Behind-the-Meter Generation Project Rules

Size: px
Start display at page:

Download "Behind-the-Meter Generation Project Rules"

Transcription

1 Behind-the-Meter Generation Project Rules 1 Purpose of these Rules The purpose of these Rules is to set out the parameters for eligible behind-the-meter generation (BMG) projects that may be accepted into conservation programs. BMG projects are subject to these Rules and the Program Rules for the Program under which an application for a BMG project is being made. These Rules will prevail in the event of any inconsistency between these Rules and the applicable Program Rules. Please refer to the Eligible Behind-the-Meter Generation Projects Approval Guideline for information on the review and approval process for eligible BMG projects. The following types of BMG projects may be eligible under Programs pursuant to the Energy Conservation Agreement: (a) Waste Energy Recovery ( WER ) projects; and (b) Conservation Combined Heat and Power ( CCHP ) projects. 2 Program Offer / Participant Incentives 2.1 Standard (Provincially Consistent) Incentives The Participant Incentive for a BMG project is subject to the Participant Incentive under the applicable Program Rules. For CCHP projects, the Participant Incentive will be the lower of 40% of the eligible costs of the BMG project or the amount of the Participant Incentive as set out under the applicable Program Rules. 3 Eligibility Criteria 3.1 Participant Eligibility In addition to any criteria set out in the applicable Program Rules, the Participant must be a Distribution Consumer and not insolvent. Page 1 of 5

2 3.2 Facility Eligibility In addition to any criteria set out in the applicable Program Rules, the Participant s proposed BMG project must be connected to the LDC s Distribution System, unless otherwise approved by the LDC. Should the Participant elect to connect to the LDC s Distribution System at a later date, they must contact their LDC and adhere to all applicable procedures for connecting generators to the LDC s Distribution System. 3.3 Project Eligibility In addition to any criteria set out in the applicable Program Rules, a proposed Behind-the-Meter Facility must: (a) have a Gross Nameplate Capacity of less than 10MW; (b) not be used for the sole purpose of reducing electricity demand during the five critical system-peak hours; (c) in the case of a WER project, demonstrate that natural gas or propane purchased from or otherwise supplied by a third party to the Participant does not exceed 10% of the Fuel Energy Input; (d) in the case of a CCHP project, meet the following additional criteria: (i) use natural gas or propane as its sole fuel, unless otherwise approved in writing by the IESO; (ii) be designed and operated in a manner that the CCHP project achieves a minimum annual Total System Efficiency of 65%; and (iii)not use the thermal output from the CCHP project to generate electricity; (e) not be the subject of, or have been the subject of, a physical or financial power or capacity purchase contract relating to the generation of electricity by such proposed facility (in whole or in part), or other form of contract relating to electricity relating to such proposed facility with the IESO, the Ontario Electricity Financial Corporation or the Government of Ontario or any other agency of the Government of Ontario; and (f) not be split across multiple applications for the purpose of circumventing the 10 MW limit on Gross Nameplate Capacity. Page 2 of 5

3 4 Participant Agreement In addition to any criteria set out in the applicable Program Rules, the Participant Agreement for a BMG project will include the terms and conditions specified in the Energy Conservation Agreement and will include the following: (a) The Participant shall not directly or indirectly assign, transfer, sell or supply electricity it generates from a BMG project into the IESO-Controlled Grid; (b) The Participant shall not use a BMG project at any time during the term of the Participant Agreement for the primary purpose of reducing electricity demand during the five critical system-peak hours; (c) The Participant shall be a Distribution Consumer at all times during the term of the Participant Agreement; (d) The Participant s facility shall be connected to the Distribution System at all times during the term of the Participant Agreement; and (e) The Participant Agreement will include any other provision required to give effect to these Behind-the Meter Generation Project Rules. 5 QA/QC and Project M&V Minimum Requirements Minimum requirements for quality assurance/quality control and Project measurement and verification are subject to the Energy Conservation Agreement and the applicable Program Rules. 6 Minimum Record-Keeping Requirements Minimum record-keeping requirements are subject to the Energy Conservation Agreement and the applicable Program Rules. At a minimum, the LDC shall retain any the confirmation obtained in accordance with the Eligible Behind-the-Meter Generation Projects Approval Guideline that capacity is available for the proposed BMG project. 7 Other In addition to any other requirements under the Energy Conservation Agreement and the applicable Program Rules, the LDC will: Page 3 of 5

