1 ASIAN DEVELOPMENT BANK PPA: IND PROJECT PERFORMANCE AUDIT REPORT ON THE NORTH MADRAS THERMAL POWER PROJECT (Loan 798-IND) IN INDIA June 2002

2 CURRENCY EQUIVALENTS Currency Unit Indian Rupee/s (Re/Rs) At Appraisal (October 1986) At Project Completion (March 2001) At Operations Evaluation (April 2002) Re1.00 = $0.083 $0.023 $0.021 $1.00 = Rs12.12 Rs43.00 Rs47.75 ABBREVIATIONS ADB Asian Development Bank EIRR economic internal rate of return FIRR financial internal rate of return GTN Government of Tamil Nadu ICHS internal coal handling system MAUP Madras City Augmentation and Upgradation Project OEM Operations Evaluation Mission PCR project completion report PFC Power Finance Corporation PPAR project performance audit report SEB state electricity board SERC state electricity regulatory commission TNEB Tamil Nadu Electricity Board TNPCB Tamil Nadu Pollution Control Board WEIGHTS AND MEASURES Cal (kilocalorie) - 1,000 calories kv (kilovolt) - 1,000 volts MW (megawatt) - 1,000,000 watts kwh (kilowatt-hour) - 1,000 watt-hours GWh (gigawatt-hour) - 1,000,000 kilowatt-hours NOTES (i) (ii) The fiscal year (FY) of the Government and the Tamil Nadu Electricity Board ends on 31 March. FY before the calendar year denotes the year in which the fiscal year ends. For example, FY2001 begins on 1 April 2000 and ends on 31 March In this report, $ refers to US dollars. Operations Evaluation Department, PE-595

3 CONTENTS Page BASIC DATA EXECUTIVE SUMMARY MAPS iii iv vi I. BACKGROUND 1 A. Rationale 1 B. Formulation 1 C. Purpose and Outputs 2 D. Cost, Financing, and Executing Arrangements 2 E. Completion and Self-Evaluation 2 F. Operations Evaluation 3 II. PLANNING AND IMPLEMENTATION PERFORMANCE 4 A. Formulation and Design 4 B. Achievements and Outputs 4 C. Cost and Scheduling 5 D. Procurement and Construction 6 E. Organization and Management 6 III. ACHIEVEMENT OF PROJECT PURPOSE 7 A. Plant Performance 7 B. Performance of the Operating Entity 7 C. Economic and Financial Reevaluation 7 D. Sustainability 8 IV. ACHIEVEMENT OF OTHER DEVELOPMENT IMPACTS 8 A. Socioeconomic Impact 8 B. Environmental Impact 9 C. Impact on Institutions and Policy 9 V. OVERALL ASSESSMENT 10 A. Relevance 10 B. Efficacy 10 C. Efficiency 10 D. Sustainability 10 E. Institutional Development and Other Impacts 10 F. Overall Project Rating 10 G. Assessment of ADB and Borrower Performance 11 H. Power Sector Policies 11 VI. ISSUES, LESSONS, AND FOLLOW-UP ACTIONS 12 A. Key Issues for the Future 12 B. Lessons Identified 12 C. Follow-Up Actions 13

4 ii APPENDIXES 1. Cost Breakdown by Project Components Implementation Schedule Financial Statements of the Tamil Nadu Electricity Board Economic and Financial Reevaluation Resettlement and Rehabilitation Measures Actions Taken on Stipulated Environmental Conditions 26 SUPPLEMENTARY APPENDIXES (available upon request) A. Socioeconomic Impact Assessment B. Environmental Impact Assessment

5 Key Project Data ($ million) BASIC DATA North Madras Thermal Power Project (Loan 798-IND) As per ADB Loan Documents Actual Total Project Cost Foreign Exchange Costs Local Costs ADB Loan Amount/Utilization Key Dates Expected Actual Fact-Finding 29 Jan 7 Feb May 1986 Appraisal 1 11 Sep 1986 Loan Negotiations Oct 1986 Board Approval 18 Nov 1986 Loan Agreement 21 Jan 1987 Loan Effectiveness 21 Apr Apr 1987 First Disbursement 5 Apr 1988 Project Completion Dec 1992 Jun 1999 Loan Closing 30 Jun Jan 1999 Months (effectiveness to completion) Economic and Financial Appraisal PCR PPAR Internal Rates of Return (%) Economic Internal Rate of Return Financial Internal Rate of Return Borrower Executing Agency Government of India Tamil Nadu Electricity Board (TNEB) Mission Data No. of Missions No. of Person-Days Fact-Finding 2 96 Preappraisal 1 16 Appraisal 1 30 Project Administration Inception 1 8 Review Project Completion 1 4 Operations Evaluation Most missions were fielded to review the progress of projects under several loans. Person-days shown are actual days spent on the Project. 2 The Operations Evaluation Mission comprised Mr. K. E. Seetharam (Evaluation Specialist/Mission Leader), Mr. K. Venkataraman (Staff Consultant), and Mr. J. P. Shrivastava (Domestic Consultant). The Mission visited India from 17 to 31 March Ms. Kus Hardjanti (Evaluation Specialist) joined the meetings and field visit from 17 to 22 March.

6 iv EXECUTIVE SUMMARY The Government of India developed a long-term power development program under the Seventh Five-Year Plan (FY ). The program aimed to alleviate severe power shortages that were serious constraints to economic growth. The program included several thermal power stations utilizing the country's large coal reserves. The North Madras Thermal Power Project (the Project) 1 was an integral part of the national power development program. The main purpose of the Project was to expand the generating capacity of the Tamil Nadu Electricity Board (TNEB), the Executing Agency, by installing north of Madras (now Chennai) two units of 210 megawatts (MW) each to meet the prevailing and anticipated power shortages in Tamil Nadu. The Project comprised (i) civil works for site preparation, foundations, the power station building, and water circulation and other systems; (ii) two 690 ton/hour capacity coal-fired steam boilers and auxiliaries; (iii) two reheat steam turbine generators each with a rated capacity of 210 MW and auxiliaries; (iv) instrumentation and control systems; (v) coal and ash handling systems; (vi) water treatment and other miscellaneous mechanical equipment; (vii) transformers, switchyard equipment, and other miscellaneous electrical equipment; and (viii) consulting services. The Operations Evaluation Mission visited India in March 2002, and held discussions with the officials and experts connected with the Project and the staff of the Asian Development Bank (ADB) India Resident Mission. The Central Electricity Authority formulated the Project. The Project was prepared without an ADB project preparatory technical assistance. Plant design and engineering were technically sound and appropriate in the context of the urgent need for additional generating capacity. At appraisal, the total project cost was estimated at $628 million equivalent, comprising $254 million in foreign exchange costs (40% of the total cost) and $374 million equivalent (60% of the total cost) in local currency costs. The actual project cost at completion was $469 million equivalent, comprising $176 million (38%) in foreign exchange costs and $293 million equivalent (62%) in local currency costs. The significant savings resulted mainly from (i) a major depreciation of the rupee during implementation, (ii) strong competition among international and domestic bidders for ADB-financed contract packages, and (iii) overestimated price contingencies. The commissioning of units 1 and 2 was originally scheduled in March and December 1991, respectively. Several factors led to major delays: land acquisition problems; procurement delays in the award of contracts (due to excessive time taken by TNEB for bid evaluation, lengthy internal approvals of contract awards within TNEB, and additional lengthy process for approval of awards by the Central Electricity Authority and the Government of Tamil Nadu [GTN] before submission to ADB for approval); and considerable delays in the implementation of some contracts, particularly that for the internal coal handling system (ICHS). Units 1 and 2 were eventually commissioned in October 1994 and March 1995, more than 3 years behind schedule. However, their optimum utilization was not possible due to the delay in the commissioning of the ICHS, which became fully operational only in June Thus the total delay in project implementation was 6.5 years. 1 Loan 798-IND: North Madras Thermal Power Project, for $150 million, approved on 18 November 1986.

