DECISION MEMO Divide Creek Barrier Enhancement
|
|
- Nancy Allen
- 6 years ago
- Views:
Transcription
1 Page 1 of 7 Background DECISION MEMO USDA Forest Service Butte Ranger District Silver Bow County, Montana T. 2 N., R. 9 W., Section 32 The North Fork of Divide Creek is approximately 4 miles west of the Fleecer Exit on I-15 in the Upper Clark Fork Landscape in the Northeast Fleecer Management Area. It is a tributary to the Big Hole River north of Divide, MT and the upper reaches harbor a non-hybridized population of westslope cutthroat trout (WCT). Decision I have decided to approve the Divide Creek barrier enhancement project. We will raise the height of the existing natural falls pictured below so the drop is increased to about 5 feet. This site is located in the S ½ S ½, Section 32, T2N, R9W, in Silver Bow County at a narrow, confined reach of the North Fork of Divide Creek. The work will be completed in 1-2 days using an excavator to move onsite material to enhance a natural partial barrier by increasing the height of the falls so they drop approximately 5 feet. In addition, we will minimize the jump pool below the falls making it even more difficult for brook trout to jump over the falls. We will use rocks and natural material adjacent to the site to accomplish the enhancement. The footprint of disturbance will extend approximately 100 feet above the barrier site and 200 feet below the barrier site and utilize rocks and natural material adjacent to the site. Some clearing may be needed to get an excavator from the road to the site as there are thick willows along the stream. Approach distances will be limited to the closest available location that is within 200 feet downstream of the barrier location. To determine effectiveness, biologists will capture brook trout upstream of the structure, permanently mark the fish by removing their adipose fin, and transport them downstream below the structure. Subsequent electrofishing upstream from the structure over a period of one to two years will reveal whether the structure successfully precludes fish passage.
2 Page 2 of 7 Figure 1. Enhancement project site on North Fork of Divide Creek with 5-gallon bucket for scale. Mitigation and Design Features Required by This Decision: Heritage Resources: If cultural resource sites or artifacts are discovered during project implementation, work will stop and the Forest Archeologist will be notified immediately. Recreation: Public notice should be placed in local newspapers and other appropriate media to inform recreation users of the project and activities. Signs should be placed on roads and trails entering the project area to notify users of activities or potential hazards and to post any necessary instructions. Hydrology: All applicable permits will be obtained prior to instream work. Contract will be administered by Montana FWP with support from BDNF aquatics, engineering, and hydrology. A hydrologist or aquatics representative will be on site during implementation to ensure impacts to water quality are limited. Noxious Weeds: Noxious weeds will be controlled following procedures in the Noxious Weed Control Program ROD (2002) for the. Range: The permittee will be notified by phone call prior to implementation.
3 Reasons for Categorically Excluding the Proposed Action Page 3 of 7 An action may be categorically excluded from further analysis and documentation in an environmental impact statement (EIS) or environmental assessment (EA) if it is within one of the categories identified by the USDA in 7 CFR part 1b.3 or 7 CFR part 1b.3 or 36 CFR 220.6(d) or (e), and there are no extraordinary circumstances related to the decision that may result in a significant individual or cumulative effect on the quality of the human environment. This project has been reviewed in accordance with FSH Chapter 30. I have determined the project fits the following category: 36 CFR 220.6(e)(7): Modification or maintenance of stream or lake aquatic habitat improvement structures using native materials or normal practices. My decision is based on a review of the project record that shows a thorough review of relevant scientific information, a consideration of responsible opposing views, and the acknowledgement of incomplete or unavailable information. The record includes the following resource specialist reports: Biological Assessments and Evaluations for Aquatic Species, Botany, and Wildlife Heritage Report Soils Report Hydrology Report Recreation Report Scenery Report By definition, categorical exclusions do not individually or cumulatively have significant effects on the human environment (40 CFR ). Resource specialists considered direct and indirect effects from the proposed action coupled with past, present, and reasonably foreseeable actions. I have examined the proposed action and the effects analyses disclosed in the resource specialist reports listed above and have concluded that without notable individual effects from the proposed action, there would be no discernible cumulative effects. The interdisciplinary team reviewed the resource conditions listed in FSH Chapter 30 (31.2) and other concerns applicable to this project to determine whether any extraordinary circumstances exist. The mere presence of one or more of the resource conditions listed below does not preclude the use of a categorical exclusion. It is the existence of a cause-effect relationship between a proposed action and the potential effect on these resource conditions and if such a relationship exists, the degree of potential effect of a proposed action on these resource conditions that determine whether extraordinary circumstances exist. The resource specialist reports have provided the necessary information to make a determination on the cause-effect relationship between the proposed action and the potential effect on the resource conditions listed below and thus the presence of extraordinary circumstances, as summarized below:
4 Page 4 of 7 RESOURCE CONDITION Federally listed threatened or endangered species or designated critical habitat, species proposed for Federal listing or proposed critical habitat, or Forest Service sensitive species. Floodplains, wetlands, or municipal watersheds Congressionally designated areas, such as wilderness, wilderness study areas, or national recreation areas. Inventoried Roadless Areas Research Natural Areas American Indians and Alaska Native religious or cultural sites. Archaeological sites, or historic properties or areas. POTENTIAL EFFECT Threatened or Endangered Species: There would be no effect to the threatened grizzly bear. Sensitive Wildlife Species: Activities may impact individual Townsend's big eared or spotted bats but will not likely contribute to a trend towards federal listing or loss of viability to the population or species. Sensitive Plant Species: No impacts to sensitive plants will occur. Sensitive Aquatic Species: Activities may impact westslope cutthroat trout in the short term, but will not likely contribute to a trend towards federal listing or loss of viability to the population or species. The project is expected to result in long-term benefit to westslope cutthroat trout. The project does not occur within a municipal watershed. This project will occur entirely in the RCA on the North Fork of Divide Creek. Short-term negative impacts to water quality are localized and limited to the immediate area of development. Although there will be short-term impacts to water quality, the long-term benefits to aquatic habitat will far outweigh those impacts and the overall effect of this project will be beneficial to the watershed. A hydrologist or aquatics representative will be on site during implementation to ensure impacts to water quality are limited. No congressionally