Construction Traffic Analysis
|
|
- Baldwin Francis
- 5 years ago
- Views:
Transcription
1 Construction Traffic Analysis
2 TRANSMITTED Ms. Julie Berger Senior Project Manager Impact Sciences, Inc. 234 East Colorado Boulevard, Suite 205 Pasadena, California RE: Figueroa & Adams Residential Project Construction Traffic Analysis Dear Julie, A traffic impact analysis has been conducted to assess potential traffic impacts of the Figueroa & Adams Residential Project during that project s construction period. This analysis is consistent with the traffic impact analysis which was prepared in July 2008 by our firm and was approved by LADOT, and which addressed the project traffic impacts following the completion of construction and long-term occupancy. The procedures, data and results of the construction traffic analysis are detailed below. Construction Phases Project construction activities are estimated to occur over a 24 months period, now estimated to begin in May 2010 and end in May 2012 (Note: Traffic Impact Study dated July 2008 assumed completion in 2011). The 24-month period construction activities will be sequenced through three phases as shown in Table 1. It should be noted that some overlaps might occur between phases. Table 1 Project Construction Phases Phase Approximate Time Period Start Month End Month 1. Grading/ Excavation 6 month May 2010 November Framing/ Superstructure 12 month November 2010 November Finishes/ Landscaping 6 month November 2011 May 2012 Please note that the above schedule is tentative and adjustments in the schedule may occur due to unforeseen circumstances.
3 Ms. Julie Berger Page 2 During the construction period, the delivery trucks would access/egress the project site during nonpeak hours. Construction workers will park at an off-site lot and be shuttled to the project site until the garage portion of the project is completed, at which time they will park in the garage. However, to reflect the maximum construction traffic generation at the site and on the surrounding streets, it is assumed that the construction workers will park on-site during the entire construction period. Likewise, it is expected that on-site construction activity will fluctuate on a weekly basis, depending largely on the number of workers and construction trucks needed for the activities during each time period. In order to remain conservative, the portion of the project construction phase which generates the highest daily construction-related traffic was analyzed. Thus, the values below represent the maximum rather than average conditions during each phase. The maximum number of construction workers on-site and delivery trucks entering/leaving the site per day will vary according to the construction phase. These maximum values are estimated in Table 2 below. Table 2 Project Construction Phases Phase Workers/Day No. of Excavation/Delivery Trucks/Day 1. Grading/ Excavation 15 workers 40 trucks 2. Framing/ Superstructure 140 workers 20 trucks 3. Finishes/ Landscaping 125 workers 5 trucks Construction Trip Generation The daily, AM and PM peak hour trip rates used for determining the project s construction trip generating potential are based on the 7th Edition of ITE Trip Generation manual for General Light Industrial workers. The rates are shown in Table 3. Table 3 Project Trip Generation Rates and Equations General Light Industrial (per employee) LU 110 Daily: T = 3.02 (E) AM Peak Hour: T = 0.44 (E); I/B = 83%, O/B = 17% PM Peak Hour: T = 0.42 (E); I/B = 21%, O/B = 79% Where: T = trip ends E = employee I/B = inbound O/B = outbound Source: Trip Generation, 7th Edition, Institute of Transportation Engineers, Washington D.C., 2003.
4 Ms. Julie Berger Page 3 Using all of the above rates, a construction-related trip generation for the proposed project was calculated and is illustrated in Table 4 below. Truck trips were added to these trips to estimate total site trips for each phase. Because excavation/delivery truck trips will occur during nonpeak hours due to restrictions placed on the haul route permit, they are not included in the trip generation rate. Table 4 Construction-Related Trip Generation AM Peak Hour * PM Peak Hour * Construction Stages Maximum Workers/Trucks Daily In Out Total In Out Total Worker Trips 1. Grading/ Excavation 15 workers/day Less Transit/Walk-in/Bicycle **: 15% (7) (1) 0 (1) 0 (1) (1) Framing/ Superstructure 140 workers/day Less Transit/Walk-in/Bicycle **: 15% (63) (8) (2) (9) (2) (7) (9) Finishes/ Landscaping 125 workers/day Less Transit/Walk-in/Bicycle **: 15% (57) (7) (1) (8) (2) (6) (8) Truck Trips 1. Grading/ Excavation 40 trucks/day 160 *** Framing/ Superstructure 20 trucks/day 80 *** Finishes/ Landscaping 5 trucks/day 20 *** Total Daily Construction Trips 1. Grading/ Excavation Framing/ Superstructure Finishes/ Landscaping * Since all truck-devlivery activities occur during non-peak hours, no truck trips were caluculated during AM and PM peak periods. ** Transit/Walk-in/Bicycle trip credits for the construction employee trips were taken to be the same percentage as the proposed project. This trip adjustment factor was approved for this site by LADOT and was discussed in the Traffic Impact Study dated July *** One inbound and one outbound trip per day and a Passenger Car Equivalent Factor of 2.0 included for each truck. As illustrated in Table 4 above, the maximum number of construction period vehicles accessing/egressing the site is expected to occur during Phase 2. For the purpose of a
