THE AKRON RECYCLE ENERGY SYSTEM: A PERFORMANCE UPDATE

Size: px
Start display at page:

Download "THE AKRON RECYCLE ENERGY SYSTEM: A PERFORMANCE UPDATE"

Transcription

1 THE AKRON RECYCLE ENERGY SYSTEM: A PERFORMANCE UPDATE DAVE CHAPMAN Formerly with Department of Public Service The City of Akron, Ohio KENNETH C. O'BRIEN R. W. Beck and Associates Denver, Colorado ABSTRACT Operating and maintenance difficulties were experienced at the Akron Recycle Energy System during initial This paper describes the modifications made to the plant and operating performance subsequent to the completion of the modifications. operation of the plant. The incineration of solid waste was suspended in June of Modifications were made and the plant has been in commercial operation since January A summary of the problems and solutions is presented along with current operating results. ORIGINAL PLANT DESCRIPTION Solid waste is delivered in trucks to the tipping floor where it is weighed on a scale. After weighin, trucks dump the solid waste into a pit which is self unloading by means of two lines of positive displacement multiple rams. INTRODUCTION In July of 1979, construction was completed on a solid waste resource recovery plant for the City of Akron, referred to as the Akron Recycle Energy System. The plant was designed to process 1000 TPD (907 tpd) of solid waste and generate steam for sale in the downtown area. The plant is located south of the central business district, adjacent to the world manufacturing headquarters of B. F. Goodrich. Operating difficulties were experienced during startup and after nearly two years of effort to resolve the problems, performance was still well below the design performance criteria. This was due primarily to operational and maintenance problems with the pneuma tic fuel transport system. The City of Akron and a co'participant in the project, Ohio Water Development Authority studied a number of alternatives and decided to enter into a contract with Tri cu Resources, Inc. to design and construct modifications to the plant to improve performance. TrieU has subse quently been retained to operate the plant. The plant has been operating successfully since it was returned to com mercial operation in January A grapple crane intercepts unsuitable materials as the solid waste reaches the end of the pit. Solid waste is conveyed from the pit to one of two 1500 hp (1119 kw) horizontal hammermill shredders. Each shredder is rated at 60 TPH (54 tph). In the original plant design the shredders were followed by an air classification density separator. The heavy fraction passed through a magnetic separator where ferrous materials were recovered. The remainder of the heavy fraction was landfi1led. The light fraction was pneumatically conveyed to a 1900 ton (1723 t) storage bin. The light fraction was then auger fed to a surge bin from wruch it was pneumatically transported to one of the boilers. One surge bin served all three boilers. The plant design incorporated three Babcock and Wilcox boilers, each rated at 126,000 lb/hr (57,204 kg/h) of steam at 560 psig, (3861 kpa) saturated, when burning refuse having a heating value of 6500 Btu/hr (3611 Call kg) or 95,600.lb/hr (43,402 kg/h) when burning 5450 Btu/ lb (3027 Cal/kg) refuse. The bouers employ the Stirling design, with spreader stokers and traveling grates. Each bouer has an economizer, four stage electrostatic precipi tator and regenerative air heater. The bouers are equipped to burn natural gas or No. 2 oil as alternative fuels. The 248

2 original plant incorporated a manual dry ash removal system. The steam generated by the plant is delivered via a pipeline system to steam customers or is used inhouse to generate electricity in one of two 2MW turbine generators. The 10 psig (69 kpa) exhaust steam is used for feedwater heating or can be vented. Deaerating steam can also be supplied directly from the 560 psig (3861 kpa) header. Condensate is returned from certain customers, amounting to about 30 percent of the steam supplied. PLANT MODIFICATIONS Construction of the plant modifications began in July of The work was substantially complete by October of Figure 1 shows the plant as it looks with the modifications completed. Figure 2 shows a simplified flow diagram for the material handling systems after modifications were made. The major changes to the plant are as follows: (1) Fuel Preparation and Handling. The air classification density separator was removed. Refuse is conveyed, by belt conveyor, directly from the discharge of the shredders to the magnetic separator. The original magnetic separator was replaced with a stronger duty double drum unit, with an air scrubber. The light fraction storage bin and pneumatic fuel transport system were deactivated and replaced with a belt conveyor and chute system which conveys fuel directly from the magnetic separator to the boilers. A series of proportioning devices are used to deliver the proper quantity of fuel to each boiler with the excess being conveyed back to the receiving/storage pit. (2) Ash Handling. The manual dry ash handling system was replaced with a wet system. Bottom ash from a boiler drops from the grates directly into a water quench tank, which also acts as an air seal. Ash recovered in the economizer section is also conveyed to the quench tanle Fly ash from the precipitator is transported to a silo and then to a pug mill. Ash from the quench tank along with fly ash is conveyed to a truck loading station for disposal. (3) Process Control. A microprocessor based control system was installed in place of the original pneumatic system. Other changes included; shredder in feed surge bin modifications, installation of shredder baffles, and in stallation of a shredder blast protection wall. In addition to the modifications made to improve plant performance, a hot water heating system was in stalled which uses 10 psig (58.95 kpa) exhaust steam from the turbine generators to produce 210 F (99 C) water for sale to nearby businesses and residences. PLANT PERFORMANCE The modified plant was first returned to operation using solid waste for fuel in late October of Performance tests were run during the period from November 15, 1982 to December 14, Acceptance criteria were as follows: (1) 800 ton (726 t) average daily throughput. (2) Excess air at or reasonably close to 50 percent. (3) Ash with carbon content less than 3 percent. The average daily throughput during the test was 656 tons (595 t). The 800 TPD (726 tpd) level was not reached primarily due to. difficulties with the delivery of solid waste to the plant. The plant processed more than 800 tons (726 t) on 13 days, more than 1000 tons (907 t) on 3 days with a daily high oq 141 tons (1035 t). Excess air was measured at percent and carbon content of the ash was measured at less than 1 percent. Plant performance was judged to be satisfactory and Trlcil began operation of the plant on a commercial basis under con tract with Akron on January 1,1983. Since that time the plant has been operating successfully. For the period January 1 October 2, 1983, the following performance was recorded: (1) Average daily throughput of 599 tons (543 t). (2) Total steam production of 1.07 X 109 lb (0.486 X 109 kg) using solid waste. (3) 84 percent of steam generated with solid waste. The remainder was generated with natural gas. (4) 100 percent of steam customers requirements served without interruption. (5) 11,200 hr of boiler operation using solid waste fuel. During the month of May, average daily throughput was 804 tons (729 t) with 91 percent of the steam generated with solid waste. The plant processed more than 1000 tons (907 t) on 4 days during that period. Performance data for the months January through August are shown in Table 1. The difference between steam produced (which is measured at the bouer outlet header) and steam sales is accounted for in distribution line losses, deaerator makeup requirements, steam used for electric power generation and in some cases steam vented to atmosphere. The quantities of ferrous metals, ash and rejects (material extracted by the grapple crane in the raw refuse area) are measured in truck loads. Trucks are weighed period ically to provide a means of estimating weight. The following conversion factors were provided: Ferrous 15 tons (13.6 t)/truckload Ash 17 tons (15.4 t)/truckload Rejects 9 tons ( 8.2 t)/truckload Using these factors, the weight of ferrous metals recov ered was calculated to be approximately 5 percent of 249

