Initial Gap Analysis: Adaptation and Planning For Change
|
|
- Sibyl Cameron
- 5 years ago
- Views:
Transcription
1 RISC Meeting Agenda Item 1.b Initial Gap Analysis: Adaptation and Planning For Change Ben Crisp, Chair NERC Planning Committee RISC Meeting October 25, 2013
2 Summary of Issue Over the next 10 years, the electric industry will face a number of significant emerging reliability issues and face a transformational change These changes affect the way the power system operates These issues all require careful consideration, preparation, and planning to avoid an adverse impact to system reliability Regional evaluations and studies provide critical insights to the industry at large 2 RELIABILITY ACCOUNTABILITY
3 Analysis Approach Challenges and associated risks of long-term planning issues should be evaluated under three risk areas Resource and Transmission Adequacy Integration of New Technologies and Operations Long-Term Planning and System Analysis All future risks generally fall into these main risk areas Some risks do not directly impact these issues, but they may be secondary, tertiary Adaptation and Planning for Change should be aligned with LTRA Leverage PC/OC technical input to LTRA for gap analysis Utilize industry risk assessment on emerging issues as input to prioritization Further evaluation is provided in the Gap Analysis document 3 RELIABILITY ACCOUNTABILITY
4 Risk Areas Resource and Transmission Adequacy Risks represent the projected inability to serve customer demand Resource and transmission adequacy risks impacted continuously by public and society pressure, regulatory uncertainty (e.g., market, environmental), and the uncertainty of future resources Given the large lead time for infrastructure development, these risks must be considered and planned for years in advance Integration of New Technologies and Operations Risks represent potential future operational issues that may introduce into the BPS as a result of change New resources with unique operating characteristics behave differently and have an aggregate impact to overall BPS operations The ability to withstand BPS disturbances in real-time operations is threatened Long-Term Planning and System Analysis Risks represent challenges to the approach and methods (the how ) used for longterm planning Incorrect assumptions and methods can lead to incorrect decision-making 4 RELIABILITY ACCOUNTABILITY
5 Risks Resource and Transmission Adequacy Environmental Regulation (High) Integration of Variable Generation (High) o Utility-grade VERs and Distributed VERs Increased Dependence on Natural Gas (High) Demand-Side Management (Med) o Demand Response and Energy Efficiency Demand Forecast Uncertainty (Low) Nuclear Generation (Low) Transmission Siting/Permitting and Aging Infrastructure (Low) Threat: Increasing uncertainty in existing and future generation (availability, feasibility) due to regulatory uncertainty creates planning challenge to meet adequacy targets Timeframe: Mid-Term to Long-Term (3 to 10 years) NERC Tools Used (to be used): Reliability Assessment, technical guidance and advocacy for regulators and policy makers Lead NERC Groups\Resources: PC, Staff (RAPA, Government Relations) 5 RELIABILITY ACCOUNTABILITY
6 Gaps in Key Risk Areas Resource and Transmission Adequacy Gaps: Medium o Regional-level planning studies that address and consider the various risks o Post-action review of specific regional resource adequacy concerns o Defining capacity: what requirements should capacity resources have (e.g., fuel) o Common approach for determining capacity contributions of variable generation o Ability to make independent assessment and engineering judgment for unknowns o Closer coordination with responsible authorities (i.e., state PUC) on adequacy challenges o Some challenges are beyond the industry s control or require significant cross-industry coordination (e.g., regulatory uncertainty, natural gas industry) o Consideration of distributed resources and demand-side resources o Better harmonization of assessment recommendations and actionable risk projects Recommendations: o Develop lessons learned/best practices and/or post-action summary for distribution to the industry o Develop Special Reliability Assessments to address the high risk issues o Advocate and educate industry, public, regulators, and policy makers o Consideration of RAS and IVGTF recommendations in LTRA and special assessments 6 RELIABILITY ACCOUNTABILITY
7 Risks Integration of New Technologies and Operations Integration of Variable Generation (High) o Utility-grade VERs and Distributed VERs Increased Dependence on Natural Gas (High) Demand Response (Med) Smart Grid (Low) Threat: The integration of new technologies on the BPS changes fundamental system behaviors and introduces new operational risks due to unknown/unplanned resource performance and/or availability. Theses threats can decrease the system s resilience and capability to withstand BPS disturbances. Timeframe: Short-Term to Long-Term (1 to 10 years) NERC Tools Used (to be used): Reliability Assessment, Technical Guidance, Reliability Standards, Alerts Lead NERC Groups\Resources: PC (support from OC), Staff (RAPA, Government Relations) 7 RELIABILITY ACCOUNTABILITY
