Kathmandu, Nepal 9-10 May BY Engr. Munawar Iqbal Director (Hydropower) PPIB, Ministry of Water and Power, Government of Pakistan

Size: px
Start display at page:

Download "Kathmandu, Nepal 9-10 May BY Engr. Munawar Iqbal Director (Hydropower) PPIB, Ministry of Water and Power, Government of Pakistan"

Transcription

1 Kathmandu, Nepal 9-10 May 2016 BY Engr. Munawar Iqbal Director (Hydropower) PPIB, Ministry of Water and Power, Government of Pakistan

2 C O N T E N T S Overview of Power Mix Hydropower Potential of Pakistan Evolution of hydro model in Pakistan Salient futures of Power Policy 2002 & 2015 Success Stories in Private Sector Concluding Remarks

3 PAKISTAN POWER SECTOR - POWER MIX Power Mix is a blend of: Hydel Wind (50 MW) Oil Gas Nuclear Coal (150 MW)

4 PAKISTAN POWER SECTOR - TOTAL INSTALLED CAPACITY MW % Public Sector Hydel 7, Thermal 5, Nuclear Total 13, Private Sector IPPs 9, K-E 2, Total 11, Private Sector, 11950, 47.4% Nuclear, 787, 3.1% Total Installed Capacity 4 Wind 50 MW Public Sector Hydel, 7013, 27.8% Public Sector Thermal, 5458, 21.6% 25,208 MW

5 HYDROPOWER

6 RESPONSIBILITY PUBLIC SECTOR WAPDA Provinces PRIVATE SECTOR Private Power & Infrastructure Board (PPIB) Alternate Energy Development Board (AEDB) Provinces

7 Tarbela Dam Capacity 3,478 MW Enhanced 4,888 MW Opening date 1976 Impounds Height 9.7 MAF m Construction

8 Mangla Dam Coordinates N E Construction Type of dam Impounds Height Embankment dam Jhelum River 147 m (482 ft) Total capacity MAF Turbines Capacity 10 x 100 MW 1,000 MW

9 Warsak Dam Capacity Impounds Height Commission MW 25,300 acre ft 76.2 m

10 Ghazi Barotha Dam Capacity 1,450 MW Impounds 20,700 AF head 69 m Construction

11 HYDROPOWER IN OPERATION By WAPDA S# Name of Project Province Installed Capacity (MW) 1 Tarbela KPK Warsak KPK Jaban (Malakand-I) KPK 20 4 Dargai (Malakand-II) KPK 20 5 Kurram Garhi KPK 4 6 Mangla AJK Ghazi Barotha Punjab Chashma Punjab Rasul Punjab Shadiwal Punjab Nandipur Punjab MW Chichoki Punjab Satpara Gilgit-Baltistan 16

12 HYDROPOWER IN OPERATION S# Name of Project Province Installed Capacity (MW) 87 MW 38.7 MW KHYBER PAKHTUNKHWA 1 Malakand-III KPK Small HPP KPK Reshun KPK 2.8 GoAJ&K 1 Jagran AJ&K Kathai AJ&K Small HPPs AJ&K Kundal Shahi AJ&K 2

13 HYDROPOWER IN OPERATION S# Name of Project Province Installed Capacity (MW) GoGILGIL-BALTISTAN 1 Naltar Gilgit Baltistan 18 2 Gilgit Gilgit Baltistan Skardu-I Gilgit Baltistan Chilas-I Gilgit Baltistan Hunza Gilgit Baltistan Shyok Gilgit Baltistan Astore Gilgit Baltistan Kachura Phase II Gilgit Baltistan 3 9 Ghizar, Thak, Phander Gilgit Baltistan 6 10 Bordas Gilgit Baltistan 2 Gilgit Baltistan 1 84 Small HPPs 47.7

14 HYDROPOWER IN OPERATION S# Name of Project Province Installed Capacity (MW) GoGILGIL-BALTISTAN 1 Naltar Gilgit Baltistan 18 2 Gilgit Gilgit Baltistan Skardu-I Gilgit Baltistan Chilas-I Gilgit Baltistan Hunza Gilgit Baltistan Shyok Gilgit Baltistan Astore Gilgit Baltistan Kachura Phase II Gilgit Baltistan 3 9 Ghizar Gilgit Baltistan 2 10 Thak Gilgit Baltistan 2

15 C G I LG I T git Rive r R. Kandhia R. Riv er or a I nd A Sawat R. Naran KaghanRiver e Ne T la m Wolar Lake J ehlu S MUZAFFARABAD Mardan I Landi Kotal A s du In h nc Pu ISLAMABAD Rawalpindi er Riv J A M er Riv M U & K H A M S H I R Mangla F G H K H W A er m Riv Sirinagar Punch Peshawar K abul R. B E R P A K H T U N Khaplu Sakardu Madian Malakand Y us R iver Chilas Dir N Pa njk r al Kalam Chakwal Bannu A Miramshah Mianwali J eh lum er Riv in Ch ab er Riv Sargodha B Dera Ismail Khan A J Sheikhupura N Lahore U Faisalabad P Jhang Zhob vi Ra er Riv Okara Sahiwal Khaniwal Quetta t le Su Vehari Dera Ghazi Khan Multan r ive jr Bahawalnagar Kohlo Bahawalpur Dadhar A Chagi B A L U H I A N D T Rahimyar Khan Jacobabad N C S Shikarpur I Kharan I Kalat Khuzdar Larkana Khairpur Dadu I nd us Riv er R A N S I N D H Nawabshah Sanghar Turbat Uthal Mirpur Khas Hyderabad Gawadar Karachi ARABIAN SEA Thatha THAR PARKAR Coal Reserved ed in ef nd ru Ch it Gilgit Mangora K H Loralai A B A L T I S TA N M as t uj G il Chitral Parachinar N N tie on Fr Area of Focus I Gilgit-Baltistan R ive r HYDROPOWER H

16 HYDROPOWER POTENTIAL NEXT BACK

17 Hydropower Potential River Wise Indus MW Jhelum 5624 MW Kandiah 1006 MW others 9704 MW Swat 1803 MW Kunhar 1480 MW Punch 462 MW

18 LOCATION OF HPPs ON JEHLUM RIVER N 500 MW Chakothi Hattian HPP AJ&K Mahl River 640 MW Azad Pattan HPP 720 MW Karot HPP 147 MW Patrind HPP PH 590 MW Mahl HPP Mangla Garhi Habibullah Khyber Pakhtunkhwa PUNJAB 18 BACK

19 NEELUM VALLEY- MAJOR HYDEL SCHEMES Nara Dudhnial 800 MW Athmuqam 350 MW Ashkot 300 MW N-J 969 MW Total= 2419 MW ATHMUQAM Jagran Kagha n Sharda Dudhnial Janawai Halmat Toabat Legend NEELUM RIVER Kundal Shahi Panjgran TITHWAL BACK