5 Ms. Julie Berger Page 4 conservative study, the proceeding analysis assumes the Phase 2 trip generation (440 daily trips with 53 AM Peak Hour trips and 50 PM Peak Hour trips) will occur during the entire 24-month construction period. The proposed project s operational trip generation identified in the July 2008 Traffic Impact Report was based on a conservative analysis that assumed all units would be leased by the general public. Based on this tenancy, it was estimated that there would be 870 daily trips with 64 AM Peak Hour trips and 82 Peak Hour trips. With implementation of mitigation requiring that the project occupancy be 90% students, faculty and staff of local education institutions, trip generation would be reduced by 50% and no significant traffic impact would occur at any of the study intersections. As shown in the analysis below, no significant traffic impact is anticipated to occur during the construction phase; therefore, no mitigation is required.. Intersection Construction Traffic Impacts of the Proposed Project Because the project s construction trip generation is less than the operational trip generation (approximately 50% fewer daily trips with 17% fewer AM Peak Hour Trips and 39% fewer PM Peak Hour trips), construction activity is anticipated result in less traffic impact at any study intersections than the completed proposed project. Even so, the temporary construction-related traffic impacts at the 11 study intersections identified in the July 2008 Traffic Impact Report were analyzed using the same existing traffic count volumes, cumulative traffic growth assumptions and utilizing the same methodology used in the Traffic Impact Report (namely the procedures outlined in Circular Number 212 of the Transportation Research Board 1 ). Since construction workers are expected to live throughout the Los Angeles region, they are also expected to arrive to the project site from all directions. As such, the construction trip distribution is assumed to be the same as the operational project trip distribution. Based on the CMA methodology, the project s construction impacts on the future conditions were calculated conservatively utilizing the same methodology which was used for the completed project in the Traffic Impact Report dated July Those results are summarized in Table 5. 1 Interim Materials on Highway Capacity, Circular Number 212, Transportation Research Board, Washington, D.C., 1980
6 Ms. Julie Berger Page 5 Table 5 Critical Movement Analysis (CMA) Summary Existing (2008) and Future (2011) Without and With Project Construction Trips Future (2011) Without Future (2011) With Peak Existing Project Construction Project Construction No. Intersection Hour CMA LOS CMA LOS CMA LOS Impact 1. Figueroa Street and AM D F F Washington Boulevard PM C E E th Street and AM A A A US- 10 W/B Ramps PM A A A Hoover Street and AM B C C US- 10 E/B Ramps PM B C C rd Street and AM A B B US- 110 S/B Off-ramp PM A A A rd Street and AM A B B Figueroa Street PM B D D rd Street and AM A A A Flower Street PM B D D Adams Boulevard and AM C D D Hoover Street PM D E E Adams Boulevard and AM C E E Figueroa Street PM D F F Adams Boulevard and AM A B B Flower Street PM D E E Adams Boulevard and AM E F F US- 110 N/B Off-ramp PM B C C Figueroa Street and AM A B B Jefferson Boulevard PM B C C As shown above, based upon a CMA analysis, the project construction-related traffic will not cause a significant traffic impact at any study intersections; therefore; no mitigation is required. Parking During Construction During the construction period, the existing 125 church parking spaces on the project site will be displaced. The developer has entered into an agreement with St. Vincent School, which is located immediate north of the project site, to utilize the school s parking lot for interim church parking on Sundays, when church attendance is highest. The letter of agreement is included in Appendix A. A separate lot will also be leased off-site for construction workers needing parking prior to completion of the site parking garage. Therefore, no significant parking impacts are anticipated during the construction period and no mitigation is required.