3 FIG.1 AKRON RECYCLE ENERGY SYSTEM plant throughput while rejects amounted to approximately 3 percent. A similar comparison was not useful for the ash since it is weighed wet. Electrical consumption at the plant has averaged 90 to 100 kwh per ton (99110 kwh/t) of refuse. This high value was due to a low power factor, approximately 0.7. The power factor is being raised to 0.9 and electrical consumption is expected to be in the range of 60 to 70 kwh/ton (6677 kwh/t). Figure 3 graphically presents the monthly performance data. The steam produced with gas cannot be measured directly. Tricil indicated that the plant uses a conversion factor of 0.79 lb (0.36 kg) of steam per 1 SCF (0.028 m 3 ) of gas. Weekly performance reports are prepared at the plant which show important operating data for each day. A typical weekly report is reproduced in Table 2. The quantity of waste processed cannot be directly measured but is estimated based on the weighing of the incoming refuse trucks and on the amount of waste remaining in the receiving/storage pit at the end of each day. This may produce some error fn the daily statistics but is not significant in the long run since the pit is emptied periodically. The number of hours each boiler is operated using solid waste is recorded as indicated in the table. The remainder of the time the boiler is either out of service or is being fueled with natural gas. Boilers are not normally fueled with solid waste and natural gas simultaneously. The boiler operating data shown in Table 2 are typical in that there are relatively few days where boilers are operated with solid waste the full 24 hr. Tricil reports that this is largely related to the availability of solid waste fuel from the fuel supply system. This condition can be detected from Table 2 where it can be seen that the maximum run times on solid waste are identical for 2 boilers on several days. The quantity of steam generated using waste is calculated by subtracting the amount generated using natural gas from the total quantity of steam generated by all three boilers, which is metered. The steam generated by natural gas is calculated by applying the 0.79 factor mentioned above to the metered gas consumption. Figure 4 shows the steam generated by solid waste as a percent of total steam generated for the period from October 1, 1982 through October 2, This curve was generated from weekly performance data. Natural gas is only used to supply steam to uninterruptible customers when solid waste cannot be supplied to the boilers. Therefore, this figure provides an indication of total plant availability to process waste. However, owing to the fact that the number of boilers and total boiler capacity are large compared to current firm steam customer loads, it is believed that this curve is also a reasonable representation of solid waste fuel supply system availability. Tricil indicated that plant performance during the first. three months of 1983 was affected to some extent by "debugging" activities with the modified plant. SOLID WASTE SUPPLY AND ENERGY SALES The Akron plant has the dual purpose of disposing of 250

4 SCALE RECEIVING AND STORAGE SHREDD ER REJECT GRAPPLE CRANE RECEIVING AND STORAGE SHREDDER MAGNET IC SEPARAT OR PREPARED FUEL RECYCLE FERROUS RECOVERY BOILER BOILER BOILER!;:i t' V> 0 a: I U I.LJ a: «l Il. V> 0 a: t I.LJ ' Il. u I.LJ V> 0 a: Il. t I.LJ c..) (..) G.J ASH DISPOSAL STACK FIG.2 SIMPLIFIED FLOW DIAGRAM 251

5 _ AUg!!st 15, , , , TABLE 1 PERFORMANCE DATA 1983 January February March Aprll May June July Solid Waste tons 15,899 15,239 16,444 19,617 23,978 20,671 Received Steaa Produced 10 6 Ibs Ibs tv Vl tv Natural Gas Purchased ":F 32,617 57,232 42,292 18,528 17,806 14,817 Electricity: Purchased Generated b Total Ferrous Recovery Loads Ash Loads Rejects Loads

6 (f) (f) Z <t 0 a:: (f) c (!) z 9 u a:: (J) z w 0 CD CD O I 0 40, ,000 GR OSS STE AM PR ODUCTI ON 75 c w > LLI U W a:: 20,000 w (f) J c oj g 10,000 10,000 SOLI D WASTE RECEIVED STEAM SALES eo to STE AM PRO UCED WITH GAS o ot._..._j.._""""_l_lo J f M A M J A o MONTH FIG.3 PERFORMANCE DATA 1983 solid waste and providing energy to customers in the form of steam and hot water. In general, the plant has been operated at less than optimum conditions due to difficulties with both the solid waste supply and energy sales. Specifically, steam and hot water sales' have not been great enough to properly utilize the plant. Also, availability of solid waste during January through March was limited due to outside causes, thus affecting the plant throughput during that period. This factor must be taken into account in an evaluation of the plant performance to date. Efforts are currently under way to improve this situation to allow better utilization of the facuity. DISCUSSION OF OPERATIONS Solid waste is currently delivered to the plant within the following schedule: Monday Friday 7:00 a.m. 4:30 p.m. Saturday 7 :00 a.m. 2 :30 p.m. Sunday Closed This schedule combined with the existing storage capacity of approximately 1200 tons (1088 t) places a limit on the rate at which solid waste can be processed between Saturday afternoon and Monday morning. Solid waste tends to bridge in the storage pit. This problem has been solved by use of a special crane to resettle the waste. The shredder' has experienced one explosion since January. This caused damage to sheet metal parts but not to the shredder itself. The shredders are operated 12 hr each on a rotating basis. Performance has been satisfactory according to TricU. 253

7 TABLE 2 TYPICAL WEEKLY PERFORMANCE REPORT Waste (Tons) Residue No. Hrs of Solid Waste Operation Steam Generated Gas Gas Consumed M 1bs M Cu Ft Date Ash Rejects Ferro us B1r B1r B1r Waste Delivered Processed Loads Loads Loads M 1bs 16 M N N N VI lj"\ 17 T 18 W 4< 0.><: (1) (1) 19 TH 20 F 21 S S WEEK ,088

