Proposed Windhoek - Gocheganas Road upgrade. Environmental Assessment Scoping Risk Report

Size: px
Start display at page:

Download "Proposed Windhoek - Gocheganas Road upgrade. Environmental Assessment Scoping Risk Report"

Transcription

1 Proposed Windhoek - Gocheganas Road upgrade Environmental Assessment

2 COPYRIGHT ENVIRO DYNAMICS, ALL RIGHTS RESERVED PROJECT NAME STAGE OF REPORT CLIENT LEAD CONSULTANT DATE OF RELEASE AUTHOR MAPPING FORMATTING, EDITING INTERNAL REVIEW Environmental Assessment Proposed Windhoek- Gocheganas Road upgrade Environmental Roads Authority Enquiries: Mumba, Vitumbiko Tel: Enviro Dynamics cc Enquiries: Quzette Bosman Tel: +264 (0) Quzette Bosman Eddy Kuliwoye Sigi Horsthemke Internal Reviewer: Stephanie van Zyl

3 i ENVIRONMENTAL ASSESSMENT PRACTITIONER DECLARATION I hereby declare that I do/will: (a) Have knowledge of and experience in conducting specialist assessments, including knowledge of the Environmental Management Act (Act 7 of 2007) and the Regulations and Guidelines that have relevance to the proposed activity; (b) Perform the work relating to the application in an objective manner, even if these results in views and findings that is not favourable to the applicant; (c) Comply with the abovementioned Act, its Regulations, Guidelines and other applicable laws. I also declare that there is, to my knowledge, no information in my possession that reasonably has or may have the potential of influencing (I) any decision to be taken with respect to the application in terms of the Act and its Regulations; or (ii) The objectivity of this report, plan or document prepared in terms of the Act and its Regulations. Quzette Bosman Environmental Assessment Practitioner

4 ii Table of Contents Table of Contents... ii Abbreviations & Acronyms...iii List of Figures... iv List of Appendices... iv 1. Introduction Purpose of Report Application for an Environmental Clearance Certificate Environmental Impact Assessment Requirements Sensitivities Project Description Overall Project Phase 1: A new road section between Gocheganas and Windhoek Need and Desirability Alternatives Public Participation Conducted to date Printed Media Background Information Document Newspaper Advertisements Site Notices Building a Stakeholder Database Public Meetings Comments and review period Key Risks and flaws Conclusion and Recommendations... 7

5 iii Abbreviations & Acronyms ABBREVIATION & ACRONYMS DEFINITION BID Background Information Document DEA Directorate of Environmental Affairs ECA Environmental Clearance Application ECC Environmental Clearance Certificate ED Enviro Dynamics cc EIA Environmental Impact Assessment EMA Environmental Management Act, 2007 (Act no. 7 of 2007) GIS Geographic Information System MET Ministry of Environment and Tourism MME Ministry of Mines and Energy NGO Non-Government Organisation PPE Personal Protective Equipment

6 iv List of Figures Figure 1: Locality... 2 Figure 2: Sensitive social receptors... 1 Figure 3: Sensitive bio-physical environment... 2 List of Appendices Appendix A: Letter to Roads Authority Appendix B: Public Consultation Process

7 1 1. Introduction The Roads Authority appointed Lithon/GIBB Joint Venture Consultants to conduct a study on how to improve the safety conditions and traffic flow on the main road B1 between Windhoek and Rehoboth by means of a new freeway. A proposed road alignment had been established and the entire section of road divided into 3 phases for environmental assessment and project implementation. These are: Phase 1: Road Section between Windhoek and Gocheganas Phase 2: Road section between Gocheganas and 15km before Rehoboth Phase 3: Potential Rehoboth Eastern Bypass and rehabilitation of T104/T105 south of eastern bypass and Rehoboth Enviro Dynamics, who provided a technical and cost proposal to the Litho/Gibb joint venture, for the related application for Environmental Clearance (and which was included in the awarded tender) have been commissioned to commence with such an application for Phase 1 of the project. This report therefor only pertains to Phase 1, the location of which is indicated on Figure 1 overleaf. According to the Namibian Environmental Management Act, 2007 (Act No 7 of 2007)(EMA) and in terms of International Environmental Impact Assessment best practice, a project of this magnitude requires the completion of an Scoping Phase followed by an Environmental Assessment Report and related Environmental Management Plan (EMP) in support of an Environmental Clearance Application (ECA). This approach will apply to each phase of the overall project separately. For Phase 1, the Scoping Phase had been initiated. This report has been compiled in terms of the activities which have been completed thus far in the scoping phase and aims at highlighting the risks of continuing with the process.

8 2 Figure 1: Locality

9 3 2. Purpose of Report This report has been compiled as an interim report to the Scoping Phase. It provides a brief overview of the following: The Application of Environmental Clearance and related assessment report, Project description, Project need and desirability, Project alternatives Public consultation conducted to date Key risks and flaws of the process By providing a brief background of the environmental processes and the project description, a clear idea of the project risks can be identified as reported in Section Application for an Environmental Clearance Certificate An ECA is required for any activity listed as per Government Notice No 29 of 2012 of the EMA. In Namibia all projects which require an ECA are subject to a Scoping Phase. Projects of a larger scale further require an Environmental Assessment developed from the Scoping Phase. All activities pertaining to these phases are listed in the Government Notice 30: Environmental Impact Assessment (EIA) Regulations: Environmental Management Act, Environmental Impact Assessment Requirements An EIA is a planning process used to help ensure that environmental features are taken into consideration early in the project development phase. For the purposes of this assessment the EIA is a valuable tool that identifies undesirable effects on the environment that may arise from prospecting activities, and provide measures for these to be avoided. The objectives thereof are to: Enable the selection of optimal alternatives from the various relevant options available if feasible. Identify adverse environmental problems as well as benefits that might be expected to occur; Allow the incorporation of appropriate mitigation measures into the project; and Identify the critical problems which require further study or monitoring. The Scoping Report and Environmental Assessment report once completed and inclusive of public / stakeholder comments, will be submitted to the Department of Environmental Affairs (DEA) of the Ministry of Environmental and Tourism (MET) which