8 Gaps in Key Risk Areas Integration of New Technologies and Operations Gaps: Medium o Regional-level planning studies that address and consider the various risks o Incorporating natural gas pipeline and/or supply risks into reliability analysis (e.g., TPL contingency analysis and power flow and stability) o Reliability Standards gap for asynchronous and variable generation o Distribution or demand-side challenges difficult to manage given NERC authority o Demand response operators (i.e., third-party aggregators not covered under NERC registration) o Ability to make independent assessment and engineering judgment for unknowns o Some challenges are beyond the industry s control or require significant cross-industry coordination (e.g., regulatory uncertainty, natural gas industry) o Better harmonization of assessment recommendations and actionable risk projects o Unknown impact of smart devices and systems (e.g., automatic control, system optimization) Recommendations: o Enhance operator training and operational planning to ensure flexibility is planned and available o Develop Special Reliability Assessments to address the high risk issues o Advocate and educate industry, public, regulators, and policy makers o Consideration of RAS and IVGTF recommendations in LTRA and special assessments 8 RELIABILITY ACCOUNTABILITY
9 Risks Long-Term Planning and System Analysis Change in Resource Mix and Operational Characteristics (High) Change in System Behavior and Composition of System Load (High) Region/Interconnection-wide Planning and Modeling (Med) Threat: Long-term planning and system analysis need to identify and reflect representative risks to the BPS. Given a large change in a given resource mix, system behavior (i.e., generation characteristics, frequency response, inertia requirements) will likely change. Robust and risk-oriented planning and modeling approaches will be needed to address transmission and operating reliability. Incorrect assumptions and methods can lead to incorrect decision-making for system reinforcement, resources, transmission, flexibility, and operational needs. Timeframe: Short-Term to Long-Term (1 to 10 years) NERC Tools Used (to be used): Reliability Assessment, Technical Guidance, Reliability Standards, Alerts Lead NERC Groups\Resources: PC (support from OC), Staff (RAPA, Government Relations) 9 RELIABILITY ACCOUNTABILITY
10 Gaps in Key Risk Areas: Long-Term Planning and System Analysis Gaps: Medium-High o Regional-level planning studies that address and consider the various risks o Identification and determination of frequency responsive resources o Incorporating natural gas pipeline and/or supply risks into reliability analysis (e.g., TPL contingency analysis and power flow and stability) o Reliability Standards gap for asynchronous and variable generation; standard models needed o Distribution or demand-side challenges difficult to manage (data and information on distributed/behind-the-meter generation often unknown to planners/operators) o Ability to make independent assessment and engineering judgment for unknowns o Better harmonization of assessment recommendations and actionable risk projects o Unknown impact of smart devices and systems (e.g., automatic control, system optimization), electronically coupled loads, and load composition o Unknown FIDVR concerns may be embedded risk that has not been fully analyzed Recommendations: o Long-term studies need to determine the amount of flexibility needed to maintain reliability o Guidelines on frequency responsive resources being developed as part of the Frequency Response Initiative to address comprehensive integration of those various resources o Consideration of RAS, SAMS and IVGTF recommendations in LTRA and special assessments 10 RELIABILITY ACCOUNTABILITY
11 Gap Analysis High-Level Conclusions Need for operator flexibility to address Generation and transmission uncertainty Changing system response with the addition of new technologies Fuel uncertainty Serving unexpected loads Need for sufficient planning reserves to address Timing of retirements, scheduled outages, regulatory requirements Regulatory uncertainty Fuel uncertainty Need for accurate assessments and planning studies to address Risks and uncertainties of emerging reliability issues Actual operating characteristics and system dynamics Regionality of reliability issues needs consideration 11 RELIABILITY ACCOUNTABILITY
12 Current NERC Actions Technical Committee Role Long-Term and Seasonal Assessments Special Reliability Assessments on emerging issues Technical support and guidance documents for use in standards development and compliance operations (e.g., IVGTF, SAMS) System Analysis and Reliability Initiatives (e.g., IFRO, modeling) NERC Staff Role Collaboration with interconnection-wide/regional planning and study groups on emerging issues (e.g., EIPC on natural gas vulnerabilities) Coordination with state regulators on resource adequacy challenges Education and key messaging to industry, regulators, and public Coordination with NERC governmental relations and communications 12 RELIABILITY ACCOUNTABILITY
