1. BACKGROUND MATERIAL SCOPE AND CONSIDERATIONS... 2

Size: px
Start display at page:

Download "1. BACKGROUND MATERIAL SCOPE AND CONSIDERATIONS... 2"

Transcription

1 POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T. Overplanting Filename ONL T_Overplanting_PP_v3 Version 3 - Public release Pages 4 QUALITY CONTROL Prepared: Daniël Vree Reviewed: Frank de Vries Approved: Frank Wester Release Table of Contents. BACKGROUND MATERIAL SCOPE AND CONSIDERATIONS ACTIVE POWER TRANSFER THROUGH THE TENNET OFFSHORE GRID Export cable design (220kV) (Status V, dd ) ADDITIONAL CALCULATIONS ON DYNAMIC LOADING OF THE EXPORT CABLES Introduction (V ) Update based on results of initial geotechnical survey (V3)... 6 Analysis of soil data of the initial geotechnical survey... 6 Update of the dynamic ampacity calculations for 380MW: basis for the calculations... 7 Update of the dynamic ampacity calculations for 380MW: calculations results EXPORT CABLE LOAD MANAGEMENT POSITION OF TENNET IMPACT ON COST FURTHER UPDATES (STATUS AS OF ) ANNEX A: SOIL RESISTIVITY ANALYSIS - OFFSHORE CABLE ROUTE FROM LANDFALL TO BORSSELE ALPHA AND BETA... 4

2 PAGE 2 of 4. Background material Literature used: N.A. 2. Scope and considerations The Figure below shows a schematic cross section of the connection of an offshore wind farm to the onshore electricity grid. Wind turbines are connected through inter-array cables (in orange) to the offshore Connection Point (CP) at the offshore substation, from which electricity is transported to shore. TenneT is responsible for the grid connection up to, and including, the offshore substation and will take care for the supply and installation. The wind park, including the wind turbines and the array cables, up to the offshore CP at the switchgear installation on the offshore substation of TenneT, is to be supplied and installed by the owner of the Power Park Module (PPM 2 ). TenneT intends to standardise the offshore substations as much as possible for all five wind areas to be realised in the coming years in line with the Energy Agreement. Figure - Schematic of the offshore electrical grid. Source: TenneT The connection point (CP) between the offshore power park module (PPM) and TenneT is specified [TenneT position paper ONL 5-06 T.3 Point of Common Coupling] at the cable termination of the inter-array cables and the switchgear installation on the platform. 2 TenneT, position paper ONL T.5 Operation of Bays

3 PAGE 3 of 4 Overplanting An important aspect in the design of an offshore wind farm, is to optimise the offshore wind farm capacity (type and number of wind turbine generators) to the fixed electrical infrastructure export capacity. This principle is also referred to as overplanting or overbooking since it usually leads to installing a (small) number of extra wind turbine generators compared to the grid connection capacity limit 3. The "overplanted" power from these extra turbines will result in higher energy yield at lower wind speeds but will lead to a curtailed power at higher wind speeds as depicted in Figure 2. Off course, the extra turbines will result in higher CAPEX, which should be balanced by extra revenues from the extra energy yield. Figure 2 - Principal of Capacity Optimisation. Source: Global Offshore Wind Conference 204. To be able to further optimise the PPM lay-out (location, type and number of wind turbine generators), it is necessary for the PPM owner not only to know to what to extent the grid connection may be continuously loaded (e.g. the grid capacity limit) but also to what extent the grid connection may be (temporary) loaded above this capacity limit. In this way, the curtailed power is reduced and the energy yield is increased further. This paper describes the position of TenneT with respect to the extent to which the offshore grid (see Figure ) may be loaded more than the rated power at CP and under which conditions. As the limiting factor in the offshore grid is the 220 kv export cable from the offshore substation up to and including the beach landing, this paper will mainly focus on these cables. 3 Money does grow on turbines Overplanting Offshore Windfarms, Andrew Henderson a.o., Global Offshore Wind Conference 204

4 PAGE 4 of 4 3. Active power transfer through the TenneT offshore grid The offshore grid design will be based on the parameters as listed in Table. Table - TenneT NL offshore grid parameters Grid parameter Value Grid capacity per PPM at offshore CP: 350MW Number of PPM per offshore platform: 2 Reactive power exchange at CP under normal conditions: Max +/- 0, p.u. (+/- 35 Mvar) Nominal voltage level onshore / offshore: 225 / 230kV +/- % To determine if more than 700MW (2 * 350MW) of active power (P) can be transferred through the offshore grid, TenneT makes an assessment of the capability of the 220 kv export cables (next paragraph) based on the parameters shown above. If there is additional capacity found in the design which allows the 220 kv export cables to transfer more than 700MW of active power, TenneT will assure that other grid components will also be capable to transfer this extra power. According to RfG, PPMs will be required to contribute to the primary voltage regulation with more reactive power than shown in Table. It is assumed that these circumstances (Q > 35Mvar or Q < -35Mvar) will be limited in time and therefore will not significantly influence the thermal loading of the cables. 3. Export cable design (220kV) (Status V, dd ) A preliminary 220 kv export cable design study was commissioned by TenneT for a capacity of 700MW in steady state condition according to the IEC Although the exact soil conditions are not yet known, the results of this design show that under a wide range of the thermal resistivity of the soil, typical cable designs are available. Furthermore, within this study dynamic load calculations on the 220 kv export cables have been performed using actual wind data over a measuring period of three and a half years. The calculations have been used to assess possibilities for optimisation of cable dimensioning. The calculations are based on various cable types (variation in conductor type and cross section), a range of thermal resistivity values of the soil and two different installation locations (near offshore platform at one meter under seabed and near shore at three meters under seabed). The results of the dynamic load calculations show that for an optimized cable design (at 700MW design capacity), the transmission of 0% additional active power is allowable, but not guaranteed, provided the following conditions are met: - Voltage at nominal voltage as defined in Table ; - Soil resistivity over the whole trajectory 0,7 K.m/W as a maximum Simulation results show that on a few occasions the maximum allowable conductor temperature would be exceeded and curtailment is necessary (provided that all wind turbine generators are in operation). These