designated areas occur in or near the project; therefore no negative impacts to any congressionally designated areas are projected. There are no inventoried roadless areas within or adjacent to the project area. Therefore, no negative impacts to inventoried roadless areas are projected. There are no research natural areas within the project area. Therefore, no negative impacts to research natural areas are projected. Potential adverse impacts to religious, cultural, or archaeological sites, or historic properties or areas are not anticipated. A categorical exclusion is appropriate in this situation because the proposed actions fit within the category described above and there are no extraordinary circumstances present. Scoping and Public Involvement A scoping letter went out to 66 individuals, agencies, and tribes on December 19, The project was also posted on the schedule of proposed actions on the same day. No responses were received. The project was made available for a 30-day public comment period; the legal notice of the proposed action and 30-day comment period was published in the newspaper of record, The Montana Standard on May 6, The 30-day notice and comment letter was posted on the Forest NEPA projects
5 Page 5 of 7 webpage. We received one letter via providing comments on the proposed action, which was submitted after the 30-day comment period. We received the following comments from the livestock grazing permittee in the Divide Creek area. Our ranch is located to the east of the proposed project site. We own water rights on Divide Creek and also are the sole Forest Service Grazing Permittee on this proposed area. We would like to submit the following comments on the Fisheries Enhancement Barrier on the North Fork of Divide Creek project. In the Purpose and Need of the proposal it is stated that the fish barrier would be the first step toward removing non-native Brook Trout to allow native Westslope Cutthroat to re-establish there. Future projects.. We would like to be kept apprised of any future proposed projects dealing with Divide Creek. In the Scoping period starting on December 19, 2011, we felt that we should have been included as one of the 66 individuals allowed to participate in that part of the process. If this Barrier Enhancement is approved, we would also like to be the first (not last) to know when and how the project will be built. It is stated in the proposal that public notice will be placed in the newspaper and other appropriate media. We would appreciate a phone call or a letter to our post office box informing us of the project activities. Our cattle go on the Forest starting July 1 until September 30. There may not be any interference with their grazing or your project but we need to work together to assure that everyone is treated fairly. We will need access to the area to the west of the project at all times. Our water rights allow us and we are dependent on the water to irrigate our pastures and water our livestock. We would not want the barrier enhancement to interfere with stream flow, especially in a drought year. Our cattle do graze in the proposed area but we don t foresee any disturbance to the proposed project. However in the event there was disturbance (like in a drought year and cattle go to water in the project area), we will not be held responsible for any damage or changes to the Barrier Enhancement area. We are okay with the project going forward and thank you for considering our position in relationship to this project. Forest Service Response: The permittee was inadvertently not included on the initial scoping address list; however, we will keep then informed about any future projects within their permitted grazing allotment. This decision memo will be mailed to the permittee. We will work with the permittee as we implement this decision to assure they are kept informed of the progress as we implement the project. We do not anticipate the barrier enhancement will interfere with stream flow or affect the permittees water rights. Should any incidental damage or changes to the barrier enhancement occur from permitted livestock, the permittee will not be held responsible. Forest Plan Direction The National Forest Management Act (NFMA) requires the development of long-range land and resource management plans. The Plan was approved in 2009 and provides guidance for all natural resource management activities on the Beaverhead-Deerlodge National Forest. NFMA also requires that all projects and activities be consistent with the plans. The decision is consistent with Forest Plan direction including all applicable standards.
6 Forest Plan Direction Page 6 of 7 Aquatic Resources Goals: Aquatic Nuisance Species: Introductions of aquatic nuisance species in riparian and aquatic habitats are prevented. Forest biologists work cooperatively with appropriate state and federal agencies, or other stakeholders to reduce or eliminate impacts, where aquatic nuisance species are adversely affecting the viability of desired aquatic species. (FP pg. 14) Findings Required by Law National Forest Management Act - The Land and Resource Management Plan (Forest Plan) was approved in 2009, as required by this Act. The Forest Plan has been reviewed in consideration of this project and the project meets all applicable management direction found in the 2009 Beaverhead-Deerlodge Forest Plan including consistency with all applicable standards. Endangered Species Act - See the Reasons for Categorically Excluding the Proposed Action Section of this document for a summary of the effects of this project to Endangered, Threatened, or Candidate Species. The summary is based on a more thorough analysis available in the project record. This project is consistent with the requirements of the Endangered Species Act. Sensitive Species (Forest Service Manual 2670) - This direction requires analysis of potential impacts to sensitive species and the Regional Forester approved the sensitive species list on October 28, Our review of the potential effects of this decision upon the sensitive species has been completed and the analysis documented in the project file and Resource Condition Table above. Environmental Justice (Executive Order 12898) - This Order requires consideration of whether projects would disproportionately affect minority or low-income populations in or around the project area. Based on internal review and public scoping, the proposed action did not identify any adversely impacted local minority or low-income populations. Clean Water Act The intent of the Act is to restore and maintain the integrity of waters. The Forest Service complies with this Act through the use of Best Management Practices (BMPs). This decision incorporates Best Management Practices to ensure protection of soil and water resources and complies with the Clean Water Act and State water quality standards. Clean Air Act Under this Act, areas of the country were designated as Class I, II or III airsheds for Prevention of Significant Deterioration purposes. There will be no air quality impacts as a result of this decision. The National Historic Preservation Act As discussed earlier in this document and in detail in the project file, impacts to cultural resources are not expected. Migratory Bird Treaty Act There will be no known substantial losses of migratory bird habitat expected from the implementation of this proposal. National Environmental Policy Act - This Act requires public involvement and consideration of potential environmental effects. This document and the project record provide documentation for this decision which supports compliance with this Act. Other Laws or Requirements The proposed action is consistent with all other Federal, State, and/or local laws or requirements.