8 SPECIAL TEST 60 FIRE 4 DEC JAN FE8 M APR MAY JUN JUL AUG SEP MONTH FIG.4 PERCENT OF STEAM GENERATED BY SOLID WASTE The magnetic separator has had four outages since January. When this happens, the ferrous materials are run through the boilers which significantly increases boiler outage time due to jams in the grate system. Also, the excess air must be increased with ferrous materials included in the fuel. The boilers were originally rated at 126,000 lb/hr (57,204 kg/h) of steam at 560 psig (3861 ka), saturated when using air classified 6500 Btu/lb (361 1 Cal/) fuel and 95,600 lb/hr (43,402 kg/h) when burning 5450 Btu/ lb (3027 Cal/kg) fuel. Tricil claims their modified system produces a fuel closer in heating value to the 5450 Btu/lb (3027 Cal/kg) figure and with this fuel considers the maximum continuous steam capacity to be about 100,000 lb/ hr (45,400 kg/h). The boilers have been operated at this rating with no apparent problems. Tricil reports having operated the boilers as high as 120,000 lb/hr (54,480 kg/ h) with a fuel feed rate of 18 tons/hr (16.3 tph). Grate loading is reported to be the limiting factor. The tubes in one boiler were recently inspected ultrasonically and found to have no Significant wastage. The grate system is reported to be the most frequent cause of down time for the boilers. Aluminum cans melt onto or into the grates and are a particular problem. Grate life is presently estimated at 1 year. Tricil believes modifications to the grates could be made which would significantly reduce grate system problems. All three boilers are operated online during the winter months. Two boilers are operated during the summer months with scheduled outages planned during this period. The solid waste fuel supply system, taken as a whole, appears to be a limiting factor in minimizing natural gas consumption. Figure 4 suggests that a solid waste fuel system availability of 90 percent is reasonable. Tricil has indicated they have a target of 90 to 92 percent. They further stated that a redundancy in some of the solid waste fuel supply system components would be desirable but was not considered feasible for Akron due to physical limitations with the existing plant. Tricil reports that other parts of the plant such as the controls, ash system and electrostatic precipitators are performing well. SUMMARY The modification program for the Akron Recycle Energy System has improved the performance of the plant significantly. The plant has demonstrated the ability to provide a reliable supply of energy to customers using solid waste for more than 80 percent of the fuel requirements. Calculations indicate that more than 1100 TPD (998 tpd) of solid waste can be processed through the plant assuming a solid waste fuel system availability of 90 percent. This has been confirmed by actual operation, and compares favorably with the original plant average design capacity of 1000 TPD (907 tpd). 255

9 ACKNOWLEDGMENTS The authors wish to thank Mr. Thomas Smith, Engineer for the City of Akron for providing data used in this report. Special thanks also go to Mr. Ralph Iacono of Tricil Resources, Inc. for providing plant records and operating information. 256

Refuse-to-Energy Facility

Refuse-to-Energy Facility Commerce Refuse-to-Energy Facility Waste Diversion: A Challenge for Southern California Communities Los Angeles County successfully diverts more than 50 percent of the solid waste generated each day from

More information

Central Heating Plants EU 311

Central Heating Plants EU 311 Central Heating Plants EU 311 Jay Becker, P.E. KEY POINTS TAKE AWAYS Why Central Plants? Boilers & Fuels Water Treatment Environmental Issues Clean Air & Clean Water COURSE OVERVIEW Central vs. Individual

More information

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET 1. A vessel of volume 0.04m 3 contains a mixture of saturated water and steam at a temperature of 250 0 C. The mass of the liquid present is 9 kg. Find the pressure, mass, specific volume, enthalpy, entropy

More information

Welcome to. Kendal Power Station

Welcome to. Kendal Power Station Welcome to Kendal Power Station Technical Overview of the power station Scope General Overview Coal Handling Milling Plant Boiler Plant Turbine Train Steam Flow Path Ash Handling Generator HV Yard Cooling

More information

CHP Case Studies. Midwest CHP Application Center (MAC) .org (312) University of Illinois at Chicago Energy Resources Center UIC

CHP Case Studies. Midwest CHP Application Center (MAC) .org (312) University of Illinois at Chicago Energy Resources Center UIC CHP Case Studies Midwest CHP Application Center (MAC) www.chpcentermw.org.org (312)413-5448 University of Illinois at Chicago Energy Resources Center CHP Case Studies Elgin Community College Presbyterian

More information

ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE AT COVANTA S HAVERHILL FACILITY

ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE AT COVANTA S HAVERHILL FACILITY Proceedings of the 18th Annual North American Waste-to-Energy Conference NAWTEC18 May 11-13, 2010, Orlando, Florida, USA Paper Number: NAWTEC18-3563 ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE

More information

Hamm MW Pyrolysis Plant. Integrated Pyrolysis into Power Plant Plant capacity 100,000 t/a Pre-processed Waste Materials

Hamm MW Pyrolysis Plant. Integrated Pyrolysis into Power Plant Plant capacity 100,000 t/a Pre-processed Waste Materials Integrated Pyrolysis into Power Plant Plant capacity 100,000 t/a Pre-processed Waste Materials Schematic Flow sheet Integrated Pyrolysis for Power Plants Pyrolysis of high calorific solid recovered fuels

More information

Report from visit of Dr. A.C.(Thanos) Bourtsalas and ten EEE graduate students to WTE facility in West Palm Beach, Florida, May 2016

Report from visit of Dr. A.C.(Thanos) Bourtsalas and ten EEE graduate students to WTE facility in West Palm Beach, Florida, May 2016 Report from visit of Dr. A.C.(Thanos) Bourtsalas and ten EEE graduate students to WTE facility in West Palm Beach, Florida, May 2016 Report by Ms. Yenaxika Bolate (EEE graduate) 1 1. General information

More information

Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat

Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat Vikrant Bhardwaj 1, Rohit Garg 2, Mandeep Chahal 3, Baljeet Singh 4 1 Asstt. Professor in Deptt. Of Mechanical Engineering, IIET, (Kinana) Jind

More information

Biomass Design & Potential

Biomass Design & Potential Biomass Design & Potential Mark Froling President Office & PDC Production Facility: 590 Hancock Road, Peterborough, NH Biomass Design & Potential This course covers: The considerations one should make

More information

Opportunities and Challenges Waste to Energy Industry

Opportunities and Challenges Waste to Energy Industry Opportunities and Challenges Industry IMIA Conference, Istanbul September 2009 Mike Robertson Liberty International Underwriters Opportunities and Challenges Industry Dynamics and Profile Key Process Features

More information

KAMENGO. FGD (SYNTHETIC) GYPSUM STORAGE AND FEED (2013) Fort McMurray, Alberta, Canada

KAMENGO. FGD (SYNTHETIC) GYPSUM STORAGE AND FEED (2013) Fort McMurray, Alberta, Canada FGD (SYNTHETIC) GYPSUM STORAGE AND FEED (2013) SUMMARY FEEDERS: BIN STORAGE: POWER: CAPACITY: (1) Kamengo Feeder 525 cu-ft bin 30HP motor 50 t/hr SIMILAR PROJECTS Recycled Gypsum Storage and Feed (1994)

More information

Smart CHP from Biomass and Waste

Smart CHP from Biomass and Waste Smart CHP from Biomass and Waste It Cost Money to Throw Energy Away Gasification Technology Conference William (Bill) Partanen, P.E October 13-16, 2013 Colorado Springs, CO. SRF and RDF and recycled wood

More information

Biomass Gasification

Biomass Gasification Biomass Gasification Efficient use of Energy Turning waste to energy, liabilities to assets and visions into reality. Table of Contents THE HTI ADVANTAGE...................... 1 FEED SYSTEMS..........................