5 PAGE 5 of 4 results are shown in Figure 3. Further analysis of these results show that from the simulated hours, the conductor temperature is 643 hours above 90 C (2,4%). A more detailed forecast on risk of curtailment will be made by TenneT when soil conditions are known and the basic design of the cable is available. Figure 3 - Thermal behaviour of one of the 220 kv export cables (preliminary design) at two thermal resistivity values at the beach with a wind farm installed power of 770MW. 4. Additional calculations on dynamic loading of the export cables 4. Introduction (V ) The duration in hours that a load of 380MW can be transferred through one of the export cables before curtailing of output power of the wind park will take place is dependent on the following factors:. Temperature of the cable before the 380MW limit is reached. This temperature is again dependent on the loading history of the cable the previous hours or even days. This again is directly related to the wind speed; 2. The method of curtailing of which preliminary information is given below; 3. Final soil resistivity values over the complete cable route; 4. Final design of the cable system; 5. Voltage level of the system. A clear and binding answer on the question of duration before curtailing will occur can't be given due to e.g. soil resistivity which will only be determined on a limited set of samples and the power output of the wind farms.

6 PAGE 6 of 4 However, TenneT made dynamic loading capability calculations based on assumptions on wind speeds, soil resistivity and cable design. In this position paper and V 4 some results of these calculations have been given 5. When soil resistivity measurement results (which are part of the geotechnical survey) are available to TenneT, TenneT will update its calculations for the Borssele case which will lead to a better estimate. This update is expected to be finished end of January 206. Within these calculations, the following calculations will be made for the worst case location on the cable route (hot spot):. Time until the conductor reaches 90 C at 380MW load with a starting conductor temperature (t=0) related to a continuous loading of the cable before (t<0) of 350MW and 0MW; 2. Time until the conductor reaches 90 C at 365MW load with a starting conductor temperature (t=0) related to a continuous loading of the cable before (t<0) of 350MW and 0MW. These simulation results (which are still estimates) can be used in the business case calculations of the offshore wind park developers. 4.2 Update based on results of initial geotechnical survey (V3) Analysis of soil data of the initial geotechnical survey In January 206 the final report of the first geotechnical survey has been received by TenneT. The final report ['Factual Report Geotechnical Investigation, '] is available on request via netopzee@tennet.eu. In this survey 5 boreholes are included with a target depth of seabed 6m including measurements of the thermal conductivity of 0cm samples per each m. Most boreholes ended between seabed 5m and seabed 6m. The raw data of this final survey report has been processed where for each borehole the effective thermal resistivity value (G) has been determined on the target depth of burial (DOB) using the conformal mapping methodology as stipulated in [Cigré ELECTRA nr 98, The calculation of the effective external thermal resistance of cables laid in materials having different thermal resistivities, 985]. These effective thermal resistivity (G) values are included in Annex A. The target DOB per route section (which can also be found in the table of Annex A) has preliminary been determined by TenneT based on expected permit requirements and preliminary results of the morphological study and may change during the ongoing route engineering works. Based on the data of the final survey report and Annex A, the areas with the highest thermal resistivity values have been listed in Table 2, where also a short description is included per area. 4 T_Overplanting_PP_v.pdf 5 KNMI measuring pole 32 Europlatform (coordinates 0044; ), measuring dates until , data was converted from 29.m height to a height of 07m.

7 PAGE 7 of 4 Table 2 Areas with highest thermal resistivity values along the Borssele cable route Location Target Effective G Description DOB [m] [K.m/W] Mudflats 3,6 The thermal resistivity which is found in the mudflats area is the result of layers of peat and clay. If the target DOB would be decreased to,2m (land equivalent), the effective resistivity value will decrease to,3 K.m/W. Spijkerplaat 20 0,7 At this moment, an estimate of the effective thermal resistivity on 20 meters has been assumed. Although the target DOB in the Spijkerplaat is now preliminary set at 0m, the morphological study indicates that in the future a coverage up to 20m can be expected and this value has to be taken into account in the cable design. Rede van Vlissingen 6 0,8 At KP-KP3 layers of clay have been identified at the southern part of the cable route. Only limited measurements are available (on route BH92 and off-route BH, BH2), but based on these measurements, clay must be taken into account which results in the given thermal resistivity value. West of Botkil 0,9 In this area clayey soil has been found. Offshore below sand wave 8 0,5 Based on the current survey data, effective thermal resistivity on the bottom of the sand wave is estimated to be 0,5 [K.m/W]. Due to the migration of sand waves and as the cables will be installed at a level below the bottom of these sand waves, cables may in the future be covered by a full sand wave with heights up to 8m. The areas of Table 2 are shown on a map in Figure 4. West of Botkil West slope of Rede van Vlissingen Mudflats Figure 4 Locations of Table 2 on the map

8 PAGE 8 of 4 Update of the dynamic ampacity calculations for 380MW 6 : basis for the calculations Soil conditions In the previous issue of this position paper the following assumption was made on the thermal resistivity along the cable route: - Thermal resistivity over the whole trajectory 0,7 K.m/W as a maximum From Table 2 it can be concluded that this is not the case in three of the areas (Mudflats, Rede van Vlissingen, West of Botkil). Also the future coverage of 20 meters at the Spijkerplaat was not taken into account at that time. Below it is described how the new results are taken into account in the basis for the dynamic ampacity calculations of this update. As currently a) cable/route engineering is still in progress and b) an additional survey is being carried out, this basis for calculation may change significantly. Therefore, this update is only an intermediate update where in some cases no calculations have been done (Mudflats) or calculations for two different scenario's (Spijkerplaat / Rede van Vlissingen). See chapter 8 on when the final update will become available. Mudflats: The thermal resistivity of the mudflats area is so high that backfill must be considered. Backfill is a mitigating measure where thermal resistivity is improved by embedding the cable in sand with a better thermal resistivity value than the original soil. At this moment, the feasibility of this option is under investigation., both technically as permit wise. Therefore, this area has not been taken into account within this update of the dynamic ampacity calculations, but will be taken into account in the final update. However, at this moment it is expected that with the right backfill design, ampacity issues can be mitigated. Spijkerplaat: The value in Table 2 of the effective thermal resistivity of the extreme future burial condition at the Spijkerplaat of 20 meters has been used as the basis for the dynamic ampacity calculations of this update. When results of the current survey (see chapter 8) will become available, the effective thermal resistivity value for this case will be calculated from actual soil measurements and may then change significantly. Therefore, the results of the calculations on this area must be treated as preliminary. As an example, also calculations for an effective thermal resistivity of 0,6 K.m/W have been made. Rede van Vlissingen: At the areas where clay has been found, the target DOB will be decreased to the minimum DOB required by permit which is seabed 3m for this area. For this area both of the following cases have been used as a basis for the dynamic ampacity calculations: - DOB of 6m with effective G-value of 0,8 [K.m/W] (original case of Table 2) - DOB of 3m with effective G-value of 0,7 [K.m/W] (case with following assumptions: a) DOB is decreased, b) trench will be dredged and c) sand will be used for filling the dredged trench). West of Botkil / sand waves: For the offshore part of the cables the West of Botkil area was determined to be the worst case situation based on the (static) ampacity calculations for 350MW and has been used for this update of the dynamic ampacity calculations. 6 In V3 of this position paper, the maximum power of 380 MW is aligned with the development framework for the offshore grid as prescribed by the Ministry of Economic Affairs

