Section 2 Proposal Description
|
|
- Ariel Kelly
- 6 years ago
- Views:
Transcription
1 Section 2 Proposal Description
2 2. PROPOSAL DESCRIPTION 2.1 Overview The Proposal comprises the construction, operation and closure of mining at the J5 and Bungalbin East iron ore deposits and associated infrastructure in the Mt Manning area north of Southern Cross. Mining will be undertaken from a total of three open-cut pits across two deposits using conventional drill and blast techniques followed by excavation, loading and transport to the ore stockyard. Stockpiled ore will be loaded onto haul trucks and transported 50 km south on dedicated haul roads to the existing ore processing facility at MRL s Carina operation. The processing facility dry-crushes and screens the ore to a suitable size for loading onto ore trains at the Mt Walton siding on the Trans-Australian railway line. The key characteristics of the Proposal are summarised in Table 2-1 and detailed in Table 2-2 and Table 2-3 in terms of the physical and operational elements of the Proposal. The key characteristics have been defined with reference to the Environmental Assessment Guideline for Defining the Key Characteristics of a Proposal (Environmental Protection Authority, 2012).The remainder of this section describes the Proposal in further detail. TABLE 2-1: KEY CHARACTERISTICS - SUMMARY OF THE PROPOSAL Proposal title Proponent name Short description Jackson 5 and Bungalbin East Iron Ore Project Mineral Resources Limited The Proposal is to construct and operate two open-cut iron ore mines, referred to as J5 and Bungalbin East, within the Mount Manning area. The Proposal is located approximately 100 km north of Southern Cross in the Yilgarn area of WA. The Proposal includes: three open-cut pits (one at J5 and two at Bungalbin East) three waste rock landforms haul roads supporting infrastructure for each mine include internal mine access roads, the ore stockpile area, site office, workshop, laydown area, explosive magazine, water bores, water storage dam (turkey nest) for potable and operational water supply, Waste Water Treatment Plant (WWTP), Reverse Osmosis plant (RO), power supply, fuel storage, hazardous materials storage area and landfill closure of both mines and rehabilitation of areas disturbed by mining and related activities. Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-1
3 TABLE 2-2: KEY CHARACTERISTICS PHYSICAL ELEMENTS Element J5 Bungalbin East Location Proposed extent Location Proposed extent Mine pit Figure 2-1 Section 0 Clearing no more than 61 hectares (ha) of native vegetation within a 2055 ha development envelope. Figure 2-1a Section 0 Clearing no more than 147 ha of native vegetation within a 2055 ha development envelope. Waste rock landform Figure 2-1 Clearing no more than 88 ha of native vegetation within a 2055 ha development envelope. Figure 2-1a Clearing no more than 98 ha of native vegetation within a 2055 ha development envelope. Supporting infrastructure Figure 2-1 Clearing no more than 47 ha of native vegetation within a 2055 ha development envelope. Figure 2-1a Clearing no more than 45 ha of native vegetation within a 2055 ha development envelope. Haul road Figure 2-1 Figure 2-1b Clearing no more than 57 ha of native vegetation within a 2055 ha development envelope. Figure 2-1a Figure 2-1c Clearing no more than 68 ha of native vegetation within a 2055 ha development envelope. TABLE 2-3: KEY CHARACTERISTICS OPERATIONAL ELEMENTS Element J5 Bungalbin East Location Proposed extent Location Proposed extent Waste rock volume Figure 2-1 Disposal of approximately 21 million tonnes of waste rock Figure 2-1a Disposal of approximately 70 million tonnes of waste rock Water abstraction Total abstraction of approximately 219,000 kilolitres per annum for construction and operational purposes. 2.2 Construction Construction will commence with clearing the centreline of the haul road, which will be subsequently widened to the full width of the haul road, inclusive of cut and fill requirements to maintain the design gradient. Locations of suitable gravel material for road construction will be identified within the development envelope and these areas cleared in preparation for excavation of this material. Topsoil and vegetation will be stockpiled in suitable locations for use in rehabilitation following the completion of mining. Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-2
4 750000mE mE mE mE mE Legend Disturbance area (Proposal) Development Envelope mN mN mN mN mN mN mN mN Sheet Layout Source: Infrastructure supplied by Mineral Resources (Apr 2016) Imagery: Landgate (2012) mE Figure: 600m Scale 1:30,000 MGA94 (Zone 50) Author: Mineral Resources CAD Ref: g2378_j5_be_per_c02_f02_01 Drawn: CAD Resources ~ Date: Jul 2016 Rev: D A4 Tel: (08) ~ Fax (08) THE PROPOSAL 2-1
5 760000mE Legend Disturbance area (Proposal) Development Envelope mN mN mE mN mN mN mN mN mN Sheet Layout Source: Infrastructure supplied by Mineral Resources (Apr 2016) Imagery: Landgate (2012) mE Scale 1:30,000 MGA94 (Zone 50) Figure: Author: Mineral Resources CAD Ref: g2378_j5_be_per_c02_f02_02 Drawn: CAD Resources ~ Date: Jul mE 600m Rev: D A4 Tel: (08) ~ Fax (08) THE PROPOSAL 2-1A
6 754000mE mE mE mE Legend Disturbance area (Proposal) Development Envelope mN mN mN mN Sheet Layout Source: Infrastructure supplied by Mineral Resources (Jul 2016) Imagery: Landgate (2012) mE mE mE mE m Scale 1:30,000 MGA94 (Zone 50) CAD Ref: g2378_j5_be_per_c02_f02_03 Date: Jul 2016 Rev: C A4 Author: Mineral Resources Drawn: CAD Resources ~ Tel: (08) ~ Fax (08) THE PROPOSAL Figure: 2-1B
7 758000mE mE mE Legend Disturbance area (Proposal) Development Envelope mN mN mN mN 4 Sheet Layout mN mN mN mN Source: Infrastructure supplied by Mineral Resources (Jul 2016) Imagery: Landgate (2012) mE m mE Scale 1:30,000 MGA94 (Zone 50) Author: Mineral Resources CAD Ref: g2378_j5_be_per_c02_f02_04 Drawn: CAD Resources ~ Date: Jul 2016 Rev: C A4 Tel: (08) ~ Fax (08) THE PROPOSAL mE Figure: 2-1C
8 Water for construction requirements may initially be sourced from the licensed production bores at the J4 and Carina mines, and the associated pipeline installed along the J4 haul road. Construction of the mines and supporting infrastructure will commence once the haul road has been completed to a sufficient standard allowing construction machinery to access the mine sites. Topsoil and vegetation will be stockpiled in suitable locations for use in progressive rehabilitation following the commencement of mining. 