10 4 is the custodian of the EMA, The contents of such documents are therefore legally binding and should the requirements not be adhered to, an Environmental Clearance Certificate (ECC) may be subject to a compliance order process as stipulated in Section 20 of the EMA Should an ECC be granted the project may commence with their planned activities for a period of three years where after an extension of the ECC may be applied for. Once these documents are submitted in support of an Environmental Clearance Certificate (ECC), the team has already incorporated and considered all possible alternatives, motivated their preferred ones and provided an impact assessment with mitigation for the preferred alternative. 4. Sensitivities The major sensitive and constraining features which have been identified to date pertain to the topography and the land use/settlements along the alignment of the proposed route, as indicated in Figure 3. Topographical constraints around the Auas Mountains comprise the steep mountain and hill slopes; the valley and the Kuduschlucht River that winds its way through the kloof where the B1 and the railway line also pass through. Further south along the proposed route a residential settlement has been established on what is known as Kruin 491 indicated in Figure 2. The property has further been developed as a self-catering and camping facility which is reliant on the naturally occurring wildlife in the valley. Both of these sensitivities (bio-physical i.e. the topography and social i.e. the affected community) indicate high risk areas where high impacts may be expected as a result of the proposed route. Biophysically one may expect major landscape transformation in this area because of steep slopes along with and a large capital requirement (i.e. resources needed) to bring about the road, as well as visual impact, erosion, impacts related to quarrying, etc). Socially the livelihoods as well as the well-being of the community will be affected.

11 1 Figure 2: Sensitive social receptors

12 2 Figure 3: Sensitive bio-physical environment

13 1 5. Project Description 3.1 Overall Project The proposed Windhoek - Rehoboth Dual Carriageway road will form the southern extension of the Windhoek Western Bypass and will join the road network at a planned Gobbis Interchange. Section 1 is classified as a Class 1 Trunk Road. The proposed new section of dual carriageway road will also provide the new link between the urban centres of Windhoek and Rehoboth for the daily commuters. 3.2 Phase 1: A new road section between Gocheganas and Windhoek. Planning for this new section of road between Gocheganas and the western bypass in Windhoek had been initiated in 1971 at which time the road reserve thereof had been proclaimed. As the proposed alignment will traverse the Auas Mountains, major earthworks will be required during the construction phase. At this section the confining influences of topography are so severe that the alignment is proposed along the existing road. In this area the existing road has to be relocated, and a major stream diversion is required. Further major earthworks may be required west of the existing road over the rail crossing at Kruin, and at the northern entrance to Auaspoort. 3.3 Need and Desirability Technical assessments as conducted by the appointed engineering consultants have determined that the current road (between Windhoek and Rehoboth) will reach its full capacity within 8 years. A dual carriage way will not only accommodate better traffic flow and lower collision risk, but will further serve to ensure safe passage of abnormal loads and heavy motor vehicles. Currently the only suitable route for abnormal loads is along the Trans-Kalahari Corridor through Botswana. Should the proposed section between Windhoek and Gocheganas not be upgraded to accommodate traffic growth, the vehicle density on this section will continue to increase due to natural traffic growth including the lack of passing opportunities until a total breakdown of flow is experienced by the road users. This will result in increased delays on the network, road surface degradation and related road works, while an increase in traffic accidents may also be expected. 3.4 Alternatives As part of the assessment proses the project team will consider the following which may constitute layout and design alternatives

14 2 The evaluation of encroachments into the alignment (if any) and possible or necessary re-alignments of the freeway; The conformance of the old planning to latest design standards; The appropriateness of the spacing and location of the planned interchanges at "Auaspoort", "Kruin" and "Gocheganas linked to existing road"; and The appropriateness and location of the planned accesses provided by the future service road in view of the developments that have taken place since All of the above will generate alternatives within the project such as design and material alternatives. No alignment alternatives have however been developed or will be considered by the Roads Authority. No environmental motivation could further be sourced for the proposed alignment and related corridor (Developed in 1971) as proposed by the Roads Authority.

15 3 6. Public Participation Conducted to date Informing Interested and Affected Parties who may be affected by, or who are interested in the proposed activities, is a key component of the ECA process. The public participation process, as set out in Section 21 of Regulation No 30 of EMA, has been allowed for during this assessment and the details thereof documented below. 7.1 Printed Media Background Information Document A Background Information Document (BID) was drafted at the onset of the Environmental Assessment (EA) process to act as a useful information handout about the proposed activities and related ECA. In addition, the BID provided details on the public participation process with contact details for further information. This document was distributed through various means of newspaper articles, meetings and the internet, Appendix B. It was further sent to all parties as listed on the project stakeholder list Newspaper Advertisements Press notices about the proposed activity and related EA was circulated in two newspapers for two weeks. These notices appeared in the Namibian and Republikein on the 27 th of March 2015 and 2 nd of April 2015 respectfully. Please refer to Appendix B to view these notices and articles Site Notices Site notices were distributed throughout the area. These provided information about the proposed project and related EA while providing contact details of the project team. Some notices were futher provided to the Kruin Community to be placed and distributed as per their discretion. 7.2 Building a Stakeholder Database A stakeholder database for the project developed. Initially stakeholder lists from previous projects in the area were used as a base list. During the advertisement of the project (through public notices in national newspapers and site-notices) the list was augmented as Interested & Affected Parties (I&AP) registered and contact information of stakeholders updated. All direct owner details were obtained and included as these are the most crucial stakeholders Information about the proposed project was further made available on the internet providing stakeholders contact information to register as I&AP A public meeting provided valuable contact details as per network and chain referral. Not only did this meeting serve to update the stakeholder list, but also