9 PAGE 9 of 4 The above scenario's are summarized in Table 3. Table 3 - Calculation scenario's used for update 0 of the dynamic ampacity calculations West of Botkil Rede van Vlissingen Spijkerplaat DOB = m DOB = 3m DOB = 6m DOB = 20m G = 0,9 G = 0,7 G = 0,8 G=0,6 G = 0,7 Scenario 380. Scenario Scenario Scenario Scenario Cable design Load Flow For cable properties which have an impact on the load flow, following values have been assumed for the dynamic ampacity calculations of this update: - Capacitance of cable: 0,22 µf / km (mean value) - Length of cable: 67 km (Borssele Beta, worst case) This results in a full load current (350 MW) at the land station side of 925A and an overload current (380 MW) of 000 A. Also, an additional preloading condition of 67% has been taken into account of 70 A 7. Variance of capacitance will lead to a variance of full load current (350 MW) in the range of 5A around the above stated current of 925 A. For Borssele Alpha with a route which is 7km less, the full load current (350 MW) will be reduced with about 0A. The reactive power compensation at full load is assumed to be 50%/50% onshore and offshore. The reduction of capacitive current in the cable further from platform or land station has not been taken into account in the dynamic ampacity calculations of this update. Losses In the previous versions of this position paper (V / V2), the provided calculation results were based on a general and preliminary 600mm2 AL (aluminium) conductor cable design not related to any specific cable manufacturer. In this update of the dynamic ampacity calculations, the same 600mm2 AL cable design is used as a base case. If static ampacity calculations on 350MW showed that this design would not reach the required static ampacity, a general and preliminary 600mm2 CU (Copper) cable design has been used instead. For both designs, on other cable properties which have an impact on the losses (apart from conductor design), following assumptions have been used: - Armour design: galvanized steel wires with λ2 factor according to IEC (worst case); - Cable (core) lead sheath: common value for thickness of the sheath and λ factor according to IEC (average value) 7 This current is higher than 67% * 925 A as at lower currents, the 50%/50% compensation scheme is shifting towards a higher current at land station side. This higher current in the loadflow has been used here.

10 PAGE 0 of 4 J-tube The J-tube is not found to be a critical part of the cable system. With the base case of 600mm2 AL, the steady state rated current in the J-tube is well above 000 A. This is based on the following conditions: - Wind speed of > 0 m/s; - Solar radiation of 602 W/m2 (max intensity of 000 W/m2 and an angle of 53 ); - Ambient temperature of 30 C. Grid connection limitations With respect to the overloading of the grid connection system, the 380 MW shall be seen as an absolute maximum as other grid components such as the main transformers have much shorter thermal time constants. If more than 380 MW is being generated by the WPO, the curtailment level 3 is applicable as described in chapter 5 (actual curtailment of the power output of the wind park by TenneT). In this case a certain time delay will be taken into account which will be related to the amount of exceedance of the 380 MW limit. Update of the dynamic ampacity calculations for 380MW: calculations results In V2 of the position paper, following was stated (see paragraph 4.): Within these calculations, the following calculations will be made for the worst case location on the cable route (hot spot):. Time until the conductor reaches 90 C at 380MW load with a starting conductor temperature (t=0) related to a continuous loading of the cable before (t<0) of 350MW and 0MW; 2. Time until the conductor reaches 90 C at 365MW load with a starting conductor temperature (t=0) related to a continuous loading of the cable before (t<0) of 350MW and 0MW In this update of the dynamic calculations, only the 380MW case has been studied, but five scenario's instead of one scenario have been assessed as well as three different preloading conditions (instead of two). The preloading condition of 67% / 70 A has been added to reflect an average loading of the cable which may be expected over a long time with a wind farm loading profile. Also, a preloading time of one year has been used for the 67% and 00% conditions to assure a starting temperature which is nearby the steady state conductor temperature when calculated according the IEC The dynamic calculations for this update have been made according to the IEC

11 PAGE of 4 The results of the calculations are given in Table 4 where the time until the conductor reaches 90 C is stated in hours. Table 4 - Time (in hours) for conductor to reach 90 C at 000 A with three preloading conditions for five scenario's % Preloading # of Preload I days [A] Scenario 380. Scenario Time to reach 90 C [hours] Scenario Scenario Scenario % n/a > 8760 > % % West of Botkil Rede van Vlissingen Spijkerplaat DOB = m DOB = 3m DOB = 6m DOB = 20m G = 0,9 G = 0,7 G = 0,8 G=0,6 G = 0,7 For the scenario's following conditions have been used: - Scenario 3 and 5: 600mm2 CU conductor - Scenario, 2 and 4: 600mm2 AL conductor - Scenario, 2: ambient temperature 5 C - Scenario 3, 4,5: ambient temperature 0 C - Overloading: 380MW, Current I [A]: 000 A 5. Export cable load management In general, TenneT identifies three levels in the export cable load management process:. Alignment of the wind park owner's (WPO) generation forecasts to dynamic cable loading capabilities; 2. Actual curtailment of the power output of the wind park by the WPO; 3. Actual curtailment of the power output of the wind park by TenneT. Ad It is the responsibility of the WPO to align its forecasts to possible curtailment of the wind park power output due to the temperature limit of the export cables (only if wind park power output is higher than the guaranteed 350 MW). To facilitate this alignment process, TenneT will provide: a) calculation results as described above (updated on the as-built situation); b) the actual cable conductor temperature measurements (data format and frequency to be defined in a later stage).