More information

\ t l_---t---iower turbulent

\ t l_---t---iower turbulent AIR CLASSIFIER PERFORMANCE AND OPERATING PRINCIPLES DONALD L. MURRAY All is-chal mers Appleton, Wisconsin ABSTRACT Allis-Chalmers involvement in solid waste processing began in the late 1960's. An air

More information

TECHNICAL PUBLICATION

TECHNICAL PUBLICATION TECHNICAL PUBLICATION REFURBISHMENT OF AN EXISTING 1000 TPD MSW FACILITY USING MODERN STATE-OF-THE-ART EQUIPMENT by Craig Gillum, Staff Engineer Babcock Borsig Power, Inc. and Arthur Cole, Vice President

More information

Newman Station Units 1, 2, and 4 Condition Assessment Report. El Paso Electric, Inc. El Paso, TX

Newman Station Units 1, 2, and 4 Condition Assessment Report. El Paso Electric, Inc. El Paso, TX Newman Station Units 1, 2, and 4 Condition Assessment Report prepared for El Paso Electric, Inc. El Paso, TX April 2010 Project No. 53549 prepared by Burns & McDonnell Engineering Company, Inc. COPYRIGHT

More information

Proven. The Stirling Power Boiler. Food products Municipal solid waste Ethanol / sugar cane Power

Proven. The Stirling Power Boiler. Food products Municipal solid waste Ethanol / sugar cane Power Since 1867, the Babcock & Wilcox (B&W) name has been synonymous with quality, dependability and service. Today, B&W continues to supply quality steam generation equipment to utilities and industry worldwide.

More information

Feed Mill Design. By Fred J. Fairchild, P. E. Department of Grain Science and Industry Kansas State University

Feed Mill Design. By Fred J. Fairchild, P. E. Department of Grain Science and Industry Kansas State University Feed Mill Design By Fred J. Fairchild, P. E. Department of Grain Science and Industry Kansas State University Planning Determine Needs Determine Purpose Design to Requirements Product Mix Bulk Feeds Mash

More information

Shredders for Pallet Recycling

Shredders for Pallet Recycling Shredders for Pallet Recycling Table of contents Introduction...3 Possible end products...4 Considerations.. 5 Two-phase system 6-11 System diagram. 12 Brochures.. 13-17 Contact us...18 Pallets, pallets

More information

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service

More information

Design Considerations for Advanced Combined Cycle Plant Using Fast Start Drum Type HRSGs

Design Considerations for Advanced Combined Cycle Plant Using Fast Start Drum Type HRSGs Presented To: Hot Topic Hour A Babcock Power Inc. Company By: Deron Johnston Date: Mar.7/13 Design Considerations for Advanced Combined Cycle Plant Using Fast Start Drum Type HRSGs Authors: Akber Pasha,

More information

NAWTEC HANDLING OAHU S WASTE DISPOSAL

NAWTEC HANDLING OAHU S WASTE DISPOSAL Proceedings of the 17th Annual North American Waste-to-Energy Proceedings of Conference NAWTEC17 17th Annual North American Waste-to-Energy NAWTEC17 Conference May 18-20, 2009, Chantilly, Maryland, Virginia,

More information

Fact Sheet. Feb 2011

Fact Sheet. Feb 2011 Fact Feb 2011 Energy Recovery index Fact 1. DESCRIPTION OF TECHNOLOGY 2. CURRENT DISTRIBUTION AND PROSPECTIVE OF TECHNOLOGY 3. Legal and political FRAMEWORK 3.1 Landfill Directive 3.2 Waste incineration

More information

Entech Pollutec 2014 WASTE TO ENERGY BY TYRANNOSAURUS SOLUTIONS

Entech Pollutec 2014 WASTE TO ENERGY BY TYRANNOSAURUS SOLUTIONS Entech Pollutec 2014 WASTE TO ENERGY BY TYRANNOSAURUS SOLUTIONS Attractive Thailand! Relatively big population => Lot of waste => Lot of resources for power production 1,5 kg of MSW per person per day

More information

Union College Combined Cooling, Heat and Power Project

Union College Combined Cooling, Heat and Power Project Union College Combined Cooling, Heat and Power Project Presented by: Mark Donovan, PE Union College, Assistant Director of Utilities Aaron Bolhous, PEng CHA, Project Engineer Agenda Introduction to Union

More information

Post Combustion CO 2 Capture Scale Up Study

Post Combustion CO 2 Capture Scale Up Study Post Combustion CO 2 Capture Scale Up Study Prachi Singh and Mike Haines International Greenhouse Gas R&D programme 6 th International Conference on Clean Coal Technologies (CCT 2013) 12-16 th May 2013

More information

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN (EXECUTIVE SESSION) November, 2007 JAPAN EXTERNAL TRADE ORGANIZATION JAPAN CONSULTING INSTITUTE SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN 1. Power Generation

More information

Bulk Bag Filling. Dust-free filling and weighing of Bulk Bags, Rigid Bins, Drums and IBCs

Bulk Bag Filling. Dust-free filling and weighing of Bulk Bags, Rigid Bins, Drums and IBCs Bulk Bag Filling Dust-free filling and weighing of Bulk Bags, Rigid Bins, Drums and IBCs Bulk Bag Weigh Fillers DESIGNED FOR VERSATILITY. BUILT FOR ADAPTABILITY. Over 100 million bulk bags are sold each

More information

Downsizing a Claus Sulfur Recovery Unit

Downsizing a Claus Sulfur Recovery Unit INFRASTRUCTURE MINING & METALS NUCLEAR, SECURITY & ENVIRONMENTAL Downsizing a Claus Sulfur Recovery Unit OIL, GAS & CHEMICALS By Charles L. Kimtantas and Martin A. Taylor ckimtant@bechtel.com & mataylo1@bechtel.com

More information

Ground-Coupled Heat Pump And Energy Storage

Ground-Coupled Heat Pump And Energy Storage Ground-Coupled Heat Pump And Energy Storage By Ed Lohrenz, Member ASHRAE; and Sergio Almeida, P.Eng., Member ASHRAE Ground-coupled heat pump (GCHP) systems consume less purchased energy than an HVAC system