20 PROJECTS ON POONCH RIVER IN AJK Sehra HPP SEHRA KOTLI GLPUR RAJDHANI 130 MW 100 MW 100 MW 132 MW Total= 462 MW KOTLI Gulpur HPP Gulpur BACK

21 PROJECTS ON KUNHAR RIVER IN KP 102 MW Batta Kundi HPP 188 MW Naran HPP Naran Balk ot 870 MW Suki Kinari HPP Paras 300 MW Balakot HPP Kaghan Bata Kundi 102 MW Naran 188 MW Suki Kinari 870 MW Balakot 300 MW Patrind 150 MW Total= 1610 MW 147 MW Patrind HPP BACK

22 LOCATION MAP RIVER INDUS TRIBUTARIES KAIGAH 548 MW Diamer Basha 4500 MW Bunji 7100 MW Yulbo 3000 MW TANGUS 2100 MW Dasu 4000 MW Duber Khwar 130 MW SPATGAH 496 MW Khan Khwar 72 MW Allai Khwar 121 MW PALAS VALLEY 665MW Warsak 243 MW Tarbela 3478 MW BACK

23 PROJECTS ON SWAT RIVER IN KPK Kalam Asrit HPP P=197 MW H=210 m Asrit Kedam HPP P=215 MW H=214 m PH PH PH Gabral Kalam HPP P=137 MW H=205 m SWAT VALLEY HPPs Madain HPP P=157 MW H=150 m PH BACK

24 Shydo Shydo 79 MW Shydo Shydo Shydo CHITRAL Shydo 58MW Shydo Shydo BACK

25 21125 MW HYDROPOWER POTENTIAL MW 6450 MW 7291 MW 1 MW 193 MW Total =59796 MW

26 STATUS OF HYDROPOWER DEVELOPMENT IN PAKISTAN TOTAL =60000 MW Under Process (PPP) Un-Tapped

27 PAKISTAN POWER SECTOR CURRENT SCENARIO Demand-supply gap up to 6000 MW resulting in load-shedding of up to 8-16 hours per day Power Planners have projected a demand of MW by the year 2020 If MW is assumed as de-rated capacity, country would need additional 13,300 MW (net) by the year 2020, requiring an investment of $15 billion Scarcity of funds in government sector so private sector is the next option For private sector, govt. have issued policies both federal and provincial levels

28 EVOLUTION OF POWER MODELS IN PAKISTAN PUBLIC SECTOR (WAPDA) Power Policy 1994 Hydel Policy 1995 Power Policy 1998 Power Policy 2002 Renewable Policy 2006 KPK 2006, Punjab 2006 Power Policy 2015 Private Sector PPP

29 POLICY - Features GENERAL FEATURES HPPs to be developed on BOOT Basis Concession Period allowed upto 30 years Tariff to be calculated on COST PLUS basis 100% foreign ownership allowed with minimum 20% equity contribution requirements Sponsors can divest equity after six (6) years of project commissioning Performance obligations of Power Purchaser and Provinces guaranteed by GOP Responsibility of power transmission facilities rests with the Power Purchaser

30 POLICY - Features FISCAL & FINANCIAL INCENTIVES Tax Holiday 5% concessionary Customs Duty Tariff adjustable for changes in Benchmark Interest Rates (LIBOR/KIBOR) Multi-Year, Long-term Tariff Attractive Return on Equity (ROE 17%) Two-part tariff structure of fixed 'Capacity' and variable 'Energy' components Conversion of Pak Rupee and remittance of Foreign Exchange ensured by GOP Exchange rate variation for COD up to

31 POLICY - Features RISK PROTECTING FEATURES Continuity of payments in case of Political Force Majeure Protection against Change in Law Risk Compensation Payment in case of project termination due to GOP default Foreign component of fixed and variable O&M Cost to be indexed with US CPI At COD, Capital Cost to be fixed in US dollars base Periodic adjustments in the Debt Service Component to cover exchange rate variation Hydrological Risk covered by assuring Capacity Payment upto 90%-95% of the Tariff

32 PROJECT AGREEMENTS

33 TARIFF DETERMINATION

34 PROCESSING OF UNSOLICITED PROJECTS ON RAW SITES Expression of Interest Reg. of Investors Feasibility Study Feasibility Completed Monitoring by POE not completed LOI Cancelled Proposal submission Evaluation Registration Cancelled Disapproved Tariff Petition before NEPRA Successfully Completed Project Readvertised Ranking approved NEPRA Approval of Tariff Issuance of LOI Issuance of LOS

35 CONTINUED.. Major Activities under LOS EPC Contractor through ICB Project Agreements WUA, PPA, IA(s) Land Acquisition Arrange Financing Environmental Approval EPC Tariff Approval Direct Agreements Fin. Close Construction COD

36 IPP MODEL BEING EXECUTED BY PPIB CSA: Coal Supply Agreement GSA: Gas Supply Agreement PPA: Power Purchase Agreement IA: Implementation Agreement DIA: Direct Implementation Agreement GoP Provinces Tripartite LOS DIA Lenders LOI/ LOS/ IA Financing CPPAG Gas/ Fuel Supplier OGRA Fuel Price GSA/ FSA IPPs EPC /O&M Contracts EPC/ O&M Contractors NTDC Transmission Licence NEPRA Purchase Licence

37 SUCCESS STORIES

38 SUCCESS STORIES OF HPPs in Private Sector 84 MW New Bong Escape HPP Project Company : Laraib Energy Limited Main Sponsor : HUBCO, Pakistan Lenders : ADB, IFC, IsDB, Proparco, HBL, NBP Project Cost : 215 Million US$ Capacity : 84 MW Energy : 471 GWh/a Firm Tariff (levelized) : USc/kWh Financial Closing : December 2009 Commissioning : March 2013

39 SUCCESS STORIES OF HPPs in Private Sector 150 MW Patrind HPP Project Company : Star Hydropower Limited Main Sponsor : K-Water, Korea Lenders : ADB, IFC, IsDB, KEXIM Project Cost : Million US$ Capacity : 150 MW Energy : GWh/a Firm Tariff (levelized) : USc/kWh Financial Closing : December 2012 Commissioning : March 2017

40 Project Layout TARCHEELA VILLAGE KUNHAR RIVER 1 WEIR SANDTRAP HEADRACE TUNNEL JHELUM RIVER MUZAFFARAB AD PATRIND VILLAGE ACCESS BRIDGE POWER HOUSE 1 WEIR & SANDTRAP 2 POWERHOUSE 2 SURGE TANK

41 Current Status of Works POWERHOUSE SITE

42 Physical Progress Diversion Tunnel

43 Physical Progress Access Bridge for Powerhouse

44 Current Status of Works WEIR SITE 4 4 Weir Site Camp (In Progress) 2 DT Outlet Portal (Water Diversion, 09 Apr 2013) 1 DT Inlet Portal (Water Diversion, 09 Apr 2013) 5 5 Stock Yard (Completed) WEIR 7 Weir & Sandtrap Excavation (In Progress) SANDTRAP 6 Adit Tunnel for HRT (145m Excavated) 7 BACK