7 Page 7 of 7 Administrative Review or Appeal Opportunities This decision is not subject to appeal pursuant to 36 CFR 215. Implementation Date Consistent with 36 CFR 215, implementation may begin immediately, and is expected to commence in late summer or early fall of Contact Person Supporting documentation for this decision is available for public review at the Butte Ranger District, 1820 Meadowlark Lane, Butte, MT Further information about the decision can be obtained from Kevin Weinner at the BDNF Supervisors Office in Dillon, MT (406) Responsible Official /s/ Peri R. Suenram June 25, 2012 PERI R. SUENRAM Date Acting District Ranger Butte/Jefferson Ranger Districts The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual s income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDAs TARGET Center at (202) (voice and TDD). To file a complaint of discrimination, write to USDA, Director, Office of Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C , or call (800) (voice) or (202) (TDD). USDA is an equal opportunity provider and employer.
DECISION MEMO. USDA Forest Service. Butte District Silver Bow County T4N, R8W, Section 36
Page 1 of 5 Background DECISION MEMO USDA Forest Service Butte District Silver Bow County T4N, R8W, Section 36 Northwestern Energy operates utility systems and facilities on federal lands under a Master
More informationDECISION MEMO. Crow Creek Hardened Crossing
Page 1 of 5 DECISION MEMO USDA Forest Service Madison Ranger District Madison County T12S, R4W in Section 35 Background A perennial cattle crossing on Crow Creek in in the Gravelly Landscape in the Centennial
More informationDECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing
Page 1 of 6 Background DECISION MEMO USDA Forest Service Madison Ranger District Madison County T12S, R4W, Section 30 The project is in the Gravelly Landscape, Snowcrest Recommended Wilderness Management
More informationDECISION MEMO. East Fork Blacktail Trail Reroute
Page 1 of 6 DECISION MEMO USDA Forest Service Madison Ranger District Madison County Background The East Fork Blacktail Trail #6069 is a mainline trail in the Snowcrest Mountains. The Two Meadows Trail
More informationDECISION MEMO. Vipond Water Development
Page 1 of 5 DECISION MEMO USDA Forest Service Wise River Ranger District Beaverhead County T2S, R10W, Sections 12, 13, 14, &18 Background This project is located in the Pioneer Landscape, East Face Management
More informationDECISION MEMO Eureka Fire Whitebark Pine Planting
Page 1 of 6 DECISION MEMO Eureka Fire Whitebark Pine Planting USDA Forest Service Madison Ranger District Madison County T11S, R2W, Sections16, 17, 18, 19, 20, 29, 30, 31 & 32 T11S, R3W, Sections 25 &
More informationDECISION MEMO Lazyman Repeater Shelter and Tower Replacement
Page 1 of 5 Background DECISION MEMO Lazyman Repeater Shelter and Tower Replacement USDA Forest Service Madison Ranger District Madison County The Lazyman Repeater was installed in 1988 and serves parts
More informationDECISION MEMO Pony Whitebark Pine Planting
Page 1 of 5 DECISION MEMO Pony Whitebark Pine Planting USDA Forest Service Jefferson Ranger District Madison County T2S, R3W, Sections 4 & 9 Background The Pony Fire of 2012 burned 5,157 acres on the (BDNF).
More informationDECISION MEMO SMART CREEK MINERAL EXPLORATION PROJECT
Page 1 of 7 DECISION MEMO SMART CREEK MINERAL EXPLORATION PROJECT Background USDA Forest Service Pintler Ranger District Granite County, Montana T8N, R13W, sections 5, 6 and 7 The Kennecott Exploration
More informationUSDA Forest Service Decision Memo. Mattie V Creek Minesite Rehabilitation Project
USDA Forest Service Decision Memo Mattie V Creek Minesite Rehabilitation Project Ninemile Ranger District Lolo National Forest Mineral County, Montana I. DECISION TO BE IMPLEMENTED A. Decision Description:
More informationDECISION MEMO REBEL CLAIMS EXPLORATION PROJECT
Page 1 of 7 DECISION MEMO REBEL CLAIMS EXPLORATION PROJECT USDA Forest Service Pintler Ranger District Granite County T8N, R15W, section 18 & 19 and T8N, R16W, sections 13 & 24 Background Charles Hinkle
More informationDECISION MEMO ROSS FORK/BITTERROOT DIVIDE TRAILS REHABILITATION AND RELOCATION
Page 1 of 6 BACKGROUND DECISION MEMO ROSS FORK/BITTERROOT DIVIDE TRAILS REHABILITATION AND RELOCATION USDA Forest Service Pintler Ranger District Granite County, Montana The purpose of this project is
More informationDecision Memo. North Fork Calispell Creek Restoration Project
Project Description Decision Memo North Fork Calispell Creek Restoration Project USDA Forest Service Newport-Sullivan Lake Ranger Districts Colville National Forest Pend Oreille County, Washington Surveys
More informationDECISION MEMO. Griz Thin (Stand )
Background DECISION MEMO Griz Thin (Stand 507089) USDA Forest Service Siuslaw National Forest Central Coast Ranger District Lane County, Oregon Township 16 South, Range 10 West, Sections 6 and 7 The Cummins-Tenmile