16 4 helped to identify key community communication channels to be used during future phases of the project. 7.3 Public Meetings A public meeting was advertised and subsequently held on the 9 th of April 2015 during which the project was formally introduced to the public. At the meeting a presentation of the ECA was provided while technical information about the proposed route was detailed. The meeting was attended by 35 people which presented a combination of authorities and I&AP. Minutes of the meeting is attached in Appendix B Comments and review period From the onset of the public participation process and the initial information sharing through the BID, newspaper and site notices, various stakeholders have registered and provided comments (all of which have been included in the public consultation Appendix B). Comments received during the public meeting had been minuted while additional comments which had been received via written notifications have been included in an issues and responses trail as per Appendix B. Further to documents received, a petition and various legal letters have been received by Enviro Dynamics and may be viewed in Appendix B. As per all the comments received thus far, the main public concern refers to the alignment of the proposed road upgrade and the lack of feasible alternatives to be considered. I&APs are very concerned about how the proposed new alignment will affect their livelihoods and quality of life. Sound technical motivation is the concern that underpins all their comments.

17 7. Key Risks and flaws At the onset of the project Enviro Dynamics met with the project team to highlight the risks of not considering an alternative alignment. The risks were further communicated to the client through a formal letter directed to the Roads Authority (Appendix A. No further communication was sent off received between the Roads Authority and Enviro Dynamics. In terms of the EIA requirements as mentioned in Section 8 and 15 any ECA should include and adhere to the following: Section 3 (h) of the EMA states: the option that provides the most benefit or causes the least damage to the environment as a whole, at a cost acceptable to society, in the long term as well as in the short term must be adopted to reduce the generation of waste and polluting substances at source; Government Notice No 30 of 2012 as per the EMA Section (8)(g): a description of the need and desirability of the proposed listed activity and any identified alternatives to the proposed activity that are feasible and reasonable, including the advantages and disadvantages that the proposed activity or alternatives have on the environment and on the community that may be affected by the area. Government Notice No 30 of 2012 as per the EMA Section (15)(d): a description of the need and desirability of the proposed listed activity and identified potential alternatives to the proposed listed activity, including advantages and disadvantages that the proposed activity may have on the environment and the community affected by the activity. Furthermore no Environmental Clearance Application had been conducted for the route determination of the road as required and indicated in Section 10.2 of Government Notice 29 of 2012 as per the EMA which states: The route determination of roads and design of associated physical infrastructure where (a) (b) it is a public road the road reserve is wider than 30 metres; or

18 (c) the road caters for more than one lane of traffic in both directions. As per all of the legislation quoted above and as per the biophysical constraints of the proposed alignment combined with the possible effects on the surrounding community, a well-motivated and feasible route alternative needs to be investigated.

19 8. Conclusion and Recommendations 1. Expected increases in the traffic volumes from Windhoek to Rehoboth seem to indicate that an upgrade of the BI National Road is necessary and desirable, although this and the design specifications and road user standard for the road upgrade still need to be determined. Most stakeholders who provided input during the scoping process seemed in agreement that a road upgrade is needed. It should be noted that the Sustainable Urban Transport Master Plan for Windhoek (2012) does not envisage major capacity increases on the Rehoboth-Windhoek link. This needs to be considered and final recommendations made. 2. The main risk currently identified is the lack of alternatives to the proposed route (or sections thereof). The planning done 45 years ago did not consider route alternatives or motivate why the current alternative was selected. No public consultation was done at the time, or there are no records of such. Affected communities have changed considerably, if not completely since then. Furthermore, when the original route selection was done, there was no EIA conducted for the route selection and for the road activity. This is required by law. Not only did Enviro Dynamics point out this risk to the Roads Authority, but the public input confirmed the same concerns. They are valid and need to be addressed. 3. It is therefore our considered and careful opinion that a route selection process needs to be completed before the scoping process of the EIA for the Windhoek-Gocheganas upgrade can be finalised, and for the full EIA to continue. There are two major environmental and social sensitivities in the area under consideration, namely steep mountain and hillslopes, and a settlement. Alternatives need to include these sensitivities and consideration to their avoidance, together with technical and financial considerations. The need and desirability for the upgrade also needs to be confirmed vis a vis the Master Plan mentioned in point 2 above.

Background Information Document

Background Information Document Environmental Assessment Proposed Windhoek- Gocheganas Road upgrade Background Information Document Introduction The Roads Authority appointed Lithon/GIBB Joint Venture Consultants to conduct a study on

More information

NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION

NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION 1. INTRODUCTION This (EIR) has been compiled as part of an Environmental Impact Assessment (EIA) that is being

More information

Figure 4. The proposed location of the Zalu Dam a) basin and b) wall.

Figure 4. The proposed location of the Zalu Dam a) basin and b) wall. A B Figure 4. The proposed location of the Zalu Dam a) basin and b) wall. Figure 5. Detailed layout of the proposed Zalu Dam (Source: Feasibility Study for the Augmentation of the Lusikisiki Regional Water

More information

BASIC ENVIRONMENTAL IMPACT ASSESSMENT for the BEER PROPERTY MANAGEMENT FILLING STATION

BASIC ENVIRONMENTAL IMPACT ASSESSMENT for the BEER PROPERTY MANAGEMENT FILLING STATION BASIC ENVIRONMENTAL IMPACT ASSESSMENT for the BEER PROPERTY MANAGEMENT FILLING STATION DEDEA Ref: EC04/C/LN1/M/53-2014 BACKGROUND INFORMATION DOCUMENT & INVITATION TO COMMENT: Return address for comments:

More information

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010 2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010 CH 1 INTERPRETATION AND PURPOSE OF THESE REGULATIONS S 1 Interpretation; S 2 Purpose of Regulations CH 2 COMPETENT AUTHORITY S3 Who;

More information

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Agricultural Expansion on Portion 2 of Farm 92, Tregaron, known as Sylvania, Sundays River Valley Municipality BACKGROUND INFORMATION DOCUMENT,

