1. INTRODUCTION. Name of Feed-in Approval Holder (FiAH) : Future Atlas Sdn Bhd (FASB)

Size: px
Start display at page:

Download "1. INTRODUCTION. Name of Feed-in Approval Holder (FiAH) : Future Atlas Sdn Bhd (FASB)"

Transcription

1 Company Name : CAM Resources Berhad Stock Name : CAMRES Type : Announcement Subject : Others Description : CAM Resources Berhad ( CAMRES ) - Feed-In Tariff ("FIT") Approval granted to Future Atlas Sdn Bhd by Sustainable Energy Development Authority Malaysia ("SEDA") for Renewable Energy Contents:- 1. INTRODUCTION The Board of Directors of CAM Resources Berhad ( CAMRES ) wishes to announce that Future Atlas Sdn Bhd ( FASB ), a wholly-owned subsidiary of CAMRES had on 2 June 2017 received the approval letter dated 9 May 2017 from SEDA on the feed-in approval for a MW biogas plant ( Plant ) to sell its renewable energy to Tenaga Nasional Berhad ( TNB ) under the SEDA feed-in tariff system for a period of sixteen (16) years commencing from the scheduled feed-in tariff commencement date of 24 May 2019 (FIA Certificate No. A ) ( SEDA Feed-In Approval ). The expected date of signing of the power purchase agreement ( PPA ) with Tenaga Nasional Berhad is on August 2017 at a fixed Feed-in tariff ( FiT ) rate of RM per kwh for sixteen (16) years. The fixed FiT rate of RM per kwh is conditional upon the use of locally manufactured or assembled gas engine technology and the use of biogas engine efficiency exceeding forty per centum (40.0%). The renewable energy power plant ( REPP ) will be located at 78Km, Jalan Raya Ipoh- Butterworth Simpang, Taiping, Larut dan Matang, Perak Darul Ridzuan. The REPP will have an installed capacity of MW. Name of Feed-in Approval Holder (FiAH) : Future Atlas Sdn Bhd (FASB) Location of Renewal Energy : 78km, Jalan Raya Ipoh-Butterworth Simpang, Taiping Installation Larut dan Matang, Perak Darul Ridzuan Renewable Resources : Biogas (Landfill/Agri Waste) Distribution Licensee : Tenaga Nasional Berhad Installed capacity : MW Net export capacity : MW (BG1) Scheduled Feed-In Tariff : 24 May 2019 Commencement Date Effective period (Commencing from : 16 Years the Feed-In Tariff Commencement Date) Feed-In Tariff Rate : RM /kWh 1

2 2. OVERVIEW OF FIT SYSTEM IN MALAYSIA Malaysia's Feed-in Tariff (FiT) system obliges Distribution Licensees (DLs) to buy from Feed-in Approval Holders the electricity produced from renewable resources (renewable energy) and sets the Feed-in Tariff rate (FiT rate). The DLs will pay for renewable energy supplied to the electricity grid for a specified duration. By guaranteeing access to the grid and setting a favourable price per unit of renewable energy, the FiT mechanism would ensure that renewable energy becomes a viable and sound long-term investment for companies and also for individuals. Key terminologies in FiT: Distribution Licensees (DLs): Companies holding the licence to distribute electricity (e.g. TNB, SESB, NUR); Feed-in Approval Holder: An individual or company who holds a feed-in approval certificate issued by Sustainable Energy Development Authority of Malaysia (SEDA Malaysia). The holder is eligible to sell renewable energy at the FiT rate; FiT rate: Fixed premium rate payable for each unit of renewable energy sold to Distribution Licensees. The FiT rate differs for different renewable resources and installed capacities. Bonus FiT rate applies when the criteria for bonus conditions are met; Indigenous: Renewable resources must be from within Malaysia and are not imported from other countries; and Duration: Period of which the renewable electricity could be sold to distribution licensees and paid with the FiT rate. The duration is based on the characteristics of the renewable resources and technologies. The duration is 16 years for biomass and biogas resources, and 21 years for small hydropower and solar photovoltaic technologies. (Source: 3. SALIENT TERMS AND CONDITIONS OF THE SEDA FEED-IN APPROVAL The terms and conditions of Feed-in Approval as follows: (a) FASB ( the Feed-in Approval Holder ) shall continue to comply with the eligibility criteria described in the Renewable Energy (Feed-In Approval and Feed-in Tariff Rate) Rules

3 (b) FASB shall meet the following milestones by the following dates: No. Milestone Milestone Due Date 1. Registration of Renewable Energy Power Purchase Agreement ( REPPA ) with SEDA & ( ST ) Public License (Provisional) 03/08/ Financing Agreement (s) 10/03/ First Payment to EPC Contractor 10/05/ Initial Operation Date ( IOD ) 10/02/ FIT Commencement Date 24/05/2019 (c) FASB shall observe and comply with the terms and conditions of the feed-in approval, the provisions of the Renewable Energy Act 2011 ( the Act ) and any subsidiary legislation made or other instruments issued under the Act, and all other applicable laws. (d) FASB shall provide information, in such format and at such intervals, as may be required by the SEDA Malaysia in connection with FASB s renewable energy installation. (e) FASB shall obtain the prior written approval of the SEDA Malaysia in respect of any change in circumstances:- i. which would result in FASB not complying with the eligibility criteria described in the Renewable Energy (Feed-in Approval and Feed-in Tariff Rate ) Rules 2011; or ii. which would otherwise result in FASB being no longer entitled to be granted a feed-in approval under the Act and its subsidiary legislation. (f) The feed-in tariff (FiT) rate shall be subject to reduction in accordance with the Act in the event the FiT commencement date occurs later than thirty-first (31 st ) day of December of the Calendar year of the scheduled FiT commencement date. Such reduced rate will be calculated by the SEDA Malaysia. (g) FASB shall ensure that all information, documentation and certifications submitted to the SEDA Malaysia pursuant to the Act and its subsidiary legislation are true, accurate and complete. (h) FASB shall ensure that its renewable energy installation meets an annual minimum performance threshold of no less than thirty five percent (35%) of the following declared annual availability for each year during the effective period: 3

