2 THE ROLE OF SYSTEM BALANCING... 9 3 EXCHANGE OF BALANCING SERVICES BETWEEN CONTROL AREAS... 12 4 DESIGN VARIABLES... 13 4.1 DESIGN

More information

INTEGRATION OF RENEWABLES

INTEGRATION OF RENEWABLES INTEGRATION OF RENEWABLES System operation and grid codes- the case of Denmark System Integration of Renewables Japan, June 21 2018 Peter Børre Eriksen, Chief Engineer, Energinet 1 ENERGINET THE DANISH

More information

Frequency Restoration Process. Cross-border balancing project Elia-TenneT

Frequency Restoration Process. Cross-border balancing project Elia-TenneT Frequency Restoration Process Cross-border balancing project Elia-TenneT TSO responsibilities: impact pilot project Scope of pilot project: Design and evaluation of a harmonised reactive balancing market

More information

Modelling An Integrated Northern European Regulating Power Market Based On A Common Day-Ahead Market

Modelling An Integrated Northern European Regulating Power Market Based On A Common Day-Ahead Market 1 Modelling An Integrated Northern European Regulating Power Market Based On A Common Day-Ahead Market Stefan Jaehnert and Gerard L. Doorman Department of Electric Power Engineering Norwegian University

More information

Modelling An Integrated Northern European Regulating Power Market Based On A Common Day-Ahead Market

Modelling An Integrated Northern European Regulating Power Market Based On A Common Day-Ahead Market 1 Modelling An Integrated Northern European Regulating Power Market Based On A Common Day-Ahead Market Stefan Jaehnert and Gerard Doorman Department of Electric Power Engineering Norwegian University of

More information

Pilot 5: The Nordic Regulating Power Market

Pilot 5: The Nordic Regulating Power Market Pilot 5: The Nordic Regulating Power Market Optimizing the existing Nordic mfrr market and investigating possibilities to exchange with other regions Thomas Elgaard Jensen, Energinet.dk ENTSO-E, Bruxelles,

More information

ENTSO-E Cross Border Electricity Balancing Pilot Projects

ENTSO-E Cross Border Electricity Balancing Pilot Projects ENTSO-E Cross Border Electricity Balancing 2 Month Report on Pilot Project 2 Patrick Gasser Swissgrid 23 October 2015 1. Introduction... 3 2. Executive summary... 3 a) Participating TSOs... 3 b) Scope

More information

EcoGrid EU. Analysis of the European Framework for Balancing Power opportunities and new trends identified within the EcoGrid EU project 20/05/2013

EcoGrid EU. Analysis of the European Framework for Balancing Power opportunities and new trends identified within the EcoGrid EU project 20/05/2013 EcoGrid EU Analysis of the European Framework for Balancing Power opportunities and new trends identified within the EcoGrid EU project Presentation at: Workshop on DSM Potentials, Implementations and

More information

ENTSO-E Cross Border Electricity Balancing Pilot Projects

ENTSO-E Cross Border Electricity Balancing Pilot Projects ENTSO-E Cross Border Electricity Balancing 2 Month Report on Pilot Project 1 (GCC) Pavel Zolotarev TransnetBW 25 June 2015 1. Introduction... 3 2. Executive summary... 3 a) Participating TSOs... 3 b) Scope

More information

2 Proposal on Measures for FRCE Reduction - Article 152(12) and Article 152(16)... 4

2 Proposal on Measures for FRCE Reduction - Article 152(12) and Article 152(16)... 4 Supporting Document for the Proposals in Accordance with Article 6(3)(e) of SOGL submitted by 50Hertz Transmission, Amprion, CREOS S. A., Energinet, TenneT TSO and TransnetBW for the LFC Block TNG+TTG+AMP+50HZT+EN+CREOS

More information

Frequency Restoration Process. Cross-border balancing project Elia-TenneT

Frequency Restoration Process. Cross-border balancing project Elia-TenneT Frequency Restoration Process Cross-border balancing project Elia-TenneT Pilot projects EU context 8 EU pilot projects in total A B C Nordic BE-NL igcc egcc Terre GCC BE-NL D GCC igcc A. Imbalance Netting

More information

Control Power and Variable Renewables A Glimpse at German Data

Control Power and Variable Renewables A Glimpse at German Data Control Power and Variable Renewables A Glimpse at German Data Lion Hirth* # and Inka Ziegenhagen* * Vattenfall GmbH # Potsdam-Institute for Climate Impact Research University of Leipzig 2013-04-19 Enerday