12 PAGE 2 of 4 Ad 2 If the conductor temperature will increase above a certain threshold value (value to be determined per project), WPO will receive a warning signal from TenneT. WPO shall start at that moment (at the latest) with the curtailment of the wind park power output, down to 350MW. If this curtailment is not started or is not sufficient and conductor temperature will increase above a second threshold value (close to but below 90 degrees Celsius, to be determined per project), WPO will receive a second and final warning signal from TenneT. Immediately after this second signal has been released, TenneT has the right to proceed to the third level as described below. The warning signals are considered to be the official legally binding information provided by TenneT to the WPO. The cable conductor temperature measurements as described under level are provided by TenneT as an extra service and will be for information only. Ad 3 When the second warning signal has been released, WPO shall immediately reduce the power output to a maximum of 350 MW. TenneT will at that time monitor conductor temperature and power output continuously. If the reduction of power by the WPO is not sufficient, TenneT will have the right to curtail under 350MW by switching off one of the strings of the wind park without any further notice. With the three levels described above, an export cable load management process has been introduced that enables the WPO to manage its generation forecasts and actual power output curtailment while at the other hand it is assured that the export cable conductor temperature will never increase above 90 degrees Celsius. 6. Position of TenneT Above considerations lead TenneT to the following position: TenneT is inclined towards allowing the PPMs to transmit 8% above their rated power (350MW), which is 30MW extra, with the requirement for PPM's to curtail their produced power, in case the 220 kv export cables reach their maximum allowable temperature limits 8. Details on curtailment of the PPMs will be addressed to in the 'Customer Connection Agreements (ATO)'. The calculations results of paragraph 4.2 are only valid for Borssele. For the Hollandse Kust (Zuid) tender, TenneT will give an update based on specific Hollandse Kust (Zuid) soil data. TenneT has decreased the allowed additional rated power from 0% (V2) to 8% (V3) in order to align this allowable addition with the development framework for the offshore grid as prescribed by the Ministry of Economic Affairs. 8 Operational limits of sea and land cables will be monitored continuously by temperature sensing systems.

13 PAGE 3 of 4 7. Impact on cost At this point in time the impact on costs cannot be analysed quantitatively, as this requires detailed knowledge (assumptions) on both wind farm layout, turbine choice and dynamic loading strategies. 8. Further updates (status as of ) At this moment a second survey is being carried out for additional information on thermal resistivity due to the following reasons: - Determination of thermal resistivity in highly mobile areas (Spijkerplaat, Nollenplaat) up to a depth of 0m (Nollenplaat) and 20m (Spijkerplaat); - Better assessment of the other areas listed in Table 2: West of Botkil and Rede van Vlissingen. The results of this additional survey will be used for a final update of this position paper. Also, 365 MW scenario's will be included in that update. This update is expected first half of April 206.

14 PAGE 4 of 4 9. Annex A: Soil resistivity analysis - Offshore cable route from landfall to Borssele Alpha and Beta Table with effective soil resistivity values.

15 Nearshore borehole locations Subsection From KP to KP km km m Northern slope Honte 0,7,3 North slope Honte to shore Honte Navigational Channel,3,8 Honte fairway Southern slope Honte,8 3,0 Slope fairway to Spijkerplaat -0m Spijkerplaat 3,0 6, Spijkerplaat from LAT-0m to -0m Rede van Vlissingen 6,,6 Between LAT-0m Spijkerplaat to Rede v. Vl Rede van Vlissingen 6,,6 Rede van Vlissingen Section Navigational channel Westerschelde / South of Nollenplaat,6 3,6 Remainder west slope Rede v.vlis-nolleplaat Nollenplaat 3,6 6,6 Nolleplaat Deurloo 6,6 27,8 Deurloo Rassen 27,8 32,3 Rassen Kaloo to LAT -0m 3) 32,3 35,6 Between Rassen and LAT-0 m length Depth of installation Point-ID Easting Nording Comment Thermal resistivity [K.m/W] Remarks 3 8-PC ,39 Conformal mapping 3 9-PC ,62 Conformal mapping 3 20-PC ,34 Conformal mapping 3 7-PC ,44 Average <3m 3 07-VC ,70 Average. Meas <2,2m VC ,70 Average. Meas <,5m VC ,45 Conformal mapping 3 08-VC Offroute but possibly required 0,65 Average. Meas <,7m 3 09-VC ,47 Conformal mapping VC ,53 Conformal mapping Average < 5,3 m, 0 066A-VC Effective G value on 5m 0,45 No samples>5m Average < 5,6 m, 0 076a-PC Effective G value on 6m 0,48 No samples>5m Average < 5,0 m, VC Effective G value on 6m 0,43 No samples>5m VC Effective G value on 6m 0,49 Conformal mapping 0 Average < 5,6 m, 02-PC Effective G value on 6m 0,45 No samples>5m 0 Average < 5,6 m, 03-PC Effective G value on 6m 0,43 No samples>5m 0 Offroute but possibly required Average < 5,6 m, 04b-PC Effective G value on 6m 0,45 No samples>5m 0 Average < 5,6 m, 0b-PC Effective G value on 6m 0,50 No samples>5m 0 Average < 5,6 m, 00-PC Effective G value on 6m 0,47 No samples>5m 0 06-VC Effective G value on 5m 0,46 No samples > 5m VC ,43 Average VC ,46 Average 6 3-VC ,45 Average VC ,48 Conformal mapping Borehole is off-route. It is not clear if layers of 6 2-VC clay extend to actual cable route 0,76 Conformal mapping VC ,45 Conformal mapping VC ,60 Conformal mapping VC ,5 Conformal mapping VC ,44 Average VC ,40 Conformal mapping VC ,4 Average <4m 3 085a-VC ,40 Average <4m VC ,4 Average <4m VC ,4 Average <4m 3 05-VC ,64 Conformal mapping VC ,4 Conformal mapping VC ,47 Conformal mapping VC ,48 Conformal mapping VC ,5 Conformal mapping VC ,67 Conformal mapping VC ,52 Conformal mapping VC ,45 Conformal mapping VC ,53 Conformal mapping VC ,37 Conformal mapping VC ,59 Conformal mapping VC ,46 Average 3 04-VC ,63 Conformal mapping VC ,39 Conformal mapping VC Effective G value for 3m 0,43 Average <2, VC ,43 Conformal mapping VC ,42 Conformal mapping VC ,7 Conformal mapping VC ,4 Conformal mapping VC ,55 Conformal mapping VC ,62 Conformal mapping VC ,49 Conformal mapping