7 Ms. Julie Berger Page 6 Mitigation The construction of the project is not anticipated to cause significant traffic impacts at any of the study intersections. In addition, interim parking for the church has been arranged to address the displacement of that parking and off-site parking will be provided for construction workers prior to completion of the site parking garage. As a result, no mitigation measures are warranted. If you have any questions, please feel free to contact me with any questions. Sincerely, George Rhyner Senior Transportation Engineer GR:kl C19372 JA89145 enclosures
8 APPENDIX A Letter of Interim Parking agreement
9
10
Appendix H. Millennium Hollywood Project Trip Cap and Mitigation Triggers
Appendix H Millennium Hollywood Project Trip Cap and Mitigation Triggers MILLENNIUM HOLLYWOOD PROJECT TRIP CAP AND MITIGATION TRIGGERS Crain and Associates Introduction The Millennium Hollywood Project
More informationDate: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis
MEMORANDUM To: CAJA Environmental Services, LLC Date: From: Subject: Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis LLG
More informationBCEO TRAFFIC IMPACT STUDY GUIDELINES
BCEO TRAFFIC IMPACT STUDY GUIDELINES February 2006 TABLE OF CONTENTS INTRODUCTION..... i TRAFFIC IMPACT STUDY STRUCTURE... 1 WHEN IS A TRAFFIC IMPACT STUDY NEEDED?..... 1 STUDY AREA, SITE PLAN & HORIZON
More informationVEHICLES MILES TRAVELED (VMT) TRAFFIC IMPACT METRIC
VEHICLES MILES TRAVELED (VMT) TRAFFIC IMPACT METRIC A project-specific quantified analysis of the MGA Campus has been undertaken to compare BAU to the project including the project s VMT reduction program
More informationAPPENDIX A. City of Hudson LWRP and. O&G Truck Route Alternatives- Traffic Analysis
APPENDIX A City of Hudson LWRP and O&G Truck Route Alternatives- Traffic Analysis LWRP Build-Out Traffic Generation Existing Zoning Area Total In Out 1A and 1B Residential 210 & 230 1,555 D.U 1,197 778
More informationTraffic and Parking. Introduction. 3G.2 Environmental Setting. Description of Key Roadways
3G 3G.1 Traffic and Parking Introduction This section presents the methodology, findings, and conclusions of the traffic impact analysis prepared by Allyn D. Rifkin, transportation planner/engineer for
More information3.6 GROUND TRANSPORTATION
3.6.1 Environmental Setting 3.6.1.1 Area of Influence The area of influence for ground transportation consists of the streets and intersections that could be affected by automobile or truck traffic to
More informationIII. ENVIRONMENTAL IMPACT ANALYSIS F. TRAFFIC
III. ENVIRONMENTAL IMPACT ANALYSIS F. TRAFFIC This section summarizes the traffic impact analysis prepared by Kaku Associates in May, 2002. Detailed calculation worksheets are contained in Appendix D to
More informationCITY OF VALLEJO PUBLIC WORKS DEPARTMENT TRAFFIC IMPACT Analysis/Study GUIDELINES
The City Engineer, under the authority of the Public Works Director and recommendations from the Traffic Engineer, will make the final decision on the need for a traffic study. The purpose of the traffic
More informationDistrict of North Vancouver Construction Traffic Management Plan Guidelines
District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction
More informationDISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS
DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver
More informationTraffic Impact Study Guidelines. City of Guelph
Traffic Impact Study Guidelines City of Guelph April 2016 Engineering and Capital Infrastructure Services Infrastructure, Development & Enterprise 1 Carden Street Guelph, Ontario Canada N1H 3A1 Page 1
More informationERRATA TO THE FINAL EIR
DRAFT EIR ERRATA TO THE FINAL EIR The following paragraphs in Section 6.0, Alternatives, are edited as follows: The following discussion evaluates alternatives to the Proposed Project and examines the
More informationCITY OF LYNDEN TRAFFIC IMPACT ANALYSIS REQUIREMENTS
CITY OF LYNDEN TRAFFIC IMPACT ANALYSIS REQUIREMENTS This analysis is required of all developments and shall be submitted with SEPA documents or, if the project is exempt from SEPA, shall be submitted with
More informationFOREST LAWN MEMORIAL PARK HOLLYWOOD HILLS MASTER PLAN TRIP GENERATION ASSESSMENT
Crain & Associates May 1, 2008 FOREST LAWN MEMORIAL PARK HOLLYWOOD HILLS MASTER PLAN TRIP GENERATION ASSESSMENT The Forest Lawn Memorial Park Hollywood Hills Master Plan Project (the Project ) is an expansion
More informationExhibit J: Other City Correspondence
Exhibit J: Other City Correspondence Case No: CPC 2012 3357 GPA SP For consideration by the City Planning Commission February 14, 2013 CITY OF LOS ANGELES CALIFORNIA Jaime de la Vega GENERAL MANAGER
More informationATTACHMENT C ATTACHMENT C
ATTACHMENT C ATTACHMENT C September 28, 2015 Ms. Nicole Criste Terra Nova Planning & Research 42635 Melanie Place, #101 Palm Desert, CA 92211 SUBJECT: PROJECT JUPITER TRIP GENERATION EVALUATION Dear Ms.
More informationFuture Build Alternative Traffic Forecasts and Level of Service Analysis
4.2.10 Future Build Alternative Traffic Forecasts and Level of Service Analysis For the five Build Alternatives, study intersections within one mile of potential station locations were analyzed, as it
More information2017 TIGER DISCRETIONARY GRANT APPLICATION
2017 TIGER DISCRETIONARY GRANT APPLICATION Spokane International Airport Spokane, WA APPENDIX A Letters of Support 801 W. Riverside Suite 100 Spokane WA 99201 Phone: 509.624.1393 800.SPOKANE
More informationArticle 16 Traffic Impact Analysis
Article 16 Traffic Impact Analysis Table of Contents... 16-1 Chapter 16.1 Purpose and Intent... 16-2 Chapter 16.2 Applicability... 16-2 Chapter 16.3 Exemptions... 16-2 Chapter 16.4 Trip Generation Data...