13 LTRA Risk Assessment The following provides some insights into the LTRA risk assessment of more granular and region-specific issues 13 RELIABILITY ACCOUNTABILITY
14 Example of Sub-Risk Assessment in LTRA Integration of Variable Generation Provides more fidelity on challenges associated with VERs Leverages existing LTRA process and stakeholder/sme inputs o values are an average of all survey participants Reactive Power and Inertia Impacts to BPS Valid and Respresentative Models of VER: Voltage Stability and Frequency Response Impacts to BPS Sub-risk Assessment: Continued Integration of Variable Generation Distributed VERs Manageable. No further action is needed from NERC 2-Manageable, assuming the continuation of existing initiatives to address the issue 3-Manageable, but will cause challenges and additional action to be taken to address the issue (e.g., special assessment, technical committee review) Overall Integration of VERs 4-Potentially unmanageable without Control (e.g. active and reactive) and Communication significant action, including shifts from existing policy and possible enhancements VER Forecasting to NERC standards and guidelines New Transmission to Support VERs 5-Unmanageable under current trajectory; extreme risk; must be addressed 0% 20% 40% 60% 80% 100% immediately 14 RELIABILITY ACCOUNTABILITY
15 Example of Sub-Risk Assessment in LTRA Integration of Variable Generation Resource Adequacy Provides more Regional perspective on risk area Provides SME insights on likelihood and timing o values are an average of all survey participants Regional Assessment: Integration of Variable Generation, Resource Adequacy 6 to 10 Years 1 to 5 Years SPP MRO SERC WECC RFC TRE NPCC FRCC % 20% 40% 60% 80% 1-Very Low: No impact to resource adequacy projections 2-Low: Some impact to resource adequacy, but adequate reserve margin projections 3-Medium: Reserve margin projections are below target 4-High: Significant impact to reserve margins 15 RELIABILITY ACCOUNTABILITY
16 Risk Assessment Highlights Most issues were categorized as Manageable, but will cause challenges and additional action to be taken to address the issue (e.g., special assessment, technical committee review) About 20 percent of participants categorized the following long-term issues as Potentially unmanageable without significant action, including shifts from existing policy and possible enhancements to NERC standards and or guidelines Continued Integration of Variable Generation Fossil-Fired Retirements and Coordination of Outages for Environmental Control Retrofits Increased Dependence on Natural Gas for Electric Power Less than 5 percent of participants identified only two long-term issues categorized as Unmanageable under current trajectory; extreme risk; must be addressed immediately Increased Dependence on Natural Gas for Electric Power Fossil-Fired Retirements and Coordination of Outages for Environmental Control Retrofits 16 RELIABILITY ACCOUNTABILITY
17 Lower Impact Higher Impact Impact LTRA Risk Assessment High Level (Preliminary) Wide-Scale Nuclear Generation Retirements and/or Long-Term Outages Increased Dependence on Demand Response Continued Integration of Variable Generation Increased Dependence on Natural Gas for Electric Power Fossil-Fired Retirements and Coordination of Outages for Environmental Increasing Uncertainty in Load Forecasts Aging Infrastructure Transmission Siting, Permitting, and other Right-of- Way Issues Lower Likelihood Higher Likelihood Likelihood 17 RELIABILITY ACCOUNTABILITY
18 Questions? 18 RELIABILITY ACCOUNTABILITY
19 More Information? NERC Reports on Accommodating High Levels of Variable Generation: DRAFT Joint NERC-CAISO Special Reliability Assessment: Maintaining Bulk Power System Reliability While Integrating Variable Energy Resources to Meet Renewable Portfolio Standards Interconnection Requirements for Variable Generation, NERC, September 2012 Potential Bulk System Reliability Impacts of Distributed Resources Methods to Model and Calculate Capacity Contributions of Variable Generation for Resource Adequacy Planning Ancillary Service and Balancing Authority Area Solutions to Integrate Variable Generation Operating Practices, Procedures, and Tools Potential Reliability Impacts of Emerging Flexible Resources Variable Generation Power Forecasting for Operations Standard Models for Variable Generation Flexibility Requirements and Potential Metrics for Variable Generation NERC Reports on Accommodating and Increased Dependency on Natural Gas Primer (Phase I) Vulnerability Assessment (Phase II) NERC Reliability Assessments (Long-Term and Seasonal) 19 RELIABILITY ACCOUNTABILITY
Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective
Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective Mark Lauby, Senior Vice President and Chief Reliability Officer North American Electric Reliability Corporation
More information2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Innovations in Bulk Power System Reliability Assessment: A North American View M.G.