7 As envisaged at appraisal, the Project provided the additional generating capacity of 420 MW and enabled TNEB to optimize the operation of its hydropower generation facilities. However, until the commissioning of the ICHS, plant performance suffered. Since the ICHS was commissioned in June 1999, performance has been very good with plant load factors exceeding 80%. Operation and maintenance personnel have been adequately trained by TNEB. With the commissioning of the external coal handling system in January 2002, the availability of coal has further improved. The coal delivered by sea will be also cheaper than that delivered by rail. Future funding for the required operation and maintenance is not expected to be a problem. Thus, the long-term sustainability of the Project is likely. Apart from the major delay, the Project has satisfactorily achieved its objectives. The additional energy generated is consumed mainly by domestic, industrial, and commercial consumers in urban areas, and by a limited number of agricultural consumers. The Project s economic internal rate of return of 14.2% and its financial internal rate of return of 8.4% both confirm its high efficiency. The actual cost, being lower than the appraisal estimates, and excellent plant performance have more than compensated for the delay. Further, the substantive issues relating to the environment and resettlement have been addressed satisfactorily. There still remains the procedural issue of obtaining environmental compliance from the Tamil Nadu Pollution Control Board. Overall, the Project is rated successful. The key indicator of the financial performance of TNEB is the 3% surplus required under Section 59 of the Electricity Act. The Loan Agreement stipulated that TNEB would maintain tariffs at a level to achieve the 3% surplus. However, given GTN s decision to give power freely to agricultural consumers, this was not possible and hence subventions were needed from GTN to achieve the stipulated surplus. These subventions have become a significant burden on GTN s budgetary resources. As regards future power projects, the key issue, which is of national relevance, is the financial viability of the state electricity boards. Two major factors contributing to the poor state of the state electricity boards finances are the politically driven tariffs and inefficient meter reading and bill collection. The Government and the state governments have agreed to depoliticize the power sector reforms and implement them expeditiously, with particular emphasis on power distribution. This provides a unique opportunity for ADB to take a lead role in distribution sector reform in India and provide the requisite technical and financial assistance, with privatization of distribution systems a precondition for receiving loan assistance. TNEB is advised to take the following actions by December 2002: (i) (ii) resolve the issue of how and where to discharge cooling water in the sea and obtain approval from the Tamil Nadu Pollution Control Board for plant operation; and improve plant safety and ensure that workers use the safety equipment procured by TNEB, including safety helmets.

8

9

10 I. BACKGROUND A. Rationale 1. With a view to alleviating the severe power shortages experienced in India, which in turn were serious constraints to economic growth, the Government developed a long-term power development program under the Seventh Five-Year Plan (FY ). The program included several thermal power generating stations, utilizing the country's large coal reserves. 2. The Tamil Nadu Electricity Board (TNEB) in the State of Tamil Nadu was the second largest power generation system in the Southern Region, with a total installed capacity of 3,553 megawatts (MW) in TNEB s power development program in the early 1980s added two 210 MW units at each of two thermal power stations in Tuticorin and Mettur. However, even with the progressive increases in TNEB s thermal capacity, the huge annual deficit of over 4,000 gigawatt-hours (GWh) of electrical energy was a persistent problem affecting economic growth in the 1980s in Tamil Nadu. The power outages caused significant disruptions in the operations of industrial consumers who accounted for over 55% of total consumption. 3. The North Madras Thermal Power Project (the Project) 1 was an integral part of the national power development program. It aimed at not only reducing the generating capacity deficit, but also providing the much-needed base-load backup for the then largely seasonal hydropower-based system in Tamil Nadu. 4. The country operational strategy of the Asian Development Bank (ADB) for India at the time of appraisal sought to assist the Government's industrialization efforts directly by providing financial assistance for industrial projects and indirectly for removing the bottlenecks in infrastructure, particularly in the crucial power sector. The Project was prepared before the introduction of the policy to promote private sector participation in the form of independent power producers. B. Formulation 5. The Project was identified as an integral component of the national power development program formulated by the Central Electricity Authority, based on detailed capacity optimization system studies. The project location was decided on the basis of least-cost studies for coal transportation and water availability for cooling as well as for steam production. The coastal location of the Project provided for coal transportation by coastal shipping, thereby relieving the already strained rail sector from the additional burden of transporting coal for the Project from eastern coalfields. It also provided flexibility for importing coal if necessary. The technical design and detailed engineering for the Project were carried out in August 1985 by an experienced domestic consulting firm engaged by TNEB, the Executing Agency. ADB appraised the Project in September 1986 and considered the project report prepared by TNEB satisfactory. ADB also assessed that TNEB had the required technical competence, as demonstrated by the successful completion of two thermal power stations in the 1980s. 1 Loan 798-IND: North Madras Thermal Power Project, for $150 million, approved on 18 November 1986.

11 2 C. Purpose and Outputs 6. The main purpose of the Project was to expand the generating capacity of TNEB in order to meet the prevailing and anticipated power shortages in Tamil Nadu. The Project assisted in building a new coal-fired thermal power station located approximately 25 kilometers north of Madras (now Chennai), the capital of Tamil Nadu. The Project constituted Phase I of the first stage development of the power station to provide a generating capacity of 420 MW. 2 The Project comprised the following components: (i) civil works for site preparation, foundations, the power station building, and cooling water and other systems; (ii) two 690 ton/hour capacity coal-fired steam boilers and auxiliaries; (iii) two reheat steam turbine generators each with a rated capacity of 210 MW and auxiliaries; (iv) instrumentation and control systems; (v) coal and ash handling systems; (vi) water treatment and other miscellaneous mechanical equipment; (vii) transformers, switchyard equipment, and other miscellaneous electrical equipment; and (viii) consulting services. D. Cost, Financing, and Executing Arrangements 7. At appraisal, the total project cost was estimated at $628 million equivalent comprising $254 million (40% of the total cost) in foreign exchange costs and $374 million equivalent (60% of the total cost) in local currency costs (Appendix 1). 8. The Member (Generation) of TNEB was designated to be in charge of the Project. The Chief Engineer (Thermal) was responsible for coordination with the consultants, procurement, and monitoring. The Chief Engineer (Civil Designs) was responsible for procurement of civil works. Actual project implementation was supervised by the Chief Engineer (Projects) and was supported by about 200 experienced professional staff. As stated in the Loan Agreement, the Chief Engineer (Planning) was the overall coordinator with ADB. TNEB was assisted in the implementation of the Project by an experienced domestic consulting firm for project engineering, preparation of technical specifications, preparation of bid documents, bid evaluation, review of vendors' drawings, preparation of operation and maintenance manuals, and construction supervision. E. Completion and Self-Evaluation 9. The project completion report (PCR) circulated in April 2001 covered comprehensively all relevant aspects of project implementation. The PCR was well documented, balanced, and objective. The evaluation of the key aspects of the Projectcosts, schedule, procurement of goods and services, environmental and social impacts, disbursements, conditions and covenants, performances of the Borrower, TNEB, and ADB, and the initial benefitswas 2 The power station was planned to be developed in three stages, comprising three units of 210 MW in the first stage, two units of 525 MW in the second stage, and one unit of 525 MW in the final stage, to bring the ultimate capacity to 2,205 MW. The third 210 MW unit was financed under Loan 1029-IND: Second North Madras Thermal Power Project, for $200 million, approved on 30 August 1990.

12 3 supported by adequate documentation and analysis. 3 The PCR reported that considerable savings in foreign exchange had resulted from the major depreciation of the rupee during implementation, with lower bid prices (in dollar terms) offered by domestic contractors who won many international competitive bidding contracts. The net amount of the ADB loan disbursed was $110.4 million. The unused amount of $39.6 million was cancelled in phases. 4 The PCR recorded the startup problems such as the lack of a proper project inception report, delayed land acquisition due to litigation, and other procurement and implementation problems, all of which contributed to the long delay in project completion. The overall conclusion of the PCR was that the Project was implemented substantially as conceived during appraisal, albeit with considerable delays. 10. The PCR also concluded that the issues relating to environment and safety were not adequately addressed. TNEB implemented measures to mitigate the adverse effects of the Project on the environment. However, at the time of the project completion review mission, although the power plant was operating, the Tamil Nadu Pollution Control Board (TNPCB) had not given its formal consent to do so, as there was still a disagreement on the location of the discharge point for the cooling water. Moreover, TNEB had not implemented the safety measures for power station workers (such as requiring them to use safety belts, boots, and helmets) and environmental protection measures concerning the residents in the areas near the ash pond. 11. The PCR was also correct to note that the high turnover of key personnel detracted from a sense of ownership of the Project. Based on the low financial internal rate of return (FIRR), of 4.0% the PCR concluded that the Project was partly successful. 5 F. Operations Evaluation 12. The main focus of the project performance audit report (PPAR) is to assess the relevance, efficacy, efficiency, sustainability, and institutional and developmental impacts of the Project and identify lessons and follow-up actions, as well as suggestions for sector policies and strategies for future ADB operations. 13. The PPAR presents the findings of the Operations Evaluation Mission (OEM) that visited India in March The PPAR is based on findings of the OEM and the analysis of data collected during field visits. It also incorporates information from discussions with the officials and experts connected with the Project, and comments received at the workshops at ADB's India Resident Mission and headquarters. Copies of the draft PPAR were provided to the Government, TNEB, and concerned ADB staff for review; comments were considered in finalizing the PPAR. 3 TNEB revised the actual costs subsequently. Those are used in the Operations Evaluation Mission s analysis (Table 2 and para. 18). 4 In June 1992, ADB and the Government initially agreed to use the loan savings under the loan to partly finance the external coal handling system that was included in the follow-on project (footnote 2). Subsequently, in 1996, to rationalize ADB s loan portfolio in India, ADB decided to cancel the loan savings. 5 Under the then prevailing three-category system: generally successful, partly successful, and unsuccessful.