More informationUPTOWN TRAFFIC IMPACT ANALYSIS
UPTOWN TRAFFIC IMPACT ANALYSIS This memorandum summarizes the results of the traffic analysis conducted to evaluate the traffic operations of the intersections along Post Oak Boulevard within Uptown Houston
More informationA+ ACADEMY HIGH SCHOOL
TRAFFIC MANAGEMENT PLAN FOR A+ ACADEMY HIGH SCHOOL IN DALLAS, TEXAS Prepared for: A+ Charter Schools, Inc. 8225 Bruton Road Dallas, Texas 75217 Prepared by: Texas Registered Engineering Firm F-3199 400
More information4. ENVIRONMENTAL IMPACT ANALYSIS 11. TRANSPORTATION AND CIRCULATION 1. TRAFFIC
4. EVIROMETAL IMPACT AALYSIS 11. TRASPORTATIO AD CIRCULATIO 1. TRAFFIC 1. ITRODUCTIO The following section summarizes the information provided in the Traffic Impact Study, SMC Malibu Satellite Campus Project,
More informationPublic Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival
Proposed Liberty Village Natural Gas Pipeline Project Public Open House Please sign-in at the registration table upon arrival Feel free to approach any team member to discuss the project Share your thoughts
More informationSection 4.8 Climate Change
Section 4.8 Climate Change This section summarizes the potential for climate change impacts resulting from construction and operation of the proposed Eastside Transit Corridor Phase 2 Project alternatives.
More information4.11 TRANSPORTATION AND CIRCULATION
4.11 TRANSPORTATION AND CIRCULATION 4.11.1 INTRODUCTION This section addresses the potential for the Proposed Project to impact traffic and circulation. Information in this section is summarized from the
More informationProposal for a Transportation Impact Analysis of the Castilleja School project in Palo Alto
October 21, 2016 Ms. Katherine Waugh, AICP Senior Project Manager Dudek 853 Lincoln Way, Suite 208 Auburn, CA 95603 Proposal for a Transportation Impact Analysis of the Castilleja School project in Palo
More information1.0 INTRODUCTION A. PURPOSE OF THE DRAFT EIR 1-1
1.0 INTRODUCTION This Draft Environmental Impact Report (Draft EIR or EIR) has been prepared for the 1020 S. Figueroa Street Project (the Project). Jia Yuan USA Co., Inc., the Applicant, proposes to develop
More informationCity of Menifee. Public Works Department. Traffic Impact Analysis Guidelines
Public Works Department Traffic Impact Analysis Guidelines Revised: August 2015 TABLE OF CONTENTS INTRODUCTION... 3 PURPOSE... 3 EXEMPTIONS... 3 SCOPING... 4 METHODOLOGY... 5 STUDY AREA... 6 STUDY SCENARIOS...
More informationLos Angeles County Congestion Reduction Demonstration Project
Los Angeles County Congestion Reduction Demonstration Project frequently asked questions update #1 /august 2008 Los Angeles County Metropolitan Transportation Authority (Metro), California Department of
More informationAPPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies
APPENDIX B Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies Revised December 7, 2010 via Resolution # 100991 Reformatted March 18, 2011 TABLE OF CONTENTS
More informationGeneral Guidelines for the Preparation of Traffic Impact Studies
ENGINEERING & OPERATIONS DIVISION General Guidelines for the Preparation of Traffic Impact Studies April 2010 Prepared by: Highway Planning and Design Branch Table of Contents 1. INTRODUCTION 1 2. TRAFFIC
More informationALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS
EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS FINAL REPORT SEPTEMBER 2010 TABLE OF CONTENTS 1.0 INTRODUCTION 1 2.0 EXISTING TRAFFIC CONDITIONS 2 3.0 FUTURE TRAFFIC CONDITIONS 3 4.0 POTENTIAL IMPACTS
More informationTRAFFIC & TRANSPORTATION COMMISSION AGENDA REPORT
TRAFFIC & TRANSPORTATION COMMISSION AGENDA REPORT AGENDA ITEM #4 T/T MTG: 092616 DATE: SEPTEMBER 26, 2016 TO: TRAFFIC & TRANSPORTATION COMMISSION FROM: BENJAMIN CHAN, P.E, T.E., DEPUTY PUBLIC WORKS DIRECTOR
More informationI-90 ALLSTON INTERCHANGE
I-90 ALLSTON INTERCHANGE A MULTIMODAL TRANSPORTATION PROJECT TASK FORCE MEETING March 10, 2016 FIORENTINO COMMUNITY CENTER 1 Meeting Agenda Welcome & Introductions Urban Interchange Concept 3K-4c with
More informationCITY OF DRAPER TRAFFIC IMPACT STUDY DESIGN GUIDELINES
CITY OF DRAPER TRAFFIC IMPACT STUDY DESIGN GUIDELINES June 1, 2012 Draper City Traffic Impact Study Guidelines Table of Contents Introduction... 1 Traffic Impact Classification Levels... 1 Analysis Approach