More information

Proposed Expansion of the existing Natal Solvent Recovery facility on ERF 7590, Pinetown (10 Clubhouse Place, Westmead) REF: 12/9/11/L44704/4

Proposed Expansion of the existing Natal Solvent Recovery facility on ERF 7590, Pinetown (10 Clubhouse Place, Westmead) REF: 12/9/11/L44704/4 Proposed Expansion of the existing Natal Solvent Recovery facility on ERF 7590, Pinetown (10 Clubhouse Place, Westmead) REF: 12/9/11/L44704/4 NOTICE OF APPLICATION FOR WASTE MANAGEMENT LICENCE, SUBJECT

More information

INTRODUCTION PROJECT DESCRIPTION

INTRODUCTION PROJECT DESCRIPTION JOE GQABI DISTRICT MUNICIPALITY DROUGHT RELIEF PROGRAMME PROPOSED LADY GREY BULK WATER SUPPLY PROJECTS, LADY GREY, SENQU MUNICIPALITY, EASTERN CAPE EIA BACKGROUND INFORMATION DOCUMENT INTRODUCTION Joe

More information

1 INTRODUCTION 1.1 PROJECT APPLICANT

1 INTRODUCTION 1.1 PROJECT APPLICANT 1 INTRODUCTION 1.1 PROJECT APPLICANT Transnet State Owned Company (SOC) Limited (Transnet) is a wholly state owned company in South Africa, which strives to enable competitiveness, growth and development

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA DEA Reference Number: 12/12/20/2175 BACKGROUND INFORMATION

More information

EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT

EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT PURPOSE OF THIS DOCUMENT The purpose of this Background Information

More information

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE Background Information Document DEDEA Ref No s: EC 155/ORT/LN1&LN2/M/13 34 EC 157/ORT/LN1&LN3/M/13

More information

DEA Reference Number: To be announced

DEA Reference Number: To be announced ENVIRONMENTAL IMPACT ASSESSMENT (EIA) FOR THE PROPOSED DEVELOPMENT AND INCLUSION OF THE METAL CONCENTRATORS (METCON) REFINERY FACILITY IN THE JEWELLERY MANUFACTURING PRECINT (JMP) WITHIN THE OR TAMBO INTERNATIONAL

More information

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI

More information

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE 1 MAY 2012 DEA REF. NO. 12/12/20/2501 NEAS REF. NO. DEAT/EIA/0000611/2011 EXECUTIVE

More information

Cape Environmental Assessment Practitioners(Pty) Ltd

Cape Environmental Assessment Practitioners(Pty) Ltd Cape Environmental Assessment Practitioners(Pty) Ltd Reg. No. 2008/004627/07 Telephone: (044) 874 0365 Facsimile: (044) 874 0432 17 Progress Street, George Web: www.cape-eaprac.co.za PO Box 2070, George,

More information

Australian Standard. Acoustics Road traffic noise intrusion Building siting and construction AS

Australian Standard. Acoustics Road traffic noise intrusion Building siting and construction AS AS 3671 1989 Australian Standard Acoustics Road traffic noise intrusion Building siting and construction This Australian Standard was prepared by Committee AV/5, Acoustics Community Noise. It was approved

More information

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: FILE CODE: D10-20/RT SUBJECT: PROPOSED

More information

Struma Lot 3.2 EIA Development, Working Document

Struma Lot 3.2 EIA Development, Working Document Struma Lot 3.2 EIA Development, Working Document Revision 1, 03 February 2016 1 Introduction 1.1 Background Struma Motorway is one of the most challenging road projects in Bulgaria. The motorway is about

More information

IMPORTANT NOTICE. Kindly note that:

IMPORTANT NOTICE. Kindly note that: 1 APPLICATION FORM FOR ENVIRONMENTAL AUTHORISATIONS IN TERMS OF THE NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 AND THE NATIONAL ENVIRONMENTAL MANAGEMENT WASTE ACT, 2008 IN RESPECT OF LISTED ACTIVITIES

More information

6. CONCLUSIONS AND RECOMMENDATIONS

6. CONCLUSIONS AND RECOMMENDATIONS Environmental Impact Assessment Report: Proposed third 400 kv Transmission line between Poseidon and Grassridge, Eastern Cape and Extension to Grassridge 6. CONCLUSIONS AND RECOMMENDATIONS This Environmental

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

1 INTRODUCTION 1.1 PROJECT BACKGROUND

1 INTRODUCTION 1.1 PROJECT BACKGROUND 1 INTRODUCTION 1.1 PROJECT BACKGROUND The International Power Consortium South Africa (IPCSA) has developed a solution to Saldanha Steel s requirement for stable, economical electricity over the long term.

More information

BACKGROUND INFORMATION DOCUMENT: EXPANSION OF SINGITA SWENI LODGE

BACKGROUND INFORMATION DOCUMENT: EXPANSION OF SINGITA SWENI LODGE PROJECT: The expansion of Singita Sweni Lodge, N Wanetsi Private Concession, Kruger National Park BACKGROUND INFORMATION DOCUMENT: EXPANSION OF SINGITA SWENI LODGE CONSULTANT: EMROSS Consulting (Pty) Ltd.