13 4 II. PLANNING AND IMPLEMENTATION PERFORMANCE A. Formulation and Design 14. The Government s Seventh Five-Year Plan (FY ) placed strong emphasis on modernization and improvement of the industrial sector and accelerated growth of industry and infrastructure. The endemic power shortages all over the country constituted a serious bottleneck constraining industrial development. 6 Accordingly, power generation projects aimed at closing the gap between the demand and supply of power were accorded a very high priority. Given the country's large coal resources and the shorter gestation period of thermal power projects, it was logical to concentrate on coal-based generation. By locating the Project in Tamil Nadu, the requisite hydrothermal power balance was provided in the state system, with a view to optimizing the utilization of the available generating capacity. The Project was consistent with ADB's strategic development objectives of assisting the Government's industrialization efforts and helping remove the bottlenecks in the infrastructure, particularly in the crucial power and transportation sectors. 15. The Project was formulated without an ADB project preparatory technical assistance, despite being an early loan to India. The OEM concurs with the PCR s assessment that the plant design and engineering prepared by the domestic consultants were technically sound and appropriate in the context of the urgent need for the additional generating capacity envisaged under the Project to meet the power shortages and the anticipated demand growth in Tamil Nadu. B. Achievements and Outputs 16. At appraisal, the Project was expected to add, upon commissioning in 1991, two units each of 210 MW of generating capacity and generate 2,575 GWh annually, meeting 10% of the annual energy demand in Tamil Nadu. The Project has successfully achieved both targets, though with major delays (para. 19). The energy output reached the appraisal target in FY1999 and significantly exceeded it in FY2000 and FY2001, as a result of high plant availability and load factor. The auxiliary consumption and thermal efficiency have been satisfactory for the given plant design and coal characteristics (Table 1). Table 1: Technical Parameters of Plant Performance Generation Plant Load Availability Auxiliary Thermal Fiscal (GWh) Factor (%) Factor (%) Consumption Efficiency Year Unit 1 Unit 2 Unit 1 Unit 2 Unit 1 Unit 2 (%) (%) ,138 1, ,172 1, ,284 1, ,386 1, ,566 1, ,645 1, GWh = gigawatt-hour. Source: Tamil Nadu Electricity Board. 6 At the time of appraisal, power shortages were about 21% of the total requirement (Appraisal Report, para. 24).

14 5 C. Cost and Scheduling 17. The total actual project cost at completion was $469 million equivalent, comprising $176 million (37.5% of the total cost) in foreign exchange costs and $293 million equivalent (62.5% of the total cost) in local currency costs. There was a significant underrun in the total project cost of 25% (Table 2; for details see Appendix 1). Table 2: Summary of Project Costs ($ million) Item Appraisal Estimate Actual Change (%) A. Base Cost (2.7) Turbine Generators and Auxiliaries (27.4) Steam Generators and Auxiliaries (26.6) Equipment Coal and Ash Handling Civil Works TNEB Miscellaneous, Freight, and Insurance Consulting Services (69.5) Taxes and Duties (50.3) B. Contingencies C. Interest During Construction (28.9) Total (A+B+C) (25.2) Source: Tamil Nadu Electricity Board. 18. The OEM confirms the PCR statements that significant savings resulted mainly from a major depreciation of the rupee during project implementation, and intense competition for ADBfinanced contracts, with domestic bidders generally quoting lower prices than foreign bidders. In addition, the interest during construction was significantly lower, as the unused ADB loan amount of $39.6 million was cancelled in phases. Finally, the price contingencies, which were a high $96.3 million, also contributed substantially to the cost underrun At appraisal, the commissioning of units 1 and 2 was scheduled for March and December 1991, respectively. Several factors led to significant delays: land acquisition problems; procurement delays in the award of contracts (due to excessive time taken by TNEB for bid evaluation, lengthy internal approvals of contract awards within TNEB, and additional lengthy process for approval of awards by the Central Electricity Authority and the Government 7 These contingencies were calculated on the assumption of a constant nominal exchange rate. In recent ADB projects, price contingencies are calculated on the assumption of a constant real exchange rate, and come out much lower.

15 6 of Tamil Nadu [GTN] before submission to ADB for approval); and delays in the implementation of some contracts, particularly that for the internal coal handling system (ICHS). 20. Units 1 and 2 were eventually commissioned in October 1994 and March 1995, respectively, more than 3 years behind schedule. However, their optimum utilization was not possible due to the delay in the commissioning of the ICHS, which became fully operational only in June Thus, the total delay in project implementation was about 6.5 years. The actual implementation of the various project components, compared with appraisal schedule, is in Appendix 2. D. Procurement and Construction 21. Following its internal procedures, TNEB engaged an experienced domestic consulting firm for engineering, preparation of technical specifications and bid documents, bid evaluation, and review of construction drawings and operation and maintenance manuals. The consultants performed the assigned tasks professionally and in accordance with their terms of reference. Equipment financed by ADB was procured in accordance with ADB's Guidelines for Procurement. Civil works and other contracts not financed by ADB were procured in accordance with TNEB's procedures. TNEB reported that the performance of all contractors, except that for the ICHS, had been generally satisfactory and that all the goods and equipment procured met the required specifications. E. Organization and Management 22. At the time of appraisal, ADB considered TNEB a mature utility possessing the requisite managerial, technical, and financial capability to plan and implement its investment and operation programs effectively. The only two matters for concern were (i) the tariff subsidies, particularly in the agricultural sector, and their adverse impact on the financial viability of TNEB; and (ii) the high power transmission and distribution losses, which stood at 22% at the time of appraisal. 23. The PCR presented a thorough analysis of the compliance with the 26 loan and project covenants (PCR, Appendix 9). The OEM concurs with the PCR s observations. While TNEB complied with most of the key covenants, it did not maintain tariffs at a level to achieve a surplus of at least 3%, as required under Section 59 of the Electricity Act. It could achieve the 3% surplus only through major subventions provided by GTN. 24. As required by the Project Agreement, TNEB also conducted two technical studies, one for upgrading the distribution system of Greater Metropolitan Madras and the other for defining the system and identifying the equipment required for upgrading the load dispatch center for efficient system operation and load management. Based on these studies, TNEB prepared the feasibility report for the Madras City Augmentation and Upgradation Project (MAUP) for which ADB provided $50.6 million under the follow-on project (footnote 2). 8 The ICHS contract comprised coal handling plant, and dust extraction and ventilation systems. The domestic contractor awarded this contract performed unsatisfactorily with serious delays in implementation. TNEB terminated the contract in February 1997 and completed the works in June 1999 with its own resources and with the support from ADB s subsequent project (footnote 2). In the meantime, until the ICHS s commissioning, suspended particulate matter in the air and suspended solids in the run-off water around the coal handling area exceeded the limits specified by TNPCB. The external coal handling system for transporting the coal from Ennore port to the Project s coal yard was completed under the subsequent project in January 2002.

16 7 III. ACHIEVEMENT OF PROJECT PURPOSE A. Plant Performance 25. The Project enabled TNEB to optimize the operation of its hydropower generation facilities. Until the commissioning of the ICHS in June 1999, the plant performance suffered. For example, the heat rate (in kilocalories per kilowatt-hour [Cal/kWh]) was 3,057 in 1995, 2,683 in 1997, and 2,563 in Once the ICHS was commissioned, the heat rate improved further to 2,550 Cal/kWh. Since then, the two units have been performing very well with plant load factors exceeding 80%. The TNEB staff for plant operation and maintenance have been adequately trained. With the commissioning of the external coal handling system in January 2002, the availability of coal is expected to further improve. The coal delivered by sea will be also cheaper than that delivered by rail. 26. The additional capacity provided and the energy generated by the plant have resulted in an increase in consumption by domestic and industrial consumers, mainly in the urban areas in Chennai. TNEB reported that, in FY2002, 2,566 GWh were distributed as a result of the Project. Domestic, industrial, and commercial consumers accounted for a total of 89.9% of the energy distributed, 9 agricultural consumers who received free electricity for 4.1%, and the balance of 6.0% was used for public buildings and street lights. B. Performance of the Operating Entity 27. The key indicator of the financial performance of TNEB is the 3% surplus required under Section 59 of the Electricity Act. The Loan Agreement stipulated that TNEB would maintain tariffs at a level to achieve the 3% surplus. However, given GTN's decision to give power free of charge to agricultural consumers, this was not possible, and hence subventions were needed from GTN to achieve the stipulated surplus. The OEM concurs with the PCR that such subventions have become a significant burden on GTN s budgetary resources. Although the subventions decreased in relative terms from 34% of TNEB s energy sales revenues in FY1991 to 23% in FY2001, they increased in absolute terms from $2.7 billion to $3.9 billion during the same period (and much more in local currency [Appendix 3]). The financial viability of the state electricity boards (SEBs) in India is a key issue (para. 46). C. Economic and Financial Reevaluation 28. The economic and financial reevaluation has been carried out by the OEM with the world price numeraire in FY2001 constant prices. Data for energy generated, auxiliary consumption, and fuel consumption for the period up to FY2001 are as recorded at the power plant. Total sales have been derived by deducting from the energy generated auxiliary consumption, and transmission and distribution losses. Category-wise, sales have been computed based on the percentage share of incremental sales in each year. Financial revenues for the period until 9 The breakdown was domestic, 55.4%; industrial, 19.0%; and commercial, 15.5%.