4 (a) confirm that the BMG project is able to connect to the Distribution System before accepting the proposed Participant s application; (b) provide any requested information to the IESO or the Technical Reviewer that is reasonably required for the IESO or the Technical Reviewer to conduct its review of the BMG project; and (c) not approve an application for a BMG project where the LDC determines that capacity for such BMG project is not available. In addition to any other requirements under the Energy Conservation Agreement and the applicable Program Rules, the IESO will review and confirm if capacity is available for CCHP projects. 8 Definitions In addition to terms that are defined in the Energy Conservation Agreement and the applicable Program Rules, the following terms have the meaning stated below when used in these Rules: Conservation Combined Heat and Power or CCHP means the simultaneous production of electrical and thermal energy where both forms of energy are productively and efficiently used within the Facility and/or its processes. Distribution System means a system connected to the IESO-Controlled Grid for distributing electricity at voltages of 50 kv or less and includes any structures, equipment or other thing used for that purpose. Electricity Output means the gross annual electricity generated from the WER or CCHP system in MWh. Eligible Fuel Source means natural gas or propane. Fuel Energy Input means the total thermal energy (expressed in MWh-thermal) required to produce the Thermal and Electricity Output as determined annually on an HHV basis. Gross Nameplate Capacity means the manufacturer s total installed rated capacity of the generating equipment to generate electricity. Higher Heating Value or HHV means the amount of heat produced by the complete combustion of a unit quantity of fuel. IESO-Controlled Grid has the meaning given to it in the IESO Market Rules. Page 4 of 5

5 IESO Market Rules means the rules made under Section 32 of the Electricity Act, 1998 (Ontario), together with all market manuals, policies, and guidelines issued by the IESO or its successor. Total System Efficiency shall be calculated on an annual basis as the sum of (the Electricity Output (MWh) plus the Useful Thermal Output (MWh-thermal) of the CCHP) divided by the Fuel Energy Input (MWh-thermal). Useful Thermal Output means thermal energy (expressed in MWh-thermal) produced by the BMG project and used for a gainful commercial or industrial purpose where such use avoids or reduces the use of fuel to produce thermal energy in an alternate process within the Facility. Waste Energy Recovery or WER means the generation of electricity primarily from heat or fuel that is a waste by-product of the Facility. Page 5 of 5

BEHIND THE METER GENERATION. Presenter: Name MONTH ##, 2017 Kia Barkhordari, MBA, P.Eng., CEM, CMVP CDM, Industrial Programs Lead Feb 21, 2018

BEHIND THE METER GENERATION. Presenter: Name MONTH ##, 2017 Kia Barkhordari, MBA, P.Eng., CEM, CMVP CDM, Industrial Programs Lead Feb 21, 2018 BEHIND THE METER GENERATION Presenter: Name MONTH ##, 2017 Kia Barkhordari, MBA, P.Eng., CEM, CMVP CDM, Industrial Programs Lead Feb 21, 2018 NOTE TO READER Please note the following slides are for your

More information

Distributed Generation in the Ontario Regulatory Context

Distributed Generation in the Ontario Regulatory Context Distributed Generation in the Ontario Regulatory Context Distributed Generation and the Future of Ontario 's Electricity Grid October 27, 2008 James C. Sidlofsky Partner, Borden Ladner Gervais LLP Chair,

More information

CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS

CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS Ontario Energy Board Commission de l énergie de l Ontario CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS Issued: September 16, 2010 Table of Contents 1. GENERAL AND ADMINISTRATIVE

More information

Conservation First Framework LDC Tool Kit Final v2.1 July 1, 2017

Conservation First Framework LDC Tool Kit Final v2.1 July 1, 2017 Program Name: Save on Energy Heating and Cooling Program 1. Program Description The Heating and Cooling Program encourages individuals and businesses to replace or retrofit existing heating and cooling

More information

Benefits from Generation and Storage on the Distribution System

Benefits from Generation and Storage on the Distribution System Benefits from Generation and Storage on the Distribution System Andrew Levitt Senior Market Strategist Emerging Markets Special MRC Meeting DER Aug 24, 2016 Generation/Storage Resource Location and Types

More information

Toronto Hydro CHP Event CDM Program Considerations & Participant Agreements

Toronto Hydro CHP Event CDM Program Considerations & Participant Agreements CHP Event CDM Program Considerations & Participant Agreements Justin MacDonald, CDM Project Consultant March 8, 2017 Agenda Topic CHP Project Incentive Funding Example Discussion Walkthrough of example

More information

Conservation Behind the Meter Generation Potential Study

Conservation Behind the Meter Generation Potential Study Conservation Behind the Meter Generation Potential Study Potential Analysis Report Prepared for: Independent Electricity System Operator (IESO) 120 Adelaide Street West, Suite 1600 Toronto, ON M5H 1T1,