More informationDraft Decision Memo Santiam Junction Maintenance Station Truck Shop Extension
Draft Decision Memo Santiam Junction Maintenance Station Truck Shop Extension USDA Forest Service McKenzie River Ranger District Willamette National Forest Linn County, OR T.13 S., R.7 E., Section 14,
More informationBeaverhead-Deerlodge National Forest Madison Ranger District
United States Department of Agriculture Forest Service Beaverhead-Deerlodge National Forest Madison Ranger District 5 Forest Service Road Ennis, MT 59729 406 682-4253 File Code: 1950 Date: April 19, 2013
More informationBeaverhead-Deerlodge National Forest Pintler Ranger District
United States Department of Agriculture Forest Service Beaverhead-Deerlodge National Forest Pintler Ranger District 88 Business Loop Philipsburg, MT 59858 406 859-3211 File Code: 1920 Date: April 20, 2012
More informationDECISION MEMO CATARACT CREEK-MOUNTAIN MEADOW PLAN OF OPERATIONS
Page 1 of 8 DECISION MEMO CATARACT CREEK-MOUNTAIN MEADOW PLAN OF OPERATIONS USDA Forest Service Madison Ranger District Madison County, Montana T2S, R3W, sections 16 & 21 Background Moen Excavation of
More informationDECISION MEMO 4-H Tree Farm LLC Driveway Permit
DECISION MEMO 4-H Tree Farm LLC Driveway Permit I. DECISION USDA Forest Service, Eastern Region, Hoosier National Forest Tell City Ranger District Perry County, Indiana T73S, R2W, SESE Section 36 A. Description
More informationDecision Memo. Cabin #5 Electric, Water, Septic Improvements
Decision Memo Cabin #5 Electric, Water, Septic Improvements USDA Forest Service Ocoee/ Hiwassee Ranger District, Cherokee National Forest Polk County, Tennessee Section 18, Township 2, Range 3 East; Lot
More informationPreliminary Decision Memo Recreation Residence Septic Repairs
Preliminary Decision Memo 2014 Recreation Residence Septic Repairs USDA Forest Service McKenzie River Ranger District Willamette National Forest Lane County, Oregon T. 16 S., R. 5 E, Section 16 Willamette
More informationDECISION MEMO SPECIAL USE AUTHORIZATION FOR GROUNDWATER MONITORING WELLS
DECISION MEMO SPECIAL USE AUTHORIZATION FOR GROUNDWATER MONITORING WELLS USDA-Forest Service, Eastern Region Huron-Manistee National Forests, Baldwin/White Cloud Ranger District Newaygo County, Michigan
More informationBackground. Purpose and Need. Proposal. Mitigation and Design Features
United States Department of Agriculture Forest Service Beaverhead-Deerlodge National Forest Madison Ranger District 5 Forest Service Rd Ennis, MT 59729 406 682-4253 File Code: 1950 Date: November 20, 2013
More informationMichigan Wing-Civil Air Patrol
DECISION MEMO Michigan Wing-Civil Air Patrol (CAP) Navigational Equipment Special Use Permit #MUN250 Hiawatha National Forest Munising Ranger District Alger County, Michigan I DECISION A. Description My
More informationDraft Decision Memo OHV Trails 22 and 42 Reroute Project
Draft Decision Memo OHV Trails 22 and 42 Reroute Project USDA Forest Service McKenzie River Ranger District Willamette National Forest Linn County, OR T13S, R7E, Sections 25 and 34 Willamette Meridian
More informationOn/Off periods Improvements Grazing System. 2 fence segments. 1 water development, 2 cattle guards
DECISION NOTICE HENRY CREEK AND SWAMP CREEK RANGE ALLOTMENT MANAGEMENT PLANS REVISION U.S. FOREST SERVICE PLAINS/THOMPSON FALLS RANGER DISTRICT LOLO NATIONAL FOREST SANDERS COUNTY, MONTANA DECISION Based
More informationDECISION MEMO. Aurora New Horizons Project
Page 1 of 7 Background DECISION MEMO USDA Forest Service Madison Ranger District Madison County In 2005 a decision covering approximately the same proposal was analyzed and a Decision Memo was signed.
More informationDecision Memo Sawtooth Trail #3634 Reroute
Decision Memo Sawtooth Trail #3634 Reroute USDA Forest Service Middle Fork Ranger District Willamette National Forest Lane County, OR T.25S, R.5.5E, Section 22, Willamette Meridian Purpose and Need The
More informationDECISION MEMO FOURTH OF JULY PARK 2 USDA Forest Service, Northern Region Red River Ranger District, Nez Perce National Forest Idaho County, Idaho
DECISION MEMO FOURTH OF JULY PARK 2 USDA Forest Service, Northern Region Red River Ranger District, Nez Perce National Forest Idaho County, Idaho I. Decision II. I have decided to authorize issuance of
More informationDECISION MEMO IDAHO DREAM PLAN OF OPERATIONS
Page 1 of 7 BACKGROUND DECISION MEMO USDA Forest Service Dillon Ranger District Beaverhead County The project area is included in the Ermont Mining District in T5S R11W Section 36 and T6S R11W Section
More informationDECISION MEMO POT MOUNTAIN TRAIL CONSTRUCTION USDA
DECISION MEMO POT MOUNTAIN TRAIL CONSTRUCTION USDA Forest Service, Northern Region North Fork Ranger District, Clearwater National Forest Clearwater County, Idaho I. Decision I have decided to authorize
More informationThe location of the valve site is displayed on a map in the project file.