17 8 FY2001 are based on actual average realization of revenue for each category. 10 For the period thereafter, FY2001 figures have been assumed. In the economic analysis, the benefits to consumers have been estimated using the methodology from a recent operations evaluation report. 11 The details of the analysis are in Appendix 4. On this basis, the economic internal rate of return (EIRR) is 14.2%, and the FIRR is 8.4%. The PCR estimate of the FIRR was 4.0%. It was significantly lower than the appraisal estimate of 7.4%, because of the long delays in project implementation and lower revenues. In the PCR, the revenues were estimated using the actual average tariffs in FY1999, which were higher in local currency terms than the average tariffs assumed in the Appraisal Report, but significantly lower when expressed in dollar terms because of the Indian Rupee depreciation. 12 The OEM's FIRR estimate is higher than both the appraisal and PCR estimates. The two main reasons for the higher FIRR are the capital cost underrun of 25% and the higher-than-expected levels of generation. 13 These factors have more than compensated for the delays in implementation. In addition, agricultural consumers who are given electricity free of charge by GTN consumed only a small portion of the incremental energy generated by the plant. 14 If the agricultural consumers were charged at the cost of supply, which is the amount reimbursed through the subventions by GTN, the FIRR would be even better at 9.9%. 15 D. Sustainability 29. Technically, the design of the Project and the technology adopted are robust and appropriate to the available human resources and institutional capabilities. Future funding for the required operation and maintenance is not expected to be a problem. Thus, the OEM has confirmed the likely long-term sustainability of the Project, on the condition that GTN would provide subventions until agricultural consumers are charged for electricity. IV. ACHIEVEMENT OF OTHER DEVELOPMENT IMPACTS A. Socioeconomic Impact 30. The OEM confirmed the PCR statements that resettlement and rehabilitation efforts were in keeping with India s prevailing standards. The OEM also investigated the PCR s points on how these resettlement and rehabilitation measures fared with respect to ADB standards, noting that the Project was implemented before ADB adopted the Policy on Involuntary Resettlement. 16 The OEM found the measures generally satisfactory (Appendix 5 and Supplementary Appendix A). Acquisition of land for the Project affected 1,010 families in three villages and a few rural 10 GTN provides subventions to TNEB to cover the cost of supply for the electricity consumed by agricultural consumers. This has not been included in the revenues. The Appraisal Report and the PCR recorded that the subventions have not covered all the financial losses incurred by TNEB because of the distribution of free power to agricultural users. Moreover, there is no contract in written form between GTN and TNEB assuring the level of subventions. 11 PE 524: Rayalaseema Thermal Power Project (Loan 988-IND) circulated in June For example, for the domestic consumers, the PCR used Rs0.75/kWh ($0.017/kWh), while the Appraisal Report assumed Rs0.55/kWh ($0.044/kWh). 13 The actual plant load factor in 2001 was 89.4% for unit 1 and 82.3% for unit 2 while at appraisal and in the PCR, the generation level was assumed at 70.0% of the plant load factor for both units. 14 Agricultural consumers accounted for about 30% of the overall sales in Tamil Nadu in 1986 (Appraisal Report, para. 114), and about 35% in FY2001. The OEM observed that the energy generated by the plant essentially met the increasing demands of domestic and industrial consumers. 15 The OEM also reaffirmed the conclusion in the previous operations evaluation report (footnote 11) that charging the agricultural consumers would reduce the burden on GTN to provide subventions and ensure the long-term financial sustainability of TNEB. 16 IN Policy on Involuntary Resettlement: Report to the Board of Directors, 30 March.

18 9 settlements. TNEB provided employment to one person in each displaced family; these families highly appreciated such compensation. The resettled areas and amenities provided by TNEB were also of a good standard, especially when compared with the original sites that the displaced families used to occupy prior to the Project. This condition was particularly seen in one village near the power plant, Athipathu, where initially 475 displaced families were accommodated. It has attracted others and currently the population has expanded to more than twice its original size. 31. However, as the new sites have grown, the people living there have started to make demands for more job opportunities and other social services. Such services have grown beyond the originally envisaged responsibility of the power plant under the resettlement plan. TNEB has recruited a sociologist and an environmental engineer as permanent staff to deal with these issues. The sociologist has planned routine programs on related social matters, such as education, public health, and income generating programs. The OEM suggested working closely with the community, social workers, and concerned nongovernment organizations in designing and implementing these programs to ensure ownership, continuous support, and sustainability. The OEM also suggested that the power plant open its facilities such as clinic and school to the displaced families to create a good relationship and mutual respect, and erase unnecessary suspicions between the people and the power plant. This approach has proven successful in a neighboring power plant, and the OEM recommended that the lessons learned from this success could be adopted. GTN and TNEB welcomed these suggestions and intend to incorporate them in their social programs. B. Environmental Impact 32. The OEM conducted detailed studies to review the environmental impact of the power plant. The OEM observed that the plant is meeting environmental standards for emissions and ash disposal (Appendix 6 and Supplementary Appendix B). The temperature rise in the cooling water is also within the prescribed limits. Nonetheless, TNPCB has not yet given its approval for plant operation because TNEB is discharging the cooling water into Buckingham canal instead of Ennore creek as was originally licensed. TNEB had in fact already constructed the requisite facilities for the discharge of the cooling water into Ennore creek. However, it is discharging the water into Buckingham canal in view of the opposition of the local fisherfolk who are concerned about the impact of the hot water being discharged into the Ennore creek on the fish there. In the OEM s view, the current practice does not constitute an environmental hazard as relatively cleaner, filtered seawater is discharged into a canal, which receives effluents and solid waste from urban areas in Chennai. TNEB is resolving this matter in consultation with TNPCB. The OEM was informed that TNEB is now preparing an $8 million project for intake and discharge of cooling water near Ennore port. C. Impact on Institutions and Policy 33. The Project did not have any significant impact on TNEB as an institution nor on GTN's power sector policies, as none was specifically envisaged during appraisal. The institutional impact of the Project was also limited, due to rapid turnover of project personnel. 34. MAUP was successfully completed with ADB assistance under the follow-on project (para. 24). MAUP has led to significant benefits such as more effective load management, improved and balanced loading of the distribution system, reduced fault location time, reduced restoration of supply time, reduced time of changeover of supply in the 33 kv network, and

19 10 lower distribution system losses. 17 The reliability of supply has also resulted in an increased number of industrial users, and has contributed to overall industrial development in Tamil Nadu. A. Relevance V. OVERALL ASSESSMENT 35. At appraisal, the Project was consistent with the Government's priorities for industrial and infrastructure development, and was in line with the strategic objectives of ADB's country operational strategy. The Project continues to be consistent with the country's priority both for economic development, for which adequate power supply is a key input, and for infrastructure. Accordingly, the Project is rated highly relevant. B. Efficacy 36. The Project successfully installed an additional 420 MW of power generating capacity utilizing domestic coal, although the coal handling systems became fully operational only under the follow-on project (footnote 2). The Project is, therefore, rated efficacious. C. Efficiency 37. Apart from providing additional generating capacity, the Project enabled TNEB to operate its largely hydro-based system optimally by providing the requisite thermal backup. The EIRR is 14.2% and the FIRR is 8.4%. The Project is rated efficient, considering the long delay in implementation. D. Sustainability 38. The technology adopted for the Project is well proven and TNEB has adequate skills and organization to operate the power plant and the associated infrastructure efficiently over its economic life. Future funding for required operation and maintenance is not expected to be a problem. Accordingly, the sustainability of the Project is rated likely. However, the rating is contingent on GTN providing the subventions until the reforms in the electricity sector in Tamil Nadu allow TNEB to charge agricultural consumers for electricity. E. Institutional Development and Other Impacts 39. At the time of appraisal, no specific targets for institutional development or other impacts were envisaged. MAUP, as formulated under the Project, achieved significant impacts in terms of capacity building, although it was implemented under the follow-on project. Overall, the Project's institutional development and other impacts are rated moderate. F. Overall Project Rating 40. The Project has satisfactorily achieved its objectives, though the delay in its implementation was significant. The FIRR is higher than envisaged during appraisal and 17 TNEB s transmission and distribution losses have been reduced from 22% at the time of appraisal to 16% in FY2002, well below the national average of 26% (Source: Annual Report , Ministry of Power, Government of India).