2.3 Operations Mine pits The J5 deposit will be mined from a single open-cut pit yielding a total estimated 13 to 32 million tonnes (Mt) of iron ore. The Bungalbin East deposit will be mined from two adjacent pits yielding a total estimated 52 to 83 Mt of iron ore. At the completion of mining, the area disturbed by the pits at J5 and Bungalbin East will be 61 ha and 147 ha, respectively. This disturbance area is inclusive of areas previously disturbed by historic land use as well as areas required during and/or after mining for: temporary storage of cleared vegetation that will be used for progressive and postmining rehabilitation temporary storage of harvested topsoil/subsoil that will be used for progressive and post-mining rehabilitation light vehicle access track between mine pits and stored vegetation and topsoil abandonment bunds where required for ongoing public safety of the area post mining. Mining will result in the removal of approximately 75 vertical metres of rock within the pit at J5 and approximately 115 vertical metres of rock within the southern (deepest) pit at Bungalbin East. Pit dewatering will not be required at either deposit as mining will not intersect the natural groundwater elevation of approximately 420 metres (m) Australian Height Datum (AHD) at J5 and 450 mahd at Bungalbin East. At Bungalbin East the southern pit will be mined first and then backfilled with waste rock from the northern pit. Backfilling of the southern pit is expected to raise the floor of the pit to about the same height as the eastern side of the pit crest (refer to Figure 12-2) Waste rock landforms Approximately 91 Mt of waste rock will be excavated during mining, comprised of approximately 21 Mt of at J5 and approximately 70 Mt at Bungalbin East. At J5 waste rock will be disposed of via two smaller Waste Rock Landforms (WRLs) adjacent to the pit. The WRLs are separated from each other and the mine pit by internal access roads. At Bungalbin East, waste rock from the southern pit will be disposed of via a single WRL containing approximately 33 Mt. Waste rock from the northern pit will be backfilled into the southern pit, comprising a volume of approximately 37 Mt. The WRL and associated access roads are located to avoid conservation significant plant species where possible. The conceptual design for the WRLs incorporates a single lift that is up to 45 m in height with concave slopes having a profile of 20 degrees at the crest grading to 15 degrees at the toe. If necessary, cells will be constructed within the centre of the WRLs to appropriately dispose of potentially acid forming or other hostile waste rock. Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-7
9 At the completion of mining the combined disturbance area of the WRLs at J5 and a Bungalbin East will be 186 ha, comprised of 88 ha at J5 and 98 ha at Bungalbin East. This disturbance area is inclusive of areas previously disturbed by historic land use as well as: temporary storage of cleared vegetation that will be used for progressive and postmining rehabilitation temporary storage of harvested topsoil/subsoil that will be used for progressive and post-mining rehabilitation light vehicle access tracks between the WRLs and stored vegetation and topsoil Supporting infrastructure Supporting infrastructure for each mine includes internal mine access roads, the ore stockpile area, site office, workshop, laydown area, explosive magazine, water storage dam (turkey nest) for potable and operational water supply, WWTP, RO plant, power supply, fuel storage, hazardous materials storage area and landfill. At the completion of mining the total area disturbed by supporting infrastructure at J5 and Bungalbin East will be 92 ha, comprised of 47 ha at J5 and 45 ha at Bungalbin East. This disturbance area is inclusive of areas previously disturbed by historic land use as well as temporary storage of cleared vegetation and harvested topsoil/subsoil that will be used for postmining rehabilitation of these areas Haul roads A total of 30 km of haul road will be constructed to connect the mine operations to the J4 haul road. The haul road network extends generally south from the deposits along L77/253 (incorporating a small diversion, being L77/270) to meet the J4 haul road on L77/254. At the completion of mining the total area disturbed by haul roads will be 125 ha, comprised of 57 ha at J5 and 68 ha at Bungalbin East. This disturbance area includes allowances for: 2.4 Closure temporary storage of cleared vegetation, topsoil and subsoil that will be used as part of post-mining rehabilitation gravel pits for road-base material as well as long-term maintenance of unsealed mine roads road drainage through the installation of v-drains and catch-ponds where necessary maintenance of surface water flow during flood events through the installation of pipes and/or culverts as necessary water pipelines and telecommunications infrastructure (e.g. fibre-optic cable and communications towers) as required. The closure phase of the Proposal comprises the decommissioning and removal of all built infrastructure and rehabilitation of all remaining disturbance associated with the Proposal. Rehabilitation and decommissioning will be undertaken in accordance with the Rehabilitation and Mine Closure Plan. Further detail on rehabilitation and decommissioning is provided in Section 12. In the interest of public safety, abandonment bunds will be constructed across mine roads and other access tracks that intersect the pits, to prevent the possibility of inadvertent vehicle access to these areas. Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-8
10 Where there is steep terrain and an absence of mine roads or access tracks the potential safety risk from inadvertent vehicular access is low, but allowance has been made for the construction of an abandonment bund within the disturbance area. MRL has consulted with the DMP regarding the positioning of abandonment bunds, noting that detailed geotechnical drilling to confirm the stability of the pit walls post mining has not been possible at this time due to access restriction. This geotechnical drilling will occur immediately following approval to confirm how close mining can safely approach the abandonment bunds thereby ensuring long-term stability of the final landform. 2.5 Existing facilities The Proposal will utilise existing facilities associated with the J4 and Carina operations, these being the J4 haul road, the Carina accommodation village, the Carina haul road, the Carina airstrip and the processing and rail load-out facilities at the Carina operation. A new accommodation village will be constructed at the intersection of the J4 and proposed Bungalbin East haul roads, outside of the MMHARCP. This village is approved under Ministerial Statement 988 in relation to the J4 proposal and the changes to that proposal approved under s45c of the EP Act. The village was not constructed to support the J4 operation for economic reasons. Whilst the new camp is under construction, the existing Aurora camp on M77/580 will be utilised to accommodate a construction workforce of up to 110 personnel, prior to the Aurora camp being decommissioned. Both the Carina and J4 mines and associated infrastructure operate pursuant to approvals obtained under relevant legislation. The aspects of these operations that are necessary for the implementation of the Proposal, such as the processing and rail load-out facilities, haul roads, accommodation village and airstrip can be managed under existing approvals under Part IV of the EP Act and therefore do not form part of the Proposal. 2.6 Alternatives considered MRL has undertaken a detailed evaluation of options or alternatives in locating, planning and designing the Proposal to mitigate environmental impacts. This evaluation began prior to the development of MRL s Carina operation in 2011, when strategic planning was undertaken with regard to the future development of all of MRL s iron ore deposits in the Yilgarn, including Carina Extended, Chameleon, Hunt Range, J4, J5 and Bungalbin East. The no development alternative is not a realistic proposition for MRL due to the significant investment it has made in the Yilgarn region for the benefit of shareholders, employees, local communities and the State of WA. In any case, the significance of residual impacts of the Proposal are not so great as to justify a no development decision. Exercise of the no development alternative is more appropriately achieved through Government policy. As no such policy exists in any tenements and their associated mineral exploration and mining entitlements that were to be relinquished by MRL would inevitably be secured by others. Mining of iron ore deposits in the Yilgarn is typically carried out using a central infrastructure hub, often attached to a mine, which receives and processes ore from one or more satellite mines in the region prior to rail load-out to a port facility. Haulage of ore from satellite mines to the central processing hub is typically done by haul trucks operating on a dedicated haul road, with rail transport inevitably being excluded on the basis of the relatively high up-front capital cost of construction that cannot be recovered over the life of the Proposal. By implementing the model outlined above, MRL is able to minimise the cumulative environmental impact of mining as ore processing facilities are not required to be constructed at Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-9