More information

Greater Ottawa Region Local Advisory Committee Meeting #5. June 21, 2016

Greater Ottawa Region Local Advisory Committee Meeting #5. June 21, 2016 Greater Ottawa Region Local Advisory Committee Meeting #5 June 21, 2016 Presentation Outline Ottawa Regional Planning Road Map Planning for Future LAC Meetings West Ottawa Needs and Options 2 WHERE WE

More information

CFT REFERENCE DOCUMENT CFT GLOSSARY

CFT REFERENCE DOCUMENT CFT GLOSSARY CFT REFERENCE DOCUMENT CFT GLOSSARY All references to section numbers are to sections of the CFT document, not the CFT Forms, CFT Reference Documents, or EPA, unless otherwise expressly stated. 1. Addendum

More information

Senate Bill No. 145 Senator Spearman

Senate Bill No. 145 Senator Spearman Senate Bill No. 145 Senator Spearman CHAPTER... AN ACT relating to energy; establishing as part of the Solar Energy Systems Incentive Program a program for the payment of incentives for the installation

More information

CFT REFERENCE DOCUMENT CFT GLOSSARY

CFT REFERENCE DOCUMENT CFT GLOSSARY CFT REFERENCE DOCUMENT CFT GLOSSARY All references to section numbers are to sections of the CFT document, not the CFT Forms, CFT Reference Documents, or EPA, unless otherwise expressly stated. 1. Addendum

More information

BULLETIN. DATE ISSUED: October 18, 2018

BULLETIN. DATE ISSUED: October 18, 2018 Ontario Energy Board Commission de l énergie de l Ontario P.O. Box 2319 C.P. 2319 2300 Yonge Street 2300, rue Yonge 27 th Floor 27 e étage Toronto ON M4P 1E4 Toronto ON M4P 1E4 Telephone: 416-481-1967

More information

(Draft Captive and Renewable Energy Generating Plants) Regulations

(Draft Captive and Renewable Energy Generating Plants) Regulations 307 Sl. No. UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Description (Draft Captive and ) Regulations - 2014 1. Short title, extent and commencement. 2. Scope and extent of application Summary (i) Uttar

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201 TARIFF FOR WHOLESALE TRANSMISSION SERVICE 1900 North Akard Dallas, Texas 75201 Applicability: Entire System Sheet No. 1 Effective Date: May 25, 2018 Revision: 17 Availability Wholesale Transmission Service

More information

BRONTE SUB-REGION INTEGRATED REGIONAL RESOURCE PLAN - APPENDICES. Part of the Burlington-Nanticoke Planning Region June 30, 2016

BRONTE SUB-REGION INTEGRATED REGIONAL RESOURCE PLAN - APPENDICES. Part of the Burlington-Nanticoke Planning Region June 30, 2016 BRONTE SUB-REGION INTEGRATED REGIONAL RESOURCE PLAN - APPENDICES Part of the Burlington-Nanticoke Planning Region June 30, 2016 Bronte Sub-region IRRP Appendix A: Demand Forecast Appendix A: Demand Forecast

More information

MidAmerican Energy Company Original Sheet No. 1 FERC Electric Tariff, Original Volume No. 10 (Supersedes Third Revised Volume No.

MidAmerican Energy Company Original Sheet No. 1 FERC Electric Tariff, Original Volume No. 10 (Supersedes Third Revised Volume No. MidAmerican Energy Company Original Sheet No. 1 MIDAMERICAN ENERGY COMPANY SERVICES TARIFF Communications concerning this tariff may be sent to: Dehn Stevens Manager Transmission Services MidAmerican Energy

More information

(2) isolated operation with standby service provided by the Company by means of a doublethrow

(2) isolated operation with standby service provided by the Company by means of a doublethrow P.S.C. NO. 3 ELECTRICITY LEAF: 370 INITIAL EFFECTIVE DATE: April 1, 2012 SERVICE CLASSIFICATION NO. 25 APPLICABLE TO USE OF SERVICE FOR: Sales and delivery of electric power supply provided by the Company,

More information

Appendix 5B. Statement of Compliance Registry Criteria

Appendix 5B. Statement of Compliance Registry Criteria Appendix 5B Statement of Compliance Registry Criteria Revision 5.1 Effective: July 1, 2014 (as noted below) The highlighted terms Bulk Electric System and Load in this document will become effective as

More information

9.1 Applicability. 9-1 Cogeneration. December 2008

9.1 Applicability. 9-1 Cogeneration. December 2008 CHAPTR 9: COGNRATION FACILITIS (Guidance for Regulation Section 95112) Operators of cogeneration facilities have sector-specific reporting obligations specified in section 95112 of the mandatory greenhouse