More informationBPS Reliability Risks and NERC RISC. Ryan D. Quint, Advanced Analytics & Modeling, NERC WECC RAC Meeting October 2017
BPS Reliability Risks and NERC RISC Ryan D. Quint, Advanced Analytics & Modeling, NERC WECC RAC Meeting October 2017 Reliability Issues Steering Committee (RISC) RISC reports directly to NERC BOT; provides
More informationEvaluating Severe Natural Gas Disruptions and Impacts to Bulk Power System Reliability
1 Evaluating Severe Natural Gas Disruptions and Impacts to Bulk Power System Reliability Robert W. Cummings NERC Senior Director of Engineering and Reliability Initiatives Key Messages 2 3 Findings From
More informationERO Business Planning and Budgeting Process
ERO Business Planning and Budgeting Process Michael Walker, Senior Vice President and Chief Financial and Administrative Officer Member Representatives Committee August 14, 2013 RISC formed NERC & REs
More informationProbabilistic Assessment Improvement Plan
Probabilistic Assessment Improvement Plan Summary and Recommendations Report December 2015 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary...1 Introduction...2 Background...2
More informationNERC Probabilistic Assessments Overview & Future Improvements
NERC Probabilistic Assessments Overview & Future Improvements Noha Abdel-Karim, PhD. NERC IEEE LOLEWG Meeting July 31, 2015 Overview NERC Probabilistic Assessment (ProbA) reports extend the LTRA data with
More informationNERC: Potential Bulk Power System Impacts due to Severe Disruptions of the Natural Gas System
NERC: Potential Bulk Power System Impacts due to Severe Disruptions of the Natural Gas System Thomas Coleman, Director, Reliability Assessment Natural Gas/Electric Partnership February 1, 2018 Houston,
More informationNERC Project. Increase Analytical Capabilities in the Probabilistic Domain
NERC Project Increase Analytical Capabilities in the Probabilistic Domain Noha Abdel-Karim, PhD. Senior Engineer for Reliability Assessment IEEE-LOLE Working Group Meeting July 21-22, 2016 About NERC International
More information2016 Long-Term Reliability Assessment
2016 Long-Term Reliability Assessment December 2016 NERC Report Title Report Date I Table of Contents Preface... v Introduction... vi Executive Summary... vii Chapter 1: Reliability Issues... 1 Resource
More informationExternal Document Links
External Document Links Relay Misoperations Reliability Indicators Dashboard http://www.nerc.com/page.php?cid=4 331 400 Misoperations Template: http://www.nerc.com/docs/pc/rmwg/protection_system_misoperation_reporting_template_final.xlsx
More informationStandards Authorization Request Form
Standards Authorization Request Form Request to propose a new or a revision to a Reliability Standard Title of Proposed Standard(s): EOP-010-1 Geomagnetic Disturbance Operations TPL-007-1 Transmission
More informationSpecial Assessment: Bulk Power System Impacts Due to Severe Disruptions on the Natural Gas System
Special Assessment: Bulk Power System Impacts Due to Severe Disruptions on the Natural Gas System John Moura, Director, Reliability Assessment and System Analysis Natural Gas Supply Association Annual
More information2013 Long-Term Reliability Assessment
Preface 2013 Long-Term Reliability Assessment December 2013 Preface Table of Contents PREFACE... III EXECUTIVE SUMMARY... 1 LONG-TERM PROJECTIONS AND HIGHLIGHTS... 5 PROJECTED DEMAND, RESOURCES, AND RESERVE
More informationBulk Power System Integration of Variable Generation - Program 173
Bulk Power System Integration of Variable Generation - Program 173 Program Description Program Overview A number of ongoing environmentally driven regulatory issues including greenhouse gas reductions
More informationReliability Assessment Subcommittee Agenda
Reliability Assessment Subcommittee Agenda January 27, 2010 8 5 p.m. January 28, 2010 8 5 p.m. SERC Reliability Corporation 2815 Coliseum Centre Drive, Suite 500 Charlotte, NC 28217 704-357-7372 Wednesday,
More informationERO Enterprise Longer-term Strategic Planning Considerations November 2015
ERO Enterprise Longer-term Strategic Planning Considerations November 2015 Background The ERO Enterprise strategic planning process provides a three-year outlook for developing NERC and Regional Entity
More informationPlanning Impacts from DER (PIDER)
Planning Impacts from DER (PIDER) Straw Man Proposal LMTF and SAMS Meeting May 14-18, 2018 Background from 2017 LTRA on DER DER Drivers Estimated addition of more than 26 GW of non-utility photovoltaic
More informationAccommodating High Levels of Distributed Energy Resources
Accommodating High Levels of Distributed Energy Resources John Moura, Director of Reliability Assessment and System Analysis 2017 NARUC Winter Committee Meetings February 14, 2017 About NERC: Mission To
More information2011 Reliability Performance Analysis Report