20 11 calculated in the PCR. The issues relating to the environment have been addressed adequately. Overall, the Project is rated successful. 18 G. Assessment of ADB and Borrower Performance 41. ADB's performance was highly satisfactory. During implementation, ADB closely monitored progress, regularly fielded review missions, and provided valuable assistance in resolving conflicts with some of the contractors. ADB also followed up on outstanding issues during the implementation of the ICHS. 42. Both the Borrower and TNEB performed satisfactorily. TNEB in general proved to be a technically competent organization. However, its internal procedures for bid evaluation and contract awards led to considerable front-end delays, which could have been avoided through rationalization of the relevant systems and procedures. Also, for historical reasons, the turnover of project personnel was high and resulted in poor ownership. TNEB also needs to improve plant safety to meet international standards. H. Power Sector Policies 43. The Project did not have any policy component. Several encouraging steps have been taken recently by the Government and the state governments to reform and restructure the power sector. In particular, the distribution subsector has now been targeted for improvement. During a conference of the Chief Ministers held on 3 March 2001, many state governments, including GTN, agreed that: (i) (ii) (iii) (iv) there is an urgent need to depoliticize power sector and tariff reforms and speed up their implementation; distribution reforms need to be carried out by making energy audits effective, developing effective management information systems, and eliminating energy theft; commercial viability in distribution is to be achieved in 2 3 years by creating profit centers, privatizing, and/or handing over local distribution to Panchayats (local bodies)/franchisees or user associations; and the state electricity regulatory commissions (SERCs) are to be made functional and tariff orders are to be issued; subsidies are to be given only to the extent of the Government's capacity to pay them explicitly through budget provisions. 44. As regards regulation, the Central Electricity Regulatory Commission, formed under the provisions of Electricity Regulatory Commissions Act 1988, was made fully functional in As of FY2001, 18 states, including Tamil Nadu, have either constituted or initiated action for constitution of SERCs. Under its accelerated power development program announced in 2001, the Government is also giving financial assistance, channeled through the Power Finance Corporation (PFC), to the states for system improvement if they are implementing reforms in their distribution systems. While the above steps are in the right direction, more needs to be done, and done quickly. One option is to divide the distribution systems in the SEBs into small manageable segments and to privatize them. The process could start with privatizing billing and 18 Under the current four-category rating system (highly successful, successful, partly successful, and unsuccessful).

21 12 collection so that there is an immediate increase in the revenues of the cash-poor SEBs. Overall, these developments provide a unique opportunity for ADB to take a lead role and assist India's power sector with technical assistance and loans in restructuring and privatizing the distribution subsector. 45. As regards the coal sector, no significant reforms have been implemented nor contemplated. As highlighted in previous ADB evaluation reports in the power sector in India, there are great concerns regarding the poor quality of the coal being mined. The Government has recognized these concerns by accepting that in future, imports of coal for coastal thermal power stations and of oil or natural gas for inland stations will be unavoidable. VI. ISSUES, LESSONS, AND FOLLOW-UP ACTIONS A. Key Issues for the Future 46. Financial Viability of SEBs. The financial viability of SEBs is of national relevance. Two major factors contributing to the poor state of SEBs' finances are the politically driven tariffs and inefficient meter reading and bill collection. As regards the tariffs, competent and impartial SERCs are essential to provide the required barrier against political intervention in tariff setting. Further, SERCs will also make the tariff setting process transparent and provide a forum for the SEBs and other suppliers, and their consumers to examine and discuss the appropriateness of the proposed tariff revisions. Such a process will therefore make the tariffs more acceptable to consumers. The problem of inefficient meter reading and bill collection can be resolved by privatizing this area of the utility operations with suitable incentives for private contractors. Such privatization will likely face limited opposition since the personnel affected are relatively small in number and since most of the redundant staff are likely to find alternate employment with the private contractors. Further, such privatization should be an integral part of the program of breaking up the distribution system into manageable segments and privatizing them. The creation of such profit-oriented distribution companies would have a critical impact on tariff rationalization, as these companies would provide a strong countervailing lobby against the farmers' lobby, which is strongly opposed to rationalization of the agricultural tariff. B. Lessons Identified 47. Land Acquisition. The Project suffered severe delays caused by difficulties in land acquisition. This problem could have been overcome by contracting out land acquisition and making it a precondition for ADB approval of the loan or for loan effectiveness. Experience in Indonesia and the Philippines demonstrates that the private sector is also effective in acquiring land expeditiously. 48. Turnkey Contract. A single turnkey contract would have avoided the considerable delays experienced in the implementation of the Project resulting from inordinate delays in the award of several contracts and coordination between them. In future projects, it is essential to discuss and agree with the Borrower and the executing agencies, prior to ADB Board approval, the systems, procedures, and timeframes for bidding and contracting processes for such turnkey contracts. Such an approach would have an additional advantage of allowing for intense scrutiny by all the concerned parties and ensuring strict compliance with ADB's Guidelines for Procurement, particularly in view of the large value of the contract.

22 13 C. Follow-Up Actions 49. The OEM recommends these follow-up actions: Action Responsibility Deadline 1. Expeditiously resolve the location of cooling water discharge in the sea. TNEB and TNPCB December Monitor environmental compliance of plant operation until the requisite certificates are issued by TNPCB. ADB s India Resident Mission July-December Improve plant safety by ensuring that the tools and equipment, including safety helmets already procured, are fully utilized. 4. Associate with community bodies and nongovernment organizations to enhance and augment efforts in the resettlement and rehabilitation of families affected. TNEB December 2002 TNEB December Give high priority for environmental concerns, due to the use of low-quality (high ash-content, and low calorific value) domestic coal in the thermal power plants in India. 6. Take a lead role in the restructuring of India s power distribution subsector and provide technical and financial assistance by adopting a sector lending approach Make a detailed review of the PCR for Loan 1029-IND: Second North Madras Thermal Power Project. ADB s South Asia Department, Infrastructure Division ADB s South Asia Department, Infrastructure Division ADB s Operations Evaluation Department 2004 Country Strategy Programming Mission 2004 Country Strategy Programming Mission December For actions 1, 3, and 4, ADB s India Resident Mission is requested to monitor implementation. 19 Such assistance can be channeled through PFC with the privatization of the distribution systems as a precondition for financial and technical assistance. To qualify for ADB assistance, states would need to privatize distribution only in such areas where it is advantageous and practical.

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR: 18181-IND PROJECT COMPLETION REPORT ON THE NORTH MADRAS THERMAL POWER PROJECT (Loan No. 798-IND) IN INDIA March 2001 CURRENCY EQUIVALENTS Currency - Indian Rupee/s (Re/Rs) At

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR:IND 20027 PROJECT COMPLETION REPORT ON THE UNCHAHAR THERMAL POWER PROJECT (Loan 907-IND) IN INDIA September 2002 CURRENCY EQUIVALENTS Currency Unit rupee/s (Re/Rs) At Appraisal

More information

India Kothagudem A Thermal Power Station Rehabilitation Project. Field Survey: July Project Profile and Japan s ODA Loan

India Kothagudem A Thermal Power Station Rehabilitation Project. Field Survey: July Project Profile and Japan s ODA Loan India Kothagudem A Thermal Power Station Rehabilitation Project Field Survey: July 2003 1. Project Profile and Japan s ODA Loan China New Delhi Nepal Bhutan Bangladesh India Calcutta Myanmar Hyderabad

More information

ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS

ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS A. Background SASEC Bangladesh India Electrical Grid Interconnection Project Additional Financing (BAN RRP 44192-14) ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS 1. The Bangladesh India Electrical

More information

Mongolia: Ulaanbaatar Heat Efficiency Project

Mongolia: Ulaanbaatar Heat Efficiency Project Validation Report Reference Number: PVR 212 Project Number: 29629 Loan Number: 1548 December 2012 Mongolia: Ulaanbaatar Heat Efficiency Project Independent Evaluation Department ABBREVIATIONS ADB Asian

More information

Philippines: Electricity Market and Transmission Development Project

Philippines: Electricity Market and Transmission Development Project Validation Report Reference Number: PVR-310 Project Number: 36018 Loan Number: 1984 June 2014 Philippines: Electricity Market and Transmission Development Project Independent Evaluation Department ABBREVIATIONS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: PAK 32381 TECHNICAL ASSISTANCE TO THE ISLAMIC REPUBLIC OF PAKISTAN FOR CAPACITY BUILDING OF THE NATIONAL ELECTRIC POWER REGULATORY AUTHORITY March 2000 CURRENCY EQUIVALENTS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 32241 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO THE KINGDOM OF NEPAL FOR MANAGEMENT REFORMS AND EFFICIENCY IMPROVEMENTS FOR THE NEPAL ELECTRICITY AUTHORITY

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Power Sector Rehabilitation Project (RRP KGZ 44198) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems, and Opportunity a. Introduction 1. The Kyrgyz Republic is a landlocked

More information

Completion Report. People s Republic of China: Hebei Zhanghewan Pumped Storage Project. Project Number: Loan Number: 1922 August 2014

Completion Report. People s Republic of China: Hebei Zhanghewan Pumped Storage Project. Project Number: Loan Number: 1922 August 2014 Completion Report Project Number: 28212 Loan Number: 1922 August 2014 People s Republic of China: Hebei Zhanghewan Pumped Storage Project This document is being disclosed to the public in accordance with

More information

AZERBAIJAN ECONOMY AND POWER SECTOR: CHALLENGES AND OPPORTUNITIES

AZERBAIJAN ECONOMY AND POWER SECTOR: CHALLENGES AND OPPORTUNITIES AZERBAIJAN ECONOMY AND POWER SECTOR: CHALLENGES AND OPPORTUNITIES 1. Analysis 1. Economy. The economy grew, on average, by 29.3% from 2005-2007 and in 2008, the gross domestic product (GDP) increased by