11 each satellite mine and other approved infrastructure such as segments of haul roads constructed as part of other proposals will be utilised. The haulage routes between J4, J5, Bungalbin East and MRL s central processing hub at Carina were carefully evaluated, particularly with respect to the MMHARCP. Two main haul routes were considered: Continue the Carina haul road in north-westerly direction to connect the Carina Extended, Chameleon and Hunt Range deposits and then in a westerly direction along the northern side of the Helena-Aurora Range to connect J4, J5 and Bungalbin East. Branch off the Carina Haul Road about 10 km south of the Carina mine in a westerly direction to connect with J4, with additional spurs along the way in a northerly direction to connect to J4 and Bungalbin East. The latter of these two options was ultimately selected on the basis that J4 would be developed first and that this option would minimise the extent of the haul road network, and therefore disturbance, within the MMHARCP. In doing so, the haulage distance between J4, J5, Bungalbin East and the central processing hub was increased at MRL s cost, in terms of the length of haul road to be constructed as well as the ore haulage distance. In terms of the sequence of development for the Proposal, it should be noted that the mines will be developed simultaneously once mining at J4 is complete. Ore from J5 is required to be blended with ore from Bungalbin East to achieve the correct product specification; therefore J5 is unlikely to be mined in isolation from Bungalbin East. MRL has invested considerable effort in site design and layout to optimise the Proposal so as to minimise environmental impact. The process of optimisation has focussed on the location and design of WRLs, supporting infrastructure and haul roads. This is because these elements, as compared to the mine pits, are more capable of being located and/or designed to avoid or minimise environmental impacts. The ore deposits, and the pits required to be excavated to recover these deposits, are fixed and cannot be located elsewhere. In direct response to stakeholder consultation, MRL has made several key changes to site design and layout optimisation since referral of the Proposal: The J5 WRL was initially a single WRL located further east than the current design. The eastern end of the WRL encroached upon a large drainage line and potentially could have impeded water flow following large rainfall events. The WRL was split into two separate WRLs, one either side of the main access road to the mine. This allowed the eastern WRL to be reduced in size so that it no longer encroached upon the drainage line. The western WRL was also redesigned to avoid populations of conservation significant flora. The Bungalbin East WRL was initially located immediately adjacent to the mine pit to reduce the waste haulage distance and therefore increase mine profitability. It has subsequently been repositioned further from the pit to minimise impacts on the landform, in this case the Helena-Aurora Range, as well as dense populations of conservation significant flora. The overall land disturbance area of the WRL at Bungalbin East has been decreased significantly from 176 ha to 98 ha. This is a result of rescheduling the mine plan to focus on the southern half of the Bungalbin pit early in the mine life to create a void for backfilling. Waste material from the northern half of the Bungalbin pit will then be hauled a shorter distance to backfill the void. This not only reduces the area and height of the waste dump, and hence the environmental impact, but also reduces the number of trucks required, improving the economics of the Proposal. MRL has successfully applied this strategy at Carina (also in the Yilgarn) and will also implement this strategy at Iron Valley in the Pilbara. This opportunity is Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-10
12 unlikely to be available at J5 where the vertical dip of the orebody means that backfilling would sterilise potential pit cutbacks (within the area proposed under this PER). Backfilling of all the waste cannot be achieved without rehandling of the entire waste rock volume after the extraction of all of the ore, an undertaking that would have an unsustainable negative impact on the economics of the proposal disproportionate to any environmental benefits of doing so. The area of disturbance comprising the mine pit at Bungalbin East was reduced to avoid a population of L. bungalbin (Priority 1). The elevation profile of all WRLs was revised from a traditional berm and batter arrangement to a single concave slope. At Bungalbin East, the shape of the WRL was also elongated from its initial circular shape. These changes are expected to provide a better aesthetic form that, coupled with appropriate landscape treatment post mining, will better blend with the surrounding topography. The extent of supporting infrastructure was decreased at both J5 and Bungalbin East by resizing the ROM pads and removing the evaporation ponds (as these ponds are not required as mining will occur above the groundwater table). The supporting infrastructure area at Bungalbin East was repositioned further west, which allowed the WRL at Bungalbin East to also be repositioned further to the southwest. Access roads between the pit and the WRL at Bungalbin East were redesigned to avoid populations of the threatened flora species Tetratheca aphylla subsp. aphylla. The mid-section of the J5 haul road was realigned further south to avoid a portion of a major drainage line with the same alignment i.e. the haul road was positioned within and parallel to the drainage line. Miscellaneous Licence L77/270 was applied for specifically for this reason. Overall, these changes have reduced the total area of direct disturbance (clearing) for the Proposal from 720 ha as referred to 611 ha as proposed. This includes a net reduction in the mine pit area at Bungalbin East from 149 ha to 147 ha. 2.7 Approach to environmental management A key principle of EIA in WA is the use of best practicable measures and genuine evaluation of options or alternatives in locating, planning and designing proposals to mitigate detrimental environmental impacts and to facilitate positive environmental outcomes and a continuous improvement approach to environmental management (Government of