More information

By Gjert H. Rosenlund, SKM Market Predictor

By Gjert H. Rosenlund, SKM Market Predictor By Gjert H. Rosenlund, SKM Market Predictor Abstract The variability and low predictability of wind speed makes handling of balances a difficult task for wind power producers. With increased investments

More information

Challenges and opportunities decentralised flex ISGAN Public workshop. Bob Hebb, Head Ancillary Services September 12th, 2017

Challenges and opportunities decentralised flex ISGAN Public workshop. Bob Hebb, Head Ancillary Services September 12th, 2017 Challenges and opportunities decentralised flex ISGAN Public workshop Bob Hebb, Head Ancillary Services September 12th, 2017 Elia Group, a unique positioning at the heart of Europe Scandinavia Denmark

More information

TRANSITION OF THE DANISH POWER SYSTEM

TRANSITION OF THE DANISH POWER SYSTEM TRANSITION OF THE DANISH POWER SYSTEM -from fossil fuels to large scale wind power International Wind & Solar Workshop October 2018 Stockholm, Sweden Peter Børre Eriksen, Chief Engineer, Energinet 1 ENERGINET

More information

THE ROLE OF DEMAND SIDE MANAGEMENT IN SCANDINAVIA AND THE BALTICS

THE ROLE OF DEMAND SIDE MANAGEMENT IN SCANDINAVIA AND THE BALTICS European Grid Service Markets Symposium 6 th July 2017 Lucerne, Switzerland 10.07.2017 THE ROLE OF DEMAND SIDE MANAGEMENT IN SCANDINAVIA AND THE BALTICS Thomas Elgaard Jensen, Director, Strategic Market

More information

Pilot Projects overview. 2 nd Stakeholders meeting September.11th.2014, Brussels

Pilot Projects overview. 2 nd Stakeholders meeting September.11th.2014, Brussels Pilot Projects overview 2 nd Stakeholders meeting September.11th.2014, Brussels Balancing Pilot Projects (processes) A B C D A. Imbalance Netting (IN) B. Replacement Reserve (RR) C. Manual Frequency Restoration

More information

Energy balances 2011 Power balances 2011/2012

Energy balances 2011 Power balances 2011/2012 Energy balances 2011 Power balances 2011/2012 May 2008 1 CONTENTS Summary and Conclusions 3-4 Forecast 5-11 Energy balances 12-19 Power balances 20-24 Security of Supply 25-33 Appendices 34-42 1. Energy

More information

Nordic Power System. Challenges and Opportunities for the Nordic Power System

Nordic Power System. Challenges and Opportunities for the Nordic Power System Challenges and Opportunities for the Nordic Power System This report summarises the shared view of the four Nordic Transmission System Operators (TSOs) Svenska kraftnät, Statnett, Fingrid and Energinet.dk,

More information

ENTSO-E Cross Border Electricity Balancing

ENTSO-E Cross Border Electricity Balancing ENTSO-E Cross Border Electricity Balancing Pilot Projects Month Report on Pilot Project 5 Peter Markussen Energinet.dk 5 June 05 ENTSO-E AISBL Avenue de Cortenbergh 00 000 Brussels Belgium Tel + 7 09 50

More information

FEASIBILITY STUDY REGARDING COOPERATION BETWEEN THE NORDIC AND THE BALTIC POWER SYSTEMS WITHIN THE NORDIC ENTSO-E PILOT PROJECT ON ELECTRICITY

FEASIBILITY STUDY REGARDING COOPERATION BETWEEN THE NORDIC AND THE BALTIC POWER SYSTEMS WITHIN THE NORDIC ENTSO-E PILOT PROJECT ON ELECTRICITY FEASIBILITY STUDY REGARDING COOPERATION BETWEEN THE NORDIC AND THE BALTIC POWER SYSTEMS WITHIN THE NORDIC ENTSO-E PILOT PROJECT ON ELECTRICITY BALANCING 1 This feasibility study regarding cooperation between

More information

The catalog is updated at least when new data is published in the Energi Data Service, and consists of the following two parts:

The catalog is updated at least when new data is published in the Energi Data Service, and consists of the following two parts: This data catalog provides a comprehensive overview of the data and datasets in Energi Data Service. The data catalog is based entirely on metadata, and is aimed at all present and potential users of Energi

More information

Power System & Markets introduction

Power System & Markets introduction Power System & Markets introduction Lars Henrik Hansen DONG Energy Smart & Cool project Skærbæk, January 18 th, 2012 Outline Current power markets in DK VPP market integration BRP Price signal market integration

More information

Balancing New Renewables in Europe - Norwegian Contributions and Research Challenges