4 Year Declared Annual Availability (MWh) Table 1 (i) The total FiT that FASB is entitled to receive in each year during the effective period shall be limited to the total FiT payable to it for renewable energy generated up to the declared annual availability of the applicable year as specified in paragraph H above. 4

5 4. RATIONALE FOR VENTURING INTO RENEWABLE POWER GENERATION The rationales for the Company to venture into renewable energy are as follows: (a) To reduce the Greenhouse Gas (GHG) emission impact of palm oil production from the generation of biogas from palm oil mill effluent (POME) and conversion of biogas as fuel into electricity; (b) To reduce the carbon footprint of FASB and the overall group of affiliated company; (c) To derive income from the sale of renewable electrical power to the national grid, which will indirectly reduce the production of power from fossil-fuel derived power generation; (d) To be part of the Group s corporate social responsibility program to reduce environmental pollution; and (e) To increase job opportunities for the local populace to operate and maintain the power plant. 5. ADVANTAGES AND BENEFITS ATTRIBUTED FROM SEDA FIT APPROVAL The SEDA FiT approval will allow the FASB to generate and supply renewable energy to Distribution Licensee (DL), Tenaga Nasional Berhad for a duration of 16 years. This is expected to provide a steady stream of income to the Group. In addition to that, with SEDA FiT approval, the FASB is eligible for Green Technology Financing Scheme ( GTFS ) application. The GTFS is a special financing scheme introduced by the government to support the development of Green Technology (GT) in Malaysia. The other benefits that can be obtained by participating in the GTFS are as follows: i. Interest subsidies of 2% from the total interest rate charged; ii. Government guarantee of 60% on the total approved loan; and iii. Training will be provided to applicants to enhance their knowledge on GT. 6. RISK FACTORS (a) Technology and Construction Risk As biogas is a fuel, its efficiency depends on the efficiency of the technology that converts the fuel into electricity. The selection of a mature and reliable technology provider with the requisite experience and track record in building, completing and commissioning such projects (referenceable projects) is a pre-requisite for the project success. 5

6 There are several technology providers in Malaysia, and the assessment for consideration of the right technology provider must include the capital expenses, the long-term serviceability and the past experience of the provider. (b) Operations and Maintenance Risk The employment of the right operation and maintenance provider is critical for the success and support of the plant s operation and maintenance. Spare parts, particularly for the biogas engines will be a major cost of the operations and maintenance. (c) Financial and Regulatory Risk FASB has to obtain all the regulatory approvals such as Renewal Energy Power Purchase Agreement ( REPPA ), Green Technology Financing Scheme ( GTFS ), Suruhanjaya Tenaga provisional and permanent licenses and approvals for construction from Department of Environment ( DOE ) and Department of Occupational Safety and Health prior to commencement of any physical work. Biogas is currently often more expensive to produce than fossil alternatives and therefore financial support is needed to make it commercially viable. Malaysia s Government has introduced a series of incentives to develop the Green Technology industries in Malaysia such as GTFS, a special financing scheme and also green technology tax incentives, such as Investment Tax Allowance. Although the Group may undertake efforts to mitigate the various risks, there is no assurance that any change in the above factors will not have material effect on the business and operations of the Group. 7. SOURCES OF FUNDING The source of funding of the construction cost of REPP will be internally-generated funds as well as bank borrowings. The breakdown of the sources of funding has yet to be determined. 8. FINANCIAL EFFECTS The SEDA FIT approval will not have any significant impact on the net assets, earnings and gearing of the Group for the financial year ending 31 December However, it shall contribute positively to the future earnings of the Group after the effective period, i.e. from 24 May 2019, the planned commencement date of the FIT up to the end of the sixteenth (16 th ) year. 6

7 The FiT approval/ppa is expected to generate a consistent revenue stream due to the guaranteed access to the electricity grid at an approved FiT rate for a duration of 16 years (refer to Table 1 of Item 3(h)). In addition to this, the project is eligible for green technology tax incentive and also GTFS. 9. INTERESTS OF DIRECTORS, MAJOR SHAREHOLDERS AND/OR PERSONS CONNECTED WITH THEM None of the directors and/or major shareholders and/or persons connected with a director or major shareholder have any interest, direct or indirect, in the FIT approval. This announcement is dated 2 June

RENEWABLE ENERGY & FEED-IN TARIFF IN MALAYSIA. 16 th October Sustainable Energy Development Authority Malaysia (SEDA Malaysia)

RENEWABLE ENERGY & FEED-IN TARIFF IN MALAYSIA. 16 th October Sustainable Energy Development Authority Malaysia (SEDA Malaysia) RENEWABLE ENERGY & FEED-IN TARIFF IN MALAYSIA 16 th October 2013 Sustainable Energy Development Authority Malaysia (SEDA Malaysia) 1 Background Definition of Renewable Energy Renewable Energy (RE) is any

More information

COMINTEL CORPORATION BHD ( COMCORP OR COMPANY ) RENEWABLE ENERGY POWER PURCHASE AGREEMENT DATED 15 NOVEMBER 2013

COMINTEL CORPORATION BHD ( COMCORP OR COMPANY ) RENEWABLE ENERGY POWER PURCHASE AGREEMENT DATED 15 NOVEMBER 2013 COMINTEL CORPORATION BHD ( COMCORP OR COMPANY ) RENEWABLE ENERGY POWER PURCHASE AGREEMENT DATED 15 NOVEMBER 2013 We refer to your Company s announcement dated 12 June 2015, in respect of the aforesaid

More information

Malaysian Financial Mechanisms for Renewable Energy (RE) & Future Direction

Malaysian Financial Mechanisms for Renewable Energy (RE) & Future Direction Malaysian Financial Mechanisms for Renewable Energy (RE) & Future Direction Ir. Ahmad Hadri Haris hadri@ptm.org.my Malaysia Energy Centre (PTM) APEC Workshop th March st April, Honolulu Hawaii Malaysia