Western Australia, 2012). Best practicable measures are discussed below in the context of environmental management. Importantly, the achievement of best practices is greatly facilitated where proponents have an environmental management system in place, particularly if it is consistent with an international standard such as ISO (Environmental Protection Authority, 2003). To manage its impacts on the environment, MRL adopts a systematic management approach based on the international standard for environmental management systems (International Organisation for Standardisation, 2015). MRL s Environment and Community Policy 2016 is the cornerstone of this approach, a copy of which is contained in Appendix 1-A. The policy promotes sustainable environmental and community practices with a stated objective of no harm to the environment or adverse impacts on the communities within which MRL operates, beyond that which is necessary to conduct its business and is approved by Government. It commits to developing and implementing management systems that enable the company to conduct its business in a responsible and appropriate manner. Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-11
13 From this policy, MRL has developed a corporate Environmental Management Plan (EMP) to provide an overview of MRL s approach (Appendix 2-A). The EMP forms an important component of MRL s Environmental Management System as it outlines the Plan-Do-Check-Act (PDCA) model and how it applies at MRL. This model is a feature of the ISO 14001:2015 standard and has leadership as a central attribute. The PDCA model, as it applies to MRL, is described in Table 2-4. Routine policies and procedures developed at the corporate level will apply to the Proposal as well as Proposal-specific plans and procedures included with this PER or to be developed in the future e.g. in response to conditions of approval. Recognising the need to achieve best practice environmental management in relation to the Proposal, MRL is committed to certifying the EMS for the Proposal to the ISO standard within two years after commencing productive mining operations. TABLE 2-4: EMS MODEL COMPONENTS AND ACTIONS Component Actions Leadership Take accountability for effectiveness of EMS. Integrate EMS into MRL's business processes. Ensure the resources needed for the EMS are available. Promote continual improvement. Plan Establish environmental objectives, KPIs and processes necessary to deliver results in accordance with MRL s policy. Identify legal obligations. Do Develop and implement an EMP. Develop and implement systems and operational procedures, and work instructions. Identify and meet training needs. Identify responsibilities and accountabilities. Emergency preparedness and response. Check Measure progress against KPIs. Environmental monitoring programs. Auditing and inspection. Records control. Act Consider performance and take actions to continually improve. Issue Date: 31/08/2016 MRL-ENV-TS-RP-0047-Rev2 Page 2-12
Section 15 Environmental Protection
Section 15 Environmental Protection 15. ENVIRONMENTAL PROTECTION The object of the EP Act is to protect the environment of the Western Australia having regard to the principles described in Table 15-1.
More information11 ASSESSMENT OF OTHER ENVIRONMENTAL FACTORS
Proposed Sandy Ridge Facility Public Environmental Review 11 ASSESSMENT OF OTHER ENVIRONMENTAL FACTORS Amenity 11.1.1 Introduction This section assesses the potential impacts on amenity during both construction
More informationSection 4 Environmental Impact Assessment Framework
Section 4 Environmental Impact Assessment Framework 4. ENVIRONMENTAL IMPACT ASSESSMENT FRAMEWORK 4.1 Environmental Impact Assessment in Western Australia The overall framework for EIA in WA is described
More informationBENGALLA Mining Company. Contamination Assessment
BENGALLA Mining Company U Contamination Assessment U CONTINUATION OF BENGALLA MINE PRELIMINARY CONTAMINATION ASSESSMENT Prepared by: HANSEN BAILEY 6 / 127 129 John Street SINGLETON NSW 2330 July 2013 For:
More informationBorrow Pit and Quarry Management Procedure Environmental
1 Purpose and Scope This procedure specifies the operational environmental requirements relating to borrow pit (BP) and quarry management at the Roy Hill Project. This procedure applies to all personnel
More informationTABLE 10-1: LEGISLATION, POLICIES AND GUIDANCE CONSIDERED DURING EIA. Provide criteria as to acceptable limits for noise.
Section 10 Amenity 10. AMENITY 10.1 EPA objective and policy The EPA objective for amenity is to: ensure that impacts to amenity are reduced to as low as reasonably practicable The policy and guidance
More informationGround Disturbance Permit Procedure Environment
1 Purpose and Scope This procedure specifies the operational environmental requirements relating to ground disturbance management at the Roy Hill Project. This procedure applies to all personnel involved
More informationMINERAL RESOURCES LIMITED
MINERAL RESOURCES LIMITED QUARTERLY EXPLORATION AND MINING ACTIVITIES REPORT OCTOBER TO DECEMBER Q2 FY2017 MINERAL RESOURCES LIMITED QUARTERLY EXPLORATION AND MINING ACTIVITIES REPORT OCTOBER TO DECEMBER,
More informationEnvironmental Assessment Chapter 8 Surface Water
Environmental Assessment Chapter 8 Surface Water 8.2.7 Rainfall and Evaporation Based on recorded data for the area of interest, the mean annual rainfall is about 700mm, with maximum monthly rainfalls
More informationBACKGROUND INFORMATION DOCUMENT
BACKGROUND INFORMATION DOCUMENT Environmental and Social Impact Assessment (ESIA) December 2017 Malingunde Graphite Project, Lilongwe District, Malawi Purpose of this document This document provides information
More informationSUBMISSION NUMBER 13 SUNWATER BYERWEN COAL PTY LTD BYERWEN COAL PROJECT
SUBMISSION NUMBER 13 SUNWATER BYERWEN COAL PTY LTD BYERWEN COAL PROJECT AIEIS for the 13. SUBMISSION NUMBER 13 SUNWATER 13.1 Issue Number 13.1 Section 3.2 of the Byerwen Coal project Terms of Reference
More informationNEWNES JUNCTION SAND AND KAOLIN EXTRACTION PROJECT
SYDNEY CONSTRUCTION MATERIALS NEWNES JUNCTION SAND AND KAOLIN EXTRACTION PROJECT QUARRY PLAN MineConsult mine management consultants May, 2004 Job No. 1864 CONFIDENTIALITY AND USE OF INTELLECTUAL PROPERTY
More informationOweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B
Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International
More informationExecutive Summary INTRODUCTION THE APPLICANT
ENVIRONMENTAL IMPACT STATEMENT EMC METALS AUSTRALIA PTY LTD INTRODUCTION This Environmental Impact Statement (EIS) has been prepared by R.W. Corkery & Co. Pty. Limited on behalf of EMC Metals Australia
More information24. Closure and Rehabilitation
24. Closure and Rehabilitation The purpose of this chapter is to describe the proposed approach to closure and rehabilitation of the Project. Unless otherwise stated, closure and rehabilitation information
More informationMINE DESIGN AND PLANNING
TE KUHA PROJECT STEVENSON MINING LIMITED AUGUST 2016 V13 MINE DESIGN AND PLANNING MINE DESIGN PIT DESIGN DESIGN Pit Slope Design is based on 10m high horizontal benches to allow for steep dipping coal
More informationFor personal use only
ABN 28 009 174 761 www.regisresources.com Level 1 1 Alvan Street Subiaco WA 6008 Australia P 08 9442 2200 F 08 9442 2290 20 February 2013 Manager Announcements Company Announcements Office Australian Securities
More informationSantoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.