Balancing New Renewables in Europe - Norwegian Contributions and Research Challenges Balancing New Renewables in Europe - Norwegian Contributions and Research Challenges Birger Mo SINTEF Energy Research 1 Content Overview of balancing options and in particular Norwegian hydro power Research

More information

Further research (Part II)

Further research (Part II) Further research (Part II) Ingeborg Graabak and Daniel H. Hernando, SINTEF ingeborg.graabak@sintef.no daniel.h.hernando@sintef.no www.sintef.no/energy SINTEF Energy Research Outline Background Existing

More information

The Green Transition of the Danish energy system

The Green Transition of the Danish energy system The Green Transition of the Danish energy system Brazilian Delegation - Smart Grid Tour Visit to Energinet.dk 24 November 2014 Peter Jørgensen, Vice President 2014.10.20 The Green Transition of the Danish

More information

4 August 2011 JSS-MIC/BTV. Energinet.dk s ancillary services strategy. Doc. No /11 v1, Case No. 10/5553 1/33

4 August 2011 JSS-MIC/BTV. Energinet.dk s ancillary services strategy. Doc. No /11 v1, Case No. 10/5553 1/33 4 August 2011 JSS-MIC/BTV Energinet.dk s ancillary services strategy Doc. No. 77566/11 v1, Case No. 10/5553 1/33 Contents 1. Introduction and summary...3 2. Framework conditions...4 2.1 Legislation...

More information

Explanatory Note on the ELIA LFC Block Operational Agreement Disclaimer

Explanatory Note on the ELIA LFC Block Operational Agreement Disclaimer Explanatory Note on the ELIA LFC Block Operational Agreement Disclaimer This document, provided by ELIA, is the explanatory note for the draft for stakeholder consultation of the ELIA proposal for the

More information

Large scale balancing and storage from Norwegian hydropower

Large scale balancing and storage from Norwegian hydropower Large scale balancing and storage from Norwegian hydropower ETIP-SNET Northern Region workshop 3-4 October, Otaniemi, Finland Coordinator Michael M. Belsnes with help from the project group Norwegian hydropower

More information

Integration of Renewable Energy Sources in the Electricity System - Grid Issues -

Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Brussels, 30 March 2005 Background At European and national level mid-term plans exist to increase the share of electricity

More information

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019,

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019, Flexibility in the Swiss Electricity Markets Jan Abrell Energieforschungsgespräche Disentis 2019, 24.01.2019 Motivation Share of renewable energy sources in electricity supply is increasing Wind and solar

More information

Capacity Calculation. Tom Tellefsen, Statnett 25.October 2018

Capacity Calculation. Tom Tellefsen, Statnett 25.October 2018 Capacity Calculation Tom Tellefsen, Statnett 25.October 2018 Capacity calculation 1. Provide the market with as high market capacities as possible, given the constraints in the grid. N-1 principle No planned

More information

Design options of TERRE Project. (Trans European Replacement Reserves Exchange) Executive Summary

Design options of TERRE Project. (Trans European Replacement Reserves Exchange) Executive Summary Design options of TERRE Project (Trans European Replacement Reserves Exchange) Executive Summary 15 th of June 2016 Executive Summary TERRE (Trans European Replacement Reserve Exchange) is the pilot project

More information

Opportunity-cost-pricing of reserves for a simple hydropower system

Opportunity-cost-pricing of reserves for a simple hydropower system Opportunity-cost-pricing of reserves for a simple hydropower system Ellen Krohn Aasgård Department of Industrial Economics and Technology Management Norwegian University of Science and Technology Trondheim,

More information

Impact of large scale wind integration on power system balancing

Impact of large scale wind integration on power system balancing 1 Impact of large scale wind integration on power system balancing S. Jaehnert*, Student Member IEEE, T. Aigner*, Student Member IEEE, G. Doorman, IEEE Senior Member and T. Gjengedal, IEEE Senior Member

More information

Load-Frequency Control and Reserves Network Code. David Bunney JESG 15 January 2013

Load-Frequency Control and Reserves Network Code. David Bunney JESG 15 January 2013 Load-Frequency Control and Reserves Network Code David Bunney JESG 15 January 2013 Agenda Overview and Timescales Key Requirements of the Network Code Key Issues Stakeholder Engagement 2 Overview One of

More information

Market-based redispatch in the Netherlands

Market-based redispatch in the Netherlands Market-based redispatch in the Netherlands Strommarkttreffen, 09.02.2018, Berlin Gebotszonen und Engpassmanagement February-8-2018 Samuel Glismann The content of this presentation does not necessarily

More information

NORDIC EDIEL GROUP NORDIC CODE LIST LIBRARY

NORDIC EDIEL GROUP NORDIC CODE LIST LIBRARY NORDIC EDIEL GROUP NORDIC CODE LIST LIBRARY Version: Version 1.5.B Date: January 11 th, 2019 CONTENT 1 INTRODUCTION... 3 1.1 NTC... 3 1.2 REFERENCES... 3 1.3 CHANGE LOG... ERROR! BOOKMARK NOT DEFINED.