16 Offshore borehole locations Section Subsection From KP Depth of length installation to KP km km m Point-ID Easting Nording Comment Thermal resistivity [K.m/W] Remarks 2 LAT -0m up to West Rond Route 3) 35,606 46,79 West of Botkil LAT -0m up to West Rond Route 3) East slope Steendiep LAT -0m up to West Rond Route 3) Steendiep LAT -0m up to West Rond Route 3) Rabsbank West Rond Route 3) 46,79 50,7 Shipping route over West-Rabsbank West Rond Route up to platform location 3) West Rond Route up to platform location 3) West Rond Route up to platform location 3) West Rond Route up to platform location 3) Between platform Alpha and platform Beta 3) 50,7 67,469 West slope Rabsbank Sandwave area Buitenbanken Sandwave area ,469 67,469 Area just before Platform Beta VC Layer of clay,,2 meter (0,2-,4m) 0,83 Conformal mapping 03-VC ,66 Conformal mapping 094-VC No wet density samples analyzed n.n. Value at -m 030-VC ,42 Value at -m 029-VC ,54 Value at -m 028-VC ,50 Value at -m First layer (0,8m): sand with high resistivity value (0,8). Data from DB/calculation, no 027-VC measurement 0,6 Conformal mapping 026-VC ,35 Value at -m 025-VC ,47 Value at -m 024-VC ,45 Value at -m 099-VC ,32 Value at -m 073A-VC On two depths (possibly sand wave) 0,56 Average of first 2 layers On two depths (possibly sand wave) 0,49 Conformal mapping 023-VC On two depths (possibly sand wave) 0,45 Value at -m On two depths (possibly sand wave) 0,42 Conformal mapping 022-VC ,37 Value at -m 02-VC ,4 Value at -m 020-VC ,39 Value at -m 09-VC ,39 Value at -m 08-VC ,5 Value at -m 07-VC ,44 Value at -m 06A-VC ,39 Value at -m 05-VC Bottom of sand wave (-34,7) 0,49 Conformal mapping 095-Vca Bottom of sand wave (-33,8m) 0,55 Conformal mapping Average <2,5m ,38 No meas >-2,5, 04-VC Average <4m On two depths; In between sand wave 0,38 No meas >-2,5, 03-VCa On two depths; Near sand wave 0,43 Value at -m ,5 Conformal mapping 02-VCa On two depths; Near sand wave 0,45 Value at -m ,4 Average <3,6m Average<2m 096-VCa ,40 No meas.<-2m On two depths; Top of sand wave. Depth Average<2m of hole only 2,5m though. 0,40 No meas.<-2m 0-VC ,34 Value at -m 00-VC ,4 Value at -m 009-VC ,37 Average <2,5m, ,37 Average <2,5m ,40 Average <2,5m 008-VC 4,5 In between sand wave (-25,5m) Average <3,5m ,42 No meas <-3,5 m 007-VC ,45 Average <2,8m In between sand wave (-24m) 0,45 Average <2,8m ,48 Average of first 2 layers,5 006-VC Near bottom of sand wave 0,48 Average of first 2 layers 2, ,58 Conformal mapping 005-VC Near bottom of sand wave 0,42 Value at -m (one meas. disregard ,47 Conformal mapping 004-VC ,40 Value at -m In between sand wave 0,40 Average <4m 003-VC Bottom of sand wave 0,45 Value at -m ,45 Conformal mapping 002-VC Bottom of sand wave 0,40 Value at -m ,48 Average<3m 2 00-VC In between sand wave 0,48 Average<3m In between sand wave 0,44 Average<4m

DECISION 1 SCOPE AND CONSIDERATIONS... 2

DECISION 1 SCOPE AND CONSIDERATIONS... 2 MEMORANDUM TO Windfarm developers FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed: Frank de Vries 19.09.2017

More information

DECISION 1 SCOPE AND CONSIDERATIONS... 2

DECISION 1 SCOPE AND CONSIDERATIONS... 2 MEMORANDUM TO Windfarm developers DATE November 02, 2018 FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) v2 DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed:

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.1 Voltage level Filename ONL15-058-T1_Voltage level_pp_v1 Version 1 - release for Expert

More information

TenneT. Stakeholder engagement and Consultation Process OWFs ONL Michiel Müller / Rob van der Hage. Expert Meeting,

TenneT. Stakeholder engagement and Consultation Process OWFs ONL Michiel Müller / Rob van der Hage. Expert Meeting, TenneT ONL 15-102 Stakeholder engagement and Consultation Process OWFs Expert Meeting, 18.03.2015, Arnhem Michiel Müller / Rob van der Hage Welcome 2 Introduction and explanation on stakeholder process

More information

TenneT. Offshore NL Interface Management Inventory of WPO/TenneT Interface Risks. TenneT NL-O Business Consolidation

TenneT. Offshore NL Interface Management Inventory of WPO/TenneT Interface Risks. TenneT NL-O Business Consolidation TenneT Offshore NL Interface Management Inventory of WPO/TenneT Interface Risks 22.06.2016, Arnhem TenneT NL-O Business Consolidation Stay tuned. Safety first! For your own safety, please be aware of the

More information

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee);

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee); Ministerial Order issued by the Minister of Economic Affairs and Climate Policy dated No. WJZ / 89976, containing specific rules for permitting offshore wind energy permits for Wind Farm Sites III and

More information

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee);

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee); Ministerial Order issued by the Minister of Economic Affairs dated 3 October 27 No. WJZ / 722295, containing specific rules for permitting offshore wind energy permits for Wind Farm Sites I and II of the

More information

Optimal wind farm power density analysis for future offshore wind farms

Optimal wind farm power density analysis for future offshore wind farms Optimal wind farm power density analysis for future offshore wind farms ECN cost model evaluation for large wind farms B.H. Bulder E.T.G. Bot G. Bedon Summary Although the information contained in this