Environmental Impact Assessment Technical Review Comments on the Environmental Impact Statement as submitted by Claude Resources Inc. Saskatchewan Ministry of Environment December, 2009 1. INTRODUCTION
More informationPhase VII Expansion Waste Rock and Overburden Management Plan
Phase VII Expansion Waste Rock and Overburden Management Plan 2018-01 Prepared by: Minto Explorations Ltd. Minto Mine January 2018 Minto Mine Phase VII Expansion January 2018 TABLE OF CONTENTS 1 Introduction...
More informationEnvironmental Management Plan (EMP)
SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit
More informationGum Creek Gold Project Free Milling Scoping Study
18 March 2016 ASX: PAN Highlights Gum Creek Gold Project Free Milling Scoping Study Mining Inventory of 4.9Mt at 1.94g/t Au for 309koz gold based on material from Swan, Swift and Howards Resources Average
More informationMorgan Stanley 2013 Emerging Companies Conference An Integrated Australian Mining Services Company June
Morgan Stanley 2013 Emerging Companies Conference An Integrated Australian Mining Services Company June 2013 www.mineralresources.com.au Service Provider Minerals Producer Process Minerals A leading processor,
More informationHunter Valley Operations South
Hunter Valley Operations South This booklet outlines a modification proposal being prepared for Coal & Allied s Hunter Valley Operations (HVO) South mining activities. In this booklet you will find an
More informationREPORT. Review of Application TE KUHA MINE. 22 December Submitted to: Department of Conservation 10 Sewell St Hokitika 7810
REPORT 22 December 2014 Review of Application TE KUHA MINE Submitted to: Department of Conservation 10 Sewell St Hokitika 7810 Table of Contents 1 Introduction 3 2 Mine Planning 3 3 Access Road 3 4 Pits
More informationThe Project is expected to disturb a total area of approximately 1,060 ha. Table
16. Rehabilitation and Mine Closure 16.1 Background The Project is expected to disturb a total area of approximately 1,060 ha. Table 2-2 provides a breakdown of area according to individual mine feature.
More informationPapua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV
Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 11: PGGP-EH-SPENV-000018-013 LNG Project Page 2 of 13 CONTENTS 1.0 Objectives... 3 2.0 Legal and Other
More informationWindarling 2015 W1 and W2 Flora Monitoring December 2015
2015 W1 and W2 Flora Monitoring December 2015 Document History Rev No. Author Distribution Date Status A K Wilkinson N Smith 19.09.2015 Draft for Internal Review 0 K Wilkinson Cliffs 18.12.2015 Final for
More information14. ENVIRON MEN TA L I MPAC T ASSE S SMEN T - INTE GR ATIN G FACTOR - OF FSE TS
14. ENVIRON MEN TA L I MPAC T ASSE S SMEN T - INTE GR ATIN G FACTOR - OF FSE TS The EPA s objective for offsets is to counterbalance any significant residual environmental impacts or uncertainty through
More informationYeelirrie Uranium Project. Environmental Management
Yeelirrie Uranium Project Environmental Management Yeelirrie Uranium Project Yeelirrie is one of Australia s largest undeveloped uranium deposits. The deposit is located approximately 660 km north east
More informationWindarling 2014 W1 and W2 Flora Monitoring April 2015
2014 W1 and W2 Flora Monitoring April 2015 Document History Rev No. Author Distribution Date Status A K. Wilkinson J. Shepherdson 25.03.2015 Draft for Internal Review 0 K. Wilkinson Cliffs, OEPA 01.04.2015
More informationMoolarben Coal Complex UG1 Optimisation Modification. Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW
Moolarben Coal Complex UG1 Optimisation Modification Environmental Assessment APPENDIX F SURFACE WATER ASSESSMENT REVIEW Moolarben Coal Complex UG1 Optimisation Modification Surface Water Assessment Review
More informationMARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES
ASX Release: 9 September 2010 MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES Definitive Mining Studies confirm continuity, quality and quantum of Ore body at MARILLANA Detrital Ore Reserves
More informationAppendix 11. Erosion and Sediment Control Management Plan. Appendix 11
Appendix 11 Erosion and Sediment Control Management Plan Appendix 11 OTAIKA QUARRY - PROPOSED OVERBURDEN DISPOSAL AREA Application for Land Use Consent and Assessment of Environmental Effects Otaika Quarry
More informationTABLE OF CONTENTS. Atlas-Campaspe Mineral Sands Project Environmental Impact Statement
TABLE OF CONTENTS 1 INTRODUCTION 1-1 1.1 PROJECT OVERVIEW 1-1 1.1.1 Purpose of this Report 1-1 1.1.2 Project Summary 1-1 1.1.3 Land Tenure, Development Application Area, Tenements and Zoning 1-7 1.1.4