More information

REPORT NORDIC POWER MARKET DESIGN AND THERMAL POWER PLANT FLEXIBILITY

REPORT NORDIC POWER MARKET DESIGN AND THERMAL POWER PLANT FLEXIBILITY REPORT NORDIC POWER MARKET DESIGN AND THERMAL POWER PLANT FLEXIBILITY Nordic power market design and thermal power plant flexibility 2/31 TABLE OF CONTENTS 1. The Danish experience on high VRE integration...

More information

Nordic synchronous area Proposal for limits for the exchange of FCR between the TSOs in accordance with Article 163(2) of the Commission Regulation

Nordic synchronous area Proposal for limits for the exchange of FCR between the TSOs in accordance with Article 163(2) of the Commission Regulation of FCR between the TSOs in accordance with Article 163(2) of the Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation 10 September

More information

Paid-as-cleared for R2 & R3 activated energy

Paid-as-cleared for R2 & R3 activated energy Paid-as-cleared for R2 & R3 activated energy STUDY under consultation (period of consultation 20/10/17 17/11/17) Working Group Balancing 08/11/2017 10:00-12:00 Agenda Scope study Basic theory Context study

More information

Evaluation of the ramping restriction in the energy market. Nordic Operations Development group (NOD)

Evaluation of the ramping restriction in the energy market. Nordic Operations Development group (NOD) Evaluation of the ramping restriction in the energy market Nordic Operations Development group (NOD) 20 December 2010 Table of contents: 1 Summary... 3 2 Introduction... 3 3 Ramping rules... 4 4 Socioeconomic

More information

Proposal from all TSOs of the Nordic synchronous area for the determination of LFC blocks within the Nordic Synchronous Area in accordance with

Proposal from all TSOs of the Nordic synchronous area for the determination of LFC blocks within the Nordic Synchronous Area in accordance with Proposal from all TSOs of the Nordic synchronous area for the determination of LFC blocks within the Nordic Synchronous Area in accordance with Article 141(2) of the Commission Regulation (EU) 2017/1485

More information

HIGHER TIME RESOLUTION: INFORMATION TO STAKEHOLDERS

HIGHER TIME RESOLUTION: INFORMATION TO STAKEHOLDERS HIGHER TIME RESOLUTION: INFORMATION TO STAKEHOLDERS Content 1. Introduction... 2 2. Cost Benefit Analysis... 3 3. Regulatory framework... 3 4. Implementation in the Nordics... 3 4.1 Trading options...

More information

CIGRE Working Group (WG) C4.603: Analytical techniques and tools for power balancing assessments

CIGRE Working Group (WG) C4.603: Analytical techniques and tools for power balancing assessments CIGRE Working Group (WG) C4.603: Analytical techniques and tools for power balancing assessments Main objective: Critical assessment of existing modelling methods and tools for analyzing power balancing

More information

Whereas. (2) This Proposal takes into account the general principles, goals and other methodologies set in EBGL.

Whereas. (2) This Proposal takes into account the general principles, goals and other methodologies set in EBGL. TSOs proposal for the establishment of common and harmonised rules and processes for the exchange and procurement of Balancing Capacity for Frequency Containment Reserves (FCR) in accordance with Article

More information

D2.2 Implementation Status and Market Focused Diagnosis of the Target Model

D2.2 Implementation Status and Market Focused Diagnosis of the Target Model D2.2 Implementation Status and Market Focused Diagnosis of the Target Model Luis Olmos, Pablo Rodilla, Camila Fernandes, Pablo Frias, Ove Wolfgang, Ricardo Loureiro, Bruno Caetano, Bettina Burgholzer,

More information

Timing of Markets- the Key Variable in Design of Ancillary Service Markets for Power Reserves

Timing of Markets- the Key Variable in Design of Ancillary Service Markets for Power Reserves Timing of Markets- the Key Variable in Design of Ancillary Service Markets for Power Reserves Alireza Abbasy 1, Reinier A. C. van der Veen, Rudi A. Hakvoort Faculty of Technology, Policy and Management,