More information

Energy Conservation Project (Loan 1492-MON[SF]) in Mongolia

Energy Conservation Project (Loan 1492-MON[SF]) in Mongolia Performance Evaluation Report PPE: MON 29012 Energy Conservation Project (Loan 1492-MON[SF]) in Mongolia November 2005 Operations Evaluation Department Asian Development Bank CURRENCY EQUIVALENTS Currency

More information

SECTOR ASSESSMENT: BIHAR POWER SECTOR

SECTOR ASSESSMENT: BIHAR POWER SECTOR P P Central Bihar Power System Improvement Project (RRP IND 41626) SECTOR ASSESSMENT: BIHAR POWER SECTOR A. Introduction 1 1. The power sector in India has an installed capacity of 159,400 megawatt (MW),PF

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY SECTOR ASSESSMENT (SUMMARY): ENERGY Country Partnership Strategy: Nepal, 2013-2017 A. Overview 1. Nepal has long recognized the development of its large hydropower potential as an important cornerstone

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PHI 30546 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE REPUBLIC OF THE PHILIPPINES FOR INSTITUTIONAL STRENGTHENING FOR THE DEVELOPMENT OF THE NATURAL GAS

More information

ASIAN DEVELOPMENT BANK Operations Evaluation Department

ASIAN DEVELOPMENT BANK Operations Evaluation Department ASIAN DEVELOPMENT BANK Operations Evaluation Department PROJECT PERFORMANCE AUDIT REPORT ON THE NAM LEUK HYDROPOWER PROJECT IN LAO PEOPLE'S DEMOCRATIC REPUBLIC In this electronic file, the report is followed

More information

People s Republic of China: Fujian Pacific Electric Company Limited

People s Republic of China: Fujian Pacific Electric Company Limited Performance Evaluation Report Project Number: PPE: PRC 29712 Equity Investment Number: 7144 Loan Number: 1610-PRC June 2006 People s Republic of China: Fujian Pacific Electric Company Limited Operations

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY (ELECTRICITY TRANSMISSION AND DISTRIBUTION)

SECTOR ASSESSMENT (SUMMARY): ENERGY (ELECTRICITY TRANSMISSION AND DISTRIBUTION) Southwest Transmission Grid Expansion Project (RRP BAN 51137) SECTOR ASSESSMENT (SUMMARY): ENERGY (ELECTRICITY TRANSMISSION AND DISTRIBUTION) Sector Road Map 1. Sector Performance, Problems, and Opportunities

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR)

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR) Installed capacity (GW) Solar Rooftop Investment Program (RRP IND 49419) Sector Road Map SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR) 1. Sector Performance, Problems, and Opportunities

More information

ECONOMIC ANALYSIS. A. Introduction and Economic Rationale

ECONOMIC ANALYSIS. A. Introduction and Economic Rationale Demand-Side Energy Efficiency Sector Project (RRP IND 48224) A. Introduction and Economic Rationale ECONOMIC ANALYSIS 1. Energy Efficiency Services Limited (EESL) was created by the Ministry of Power within

More information

ASIAN DEVELOPMENT BANK NEP 31401

ASIAN DEVELOPMENT BANK NEP 31401 ASIAN DEVELOPMENT BANK NEP 31401 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR CAPACITY BUILDING FOR THE ACCOUNTING AND AUDITING PROFESSION December 1999 CURRENCY EQUIVALENTS (as of 23 November 1999)

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Madhya Pradesh Transmission System Modernisation Project Loan Agreement: June 16, 2011 Loan Amount:

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) 1. Basic Information Ex-Ante Evaluation (for Japanese ODA Loan) South Asia Division 1, South Asia Department, JICA Country: India Project Name: Project for the Construction of Turga Pumped Storage (I)

More information

ECONOMIC ANALYSIS. B. Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis

ECONOMIC ANALYSIS. B. Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis A. Background and Approach ECONOMIC ANALYSIS Tanahu Hydropower Project (RRP NEP 43281) 1. Energy consumption in Nepal has been dominated by traditional sources. Only 56% of households have access to electricity

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK PCR:IND 18182 PROJECT COMPLETION REPORT ON THE COAL PORTS PROJECT (Loan 1181-IND) IN INDIA September 2003 CURRENCY EQUIVALENTS Currency Unit Indian rupee/s (Re/Rs) At Appraisal 30

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People's Republic of Bangladesh Project: Dhaka Urban Transport Development Project (I) Loan Agreement: February

More information

People s Republic of China: Inner Mongolia Autonomous Region Environment Improvement Project

People s Republic of China: Inner Mongolia Autonomous Region Environment Improvement Project Completion Report Project Number: 39019-013 Loan Number: 2260 September 2017 People s Republic of China: Inner Mongolia Autonomous Region Environment Improvement Project This document is being disclosed

More information

ASIAN DEVELOPMENT BANK PPA: INO 22048

ASIAN DEVELOPMENT BANK PPA: INO 22048 ASIAN DEVELOPMENT BANK PPA: INO 22048 PROJECT PERFORMANCE AUDIT REPORT ON THE SECOND IKK WATER SUPPLY SECTOR PROJECT (Loan 1069-INO) IN INDONESIA November 2001 At Appraisal (September 1990) CURRENCY EQUIVALENTS

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) 1. Basic Information Ex-Ante Evaluation (for Japanese ODA Loan) South Asia Division 1, South Asia Department, JICA Country: India Project Name: Project for Renovation and Modernization of Umiam-Umtru Stage-III

More information

Document of The World Bank FOR OFFICIAL USE ONLY

Document of The World Bank FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Private Sector Development and Infrastructure Country Department II Middle East and North

More information

Japanese ODA Loan. Ex-Ante Evaluation

Japanese ODA Loan. Ex-Ante Evaluation Japanese ODA Loan Ex-Ante Evaluation 1. Name of the Project Country: People s Republic of Bangladesh Project: Dhaka-Chittagong Main Power Grid Strengthening Project Loan Agreement: December 13, 2015 Loan

More information

Pakistan Bin Qasim Thermal Power Station Unit 6 Project. Report date: March 2001 Field survey: August Project Profile and Japan s ODA Loan

Pakistan Bin Qasim Thermal Power Station Unit 6 Project. Report date: March 2001 Field survey: August Project Profile and Japan s ODA Loan Pakistan Bin Qasim Thermal Power Station Unit 6 Project Report date: March 2001 Field survey: August 2000 1. Project Profile and Japan s ODA Loan Project site Project Site: 50-km east of the city of Site

More information

Evaluation Approach Project Performance Evaluation Report for Tianjin Wastewater Treatment and Water Resources Protection Project March 2010

Evaluation Approach Project Performance Evaluation Report for Tianjin Wastewater Treatment and Water Resources Protection Project March 2010 Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 5467; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Project Performance

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Ex-Ante Evaluation (for Japanese ODA Loan) Southeast Asia Division 1, Southeast Asia and Pacific Department, JICA 1. Basic Information Country: The Republic of Indonesia Project: Construction of Jakarta

More information

PROGRAM PREPARATORY TECHNICAL ASSISTANCE. 1. The program preparatory technical assistance (TA) is required to:

PROGRAM PREPARATORY TECHNICAL ASSISTANCE. 1. The program preparatory technical assistance (TA) is required to: Appendix 3 11 A. Justification PROGRAM PREPARATORY TECHNICAL ASSISTANCE 1. The program preparatory technical assistance (TA) is required to: (i) Undertake sector preparatory work, define the scope of the

More information

SECTOR ASSESSMENT (SUMMARY): POWER

SECTOR ASSESSMENT (SUMMARY): POWER Power System Expansion and Efficiency Improvement Investment Program (RRP BAN 42378) A. Power Generation SECTOR ASSESSMENT (SUMMARY): POWER 1. The energy sector in Bangladesh is characterized by an acute

More information

ASIAN DEVELOPMENT BANK PPA: PHI 24212

ASIAN DEVELOPMENT BANK PPA: PHI 24212 ASIAN DEVELOPMENT BANK PPA: PHI 24212 PROJECT PERFORMANCE AUDIT REPORT ON THE SIXTEENTH POWER (MASINLOC THERMAL POWER) PROJECT (Loan 1042-PHI) IN THE PHILIPPINES October 2002 At Appraisal (as of October

More information

(Financed by the Japan Fund for Poverty Reduction)

(Financed by the Japan Fund for Poverty Reduction) Technical Assistance Report Project Number: 45124 Regional Capacity Development Technical Assistance (R-CDTA) December 2011 Smart Grid Capacity Development (Financed by the Japan Fund for Poverty Reduction)

More information

1. Name of the Project

1. Name of the Project Japan ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: India Project: Mumbai Metro Line III Project Loan Agreement: September 17, 2013 Loan Amount: 71,000 million yen

More information

Japanese ODA Loan. Ex-Ante evaluation

Japanese ODA Loan. Ex-Ante evaluation Japanese ODA Loan Ex-Ante evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Matarbari Ultra Super Critical Coal-Fired Power Project (I) Loan Agreement: June 16, 2014 Loan