45 SUCCESS STORIES OF HPPs in Private Sector 102 MW Gulpur HPP Project Company : Mira Power Limited Main Sponsor : KOSEP, Korea Lenders : ADB, IFC, KEXIM Project Cost : Million US$ Capacity : 102 MW Energy : 475 GWh/a Tariff (levelized) : USc/kWh Financial Closing : October 2015 Commissioning : October 2019

46 102 MW GULPUR HYDROPOWER PROJECT

47 102 MW GULPUR HYDROPOWER PROJECT BACK

48 SUCCESS STORIES OF HPPs in Private Sector 870 MW Suki Kinari HPP Project Company : Suki Kinari Private Limited Main Sponsor : Al-Jumaia, Saudi Arabia Lenders : CEXIM, ICB China Project Cost : Million US$ Capacity : 870 MW Energy : 3081 GWh/a Firm Tariff (levelized) : USc/kWh Financial Closing : June 2016 Commissioning : June 2021

49 SUCCESS STORIES OF HPPs -in Private Sector 1100 MW Kohala HPP Project Company : Kohala Hydro Co. Pvt. Limited Main Sponsor : CSAIL, CTGC China Lenders : CEXIM, ICBC China, IFC Project Cost : 2300 Million US$ Capacity : 1100 MW Energy : 5093 GWh/a Feasibility Tariff (levelized) : USc/kWh Financial Closing : December 2017 Commissioning : December

50 SUCCESS STORIES OF HPPs -in Private Sector 720 MW Karot HPP Project Company : Karot Power Co. Pvt. Ltd Main Sponsor : CSAIL, CTGC China Lenders : CEXIM, ICBC, IFC, SRF Project Cost : Million US$ Capacity : 720 MW Energy : 3174 GWh/a Firm Tariff (levelized) : USc/kWh Financial Closing : August 2016 Commissioning : August 2021

51 PUBLIC SECTOR PROJECT 969 MW NEELUM JHELUM HYDROPOWER PROJECT

52 NEELUM JHELUM LAYOUT PLAN

53 BACK INTRO

54 PPIB s PORTFOLIO OF UPCOMING PRIVATE POWER PROJECTS (IPPs) Description/ Year Hydel Coal Gas MW No. MW No. MW No. Total (MW) No. of Projects , , , , , , , , , , , , , Grand Total 7, , ,

55 How Hydropower is Renewable The circulation of earth s water as it circulates from the land to the sky and back again is called the hydrological cycle or water cycle.

56 Methematical Concept Renewable P =ρ.g. η. QH NON-Renewable P = 8.5 x Q H (SI Units) Head = H, Discharge = Q

57 CASA-1000 POWER SUPPLY PROJECT TO BE INAUGURATED ON MAY 12, 2016 The project, signed between Tajikistan and Pakistan, would be completed at a cost of $1.2 billion in two years The Central Asia-South Asia (CASA) 1000 project to supply one thousand megawatts electricity from Tajikistan to Pakistan would formally be inaugurated in Dushanbe on Thursday. The project, signed between Tajikistan and Pakistan, would be completed at a cost of 1.2 billion dollars in two years. The project would help Pakistan get cheaper and clean energy to minimize its electricity shortages. Afghanistan has already given a guarantee to ensure security of 750 km long transmission line. According to Ambassador of Tajikistan to Pakistan, all arrangements including necessary financial resources have been made to undertake the project forthwith.

58

PAKHTUNKHWA ENERGY DEVELOPMENT ORGANIZATION (PEDO) KHYBER PAKHTUNKHWA PAKISTAN

PAKHTUNKHWA ENERGY DEVELOPMENT ORGANIZATION (PEDO) KHYBER PAKHTUNKHWA PAKISTAN PAKHTUNKHWA ENERGY DEVELOPMENT ORGANIZATION (PEDO) KHYBER PAKHTUNKHWA PAKISTAN June 2017 1 1986 - Establishment of Small Hydel Development Organization (SHYDO) To identify and develop hydel potential up

More information

Unit: Power. Class 8 Geography Project. Power potential in Pakistan

Unit: Power. Class 8 Geography Project. Power potential in Pakistan Unit: Power Class 8 Geography Project Power potential in Pakistan The Material Power potential in Pakistan Pakistan does not have large proven reserves of fossil fuels but is fortunate enough to have been

More information

Experiences with Electricity Tariff Reforms

Experiences with Electricity Tariff Reforms Experiences with Electricity Tariff Reforms Presented by: Muhammad Safdar NEPRA, Pakistan ERRA Tariff / Pricing Committee meeting October 19, 2016 Bratislava, Slovakia 1 Experiences with electricity Tariff

More information

Pakistan Energy Crisis: An Overview

Pakistan Energy Crisis: An Overview Pakistan Energy Crisis: An Overview Contents Power Sector Highlights Pakistan Energy Stats Causes of Power Crisis Circular Debt Issue GoP s Initiatives for the Power Sector/Sectoral Recommendations VTT

More information

PAKISTAN POWER SECTOR. A Profile & Opportunities

PAKISTAN POWER SECTOR. A Profile & Opportunities PAKISTAN POWER SECTOR A Profile & Opportunities February, 2010 1 Pakistan Power Sector A Profile 2 2 Pakistan Power Sector a Profile Pakistan Power Sector is organized into nine Distribution Companies

More information

Private Power Generation Opportunities and Challenges

Private Power Generation Opportunities and Challenges The Pakistan Development Review 47 : 4 Part II (Winter 2008) pp. 1019 1027 Private Power Generation Opportunities and Challenges N. A. ZUBERI * POWER INDUSTRY DYNAMICS The concept of modern world is imperfect

More information

Proposal for Cash on Delivery Services For Online Merchants Submitted to Hassan

Proposal for Cash on Delivery Services For Online Merchants Submitted to Hassan Proposal for Cash on Delivery Services For Online Merchants Submitted to Hassan Dated: 13th Feb 2017 About MTM Logistics: MTM COURIER is a product of MTM Logistics an emerging company which is mainly focused

More information

Research Output in Natural Sciences and Agriculture during 2010 ( ***revised 9/12/2011) University Name

Research Output in Natural Sciences and Agriculture during 2010 ( ***revised 9/12/2011) University Name Research Output in Natural Sciences and Agriculture during 2010 ( ***revised 9/12/2011) University Name Research Papers University of Karachi, Karachi 342 University of Agriculture, Faisalabad 299 Govt.