More information

Prepared for: The Ministry of Economy, Trade and Industry

Prepared for: The Ministry of Economy, Trade and Industry STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES IN FY2011 Study on the Solar Photovoltaic Power Generation Projects in the Federation of Malaysia SUMMARY February 2012 Prepared

More information

Vertical Axis Wind Turbines Feed In Tariff. James Hoare Leon O Neil

Vertical Axis Wind Turbines Feed In Tariff. James Hoare Leon O Neil Vertical Axis Wind Turbines Feed In Tariff James Hoare Leon O Neil Installer of Solar PV Wind Turbines Solar Thermal Heat Pumps Wind Turbines Principal Types Vertical Axis Horizontal Axis Principal Sectors

More information

DECEMBER Renewable Energy

DECEMBER Renewable Energy DECEMBER 2016 Renewable Energy law EMPOWERING ASEAN One of the fastest growing energy markets in the world lies in Southeast Asia. By 2040, regional demand for energy may grow by 80% and electricity demand

More information

BASIC ELEMENTS OF A PROPOSED RENEWABLE ENERGY FEED-IN TARIFF LAW FOR [AZERBAIJAN] 2009 CONTENTS

BASIC ELEMENTS OF A PROPOSED RENEWABLE ENERGY FEED-IN TARIFF LAW FOR [AZERBAIJAN] 2009 CONTENTS BASIC ELEMENTS OF A PROPOSED RENEWABLE ENERGY FEED-IN TARIFF LAW FOR [AZERBAIJAN] 2009 CONTENTS 1 Purpose 2 Scope 3 Targets 4 Eligible technologies and plants 5 Grid connection, reinforcement and costs

More information

SUNSOURCE ENERGY SDN. BHD.

SUNSOURCE ENERGY SDN. BHD. SUNSOURCE ENERGY SDN. BHD. 1 ABOUT US At Sunsource, we position ourselves as the client representative to perform Project Planning & Management, Engineering, Development of Bill Quantity, Procurement,

More information

An Outlook of Renewable Energy Development in Malaysia

An Outlook of Renewable Energy Development in Malaysia An Outlook of Renewable Energy Development in Malaysia Biomass Asia Conference, 21 st May 2013 Amer Aqel Amer Nordin Consultant, Energy & Environment Amer Aqel Amer Nordin Functional Expertise Consulting

More information

(a) The Commission shall establish a Renewable Portfolio Standard Rule (hereafter called

(a) The Commission shall establish a Renewable Portfolio Standard Rule (hereafter called I. Renewable Portfolio Standard.00 Florida Renewable Portfolio Standard () Application and Scope. (a) The Commission shall establish a Renewable Portfolio Standard Rule (hereafter called RPS Rule ) that

More information

BRIGHTER SOLUTIONS FOR GREEN ENERGY KEYNOTE SPEECH BY:

BRIGHTER SOLUTIONS FOR GREEN ENERGY KEYNOTE SPEECH BY: BRIGHTER SOLUTIONS FOR GREEN ENERGY KEYNOTE SPEECH BY: IR. MOHD AZHAR ABDUL RAHMAN MANAGING DIRECTOR TNB ENERGY SERVICES SDN. BHD. TENAGA NASIONAL BERHAD SEPTEMBER 2014 CONTENT BACKGROUND MALAYSIA S PERSPECTIVE

More information

Feed-in Tariff Mechanism : Malaysia s Choice to Catalyst Renewable Energy Growth & Policy Updates on Solar PV

Feed-in Tariff Mechanism : Malaysia s Choice to Catalyst Renewable Energy Growth & Policy Updates on Solar PV Feed-in Tariff Mechanism : Malaysia s Choice to Catalyst Renewable Energy Growth & Policy Updates on Solar PV Leong CF ICT Director, e-fit Online System Sustainable Energy Development Authority Malaysia

More information

Biomass Asia Conference, May G. Ilango Bharathi YTL SV Carbon Sdn. Bhd. Malaysia

Biomass Asia Conference, May G. Ilango Bharathi YTL SV Carbon Sdn. Bhd. Malaysia Biomass Asia Conference, 2013 21 May 2013 G. Ilango Bharathi YTL SV Carbon Sdn. Bhd. Malaysia Contents 1. Introductory details 2. Challenges for utilisation of palm biomass 3. Some suggestions to increase

More information

Renewable Energy the opportunities?

Renewable Energy the opportunities? Renewable Energy the opportunities? The main incentive for new and young entrants is a profitable business which provides good opportunities for business growth. Whilst there has been interest in, and

More information

5 th Energy Forum. Round Table Discussion Taking on Tomorrow s Energy Challenges Today. Tenaga Nasional Berhad. 3 September 2013

5 th Energy Forum. Round Table Discussion Taking on Tomorrow s Energy Challenges Today. Tenaga Nasional Berhad. 3 September 2013 5 th Energy Forum Round Table Discussion Taking on Tomorrow s Energy Challenges Today Tenaga Nasional Berhad 3 September 2013 Three Major Electricity Utilities in Malaysia PENINSULAR MALAYSIA Tenaga Nasional

More information

CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS

CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS Ontario Energy Board Commission de l énergie de l Ontario CONSERVATION AND DEMAND MANAGEMENT CODE FOR ELECTRICITY DISTRIBUTORS Issued: September 16, 2010 Table of Contents 1. GENERAL AND ADMINISTRATIVE

More information

UNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY

UNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/REG/2004/22 30 June 2004 REGULATION NO.