DECISION MEMO Special Use Permit # RAR401201 Amendment #7 Hiawatha National Forest Rapid River Ranger District Delta County, Michigan I DECISION A. Description My decision is to issue an amendment to the
More informationBeaverhead-Deerlodge National Forest Madison Ranger District
United States Department of Agriculture Forest Service Beaverhead-Deerlodge National Forest Madison Ranger District 5 Forest Service Road Ennis, MT 59729 406 682-4253 File Code: 1950 Date: April 4, 2012
More informationDECISION MEMO. Bull Bear 1H-18 Oil and Gas Pipeline
DECISION MEMO Bull Bear 1H-18 Oil and Gas Pipeline USDA, Forest Service Cibola National Forest, Black Kettle National Grasslands Roger Mills County, Oklahoma BACKGROUND: Laredo Petroleum, Inc., in order
More informationPROJECT INFORMATION Manchester Ranger District Apple Tree Release and Maintenance Project
PROJECT INFORMATION Manchester Ranger District Apple Tree Release and Maintenance Project The USDA Forest Service is proposing to release and prune living apple trees in the Manchester Ranger District,
More informationI. Decision to be Implemented. II. Reasons for Categorically Excluding the Decision. A. Description of Decision - 1 -
Decision Memo Guitonville Penelec Power Line Right-of-Way Special Use Permit USDA Forest Service, Eastern Region 9 Allegheny National Forest Marienville Ranger District Warrant 5133, Green Township Forest
More informationDECISION MEMO. Missoula Electric Cooperative Point 118. MEC - Buried Electric Powerline (Along West Fork Butte Access Road #37 to Point 118)
DECISION MEMO Missoula Electric Cooperative Point 118 MEC - Buried Electric Powerline (Along West Fork Butte Access Road #37 to Point 118) USDA Forest Service - Lolo National Forest Missoula Ranger District
More informationDecision Memo. Programmatic Forest Plan Amendment for Cultural Resource Protection Standards and Guidelines. United States Department of Agriculture
United States Department of Agriculture Forest Service Decision Memo Programmatic Forest Plan Amendment for Cultural Resource Protection Standards and Guidelines Coconino National Forest Coconino, Gila,
More informationDECISION MEMO LOWER STILLWATER FISHERY ENHANCEMENT U.S. FOREST SERVICE DUCHESNE RANGER DISTRICT ASHLEY NATIONAL FOREST DUCHESNE COUNTY, UTAH
DECISION MEMO LOWER STILLWATER FISHERY ENHANCEMENT U.S. FOREST SERVICE DUCHESNE RANGER DISTRICT ASHLEY NATIONAL FOREST DUCHESNE COUNTY, UTAH BACKGROUND The Rock Creek drainage is a very popular recreation
More informationBACKGROUND DECISION. June 2016 Page 1 of 6
BACKGROUND DECISION MEMO HOUSE ROCK WILDLIFE AREA PASTURE FENCE USDA FOREST SERVICE, SOUTHWEST REGION (R3) KAIBAB NATIONAL FOREST - NORTH KAIBAB RANGER DISTRICT COCONINO COUNTY, ARIZONA The Kaibab National
More informationKENTUCKY UTILITIES SPECIAL USE AUTHORIZATION AMENDMENT: MOUNT VICTORY TRANSMISSION TOWER REPLACEMENT DECISION MEMO
UNITED STATES DEPARTMENT OF AGRICULTURE FOREST SERVICE SOUTHERN REGION DANIEL BOONE NATIONAL FOREST KENTUCKY MARCH 2016 KENTUCKY UTILITIES SPECIAL USE AUTHORIZATION AMENDMENT: MOUNT VICTORY TRANSMISSION
More informationScoping and 30-Day Notice and Comment Period for. Grassy Knob American Chestnut Planting
United States Department of Agriculture Forest Service Monongahela National Forest Greenbrier Ranger District Box 67 Bartow, WV 24920 Phone (304) 456-3335 File Code: 2020/2070/1950 Date: November 15, 2012
More informationSHASTA-MCCLOUD MANAGEMENT UNIT OVER SNOW VEHICLE TRAIL GROOMING AND SNOWMOBILE FACILITY MAINTENANCE PROPOSAL
DRAFT DECISION MEMO SHASTA-MCCLOUD MANAGEMENT UNIT OVER SNOW VEHICLE TRAIL GROOMING AND SNOWMOBILE FACILITY MAINTENANCE PROPOSAL U.S. FOREST SERVICE TOWNSHIP 40, 41, 42 AND 43 NORTH, RANGE 1, 2, 3 WEST,
More informationDECISION MEMO MANHATTAN FUELS REDUCTION PROJECT U.S. FOREST SERVICE CANYON LAKES RANGER DISTRICT LARIMER COUNTY, CO
DECISION MEMO MANHATTAN FUELS REDUCTION PROJECT U.S. FOREST SERVICE CANYON LAKES RANGER DISTRICT LARIMER COUNTY, CO Background and Project Description In order to improve forest health and reduce hazardous
More informationDECISION MEMO Robinhood Creek Helicopter Log Deck June, 2008
DECISION MEMO Robinhood Creek Helicopter Log Deck June, 2008 USDA Forest Service, Mt. Hood National Forest Hood River Ranger District Hood River County, Oregon Flooding in the fall of 2006 caused significant
More informationUnited States Department of Agriculture. Forest Service. Beaverhead-Deerlodge National Forest. September 2014
United States Department of Agriculture Forest Service Beaverhead-Deerlodge National Forest September 2014 Beaverhead-Deerlodge National Forest Land and Resource Management Plan Explanation Supporting
More informationDECISION MEMO. Cheat-Potomac Ranger District Multiple Recreation Facilities and Related Granger-Thye Concessions Special Use Permit
DECISION MEMO Cheat-Potomac Ranger District Multiple Recreation Facilities and Related Granger-Thye Concessions Special Use Permit United States Department of Agriculture Forest Service (FS) Eastern Region
More informationDecision Memo Raptor 1 and 9 Prescribed Burns Project
Decision Memo Raptor 1 and 9 Prescribed Burns Project USDA Forest Service Chemult Ranger District, Fremont-Winema National Forests Klamath County, OR Township (T) 29 South (S), Range (R) 6 East (E), Section
More informationThe project will be conducted in partnership with the Nez Perce Tribe.