More information

Frequency Quality in the Nordic Power System: Wind Variability, Hydro Power Pump Storage and Usage of HVDC Links

Frequency Quality in the Nordic Power System: Wind Variability, Hydro Power Pump Storage and Usage of HVDC Links Available online at www.sciencedirect.com ScienceDirect Energy Procedia 35 (213 ) 62 68 DeepWind'213, 24-25 January, Trondheim, Norway Frequency Quality in the Nordic Power System: Wind Variability, Hydro

More information

IMPACT OF INCREASED AMOUNTS OF RENEWABLE ENERGY ON NORDIC POWER SYSTEM OPERATION

IMPACT OF INCREASED AMOUNTS OF RENEWABLE ENERGY ON NORDIC POWER SYSTEM OPERATION IMPACT OF INCREASED AMOUNTS OF RENEWABLE ENERGY ON NORDIC POWER SYSTEM OPERATION 31.08.2010 Summary The Electricity Market Group, which is a working group for the Nordic Council of Ministers responsible

More information

Short-term Electricity Markets and Imbalance Settlement. What is Demand Side Management (DSM) Valuing Flexibility for DSM

Short-term Electricity Markets and Imbalance Settlement. What is Demand Side Management (DSM) Valuing Flexibility for DSM Short-term Electricity Markets and Imbalance Settlement What is Demand Side Management (DSM) Valuing Flexibility for DSM 2 EU Unbundling has created 4 different roles: Electricity Producer (competition

More information

PRINCIPLES FOR DETERMINING THE TRANSFER CAPACITIES IN THE NORDIC POWER MARKET

PRINCIPLES FOR DETERMINING THE TRANSFER CAPACITIES IN THE NORDIC POWER MARKET PRINCIPLES FOR DETERMINING THE TRANSFER CAPACITIES IN THE NORDIC POWER MARKET 30.11.2017 Revision Date Summary of updates 3. Final 2010-06-22 New version 4. Final 2011-02-18 Text about Estlink updated.

More information

NORDIC EDIEL GROUP NORDIC CODE LIST LIBRARY

NORDIC EDIEL GROUP NORDIC CODE LIST LIBRARY NORDIC EDIEL GROUP NORDIC CODE LIST LIBRARY Version: Version 1.4.A Date: April 19 th, 2017 CONTENT 1 INTRODUCTION... 3 1.1 NTC... 3 1.2 REFERENCES... 4 1.3 CHANGE LOG... 4 2 NORDIC EXTENSIONS TO ENTSO-E

More information

System operations and market development plan Executive summary

System operations and market development plan Executive summary System operations and market development plan 2017-2021 Executive summary Her må Statnett fylle på med bildetekster. Her må Statnett fylle på med bildetekst. Preface The power system is a crucial infrastructure

More information

Full Activation Time (FAT) and Deactivation

Full Activation Time (FAT) and Deactivation DRAFT: Chapter 4.1.1. Full Activation Time of the Explanatory Document to All TSOs proposal for the implementation framework for a European platform for the exchange of balancing energy from frequency

More information

Economic solutions to improve frequency quality

Economic solutions to improve frequency quality Norwegian School of Economics Bergen, Spring 2013 Economic solutions to improve frequency quality A discussion of Statnetts challenges in the power system Fredrik Vigeland Christoffersen Supervisor: Linda

More information

Project: Increased Utilisation of the Nordic Power Transmission System

Project: Increased Utilisation of the Nordic Power Transmission System Workshop: Project: Increased Utilisation of the Nordic Power Transmission System The main aim of the workshop is to establish a meeting place for all project participants to present preliminary results

More information

Long-term Market Analysis Nordics and Europe Executive summary

Long-term Market Analysis Nordics and Europe Executive summary Long-term Market Analysis Nordics and Europe 2018 2040 Executive summary 1 December 2018 Europe is set to develop a low carbon power system with significant contribution from renewable energy sources.