More information

March Protected area boundary adjustments fall within one of three categories:

March Protected area boundary adjustments fall within one of three categories: PROVINCIAL PROTECTED AREA BOUNDARY ADJUSTMENT POLICY, PROCESS AND GUIDELINES March 2010 1. BACKGROUND: Provincial protected areas 1 are set aside to provide a wide range of opportunities that support tourism

More information

Proposed Establishment of the N.N. Metals (Pty) Ltd Waltloo Metal Reclamation Facility

Proposed Establishment of the N.N. Metals (Pty) Ltd Waltloo Metal Reclamation Facility Proposed Establishment of the N.N. Metals (Pty) Ltd Waltloo Metal Reclamation Facility BACKGROUND INFORMATION DOCUMENT (BID) Prepared for: Prepared by: Project Ref No: N.N. Metals (Pty) Ltd Bokamoso Landscape

More information

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 AGENDA Opening and Welcome Introduction of Consultants Profile of Izwelisha Consortium Explanation of the EMF process Environmental

More information

Engineering Compliance East London Regional Waste Disposal Site A Case Study

Engineering Compliance East London Regional Waste Disposal Site A Case Study Engineering Compliance East London Regional Waste Disposal Site A Case Study A.S Dookhi, Envitech Solutions (Pty) Ltd, South Africa, nash@envitech.co.za ABSTRACT The East London Regional Waste Disposal

More information

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD. ENVIRONMENTAL IMPACT ASSESSMENT (EIA), MINING RIGHT APPLICATION AND OTHER ANCILLARY LICENSING PROCESSES: PROPOSED PLATINUM GROUP METALS MINE & ASSOCIATED INFRASTRUCTURE PROPOSED VOLSPRUIT MINE, MOKOPANE

More information

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: APPLICATION FOR THE MINING OF SAND AT BORROW PIT MR771/8.6/R/80, VAN WYKSVLEI, NORTHERN CAPE.

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: APPLICATION FOR THE MINING OF SAND AT BORROW PIT MR771/8.6/R/80, VAN WYKSVLEI, NORTHERN CAPE. ENVIRONMENTAL AUTHORISATION AMENDMENT APPLICATION NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: APPLICATION FOR THE MINING OF SAND AT BORROW PIT MR771/8.6/R/80, VAN WYKSVLEI, NORTHERN CAPE. BACKGROUND

More information

3 EIA PROCESS AND METHODOLOGY

3 EIA PROCESS AND METHODOLOGY 3 EIA PROCESS AND METHODOLOGY 3.1 Introduction The Environmental Impact Assessment (EIA) and Waste Licence Application process for the proposed Majuba Continuous Ashing project is comprised of two main

More information

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL BACKGROUND INFORMATION DOCUMENT April 2014 (2 nd Edition) Project developer: South Africa Mainstream

More information

Senior Minister, Minister of Environment

Senior Minister, Minister of Environment Unofficial Translation by Mr. DANH Serey, EIA Department KINGDOM OF CAMBODIA Nation Religion King MINISTRY of ENVIRONMENT N. 376 BRK.BST Phnom Penh, 02 September 2009 - - - - - - - PRAKAS (DECLARATION)

More information

Information-sharing Meeting

Information-sharing Meeting THE EUROPEAN INVESTMENT BANK AND NAMPOWER EIA FOR THE PROPOSED ENCROACHER BUSH BIOMASS POWER PROJECT IN NAMIBIA Information-sharing Meeting June 2017 1 Agenda Introduction (SLR) Meeting Procedure General

More information

DEVELOPMENT OF AN ONLINE HARMONIZED CUSTOMS AND EXCISE TARIFF DATABASE AND REFERENCE TOOL. Tender Number: SACU/014/2018/O

DEVELOPMENT OF AN ONLINE HARMONIZED CUSTOMS AND EXCISE TARIFF DATABASE AND REFERENCE TOOL. Tender Number: SACU/014/2018/O DEVELOPMENT OF AN ONLINE HARMONIZED CUSTOMS AND EXCISE TARIFF DATABASE AND REFERENCE TOOL Tender Number: SACU/014/2018/O Closing Date: 17h00 Namibian time on 05 March 2018 Delivery Address: Attention:

More information

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA BACKGROUND INFORMATION DOCUMENT SRK Project 364470/42G June 2007

More information

An evaluation of the Irish Remote Interpreting Service (IRIS) Request for Tenders

An evaluation of the Irish Remote Interpreting Service (IRIS) Request for Tenders An evaluation of the Irish Remote Interpreting Service (IRIS) 2018. Request for Tenders The latest date for receipt of tenders is Thursday 30 th August 2018 at 4 pm July 2018 Sign Language Interpreting

More information

FINALISATION OF LIMPOPO PROVINCIAL INFORMAL SETTLEMENT UPGRADING STRATEGY

FINALISATION OF LIMPOPO PROVINCIAL INFORMAL SETTLEMENT UPGRADING STRATEGY P.O. Box 3209, Houghton, 2041 Block A, Riviera Office Park, 6- Riviera Road, Riviera R E Q U E S T F O R P R O P O S A L S FINALISATION OF LIMPOPO PROVINCIAL INFORMAL SETTLEMENT UPGRADING STRATEGY RFP/JHB//2015/017

More information

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed

More information

Crossrail Environmental Statement Volume 1

Crossrail Environmental Statement Volume 1 Crossrail Environmental Statement Volume 1 Project description The environmental impact assessment process The need for Crossrail Planning policy context Route development and alternatives 1 If you would

More information

Road Safety Audit. Volume 5 Section 2 Part 2 NRA HD 19/09. January 2009

Road Safety Audit. Volume 5 Section 2 Part 2 NRA HD 19/09. January 2009 Volume 5 Section 2 Part 2 NRA HD 19/09 Road Safety Audit January 2009 St. Martin s House, Waterloo Road, Dublin 4. Tel:+353 1 660 2511 Fax +353 1 668 0009 Email: info@nra.ie Web: www.nra.ie Summary : This

More information

PUBLIC DISCLOSURE OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT FOR THE MZIMBA TURN OFF- MZUZU-KACHECHE SECTION OF THE M1 ROAD.

PUBLIC DISCLOSURE OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT FOR THE MZIMBA TURN OFF- MZUZU-KACHECHE SECTION OF THE M1 ROAD. Malawi Government Accelerating Malawi s Economic Growth PUBLIC DISCLOSURE OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT FOR THE MZIMBA TURN OFF- MZUZU-KACHECHE SECTION OF THE M1 ROAD.