More information

PAKISTAN RAIN/FLOOD 2011

PAKISTAN RAIN/FLOOD 2011 2011 PAKISTAN RAIN/FLOOD 2011 (Interim Report IV) Report on Flash floods, breaches in canals and damage to infrastructure & agriculture sectors in Sind Province (The period under report is from Aug 08

More information

PROVIDER A Case Study for EPC Projects in Pakistan. Jun. 4th, 2012

PROVIDER A Case Study for EPC Projects in Pakistan. Jun. 4th, 2012 NORDEX A SOLUTION PROVIDER A Case Study for EPC Projects in Pakistan Jun. 4th, 2012 CONTENT 1. Project background Pakistan wind market environment 2. Wind resources assessment 3. Financial model 4. Project

More information

on the basis of energy pathway scenarios

on the basis of energy pathway scenarios Available online at www.sciencedirect.com ScienceDirect Energy Procedia 61 (2014 ) 2403 2411 The 6 th International Conference on Applied Energy ICAE2014 Forecasting of Pakistan s net electricity energy

More information

POWER SECTOR AN OVERVIEW

POWER SECTOR AN OVERVIEW POWER SECTOR AN OVERVIEW October 2012 Demand Why Power? 1. Manufacturing companies need it to operate plant and machines 2. Service companies need it to operate technology 3. Agriculture needs it for tube

More information

PAKISTAN RAIN/FLOOD 2011

PAKISTAN RAIN/FLOOD 2011 2011 PAKISTAN RAIN/FLOOD 2011 Report on Flash floods, breaches in canals and damage to infrastructure & agriculture sectors in Sind Province (The period under report is from Aug 08 to Sep 20) September

More information

A n n u a l. v i. e w

A n n u a l. v i. e w ENERGY FOR PAKISTAN A n n u a l R e v i e w 2 0 1 6 Strategic Report ORACLE COALFIELDS PLC ANNUAL REVIEW 2016 Welcome to Oracle Coalfields PLC ORACLE Coalfields ( Oracle or the Company ) was founded in

More information

Thar Coal & Energy Board Government of Sindh

Thar Coal & Energy Board Government of Sindh Thar Coal & Energy Board Government of Sindh www.sindhcoal.gos.pk Coal Fields of Pakistan & Thar Thar coalfield is approximately located between Latitudes 24 o 15 N and 25 o 45 N Longitudes 69 o 45 E and

More information

INTEGRATED WATER RESOURCE MANAGEMENT IN PAKISTAN

INTEGRATED WATER RESOURCE MANAGEMENT IN PAKISTAN Paper No. 286 INTEGRATED WATER RESOURCE MANAGEMENT IN PAKISTAN Dr. Allah Baksh Sufi, Zahid Hussain, Syed Javed Sultan, Imran Tariq 36 Sufi, Hussain, Sultan, Tariq INTEGRATED WATER RESOURCE MANAGEMENT IN

More information

Hydrology of mountainous areas in the upper Indus Basin, Northern Pakistan with the perspective of climate change

Hydrology of mountainous areas in the upper Indus Basin, Northern Pakistan with the perspective of climate change Environ Monit Assess (212) 184:5255 5274 DOI 1.17/s1661-11-2337-7 Hydrology of mountainous areas in the upper Indus Basin, Northern Pakistan with the perspective of climate change Zulfiqar Ahmad & Mohsin

More information

Pre-Feasibility Study. (Injection Molding Plastic Products)

Pre-Feasibility Study. (Injection Molding Plastic Products) Pre-Feasibility Study (Injection Molding Plastic Products) HEAD OFFICE Constitution Avenue, Sector G-5/2, ISLAMABAD Ph#. 051-9225393 PCSIR, Precision System Training Centre Lahore Ferozepur Road, Lahore

More information

Electrical Energy Crisis in Pakistan and Their Possible Solutions

Electrical Energy Crisis in Pakistan and Their Possible Solutions International Journal of Basic & Applied Sciences IJBAS-IJENS Vol: 11 No: 05 38 Electrical Energy Crisis in Pakistan and Their Possible Solutions Dr,M. Arshad Javaid 1, Sarfraz Hussain, Abdul-Maqsood,

More information

Hydro and Wind Power Integration: A Case Study of Dargai Station in Pakistan

Hydro and Wind Power Integration: A Case Study of Dargai Station in Pakistan Energy and Power Engineering, 2012, 4, 203-209 http://dx.doi.org/10.4236/epe.2012.44028 Published Online July 2012 (http://www.scirp.org/journal/epe) Hydro and Wind Power Integration: A Case Study of Dargai

More information

KALABAGH - A SUPERIOR DAM DESIGNERS VIEW POINT

KALABAGH - A SUPERIOR DAM DESIGNERS VIEW POINT Paper No. 688 KALABAGH - A SUPERIOR DESIGNERS VIEW POINT Engr. Barkat Ali Luna, Engr. Muhammad Jabbar 288 Luna, Jabbar Pakistan Engineering Congress, 71st Annual Session Proceedings 289 KALABAGH - A SUPERIOR

More information

ARSENIC CONTAMINATION OF GROUNDWATER AND ITS MITIGATION IN THE PROVINCE OF PUNJAB (PAKISTAN) IN THE LIGHT OF THE SITUATION IN SOUTH ASIA

ARSENIC CONTAMINATION OF GROUNDWATER AND ITS MITIGATION IN THE PROVINCE OF PUNJAB (PAKISTAN) IN THE LIGHT OF THE SITUATION IN SOUTH ASIA ARSENIC CONTAMINATION OF GROUNDWATER AND ITS MITIGATION IN THE PROVINCE OF PUNJAB (PAKISTAN) IN THE LIGHT OF THE SITUATION IN SOUTH ASIA M. Irshad Ramay - AIT, Thailand Tameez Ahmad - UNICEF Pakistan Oleg

More information

Pre-Feasibility Study

Pre-Feasibility Study Pre-Feasibility Study (Semi-Intensive Tilapia Aquaculture) Small and Medium Enterprises Development Authority Ministry of Industries & Production Government of Pakistan www.smeda.org.pk HEAD OFFICE 4th

More information

Impact of Energy Consumption on Pakistan s Economic Growth

Impact of Energy Consumption on Pakistan s Economic Growth International Journal of Humanities and Social Science Invention ISSN (Online): 2319 7722, ISSN (Print): 2319 7714 Volume 2 Issue 6 ǁ June. 2013ǁ PP.51-60 Impact of Energy Consumption on Pakistan s Economic

More information

THERMAL AND NUCLEAR POWER

THERMAL AND NUCLEAR POWER THERMAL AND NUCLEAR POWER 1.0 POWER GENERATION CAPACITY OF PAKISTAN The total power generation capacity in Pakistan is of the order of 17,457 MW. This includes the hydropower generation capacity of 5,013

More information

1. HYDROPOWER ENGINEERING 1.1. HISTORY OF HYDROPOWER DEVELOPMENT

1. HYDROPOWER ENGINEERING 1.1. HISTORY OF HYDROPOWER DEVELOPMENT 1. HYDROPOWER ENGINEERING 1.1. HISTORY OF HYDROPOWER DEVELOPMENT Wind and running water were the only available sources of mechanical power (Fig: 1-1), other than animals from the time immemorial. In the