More information

Determining the optimal use of wind power in the balancing markets

Determining the optimal use of wind power in the balancing markets Determining the optimal use of wind power in the balancing markets Amsterdam 17 October 2013 Henning Parbo Chief Economist Market Development Energinet.dk 1 Agenda Briefly about Energinet.dk Wind Power

More information

The influence of existing bidding zones on electricity markets

The influence of existing bidding zones on electricity markets Your reference Our reference Date 30.09.2013 Agency for the cooperation of energy regulators consultation2013e04@acer.europa.eu The influence of existing bidding zones on electricity markets Energy Norway

More information

Need for Flex & Capacity

Need for Flex & Capacity Need for Flex & Capacity Flux50 Energy transition: next steps? Brussels May, 25 th 2018 David Zenner, Head of customer Relations Part I: Need for Flex Major trends impacting the power system The development

More information

Balancing Challenges for Future North Sea Offshore Network

Balancing Challenges for Future North Sea Offshore Network Downloaded from orbit.dtu.dk on: Jan 23, 2019 Balancing Challenges for Future North Sea Offshore Network Das, Kaushik; Koivisto, Matti Juhani; Sørensen, Poul Ejnar; Gea-Bermudez, Juan Published in: Proceedings

More information

15 January FCR Cooperation Draft Proposal

15 January FCR Cooperation Draft Proposal Proposal for the establishment of common and harmonised rules and processes for the exchange and procurement of Frequency Containment Reserve (FCR) in accordance with Art. 33 of COMMISSION REGULATION (EU)

More information

Swedenergy on Thema's report 'Capacity adequacy in the Nordic Electricity märket'

Swedenergy on Thema's report 'Capacity adequacy in the Nordic Electricity märket' SVENSK ENERGI - SWEDENERGY - AB Marknad/Märkets Magnus Thorstensson +46-8-677 2806, +46-733 925761 magnus.thorstensson@svenskenergi.se YTTRANDE 1 (5) Datum 2015-08-17 NR 041/2015 Elmarknadsgruppen Nordiska

More information

Unlocking Investment in a changing Power Sector. Anne Malorie Géron Vice-President European Affairs Third EFORIS event, Stockholm, 23 November 2017

Unlocking Investment in a changing Power Sector. Anne Malorie Géron Vice-President European Affairs Third EFORIS event, Stockholm, 23 November 2017 Unlocking Investment in a changing Power Sector Anne Malorie Géron Vice-President European Affairs Third EFORIS event, Stockholm, 23 November 2017 Solar more competitive in sunbelt, wind in North in retail,

More information

Neas Energy A/S. Electrolysis for grid balancing - BioCat European Power-to-Gas Platform: Second meeting Square Hotel, Copenhagen, 22 June 2016

Neas Energy A/S. Electrolysis for grid balancing - BioCat European Power-to-Gas Platform: Second meeting Square Hotel, Copenhagen, 22 June 2016 Neas Energy A/S Electrolysis for grid balancing - BioCat European Power-to-Gas Platform: Second meeting Square Hotel, Copenhagen, 22 June 2016 Agenda Neas Energy Electricity markets Trading strategy and

More information

Explanatory note for the FCR dimensioning rules proposal

Explanatory note for the FCR dimensioning rules proposal Explanatory note for the FCR dimensioning rules proposal 08.08.2018 Explanatory note for the FCR dimensioning rules proposal Explanatory note An appropriate amount of FCR available in the synchronous area

More information

HANDLING OF FLUCTUATING WIND PRODUCTION ON THE EL SPOT MARKET,

HANDLING OF FLUCTUATING WIND PRODUCTION ON THE EL SPOT MARKET, HANDLING OF FLUCTUATING WIND PRODUCTION ON THE EL SPOT MARKET, A CASE STORY FROM A PBA. CREATING MORE VALUE IN WIND EWEA2012 PRE-CONFERENCE SEMINAR BY THE DANISH WIND INDUSTRY ASSOCIATION APRIL 15 TH,

More information

Harmonisation of Imbalance Settlement proposals

Harmonisation of Imbalance Settlement proposals Public Harmonisation of Imbalance Settlement proposals Industry Workshop 22 August 2018 Welcome Steve Wilkin, ELEXON Health & Safety 3 Who we are Steve Wilkin George Daniel Peter Frampton ELEXON National

More information

C1-201 ASSESSMENT OF SYSTEM ADEQUACY: A NEW MONITORING TOOL

C1-201 ASSESSMENT OF SYSTEM ADEQUACY: A NEW MONITORING TOOL 21, rue d'artois, F-8 Paris http://www.cigre.org C1-201 Session 2004 CIGRÉ ASSESSMENT OF SYSTEM ADEQUACY: A NEW MONITORING TOOL René J.L. Beune 1 (*), Frank A. Nobel (*), Gerard L. Doorman (**) (*) TenneT

More information

Capacity calculation methodology within the Baltic Capacity Calculation Region

Capacity calculation methodology within the Baltic Capacity Calculation Region Capacity calculation methodology within the Baltic Capacity Calculation Region Among: AS Augstsprieguma tīkls Elering AS LITGRID AB PSE S.A. Svenska kraftnät Fingrid Oyj.. 2017 Vilnius, Riga, Tallinn,