More information

GUIDELINES FOR GREEN TECHNOLOGY TAX INCENTIVE (GITA GITE) Green Investment Tax Allowance (GITA) and Green Income Tax Exemption (GITE) Updated May 2016

GUIDELINES FOR GREEN TECHNOLOGY TAX INCENTIVE (GITA GITE) Green Investment Tax Allowance (GITA) and Green Income Tax Exemption (GITE) Updated May 2016 GUIDELINES FOR GREEN TECHNOLOGY TAX INCENTIVE (GITA GITE) REG NO. MGTC/DC/REC/GC-031 REVISION 0 DATE 01/06/2018 GUIDELINES FOR GREEN TECHNOLOGY TAX INCENTIVE Green Investment Tax Allowance (GITA) and Green

More information

Financing Renewable Energy Projects. Part I: Government Subsidies

Financing Renewable Energy Projects. Part I: Government Subsidies Financing Renewable Energy Projects Part I: Government Subsidies Part I: Government Subsidies Goals of Government Subsidies Renewable Portfolio Standards and Renewable Energy Certificates Illinois Renewable

More information

MALAYSIAN GREEN TECHNOLOGY CORPORATION. GUIDELINES FOR THE REGISTRATION OF MyHIJAU MARK PRODUCT

MALAYSIAN GREEN TECHNOLOGY CORPORATION. GUIDELINES FOR THE REGISTRATION OF MyHIJAU MARK PRODUCT MALAYSIAN GREEN TECHNOLOGY CORPORATION GUIDELINES FOR THE REGISTRATION OF MyHIJAU MARK PRODUCT Updated June 2015 CONTENTS 1.0 INTRODUCTION 3 2.0 DEFINITIONS 4 3.0 ELIGIBILITY CRITERIA 7 3.1 Eligibility

More information

Renewable & Alternative Energy Resources: What s the difference? 2

Renewable & Alternative Energy Resources: What s the difference? 2 The Development of Renewable & Alternative Energy Resources: The Role of the Commissioner Jeff Davis Commissioner Missouri Public Service Commission 1 Renewable & Alternative Energy Resources: What s the

More information

APRIL 2018 OVERVIEW TIMAH RESOURCES LIMITED MARKET DATA

APRIL 2018 OVERVIEW TIMAH RESOURCES LIMITED MARKET DATA APRIL 2018 TIMAH RESOURCES LIMITED MARKET DATA ASX Code TML Current Price $0.050 Total Shares 93.48 million Market Cap BOARD OF DIRECTORS $ 4.67 million Tan Sri Dr Mah King Thian (Executive Chairman) Dato

More information

ADVANCES IN BIOGAS PROCESSING June 2013

ADVANCES IN BIOGAS PROCESSING June 2013 PRESENTATION ON ADVANCES IN BIOGAS PROCESSING June 2013 GASALAM SDN BHD TAIYO NIPPON SANSO CORP SGPADIMAS ENGINEERING SDN BHD Copyright GasAlam 2013 MALAYSIA BIOGAS INDUSTRY Palm Oil & Biogas Industry

More information

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity

More information

S&P INTERNATIONAL HOLDING LIMITED 椰豐集團有限公司

S&P INTERNATIONAL HOLDING LIMITED 椰豐集團有限公司 Hong Kong Exchanges and Clearing Limited and The Stock Exchange of Hong Kong Limited take no responsibility for the contents of this announcement, make no representation as to its accuracy or completeness

More information

YTL LAND & DEVELOPMENT BERHAD Company No M Incorporated in Malaysia

YTL LAND & DEVELOPMENT BERHAD Company No M Incorporated in Malaysia YTL LAND & DEVELOPMENT BERHAD Company No. 1116-M Incorporated in Malaysia Interim Financial Report 31 December 2009 YTL LAND & DEVELOPMENT BERHAD Company No. 1116-M Incorporated in Malaysia Interim Financial

More information

France renewable energy policies

France renewable energy policies France renewable energy policies Louise ORIOL Renewable Energy Office Ministry of Environment, Energy and the Sea 1 st September 2016 Key energy figures about France Total final energy consumption (2014):

More information

Guidance Note for CLA members

Guidance Note for CLA members Guidance Note for CLA members Feed in Tariff (FIT) for Solar Photovoltaic (PV) Installations Date: 10 February 2015 CLA Guidance Note Reference: GN11-15 Introduction The Feed in Tariff (FiT) scheme was

More information

FELDA PALM INDUSTRIES SDN. BHD

FELDA PALM INDUSTRIES SDN. BHD FELDA PALM INDUSTRIES SDN. BHD Development of Biogas Projects in Felda Global Ventures Reflections & Way Forward and Opportunities for Value Creation in Palm Oil Based Biogas Biogas Asia Pacific Forum

More information

STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES IN FY2011

STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES IN FY2011 STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES IN FY2011 Study on the Solar Photovoltaic Power Generation Projects in the Federation of Malaysia FINAL REPORT February 2012

More information

Guideline for Claims of Made with Renewable Energy or Reduced Carbon Footprint Based on Power Purchase Agreement

Guideline for Claims of Made with Renewable Energy or Reduced Carbon Footprint Based on Power Purchase Agreement SCS Global Services Guideline Guideline for Claims of Made with Renewable Energy or Reduced Carbon Footprint Based on Power Purchase Agreement Version: 1-0 (February 2018) 2000 Powell Street, Ste. 600,

More information

Barriers preventing the deployment of Small Wind Systems and the Economic Advantages

Barriers preventing the deployment of Small Wind Systems and the Economic Advantages Barriers preventing the deployment of Small Wind Systems and the Economic Advantages Simon Powell Marine South East Ltd Southampton, UK EU Sustainable Energy Week, Brussels 14 April 2011 Wind a free fuel

More information

Solar PV: Policy, Market & Industry in Malaysia

Solar PV: Policy, Market & Industry in Malaysia Solar PV: Policy, Market & Industry in Malaysia Dr Wei-nee Chen Chief Corporate Officer, Sustainable Energy Development Authority (SEDA) Malaysia October 2017 Malaysia: Electricity Generation Mix Source:

More information

The main features of the Act on granting priority to renewable energy sources (Renewable Energy Sources Act) of 21 July 2004

The main features of the Act on granting priority to renewable energy sources (Renewable Energy Sources Act) of 21 July 2004 Federal Ministry for the Environment, Nature Conservation and Nuclear Safety Public Relations Division 11055 Berlin Tel.: 01888/305-0. Fax: 01888/ 305-2044 E-Mail: service@bmu.bund.de http://www.bmu.de

More information

( A) (2 Days Program) HRDF Claimable SBL Date: 18 & 19 July 2016 Venue: Vistana Hotel,Penang