More information

INDUS BASIN IRRIGATION SYSTEM: WATER BUDGET AND ASSOCIATED PROBLEMS

INDUS BASIN IRRIGATION SYSTEM: WATER BUDGET AND ASSOCIATED PROBLEMS INDUS BASIN IRRIGATION SYSTEM: WATER BUDGET AND ASSOCIATED PROBLEMS Dr. Shahid Ahmad and Rashida Majeed* Abstract Around 74% of mean annual river flows (140 MAF) are diverted to the canal system and the

More information

Mechanics, Energy, Environment

Mechanics, Energy, Environment Prevailing Energy Crisis in Pakistan FARAH HAYAT, Dr DANIAL PIRZADA DEPARTMENT OF ENG MGT CENTER FOR ADVANCE STUDIES IN ENGINEERING (CASE) ISLAMABD PAKISTAN farahayat@gmail.com Abstract: - Pakistan is

More information

LIST OF BRANCHES TO REMAIN OPENED ON SATURDAYS SR # BRANCH NAME BRANCH CODE

LIST OF BRANCHES TO REMAIN OPENED ON SATURDAYS SR # BRANCH NAME BRANCH CODE ANNEXURE A LIST OF BRANCHES TO REMAIN OPENED ON SATURDAYS SR # BRANCH NAME BRANCH CODE CONVENTIONAL BRANCHES 1. Karachi Main Branch 0005 2. North Karachi Industrial Area Branch 0009 3. Gulshan-e-551 Branch,

More information

Rwanda, Burundi, Democratic Republic of Congo (DRC) East Africa Near Lake Kivu and the Ruzizi River at the border of Rwanda and the DRC

Rwanda, Burundi, Democratic Republic of Congo (DRC) East Africa Near Lake Kivu and the Ruzizi River at the border of Rwanda and the DRC Project Number: E.12.1 Project Title: Ruzizi III Hydropower Project Status: S3 programme/project structuring and promotion to obtain financing Countries Region Rwanda, Burundi, Democratic Republic of Congo

More information

The principal Investment Promotion Agency of the province of Sindh to facilitate Foreign & Local Businesses

The principal Investment Promotion Agency of the province of Sindh to facilitate Foreign & Local Businesses Sindh The Land of Endless Opportunities SBI At a Glance SBI has been established as : The principal Investment Promotion Agency of the province of Sindh to facilitate Foreign & Local Businesses A bridge

More information

Pakistan Development Forum. Presentation by

Pakistan Development Forum. Presentation by Pakistan Development Forum Presentation by M. Ali Shah, Country Director, ADB Pakistan Resident Mission Islamabad 18 March 2004 Part 1 - An Overview of Pakistan Part 2 - The Water Perspective Part 3 -

More information

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati Introduction Indonesian power sector is one of the business sectors in Indonesia which is strictly regulated. For the

More information

www.sindhcoal.gos.pk Vision To position Sindh as the power house of the region Mission To develop Thar Coal as a major source of power generation for Energy & Economic Security of the country and as a

More information

Daily Emergency and Response Situational Information Report 12 th Sep, th Sep

Daily Emergency and Response Situational Information Report 12 th Sep, th Sep 12 th Sep i NOTE - immap compiles these reports from the specified data sources and endeavors to get the most up-to-date and accurate figures available. immap and USAID do not take any ownership or responsibility

More information

DRAFT. Pakistan Water Apportionment Accord for Resolving Inter-provincial Water Conflicts Policy Issues and Options

DRAFT. Pakistan Water Apportionment Accord for Resolving Inter-provincial Water Conflicts Policy Issues and Options DRAFT Pakistan Water Apportionment Accord for Resolving Inter-provincial Water Conflicts Policy Issues and Options BALOCHISTAN PARTNERSHIPS FOR SUSTAINABLE DEVELOPMENT The designation of geographical entities

More information

Solar Power Initiative

Solar Power Initiative Solar Power Initiative by Government of the Punjab Presented by: Raza Ali Zaidi Procurement Manager Quaid-e-Azam Solar Power (Pvt.) Ltd Table of Contents Current Energy Crises & Possible Ways Forward To

More information

Tender Document - Request for Quotation

Tender Document - Request for Quotation Tender Document - Request for Quotation Subject of the Tender: Tender Number: Quantity: Fabrication and Supply of Solar Drying Units JOBS/ GIZ-001 350 Kits Tender Announcement date: April 3 rd, 2014 Tender

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

ISSUES & FUTURE PROSPECTS

ISSUES & FUTURE PROSPECTS SMALL DAMS IN PUNJAB ISSUES & FUTURE PROSPECTS SMALL DAMS ORGANIZATION ISLAMABAD POTHOHAR REGION BACKGROUND Pothohar region consist of 4 No. of districts namely Rawalpindi, Attock, Chakwal, Jhelum. Total

More information

Overview of BPC, its hydropower projects and Opportunities for further Development

Overview of BPC, its hydropower projects and Opportunities for further Development Overview of BPC, its hydropower projects and Opportunities for further Development Pratik Pradhan, Vice President BPC Nepal Power Investment Summit 2016 Kathmandu 1 June 2016 Content Overview of BPC Generation

More information

Power Generation Capacity and Its Investment Requirements in Pakistan for Twenty Years ( )

Power Generation Capacity and Its Investment Requirements in Pakistan for Twenty Years ( ) Chapter 117 Power Generation Capacity and Its Investment Requirements in Pakistan for Twenty Years (2011-2030) Nadeem A. Syed, Akbar Saeed and Asif Kamran Abstract Pakistan is facing an unprecedented power

More information

IMPACT OF VARIATION ORDERS ON TIME & COST IN MEGA HYDROPOWER PROJECTS OF PAKISTAN

IMPACT OF VARIATION ORDERS ON TIME & COST IN MEGA HYDROPOWER PROJECTS OF PAKISTAN IMPACT OF VARIATION ORDERS ON TIME & COST IN MEGA HYDROPOWER PROJECTS OF PAKISTAN a Hashim Hanif *, b Muhammad Bilal Khurshid, c Shazia Nauman, d Søren Lindhard a,b College of Civil Engineering, National

More information

Pre-Feasibility Study

Pre-Feasibility Study COLD STORAGE (FRUIT & VEGETABLE) Small and Medium Enterprises Development Authority Ministry of Industries & Production Government of Pakistan www.smeda.org.pk HEAD OFFICE 4th Floor, Building No. 3, Aiwan-e-Iqbal

More information

Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT

Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT 1 Introduction The demand for electricity in Vietnam is rising rapidly to power the growing economy and forecasts predict an annual growth rate for electricity

More information

Gulpur Hydropower Project. Assessment of Cumulative Impacts and Management. February, Vaqar Zakaria