2011 Reliability Performance Analysis Report July 2011 NERC s Mission NERC s Mission The North American Electric Reliability Corporation (NERC) is an international regulatory authority established to evaluate
More informationDraft Electric Reliability Organization Enterprise Strategic Plan
Draft Electric Reliability Organization Enterprise Strategic Plan 2017 2020 NERC Report Title Report Date I Table of Contents Preface... iii Introduction...1 Vision, Mission, and Values...2 Goal 1: Timely
More informationERO Reliability Risk Priorities
ERO Reliability Risk Priorities RISC Recommendations to the NERC Board of Trustees October 2015 NERC ERO Reliability Risk Priorities RISC Recommendations to the NERC Board of Trustees October 2015 I Table
More informationBulk Power System Integration of Variable Generation - Program 173
Program Description Program Overview Environmentally driven regulations such as state-mandated renewable energy standards and federal air and water standards, along with improved economic viability for
More informationState of Reliability 2017
State of Reliability 2017 June 2017 NERC Report Title Report Date I Table of Contents Preface... v Executive Summary... vi Chapter 1: Key Findings and Recommendations...1 Chapter 2: 2016 Reliability Highlights...7
More informationReview of Standards Becoming Enforceable in 2014
Review of Standards Becoming Enforceable in 2014 Laura Hussey, NERC Director of Standards Development Standards and Compliance Workshop April 3, 2014 New BAL and VAR Standards in 2014 BAL-001-1 Real Power
More informationEssential Reliability Services Task Force
Essential Reliability Services Task Force A Concept Paper on Essential Reliability Services that Characterizes Bulk Power System Reliability October 2014 I Table of Contents Preface... ii Executive Summary...
More informationIntegrating High Levels of Variable Renewable Energy Sources
Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning
More informationJanuary 2016 Update on High, Medium and Low Priority Transmission Lines
March 11, 2016 Mr. Loye Hull Office of Electric Reliability Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Recommendation to Industry: Consideration of Actual Field
More information2010 Annual Report on Bulk Power System Reliability Metrics
2010 Annual Report on Bulk Power System Reliability Metrics June 2010 NERC s Mission NERC s Mission The North American Electric Reliability Corporation (NERC) is an international regulatory authority for
More informationStandard Authorization Request Form
Standard Authorization Request Form Title of Proposed Standard Withdraw 3 Midwest ISO Waivers Request Date April 2, 2009 SC Approval Date April 15, 2009 SAR Requester Information SAR Type (Check a box
More informationPotential Reliability Impacts of EPA s Proposed Clean Power Plan
Potential Reliability Impacts of EPA s Proposed Clean Power Plan Phase I April 2015 NERC Potential Reliability Impacts of EPA s Proposed Clean Power Plan Phase I April 2015 I Table of Contents Preface...
More informationFRCC Florida Reliability Coordinating Council. MRO Midwest Reliability Organization
NERC IVGTF Task 2.4 Report Operating Practices, Procedures, and Tools March 2011 NERC s Mission to ensure the reliability of the bulk power system The North American Electric Reliability Corporation (NERC)
More informationNERC Planning Committee Report
NERC Planning Committee Report 2017 Meeting Highlights John Seidel, on behalf of Dale Burmester - MRO member rep on NERC PC MRO Board of Directors November 30, 2017 Midwest Reliability Organization Operating
More informationMinutes NERC System Analysis and Modeling Subcommittee (SAMS) January 28-30, 2014
Minutes NERC System Analysis and Modeling Subcommittee (SAMS) January 28-30, 204 ERCOT Austin MET Center 7620 Metro Center Drive Austin, TX 78744. Administrative The meeting commenced at :00 p.m. CST with
More informationImproving Fossil Fleet Performance through Actionable Benchmarking
Improving Fossil Fleet Performance through Actionable Benchmarking ScottMadden s Methodology for Achieving Results Author: Jake Jacobi Contact: Stuart Pearman Introduction With ever-increasing performance
More informationEnergy Department Report on Electricity Markets and Reliability
Quick Insights Energy Department Report on Electricity Markets and Reliability RESEARCH QUESTION What are the key findings and recommendations from the Staff Report to the Secretary on Electricity Markets
More information2009 Long-Term Reliability Assessment the reliability of the. October 2009
2009 Long-Term Reliability Assessment 2009-2018 to ensure the reliability of the bulk power system October 2009 116-390 Village Blvd., Princeton, NJ 08540 609.452.8060 609.452.9550 fax www.nerc.com NERC
More informationTable of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.
Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6
More informationStandards Authorization Request Form
Standards Authorization Request Form When completed, please email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability
More informationConsistency in BPS Data Reporting
Consistency in BPS Data Reporting Presented by: John A Seidel, MRO, PSMTF Chairperson Date: August 1, 2012 Consistent BPS Data Reporting Consistent and accurate BPS data reporting is a key ingredient needed
More informationStandards Authorization Request Form
Standards Authorization Request Form When completed, please email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved Reliability
More informationReliability Guideline
Reliability Guideline Modeling Distributed Energy Resources in Dynamic Load Models December 2016 NERC Report Title Report Date I Table of Contents Preface... iii Preamble... iv Purpose...1 Discussion of
More informationTracking New Coal-Fired Power Plants
Tracking New Coal-Fired Power Plants National Energy Technology Laboratory Office of Systems Analyses and Planning Erik Shuster October 10, 2007 Tracking New Coal-Fired Power Plants This report is intended
More informationStandards Authorization Request Form
When completed, email this form to: sarcomm@nerc.net NERC welcomes suggestions for improving the reliability of the Bulk-Power System through improved Reliability Standards. Please use this form to submit
More informationStandard Authorization Request Form
When completed, email to: gerry.cauley@nerc.net Standard Authorization Request Form Title of Proposed Standard System Personnel Training Request Date 07/01/2004 Revised 12/01/04 SAR Requestor Information
More informationEIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015
EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be
More information(This page is intentionally'
FORTISBC INC 2012-13 REVENUE REQUIREMENTS AND REVIEW OF ISP EXHIBIT C9-17 (This page is intentionally' left blank.) to ensure the reliability of the bulk power system The North American Electric Reliability
More information2017 Long-Term Reliability Assessment
2017 Long-Term Reliability Assessment Table of Contents Preface 3 About This Assessment 4 Executive Summary 5 Detailed Review of 2017 Findings 7 Reserve Margin Analysis 8 Changing Resource Mix 13 Essential
More informationReliability Standards Development Plan
Reliability Standards Development Plan 2018-2020 October 18, 2017 NERC Report Title Report Date I Table of Contents Background... iii Executive Summary... iv 2017 Progress Report...1 FERC Directives...1
More informationFINAL Meeting Minutes NERC System Analysis and Modeling Subcommittee (SAMS) April 28-30, 2015
FINAL Meeting Minutes NERC System Analysis and Modeling Subcommittee (SAMS) April 28-30, 205 The Hotel Northampton 36 King Street Northampton, MA 0060. Administrative The meeting commenced at :00 p.m.
More information2007 Long-Term Reliability Assessment
2007 Long-Term Reliability Assessment American Antitrust Institute 8 th Annual Energy Roundtable March 3, 2008 Dave Nevius, Senior Vice President NERC What is the LTRA? Annual 10-year assessment of future
More informationReliability Standards Development Plan:
Reliability Standards Development Plan: 2010 2012 Volume I Overview October 7, 2009 Reliability Standards Development Plan: 2010 2012 Acknowledgement The NERC Reliability Standards Program would like to
More informationStandards Authorization Request Form
When completed, please email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards. Please use this form to
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More information2013 SPP RE Annual CMEP Implementation Plan
2013 SPP RE Annual CMEP Implementation Plan December 3, 2012 Jeff Rooker, Lead Compliance Engineer jrooker.re@spp.org 501.614.3261 Leesa Oakes, Compliance Specialist II loakes.re@spp.org 501.614.3274 Outline
More informationLocational Net Benefits Analysis Working Group Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart
Locational Net Benefits Analysis Working Group Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart Background: A June 7, 2017 Assigned Commissioner Ruling
More informationAgenda Member Representatives Committee Pre-Meeting Informational Session Conference Call and Webinar July 18, :00 a.m. 12:00 p.m.