( A) (2 Days Program) HRDF Claimable SBL Date: 18 & 19 July 2016 Venue: Vistana Hotel,Penang (1089589 A) Address: No.316-E, Desaria Shop-Office,Jalan Dato Ismail Hashim,Sungai Ara,11900, Bayan Lepas, Pulau Pinang Tel: 04-6430762 ; Email: info@lcec.com.my LICENSED MANUFACTURING WAREHOUSES (LMW)

More information

MANITOBA HYDRO Power Smart Load Displacement Program. Engineering Cost Estimate Study Guide (Version 3)

MANITOBA HYDRO Power Smart Load Displacement Program. Engineering Cost Estimate Study Guide (Version 3) MANITOBA HYDRO Power Smart Load Displacement Program Engineering Cost Estimate Study Guide (Version 3) September, 2014 * Manitoba Hydro is a licensee of the Trademark and Official Mark Load Displacement

More information

Biomass and Energy A Perspective from Municipal Solid Waste (MSW)

Biomass and Energy A Perspective from Municipal Solid Waste (MSW) Biomass and Energy A Perspective from Municipal Solid Waste (MSW) Agamuthu P. and Fauziah S.H. Institute of Biological Sciences, Faculty of Science, University of Malaya, 50603 Kuala Lumpur, Malaysia.

More information

Power System Study for Renewable Energy Interconnection in Malaysia

Power System Study for Renewable Energy Interconnection in Malaysia IOP Conference Series: Earth and Environmental Science OPEN ACCESS Power System Study for Renewable Energy Interconnection in Malaysia To cite this article: O F Askar and V K Ramachandaramurthy 2013 IOP

More information

GRENLEC s Renewable Standard Offer

GRENLEC s Renewable Standard Offer GRENLEC s Renewable Standard Offer Version: 1.1 Last Updated: September 10 th, 2011 This document provides as a general overview of the Customer-owned Renewable Generation Standard Offer, for the purchase

More information

In general, all technologies used in renewable electricity generation are eligible for promotion.

In general, all technologies used in renewable electricity generation are eligible for promotion. Research RES LEGAL Promotion system Country: Portugal 1. Overview of promotion system Overview of promotion system In Portugal, electricity from renewable sources is mainly promoted through price-regulation

More information

FINANCIAL VIABILITY INSTRUCTIONS Applicants and Providers of FEE-HELP and VET FEE-HELP assistance

FINANCIAL VIABILITY INSTRUCTIONS Applicants and Providers of FEE-HELP and VET FEE-HELP assistance FINANCIAL VIABILITY INSTRUCTIONS Applicants and Providers of FEE-HELP and VET FEE-HELP assistance Document publishing date (May 2015) Department of Education and Training Version control Version Date Summary

More information

Renewable Power and Energy Efficiency: Policies in Iowa and Other States

Renewable Power and Energy Efficiency: Policies in Iowa and Other States Executive Summary Renewable Power and Energy Efficiency: Policies in Iowa and Other States Matthew D. Ritsema Mark A. Edelman Daniel M. Otto April 2003 A report for The Iowa Policy Project 318 2nd Avenue

More information

Construction Financing Facility to Support Private Sector Participation in Renewable Energy Development

Construction Financing Facility to Support Private Sector Participation in Renewable Energy Development Construction Financing Facility to Support Private Sector Participation in Renewable Energy Development Atty. Patrick Aquino Director III, Department of Energy Government of the Philippines Global NAMA

More information

EXAMPLE TARIFF MID-SIZE COMMERCIAL

EXAMPLE TARIFF MID-SIZE COMMERCIAL SOLAR PV EXAMPLE TARIFF MID-SIZE COMMERCIAL CONTENTS 1 Contents 2 Introduction 3 Examples 4 Important 5 How to proceed Approved Installer Telephone 01843 855 019 1 INTRODUCTION A LITTLE ABOUT TARIFFS The

More information

A GUIDE TO THE GB RENEWABLE HEAT INCENTIVE SCHEME.

A GUIDE TO THE GB RENEWABLE HEAT INCENTIVE SCHEME. A GUIDE TO THE GB RENEWABLE HEAT INCENTIVE SCHEME 1. What is the Renewable Heat Incentive Scheme ("RHI")? The RHI is a scheme to encourage the take up of renewable heat technologies such as biomass boilers,

More information

Here Comes the Sun: Development of the Solar Energy Industry in Malaysia

Here Comes the Sun: Development of the Solar Energy Industry in Malaysia Renewable Energy Here Comes the Sun: Development of the Solar Energy Industry in Malaysia The Ministry of Energy, Science, Technology, Environment and Climate Change has set an ambitious goal for 20% of

More information

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS Program Guide TABLE OF CONTENTS Introduction... 2 Purpose... 2 About CHP... 2 Program Description... 2 Call for CHP Projects... 3 Participant Webinar...

More information

Independence Freedom Happiness No: 11 /2017/QD-TTg Ha Noi, 11 th April 2017 DECISION. On the

Independence Freedom Happiness No: 11 /2017/QD-TTg Ha Noi, 11 th April 2017 DECISION. On the PRIME MINISTER SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness No: 11 /2017/QD-TTg Ha Noi, 11 th April 2017 DECISION On the Support mechanisms for the Development of Solar Power Projects in

More information

EXAMPLE TARIFF DOMESTIC

EXAMPLE TARIFF DOMESTIC SOLAR PV EXAMPLE TARIFF DOMESTIC CONTENTS 1 Contents 2 Introduction 3 Examples 4 Important 5 How to proceed Approved Installer Telephone 01843 855 019 1 INTRODUCTION A LITTLE ABOUT TARIFFS The Feed-In

More information

How to deliver a renewable energy project. Jemma Benson CO2Sense

How to deliver a renewable energy project. Jemma Benson CO2Sense How to deliver a renewable energy project Jemma Benson CO2Sense CO2Sense Helping businesses to prosper in the low carbon economy Support for regional renewable electricity: specialist support larger schemes