Gulpur Hydropower Project. Assessment of Cumulative Impacts and Management. February, Vaqar Zakaria Gulpur Hydropower Project Assessment of Cumulative Impacts and Management February, 2016 Vaqar Zakaria The Project 2/26/2016 2/26/2016 Diversion Tunnels Powerhouse Intake Cofferdam Weir and Spillway

More information

Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014

Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014 Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014 Western Power Company Western Power Company (WPC) is a Zambian Independent Power Producer which is working for the development

More information

KALABAGH DAM Shaukat Mahmood Alvi Al-Khobar INTRODUCTION

KALABAGH DAM Shaukat Mahmood Alvi Al-Khobar INTRODUCTION KALABAGH DAM A Multi-purpose Project of NATIONAL WATER RESOURCES DEVELOPMENT PROGRAMME A Long-term Solution to National Water & Power Problems Sent to CP by Shaukat Mahmood Alvi Al-Khobar INTRODUCTION

More information

PRESENTATION ON ALTERNATIVE CONCEPTS OF WATER STORAGE IN SPATE AREAS OF PAKISTAN

PRESENTATION ON ALTERNATIVE CONCEPTS OF WATER STORAGE IN SPATE AREAS OF PAKISTAN 1 DIRECTORATE GENERAL OF SMALL DAMS IRRIGATION DEPARTMENT KHYBER PAKHTUNKHWA PRESENTATION ON ALTERNATIVE CONCEPTS OF WATER STORAGE IN SPATE AREAS OF PAKISTAN JUNE 24, 2014 LAND USE IN KHYBER PAKHTUNKHWA

More information

Financing Small Hydro Projects (SHP): The Challenges and the Opportunities

Financing Small Hydro Projects (SHP): The Challenges and the Opportunities Financing Small Hydro Projects (SHP): The Challenges and the Opportunities Presented by: Mark Matousek Founder & Vice Chairman ORENCO Hydropower Presented at: NWHA Small Hydro Workshop 2011 September Clean

More information

Power Crisis in Pakistan: A Crisis in Governance?

Power Crisis in Pakistan: A Crisis in Governance? PIDE Monograph Series Power Crisis in Pakistan: A Crisis in Governance? Afia Malik PAKISTAN INSTITUTE OF DEVELOPMENT ECONOMICS ISLAMABAD All rights reserved. No part of this publication may be reproduced,

More information

Climate Change, Agriculture and Food Security in Pakistan: Adaptation Options and Strategies

Climate Change, Agriculture and Food Security in Pakistan: Adaptation Options and Strategies October 2013 IDRC CRDI Canada International Development Research Centre Centre de recherches pour le développement international Climate Change Brief Climate Change, Agriculture and Food Security in Pakistan:

More information

ABENGOA. Chile, changing the energy matrix. Completing Transformation. Ivan Araneda. Innovative Technology Solutions for Sustainability

ABENGOA. Chile, changing the energy matrix. Completing Transformation. Ivan Araneda. Innovative Technology Solutions for Sustainability Innovative Technology Solutions for Sustainability ABENGOA Chile, changing the energy matrix Completing Transformation 9th Annual Analyst and Investor Day Ivan Araneda General Manager Abengoa Chile New

More information

PRE-FEASIBILITY STUDY ON PURIFICATION OF ORGANIC SOLVENTS

PRE-FEASIBILITY STUDY ON PURIFICATION OF ORGANIC SOLVENTS PRE-FEASIBILITY STUDY ON PURIFICATION OF ORGANIC SOLVENTS Pakistan Council of Scientific and Industrial Research. PCSIR. HEAD OFFICE Constitution Avenue, Sector G-5/2, 051-9225393 Islamabad. Pharmaceutical

More information

Transboundary Water Cooperation in the Indus Basin: Challenges & Opportunities

Transboundary Water Cooperation in the Indus Basin: Challenges & Opportunities Transboundary Water Cooperation in the Indus Basin: Challenges & Opportunities Dr Shaheen Akhtar Regional Workshop on Transboundary Water Cooperation in the context of the SDGs in South Asia and beyond,

More information

Vision: Our vision is to ensure optimum performance of client organizations through efficient and effective services for their beneficiaries.

Vision: Our vision is to ensure optimum performance of client organizations through efficient and effective services for their beneficiaries. Introduction CHIP Training & Consulting CTC (Private Limited) emerged as the dynamic training and consulting arm of Civil Society Human & Institutional Development Programme (CHIP) in Pakistan in the year

More information

Development and Financing of Renewable Energy Projects in India

Development and Financing of Renewable Energy Projects in India Development and Financing of Renewable Energy Projects in India A Perspective By K.S. Popli Director (Technical) Indian Renewable Energy Development Agency Limited New Delhi ( India ) World primary energy

More information

Electricity Infrastructure in Pakistan: an Overview

Electricity Infrastructure in Pakistan: an Overview Electricity Infrastructure in Pakistan: an Overview Kafait Ullah Research Fellow, Center for Technology and Sustainable Development (CSTM), University of Twente, the Netherlands kafiatullah@gmail.com Abstract

More information

Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities

Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities Dendy Kurniawan Finance Director PT Geo Dipa Energi April 2013 1 Geo Dipa Energi (GDE) PT GEO DIPA ENERGI Est. 5 July 2002

More information

EIC Climate Change Technology Conference 2013

EIC Climate Change Technology Conference 2013 Flood Disaster and Risk Reduction through Adaptation Measures: A Case of Punjab, Pakistan CCTC 2013 Paper Number 1569692165 Sajid Noor 1 Munazza Fatima 2 1 Assistant Professor, Department of Geography,

More information

Pre-Feasibility Study

Pre-Feasibility Study Pre-Feasibility Study () Small and Medium Enterprises Development Authority Ministry of Industries & Production Government of Pakistan www.smeda.org.pk HEAD OFFICE 4th Floor, Building No. 3, Aiwan e Iqbal,

More information

PAKISTAN 1. PHYSIOGRAPHY

PAKISTAN 1. PHYSIOGRAPHY PAKISTAN 1. PHYSIOGRAPHY Pakistan is located in the north-west part of the Indo-Pakistan sub continent about in the middle of the South Asian region. it is surrounded by the neighbouring countries of Iran,

More information

SITE IDENTIFICATION REPORT

SITE IDENTIFICATION REPORT Public Disclosure Authorized Public Disclosure Authorized Wind Resource Mapping in Pakistan SITE IDENTIFICATION REPORT FEBRUARY 2016 Public Disclosure Authorized Public Disclosure Authorized This report

More information

FIELD BASED ASSESSMENT OF RICE BACTERIAL LEAF BLIGHT IN MAJOR RICE GROWING ZONES OF PAKISTAN

FIELD BASED ASSESSMENT OF RICE BACTERIAL LEAF BLIGHT IN MAJOR RICE GROWING ZONES OF PAKISTAN Sarhad J. Agric. Vol.29, No.3, 2013 FIELD BASED ASSESSMENT OF RICE BACTERIAL LEAF BLIGHT IN MAJOR RICE GROWING ZONES OF PAKISTAN ABDUL RAFI 1 *, ABDUL HAMEED 2, MUHAMMAD AFZAL AKHTAR 3, SYED MEHER ALI