DECISION MEMO Tributary to Brushy Fork Culvert Replacements Private Land USDA Forest Service, Northern Region Powell Ranger District Nez Perce Clearwater National Forests Idaho County, Idaho I. Decision
More informationDecision Memo for the City of Detroit Root Rot Timber Sale Project
Decision Memo for the City of Detroit Root Rot Timber Sale Project USDA Forest Service Detroit Ranger District Willamette National Forest Marion and Linn Counties, OR T.10S., R.5 E., Section 2, Willamette
More informationEnvironmental Assessment
United States Department of Agriculture Forest Service May 2009 Environmental Assessment Powder River Campground Decommissioning Powder River Ranger District, Bighorn National Forest Johnson and Washakie
More informationDecision Memo Hungry Creek Watershed Road Maintenance and Stony Quarry Development Project
Decision Memo Hungry Creek Watershed Road Maintenance and Stony Quarry Development Project USDA Forest Service Mount Hough and Beckwourth Ranger Districts Plumas County, CA Background We, (the USDA Forest
More informationDECISION MEMO SPECIAL USE AUTHORIZATION FOR PRIVATE ROAD PERMIT
DECISION MEMO SPECIAL USE AUTHORIZATION FOR PRIVATE ROAD PERMIT USDA-Forest Service, Eastern Region Huron-Manistee National Forests, Baldwin Ranger District Newaygo County, Michigan I. DECISION A. Background
More informationDecision Notice and Finding of No Significant Impact
Decision Notice and Finding of No Significant Impact Gold Lake Bog Research Natural Area Boundary Adjustment and Nonsignificant Forest Plan Amendment #53 USDA Forest Service Middle Fork Ranger District,
More informationDecision Memo Starkey Elk Handling Facility Water System Improvements
Decision Memo Starkey Elk Handling Facility Water System Improvements USDA Forest Service Wallowa-Whitman National Forest La Grande Ranger District Union County, Oregon I. DECISION TO BE IMPLEMENTED A.
More informationWetland Creation Project. Decision Memo
Wetland Creation Project UNITED STATES DEPARTMENT OF AGRICULTURE FOREST SERVICE Eastern REGION Monongahela NATIONAL FOREST West Virginia Decision Memo USDA Forest Service, Eastern Region, Monongahela National
More informationDecision Memo Halliburton Ann Exploration Project U.S. Forest Service Austin Ranger District, Humboldt-Toiyabe National Forest Nye County, Nevada
Decision Memo Halliburton Ann Exploration Project U.S. Forest Service Austin Ranger District, Humboldt-Toiyabe National Forest Nye County, Nevada Background The Ann Exploration Project is located on the
More informationDECISION MEMO WEST RIVER COOPERATIVE TELEPHONE COMPANY BURIED FIBER OPTIC CABLE PROJECT
DECISION MEMO WEST RIVER COOPERATIVE TELEPHONE COMPANY BURIED FIBER OPTIC CABLE PROJECT USDA, FOREST SERVICE GRAND RIVER NATIONAL GRASSLAND GRAND RIVER RANGER DISTRICT INTRODUCTION: West River Cooperative
More informationDECISION MEMO FOR USDA FOREST SERVICE DAKOTA PRAIRIE GRASSLANDS LITTLE MISSOURI NATIONAL GRASSLAND MEDORA RANGER DISTRICT SLOPE COUNTY, NORTH DAKOTA
DECISION MEMO FOR TWO (2) MEDORA RANGER DISTIRICT RANGE WATER PROJECTS ON ALLOTMENTS 023 AND 037 RANGE WATER STOCK TANKS AND PIPELINES AND RECLAIM and FENCE OUT DAMS USDA FOREST SERVICE DAKOTA PRAIRIE
More informationDECISION MEMO USDA FOREST SERVICE
DECISION MEMO USDA FOREST SERVICE Eagle River-Florence and Lakewood-Laona Ranger Districts Chequamegon-Nicolet National Forest Florence, Forest, Langlade, Oconto, Oneida, and Vilas Counties, Wisconsin
More informationDECISION MEMO. Wildlife Habitat Improvement Project Wildlife Opening Construction, Rehabilitation and Expansion FY
DECISION MEMO Wildlife Habitat Improvement Project Wildlife Opening Construction, Rehabilitation and Expansion FY 2007-2013 USDA Forest Service Bankhead National Forest - National Forests in Alabama Winston
More informationTenmile and Priest Pass Restoration Project Scoping Notice
Introduction Tenmile and Priest Pass Restoration Project Scoping Notice USDA Forest Service Helena National Forest Helena Ranger District Lewis and Clark County, Montana The Helena Ranger District of the
More informationI. DECISION. A. Description of Decision
DECISION MEMO Southern Indiana Power Oriental Road USDA Forest Service, Eastern Region Hoosier National Forest Tell City Ranger District Perry County, Indiana I. DECISION A. Description of Decision My
More informationDecision Memo. Delta A Septic Repair (#33)
Decision Memo Delta A Septic Repair (#33) USDA Forest Service Willamette National Forest McKenzie River Ranger District T16S, R5E, Section 16 Lane County, OR Proposed Action The McKenzie River Ranger District
More informationU.S.D.A. Forest Service National Forest & Grasslands in Texas Angelina National Forest Angelina/Sabine Ranger District Jasper County, Texas