More informationSouthern Cross Goldfields Ltd
Southern Cross Goldfields Ltd ASX Announcement - 20 December 2013 Marda Gold Project: Feasibility Study Review Additional Information On 10 December 2013, Southern Cross Goldfields (ASX: SXG SXG or the
More informationInrushes and Subsidence
PURPOSE AND SCOPE... 2 DETAILS... 2 Appendices... 11 A Definitions... 11 B Related Documents... 11 C Revision Information... 11 1. Responsibility... 2 2. Hazard Management Process... 3 2.1 Overview...3
More informationThe key contact for this proposal is Belinda Bastow (AngloGold), Environmental Manager Exploration/ Tropicana:
Tropicana Gold Project: Public Environmental Review 1. Introduction 1. INTRODUCTION This document and supporting appendices comprises the Public Environmental Review (PER) documentation for the Tropicana
More information8.0 CLOSURE AND DECOMMISSIONING
Closure and Decommissioning 8-1 8.0 CLOSURE AND DECOMMISSIONING Closure and decommissioning of the Project would be accomplished in accordance with Ghana s Mining and Environmental Guidelines (1994) and
More informationEXTENSION TO THE WILUNA URANIUM PROJECT ASSESSMENT NO: 2002 (CMS14025) PUBLIC ENVIRONMENTAL REVIEW EXECUTIVE SUMMARY NOVEMBER 2015
EXTENSION TO THE WILUNA URANIUM PROJECT ASSESSMENT NO: 2002 (CMS14025) PUBLIC ENVIRONMENTAL REVIEW EXECUTIVE SUMMARY NOVEMBER 2015 Toro Energy Limited ABN 48 117 127 590 Level 3, 33 Richardson Street,
More informationIn-Pit Tailing Storage Facility Management Plan
J.1 In-Pit Tailing Storage Facility Management Plan IN-PIT TAILINGS STORAGE FACILITY MANAGEMENT PLAN New Acland Coal Mine Stage 3 Project JANUARY 2014 Contents 1. Introduction 2 1.1. Overview 2 1.2. Purpose
More informationAnglesea Mine Revegetation Strategy Technical Study
Anglesea Mine Revegetation Strategy Technical Study Introduction Alcoa s Anglesea mine is located at Anglesea, in south western Victoria, approximately 35 kilometres from Geelong. The Anglesea Mine supplied
More informationFor personal use only
4 AUGUST 2017 TROPICANA GOLD MINE UPDATE Independence Group NL ( IGO or the Company ) (ASX: IGO) is pleased to provide a progress report on initiatives to further maximise and optimise the Tropicana Gold
More informationMINING OPERATION SERVICES
METROMIX PTY LIMITED Lower Level Management Plan Prepared in conjunction with: MINING OPERATION SERVICES SEPTEMBER 2016 CONTENTS Page COMMONLY USED ACRONYMS... 4 1 INTRODUCTION... 5 2 APPROVED ACTIVITIES...
More informationGUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK
PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the
More informationATTACHMENT 5 AQUIFER INTERFERENCE POLICY AND WATER LICENSING ADDENDUM
ATTACHMENT 5 AQUIFER INTERFERENCE POLICY AND WATER LICENSING ADDENDUM COWAL GOLD MINE EXTENSION MODIFICATION TABLE OF CONTENTS A5 AQUIFER INTERFERENCE POLICY CONSIDERATIONS AND WATER LICENSING ADDENDUM
More information1 Introduction 1-1. Project Need and Objectives
Introduction 1 CONTENTS 1 Introduction 1-1 1.1 1.1 Introduction Introduction 1-1 1-1 1.2 1.2 Project Overview Project Overview 1-1 1-1 1.3 1.3 Project Site Project Site 1-1 1-1 1.4 1.4 The Proponent The
More informationleft over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or
14. Waste Management 14.1. Waste Management Regulations The regulatory requirements governing waste management are provided within the EP Act, the EPR and associated Environmental Protection (Waste Management)
More informationCOMMUNITY OVERVIEW MARCH Overburden Management Project Environmental Impact Statement (EIS)
COMMUNITY OVERVIEW MARCH 2017 Overburden Management Project Environmental Impact Statement (EIS) About McArthur River Mine McArthur River Mining Pty Ltd (MRM) is wholly owned by Glencore and is the operator
More informationBROCKMAN RESOURCES LTD. MARILLANA IRON ORE PROPOSAL EPA ASSESSMENT No OFFSET PLAN
BROCKMAN RESOURCES LTD MARILLANA IRON ORE PROPOSAL EPA ASSESSMENT No. 1781 OFFSET PLAN October 2010 This page has been left blank intentionally Brockman Resources Limited Document Status Rev Author Reviewer/s
More information3. MINING SYSTEM AND RESOURCE RECOVERY
3. MINING SYSTEM AND RESOURCE RECOVERY (SMP Guideline Section 6.1) 3.1. MINING METHOD Longwalls 705 to 710 will be extracted using a longwall retreating system of mining, an established method of coal
More informationAmulsar Gold Mine Project Environmental and Social Impact Assessment, Chapter 6 6 CONTENTS
6 CONTENTS 6.17 CULTURAL HERITAGE... 6.17.2 6.17.1 Project Activities Affecting Cultural Heritage... 6.17.2 6.17.2 Impact Prediction Methodology... 6.17.4 6.17.3 Predicted Magnitude of Potential Impacts...