More information5.3 Traffic and Circulation
5.3 Traffic and Circulation 5.3 TRAFFIC/CIRCULATION This section is based upon the Traffic Impact Study for Azusa Material Recovery Facility and Transfer Station (Traffic Impact Study), dated December
More informationTRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES
TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES The District of West Vancouver requires a Traffic Management Plan (TMP) to be submitted for acceptance by the Land Development
More informationGuidelines for the Submission of a Transportation Study Level 2
Guidelines for the Submission of a Transportation Study Level 2 For Site Development Applications in the City of North Vancouver Transportation Group, City of North Vancouver Engineering, Parks & Environment
More informationLANDSIDE FACILITIES AIRLINE TERMINAL FACILITIES INVENTORY 5.0 INTRODUCTION C H A P T E R 1 CHAPTER 5
C H A P T E R 1 INVENTORY AIRLINE TERMINAL FACILITIES INVENTORY CHAPTER 5 LANDSIDE FACILITIES 5.0 INTRODUCTION This chapter focuses on the landside circulation and access system at the Spokane International
More informationRegional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report
Los Angeles County Metropolitan Transportation Authority Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report Public Scoping Meeting 1 Agenda!
More informationCity of Berkeley. Guidelines for Development of Traffic Impact Reports
Office of Transportation (OOT) City of Berkeley Guidelines for Development of Traffic Impact Reports Office of Transportation, City of Berkeley 1 1. Overview These guidelines provide a framework to help
More informationTraffic Impact Analysis Guidelines. Town of Queen Creek
Traffic Impact Analysis Guidelines Town of Queen Creek January 2016 1. INTRODUCTION The purpose of this document is to outline the procedures and requirements for preparing a Transportation Impact Analysis
More informationLetter No Impact Sciences, Inc Temporary use of the Rose Bowl by the NFL November 2012
Letter No. 48 1 3.0-303 1 2 3 3.0-304 3 4 5 3.0-305 6 7 8 9 10 11 3.0-306 12 13 3.0-307 13 14 3.0-308 14 15 3.0-309 15 3.0-310 16 3.0-311 16 17 3.0-312 17 18 19 3.0-313 19 20 21 22 3.0-314 22 23 24 3.0-315
More informationEnvironmental Impact Statement Milton Logistics Hub Project Transportation & Municipal Finance
Milton Logistics Hub Project 187 EllSo Consulting Inc. March 10, 2017 www.ellsoconsulting.com EllSo Consulting March 10, 2017 Curt Benson, MCIP RPP Manager, Community Planning Halton Region 1151 Bronte
More informationSource: Utah Department of Transportation. Page 1
SUMMARY The Los Angeles Departments of City Planning (DCP) and Transportation (LADOT) are updating the City s California Environmental Quality Act (CEQA) Transportation Section of the City s California
More informationDear Mr. Huerta, A hard copy will follow via US Mail. Best Regards,
From: Alejandro Huerta [mailto:alejandro.huerta@lacity.org] Sent: Wednesday, November 18, 2015 1:41 PM To: Heidi Mekkelson; Stephanie Eyestone-Jones Subject: Fwd: Crossroads Hollywood_NOP_DEIR_Metro Comments
More informationA.M. Peak Hour P.M. Peak Hour Land Use Intensity Daily Total In Out Total In Out. Shopping Center 236,160 SF
April 23, 218 Mr. Michael Berenbom LANE4 Property Group, Inc. 475 Central Street Kansas City, MO 64112 RE: Dear Mr. Berenbom, French Market Trip Generation Overland Park, Kansas As requested, Priority
More information1.0 Introduction Traffic Study Overview Study Area Overview of Senate Bill
TABLE OF CONTENTS SECTION PAGE 1.0 Introduction... 1 1.1 Traffic Study Overview... 1 1.2 Study Area... 3 1.3 Overview of Senate Bill 743... 4 2.0 Project Description... 5 2.1 Site Location... 5 2.2 Existing
More informationCOMMERCIAL WASTE MANAGEMENT STUDY VOLUME III CONVERTED MARINE TRANSFER STATIONS - Commercial Waste Processing and Analysis of Potential Impacts
COMMERCIAL WASTE MANAGEMENT STUDY VOLUME III CONVERTED MARINE TRANSFER STATIONS - Commercial Waste Processing and Analysis of Potential Impacts March 2004 Prepared for: New York City Department of Sanitation
More informationPrepared By: Gorove/Slade Associates, Inc.