More information

Uzbekistan: Land Improvement Project

Uzbekistan: Land Improvement Project Validation Report August 2017 Uzbekistan: Land Improvement Project Reference Number: PVR-504 Project Number: 37536 Loan/Grant Numbers: 2245, 2246, and 0080 ABBREVIATIONS ADB Asian Development Bank DMF

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sector Project ID Borrower Implementing Agency Report No. PID6033

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 9 PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification 1. A project preparatory technical assistance (PPTA) is required to prepare all documents for the sector project framework and core

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Country Partnership Strategy: Azerbaijan, 2014 2018 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map A. Sector Performance, Problems, and Opportunities 1. Azerbaijan is rich in energy resources. The

More information

ASIAN DEVELOPMENT BANK PPA: NEP 18030

ASIAN DEVELOPMENT BANK PPA: NEP 18030 ASIAN DEVELOPMENT BANK PPA: NEP 18030 PROJECT PERFORMANCE AUDIT REPORT ON THE FIFTH AND SIXTH POWER PROJECTS (Loans 670 and 708-NEP[SF]) IN NEPAL December 1999 CURRENCY EQUIVALENTS Currency Unit Nepalese

More information

People s Republic of Bangladesh: Enhancing the Institutional Capacity of the Implementation Monitoring and Evaluation Division, Ministry of Planning

People s Republic of Bangladesh: Enhancing the Institutional Capacity of the Implementation Monitoring and Evaluation Division, Ministry of Planning Technical Assistance Report Project Number: 48139-001 Capacity Development Technical Assistance (CDTA) December 2014 People s Republic of Bangladesh: Enhancing the Institutional Capacity of the Implementation

More information

Telecommunication Expansion Project (II)

Telecommunication Expansion Project (II) Ghana Telecommunication Expansion Project (II) Report Date: October, 2002 Field Survey: July, 2001 1. Project Profile and Japan s ODA Loan Project Site Switchboard System (Accra Station) 1.1 Background

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT AND INFORMATION AND COMMUNICATION TECHNOLOGY. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): TRANSPORT AND INFORMATION AND COMMUNICATION TECHNOLOGY. 1. Sector Performance, Problems, and Opportunities Country Partnership Strategy: IND, 2013 2017 SECTOR ASSESSMENT (SUMMARY): TRANSPORT AND INFORMATION AND COMMUNICATION TECHNOLOGY Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Significant

More information

Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed by the Japan Fund for Poverty Reduction)

Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed by the Japan Fund for Poverty Reduction) Technical Assistance Report Project Number: 46343 Project Preparatory Technical Assistance (PPTA) April 2014 Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed

More information

India Raichur Thermal Power Station Expansion Project. Report date: March 2001 Field survey: August Project Profile and Japan s ODA Loan

India Raichur Thermal Power Station Expansion Project. Report date: March 2001 Field survey: August Project Profile and Japan s ODA Loan India Raichur Thermal Power Station Expansion Project Report date: March 2001 Field survey: August 2000 1. Project Profile and Japan s ODA Loan Project site Site Map: Raichur, Karnataka State Raichur Thermal

More information

ASIAN DEVELOPMENT BANK PPA: PRC 21064

ASIAN DEVELOPMENT BANK PPA: PRC 21064 ASIAN DEVELOPMENT BANK PPA: PRC 21064 PROJECT PERFORMANCE AUDIT REPORT ON LAIWU IRON AND STEEL COMPANY MODERNIZATION AND EXPANSION PROJECT (Loan 1162-PRC) IN PEOPLE S REPUBLIC OF CHINA January 2003 At

More information

SUMMARY SECTOR ASSESSMENT: ENERGY 1

SUMMARY SECTOR ASSESSMENT: ENERGY 1 Access to Clean Energy Investment Program (RRP PAK 49056) SUMMARY SECTOR ASSESSMENT: ENERGY 1 A. Sector Performance, Problems, and Opportunities 1. A reliable and sustainable energy sector is essential

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (RAIL TRANSPORT [NONURBAN])

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (RAIL TRANSPORT [NONURBAN]) Railway Rolling Stock Project (RRP BAN 49094) SECTOR ASSESSMENT (SUMMARY): TRANSPORT (RAIL TRANSPORT [NONURBAN]) Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Bangladesh s transport

More information

The Philippine Energy Efficiency Project Lighting Up the Philippines in an Efficient Way

The Philippine Energy Efficiency Project Lighting Up the Philippines in an Efficient Way The Philippine Energy Efficiency Project Lighting Up the Philippines in an Efficient Way A technician from the Department of Energy tests a compact fluorescent lamp. ADB photo library Amid a looming energy

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Ex-Ante Evaluation (for Japanese ODA Loan) Country: India Project: Dedicated Freight Corridor Project (Procurement of Electric Locomotives) Loan Agreement: September 15, 2017 Loan

More information

Request for Proposal for Annual Financial Audit Services

Request for Proposal for Annual Financial Audit Services Request for Proposal for Annual Financial Audit Services RFP # 19_001 Jan 10, 2019 Page 1 I. RFP Timeline The following Timeline has been defined to efficiently solicit multiple competitive proposals,

More information

Republic of Indonesia FY 2015 Ex-Post Evaluation of Japanese ODA Loan Project Tarahan Coal Fired Steam Power Plant Project External Evaluator: Masumi

Republic of Indonesia FY 2015 Ex-Post Evaluation of Japanese ODA Loan Project Tarahan Coal Fired Steam Power Plant Project External Evaluator: Masumi Republic of Indonesia FY 2015 Ex-Post Evaluation of Japanese ODA Loan Project Tarahan Coal Fired Steam Power Plant Project External Evaluator: Masumi Shimamura, Mitsubishi UFJ Research and Consulting Co.,

More information

ASIAN DEVELOPMENT BANK PPA: THA 26347

ASIAN DEVELOPMENT BANK PPA: THA 26347 ASIAN DEVELOPMENT BANK PPA: THA 26347 PROJECT PERFORMANCE AUDIT REPORT ON THE SECOND ERAWAN GAS TRANSMISSION PROJECT (Loan 1276-THA) IN THAILAND June 2001 At Appraisal (31 Oct 1993) CURRENCY EQUIVALENTS

More information

Water Supply and Sewerage

Water Supply and Sewerage Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Report No. PID3147 Project Name Poland-Bydgoszcz Water & Wastewater (@ +) Region Sector

More information

ADB and Renewable Energy

ADB and Renewable Energy ADB and Renewable Energy A Presentation at the Workshop on Participated in a workshop organized by GIZ on Solar Energy in the Philippines Solar Energy in the Philippines - Opportunities for German Companies

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction ECONOMIC ANALYSIS Wind Power Generation Project (RRP SRI 49345) A. Introduction 1. The economic analysis of the Ceylon Electricity Board (CEB) Wind Power Generation Project in Mannar Island, Sri Lanka,

More information

Implementation Status & Results Vietnam Customs Modernization Project (P085071)

Implementation Status & Results Vietnam Customs Modernization Project (P085071) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Vietnam Customs Modernization Project (P085071) Operation Name: Customs Modernization Project (P085071)

More information

Mid-Term Review Report of Japanese ODA Loan Project for FY2012

Mid-Term Review Report of Japanese ODA Loan Project for FY2012 Mid-Term Review Report of Japanese ODA Loan Project for FY2012 External Evaluator: Hiroshi Oita (OPMAC Corporation) Field Study: October, 2012 Project Name: Indonesia PLN Operation Improvement System Project

More information

PROJECT TECHNICAL DESCRIPTION

PROJECT TECHNICAL DESCRIPTION Green Energy Corridor and Grid Strengthening Project (RRP IND 44426) PROJECT TECHNICAL DESCRIPTION A. Introduction 1. Power Grid Corporation of India Limited (POWERGRID) is India s national power transmission

More information

Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector

Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector Dr. Pradeep Perera Head Energy ( India) Principal Energy Specialist Asian Development Bank Generation

More information

Resume of GAJENDRA HALDEA

Resume of GAJENDRA HALDEA Resume of GAJENDRA HALDEA Gajendra Haldea graduated in Economics and Law at the University of Rajasthan and joined the Indian Administrative Service in 1973. He later went for a Fellowship at the London

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Country Partnership Strategy: Armenia, 2014 2018 SECTOR ASSESSMENT (SUMMARY): ENERGY A. Sector Performance, Problems, and Opportunities 1. Sector performance. Armenia has no proven reserves of oil or natural

More information

Malaysia Ex-Post Evaluation of Japanese ODA Loan Project Port Dickson Power Station Rehabilitation Project (2)

Malaysia Ex-Post Evaluation of Japanese ODA Loan Project Port Dickson Power Station Rehabilitation Project (2) Malaysia Ex-Post Evaluation of Japanese ODA Loan Project Port Dickson Power Station Rehabilitation Project (2) External Evaluator: Mitsue Mishima, OPMAC Corporation 0. Summary The Project aimed at stable

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People s Republic of Bangladesh Project: The Kanchpur, Meghna and Gumti 2nd Bridges Construction and Existing Bridges Rehabilitation

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Namangan 500-Kilovolt Power Transmission Project (RRP UZB 46007-002) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Uzbekistan is a Central Asian