More informationSection 3. Legislative Framework and Impact Assessment Process
Section 3 Legislative Framework and Impact Assessment Process 22 Cameco Australia Pty Ltd 3. Legislative Framework and Impact Assessment Process 3.1 Key Legislative Requirements The Project requires environmental
More informationDraft Guidance - Materials Characterisation Baseline Data Requirements for Mining Proposals
Submission May 2016 Draft Guidance - Materials Characterisation Baseline Data Requirements for Mining Department of Mines and Petroleum Contact Kirrillie Caldwell k.caldwell@cmewa.com The Chamber of Minerals
More information/', MINISTER FOR THE ENVIRONMENT
/', Statement No. MINISTER FOR THE ENVIRONMENT 000653 STATEMENT TO AMEND CONDITIONS APPLYING TO A PROPOSAL (PURSUANT TO THE PROVISIONS OF SECTION 46 OF THE ENVIRONMENTAL PROTECTION ACT 1986) CLAY EXCAVATION
More informationConservation and Reclamation INFORMATION LETTER. Environmental Protection Guidelines for Oil Production Sites - Revised January 2002
March 2002 Conservation and Reclamation INFORMATION LETTER C&R/IL/02-1 Environmental Protection Guidelines for Oil Production Sites - Revised January 2002 CHANGES TO THE INFORMATION LETTER This Information
More informationBOGGABRI COAL PROJECT MODIFICATION ENVIRONMENTAL ASSESSMENT
BOGGABRI COAL PROJECT MODIFICATION ENVIRONMENTAL ASSESSMENT PREPARED FOR BOGGABRI COAL PTY LIMITED JULY 2013 Project No. WHC-12-08 Document No. 00532603.doc TABLE OF CONTENTS EXECUTIVE SUMMARY ES-1 1 INTRODUCTION
More informationATTACHMENT 2. Aquifer Interference Policy Considerations and Water Licensing COWAL GOLD OPERATIONS MINE LIFE MODIFICATION
ATTACHMENT 2 Aquifer Interference Policy Considerations and Water Licensing COWAL GOLD OPERATIONS MINE LIFE MODIFICATION Environmental Assessment 2016 TABLE OF CONTENTS A2 AQUIFER INTERFERENCE POLICY CONSIDERATIONS
More informationScope of Works Mount Dove Artificial Quoll Habitat PRJ EN-SOW-0001
Scope of Works Mount Dove Artificial Quoll Habitat PRJ0004-128-800-EN-SOW-0001 Revision 0 This document is the property of Atlas Iron Limited and must not be copied, reproduced, or passed onto any other
More informationGUIDELINES to the MINING ACT
GUIDELINES to the MINING ACT PART I Format Requirements Reports 1. All reports required to be submitted to the minister by the Mining Act or regulations shall (a) be bound in a folder; (b) be a typewritten
More information8. Greenhouse Gas Emissions
8. Greenhouse Gas Emissions This section provides a summary of the greenhouse gas assessment undertaken, and the potential impacts identified, in regards to the Project (Mine) during construction and operation.
More informationDraft Mine Closure Plan. 17 October 2018 Longlac & Geraldton
Draft Mine Closure Plan 17 October 2018 Longlac & Geraldton Project Update Federal EA Decision report was issued on October 1 st and Provincial Report is expected to be issued Oct 22 nd Federal approval
More informationFor personal use only
ACN. 000 317 251 MARKET RELEASE 4 th March 2013 ROCKLANDS COPPER PROJECT (CDU 100%) DEVELOPMENT UPDATE PICTORIAL UPDATE 10 Development of the Rocklands Group Copper Project, located just outside the major
More informationFormat and Guideline for the Preparation of an Annual Environmental Management Report: SMALL MINE VERSION
Environmental Management Guidelines for Industry Format and Guideline for the Preparation of an Annual Environmental Management Report: SMALL MINE VERSION This form may be used as an alternative to the
More informationEnvironmental Impact Statement for the Slave Falls Tramway Conversion Project
Environmental Impact Statement for the Slave Falls Tramway Conversion Project Prepared for Submitted by 41844.101 March 2008 ENVIRONMENTAL IMPACT STATEMENT FOR THE SLAVE FALLS TRAMWAY CONVERSION PROJECT
More informationANNUAL NOISE MONITORING REPORT. Environmental Protection (Fimiston Gold Mine Noise Emissions) Approval 2016
ANNUAL NOISE MONITORING REPORT Environmental Protection (Fimiston Gold Mine Noise Emissions) Approval 2016 22 March 2016 21 March 2017 1 PURPOSE OF DOCUMENT... 3 2 SUMMARY OF KCGM OPERATIONS... 4 3 NOISE
More informationDOORNVALLEI EXT 5 & 6
DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED
More informationPOLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)
Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,
More informationRehabilitation Management
Rehabilitation Management Andrea Sutton Chief Executive 27 August 2015 www.energyres.com.au Forward-looking statements This presentation has been prepared by Energy Resources of Australia Ltd ( ERA ) and
More informationASX ANNOUNCEMENT. Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA. Mt Stuart Joint Venture MAIDEN ORE RESERVE STATEMENT
ABN 46 006 045 790 14 th December 2010 ASX ANNOUNCEMENT Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA Cullen Resources Limited (ASX:CUL) (Cullen) is pleased to report the maiden JORC
More informationDendrobium Mine. Waste Management Plan
Dendrobium Mine Waste Management Plan DOCUMENT SIGN OFF SHEET AND REVISION LOG Document Owner: Authorised by: Peter McMillan 25/06/2018 (Name) (Date) Peter McMillan 25/06/2018 (Name) (Date) VERSION HISTORY
More informationMuskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1
Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Updated: November 2010 Directive 74 Appendix C Requirement Approval: 8512D Submitted to SHELL CANADA ENERGY MRM DDA PLAN-UPDATE NOV
More informationBEST PRACTICE GUIDELINE G1 STORMWATER MANAGEMENT
BEST PRACTICE GUIDELINE G1 STORMWATER MANAGEMENT William Pulles Structure of BPG G1 Chapter 1 Introduction to guideline Chapter 2 - The principles and objectives to be incorporated in the storm water management
More informationLeighton Asia, India and Offshore. Mining
Leighton Asia, India and Offshore Mining Optimising mine productivity responsibly through planning excellence, a focused and performance-driven workforce and safety and environment best practices has long
More informationIMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION. Marc Johnson, Regional Manager - South America
IMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION Marc Johnson, Regional Manager - South America Abstract In Pit Crushing and Conveying (IPCC) systems have matured as a technology to the
More informationWelcome to ICN s. accessing resources seminar. David Roberts ICN National Sector Manager - Mining
Welcome to ICN s accessing resources seminar David Roberts ICN National Sector Manager - Mining 2013 FORMULA 1 ROLEX AUSTRALIAN GRAND PRIX Wednesday 13 March 2013, 1.00pm 6.30pm Agenda Overview of the