Agenda Member Representatives Committee Pre-Meeting Informational Session Conference Call and Webinar July 18, 2018 11:00 a.m. 12:00 p.m. Eastern Dial-in: 1-800-581-5838 Conference ID: 988973 Click here
More informationReliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective
Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective John Moura, Director of Reliability Assessments and System Analysis The Center for Energy, Economic and
More informationLoad Shed Philosophy
APPLICABILITY: Reliability Coordinator I. Background While time limits exist for mitigation of the exceedance of certain types of system operating limits, events can occur quickly necessitating a responsive
More informationMeeting Location: NERC Offices 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326
Minutes Essential Reliability Services Working Group Leadership Meeting (Invite Only) February 22, 2017 12:00 5:00 p.m. EST February 23, 2017 8:00 a.m. 12:00 p.m. EST Meeting Location: NERC Offices 3353
More informationComment Form for Functional Model Version 4 and Associated Technical Reference
Comment Form for Functional Model Version 4 and Associated Technical Reference Please use this form to submit comments on Version 4 of the Functional Model and its associated Technical Reference. must
More informationTracking New Coal-Fired Power Plants
Tracking New Coal-Fired Power Plants National Energy Technology Laboratory Office of Systems Analyses and Planning Erik Shuster February 18, 2008 a Tracking New Coal-Fired Power Plants This report is intended
More informationMapping Document for FAC-010-3
Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding
More informationERO Enterprise Guide for Compliance Monitoring
ERO Enterprise Guide for Compliance Monitoring October 2016 NERC Report Title Report Date I Table of Contents Preface... iv Revision History... v 1.0 Introduction...1 1.1 Processes within the Overall Risk-Based
More informationGrid Resilience in Regional Transmission Organizations and Independent System Operators AD
Grid Resilience in Regional Transmission Organizations and Independent System Operators AD18-7-000 Chris O Hara Vice President, Deputy General Counsel Markets and Reliability Committee January 25, 2018
More informationSpecial Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards
Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Draft for Planning Committee Review 3353 Peachtree Road
More informationAEP Guidelines for Transmission Owner Identified Needs
AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal
More informationSPP at a Glance. Located in Little Rock. Approximately 600 employees
SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment
More informationEssential Reliability Services
Essential Reliability Services Whitepaper on Sufficiency Guidelines December 2016 NERC Report Title Report Date I Table of Contents Preface... iii Executive Summary... iv Introduction... vi Chapter 1:
More informationMeeting Minutes System Analysis and Modeling Subcommittee April 29 - May 1, 2014
Meeting Minutes System Analysis and Modeling Subcommittee April 29 - May, 204 SERC Reliability Corporation Offices 285 Coliseum Centre Drive, Suite 500 Charlotte, NC 2827. Administrative The meeting commenced
More informationStandard BAL-502-RFC-02
A. Introduction 1. Title: Planning Analysis, Assessment and Documentation 2. Number: BAL-502-RFC-02 3. Purpose: To establish common criteria, based on one day in ten year loss of Load expectation principles,
More information2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool
2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.
More informationDeleted: RFC-02 12/04/08
A. Introduction 1. Title: Planning Resource Adequacy Analysis, Assessment and Documentation 2. Number: BAL-502-RF-03 3. Purpose: To establish common criteria, based on one day in ten year loss of Load
More informationPrimary Contact Roger Harszy Revision to existing Standard. Telephone: Withdrawal of existing Standard
Title of Proposed Standard: Coordinate Operations Request Date: March 7, 2002 Authorized for Posting: March 20, 2002 SAR ID# : COORD_OPERATONS_01_02 SAR Requestor Information Name: Jim Byrd (Roger Harszy
More informationStandards Authorization Request Form
Standards Authorization Request Form When completed, email this form to: Howard.Gugel@nerc.netValerie.Agnew@nerc.net For questions about this form or for assistance in completing the form, call Howard
More informationNorthwest Power Pool Processes
Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed
More informationPAS Update. Paul Kure, Chair, NERC Performance Analysis Subcommittee Meeting Planning Committee Meeting June 5-6, 2018
PAS Update Paul Kure, Chair, NERC Performance Analysis Subcommittee Meeting Planning Committee Meeting June 5-6, 2018 PAS Update PAS update PAS and working group work plans updated Working groups addressing:
More informationIntegrated Reliability Index Concepts
Integrated Reliability Index Concepts The development of an integrated reliability index aims to inform, increase transparency, and quantify the effectiveness of risk reduction and/or mitigation actions.