Traffic Impact Analysis Monument View Arlington County, Virginia Prepared For: Gensler 2020 K Street, NW Suite 200 Washington DC 20006 Prepared By: Gorove/Slade Associates, Inc. PREPARED BY: Gorove/Slade
More informationTABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...
Amendment No. 2 to Reclamation Plan 2006-01 Traffic Impact Analysis TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX
More informationRobinson Landing: Townhouse Pre-Construction Presentation January 9, 2018
Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence
More informationAPPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED
APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT
Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS B203 Sacramento,
More information2017 TIGER DISCRETIONARY GRANT APPLICATION
2017 TIGER DISCRETIONARY GRANT APPLICATION Spokane International Airport Spokane, WA APPENDIX D 2015 Airport Drive Couplet at Spotted Road Airport Drive Couplet at Spotted Road April 2015 Prepared for:
More informationTransportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1
TRANSPORTATION IMPACT STUDY (TIS) GUIDELINES FOR DEVELOPMENT APPLICATIONS Transportation and Works Department The Regional Municipality of York 17250 Yonge Street Newmarket, Ontario L3Y 6Z1 August, 2007
More informationMs. Jennifer Campos RECON Environmental, Inc Fifth Avenue San Diego, CA LLG Reference:
September 22, 2017 Ms. Jennifer Campos RECON Environmental, Inc. 1927 Fifth Avenue San Diego, CA 92101 LLG Reference: 3-17-2780 Subject: Victory Industrial Park/Escondido Innovation Center: Warehouse Proposal
More informationVIII. LAND USE ISSUES
VIII. LAND USE ISSUES The & Route 57 Land Use and Circulation Study (Land Use Study, Figure 6) was completed for the Town of Clay in November 1999 (Clough, Harbour & Associates). This study investigated
More informationTraffic Impact Studies
G U I D E Ministry of Transportation General Guidelines for the Preparation of Traffic Impact Studies L I N E S January 2008 1.0 Introduction: The main purpose of a Traffic Impact Study (TIS) is to demonstrate
More informationCHAPTER 12 TRANSPORTATION. Introduction Setting Impacts and Mitigation Measures of the 2015 Plan Alternatives
CHAPTER 2 TRANSPORTATION Introduction Setting Impacts and Mitigation Measures of the 205 Plan Alternatives CHAPTER 2 TRANSPORTATION INTRODUCTION This chapter presents the traffic impact analysis conducted
More informationHERALD EXAMINER PROJECT
D R A F T E N V I R O N M E N T A L I M P A C T R E P O R T HERALD EXAMINER PROJECT Volume I EIR Case File No: ENV-2005-4654-EIR SCH No. 2005081146 Prepared for: Los Angeles Department of City Planning
More information5.4.1 METHODOLOGY AND PERFORMANCE CRITERIA
Section 5.4 TRAFFIC 5.4 TRAFFIC This section evaluates the impacts of the proposed project on the local traffic system in the vicinity of the project site. This analysis summarizes the findings of the
More informationPORT OF FERNANDINA TRUCK CIRCULATION STUDY
OCTOBER 2015 PREPARED FOR: I. Introduction... 1 II. Study Area... 1 III. Field Data Collection... 3 IV. Existing Traffic... 5 V. Truck Circulation Analysis... 8 VI. Peak Hour Intersection Analysis... 10
More informationST. MARK S SCHOOL OF TEXAS
TRAFFIC MANAGEMENT PLAN FOR ST. MARK S SCHOOL OF TEXAS IN DALLAS, TEXAS DESHAZO PROJECT NO. 15200 Z156-218 (RB) Prepared for: 10600 Preston Road Dallas, Texas 75230 Prepared by: Texas Registered Engineering
More informationProject Title: Using Truck GPS Data for Freight Performance Analysis in the Twin Cities Metro Area Prepared by: Chen-Fu Liao (PI) Task Due: 12/31/2013
Project Title: Using Truck GPS Data for Freight Performance Analysis in the Twin Cities Metro Area Prepared by: Chen-Fu Liao (PI) Task Due: 12/31/2013 TASK #5: IDENTIFY FREIGHT NODE, FREIGHT SIGNIFICANT
More informationTraffic Impact Study Requirements
[TYPE THE COMPANY NAME] Traffic Impact Study Requirements County of San Mateo Department of Public Works Roadway Services 9/1/2013 I. Introduction The County of San Mateo (County), Department of Public
More informationCITY OF MARIANNA MUNICIPAL DEVELOPMENT DEPARTMENT Post Office Box 936 Marianna, FL (850)
CITY OF MARIANNA MUNICIPAL DEVELOPMENT DEPARTMENT Post Office Box 936 Marianna, FL 32447 (850) 482-2786 TRANSPORTATION CONCURRENCY ANALYSIS CITY OF MARIANNA CONCURRENCY MANAGEMENT SYSTEM (CMS) This form
More informationPROJECT DESCRIPTION...