More information

State aid SA /N FI Fixed operating aid for power plants using renewable energy sources

State aid SA /N FI Fixed operating aid for power plants using renewable energy sources EUROPEAN COMMISSION Brussels, 22.03.2011 C (2011) 1951 PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid SA. 32470 2011/N FI Fixed operating

More information

Overview of financing energy projects

Overview of financing energy projects Overview of financing energy projects 2004 Cogeneration Week in Cambodia 8 June 2004 Inter-Continental Hotel, Phnom Penh Romel M. Carlos COGEN 3 Financial Adviser 1 STAKEHOLDERS FUEL SUPPLIER Consultants/

More information

SINAR KAMIRI SDN BHD GREEN SRI SUKUK SECOND OPINION REPORT 2 NOVEMBER 2017 PROPOSED SUKUK ISSUANCE OF RM245.0 MILLION

SINAR KAMIRI SDN BHD GREEN SRI SUKUK SECOND OPINION REPORT 2 NOVEMBER 2017 PROPOSED SUKUK ISSUANCE OF RM245.0 MILLION SINAR KAMIRI SDN BHD GREEN SRI SUKUK PROPOSED SUKUK ISSUANCE OF RM245.0 MILLION SECOND OPINION REPORT 2 NOVEMBER 2017 Analyst Dinagaran Chandra (603) 7628 1039 dina@ram.com.my SUMMARY Sinar Kamiri Sdn

More information

CHANGING THE WAY WE CREATE ENERGY. A high yield wind energy investment.

CHANGING THE WAY WE CREATE ENERGY. A high yield wind energy investment. CHANGING THE WAY WE CREATE ENERGY. A high yield wind energy investment. RENEWABLE ENERGY, THE WAY FORWARD The renewable energy sector has witnessed unprecedented growth over the last few years. This growth

More information

DRAFT 8/11/08. I. Renewable Portfolio Standard. (a) The Commission shall establish minimum numerical portfolio standards for each investorowned

DRAFT 8/11/08. I. Renewable Portfolio Standard. (a) The Commission shall establish minimum numerical portfolio standards for each investorowned I. Renewable Portfolio Standard 0 0.00 Florida Renewable Portfolio Standard () Application and Scope. (a) The Commission shall establish minimum numerical portfolio standards for each investorowned electric

More information

Comm/CP/NCE/Tariff/28362 Date: COMMERCIAL CIRCULAR No. 228

Comm/CP/NCE/Tariff/28362 Date: COMMERCIAL CIRCULAR No. 228 (A Govt. of Maharashtra Undertaking) CIN: U40109MH2005SGC153645 Maharashtra State Electricity Distribution Co. Ltd. Office of the Chief Engineer (Commercial) Prakashgad, 5th Floor, Station Road, Bandra

More information

RATE 665 RENEWABLE FEED-IN TARIFF

RATE 665 RENEWABLE FEED-IN TARIFF NORTHERN INDIANA PUBLIC SERVICE COMPANY Third Revised Sheet No. 104 Superseding Second Revised Sheet No. 104 TO WHOM AVAILABLE No. 1 of 11 Sheets This is a rate that is a voluntary offer available to any

More information

Support Scheme for Renewable Heat. Scheme Overview

Support Scheme for Renewable Heat. Scheme Overview Support Scheme for Renewable Heat Scheme Overview Table of Contents Introduction... 3 Support Types... 4 Operational Support... 4 Installation Grant... 8 Page 2 Introduction 1. This document is intended

More information

The Effects of: Peak Load Generation on Average Electricity Tariff. And Peak Load Reduction By Solar PV on Gas Subsidy

The Effects of: Peak Load Generation on Average Electricity Tariff. And Peak Load Reduction By Solar PV on Gas Subsidy The Effects of: Peak Load Generation on Average Electricity Tariff. And Peak Load Reduction By Solar PV on Gas Subsidy Components of Existing Electricity Tariff Structure Based on Gas price of RM15.20/MMBtu,

More information

Saving and Generating Energy Dollars

Saving and Generating Energy Dollars Saving and Generating Energy Dollars Overview of Energy Performance Contracting & Self-Generation through Renewables Presented by John Silverio Director Project Development Who are we? Canadian organization

More information

Application Guide. Ver 1.5

Application Guide. Ver 1.5 Renewable Application Guide Ver 1.5 IMPORTANT NOTICE SEI shall bear no responsibility for the quality, specification or standard of the product or its suitability for the application for which it is installed,

More information

Germany: Energy Briefing

Germany: Energy Briefing Germany: Energy Briefing February 2014 Contents Introduction 01 1. Amended Remuneration 02 2. Compulsory Direct Marketing 03 3. Tender Procedures 04 4. Self Consumption, Support for 04 Energy Intensive

More information

GREEN ENERGY FROM PALM-BASED BIOGAS BELL Group s Experience On Biogas Capture

GREEN ENERGY FROM PALM-BASED BIOGAS BELL Group s Experience On Biogas Capture GREEN ENERGY FROM PALM-BASED BIOGAS BELL Group s Experience On Biogas Capture Liana Low CEO BELL Group of Companies 19 21 November 2013 Kuala Lumpur Convention Centre At PIPOC 2007, I spoke on Revenue

More information

Power Saver TM Program

Power Saver TM Program Power Saver TM Program COMMERCIAL SOLAR PHOTOVOLTAIC PERFORMANCE-BASED INCENTIVE PROGRAM GUIDELINES These guidelines govern the procedures and qualifications for incentives under the Austin Energy Commercial

More information

The amendment of the energy consumption pattern Act

The amendment of the energy consumption pattern Act The amendment of the energy consumption pattern Act The Islamic Consultative Assembly has taken measures relative to notify the amendment of the energy consumption pattern Act on the 4/12/1389. The ministries

More information

Renewable Energy Sources Act. Progress Report 2007

Renewable Energy Sources Act. Progress Report 2007 Renewable Energy Sources Act Progress Report 2007 pursuant to Article 20 of the Act - Draft prepared by the Federal Ministry for the Environment, Nature Conservation and Nuclear Safety (BMU) Summary 5.7.2007

More information

PASADENA WATER AND POWER MEMORANDUM. August 9, 2016

PASADENA WATER AND POWER MEMORANDUM. August 9, 2016 PASADENA WATER AND POWER MEMORANDUM August 9, 2016 To: Environmental Advisory Committee From: Gurcharan Bawa Interim General Manager Subject: Pasadena Solar Program Updates This report is for information

More information

Renewable Energy Is it feasible in a distillery environment?