More information

The Vermont Statutes Online

The Vermont Statutes Online VERMONT GENERAL ASSEMBLY The Vermont Statutes Online Title 30: Public Service Chapter 89: Renewable Energy Programs Subchapter 1: General Provisions 8001. Renewable energy goals (a) The General Assembly

More information

Statement of Compliance Registry Criteria (Revision 3.1)

Statement of Compliance Registry Criteria (Revision 3.1) Statement of Compliance Registry Criteria (Revision 3.1) Summary Since becoming the Electric Reliability Organization (ERO), NERC has initiated a program to identify candidate organizations for its compliance

More information

Energy Use in Ontario

Energy Use in Ontario Every Joule Counts - Ontario s Energy Use and Conservation Year in Review Chapter Energy Use in Ontario Contents Abstract....17.1 Overall Energy Use Changes...18. Fuel-by-Fuel Use Changes...0..1 Transportation

More information

Thunder Bay Sub-Region Local Advisory Committee Introductory Meeting. November 26, 2015

Thunder Bay Sub-Region Local Advisory Committee Introductory Meeting. November 26, 2015 Thunder Bay Sub-Region Local Advisory Committee Introductory Meeting November 26, 2015 Presentation Outline Role of the Local Advisory Committee Regional Electricity Planning Process Electricity Planning

More information

Energy Storage Buildings-to- Grid Applications

Energy Storage Buildings-to- Grid Applications Energy Storage Buildings-to- Grid Applications Ben Falber NYSERDA Energy Storage Program March 14 th Capture the Energy 2019 2 Advanced Energy Storage Deployed Approximately 20 MW of chemical, 20 MW of

More information

Project Measurement and Verification Procedures

Project Measurement and Verification Procedures Project and Verification Procedures 1) Introduction The objective of measurement and verification (M&V) activities at the Project level is to confirm that the Measures that are supported by the Retrofit

More information

SCHEDULE 6A Black Start Service

SCHEDULE 6A Black Start Service SCHEDULE 6A Black Start Service References to section numbers in this Schedule 6A refer to sections of this Schedule 6A, unless otherwise specified. To ensure the reliable restoration following a shut

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND ORDER EB Commission de l énergie de l Ontario DECISION AND ORDER In the matter of regulatory charges effective January 1, 2019, for the Wholesale Market Services rate and the Rural or Remote Electricity Rate Protection

More information

Market Rule Amendment Proposal

Market Rule Amendment Proposal Market Rule Amendment Proposal PART 1 MARKET RULE INFORMATION Identification No.: MR-00381 Subject: Renewable Integration Initiative Title: Floor Prices for Variable and Nuclear Generation Nature of Proposal:

More information

GLOSSARY OF TERMS January 2017

GLOSSARY OF TERMS January 2017 GLOSSARY OF TERMS January 2017 ENERGY EFFICIENCY GLOSSARY Advanced Meter Any new or appropriately retrofitted meter that functions as part of an advanced metering system and that has the features specified

More information

'^E y^s THROUGH: Jason Eisdorferand JP Batmale

'^E y^s THROUGH: Jason Eisdorferand JP Batmale PUBLIC UTILITY COMIVHSSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: December 18, 2018 ITEM NO. RIVH REGULAR X CONSENT EFFECTIVE DATE Upon Approval DATE: TO: Public Ujiiity Commission FROM: Seth^Wiggin^,

More information

Part 1 Introduction and Overview

Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Application for Customer Generation Cost Responsibility Surcharge (CRS) Tariff Exemptions (Application) is for the purpose of requesting an exemption

More information

Requirements for Real and Reactive Power Testing

Requirements for Real and Reactive Power Testing Requirements for Real and Reactive Power Testing Kathy Whitaker Manager, Auxiliary Market Operations New York Independent System Operator Reliability Rules Subcommittee Meeting New York State Reliability

More information

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid ONTARIO ENERGY REPORT Q3 Y T ELECTRICITY Electricity Highlights Third Quarter Electricity Generation Output by Fuel Type (Q3) Nuclear Ontario Peak Demand (Q3) 21,363 MW 25.0 TWh 65.7% Hydro 8.8 TWh 23.1%

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The

More information

Green Energy and Green Economy Act. Changes to Ontario s Electricity Sector

Green Energy and Green Economy Act. Changes to Ontario s Electricity Sector Green Energy and Green Economy Act Changes to Ontario s Electricity Sector What the GEGEA represents Ontario s Legislature passed the Act on May 14, 2009. Intended to attract new investment, create new

More information

CONSERVATION FRAMEWORK MID-TERM REVIEW

CONSERVATION FRAMEWORK MID-TERM REVIEW CONSERVATION FRAMEWORK MID-TERM REVIEW DRAFT PROJECT PLAN FEBRUARY 23, 2017 1 / 2016 NAVIGANT CONSULTING LTD. ALL RIGHTS RESERVED DISCLAIMER This report was prepared by Navigant Consulting Ltd. (Navigant)