More information

Midpeninsula Regional Open Space District

Midpeninsula Regional Open Space District Midpeninsula Regional Open Space District PLANNER I-II DEFINITION Under direct supervision, performs various professional field and office planning work related to open space, natural resource, land acquisition

More information

AIR QUALITY MANAGEMENT PLAN (AQMP) FOR THE NORTHERN CAPE

AIR QUALITY MANAGEMENT PLAN (AQMP) FOR THE NORTHERN CAPE AIR QUALITY MANAGEMENT PLAN (AQMP) FOR THE NORTHERN CAPE PROJECT PROCESS PLAN To: From: Northern Cape Department of Environment and Nature Conservation Sasko Building 90 Long Street Kimberley, 8300 umoya-nilu

More information

Alexandra Basin Redevelopment Project. and a. Possible Future Eastern Bypass

Alexandra Basin Redevelopment Project. and a. Possible Future Eastern Bypass Alexandra Basin Redevelopment Project and a Possible Future Eastern Bypass 6 th March 2014 Contents 1. Background... 1 2. Dublin Port and the Eastern Bypass... 1 3. Planning framework... 2 4. Adopted statements

More information

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP)

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) No Action Environmental Risks, Liability/ Benefits Legislative Requirement / EBRD Performance Requirement

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

KENYA: NATIONAL URBAN TRANSPORT IMPROVEMENT PROJECT (P126321)

KENYA: NATIONAL URBAN TRANSPORT IMPROVEMENT PROJECT (P126321) Public Disclosure Authorized AFRICA Kenya Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 10 ARCHIVED on 07-Sep-2018 ISR33423 Implementing Agencies:

More information

CONCLUSIONS AND RECOMMENDATIONS CHAPTER 7

CONCLUSIONS AND RECOMMENDATIONS CHAPTER 7 CONCLUSIONS AND RECOMMENDATIONS CHAPTER 7 The Environmental Scoping Study for the proposed activities within the Gauteng Province has been undertaken in accordance with the EIA Regulations which was published

More information

BOLAND ENVIRONMENTAL CONSULTANTS CC

BOLAND ENVIRONMENTAL CONSULTANTS CC BOLAND ENVIRONMENTAL CONSULTANTS CC y ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Proposed Photo-Voltaic Solar Power Plant On Farm Nuwerus, No. 450 Portion 6, Worcester DEA REF. NO: 12/12/20/2019 BACKGROUND

More information

ENVIRONMENTAL ASSESSMENT FOR THE PROPOSED POLICE FUEL DEPOT IN NCAUTE

ENVIRONMENTAL ASSESSMENT FOR THE PROPOSED POLICE FUEL DEPOT IN NCAUTE SEPTEMBER 2014 ENVIRONMENTAL ASSESSMENT FOR THE PROPOSED POLICE FUEL DEPOT IN NCAUTE SCOPING REPORT PUBLIC REVIEW MINISTRY OF SAFETY AND SECURITY ENVIRO DYNAMICS CC ii COPYRIGHT ENVIRO DYNAMICS, 2014.

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People s Republic of Bangladesh Project: Dhaka Mass Rapid Transit Development Project (Line 5) (E/S) Loan

More information

Annexure E.3. Comment Response Report. Proposed Expansion of Ash Disposal Facility at the Kriel PowerStation, Mpumalanga: Scoping Report

Annexure E.3. Comment Response Report. Proposed Expansion of Ash Disposal Facility at the Kriel PowerStation, Mpumalanga: Scoping Report Proposed Expansion of Ash Disposal Facility at the Kriel PowerStation, Mpumalanga: Scoping Report Annexure E.3 Comment Response Report Project 113084 / 11081File Kriel Ash Disposal Facility Scoping_2017

More information

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS 4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS 4.1 INTRODUCTION This Chapter provides a summary of the EIA process that is being followed for the Sasol Pipeline and FSO Project. The process is structured

More information

National Environmental Management Act, 1998: Draft National Biodiversity Offset Policy

National Environmental Management Act, 1998: Draft National Biodiversity Offset Policy National Environmental Management Act, 1998: Draft National Biodiversity Offset Policy A summary of the Draft National Biodiversity Offset Policy, and critical comments on some of the content, follow below.

More information

ROAD DEVELOPMENT AGENCY

ROAD DEVELOPMENT AGENCY ROAD DEVELOPMENT AGENCY CUSTOMER SERVICE CHARTER RDA: TRANSFORMING ZAMBIA INTO A TRULY LAND LINKED COUNTRY 1 1.0 GLOSSARY ZSIC - Zambia State Insurance Corporation ICT - Information and Communication Technology

More information

BACKGROUND INFORMATION DOCUMENT

BACKGROUND INFORMATION DOCUMENT BACKGROUND INFORMATION DOCUMENT PROPOSED CONSTRUCTION OF 400/132KV MARANG B SUBSTATION AND ±2KM, 400kv POWER LINE LOOPING IN AND OUT FROM THE BIGHORN-MARANG OR MEDUPI MARANG 400KV POWERLINES WITHIN RUSTENBURG

More information

The aim of the public participation process undertaken as part of this Scoping phase is to:

The aim of the public participation process undertaken as part of this Scoping phase is to: SECTION 5: PUBLIC PARTICIPATION PROCESS 5.1 PUBLIC PARTICIPATION PROCESS Public participation is an integral aspect of any EIA process and should aim to meaningfully engage stakeholders at all levels throughout

More information

Background Information Document

Background Information Document Environmental Impact Assessment (EIA) of the Proposed Development of Phosphate Deposits off the Coast of Namibia Background Information Document Note 1. This BID addresses the proposed activities within

More information

Background Information Document

Background Information Document Background Information Document Independent Power Producer Programme: EIA for a Floating Power Plant and EIA for LNG Import Facilities, Port of Richards Bay: ERM Ref Number: 0320839 Purpose of this Background

More information

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT 1. Background The Asian Development Bank (ADB) has assisted the Kyrgyz Republic in the rehabilitation

More information

1 Non-technical summary

1 Non-technical summary 1 1 Non-technical summary 11 Introduction This report constitutes a brief summary of the Environmental Impact Assessment Statement (EIAS) elaborated as a part of the Feasibility Study on the reconstruction