More information

miii% NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LTD. mia 1-C, BLOCK-N, MODEL TOWN EXTENSION m LAHORE - PAKISTAN

miii% NATIONAL ENGINEERING SERVICES PAKISTAN (PVT) LTD. mia 1-C, BLOCK-N, MODEL TOWN EXTENSION m LAHORE - PAKISTAN ISLAMIC REPUBLIC OF PAKISTAN FEDERAL FLOOD COMMISSION MINISTRY OF WATER AND POWER MASTER FEASIBILITY STUDIES FOR FLOOD MANAGEMENT OF HILL TORRENTS OF PAKISTAN SUMMARY a NORTHERN A REAS "Y HILL TORRENTS

More information

ENERGY AND WATER STATISTICS 2016

ENERGY AND WATER STATISTICS 2016 ENERGY AND WATER STATISTICS 216 Introduction This issue of Economic and Social Indicators presents Statistics on Energy and Water for the years 215 and 216. The statistics have been compiled in close collaboration

More information

Hydropower infrastructure - How to make Swiss hydropower more competitive?

Hydropower infrastructure - How to make Swiss hydropower more competitive? Hydropower infrastructure - How to make Swiss hydropower more competitive? Anton Schleiss, LCH-EPFL Annual Conference, Neuchâtel, 10. 9. 2015 Contents - How to make Swiss hydropower more competitive? 1.

More information

Dr. Jyoti Parikh Executive Director Integrated Research and Action for Development (IRADe)

Dr. Jyoti Parikh Executive Director Integrated Research and Action for Development (IRADe) South Asia Investor s Workshop on Cross-Border Electricity Trade South Asia Regional Initiative for Energy Integration(SARI/EI) 24 th -25 th September, 2014 New Delhi, India Dr. Jyoti Parikh Executive

More information

SOLAR DUE DILIGENCE. Instructor: Peter Cockcroft March Jakarta

SOLAR DUE DILIGENCE. Instructor: Peter Cockcroft March Jakarta SOLAR DUE DILIGENCE Instructor: Peter Cockcroft 20 22 March 2017 Jakarta COURSE BENEFITS This 3-day course is essential for all players in the international solar power game, and you will walk away with

More information

WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES

WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES QUÉBEC HAS THE CLEAN ENERGY MASSACHUSETTS NEEDS Hydro-Québec is proposing a new source of clean energy to Massachusetts, in the form of firm deliveries

More information

GROUNDS OF MOTION FOR REVIEW

GROUNDS OF MOTION FOR REVIEW GROUNDS OF MOTION FOR REVIEW At the outset the Petitioner would like to express its gratitude and thank the learned Authority for its decision/determination in respect of tariff petition dated 02.12.2015

More information

Corporate Overview. descon.com

Corporate Overview. descon.com Corporate Overview descon.com descon.com The Descon Group operates four major business lines POWER GENERATION & SERVICES Own & Operate Two Power Plants with supplies to State. Providing Operations & Maintainace

More information

Hydro & Small Hydro Outlook in India 2017

Hydro & Small Hydro Outlook in India 2017 Hydro & Small Hydro Outlook in India 217 Evaluating Business Case & Future Scenario of Large & Small Hydro Power Plants in India Report Summary enincon consulting llp, 217, New Delhi, India Enincon s Key

More information

Vietnam s Power Sector: An Overview. Richard Spencer Power Sector Experience Sharing Event Dhaka February 9, 2011

Vietnam s Power Sector: An Overview. Richard Spencer Power Sector Experience Sharing Event Dhaka February 9, 2011 Vietnam s Power Sector: An Overview Richard Spencer Power Sector Experience Sharing Event Dhaka February 9, 2011 Outline Vietnam s power sector The reform program Investment planning Who Does What in the

More information

Research on China's power industry investment in Kazakhstan. Gao Yang

Research on China's power industry investment in Kazakhstan. Gao Yang International Conference on Energy and Environmental Protection (ICEEP 2016) Research on China's power industry investment in Kazakhstan Gao Yang The Central Asian Economic Research Institute, China (Xinjiang)

More information

sustainable Energy Deployment in Egypt

sustainable Energy Deployment in Egypt Ministry of Electricity and Renewable Energy sustainable Energy Deployment in Egypt Eng. Ahmed Mohina Undersecretary for Authorities follow up 9/11/2017 contents Where we want to be?. Where are we now?.

More information

Power Africa Geothermal Road Show. Presented by David Kagiri

Power Africa Geothermal Road Show. Presented by David Kagiri Power Africa Geothermal Road Show Presented by David Kagiri September 2014 Outline of Presentation JOH-KGN001-20070825-JvW-P1 1.Summary of power sector and country investment environment 2. Detailed summary

More information

CK Power Public Company Limited (CKP) Stable Income, Diversified Portfolio and High Growth Company

CK Power Public Company Limited (CKP) Stable Income, Diversified Portfolio and High Growth Company CK Power Public Company Limited (CKP) Stable Income, Diversified Portfolio and High Growth Company 0 1 COMPANY STRUCTURE 1 1 Company and Shareholding Structure Current Shareholding Structure Bangpa-in

More information

RenovAr PROJECT ON ARGENTINA Ministry of Energy and Mining Argentina Republic

RenovAr PROJECT ON ARGENTINA Ministry of Energy and Mining Argentina Republic RenovAr PROJECT ON RENEWABLE ENERGIES ARGENTINA 2016-2025 Ministry of Energy and Mining Argentina Republic THE ACT ON RENEWABLE ENERGIES SETS A NEW STAGE IN THE ARGENTINE REPUBLIC It is a historic event

More information

STATISTICS ON WORLD PRODUCTION, EXPORT, IMPORT, PRICES AND UTILIZATION OF RICE: REPORT COMPILED BY: IQRA JUNEJO

STATISTICS ON WORLD PRODUCTION, EXPORT, IMPORT, PRICES AND UTILIZATION OF RICE: REPORT COMPILED BY: IQRA JUNEJO STATISTICS ON WORLD PRODUCTION, EXPORT, IMPORT, PRICES AND UTILIZATION OF RICE: REPORT COMPILED BY: IQRA JUNEJO 1 TABLE OF CONTENT S:NO CONTENT PAGE # 1 Acknowledgement 3 2 Rice sector of Pakistan 4 3

More information

Regulator s Role in the Promotion of Renewable Energy Resources

Regulator s Role in the Promotion of Renewable Energy Resources Regulator s Role in the Promotion of Renewable Energy Resources 16 September 2008 Marie Römpötti Econ Pöyry AB The views expressed in this presentation are the views of the author and do not necessarily