Renewable Energy Is it feasible in a distillery environment? Renewable Energy Is it feasible in a distillery environment? Andrew Bright, ITPEnergised SWA Guide Published in 2012 Details on a range of technologies Information on subsidies Numerous examples of the

More information

Chevening Chat Series 4: REsolutions: Renewable Energy (RE) for Sustainable and Inclusive Development 20 January 2017; 1:00 PM - 5:00 PM at SEDA

Chevening Chat Series 4: REsolutions: Renewable Energy (RE) for Sustainable and Inclusive Development 20 January 2017; 1:00 PM - 5:00 PM at SEDA Chevening Chat Series 4: REsolutions: Renewable Energy (RE) for Sustainable and Inclusive Development 20 January 2017; 1:00 PM - 5:00 PM at SEDA Hotel BGC 1 incentive mechanism in the renewable energy

More information

Status Review of Renewable and Energy Efficiency Support Schemes in EU

Status Review of Renewable and Energy Efficiency Support Schemes in EU Status Review of Renewable and Energy Efficiency Support Schemes in EU Ref: C08-SDE-05-03 10 December 2008 Council of European Energy Regulators ASBL 28 rue le Titien, 1000 Bruxelles Arrondissement judiciaire

More information

Auctions preparation, course, wins. Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office

Auctions preparation, course, wins. Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office Warsaw, March 2015 Installations subject to the auction procedure: existing including modernised

More information

SMALL HYDRO PROGRAMME IN INDIA. Bhuwanesh Kumar Bhatt Ministry of New and Renewable Energy

SMALL HYDRO PROGRAMME IN INDIA. Bhuwanesh Kumar Bhatt Ministry of New and Renewable Energy SMALL HYDRO PROGRAMME IN INDIA Bhuwanesh Kumar Bhatt Ministry of New and Renewable Energy e-mail : bhattbk88@gmail.com; bkbhatt@nic.in MILESTONES IN RENEWABLE ENERGY DEVELOPMENT IN INDIA 1980s - Setting

More information

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme What s inside 3 Make money from the energy you generate An introduction to Feed In Tariffs 4-5 How it works Your

More information

Your budgeting companion

Your budgeting companion Your budgeting companion October 2018 r Get in touch Page 08001056 of 29 8101 customer_services@orsted.co.uk orstedbusiness.co.uk Page 1 of 29 Budget with confidence Inside this new report, you ll find

More information

Three Years of Italian Green Certificates: a First Assessment

Three Years of Italian Green Certificates: a First Assessment Three Years of Italian Green Certificates: a First Assessment Natascia Falcucci Operations Department Realise Forum Milan, 15 December 2005 www.grtn.it Contents GRTN s role in the electricity market General

More information

Climate Change and the Carbon Market

Climate Change and the Carbon Market Click to edit Master title style Forest Industry: Opportunities and Incentives Climate Change and the Carbon Market Focus on Forest Engineering November 2010 TAPPSA 2010 Conference Durban, South Africa

More information

Updates on RE programme and efforts in Malaysia Azah Ahmad Sustainable Energy Development Authority Malaysia

Updates on RE programme and efforts in Malaysia Azah Ahmad Sustainable Energy Development Authority Malaysia Updates on RE programme and efforts in Malaysia Azah Ahmad Sustainable Energy Development Authority Malaysia 12-13 November 2014 EGNRET 43, Chiang Mai, Thailand 1 Renewable Malaysia: Energy Renewable Development

More information

Outline. Introduction to Wisconsin. Barriers to Generating Electricity from. Incentives and Regulations Intended to

Outline. Introduction to Wisconsin. Barriers to Generating Electricity from. Incentives and Regulations Intended to Experience of the United States in the Application of Incentives and Regulations for the Supply of Renewable Energy Chairperson Eric J. Callisto Public Service Commission of Wisconsin 20 May 2010 Outline

More information

UPDATE ON FEED-IN TARIFF IN MALAYSIA

UPDATE ON FEED-IN TARIFF IN MALAYSIA UPDATE ON FEED-IN TARIFF IN MALAYSIA Malaysia Biomass Industry Networking Seminar 5 th February 2015 Dr Wei-nee Chen, Chief Corporate Officer, Sustainable Energy Development Authority Malaysia 1 Disclaimer

More information

Certification of electricity products from renewable energy sources with new renewables requirement Abbreviated: Product EE01

Certification of electricity products from renewable energy sources with new renewables requirement Abbreviated: Product EE01 TÜV SÜD Standard Certification of electricity products from renewable energy sources Abbreviated: Product EE01 with Regionality module EE01 Region product : Minimum percentage from regional sources Version

More information

Renewable Heat Incentive: Proposals for a domestic scheme

Renewable Heat Incentive: Proposals for a domestic scheme (Updated Version) 24 th September 2012 Renewable Heat Incentive: Proposals for a domestic scheme Introduction This consultation on the long awaited domestic Renewable Heat Incentive (RHI) follows the launch

More information

OFFICE OF THE CITY ADMINISTRATIVE OFFICER

OFFICE OF THE CITY ADMINISTRATIVE OFFICER REPORT FROM OFFICE OF THE CITY ADMINISTRATIVE OFFICER Date: January 16, 2015 CAO File No. 0150-10310-0000 Council Fife No. Council District: outside City limits To: The Mayor The City Council From: Miguel

More information

Joint Session of the ECE Timber Committee and

Joint Session of the ECE Timber Committee and Joint Session of the ECE Timber Committee and the FAO European Forestry Commission Location, Turkey 10 14 October 2011 Wood as a Renewable Energy Source Market and Policy Issues Francisco X. Aguilar, Ph.D.