More information

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design

Request for Proposals. Hillsdale Pedestrian/Bicyclist Bridge Design Request for Proposals Hillsdale Pedestrian/Bicyclist Bridge Design Public Works Department City of San Mateo 330 West 20th Avenue San Mateo, CA 94403 JUNE 13, 2013 The City of San Mateo (CITY) is accepting

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE ANNEXURE A T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 SCOPE OF WORK FOR

More information

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement Non Technical Summary Business and Environmental Services A responsive County Council providing excellent and efficient local services

More information

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018 What is the Carolina Crossroads Project? The South Carolina Department of Transportation (SCDOT), in cooperation with the Federal Highway Administration (FHWA), is proposing to upgrade and redesign a key

More information

REVIEW OF THE FREE STATE PROVINCIAL INFORMAL SETTLEMENT UPGRADING STRATEGY

REVIEW OF THE FREE STATE PROVINCIAL INFORMAL SETTLEMENT UPGRADING STRATEGY P.O. Box 3209, Houghton, 2041 Block A, Riviera Office Park, 6-10 Riviera Road, Riviera R E Q U E S T F O R P R O P O S A L S REVIEW OF THE FREE STATE PROVINCIAL INFORMAL SETTLEMENT UPGRADING STRATEGY PROPOSALS

More information

Welsh Government M4 Corridor Enhancement Measures (CEM) Participation Report Executive Summary

Welsh Government M4 Corridor Enhancement Measures (CEM) Participation Report Executive Summary M4 Corridor Enhancement Measures (CEM) Participation Report Executive Summary Issue 5 August 2013 This report takes into account the particular instructions and requirements of our client. It is not intended

More information

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI 220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TERMS OF REFERENCE Transmission line Akhalsikhe-Batumi Georgia Terms of Reference for Tender docs and ESIA 2 1 PROJECT

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 12 th June 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/

MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/ Requesting Office: Head Office Contact Person: Mr T Mosete Contact Numbers: 014 597 4636 E-mail address: tenders@magalieswater.co.za MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/2019-20 PROFESSIONAL SERVICE

More information

subdivision INFILL SUBDIVISION ASSESSMENT CRITERIA RULES

subdivision INFILL SUBDIVISION ASSESSMENT CRITERIA RULES Safety and Heritage RULES 3.0 General The following rules shall apply to the of land situated in the Living Environment where the is of existing sites either up to 1ha in net site area or which creates

More information

Figure 1.1: Location of Majuba Power Station within the Pixley Ka Seme Local Municipality

Figure 1.1: Location of Majuba Power Station within the Pixley Ka Seme Local Municipality 1 INTRODUCTION Majuba Power Station is located near Amersfoort in the Mpumalanga Province and falls within the Pixley Ka Seme Local Municipality (Figure 1.1) which falls within the Gert Sibande District

More information

ANGLESEA FUTURES Land Use Scenarios Summary of Feedback - December 2017

ANGLESEA FUTURES Land Use Scenarios Summary of Feedback - December 2017 ANGLESEA FUTURES Land Use Scenarios - Summary of Feedback December 2017 ANGLESEA FUTURES Land Use Scenarios Summary of Feedback - December 2017 i Acknowledgements The Victorian Government s Department

More information

The Network Rail Hope Valley Capacity Scheme Frequently Asked Questions February 2015

The Network Rail Hope Valley Capacity Scheme Frequently Asked Questions February 2015 The Network Rail Hope Valley Capacity Scheme Frequently Asked Questions February 2015 1. The Plans 1.1 What are you doing and why? Demand for rail travel between Sheffield and Manchester is increasing,

More information

City of Menifee. Public Works Department. Traffic Impact Analysis Guidelines

City of Menifee. Public Works Department. Traffic Impact Analysis Guidelines Public Works Department Traffic Impact Analysis Guidelines Revised: August 2015 TABLE OF CONTENTS INTRODUCTION... 3 PURPOSE... 3 EXEMPTIONS... 3 SCOPING... 4 METHODOLOGY... 5 STUDY AREA... 6 STUDY SCENARIOS...

More information

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project May 2018 Third Draft GEO: East West Highway (Khevi Ubisa Section) Improvement Project Section F2 of the Khevi Ubisa Shorapani Argveta Road (E60 Highway) Part 6 Appendices A D Prepared by JV IRD Engineering

More information

INDUSTRIAL LAND DEVELOPMENT

INDUSTRIAL LAND DEVELOPMENT INDUSTRIAL LAND DEVELOPMENT EXPERTISE COLLABORATIVE PLANNING AND IMPLEMENTATION begins with EMPOWER ENGINEERS & PROJECT MANAGERS VALUE EQUATION INTELLIGENT AND RESPONSIVE DESIGN which delivers Empower

More information

BACKGROUND INFORMATION DOCUMENT:

BACKGROUND INFORMATION DOCUMENT: BACKGROUND INFORMATION DOCUMENT: APPLICATION FOR A MINING RIGHT MMAKAU COAL (PTY) LTD SCHURVEKOP 227 IS, BETHAL, MPUMALANGA 1. INTRODUCTION Mmakau Coal (Pty) Ltd intends to submit an application for a

More information

Proposed Acetylene Gas Production Facility

Proposed Acetylene Gas Production Facility Proposed Acetylene Gas Production Facility Environmental Impact Assessment Public Meeting 24 July 2014 Agenda Introduction 5 minutes Project Description 15 minutes EIA Findings and Mitigation 10 minutes

More information

1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\

1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\ 1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\ Executive Summary 3UHSDUHGýIRUã 3UHSDUHGýE\ã.DQVDVý'HSDUWPHQWýRI 7UDQVSRUWDWLRQ,QýDVVRFLDWLRQýZLWKã (DUWKý7HFKý,QFï EXECUTIVE SUMMARY Introduction This Northwest