More information

A New Connection Concept to Connect an Offshore Wind Park to an Onshore Grid

A New Connection Concept to Connect an Offshore Wind Park to an Onshore Grid A New Connection Concept to Connect an Offshore Wind Park to an Onshore Grid Marc VAN DYCK, Shantanu DASTIDAR and Kristof VAN BRUSSELEN CG Holdings Belgium NV Systems Division, Mechelen, Belgium Tel: +32

More information

Factors Affecting Current Ratings for Underground and Air Cables

Factors Affecting Current Ratings for Underground and Air Cables Factors Affecting Current Ratings for Underground and Air Cables S. H. Alwan, J. Jasni, M. Z. A. Ab Kadir, N. Aziz Abstract The aim of this paper is to present a parametric study to determine the major

More information

Cluster Design Toolbox. Cluster Design Workshop, 15/04/2016

Cluster Design Toolbox. Cluster Design Workshop, 15/04/2016 Cluster Design Toolbox Cluster Design Workshop, 15/04/2016 Layout 1 Idea and Concept Integrated approach 2 3 Architecture Toolbox compartments Architecture of the toolbox Interaction with computation models

More information

New designed XLPE-insulated cables substituting paper-insulated pipe type cables

New designed XLPE-insulated cables substituting paper-insulated pipe type cables MODERN CABLE SYSTEMS IN STEEL PIPES New designed XLPE-insulated cables substituting paper-insulated pipe type cables Volker AUE, Nexans Deutschland Industries, Germany, Volker.Aue@nexans.com Wilfried ROSEBROCK,

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

Net Project Value Assessment of Korean Offshore Floating Wind Farm using Y-Wind Semi Platform

Net Project Value Assessment of Korean Offshore Floating Wind Farm using Y-Wind Semi Platform 1016_DA2_SE1_05 Net Project Value Assessment of Korean Offshore Floating Wind Farm using Y-Wind Semi Platform Steffen Shelley*, Sung Youn Boo* and Daejun Kim* *VL Offshore LLC, Houston, USA 1. Introduction

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

Kentish Flats Offshore Wind Farm

Kentish Flats Offshore Wind Farm Kentish Flats Offshore Wind Farm A pure spot on the Map of the World Kentish Flats Offshore Wind Farm features 30 wind-powered turbines each with a nominal rated capacity of 3 MW making a net capacity

More information

The Netherlands Offshore wind hub

The Netherlands Offshore wind hub The Netherlands Offshore wind hub Opportunities for green hydrogen and electrification of industry Mel Kroon, CEO TenneT WindDays 2018 Strategy 2002: strenghten and build One strong, independent transmission

More information

NPS/002/023 Technical Specification for 132kV Power Cables.

NPS/002/023 Technical Specification for 132kV Power Cables. Version:- 2.2 of Issue:- June 09 Page 1 of 11 NPS/002/023 Technical Specification for 132kV Power Cables. 1. Purpose The purpose of this document is to detail the technical requirements of Northern Powergrid

More information

Fact Sheet. Brief Description of the Planned Offshore Wind Farm Witte Bank Updated: February 27, 2015

Fact Sheet. Brief Description of the Planned Offshore Wind Farm Witte Bank Updated: February 27, 2015 Fact Sheet Brief Description of the Planned Offshore Wind Farm Witte Bank Updated: February 27, 2015 FACT SHEET Seite 2 INHALT 1. Preliminary Remarks... 3 2. Offshore Wind Farm Witte Bank, German EEZ,

More information

NPS/002/020 Technical Specification for 11 & 20kV Power Cables

NPS/002/020 Technical Specification for 11 & 20kV Power Cables Version:- 3.1 of Issue:- Nov - 09 Page 1 of 11 NPS/002/020 Technical Specification for 11 & 20kV Power Cables 1. Purpose The purpose of this document is to detail Northern Powergrid (the Company) requirements

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Wind Power in Denmark Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Outline Status on wind power deployment and large scale integration Support system and consent

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

TSOs, taking into account the following: Whereas

TSOs, taking into account the following: Whereas All TSOs proposal for a common grid model methodology in accordance with Articles 67(1) and 70(1) of Commission Regulation (EU) 2017/1485 of 02 August 2017 establishing a guideline on electricity transmission

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

CLNR Trial Analysis Real-Time Thermal Rating Underground Cables

CLNR Trial Analysis Real-Time Thermal Rating Underground Cables CLNR Trial Analysis Real-Time Thermal Rating Underground Cables DOCUMENT NUMBER CLNR-L131 AUTHORS Peter Davison, Newcastle University ISSUE DATE 22/12/2014 University of Durham, and EA Technology Ltd,

More information

SPECIFICATION FOR FRLS POWER CABLES

SPECIFICATION FOR FRLS POWER CABLES SPECIFICATION FOR FRLS POWER CABLES 1.0 SCOPE This specification cover the technical requirements of design, manufacture, testing and delivery to site of Power Cables of 1100V grade with FRLS PVC Sheathed,

More information

Background and Project Description. Chapter 05: Description of Development

Background and Project Description. Chapter 05: Description of Development Background and Project Description Chapter 05: Description of Development Background and and Project Project Description Description DESCRIPTION OF DEVELOPMENT OF Chapter Chapter Contents Contents...

More information

Wind Farm Performance on the Grid: Perception and Reality

Wind Farm Performance on the Grid: Perception and Reality Wind Farm Performance on the Grid: Perception and Reality WindVAR and LVRT Data and Graphs provided by Nicholas W. Miller GE Energy, Energy Consulting 1 GE Energy Wind Energy Grid Performance: A Perception

More information

TECHNICAL SPECIFICATION FOR L. T. XLPE POWER CABLE

TECHNICAL SPECIFICATION FOR L. T. XLPE POWER CABLE TECHNICAL SPECIFICATION FOR L. T. XLPE POWER CABLE SEAL & SIGNATURE OF THE TENDERER PAGE 1 OF 14 TECHNICAL SPECIFICATION FOR LT XLPE POWER CABLES (SPECIFICATION NO.MM/I/LTXLPE/2006) 1. SCOPE: The specification

More information

score The knowledge and This wind farm (these wind farms) has (have) a (joint) capacity of less than 250 MW 0

score The knowledge and This wind farm (these wind farms) has (have) a (joint) capacity of less than 250 MW 0 Criterion Sub-criterion Qualitative criteria Assessment criteria score A The knowledge and the parties involved. the party or parties responsible for project management (have) been responsible for the