More information

2,400 TONS PER DAY REFUSE DERIVED FUEL FACILITY WITH ADVANCED BOILER AND AIR POLLUTION CONTROL SYSTEMS

2,400 TONS PER DAY REFUSE DERIVED FUEL FACILITY WITH ADVANCED BOILER AND AIR POLLUTION CONTROL SYSTEMS Proceedings of the 18th Annual North American Waste-to-Energy Conference NAWTEC18 May 11-13, 2010, Orlando, Florida, USA NAWTEC18-3549 2,400 TONS PER DAY REFUSE DERIVED FUEL FACILITY WITH ADVANCED BOILER

More information

TACOMA STEAM PLANT NO.2 REPOWERING PROJECT: A MULTIFUELED SOLID WASTE FACILITY

TACOMA STEAM PLANT NO.2 REPOWERING PROJECT: A MULTIFUELED SOLID WASTE FACILITY TACOMA STEAM PLANT NO.2 REPOWERING PROJECT: A MULTIFUELED SOLID WASTE FACILITY GREGORY L. FORD HDR Engineering, Inc. Minneapolis, Minnesota ABSTRACT Steam Plant No. 2 of the municipal utility system of

More information

OXYGEN ENRICHMENT OF COMBUSTION AIR IN A 360 TPD MASS BURN REFUSE-FIRED WATERWALL FURNACE

OXYGEN ENRICHMENT OF COMBUSTION AIR IN A 360 TPD MASS BURN REFUSE-FIRED WATERWALL FURNACE OXYGEN ENRICHMENT OF COMBUSTION AIR IN A 360 TPD MASS BURN REFUSE-FIRED WATERWALL FURNACE WILLIAM S. STRAUSS AND JOHN A. LUKENS Harrisburg Steam Generating Facility Harrisburg, Pennsylvania FLORIO K. YOUNG

More information

Garden Street Iron & Metal Processes 8,000 Tons of Scrap Each Month Using

Garden Street Iron & Metal Processes 8,000 Tons of Scrap Each Month Using Garden Street Iron & Metal Processes 8,000 Tons of Scrap Each Month Using Variety of Eriez Recycling Equipment Starting a family business and keeping it going for more than 55 years takes dedication, resourcefulness,

More information

Chapter 2.6: FBC Boilers

Chapter 2.6: FBC Boilers Part-I: Objective type questions and answers Chapter 2.6: FBC Boilers 1. In FBC boilers fluidization depends largely on --------- a) Particle size b) Air velocity c) Both (a) and (b) d) Neither (a) nor

More information

Refuse Collections Division Solid Waste Services Department Anchorage: Performance. Value. Results.

Refuse Collections Division Solid Waste Services Department Anchorage: Performance. Value. Results. Refuse Collections Division Solid Waste Services Department Anchorage: Performance. Value. Results. Mission Provide solid waste collection and disposal service to rate-paying customers within our defined

More information

Enhanced usage of Alternative Fuels in Cement Industry

Enhanced usage of Alternative Fuels in Cement Industry ALTERNATE FUEL --- MSW RDF BY V. P. TONDAPURKAR ROCHEM GREEN ENERGY PVT LTD MUMBAI 51 1 UNDERSTANDING OF CEMENT INDUSTRY - Cement Production India Year Capacity Mn T 2010 228.3 2014 255.6 2024 666 Plant

More information

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Styrene

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Styrene Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Styrene The feasibility of constructing a new, grass-roots, 100,000 tonne/y, styrene plant is being investigated. As part of

More information

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Ammonia Your assignment is to continue evaluating the details of a process to produce 50,000 tonne/y of ammonia from a syngas

More information

Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on

Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on Chapter 10, Problem 8C. Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on Pump work input: Turbine work output: Heat supplied:

More information

Equipment Design. Detailed Plant Conceptual Design. Version 9.0

Equipment Design.  Detailed Plant Conceptual Design. Version 9.0 Equipment Design Version 9.0 Detailed Plant Conceptual Design SOAPP CT sizes all major plant equipment, based on your Project Input, the process configuration derived from this input, and the results of

More information

Electric Furnace Off-Gas Cleaning Systems Installation at PT Inco ABSTRACT

Electric Furnace Off-Gas Cleaning Systems Installation at PT Inco ABSTRACT Electric Furnace Off-Gas Cleaning Systems Installation at PT Inco Paykan Safe and Matt Russell WorleyParsons Gas Cleaning, Irving, Texas USA ABSTRACT PT Inco is a ferronickel smelter in Soroako, Sulawesi,

More information

PAPER NUMBER 64-GTP-16 S. T. ROBINSON J. W. GLESSNER. Solar, A Division of International Harvester Company, San Diego, Calif. Mems. ASME.

PAPER NUMBER 64-GTP-16 S. T. ROBINSON J. W. GLESSNER. Solar, A Division of International Harvester Company, San Diego, Calif. Mems. ASME. PAPER NUMBER 4-GTP-1 Copyright 194 by ASME AN ASME PUBLICATION Total Turbine Energy in Refrigeration Cycles S. T. ROBINSON J. W. GLESSNER Solar, A Division of International Harvester Company, San Diego,

More information

Non-Toxic, OEM Compliant Metal Protection. A Surface-Active Metal Passivation Technology For Low, Medium & High Pressure Boilers

Non-Toxic, OEM Compliant Metal Protection. A Surface-Active Metal Passivation Technology For Low, Medium & High Pressure Boilers Non-Toxic, OEM Compliant Metal Protection A Surface-Active Metal Passivation Technology For Low, Medium & High Pressure Boilers HOW DOES IT WORK? Video Example of No Surface-Active Chemistry Protection

More information

Performance Analysis of Cement manufacturing Industry

Performance Analysis of Cement manufacturing Industry www.ijecs.in International Journal Of Engineering And Computer Science ISSN:2319-7242 Volume 4 Issue 3 March 2015, Page No. 10937-10941 Performance Analysis of Cement manufacturing Industry Neeraj Pandagre

More information

DUAL REPRESENTATION OF MINIMUM ENERGY REQUIREMENTS APPLICATIONS TO P&P PROCESSES

DUAL REPRESENTATION OF MINIMUM ENERGY REQUIREMENTS APPLICATIONS TO P&P PROCESSES Congrès s Annuel ATIP Annecy 27-29 29 avril 2005 DUAL REPRESENTATION OF MINIMUM ENERGY REQUIREMENTS APPLICATIONS TO P&P PROCESSES David Brown Zoé Périn-Levasseur François Maréchal Jean Paris EP Montréal

More information

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES This article was published in ASHRAE Journal, January 2014. Copyright 2014 ASHRAE. Posted at www. ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission

More information

CSX TRANSPORTATION GUIDELINES FOR THE DEVELOPMENT OF COAL UNIT TRAIN FASTLOAD ORIGINS

CSX TRANSPORTATION GUIDELINES FOR THE DEVELOPMENT OF COAL UNIT TRAIN FASTLOAD ORIGINS CSX TRANSPORTATION GUIDELINES FOR THE DEVELOPMENT OF COAL UNIT TRAIN FASTLOAD ORIGINS Coal Development Department A) OVERVIEW CSXT s Coal Development Department is located in Lexington, Kentucky, which

More information

SAUDER WOODWORKING COMPANY: A WASTE WOOD ELECTRIC GENERATING FACILITY

SAUDER WOODWORKING COMPANY: A WASTE WOOD ELECTRIC GENERATING FACILITY National Waste Processing Conference Proceedings ASME 1994 SAUDER WOODWORKING COMPANY: A WASTE WOOD ELECTRIC GENERATING FACILITY NEIL H. JOHNSON SFf, Incorporated Toledo, Ohio ABSTRACT Sauder Woodworking

More information

Automated Aluminum & Steel Stacking. Solutions

Automated Aluminum & Steel Stacking. Solutions Automated Aluminum & Steel Stacking Solutions Overview Atlas Technologies blank stacking systems reduce manual handling, improve surface finish quality and increase production of cut-to length operations

More information

PRIMARY OR ALTERNATIVE OPERATING SCENARIO

PRIMARY OR ALTERNATIVE OPERATING SCENARIO EMISSION SOURCE (Fuel Combustion Source) Instructions for Form B2 Form B2 should be completed for all fuel combustion emission sources (e.g., generators, boilers, burn-off ovens, bakeon ovens, bakery ovens,

More information

A Solid aste Utilization SysteIll for St. Louis

A Solid aste Utilization SysteIll for St. Louis A Solid aste Utilization SysteIll for St. Louis DAVID L. KLUMB and EARL M. WELLS ABSTRACT This paper describes the waste processing and boiler feed facilities which serve as the prototype for Union Electric

More information

Metal and Particulate Emissions from Incinerators Burning Sewage Sludge and Mixed Refuse

Metal and Particulate Emissions from Incinerators Burning Sewage Sludge and Mixed Refuse Metal and Particulate Emissions from Incinerators Burning Sewage Sludge and Mixed Refuse F. l. CROSS, JR. R. J. DRAGO H. E. FRANCIS Roy F. Weston West Chester, Pennsylvania National Air Pollution Control

More information

On-Line Carbon in Ash System at PPL Montour for Increasing Ash Sales

On-Line Carbon in Ash System at PPL Montour for Increasing Ash Sales 2013 World of Coal Ash (WOCA) Conference - April 22-25, 2013 in Lexington, KY http://www.flyash.info/ On-Line Carbon in Ash System at PPL Montour for Increasing Ash Sales Todd Melick 1, Larry LaBuz 2,

More information

Waste Heat Recovery as an Alternative Energy Source

Waste Heat Recovery as an Alternative Energy Source Waste Heat Recovery as an Alternative Energy Source D. Paul Mehta and Ryan Esch, Bradley University ABSTRACT Heat recovery can substantially lower the operating costs for a manufacturing facility by utilizing

More information

Coal to Gas Capability Benefits & Impacts

Coal to Gas Capability Benefits & Impacts Coal to Gas Capability Benefits & Impacts Presented to: Southeastern Construction Owners & Associates Roundtable Edward C. Healy, P.E. October 13, 2016 Presentation Outline Southern Company Overview Southern

More information

Waste to Energy WTERT, N.Y., October 2008

Waste to Energy WTERT, N.Y., October 2008 Waste to Energy MUNICIPAL SOLID WASTE INCINERATION WITH SIMULTANEOUS ENERGY PRODUCTION (WASTE TO ENERGY) MUNICIPAL SOLID WASTE TREATMENT IN THE SURROUNDINGS ATHENS REGION One of the most important political

More information

Seal Main HCSS Pilot Approval Annual Performance Presentation

Seal Main HCSS Pilot Approval Annual Performance Presentation Seal Main HCSS Pilot Approval 11377 Annual Performance Presentation 11-Feb-2015 Agenda Introductions Seal Main Horizontal Cyclic Steam Stimulation (HCSS) Pilot Subsurface Surface Harmon Valley South HCSS

More information

Retrofit of Rodenhuize 4 power station: The Max Green and Cold Back-up-projects

Retrofit of Rodenhuize 4 power station: The Max Green and Cold Back-up-projects Retrofit of Rodenhuize 4 power station: The Max Green and Cold Back-up-projects Dr. Stefan Hamel, Babcock Borsig Steinmüller GmbH Dr. Christian Storm, Babcock Borsig Steinmüller GmBH Peter Goorden, Project

More information

A Thermal Processing Plant in Thailand. A Case Study of Oil Palm Residues

A Thermal Processing Plant in Thailand. A Case Study of Oil Palm Residues A Thermal Processing Plant in Thailand A Case Study of Oil Palm Residues Case Study: Thermal Process Plant in Thailand START Technological Considerations Social-Cultural Considerations Environmental Considerations

More information

Feedwater Heaters (FWH)

Feedwater Heaters (FWH) Feedwater Heaters (FWH) A practical Regeneration process in steam power plants is accomplished by extracting or bleeding, steam from the turbine at various points. This steam, which could have produced

More information

Control Options For FPI Boilers to Meet Proposed Boiler MACT Limits

Control Options For FPI Boilers to Meet Proposed Boiler MACT Limits Control Options For FPI Boilers to Meet Proposed Boiler MACT Limits by Arun V. Someshwar NCASI West Coast Regional Meeting Vancouver, WA September 30, 2010 1 Outline Currently available options for control

More information

Carrington Power Station

Carrington Power Station Carrington Power Station INTRODUCTION 01 Welcome to Carrington Power Station Carrington Power Station is a 884.2MW plant that generates enough electricity to power more than one million homes and businesses.