More information

Annex B2.3. Background Information Document

Annex B2.3. Background Information Document Annex B2.3 Background Information Document Background Goldfields South Deep Mine, in partnership with Enel Green Power, proposes to design, construct, and operate 2x20MW Solar PV plants on Mine owned property

More information

Strategic Environment Assessment. For the. New Structure Plan for the Maltese Islands. Scoping Report

Strategic Environment Assessment. For the. New Structure Plan for the Maltese Islands. Scoping Report Strategic Environment Assessment For the New Structure Plan for the Maltese Islands Scoping Report Structure Plan Team December 2004 CONTENTS 1 Introduction...3 1.1 Purpose of the scoping report...3 1.2

More information

BACKGROUND INFORMATION DOCUMENT SEPTEMBER 2014 MDEDET REF NUMBER: 17/2/3N-389

BACKGROUND INFORMATION DOCUMENT SEPTEMBER 2014 MDEDET REF NUMBER: 17/2/3N-389 ENVIRONMENTAL AUTHORISATION PROCESS AND APPLICATION FOR REQUIRED LICENCES FOR THE PHOLA COAL PROCESSING PLANT, EMALAHLENI LOCAL MUNICIPALITY, MPUMALANGA PROVINCE BACKGROUND INFORMATION DOCUMENT SEPTEMBER

More information

Air Quality Monitoring PE Terminals

Air Quality Monitoring PE Terminals SCOPE OF WORK FOR THE AIR QUALITY MONITORING (DUST SAMPLING) & MAINTENANCE OF MONITORING EQUIPMENT AT PORT ELIZABETH TERMINALS FOR A PERIOD OF THREE (3) MONTHS. 1. INTRODUCTION Transnet Port Terminals

More information

Summary of Environmental and Social Consideration in Development Study (Preparatory Study)

Summary of Environmental and Social Consideration in Development Study (Preparatory Study) Summary of Environmental and Social Consideration in Development Study (Preparatory Study) 1. Full title of the Project The Study on Integrated Development Strategy for Danang City and Its Neighboring

More information

RECENT SEA EXPERIENCE IN SOUTH AFRICA AND NATIONAL PRINCIPLES: Learning from national scale SEAs for renewable energy and power corridors

RECENT SEA EXPERIENCE IN SOUTH AFRICA AND NATIONAL PRINCIPLES: Learning from national scale SEAs for renewable energy and power corridors RECENT SEA EXPERIENCE IN SOUTH AFRICA AND NATIONAL PRINCIPLES: Learning from national scale SEAs for renewable energy and power corridors Authors: Paul Lochner (1), Marshall Mabin and Lydia Cape Council

More information

Government of Namibia Ministry of Agriculture, Water and Forestry Directorate Rural Water Supply INFORMATION BRIEF

Government of Namibia Ministry of Agriculture, Water and Forestry Directorate Rural Water Supply INFORMATION BRIEF Government of Namibia Ministry of Agriculture, Water and Forestry Directorate Rural Water Supply INFORMATION BRIEF Environmental Assessment Scoping Phase for the Neckartal Dam Project, Namibia Project

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Generic Terms of Reference (ToR) for Consulting Services for Environmental Impact Assessment (EIA) and Preparation of Environmental Management Plans (EMPs) for Transport Sector (Bridge and/or Road) Projects

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

Photovoltaic Power Generation Facility, Prieska EXECUTIVE SUMMARY

Photovoltaic Power Generation Facility, Prieska EXECUTIVE SUMMARY ii EXECUTIVE SUMMARY Introduction Mulilo Renewable Energy (Pty) Ltd, the applicant, intends to develop a 20 mega watt solar farm in Prieska. The context within which this development is proposed is the

More information

Report for Agenda Item: 2

Report for Agenda Item: 2 QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage

More information

Trans Canada Hwy. No.1 Donald Bridges and Approaches

Trans Canada Hwy. No.1 Donald Bridges and Approaches Ministry of Transportation and Infrastructure REQUEST FOR EXPRESSION OF INTEREST Project Number 21754 Trans Canada Hwy. No.1 Donald Bridges and Approaches Conceptual and Detailed Bridge Design & Functional

More information

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

Hastings District Council. Whakatu Arterial Link Traffic Management Plan Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...

More information

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref: Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by

More information

3 APPROACH TO EIA PROCESS AND PUBLIC PARTICIPATION

3 APPROACH TO EIA PROCESS AND PUBLIC PARTICIPATION SLR Environmental Consulting (Namibia) (Pty) Ltd Page 3-1 3 APPROACH TO EIA PROCESS AND PUBLIC PARTICIPATION This chapter provides presents the EIA assumptions and limitations and outlines the EIA process,

More information

GUIDELINES FOR THE USE OF VARIABLE MESSAGE SIGNS ON NATIONAL ROADS PART A GENERAL INFORMATION

GUIDELINES FOR THE USE OF VARIABLE MESSAGE SIGNS ON NATIONAL ROADS PART A GENERAL INFORMATION GUIDELINES FOR THE USE OF VARIABLE MESSAGE SIGNS ON NATIONAL ROADS PART A GENERAL INFORMATION July 2010 Project co-funded by the European Commission DG TREN DOCUMENT CONTROL Client: National Roads Authority

More information

Background Information Document

Background Information Document Background Information Document Independent Power Producer Programme: EIA for a Floating Power Plant and EIA for LNG Import Facilities, Port of Richards Bay: ERM Ref Number: 0320839 Purpose of this Background

More information

Lodestone Namibia (Pty) Ltd. Magnetite Mining Prospect near Dordabis: EPL 3112 PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT CONTENTS

Lodestone Namibia (Pty) Ltd. Magnetite Mining Prospect near Dordabis: EPL 3112 PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT CONTENTS Colin Christian & Associates CC Environmental Consultant 3 Gordon Day St PO Box 81182 Olympia Windhoek Namibia Lodestone Namibia (Pty) Ltd Tel: 061 302296 Fax: 061-302297 Cellphone: 081 1490037 Email:

More information