More information

Total Market Demand Wed Aug 08 Thu Aug 09 Fri Aug 10 Sat Aug 11 Sun Aug 12 Mon Aug 13 Tue Aug 14

Total Market Demand Wed Aug 08 Thu Aug 09 Fri Aug 10 Sat Aug 11 Sun Aug 12 Mon Aug 13 Tue Aug 14 MW This report provides a summary of key market data from the IESO-administered markets. It is intended to provide a quick reference for all market stakeholders. It is composed of two sections: Section

More information

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES PECO is offering cash incentives for qualified Combined Heat and Power (CHP) technology projects 1 to encourage the development of projects that improve

More information

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh) For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold

More information

SCHEDULE 8 Non-Firm Point-To-Point Transmission Service

SCHEDULE 8 Non-Firm Point-To-Point Transmission Service SCHEDULE 8 Non-Firm Point-To-Point Transmission Service 1) The Transmission Customer shall pay for Non-Firm Point-To-Point Transmission Service up to the sum of the applicable charges set forth below for

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

Demand Response Availability Data Systems Definitions

Demand Response Availability Data Systems Definitions Demand Response Availability Data Systems Definitions August 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents Table of

More information

Managing Energy Use and Cost with Integrated Metering

Managing Energy Use and Cost with Integrated Metering Managing Energy Use and Cost with Integrated Metering Regional Municipality of Durham October 29, 2015 Joe Green P.Eng, CEM Overview Duffin Creek WPCP Jointly owned by York and Durham Regions Capacity

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

Regulated Price Plan. Manual

Regulated Price Plan. Manual Regulated Price Plan Manual Ontario Energy Board Issued February 16, 2016 (Replacing version issued on November 5, 2013) NOTE TO READERS: The February 16, 2016 revisions update the time of use pricing

More information

NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS

NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS PREPARED BY: AEMO Markets and Strategy & Innovation VERSION: 2.2 EFFECTIVE DATE: 20 March 2018 STATUS: FINAL

More information

RATE DS-4 LARGE GENERAL DELIVERY SERVICE

RATE DS-4 LARGE GENERAL DELIVERY SERVICE d/b/a Ameren Illinois 5 th Revised Sheet No. 14 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 14) AVAILABILITY Service under this Rate is available for any eligible non-residential

More information

SCHEDULE COGEN/SPP (Cogeneration and/or Small Power Production)

SCHEDULE COGEN/SPP (Cogeneration and/or Small Power Production) Ohio Power Rate Zone 2 nd Revised Sheet No. 226-1 Cancels 1 st Revised Sheet No. 226-1 Availability of Service This schedule is available to customers with cogeneration and/or small power production (COGEN/SPP)

More information

MODULE 3: Conservation and Demand Response Outlook. August 2016

MODULE 3: Conservation and Demand Response Outlook. August 2016 MODULE 3: Conservation and Demand Response Outlook August 2016 Summary In 2015, conservation is estimated to have contributed nearly 13 TWh of energy reductions Conservation savings come from energy efficiency

More information

Relevant changes will be made to corresponding sections of OA and RAA.

Relevant changes will be made to corresponding sections of OA and RAA. PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010

More information

Energy Performance Program Customer Presentation

Energy Performance Program Customer Presentation Energy Performance Program Customer Presentation Ali Hoss, PhD, P.Eng, CEM, CMVP Business Manager, Conservation & Corporate Relations Independent Electricity System Operator (IESO) March 2017 Agenda Why

More information

Setting the Stage for Renewable Energy in Ontario: the Renewable Energy Standard Offer Program (RESOP) and other OPA Initiatives For Sustainable

Setting the Stage for Renewable Energy in Ontario: the Renewable Energy Standard Offer Program (RESOP) and other OPA Initiatives For Sustainable Setting the Stage for Renewable Energy in Ontario: the Renewable Energy Standard Offer Program (RESOP) and other OPA Initiatives For Sustainable Development in Communities (Nov. 26/07) By Kevin Devitt,

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B;

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B; Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, Schedule B; AND IN THE MATTER OF an application by Hydro One Networks Inc.