More information

PHOTOVOLTAIC OBSERVATORY POLICY RECOMMENDATIONS 2011

PHOTOVOLTAIC OBSERVATORY POLICY RECOMMENDATIONS 2011 PHOTOVOLTAIC OBSERVATORY POLICY RECOMMENDATIONS 2011 Observing PV policies in Europe Climate change and the perspective of fossil fuel scarcity have strengthened the need to promote renewable energies.

More information

Sharing Malaysia s experience in development of Renewable Energy

Sharing Malaysia s experience in development of Renewable Energy Knowledge Partnership Dialogue Centre of Excellence for Clean Energy Jakarta 8 Oct 2015 Sharing Malaysia s experience in development of Renewable Energy SEDA Sustainable Energy Development Authority Set

More information

Promotion of distributed generation by educational institutions Comments requested from Stakeholders.

Promotion of distributed generation by educational institutions Comments requested from Stakeholders. Promotion of distributed generation by educational institutions Comments requested from Stakeholders. Introduction and Context On 31st May 2018 the Hon ble Minister for Electricity announced in the Tamil

More information

Overview of Kenya Power Situation

Overview of Kenya Power Situation MINISTRY OF ENERGY AND PETROLEUM RENEWABLE ENERGY PROGRAMMES AND MINIGRIDS ACTIVITIES Eng. Isaac N. KIVA 11-12 th May 2015, Intercontinental Hotel, Nairobi Overview of Kenya Power Situation TYPE OF GENERATION

More information

Mandatory Energy Management Requirements under Energy Conservation Act

Mandatory Energy Management Requirements under Energy Conservation Act Mandatory Energy Management Requirements under Energy Conservation Act Presented by: Mr Winston Tan Assistant Manager Energy Efficiency & Conservation Department Presented at: Workshop on Energy Management

More information

DEMAND FOR BIOMASS PELLETS AND CHIPS: JAPAN AND SOUTH KOREA

DEMAND FOR BIOMASS PELLETS AND CHIPS: JAPAN AND SOUTH KOREA DEMAND FOR BIOMASS PELLETS AND CHIPS: JAPAN AND SOUTH KOREA In Asian markets, South Korea and Japan are the two largest consumers of wood pellets and wood chips. South Korea has been consuming roughly

More information

Vietnam Renewable Energy development project to 2030 with outlook to 2050

Vietnam Renewable Energy development project to 2030 with outlook to 2050 Vietnam Renewable Energy development project to 2030 with outlook to 2050 Pham Trong Thuc Director, Department of Renewable Energy The General Directorate of Energy Ministry of Industry and Trade 1 CONTENTS

More information

Commercial Project Management Services

Commercial Project Management Services Introduction Rod Jané President, New England Expansion Strategies Former Executive Director, MOBD Former Senior Executive with Honeywell, Inc. Former Selectman in Westborough 1 Commercial Project Management

More information

European Parliament plenary vote, 17 January this Directive have the sole function of showing

European Parliament plenary vote, 17 January this Directive have the sole function of showing Overview of final draft text of Renewable Energy Directive (REDII) Comparing proposals from the EU Commission, Council and Parliament as of January 17th, 2018 - Includes only text elements which comprises

More information

YTL POWER INTERNATIONAL BERHAD (Company No H) (Incorporated in Malaysia)

YTL POWER INTERNATIONAL BERHAD (Company No H) (Incorporated in Malaysia) Interim financial report on consolidated results for the quarter ended 31 December 2006. The figures have not been audited. CONDENSED CONSOLIDATED INCOME STATEMENTS INDIVIDUAL QUARTER CUMULATIVE PERIOD

More information

Employment Investment Incentive Scheme (EII) Application Form. Fáilte Ireland

Employment Investment Incentive Scheme (EII) Application Form. Fáilte Ireland Employment Investment Incentive Scheme (EII) Application Form Fáilte Ireland 1 The Employment Investment Incentive Scheme for Tourism Background: The new Employment Investment Incentive Scheme ( EII ),

More information

To: The Chief Executives of Education and Training Boards

To: The Chief Executives of Education and Training Boards To: The Chief Executives of Education and Training Boards Circular Letter 0065/2017 PROTECTION OF EMPLOYEES (FIXED-TERM WORK) ACT 2003 IMPLEMENTATION OF AGREEMENT IN RESPECT OF TUTORS EMPLOYED BY EDUCATION

More information

APEX HEALTHCARE BERHAD (COMPANY NO T)

APEX HEALTHCARE BERHAD (COMPANY NO T) 1. Introduction The Board of Directors of Apex Healthcare Berhad ( AHB or the Company ) is pleased to announce that its wholly-owned subsidiary, Xepa-Soul Pattinson (Malaysia) Sdn Bhd ( Xepa ), has been

More information

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Wind Power in Denmark Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Outline Status on wind power deployment and large scale integration Support system and consent

More information

PROCUREMENT CODE OF CONDUCT

PROCUREMENT CODE OF CONDUCT PROCUREMENT CODE OF CONDUCT 1 PROCUREMENT CODE OF CONDUCT Sabah Electricity Sdn Bhd (SESB) believes that all supplier/contractor relationships should be based on principles of good governance such as integrity,

More information

Labelling provision in Directive 2003/54/EC

Labelling provision in Directive 2003/54/EC NOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54 AND 2003/55 ON THE INTERNAL MARKET IN ELECTRICITY AND NATURAL GAS THIS DOCUMENT IS NOT BINDING ON THE COMMISSION Labelling provision in Directive 2003/54/EC

More information

Walk through the Eligible Customer Regulation. Dr. Seun Amoda

Walk through the Eligible Customer Regulation. Dr. Seun Amoda Walk through the Eligible Customer Regulation Dr. Seun Amoda 1 INTRODUCTION 2 The Nigerian Grid Voltages 330kV 132kV 33KV 11KV 415V 3 The Nigerian Grid 4 Eligibility - EPSRA 2005 Section 100 of EPSR Act

More information