TABLE OF CONTENTS Volume I Chapter Page 1. INTRODUCTION... 1-1 1.1 Introduction... 1-1 1.2 Project Description... 1-1 1.3 Purpose of the EIR... 1-2 1.4 EIR Process... 1-3 1.5 Scope of the Draft EIR...
More informationHALDIMAND COUNTY DESIGN CRITERIA SECTION T TRAFFIC IMPACT STUDY GUIDELINES
HALDIMAND COUNTY DESIGN CRITERIA SECTION T TRAFFIC IMPACT STUDY GUIDELINES Revised 2015 TRAFFIC IMPACT STUDIES PAGE 1 T 1.00 T 1.01 INTRODUCTION TRAFFIC IMPACT STUDY One of Haldimand County s key objectives
More informationAPPENDIX 'G' Noise Attenuation Analysis
Our File: 6552 ENVIRONMENTAL STUDY REPORT ADDENDUM APPENDIX 'G' Noise Attenuation Analysis March 2008 McCORMICK RANKIN CORPORATION 2655 North Sheridan Way Mississauga, Ontario, L5K 2P8 Tel: (905)823-8500
More informationCITY OF CLOVIS Traffic Impact Study Guidelines
CITY OF CLOVIS Traffic Impact Study Guidelines CLOVIS, A WAY OF LIFE Approved August 25, 2014 City Council Resolution 2014-79 Prepared by City of Clovis Engineering Division Steve White, City Engineer
More informationTRANSPORTATION IMPACT ANALYSISGUIDELINES
TRANSPORTATION IMPACT ANALYSISGUIDELINES ADOPTED OCTOBER2014 SANTACLARAVALLEYTRANSPORTATION AUTHORITY CONGESTION MANAGEMENTPROGRAM CONGESTION MANAGEMENT PROGRAM TRANSPORTATION IMPACT ANALYSIS GUIDELINES
More informationDevelopment of TSP warrants. to-day variability in traffic demand
Development of TSP warrants considering vehicular emissions and day-to to-day variability in traffic demand Zeeshan Abdy Supervisor: Bruce R. Hellinga Dec 2006 Introduction Signalized intersections Traffic
More informationCity of Lake Forest SERRANO SUMMIT (IRWD SITE) Traffic Study. April 2010
G: Traffic Study City of Lake Forest SERRANO SUMMIT (IRWD SITE) Traffic Study April 2010 Draft City of Lake Forest SERRANO SUMMIT (IRWD SITE) Traffic Study Prepared by: Austin-Foust Associates, Inc. 2223
More informationSacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project
Sacramento Municipal Utility District Headquarters Building Final Initial Study and Mitigated Negative Declaration March 2015 Sacramento Municipal Utility District Headquarters Building Final Initial Study
More informationJanuary 16, Rhode Island Energy Facilities Siting Board 89 Jefferson Boulevard Warwick, Rhode Island 02888
INVENERGY 196 January 16, 2019 Rhode Island Energy Facilities Siting Board 89 Jefferson Boulevard Warwick, Rhode Island 02888 Re: Clear River Energy Center Invenergy Docket No. SB-2015-06 When Invenergy
More informationAppendix G Analysis of Project Impacts Compared to Existing Conditions
Appendix G Analysis of Project Impacts Compared to Existing Conditions This page intentionally left blank. Analysis of Project Impacts Compared to Existing Conditions Introduction The analysis scenarios
More informationRE: A Traffic Impact Statement for the newly proposed Fall River South Development
James J. Copeland, P.Eng. GRIFFIN transportation group inc. 30 Bonny View Drive Fall River, NS B2T 1R2 May 15, 2018 Chris Boudreau, P.Eng. Manager Engineering Strum Consulting Railside, 1355 Bedford Highway
More informationThe Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges
The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares
More informationTruck Management ` Strategies in Los Angeles
Truck Management ` Strategies in Los Angeles Susan Bok, AICP Senior Transportation Planner Los Angeles Department of Transportation NACTO Chicago Workshop May 11-12, 2009 Context Population Downtown LA
More informationNovember 8, RE: Harrah s Station Square Casino Transportation Analysis Detailed Traffic Impact Study Review. Dear Mr. Rowe:
November 8, 2006 Mr. Glenn Rowe, P.E. Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering Commonwealth Keystone Building 400 North Street, 6 th Floor Harrisburg,
More informationJim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project
Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail
More informationEXHIBIT LIST No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20
Reference No: HOC/10001 Petitioner: Phase 2a Teach-ins Published to Collaboration Area: Friday 23-Mar-2018 EXHIBIT LIST Page 1 of 20 No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20 HOC/10001/0001
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,
More informationCITY OF LETHBRIDGE TRAFFIC IMPACT STUDY GUIDELINES
CITY OF LETHBRIDGE TRAFFIC IMPACT STUDY GUIDELINES March 2008 0526 TABLE OF CONTENTS Section Contents Page 1.0 INTRODUCTION 1 1.1 Traffic Impact Study 1 1.2 Need and Justification 2 1.3 Purpose of Guidelines
More informationTRAFFIC STUDY GUIDELINES
TRAFFIC STUDY GUIDELINES December 2013 The scope of the traffic impact analysis (TIA) should follow these guidelines and the requirements of VMC 11.80.130 and VMC 11.70, transportation concurrency (attached
More informationAuthors: Address: 550 W Algonquin Road Arlington Heights, IL Phone:
Title: Authors: Harvey Transit Signal Priority Demonstration Project Evaluation Taqhiuddin Mohammed, Senior Transit ITS Engineer Pace Bus. Kevin O Neill, ITS & Traffic Engineer, URS Corporation, Chicago.