DECISION MEMO WESTWOOD WATER SUPPLY CORPORATION SPECIAL USE PERMIT REISSUANCE AND MODIFICATION PROJECT U.S.D.A. Forest Service National Forest & Grasslands in Texas Angelina National Forest Angelina/Sabine
More informationDECISION MEMO JASON MINE-BAT HABITAT IMPROVEMENT AND MINE CLOSURE Section 22, T. 13S., R. 2W. Union County, Illinois
DECISION MEMO JASON MINE-BAT HABITAT IMPROVEMENT AND MINE CLOSURE Section 22, T. 13S., R. 2W. Union County, Illinois USDA Forest Service Mississippi Bluffs Ranger District, Shawnee National Forest Background
More informationTwo Med/Pike Oblit/Restoration Project Rocky Mountains
S DA 0, TED DEP1R-VENT AGR,CUL-JPE FOREST SERPCE Two Med/Pike Oblit/Restoration Project Rocky Mountains Decision Memo Rocky Mountain Ranger District Glacier County, Montana NORTHERN REGION Lewis and Clark
More informationDecision Memo North Boundary Salvage
Map # Proposal and Need for the Proposal Decision Memo North Boundary Salvage USDA Forest Service Chequamegon-Nicolet National Forest Medford-Park Falls Ranger District The U.S. Forest Service (USFS) is
More informationDECISION MEMO Chief Joseph Cross Country Ski Area Hazard Tree Project
Page 1 of 7 DECISION MEMO Chief Joseph Cross Country Ski Area Hazard Tree Project Background and Rationale for Decision USDA Forest Service Beaverhead-Deerlodge National Forest T 1S, R 19W, Sections 34,
More informationDECISION MEMO OREGON DEPARTMENT OF TRANSPORTATION (ODOT) SAND SHED CINDER PIT EXPLORATION PROJECT
DECISION MEMO OREGON DEPARTMENT OF TRANSPORTATION (ODOT) SAND SHED CINDER PIT EXPLORATION PROJECT USDA Forest Service Bend/Fort Rock Ranger District, Deschutes National Forest Deschutes County, Oregon
More informationDECISION MEMO SFA EXPERIMENTAL FOREST HERBACEOUS POND RESTORATION AUGUST, 2009 ANGELINA/SABINE RANGER DISTRICT ANGELINA NATIONAL FOREST
402 C B B DECISION MEMO SFA EXPERIMENTAL FOREST HERBACEOUS POND RESTORATION AUGUST, 2009 ANGELINA/SABINE RANGER DISTRICT ANGELINA NATIONAL FOREST NACOGDOCHES COUNTY, TEXAS USDA FOREST SERVICE, REGION 8
More informationFinal Decision Memo. Murphy Meadow Restoration Project. USDA Forest Service Willamette National Forest McKenzie River Ranger District
Final Decision Memo Murphy Meadow Restoration Project USDA Forest Service Willamette National Forest McKenzie River Ranger District T19S, R5E, Sec. 23, 24. Lane County Oregon BACKGROUND The Murphy Meadow
More informationDECISION MEMO Clay Butte Radio Repeater Relocation Project
Background DECISION MEMO Clay Butte Radio Repeater Relocation Project USDA FOREST SERVICE Rocky Mountain Region (R2) Shoshone National Forest Park County, Wyoming The Shoshone National Forest, Clarks Fork
More informationKeefer Pasture Drift Fence Project. Challis-Yankee Fork Ranger District Salmon-Challis National Forest
Keefer Pasture Drift Fence Project Challis-Yankee Fork Ranger District Salmon-Challis National Forest PROPOSED ACTION The Challis-Yankee Fork Ranger District proposes construction of approximately.11 miles
More informationDECISION MEMO PROJECT NAME: CLARK CREEK BLOWDOWN USDA FOREST SERVICE IDAHO PANHANDLE NATIONAL FOREST BONNERS FERRY RANGER DISTRICT
United States Department of Agriculture Forest Service Idaho Panhandle National Forests Bonners Ferry Ranger District 6286 Main Street Bonners Ferry, ID 83805 (208) 267-5561 File Code: 1950 Date: July
More informationProposed Action: In response to resource specialist concerns raised during internal scoping, the following restrictions will apply:
DECISION MEMO USDA Forest Service Inyan Kara Riders Motorcycle Enduro Event Rocky Mountain Region Thunder Basin National Grassland Medicine Bow-Routt National Forests Douglas Ranger District April 2011
More informationPRELIMINARY DECISION MEMO
PRELIMINARY DECISION MEMO Snoqualmie Christmas Tree Project USDA Forest Service Mt. Baker-Snoqualmie National Forest Snoqualmie Ranger District King County, Washington Proposed Action, Purpose and Need
More informationDecision Memo. USDA Forest Service Mountain Home Ranger District, Boise National Forest Boise County, Idaho
Decision Memo BOGUS CREEK OUTFITTERS SPECIAL USE PERMIT RENEWAL USDA Forest Service Mountain Home Ranger District, Boise National Forest Boise County, Idaho August 2014 DECISION It is my decision to renew
More informationDECISION MEMO ISSUE AN AMENDMENT TO AN EXISTING SPECIAL USE PERMIT
DECISION MEMO ISSUE AN AMENDMENT TO AN EXISTING SPECIAL USE PERMIT HIGH WEST ENERGY, INC. For A Single-Phase (2-Wire), Overhead Power Line US FOREST SERVICE Arapaho & Roosevelt National Forests and Pawnee
More informationDRAFT DECISION NOTICE AND FINDING OF NO SIGNIFICANT IMPACT ROAD/TRAIL DECOMMISSIONING AND SEASONAL CLOSURE PROJECT U.S.