More information

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C O - O P C I T Y - R I V E R B A Y

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C O - O P C I T Y - R I V E R B A Y NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C O - O P C I T Y - R I V E R B A Y October 9, 2013 Co-op City - Riverbay Coop City - Riverbay DISCLAIMER OF WARRANTY Information

More information

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Statement of Compliance Registry Criteria (Revision 5.2) Summary This document describes how the North American

More information

WASHINGTON ELECTRIC COOPERATIVE 2018 ANNUAL PLAN FOR TIER III COMPLIANCE

WASHINGTON ELECTRIC COOPERATIVE 2018 ANNUAL PLAN FOR TIER III COMPLIANCE WASHINGTON ELECTRIC COOPERATIVE 2018 ANNUAL PLAN FOR TIER III COMPLIANCE WITH VERMONT S RENEWABLE ENERGY STANDARD I. INTRODUCTION In compliance with requirements from the Vermont Public Utility Commission

More information

1. Program Description

1. Program Description Program Name: Save on Energy - Instant Discount Program 1. Program Description The Save on Energy - Instant Discount Program (the ID Program ) encourages households to reduce their energy use by offering

More information

CHAPTER THREE. Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve.

CHAPTER THREE. Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve. CHAPTER THREE Load Curves The curve showing the variation of load on the power station (power plant) with reference to time is known as load curve. Daily Load Curve Maximum Load (Peak Load) It represents

More information

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 1. ELIGIBILITY FOR SERVICE RETAIL WHEELING SERVICE All Special Contract Customers, and all Schedule 48 Customers as of March 9, 2001,

More information

NPCC 2017 Ontario Interim Review of Resource Adequacy

NPCC 2017 Ontario Interim Review of Resource Adequacy NPCC 2017 Ontario Interim Review FOR THE PERIOD FROM 2018 TO 2020 APPROVED BY THE RCC ON DECEMBER 5, 2017 This page intentionally left blank. ii Document Change History Issue Reason for Issue Date 1.0

More information

Lansing Board of Water & Light Renewable Energy Plan Annual Report for 2011 MPSC Case No. U-16619

Lansing Board of Water & Light Renewable Energy Plan Annual Report for 2011 MPSC Case No. U-16619 Lansing Board of Water & Light Renewable Energy Plan Annual Report for 2011 MPSC Case No. U-16619 SECTION 1: PA 295 SECTION 51 SUBSECTIONS 1-3 REQUIREMENTS Section 51. (1) By a time determined by the commission,

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared

More information

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 Prepared by System Planning Department PJM 2017 Table of Contents Table of Contents

More information

Revised Cal. P.U.C. Sheet No E Cancelling Revised Cal. P.U.C. Sheet No E

Revised Cal. P.U.C. Sheet No E Cancelling Revised Cal. P.U.C. Sheet No E Revised Cal. P.U.C. Sheet No. 40911-E Cancelling Revised Cal. P.U.C. Sheet No. 40581-E ELECTRC SCHEDULE TBCC Sheet 1 TRANSTONAL BUNDLED COMMODTY COST APPLCABLTY: TERRTORY: RATES: This schedule applies

More information

Concepts for Behind-the- Meter Net Generation

Concepts for Behind-the- Meter Net Generation Concepts for Behind-the- Meter Net Generation Pradip Ganesan Donna Pratt New York Independent System Operator Joint Meeting of Installed Capacity, Market Issues and Price Responsive Load Working Groups

More information

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity

More information

Comments on Treatment of Combined Heat and Power in EPA s Proposed Clean Power Plan Rule Docket ID No. EPA-HQ-OAR

Comments on Treatment of Combined Heat and Power in EPA s Proposed Clean Power Plan Rule Docket ID No. EPA-HQ-OAR Background Comments on Treatment of Combined Heat and Power in EPA s Proposed Clean Power Plan Rule Docket ID No. EPA-HQ-OAR-2013-0602 Southwest Energy Efficiency Project (SWEEP) Nov. 28, 2014 Combined

More information

Combined Heat and Power Catalog

Combined Heat and Power Catalog Combined Heat and Power Catalog CHP Program PON 2568 Attachment C New York State Energy Research and Development Authority CHP Program CHP Catalog (PON 2568 Attachment C) Revision History Version 1.0 December

More information

Ontario Energy Board

Ontario Energy Board Ontario Energy Board Standard Supply Service Code for Electricity Distributors Revised (Replacing version issued on October 8, 2015) Table of Contents 1. GENERAL AND ADMINISTRATIVE PROVISIONS 1.1 PURPOSE

More information

MPSC Staff s Avoided Cost Methodology Case No.: U Capacity Component of Staff's Proposed Method

MPSC Staff s Avoided Cost Methodology Case No.: U Capacity Component of Staff's Proposed Method MPSC Staff s Avoided Cost Methodology Case No.: U-18090 Capacity Component of Staff's Proposed Method Exhibit: S-14 (JJH-8) Levelized Cost Calculation Simple Cycle Gas Turbine Page: 1 of 2 CT CT No Variable