More information

Pakistan s Gas Import Pipeline Projects

Pakistan s Gas Import Pipeline Projects Pakistan s Gas Import Pipeline Projects Energy Charter Treaty Meeting on Transit and Trade Brussels October 26 & 27, 2006 Syed Hassan Nawab Managing Director INTER STATE GAS SYSTEMS (PVT) LTD. A Joint

More information

The State of Renewable Energy in the Region Wind Ene rgy Te chnology &Tre nds

The State of Renewable Energy in the Region Wind Ene rgy Te chnology &Tre nds The State of Renewable Energy in the Region Wind Ene rgy Te chnology &Tre nds 01 02 03 T e c h n o l o g y T r e n d s a n d F u t u r e C h a l l e n g e s M a r k e t T r e n d s a n d P o l i c y D

More information

GREEN BUILDINGS MARKET INTELLIGENCE PAKISTAN COUNTRY PROFILE

GREEN BUILDINGS MARKET INTELLIGENCE PAKISTAN COUNTRY PROFILE GREEN BUILDINGS MARKET INTELLIGENCE PAKISTAN COUNTRY PROFILE 1,500 1,000 500 MARKET GROWTH PAKISTAN: COUNTRY SUMMARY Building Stock (million m2) Residential Office & Retail Other Commercial OTHER FACTORS

More information

Power Development and Planning in China

Power Development and Planning in China Power Development and Planning in China Dr. Shuli WANG Electric Power Planning & Engineering Institute August 29, 2017 Outline 1 Introduction of power industry in China 2 Power planning and cooperation

More information

Success Factors for the Implementation of Mini Grids. Michael Franz, Project Manager, GIZ

Success Factors for the Implementation of Mini Grids. Michael Franz, Project Manager, GIZ Success Factors for the Implementation of Mini Grids Michael Franz, Project Manager, GIZ Berlin, 26 February 2013 Page 1 giz Service Portfolio for the Energy Sector Capacity development Technical and management

More information

The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts

The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts RENEWABLE AFFORDABLE RELIABLE PROJECT OVERVIEW The New England Clean Power Link A powerful wind and hydro partnership

More information

Public Private Partnership in Wind Power in India

Public Private Partnership in Wind Power in India Public Private Partnership in Wind Power in India Introduction India is the one of the fastest growing economies in the world. In the last five years, India has averaged a phenomenal 8.775% growth, as

More information

Indonesia update: Tariff framework for renewable energy

Indonesia update: Tariff framework for renewable energy September 2017 Indonesia update: Tariff framework for renewable energy In brief On 7 August 2017, the Ministry of Energy and Mineral Resources of the Republic of Indonesia ( MEMR ) enacted Regulation No.

More information

ELECTRICITY PRICING IN TANZANIA

ELECTRICITY PRICING IN TANZANIA ELECTRICITY PRICING IN TANZANIA Felix Ngamlagosi Director of Regulatory Economics EWURA 10 13 SEPT. 2012 ELECTRICITY PRICING IN TANZANIA BACKGROUND TARIFF APPLICATION GUIDELINES 2009 CURRENT TARIFF SETTING

More information

BUSINESS INFRASTRUCTURE ON RENEWABLE ENERGY POWER PLANT. Indonesia Clean Energy Development (ICED) Project. Bill Meade 13 March 2013

BUSINESS INFRASTRUCTURE ON RENEWABLE ENERGY POWER PLANT. Indonesia Clean Energy Development (ICED) Project. Bill Meade 13 March 2013 BUSINESS INFRASTRUCTURE ON RENEWABLE ENERGY POWER PLANT Indonesia Clean Energy Development (ICED) Project Bill Meade 13 March 2013 ICED s approach in developing the Clean Energy Sector in Indonesia Clean

More information

INTERNATIONAL O&M CONFERENCE

INTERNATIONAL O&M CONFERENCE INTERNATIONAL O&M CONFERENCE COAL SUPPLY CHALLENGES & WAY FORWARD 14 TH FEB 2012 - BY DK SAHA, DGM(FM) & JANARTHAN C. DGM(FM) Electricity Per Capita consumption India Egypt China Brazil World Average Russia

More information

Overview of the Legal Framework. New Policy Initiatives. Renewable Energy Certificate Mechanism

Overview of the Legal Framework. New Policy Initiatives. Renewable Energy Certificate Mechanism 1 Overview of the Legal Framework New Policy Initiatives Renewable Energy Certificate Mechanism 2 3 Tariff regulations of the Regulatory Commissions to be guided by promotion of generation of electricity

More information

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation

More information

Fast Tracking Hydro Infrastructure Build in Developing Economies. BJ Rochecouste Collet Technical Director Aurecon South Africa

Fast Tracking Hydro Infrastructure Build in Developing Economies. BJ Rochecouste Collet Technical Director Aurecon South Africa Fast Tracking Hydro Infrastructure Build in Developing Economies BJ Rochecouste Collet Technical Director Aurecon South Africa Fast Tracking? Hydro is the cheapest power source in the Nordic market (Source:

More information

Nuclear energy development in the Republic of Armenia. IAEA, Amsterdam June

Nuclear energy development in the Republic of Armenia. IAEA, Amsterdam June Nuclear energy development in the Republic of Armenia IAEA, Amsterdam 21-23 June Geography and Climate The Republic of Armenia is a landlocked mountainous country bordered on the north by the Republic

More information

An analysis of losses and gains in Indus river system of Pakistan

An analysis of losses and gains in Indus river system of Pakistan An analysis of losses and gains in Indus river system of Pakistan Kharal F.H., Ali S. in Lamaddalena N. (ed.), Bogliotti C. (ed.), Todorovic M. (ed.), Scardigno A. (ed.). Water saving in Mediterranean

More information

A STUDY OF WATER SUPPLY FOR ISLAMABAD / RAWALPINDI

A STUDY OF WATER SUPPLY FOR ISLAMABAD / RAWALPINDI A STUDY OF WATER SUPPLY FOR ISLAMABAD / RAWALPINDI By Engr. Muhammad Jabbar 1 and Azhar Masood Panni 2 The present major source of water supply to Islamabad / Rawalpindi, some industrial units and irrigation

More information

Flexible Fiscal Incentives and Policy Reforms: What works for Clean Energy Investments?

Flexible Fiscal Incentives and Policy Reforms: What works for Clean Energy Investments? Flexible Fiscal Incentives and Policy Reforms: What works for Clean Energy Investments? VENKATACHALAM ANBUMOZHI, ERIA Objective of Fiscal Policy Reforms Revenue Mobilization for Clean Energy in Changing

More information

Case Study: Lokoho Project, Madagascar

Case Study: Lokoho Project, Madagascar Session 2.1 RE Identification Case Study: Lokoho Project, Madagascar Pascale Bonzom (UNDP) / Sascha Thielmann (GTZ) Rural Electrification Workshop March 1-3, 2006 Nairobi Case Study: Lokoho Project, Madagascar

More information