More information

Analysis of Integrated Balancing Markets in Northern Europe under Different Market Design Options

Analysis of Integrated Balancing Markets in Northern Europe under Different Market Design Options Yonas Tesfay Gebrekiros Doctoral thesis Doctoral theses at NTNU, 2015:311 Doctoral theses at NTNU, 2015:311 NTNU Norwegian University of Science and Technology Thesis for the degree of Philosophiae Doctor

More information

Explanatory document to the proposal for the coordinated redispatching and countertrading methodology for Capacity Calculation Region Hansa in

Explanatory document to the proposal for the coordinated redispatching and countertrading methodology for Capacity Calculation Region Hansa in Explanatory document to the proposal for the coordinated redispatching and countertrading methodology for Capacity Calculation Region Hansa in accordance with Article 35 of the Commission Regulation (EU)

More information

Capacity reserves until 2025: declining, but sufficient

Capacity reserves until 2025: declining, but sufficient 1 Capacity reserves until 2025: declining, but sufficient Trends from ENTSO-E s Scenario Outlook & Adequacy Forecast 2015 Once a year, ENTSO-E 1 publishes a Scenario Outlook & Adequacy Forecast (SO&AF).

More information

Integrated modelling of the future energy system results and challenges

Integrated modelling of the future energy system results and challenges Integrated modelling of the future energy system results and challenges Magnus Korpås, Michael Belsnes, Ingeborg Graabak SINTEF Energi AS magnus.korpas@sintef.no Technology for a better society 1 Contents

More information

Proposal for standard products - draft - Working Group Ancillary Services

Proposal for standard products - draft - Working Group Ancillary Services Proposal for standard products - draft - Working Group Ancillary Services 1. ABSTRACT Operating power systems, including performing balancing at the lowest cost and the best security of supply level is

More information

PÖYRY S VIEW ON MAIN ISSUES FOR PHASE II OF THE REVIEW OF THE SEM HLD 14 October 2013 Gary Keane

PÖYRY S VIEW ON MAIN ISSUES FOR PHASE II OF THE REVIEW OF THE SEM HLD 14 October 2013 Gary Keane PÖYRY S VIEW ON MAIN ISSUES FOR PHASE II OF THE REVIEW OF THE SEM HLD 14 October 2013 Gary Keane The wider policy context for the Market Integration project is complicated and continues to change We have

More information

Balancing modern Power System with large scale of wind power

Balancing modern Power System with large scale of wind power Downloaded from orbit.dtu.dk on: Aug 17, 2018 Balancing modern Power System with large scale of wind power Basit, Abdul; Altin, Müfit; Hansen, Anca Daniela; Sørensen, Poul Ejnar Published in: Proceedings

More information

Reservation of cross-zonal capacity for balancing services

Reservation of cross-zonal capacity for balancing services Public ISBN nr. 978-82-93150-62-6 Reservation of cross-zonal capacity for balancing services Commissioned by the Norwegian Water Resources and Energy Directorate December, 2014 THEMA Report 2014-32 About

More information

The economic welfare impacts of reserving interconnector capacity for trade in balancing products

The economic welfare impacts of reserving interconnector capacity for trade in balancing products The economic welfare impacts of reserving interconnector capacity for trade in balancing products A REPORT PREPARED FOR EBL September 2009 Frontier Economics Ltd, London. Confidential September 2009 Frontier

More information

Nordic power markets. Timo Karttinen. Senior Vice President Fortum Corporation

Nordic power markets. Timo Karttinen. Senior Vice President Fortum Corporation Nordic power markets Timo Karttinen Senior Vice President Fortum Corporation Capital Markets Day Helsinki, 30 October 2008 Disclaimer This presentation does not constitute an invitation to underwrite,

More information

Modelling Transitions to Robust High-VRE Systems

Modelling Transitions to Robust High-VRE Systems Modelling Transitions to Robust High-VRE Systems Colin Silvester, Christopher Bates and Arjun Chohan Digital Engineering Solutions Uniper Nottingham, UK Colin.Silvester@uniper.energy Abstract Uniper is

More information

Session 2: Grids: the gateway to power

Session 2: Grids: the gateway to power Session 2: Grids: the gateway to power the TWENTIES project will discuss examples of best practice and Provide their perspectives on future energy systems Latvian Association of Wind Energy (LAWE) 1 Demo