More informationGRID OPERATIONS AND PLANNING
GRID OPERATIONS AND PLANNING VISION The future transmission grid will be highly automated, will be flexible in connecting all available energy sources, will facilitate active participation by all grid-connected
More informationStandard Authorization Request Form
Standard Authorization Request Form Title of Proposed Standard Glossary of Terms change System Operator definition (Project 2010-16 Definition of System Operator) Request Date October 5, 2010 SC Approval
More information2018 Business Plan and Budget
2018 Business Plan and Budget Draft 1 May 19, 2017 I Table of Contents Table of Contents... ii About NERC... 1 Overview... 1 Membership and Governance... 2 Scope of Oversight... 2 Statutory and Regulatory
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationDemand Response Data Task Force Draft Report Outline and Work Plan
Demand Response Data Task Force Draft Report Outline and Work Plan DRDTF Objectives: 1. Identify how the Demand Response (DR) resource data will be used by NERC Work backward from NERC s operational needs
More information2019 ERO Enterprise Dashboard
2019 ERO Enterprise Dashboard Mark Lauby, Senior Vice President and Chief Reliability Officer Corporate Governance and Human Resources Committee Meeting February 6, 2019 Proposed 2019 Industry Dashboard
More informationProposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources
Draft White Paper Proposed Revisions to the Applicability of NERC Reliability Standards NERC Standards Applicability to Dispersed Generation Resources Project 2014-01 Standards Applicability for Dispersed
More informationPacific Northwest Utilities Conference Committee
Pacific Northwest Utilities Conference Committee Elements of Transformation Paul De Martini Senior Fellow November 6, 2015 Evolution of Customer & Distribution Grid 3 Stages of Evolution as DER Adoption
More informationBusiness Practice Manual for The Transmission Planning Process
Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...
More information2018 Business Plan and Budget
2018 Business Plan and Budget Draft 2 July 17, 2017 I Table of Contents Table of Contents... ii About NERC... 1 Overview... 1 Membership and Governance... 2 Scope of Oversight... 2 Statutory and Regulatory
More information2018 Business Plan and Budget
2018 Business Plan and Budget Final August 10, 2017 I Table of Contents Table of Contents... ii About NERC... 1 Overview... 1 Membership and Governance... 2 Scope of Oversight... 2 Statutory and Regulatory
More informationRevised Event Analysis Process Event Analysis Subcommittee (EAS) Process Update Team (EUT)
Revised Event Analysis Process Event Analysis Subcommittee (EAS) Process Update Team (EUT) Sam Holeman Duke Energy, EAS chair Hassan Hamdar FRCC, EAS vice-chair Rich Bauer NERC August 28, 2013 Webinar
More informationTransfer Capability Methodology. for the Near-Term. Transmission Planning Horizon
Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY
More informationDefinition of Adequate Level of Reliability. Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET
Definition of Adequate Level of Reliability Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET Outline Background Definition and Reliability Objectives Supporting Documents Industry Feedback Next Steps Questions
More informationReliability Assessment Procedure Subregional Restructuring to Support ISO/RTO Boundaries
Reliability Assessment Procedure Subregional Restructuring to Support ISO/RTO Boundaries Background One key to delivering credible and meaningful assessments of the bulk power system reliability is the
More information2011 Special Reliability Assessment: A Primer on the Natural Gas and Electric Power Interdependency in the United States
2011 Special Reliability Assessment: A Primer on the Natural Gas and Electric Power Interdependency in the United States Timeline Phase I Sept 13-14 October 25 November 18 Mid November Report sent to PC
More informationComment Form System Operator Training Standard 1 st Draft
Please use this form to submit comments on the proposed System Operator Training standard. Comments must be submitted by October 26, 2006. You may submit the completed form by e-mail to sarcomm@nerc.com
More information2015 Summer Reliability Assessment
2015 Summer Reliability Assessment May 2015 I Table of Contents Preface... iii Assessment Development... iv Executive Summary...1 Key Finding #1:...2 Key Finding #2:...5 Key Finding #3:...8 Key Finding
More informationAEP Transmission Local Planning Assumptions, Models, and Criteria
AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationDRAFT Reliability Standards Development Plan. June 15, 2016
DRAFT Reliability Standards Development Plan 2017 2019 June 15, 2016 I Table of Contents Background... iii Executive Summary... iv 2016 Progress Report...1 FERC Directives...1 Projects Completed in 2016...1
More information