More information

CUSTOMER FACILITY INFORMATION

CUSTOMER FACILITY INFORMATION This Project Information Form provides a template to collect project systems and equipment information and specifications. In addition, this form serves as a general overview of eligibility criteria for

More information

University System of New Hampshire, Durham UNH CHP Plant Application for New Hampshire State Certification as Class I Resource

University System of New Hampshire, Durham UNH CHP Plant Application for New Hampshire State Certification as Class I Resource University System of New Hampshire, Durham UNH CHP Plant Application for New Hampshire State Certification as Class I Resource Puc 2505.02 Application Requirements. (a) To qualify as a facility eligible

More information

GUIDE. Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria PUBLIC

GUIDE. Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria PUBLIC PUBLIC IESO_GDE_0364 GUIDE Market Manual 11: Reliability Compliance Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria Issue 6.0 Public Disclaimer The posting

More information

Incentives. After work is complete:

Incentives. After work is complete: SAVE your WAY Create your own Energy Demand Savings with OUC s Commercial & Industrial Custom Incentive Program Overview OUC is committed to helping your business become more energy efficient. We understand

More information

PURPOSE SECTION I: TERMS

PURPOSE SECTION I: TERMS ATTACHMENT M-2 (FirstEnergy Zones) FirstEnergy Procedure for Determining a Load Serving Entity s Peak Load Contribution (PLC) and Network Service Peak Load (NSPL) PURPOSE The purpose of this Attachment

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid And Self-Schedule Submission For All CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

Demand Response Marketplace and DR programs in Ontario

Demand Response Marketplace and DR programs in Ontario Demand Response Marketplace and DR programs in Ontario Demand-Response-Shop.com Collaboration Project with Sheridan College-Building Intelligence Quotient- RFQ Strategies partially funded by Ontario Centres

More information

BTM:NG Initiative Energy Market Design Concepts

BTM:NG Initiative Energy Market Design Concepts BTM:NG Initiative Energy Market Design Concepts Pradip Ganesan Market Product Specialist, Energy Market Design New York Independent System Operator MIWG January 29, 2015 Rensselaer, NY 2014 New York Independent

More information

HYDROELECTRIC INCENTIVE MECHANISM AND SURPLUS BASELOAD GENERATION

HYDROELECTRIC INCENTIVE MECHANISM AND SURPLUS BASELOAD GENERATION Filed: 0-0- EB-0-0 Exhibit E Tab Schedule Page of 0 0 HYDROELECTRIC INCENTIVE MECHANISM AND SURPLUS BASELOAD GENERATION.0 PURPOSE This evidence describes OPG s proposed treatment of Surplus Baseload Generation

More information

1 The Needs Screening Report for the GTA East Region can be found at:

1 The Needs Screening Report for the GTA East Region can be found at: Scoping Assessment Outcome Report Region: GTA East Start Date: September 9, 2014 End Date: December 15, 2014 1. Introduction This Scoping Assessment Outcome Report is part of the Ontario Energy Board s

More information

ATTACHMENT M-1 (FirstEnergy Zones) FirstEnergy Procedure for Determining a Load Serving Entity s Hourly Energy Obligations

ATTACHMENT M-1 (FirstEnergy Zones) FirstEnergy Procedure for Determining a Load Serving Entity s Hourly Energy Obligations Purpose ATTACHMENT M-1 (FirstEnergy Zones) FirstEnergy Procedure for Determining a Load Serving Entity s Hourly Energy Obligations The purpose of this Attachment M-1 is to give PJM members serving load

More information

NPCC 2016 Ontario Interim Review Of Resource Adequacy

NPCC 2016 Ontario Interim Review Of Resource Adequacy Approved by the RCC December 6, 2016 NPCC 2016 Ontario Interim Review Of Resource Adequacy FOR THE PERIOD FROM 2017 TO 2020 DECEMBER 2016 [Type here] This page intentionally left blank. ii Document Change

More information

Revision: 67. Prepared by

Revision: 67. Prepared by PJM Manual 11: Energy & Ancillary Services Market Revision: 67 Effective Date: June 1, 2014 Prepared by Forward Market PJM 2014 i Section 9: Hourly Scheduling Section 4: Overview of the PJM Synchronized

More information

SCHEDULE 2 - COMPONENTS OF COST 1. GENERAL COST PROVISIONS. For generating units powered by boilers Firing-up cost Peak-prepared-for maintenance cost

SCHEDULE 2 - COMPONENTS OF COST 1. GENERAL COST PROVISIONS. For generating units powered by boilers Firing-up cost Peak-prepared-for maintenance cost SCHEDULE 2 - COMPONENTS OF COST 1. GENERAL COST PROVISIONS 1.1 Permissible Components of Cost-based Offers. (a) Each Market Participant obligated to sell energy on the PJM Interchange Energy Market at