More information

ENGINEERED SOLUTIONS ENERGY ENVIRONMENTAL

ENGINEERED SOLUTIONS ENERGY ENVIRONMENTAL ENGINEERED SOLUTIONS ENERGY ENVIRONMENTAL As a technology innovator, Babcock & Wilcox (B&W) provides a comprehensive package of engineered solutions for a wide range of applications. Established in 1867,

More information

Dust Recycling System by the Rotary Hearth Furnace

Dust Recycling System by the Rotary Hearth Furnace UDC 669. 054. 83 : 66. 041. 49 Dust Recycling System by the Rotary Hearth Furnace Hiroshi ODA* 1 Tetsuharu IBARAKI* 1 Youichi ABE* 2 Abstract Dust recycling technology by the rotary hearth furnace has

More information

IRISH CEMENT PLATIN INVESTING IN OUR FUTURE

IRISH CEMENT PLATIN INVESTING IN OUR FUTURE IRISH CEMENT PLATIN INVESTING IN OUR FUTURE INTRODUCTION Investing in our future. The next phase of investment in Platin will see further energy efficiency improvements with on site electricity generation

More information

CANSOLV SO2 Scrubbing System - 10 Years of Reliable Operation Integration with SRU Tail Gas Incineration

CANSOLV SO2 Scrubbing System - 10 Years of Reliable Operation Integration with SRU Tail Gas Incineration CANSOLV SO2 Scrubbing System - 1 Years of Reliable Operation Integration with SRU Tail Gas Incineration NICOLAS EDKINS, NANCY MORETON Cansolv Technologies Inc. (an affiliate of Shell Global Solutions BV)

More information

PINCH ANALYSIS: For the Efficient Use of Energy, Water & Hydrogen. PULP AND PAPER INDUSTRY Energy Recovery and Effluent Cooling at a TMP Plant

PINCH ANALYSIS: For the Efficient Use of Energy, Water & Hydrogen. PULP AND PAPER INDUSTRY Energy Recovery and Effluent Cooling at a TMP Plant PINCH ANALYSIS: For the Efficient Use of Energy, Water & Hydrogen PULP AND PAPER INDUSTRY Energy Recovery and Effluent Cooling at a TMP Plant PINCH ANALYSIS: For the Efficient Use of Energy, Water & Hydrogen

More information

BUILDING FOR THE FUTURE

BUILDING FOR THE FUTURE BUILDING FOR THE FUTURE The following article was published in ASHRAE Journal, September 4. Copyright 4 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented

More information

B-95S. Food Equipment Metal Separation, METAL Detection AND Material Handling

B-95S. Food Equipment Metal Separation, METAL Detection AND Material Handling B-95S Food Equipment Metal Separation, METAL Detection AND Material Handling Eriez Programs for the Food Industry ProGrade Magnets A full line of low-cost magnetic separators ready to ship. PROGRADE features

More information

Stokers, CHP, Isolated Power Units

Stokers, CHP, Isolated Power Units Stokers, CHP, Isolated Power Units Stoker Boilers The term stoker implies a boiler that automatically feeds (or " stokes ) the boiler. Stoker coal size is typically 1.25 inches maximum with less than 30%

More information

The Locomotive. A Copper-Plated Thief: The Problem of Copper Deposits in Turbines

The Locomotive. A Copper-Plated Thief: The Problem of Copper Deposits in Turbines A Copper-Plated Thief: The Problem of Copper Deposits in Turbines By Dave Daniels and John Latcovich, The Hartford Steam Boiler Introduction Operators at a coal-fired, 2,600 PSI power plant performed monthly

More information

Dalmia Cement (Bharat) Limited, Kadapa 1 st Workshop on Energy Efficiency in Cement Sector 23 rd June 2015

Dalmia Cement (Bharat) Limited, Kadapa 1 st Workshop on Energy Efficiency in Cement Sector 23 rd June 2015 Dalmia Cement (Bharat) Limited, Kadapa 1 st Workshop on Energy Efficiency in Cement Sector 23 rd June 2015 Presented by :Mr. P. Kamalanathan Manager Electrical p.kamalanathan@dalmiacement.com Dalmia Cement

More information

Condenser Water Heat Recovery"

Condenser Water Heat Recovery PLEASE MUTE CELL PHONES Condenser Water Heat Recovery" Julian de Bullet ASHRAE Distinguished Lecturer Director of Industry Relations McQuay International 703-395-5054 1 What Is Sustainability? sustainable

More information

WASTE MANAGEMENT IN BRAZIL. Dr. Sergio Guerreiro Ribeiro University of Brasil Rio de Janeiro (UFRJ) Chairman, WTERT-Brasil

WASTE MANAGEMENT IN BRAZIL. Dr. Sergio Guerreiro Ribeiro University of Brasil Rio de Janeiro (UFRJ) Chairman, WTERT-Brasil WASTE MANAGEMENT IN BRAZIL Dr. Sergio Guerreiro Ribeiro University of Brasil Rio de Janeiro (UFRJ) Chairman, WTERT-Brasil WTERT-Brasil homepage www.wtert.com.br BRAZIL APPROVED NEW SOLID WASTE MANAGEMENT

More information

Refurbishment of an Existing 1000 TPD MSW Facility Using Modem State of the Art Equipment

Refurbishment of an Existing 1000 TPD MSW Facility Using Modem State of the Art Equipment 10th North American Waste to Energy Conference ASME 2002 NAWTEC101004 Refurbishment of an Existing 1000 TPD MSW Facility Using Modem State of the Art Equipment Craig Gillum Staff Engineer Babcock Borsig

More information

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3 DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3 This chapter provides details regarding the scope of the proposed Gourikwa Power Station and Transmission Integration

More information

Development status of the EAGLE Gasification Pilot Plant

Development status of the EAGLE Gasification Pilot Plant Development status of the EAGLE Gasification Pilot Plant Gasification Technologies 2002 San Francisco, California, USA October 27-30, 2002 Masaki Tajima Energy and Environment Technology Development Dept.

More information

Kawasaki Gas Turbines-Americas Gas Turbines Power Generation Technology & Applications

Kawasaki Gas Turbines-Americas Gas Turbines Power Generation Technology & Applications Kawasaki Gas Turbines-Americas Gas Turbines Power Generation Technology & Applications Gas Turbine (GT) Technology Overview Gas Turbine Theory GT - Centrifugal Compressor FUEL INLET COMBUSTION CHAMBER

More information

ENERGY AUDIT. 123 Main Street Mississauga, Ontario. January 1, Report To: Mr. John Smith Smith Printing Company.