More information

CONSULTATIONS TECHNICAL GUIDELINE. HVDC extruded cable

CONSULTATIONS TECHNICAL GUIDELINE. HVDC extruded cable UNIT, BU1SNESS AREA OUR REFERENCE TR14-02-2E DATE 2018-01-24 CONSULTATIONS TECHNICAL GUIDELINE EDITION 1 APPROVED HVDC extruded cable This technical guideline describes the basic design and construction

More information

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date Description

More information

Subsidies Dutch offshore wind parks How low can you go? Energy Law Group 22 September 2017, Warsaw

Subsidies Dutch offshore wind parks How low can you go? Energy Law Group 22 September 2017, Warsaw Subsidies Dutch offshore wind parks How low can you go? Energy Law Group 22 September 2017, Warsaw Developments in offshore wind energy The Netherlands are lagging behind in terms of renewable target Target

More information

LSI Toolbox. Heidi Roberts.

LSI Toolbox. Heidi Roberts. LSI Toolbox Heidi Roberts hroberts@abpmer.co.uk Name of presentation Integration of LSI into MSP and associated SEA Practical Toolbox for Practitioners on LSI Easily applied within any admin. or governance

More information

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events A. Introduction 1. Title: Transmission System Planned Performance for Geomagnetic Disturbance Events 2. Number: TPL-007-1 3. Purpose: Establish requirements for Transmission system planned performance

More information

Compact Transformers for Offshore Wind Power Plants Applications

Compact Transformers for Offshore Wind Power Plants Applications International Conference on Renewable Energies and Power Quality (ICREPQ 14) Cordoba (Spain), 8 th to 10 th April, 2014 Renewable Energy and Power Quality Journal (RE&PQJ) ISSN 2172-038 X, No.12, April

More information

MEMO CONCERNS. DISTRIBUTION For general information ELECTRONIC FILE CODE AUTHOR(S) DATE. 14F013 9

MEMO CONCERNS. DISTRIBUTION For general information ELECTRONIC FILE CODE AUTHOR(S) DATE. 14F013 9 MEMO CONCERNS PROJECT MEMO SINTEF Energy Research Address: NO-7465 Trondheim, NORWAY Reception: Sem Sælands vei 11 Telephone: +47 73 59 72 00 Telefax: +47 73 59 72 50 Direct Electrical Heating System for

More information

MINUTES OF MEETING. See attendance list Filename MOM_EM_ _v1. Pages 15. QUALITY CONTROL Prepared: A. Ritzen

MINUTES OF MEETING. See attendance list Filename MOM_EM_ _v1. Pages 15. QUALITY CONTROL Prepared: A. Ritzen MINUTES OF MEETING STAKEHOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Minutes of Meeting Meeting date 24.09.2015 Meeting place Bilderberg hotel, Wolfheze Subject Expert Meeting Present See attendance

More information

Cost reduction in offshore deployment

Cost reduction in offshore deployment Cost reduction in offshore deployment Danielle Lane Head of Portfolio & Transactions Offshore 27 September 2018 1 This is Vattenfall Basic facts One of Europe s largest producers of electricity and heat

More information

Note on technology costs for offshore wind farms and the background for updating CAPEX and OPEX in the technology catalogue datasheets

Note on technology costs for offshore wind farms and the background for updating CAPEX and OPEX in the technology catalogue datasheets Note on technology costs for offshore wind farms and the background for updating CAPEX and OPEX in the technology catalogue datasheets The winning price in the tenders for the offshore wind farms in Denmark

More information

SIEA LUNGGA POWER STATION RETAINING WALL

SIEA LUNGGA POWER STATION RETAINING WALL SIEA LUNGGA POWER STATION RETAINING WALL 1. Glossary In this scope of work the following abbreviations and definitions apply. Term AS 3000 AS 3600 AS 3700 Boundary Lines AS 4678 Brick Works Contract Contractor

More information

7 Project Description

7 Project Description 7 Project Description 7.1 Project Promoter The CEB (Green energy) Co. Ltd. is a private company fully owned by the Central Electricity Board incorporated on 11 October 2016 to promote the generation of

More information

GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK

GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK Anna KULMALA Sami REPO Jouni PYLVÄNÄINEN VTT Finland Tampere University of Techlogy

More information

26/35kV Copper XLPE Insulation Electric Cable

26/35kV Copper XLPE Insulation Electric Cable 26/35kV Copper XLPE Insulation Electric Cable Specifications 1.1~35kv XLPE insulated power cable 2.Standard: IEC,VDE,BS,UL,AS/NZS Black PVC sheath XLPE insulated armored copper power cable YJV22 YJV32

More information

Note on technology costs for offshore wind farms and the background for updating CAPEX and OPEX in the technology catalogue datasheets

Note on technology costs for offshore wind farms and the background for updating CAPEX and OPEX in the technology catalogue datasheets Note on technology costs for offshore wind farms and the background for updating CAPEX and OPEX in the technology catalogue datasheets The winning price in the tenders for the offshore wind farms in Denmark

More information

Cable Details and Grid Connection Statement. March 2014

Cable Details and Grid Connection Statement. March 2014 March 2014 Cable Details and Grid Connection Statement Pursuant to Regulation 6(1)(b)(i) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 Application reference:

More information

SENSE - Self Erecting Nacelle and Service System Estimated Cost Savings

SENSE - Self Erecting Nacelle and Service System Estimated Cost Savings - Self Erecting Nacelle and Service System Estimated Cost Savings 1. Modelling Work This document sets out the preliminary final results from the combined cost and marine operations modelling undertaken

More information

L1-CHE-SPE-171 TECHNICAL SPECIFICATION FOR ELECTRIC CABLE

L1-CHE-SPE-171 TECHNICAL SPECIFICATION FOR ELECTRIC CABLE Engineering Specification Electrical Networks L1-CHE-SPE-171 TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM OR COPPER CONDUCTOR 3.8/6.6kV XLPE INSULATED WITHOUT METALLIC SCREEN PVC Version:

More information

POWER HUB AS AN ISLAND 17 NOVEMBER 2017

POWER HUB AS AN ISLAND 17 NOVEMBER 2017 POWER HUB AS AN ISLAND 17 NOVEMBER 2017 Executive Summary Reduction of the total system cost is essential to facilitate large scale offshore wind and interconnection capacity deployment and all options