DRAFT DECISION NOTICE AND FINDING OF NO SIGNIFICANT IMPACT ROAD/TRAIL DECOMMISSIONING AND SEASONAL CLOSURE PROJECT U.S. FOREST SERVICE CHATTAHOOCHEE-OCONEE NATIONAL FORESTS CONASAUGA RANGER DISTRICT FANNIN,
More informationDECISION MEMO WILLOW CREEK RECREATION AREA FACILITY RESTORATION U.S. FOREST SERVICE WILLOW CREEK RESERVE RANGER DISTRICT CATRON COUNTY, NEW MEXICO
DECISION MEMO WILLOW CREEK RECREATION AREA FACILITY RESTORATION U.S. FOREST SERVICE WILLOW CREEK RESERVE RANGER DISTRICT CATRON COUNTY, NEW MEXICO BACKGROUND The Willow Creek recreational area is located
More informationPROJECT INFORMATION Warren Falls Parking Lot Expansion Project
PROJECT INFORMATION Warren Falls Parking Lot Expansion Project The USDA Forest Service (USFS) has initiated an environmental analysis process for the proposed Warren Falls Parking Lot Expansion Project
More informationDecision Memo for Pax Ponderosa Pine Planting Project
Decision Memo for Pax Ponderosa Pine Planting Project USDA Forest Service Pacific Northwest Region Fremont-Winema National Forests Lakeview Ranger District Lake County, Oregon Introduction The Lakeview
More informationDecision Memo Tongass National Forest. Wrangell Ranger District. Pre-Commercial Thinning CE 2010
Decision Memo Tongass National Forest Pre-Commercial Thinning CE 2010 Decision It is my decision to authorize pre-commercial thinning (PCT) on approximately 7,500 acres of overstocked young-growth forest
More informationDecision Notice and Finding of No Significant Impact
Decision Notice and Finding of No Significant Impact Indigo and Middle Fork Willamette Enhancement Project USDA Forest Service Middle Fork Ranger District Willamette National Forest Lane County, Oregon
More informationMoonlight Aquatic Organism Passage Project
Notice of Proposed Action Moonlight Aquatic Organism Passage Project Mt. Hough Ranger District Plumas National Forest Plumas County, California Figure 1. Hungry 1 aquatic organism passage outlet showing
More informationDECISION MEMO For ASL (Allegheny Snowmobile Loop) Marshburg Connector Project
DECISION MEMO For ASL (Allegheny Snowmobile Loop) Marshburg Connector Project I. DECISION TO BE IMPLEMENTED A. Description of Decision USDA Forest Service, Eastern Region 9 Allegheny National Forest Bradford
More informationKinder/Morgan Southern Natural Gas. Right-of-Way Maintenance Project Woody Vegetation Control. Decision Notice And Finding of No Significant Impact
Kinder/Morgan Southern Natural Gas United States Department of Agriculture Southern Region Forest Service March 2013 Right-of-Way Maintenance Project Woody Vegetation Control Decision Notice And Finding
More informationDecision Memo USDA Forest Service Lookout Mountain Ranger District, Ochoco National Forest Crook County, Oregon Canyon Creek and Reservoir Allotments
Decision Memo USDA Forest Service Lookout Mountain Ranger District, Ochoco National Forest Crook County, Oregon Canyon Creek and Reservoir Allotments Background The Canyon Creek and Reservoir Allotments
More informationAppalachian Trail/Long Trail Cold River Road Relocation Project
United States Department of Agriculture Forest Service Eastern Region Appalachian Trail/Long Trail Cold River Road Relocation Project Decision Memo August 2012 Green Mountain National Forest Manchester
More informationDecision Memo - Elko Grade Improvement Project, Jarbidge Ranger District, Elko County, Nevada
Forest Service Humboldt-Toiyabe National Forest Ruby Mountains/Jarbidge Ranger Districts P. O. Box 246 Wells, NV 89835 File Code: 7730 Date: February 28, 2011 Route To: (7730) Subject: To: Decision Memo
More informationDECISION MEMO USDA FOREST SERVICE (USFS)
DECISION MEMO USDA FOREST SERVICE (USFS) Lakewood-Laona Ranger District Chequamegon-Nicolet National Forest Oconto County, Wisconsin DECISION I have decided to implement Project, as identified below, and
More informationLambson Draw On/Off Allotment Livestock Conversion Decision Notice
United States Department of Agriculture Forest Service Lambson Draw On/Off Allotment Livestock Conversion Decision Notice Ashley National Forest Flaming Gorge-Vernal Ranger District Uintah County, Utah
More informationDECISION MEMO. NORTH FORK of NORTH CREEK FISH BARRIER PROJECT
DECISION MEMO NORTH FORK of NORTH CREEK FISH BARRIER PROJECT USDA Forest Service Fishlake National Forest, Beaver Ranger District Beaver County, Utah I. DECISION I have decided to allow the Utah Division
More informationMeacham Creek Restoration Project
Meacham Creek Restoration Project Meacham Creek Restoration Project Umatilla National Forest Walla Walla Ranger District Michael Rassbach, District Ranger Public Scoping Document Proposal Summary The Walla
More informationForest Plan Amendment to Remove the Layng Creek Municipal Watershed Management Plan
United States Department of Agriculture Forest Service Forest Plan Amendment to Remove the Layng Creek Municipal Watershed Management Plan Draft Decision Memo Umpqua National Forest Cottage Grove Ranger
More informationPreliminary Decision Memo 2017 BPA Utility Corridor Maintenance and Danger Tree Project
Preliminary Decision Memo 2017 BPA Utility Corridor Maintenance and Danger Tree Project USDA Forest Service Crescent Ranger District, Deschutes National Forest Klamath County, Oregon The Crescent Ranger
More informationDecision Memo Rose Canyon Salvage Project
Decision Memo Rose Canyon Salvage Project USDA Forest Service Coronado National Forest Pima County, Arizona Background The Rose Canyon Salvage Project is located in the Rose Canyon Campground on the Santa
More informationMount Diablo Baseline and Meridian. T42N, R54E, Section 29 and 30
DECISION MEMO Walker Ridge Gold Exploration Project Plan of Operations #06-12-05 Mountain City Ranger District, Humboldt-Toiyabe National Forest Elko County, Nevada BACKGROUND On February 21, 2012, Columbia
More informationDecision Memo. Big Spring Gold LLC Big Spring Gold Exploration Project Plan of Operations #
Decision Memo United States Department of Agriculture Forest Service July, 2014 Big Spring Gold LLC Big Spring Gold Exploration Project Plan of Operations # 03-13-01 Austin Ranger District, Humboldt-Toiyabe
More information