More informationPEER REVIEW FOR TRANSPORTATION ASSESSMENT ZONING APPLICATION REVIEW
PEER REVIEW FOR TRANSPORTATION ASSESSMENT ZONING APPLICATION REVIEW REPORT MARCH 2011 I B I G R O U P R E P O R T TABLE OF CONTENTS 1. INTRODUCTION... 1 2. SYNOPSIS OF APPLICANT S ASSESSMENT... 1 2.1 Transportation
More information6.0 CONGESTION HOT SPOT PROBLEM AND IMPROVEMENT TRAVEL DEMAND MODEL ANALYSIS
6.0 CONGESTION HOT SPOT PROBLEM AND IMPROVEMENT TRAVEL DEMAND MODEL ANALYSIS 6.1 MODEL RUN SUMMARY NOTEBOOK The Model Run Summary Notebook (under separate cover) provides documentation of the multiple
More informationAdaptive Traffic Control OCTEC Meeting
PRESENTATION FOR THE Adaptive Traffic Control OCTEC Meeting June 21, 2012 VPH (vehicles per hour) Traditional Signal TIming PEAK 15 Min 4000 3500 3000 2500 2000 1500 1000 500 0 AM 12:00 AM 2:00 AM 4:00
More informationWoodburn Interchange Project Transportation Technical Report
Final Report Woodburn Interchange Project Transportation Technical Report Prepared for Oregon Department of Transportation April 212 Prepared by DKS Associates Contents Methodologies... 4 Volume Development...
More informationTRANSPORTATION IMPACT ANALYSIS GUIDELINES FOR ENVIRONMENTAL REVIEW
TRANSPORTATION IMPACT ANALYSIS GUIDELINES FOR ENVIRONMENTAL REVIEW October 2002 The Planning Department City and County of San Francisco TABLE OF CONTENTS I. Introduction 1 II. Overview of Process and
More informationThe TIS is to be signed and sealed by a Florida Registered Professional Engineer.
CHAPTER 900. SECTION 901. DEVELOPMENT STANDARDS INFRASTRUCTURE STANDARDS 901.5. Transportation Impact Study A. Intent and Purpose The intent and purpose of the Traffic Impact Study (TIS) is to identify
More informationDRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0
SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605/SR-60 EA# 3101U0 October 9, 2017 Contents 1 Purpose of ICE Memo... 1 2 Background... 1 3 Existing Interchange Deficiencies... 1 4 Context Sensitive
More information3.12 NOISE Regulatory Setting Environmental Setting EXISTING NOISE SOURCES AND SENSITIVE LAND USES
3.12 NOISE This section assesses the potential for implementation of the West Village Expansion component to result in impacts related to short-term construction, long-term operational noise sources, and
More informationBow Concord I-93 Improvements City of Concord Transportation Policy Advisory Committee
Bow Concord I-93 Improvements City of Concord Transportation Policy Advisory Committee December 15, 2016 Agenda Project History / Project Development Process Traffic Modeling Alternatives Development o
More informationGUIDELINES FOR TRAFFIC IMPACT ANALYSIS (ZONING PETITIONS)
GUIDELINES FOR TRAFFIC IMPACT ANALYSIS (ZONING PETITIONS) (A) INTENT This Section is intended to help ensure that new development does not adversely affect the capacity of streets and intersections to
More informationPlanning Group. Alternative Screening Presentations October/November Bow-Concord Interstate 93 Transportation Planning Study
Planning Group Alternative Screening Presentations October/November 2006 Part A Schedule Planning Group 1 February 1, 2006 Planning Group 2 March 7, 2006 Introduction CSS Overview Brainstorm Problem Statement
More information