More information

Article 5. Electricity Generation Source Disclosure

Article 5. Electricity Generation Source Disclosure 1390. Scope Article 5. Electricity Generation Source Disclosure The regulations in this Article implement the disclosure and reporting requirements established in Article 14 (commencing with section 398.1)

More information

Ultraflex MV2 Final Data Summary

Ultraflex MV2 Final Data Summary Ultraflex Final Data Summary The Ultraflex CHP site concluded on May 26, 213. As a final check on the system measured data, overall trends in the fundamental temperature, flow, power and gas use data were

More information

7. Electrical Facility Ratings

7. Electrical Facility Ratings 7. Electrical Facility Ratings 7.1 Accredited Net Generating Capacity This Section shall be used to determine the annual and seasonal accredited net generating capacity of generators in calculating the

More information

BGE Smart Energy Savers Program Combined Heat and Power Program Manual

BGE Smart Energy Savers Program Combined Heat and Power Program Manual BGE Smart Energy Savers Program Combined Heat and Power 2015-2017 Program Manual Page 1 of 20 Table of Contents Introduction... 3 Purpose... 3 Goal... 3 ICF s Role... 3 Overview of BGE... 3 BGE Service

More information

The Treatment of Combined Heat and Power (CHP) under the Trading and Settlement Code A Draft Decision by the Commission for Electricity Regulation

The Treatment of Combined Heat and Power (CHP) under the Trading and Settlement Code A Draft Decision by the Commission for Electricity Regulation The Treatment of Combined Heat and Power (CHP) under the Trading and Settlement Code A Draft Decision by the Commission for Electricity Regulation CER/01/66 6 th June 2001 Introduction This document contains

More information

Waste Heat and Carbon Emissions Reduction

Waste Heat and Carbon Emissions Reduction Waste Heat and Carbon Emissions Reduction This Act is based on California law. Under California law, the State Energy Resources Conservation and Development Commission (Energy Commission) is charged with

More information

Support Scheme for Renewable Heat. Scheme Overview

Support Scheme for Renewable Heat. Scheme Overview Support Scheme for Renewable Heat Scheme Overview Table of Contents Introduction... 3 Support Types... 4 Operational Support... 4 Installation Grant... 8 Page 2 Introduction 1. This document is intended

More information

Network Load Reporting. March 28, 2018

Network Load Reporting. March 28, 2018 Network Load Reporting March 28, 2018 2 Purpose of Presentation Review of current requirements for reporting of Network Load Focus on Behind-the-Meter Generation (BTMG) requirements Discussion of results

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

Context - Current State

Context - Current State Generator - HONI Workshop Context - Current State January 22, 2009 Context Minister s Directive Increase amount of renewables in supply mix Accelerate achievement of conservation targets Improve transmission

More information

DRAFT 8/11/08. I. Renewable Portfolio Standard. (a) The Commission shall establish minimum numerical portfolio standards for each investorowned

DRAFT 8/11/08. I. Renewable Portfolio Standard. (a) The Commission shall establish minimum numerical portfolio standards for each investorowned I. Renewable Portfolio Standard 0 0.00 Florida Renewable Portfolio Standard () Application and Scope. (a) The Commission shall establish minimum numerical portfolio standards for each investorowned electric

More information

Helpful hints for utilities providing energy or water consumption data to building owners

Helpful hints for utilities providing energy or water consumption data to building owners Helpful hints for utilities providing energy or water consumption data to building owners Overview Under Ontario Regulation 20/17 (Reporting of Energy Consumption and Water Use), owners of buildings that

More information

Rules and Procedures for Determination of Generating Capability

Rules and Procedures for Determination of Generating Capability PJM Manual 21 Rules and Procedures for Determination of Generating Capability Revision: 11 Effective Date: March 5, 2014 Prepared by System Planning Department PJM 2014 PJM 2007 Revision 05, Effective

More information

Final Report for National Grid USA Service Company. Evaluation of 2003 Custom HVAC Installations Part II. September 27, 2005.

Final Report for National Grid USA Service Company. Evaluation of 2003 Custom HVAC Installations Part II. September 27, 2005. Final Report for National Grid USA Service Company Evaluation of 2003 Custom HVAC Installations Part II September 27, 2005 Submitted by Select Energy Services, Inc. is the energy services subsidiary of

More information

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability ReliabilityFirst Regional Criteria 1 Verification and Data Reporting of Generator Gross and Net Reactive Power Capability 1 A ReliabilityFirst Board of Directors approved good utility practice document

More information