More informationFor personal use only
ABN 64 123 993 233 ASX Announcement 21 March ABN 2016 64 123 993 233 Leigh Creek Magnesite - Project Study Highlights The Study examines possible open pit mining and processing options and provides a strong
More informationGeneral Information Required to Assist Assessment of Development Proposals Involving Acid Sulfate Soils (Version 4, June 2004)
General Information Required to Assist Assessment of Development Proposals Involving Acid Sulfate Soils (Version 4, June 2004) Purpose This document contains information required by officers of the Department
More informationAnnex F Scoping Checklist
Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve
More informationOperating and Reclamation Plan
Operating and Reclamation Plan For sites in sensitive locations, additional information may be required. If more space is needed, attach additional sheets or use the blank sheet provided at the end of
More informationSANDY RIDGE FACILITY MINE CLOSURE PLAN. Final Report November 2016
Mine Closure Plan SANDY RIDGE FACILITY MINE CLOSURE PLAN Final Report November 2016 vi Document control Rev Issue date Description Originator Checked Approved 1
More informationRE: HWY 63:02 HIGHWAY EMBANKMENT REPAIR NORTH OF LABICHE RIVER BRIDGE COMPLETION REPORT
THURBER ENGINEERING LTD. Suite 200, 9636-51st Avenue EDMONTON, Alberta T6E 6A5 Phone (780) 438-1460 Fax [780) 437-7125 I \ DO THURBER February 2, 1999 File: 15-16-101 Alberta Transportation & Utilities
More informationGRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION
CHAPTER 23.105 GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION Sections 23.105.101 General... 1 23.105.102 Definitions... 1 23.105.103 Permits required... 3 23.105.104 Hazards.... 4 23.105.105 Permit
More informationResource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd
27 March 2012 Project No. 42780930 South Taranaki District Council Private Bag 902 Hawera, 4640 Attention: Blair Sutherland Dear Blair Subject: Resource Consent Application - Removal/Remediation of Flare/Blowdown
More informationA1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871
Appendix A EIS Guidelines CONTENTS A1 Australian and South Australian Government Guidelines 813 A2 South Australian Government Guidelines 871 A3 Northern Territory Government Guidelines 929 Olympic Dam
More informationClosure Planning for a Tailings Storage Facility in Western Australia
Closure Planning for a Tailings Storage Facility in Western Australia K. Bonstrom O Kane Consultants Pty. Ltd, Australia D. Chapman O Kane Consultants Inc, Canada D. Swain Perth, Australia M. O Kane O
More informationAustralia s leading magnetite producer Southdown Magnetite Project. Russell Clark Managing Director & CEO February 2012
Australia s leading magnetite producer Southdown Magnetite Project Russell Clark Managing Director & CEO February 2012 Disclaimer The material in this presentation ( material ) is not and does not constitute
More informationMarket Release Newcrest Mining 15 February 2016
Market Release Newcrest Mining 15 February 2016 Lihir Pit Optimisation Project to progress to Feasibility Study stage As previously advised, a project is being undertaken to optimise the integrated life
More information12. Environmental management
12. Environmental management 12.1 Overview This section summarises the framework for managing environmental risks associated with construction, commissioning and operation of the Project. It also includes
More informationDevelopment Approval 211/93 (as modified) Schedule Condition Commitment Audit Finding
Independent Environmental Audit Bengalla Mine Development Approval 211/93 (as modified) Schedule Condition Commitment Audit Finding 3 1 The Applicant shall ensure that the noise generated by the development
More informationAPPENDIX 8. Surface Water Management
APPENDIX 8 Surface Water Management Readymix Holdings Pty Limited Surface Water Assessment Proposed Lynwood Quarry, Marulan May 2005 Surface Water Assessment Proposed Lynwood Quarry, Marulan Table of Contents
More informationH28. Special Purpose Quarry Zone
H28. Special Purpose Quarry Zone H28.1. Zone description Mineral resources are important to Auckland s economy and development. The Special Purpose Quarry Zone provides for significant mineral extraction
More informationFlow Diversion Banks: General
Flow Diversion Banks: General DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Flow diversion
More information3.0 Existing Mine Water Management System
Existing Mine Water Management System 3.0 Existing Mine Water Management System UCML has an extensive mine water management system, which includes mine dewatering systems, water storages, the Bobadeen
More information5 JULY 2018 COMPLETION OF AUTHIER ENVIRONMENTAL STUDIES AND PERMITTING UPDATE
5 JULY 2018 COMPLETION OF AUTHIER ENVIRONMENTAL STUDIES AND PERMITTING UPDATE All major base-line environmental studies completed and no significant environmental issues identified Technical studies determined
More informationWAMBO COAL PTY LTD ENVIRONMENTAL ASSESSMENT. ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies
WAMBO COAL PTY LTD NORTH WAMBO UNDERGROUND MINE LONGWALL 10A MODIFICATION ENVIRONMENTAL ASSESSMENT ATTACHMENT 2 Relevant Environmental Planning Instruments and Government Policies A2 PLANNING FRAMEWORK
More informationEnvironmental Risk Analysis
Appendix 10 11 12 13 14 15 16 17 18 191 Groundwater Controlled UHSA Air Agricultural Historic EIS Preliminary Environmental Blasting Quality Surface Secretary s Noise Statement Aboriginal Economic Action
More informationCottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:
Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by
More informationBLOOMFIELD MINING OPERATIONS (RIX S CREEK MINE) Mine Closure Plan BLOOMFIELD GROUP PTY LTD INTEGRATED MANAGEMENT SYSTEMS
BLOOMFIELD MINING OPERATIONS (RIX S CREEK MINE) Mine Closure Plan V Date Description By Chk App er 1 22/01/12 Original Draft JH JD GB BLOOMFIELD GROUP PTY LTD INTEGRATED MANAGEMENT SYSTEMS File Name: Mine
More informationMAPPING & SOLUTIONS GUIDE. RIIENV201D Identify and assess environmental and heritage concerns
MAPPING & SOLUTIONS GUIDE RIIENV201D Identify and assess environmental and heritage concerns RIIENV201D - Identify and assess environmental and heritage concerns Mapping This Learning Guide covers the
More informationEIS TABLE OF CONTENTS
EIS TABLE OF CONTENTS GLOSSARY OF TERMS... GL-1 Glossary and Abbreviations... GL-1 Units... GL-14 EXECUTIVE SUMMARY... ES-1 INTRODUCTION... ES-1 PROJECT PROPONENTS... ES-1 LOCATION... ES-1 PROJECT DESCRIPTION...
More information