More information

Response 1 (5) Public

Response 1 (5) Public Response 1 (5) ACER, Agency for the Cooperation of Energy Regulators consultation2013e04@acer.europa.eu The influence of existing bidding zones on electricity markets FORTUM'S RESPONSE TO PUBLIC CONSULTATION

More information

Energy Norway response to the ERGEG consultation on the Framework guidelines on Capacity Calculation and Congestion Management for Electricity

Energy Norway response to the ERGEG consultation on the Framework guidelines on Capacity Calculation and Congestion Management for Electricity Your reference Our reference Date DM-308213 9 November 2010 ERGEG 28 rue le Titien 1000 Brussels Energy Norway response to the ERGEG consultation on the Framework guidelines on Capacity Calculation and

More information

The case for building out the North Sea grid a business perspective. Anders Stouge, Deputy Director General

The case for building out the North Sea grid a business perspective. Anders Stouge, Deputy Director General The case for building out the North Sea grid a business perspective Anders Stouge, Deputy Director General About SeaStarAlliance - Industrial collaboration on cost-reduction A pan-european offshore wind

More information

TradeWind Favourable distribution Reinforcing interconnections

TradeWind Favourable distribution Reinforcing interconnections TradeWind Europe s dependency on imported fossil fuel has become a threat to economic stability, and enhances energy price development uncertainties. Simultaneously, European utilities face huge challenges

More information

NORWEGIAN ENERGY SOURCING STRATEGY

NORWEGIAN ENERGY SOURCING STRATEGY NORWEGIAN ENERGY SOURCING STRATEGY JWPA, Tokyo 27.10.2009 Leon Eliassen Notkevich, Statkraft Wind Power Prof. Terje Gjengedal, Statnett/NTNU THIS PRESENTATION Statkraft today Dynamic power system Market

More information

The power market. How the power market functions Power trading Price formation International power trading Electricity output un the Nordic countries

The power market. How the power market functions Power trading Price formation International power trading Electricity output un the Nordic countries The power market How the power market functions Power trading Price formation International power trading Electricity output un the Nordic countries 7 82 The power supply sector in Norway is regulated

More information

Analyses on the effects of implementing implicit grid losses in the Nordic CCR

Analyses on the effects of implementing implicit grid losses in the Nordic CCR Analyses on the effects of implementing implicit grid losses in the Nordic CCR Publication date, 30 April 2018 Executive summary The purpose of this study is to analyze the effects of implementing implicit

More information

I-SEM Testing Tariff High Level Options Consultation

I-SEM Testing Tariff High Level Options Consultation I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on

More information

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: 1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call

More information

Guidelines for implementation of transitional peak load arrangements. Proposal of Nordel

Guidelines for implementation of transitional peak load arrangements. Proposal of Nordel Guidelines for implementation of transitional peak load arrangements Proposal of Nordel February 2007 Updated March 2009 2(8) Nordel s Guidelines for implementation of transitional peak load arrangements

More information

NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2015

NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2015 NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2015 16.01.2017 REGIONAL GROUP NORDIC Table of Contents 1 SUMMARY... 3 2 INTRODUCTION AND BACKGROUND... 4 3 SCOPE... 5 CONTACT PERSONS...

More information

INITIAL FINDINGS REPORT

INITIAL FINDINGS REPORT Transmission System Operators for Electricity INITIAL FINDINGS REPORT DETERMINISTIC FREQUENCY DEVIATIONS 2 ND STAGE IMPACT ANALYSIS VERSION 03.12.12 AHT DETERMINISTIC FREQUENCY DEVIATIONS TABLE OF CONTENTS

More information

D6.1.2 Report on the Roadmap for RES penetration under the current Target Model high-level principles ( )

D6.1.2 Report on the Roadmap for RES penetration under the current Target Model high-level principles ( ) D6.1.2 Report on the Roadmap for RES penetration under the current Target Model high-level principles (2014-2020) Part 2: recommendations about other short term market topics Sophie Dourlens-Quaranta,

More information

Counter activations in PICASSO. Overview of the options and their implications

Counter activations in PICASSO. Overview of the options and their implications Counter activations in PICASSO Overview of the options and their implications Contents 1 Introduction... 3 2 Options... 3 2.1 Option 1: No limitation of counter Activation... 4 2.2 Option 2: Complete avoidance

More information

Nordic Power System. Challenges and Opportunities for the Nordic Power System

Nordic Power System. Challenges and Opportunities for the Nordic Power System Challenges and Opportunities for the Nordic Power System Executive summary This report summarises the shared view of the four Nordic Transmission System Operators (TSOs) Svenska kraftnät, Statnett, Fingrid

More information