ENERGY AUDIT. 123 Main Street Mississauga, Ontario. January 1, Report To: Mr. John Smith Smith Printing Company. Report To: Mr. John Smith Smith Printing Company ENERGY AUDIT 123 Main Street Mississauga, Ontario January 1, 2009 120 Carlton Street, Suite 212 Toronto, Ontario M5A 4K2 Tel 416-964-3246 Toll Free 1-866-964-3246

More information

Case Studies in Energy Efficiency and Water Conservation Projects

Case Studies in Energy Efficiency and Water Conservation Projects Case Studies in Energy Efficiency and Water Conservation Projects Introduction About PepsiCo World leader in convenient snacks, foods and beverages + $60 billion revenues + 285,000 employees Fortune 50

More information

Kompogas dry anaerobic digestion Energy from organic waste

Kompogas dry anaerobic digestion Energy from organic waste Kompogas dry anaerobic digestion Energy from organic waste 2 I 3 Kompogas dry anaerobic digestion Energy from organic waste From a waste to a resource economy The Kompogas technology converts organic waste

More information

Chariton Valley Biomass Project

Chariton Valley Biomass Project Chariton Valley Biomass Project Research / Reports Equipment Development Processing Facility Outreach Crop Studies & Cost Baler Development June 2005 Public Outreach Soil Stability/Erosion/Carbon Bale

More information

The Cardiac Arrest of Hot Mix Asphalt Pavements

The Cardiac Arrest of Hot Mix Asphalt Pavements The Cardiac Arrest of Hot Mix Asphalt Pavements Timothy R. Murphy, P.E. President What Are You Really Going To Remember from this Convention? What will you really remember most about today? 70% of what

More information

Reduction Systems and Equipment at Moss Landing Power Plant

Reduction Systems and Equipment at Moss Landing Power Plant B&W s NO x Reduction Systems and Equipment at Moss Landing Power Plant Presented to: ICAC NO x Forum March 23-24, 2000 Washington D.C., U.S.A. Bill Becker Don Tonn Babcock & Wilcox Barberton, Ohio, U.S.A.

More information

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012 Cogeneration and Thermal Chillers.. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012 Agenda Cogeneration Interest and Application Basics Equipment Matching Thermal Chiller Overview Steam Components

More information

China - Canada Co-operation Project in Cleaner Production. Checklist for Cleaner Production Auditing in Pulp and Paper Mills

China - Canada Co-operation Project in Cleaner Production. Checklist for Cleaner Production Auditing in Pulp and Paper Mills China - Canada Co-operation Project in Cleaner Production Checklist for Cleaner Production Auditing in Pulp and Paper Mills TABLE OF CONTENTS Page 1. GENERAL INFORMATION... 1 2. CONCERNING THE FACILITY...3

More information

ANNUAL ENERGY PERFORMANCE OF SOLAR THERMAL SYSTEMS IN BRAŞOV, ROMANIA

ANNUAL ENERGY PERFORMANCE OF SOLAR THERMAL SYSTEMS IN BRAŞOV, ROMANIA Bulletin of the Transilvania University of Braşov Series I: Engineering Sciences Vol. 5 (54) No. 2-212 ANNUAL ENERGY PERFORMANCE OF SOLAR THERMAL SYSTEMS IN BRAŞOV, ROMANIA C. ŞERBAN 1 E. EFTIMIE 1 Abstract:

More information

1 st Renewable Energy Technologies, LP. Organic Rankine Cycle

1 st Renewable Energy Technologies, LP. Organic Rankine Cycle 11/18/2010 1 st Renewable Energy Technologies, LP 8147 Clear Shade Drive, Windber, PA 15963 Phone: (814) 467-0431 Fax: (814) 467-8675 Email: Sales@1stRET.com Web: www.1stret.com Organic Rankine Cycle The

More information

Geothermic Fuel Cell Applications in Coal Coal Gasification---Coal to Liquids (Summary Highlights)

Geothermic Fuel Cell Applications in Coal Coal Gasification---Coal to Liquids (Summary Highlights) Geothermic Fuel Cell Applications in Coal Coal Gasification---Coal to Liquids (Summary Highlights) Introduction Historically, capital costs of Fischer-Tropsch (FT) coal-to-liquids projects have been high.

More information

DUDLEY ENERGY FROM WASTE PLANT. PERMIT No AP3435SD WASTE INCINERATION DIRECTIVE ANNUAL REPORT

DUDLEY ENERGY FROM WASTE PLANT. PERMIT No AP3435SD WASTE INCINERATION DIRECTIVE ANNUAL REPORT DUDLEY ENERGY FROM WASTE PLANT PERMIT No AP3435SD WASTE INCINERATION DIRECTIVE ANNUAL REPORT 2011 1 CONTENTS Page Introduction 3 Non technical plant description 4 Plant operation 5 Annual waste throughputs

More information

DOE Best Practice Software Tools. Joseph Chappell Adam Roget

DOE Best Practice Software Tools. Joseph Chappell Adam Roget DOE Best Practice Software Tools Joseph Chappell Adam Roget DOE Software Tool Use Over the past year 12 regular IAC assessments 3 large energy user assessments 1 SEN type assessment for a local hospital

More information

Gasification Based Biomass Cofiring Project

Gasification Based Biomass Cofiring Project National Energy Technology Laboratory Co-op Agreement No. DE-PS26-00NT 40898 Gasification Based Biomass Cofiring Project Integration of poultry litter gasification with conventional PC fired power plant

More information

ENERGY SOURCE ESI. A Newsletter published by. The Steam and Power SPECIAL FORCES

ENERGY SOURCE ESI. A Newsletter published by. The Steam and Power SPECIAL FORCES ENERGY SOURCE A Newsletter published by ESI The Steam and Power SPECIAL FORCES Summer 2010 Consider This... Designing a Successful Biomass Material Handling System Part 2 : Material Receiving System Design

More information

ENERGY EFFICIENCY AND EMISSION REDUCTION OF TPM, PM 2.5, AND SO 2 FROM NATURAL GAS AND FUEL OIL FIRED BOILER EXHAUSTS

ENERGY EFFICIENCY AND EMISSION REDUCTION OF TPM, PM 2.5, AND SO 2 FROM NATURAL GAS AND FUEL OIL FIRED BOILER EXHAUSTS ENERGY EFFICIENCY AND EMISSION REDUCTION OF TPM, PM 2.5, AND SO 2 FROM NATURAL GAS AND FUEL OIL FIRED BOILER EXHAUSTS Robert W. Triebe, M.A.Sc., P.Eng. CTO, Thermal Energy International Inc. Robert A.

More information

Zero Waste to the Landfill Unifi s Experience. April 2014

Zero Waste to the Landfill Unifi s Experience. April 2014 Zero Waste to the Landfill Unifi s Experience April 2014 Background on Solid Waste Reduction Strong history of recycling and minimizing waste to the landfill Dedicated company recycling facility (Topsider)

More information

Steam Power Station (Thermal Station)

Steam Power Station (Thermal Station) Steam Power Station (Thermal Station) A generating station which converts heat energy into electrical energy through turning water into heated steam is known as a steam power station. A steam power station

More information

Worldwide Pollution Control Association. August 3-4, 2010

Worldwide Pollution Control Association. August 3-4, 2010 Worldwide Pollution Control Association IL Regional Technical Seminar August 3-4, 2010 Visit our website at www.wpca.infowpca An Unbiased Comparison of FGD Technologies: Wet, Spray Dry and CDS WPCA Conference

More information