More information

Democratic Socialist Republic of Sri Lanka: Supporting Capacity Development for Wastewater Management Services in Colombo

Democratic Socialist Republic of Sri Lanka: Supporting Capacity Development for Wastewater Management Services in Colombo Technical Assistance Report Project Number: 36173-03 Capacity Development Technical Assistance (CDTA) July 2009 Democratic Socialist Republic of Sri Lanka: Supporting Capacity Development for Wastewater

More information

People s Republic of Bangladesh: Supporting Education and Skills Development Investment Programs

People s Republic of Bangladesh: Supporting Education and Skills Development Investment Programs Technical Assistance Report Project Number: 46456 Capacity Development Technical Assistance (CDTA) December 2013 People s Republic of Bangladesh: Supporting Education and Skills Development Investment

More information

People s Republic of China: Capacity Building to Combat Land Degradation Project

People s Republic of China: Capacity Building to Combat Land Degradation Project Validation Report Reference Number: PCV: PRC 2011-39 Project Number: 36445 Grant Number: 4357 November 2011 People s Republic of China: Capacity Building to Combat Land Degradation Project Independent

More information

STATUTORY AUTHORITY: ACT no. 50 of 29 June 1990, section 7-6

STATUTORY AUTHORITY: ACT no. 50 of 29 June 1990, section 7-6 NOTE: Unofficial translation - for information only REG. no. 959 of 7 December 1990: Regulations concerning the generation, conversion, transmission, trading, distribution and use of energy etc. (The Energy

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1.Name of the Project Country: Socialist Republic of Viet Nam Project: O Mon Thermal Power Plant Unit No.2 Construction Project (II) Loan Agreement:

More information

BEST PRACTICES IN WATER SUPPLY AND SANITATION:

BEST PRACTICES IN WATER SUPPLY AND SANITATION: BEST PRACTICES IN WATER SUPPLY AND SANITATION: LEARNING FROM SUCCESSFUL PROJECTS A Case Study from the 2006 Annual Evaluation Review March 2007 Marco Gatti Operations Evaluation Department Abbreviations

More information

Implementation Status & Results Jordan Promotion of a Wind Power Market (P093201)

Implementation Status & Results Jordan Promotion of a Wind Power Market (P093201) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Jordan Promotion of a Wind Power Market (P9321) Operation Name: Promotion of a Wind Power Market

More information

RWA GSA Schedule Contract Prices Contract Number GS 35F-0112J With IFF

RWA GSA Schedule Contract Prices Contract Number GS 35F-0112J With IFF RWA GSA Schedule Contract Prices Contract Number GS 35F-0112J With IFF Effective Effective Effective Effective Effective Job Title 1-Dec-13 1-Dec-14 1-Dec-15 1-Dec-16 1-Dec-17 through through through through

More information

Implementation Status & Results Africa WAPP APL 2 - OMVS Felou Hydroelectric Project (P094916)

Implementation Status & Results Africa WAPP APL 2 - OMVS Felou Hydroelectric Project (P094916) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa WAPP APL 2 - OMVS Felou Hydroelectric Project (P094916) Operation Name: WAPP APL 2 - OMVS

More information

SECTOR OVERVIEW. be restructured with commercial banks. In turn, the utilities commit to implement annual tariff increases. 8

SECTOR OVERVIEW. be restructured with commercial banks. In turn, the utilities commit to implement annual tariff increases. 8 Solar and Wind Power Development Project (RRP IND 47920) SECTOR OVERVIEW A. The Energy Sector in India 1. India remains in chronic need of additional power generation capacity. Although, the electrification

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction Solar Power Development Project (RRP SOL 48346) ECONOMIC ANALYSIS A. Introduction 1. The economic analysis of the Solar Power Development Project in Solomon Islands was conducted in accordance with the

More information

ARYAN M.P. POWER GENERATION PVT. LTD.

ARYAN M.P. POWER GENERATION PVT. LTD. ARYAN M.P. POWER GENERATION PVT. LTD. Corp off: 7 th Floor, Corporate Tower Ambience Mall, N.H.-8 Gurgaon-122 001 (Haryana) Ph: +91-124-2719000, Fax: +91-11-2719185 Email: acbpower@gmail.com NOTICE INVITING

More information

IND: Energy Efficiency Enhancement Project in Assam

IND: Energy Efficiency Enhancement Project in Assam Initial Poverty and Social Assessment Project Number: 41614 July 2008 IND: Energy Efficiency Enhancement Project in Assam An initial poverty and social assessment (IPSA) is prepared in the early stage

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Country Partnership Strategy: IND, 2013 2017 SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Sector overview. The demand for power in India has

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Sectors Project ID Borrower Responsible Agency Report No. PID6537

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (RRP VIE 46391) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems and Opportunities 1. The Ministry of

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Lahendong II Geothermal Power Project

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Lahendong II Geothermal Power Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Lahendong II Geothermal

More information

SUMMARY OF PROJECT PERFORMANCE

SUMMARY OF PROJECT PERFORMANCE Additional Financing of Ha Noi Metro Rail System Project (Line 3: Nhon Ha Noi Station Section) (RRP VIE 40080) A. Background SUMMARY OF PROJECT PERFORMANCE 1. The Ha Noi Metro Rail System Project (Line

More information

The World Bank Vietnam Renewable Energy Development Project (P103238)

The World Bank Vietnam Renewable Energy Development Project (P103238) Public Disclosure Authorized EAST ASIA AND PACIFIC Vietnam Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2009 Seq No: 15 ARCHIVED on 14-Feb-2018 ISR29615 Implementing Agencies:

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized SOUTH ASIA Bangladesh Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2009 Seq No: 19 ARCHIVED on 20-Dec-2017 ISR30643 Implementing Agencies:

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 43281 August 2010 Proposed Grant and Administration of Technical Assistance Grant Nepal: Detailed Engineering Study

More information

EAST COAST ROAD, TAMIL NADU, INDIA. Case Study (Transportation) Project Summary:

EAST COAST ROAD, TAMIL NADU, INDIA. Case Study (Transportation) Project Summary: EAST COAST ROAD, TAMIL NADU, INDIA Case Study (Transportation) Project Summary: The southern India state of Tamil Nadu has been a leader in the area of urban sector reforms and has established an efficient

More information

Accord Energy Corporation India Pvt. Ltd.

Accord Energy Corporation India Pvt. Ltd. Accord Energy Corporation India Pvt. Ltd. PRE-FEASIBILITY REPORT ON ENVIRONMENTAL ASPECTS OF PROPOSED INCREASE IN CAPACITY 2 x 150 MW to 2 x 180 MW OF EXISTING ENVIRONMENTAL CLEARANCE ( J-13012/107/ 2009-IA-II

More information

September 12, P age

September 12, P age September 12, 2013 RESPONSES TO COMMENTS FROM THE CTF TRUST FUND COMMITTEE ON THE DEVELOPMENT POLICY LOAN (DPL) TO PROMOTE INCLUSIVE GREEN GROWTH AND SUSTAINABLE DEVELOPMENT IN HIMACHAL PRADESH Comments

More information

CAPACITY BUILDING FOR EXECUTING AGENCIES

CAPACITY BUILDING FOR EXECUTING AGENCIES A. Background Madhya Pradesh Power Transmission and Distribution System Improvement Project (RRP IND 47100) CAPACITY BUILDING FOR EXECUTING AGENCIES 1. Over the last decade, Madhya Pradesh power sector

More information

Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia

Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia Prepared by: Bill Meade Director, Tetra Tech (USA) CLEAN POWER ASIA 29-30 April 2013 Bangkok, Thailand Presentation

More information

ECONOMIC ANALYSIS. 2. Economic rationale. The investment program economic rationale is as follows:

ECONOMIC ANALYSIS. 2. Economic rationale. The investment program economic rationale is as follows: Urban Services Improvement Investment Program (RRP GEO 43405) ECONOMIC ANALYSIS 1. Methodology. The economic analysis for the Urban Services Improvement Investment Program followed the Guidelines for the

More information

SUMMARY OF OPERATION EVALUATION. A wind farm. November 2013 EBRD EVALUATION DEPARTMENT

SUMMARY OF OPERATION EVALUATION. A wind farm. November 2013 EBRD EVALUATION DEPARTMENT SUMMARY OF OPERATION EVALUATION A wind farm November 2013 EBRD EVALUATION DEPARTMENT The Evaluation Department (EvD) at the EBRD evaluates the performance of the Bank s completed projects and programmes

More information

Proposed additional financing to the Kingdom of Cambodia for the Tonle Sap Poverty Reduction and Smallholder Development Project

Proposed additional financing to the Kingdom of Cambodia for the Tonle Sap Poverty Reduction and Smallholder Development Project Document: EB 2017/LOT/P.20 Date: 17 November 2017 Distribution: Public Original: English E President s memorandum Proposed additional financing to the Kingdom of Cambodia for the Tonle Sap Poverty Reduction

More information

AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project

AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project A. Introduction AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project TERMS OF REFERENCE FOR PROJECT MANAGEMENT

More information