More information

CHAPTER 1 OFFSHORE RENEWABLE ENERGY DEVELOPMENT IN THE BELGIAN PART OF THE NORTH SEA

CHAPTER 1 OFFSHORE RENEWABLE ENERGY DEVELOPMENT IN THE BELGIAN PART OF THE NORTH SEA CHAPTER 1 OFFSHORE RENEWABLE ENERGY DEVELOPMENT IN THE BELGIAN PART OF THE NORTH SEA RUMES Bob 1 & BRABANT Robin 2 Royal Belgian Institute of Natural Sciences (RBINS), Operational Directorate Natural Environment

More information

Integrated SET Plan Actions No.1&2. ISSUES PAPER on OCEAN ENERGY

Integrated SET Plan Actions No.1&2. ISSUES PAPER on OCEAN ENERGY EUROPEAN COMMISSION RTD - Energy ENER - Renewables, R&I, Energy Efficiency JRC Institute for Energy and Transport SET Plan Secretariat Integrated SET Plan Actions No.1&2 ISSUES PAPER on OCEAN ENERGY Purpose

More information

Integration of Renewable Energy Sources in the Electricity System - Grid Issues -

Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Brussels, 30 March 2005 Background At European and national level mid-term plans exist to increase the share of electricity

More information

Prof. Jean-Louis Lilien & Huu-Minh Nguyen University of Liège Belgium

Prof. Jean-Louis Lilien & Huu-Minh Nguyen University of Liège Belgium LARGE PENETRATION OF DISTRIBUTED PRODUCTIONS: DYNAMIC LINE RATING AND FLEXIBLE GENERATION, A MUST REGARDING INVESTMENT STRATEGY AND NETWORK RELIABILITY. Peter Schell & Bertrand Godard Vanessa De Wilde

More information

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms In 2010, offshore wind farms accounted for 9.5% of the overall

More information

D e s i g n a n d c o n f i g u r a t i o n s t a n d a r d

D e s i g n a n d c o n f i g u r a t i o n s t a n d a r d D e s i g n a n d c o n f i g u r a t i o n s t a n d a r d 132 kv 400 kv Installation of underground AC cables in urban areas EDS-0074 Document title EDS-0074 Rev 0 Installation of underground AC cables

More information

Lowering the production costs of offshore wind energy to a competitive level

Lowering the production costs of offshore wind energy to a competitive level Lowering the production costs of offshore wind energy to a competitive level Lisbon November 2013 www.ecn.nl Energy Center of the Netherlands Experience with wind since 1974 WMC EWTW Q7 OWEZ 2 test locations

More information

ober Oct 10 y uesdat

ober Oct 10 y uesdat Tuesday 10 October Future forecast: reading the map Leo de Vrees Senior advisor Dutch Ministry of Infrastructure & Environment Part of: Powered by: Created and produced by: Challenges with regard to North

More information

Town of Babylon Cost Accounting: Long Island Offshore Wind Project

Town of Babylon Cost Accounting: Long Island Offshore Wind Project Town of Babylon Cost Accounting: Long Island Offshore Wind Project Steve Bellone, Supervisor Dorian Dale, Energy Director Babylon s Cost Accounting: Long Island Offshore Wind Project (LIOWP) relied, for

More information

OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH

OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH SUSTAINABLE EUROPEAN INFRASTRUCTURE FINANCING UNDER THE CONDITIONS OF COMPETITION, ENVIRONMENTAL

More information

Maximum Admissible active power reduction at low frequencies

Maximum Admissible active power reduction at low frequencies Maximum Admissible active power reduction at ENTSO-E guidance document for national implementation for network codes on grid connection 31 January 2018 Table of Contents DESCRIPTION...3 Code(s) & Article(s)...3

More information

Demarcation Points. Example 1

Demarcation Points. Example 1 Example 1 control of distribution equipment including connection assets, ending at the customer. REVISION 03 14/04/10 Example 2 ROAD The transformer is normally at the property line. If the transformer

More information

From close to the coast to farshore E.ON s Experience with Offshore Wind Energy Projects

From close to the coast to farshore E.ON s Experience with Offshore Wind Energy Projects From close to the coast to farshore E.ON s Experience with Offshore Wind Energy Projects Dr. Frank Mastiaux, CEO Eufores-Conference, 16th of September 2010 Offshore wind energy: more than wind onshore

More information

Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities

Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities Content Introduction... 2 Procedural Guidelines... 2 1. Scope of recommended procedural guidelines... 3 2.

More information

Walney Extension Offshore Wind Farm

Walney Extension Offshore Wind Farm WALNEY EXTENSION OFFSHORE WIND FARM Walney Extension Offshore Wind Farm Statement of Common Ground Between: 1. DONG Energy Walney Extension (UK) Limited 2. Whale and Dolphin Conservation In relation to

More information

Independent Report ASSESSMENT OF TECHNICAL ALTERNATIVES TO STRENGTHEN THE 400 KV TRANSMISSION GRID

Independent Report ASSESSMENT OF TECHNICAL ALTERNATIVES TO STRENGTHEN THE 400 KV TRANSMISSION GRID Independent Report ASSESSMENT OF TECHNICAL ALTERNATIVES TO STRENGTHEN THE 400 KV TRANSMISSION GRID DECEMBER 2018 PUBLIC Independent Report ASSESSMENT OF TECHNICAL ALTERNATIVES TO STRENGTHEN THE 400 KV

More information

HORNS REV 1 OFFSHORE WIND FARM

HORNS REV 1 OFFSHORE WIND FARM HORNS REV 1 OFFSHORE WIND FARM Mankind has been making use of wind power for thousands of years. The current trend is moving away from small groups of land-based wind turbines to larger offshore wind farms.

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT. Location:

REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT. Location: REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT Location: Dist.: Jodhpur Rajasthan, INDIA Latitude 27.32 & Longitude 71.54 Elevation: 151 meter GENERAL INFORMATION AND TECHNICAL SPECIFICATION

More information

Chapter. Background and Project Description DESCRIPTION OF DEVELOPMENT. Contents

Chapter. Background and Project Description DESCRIPTION OF DEVELOPMENT. Contents Contents Contents... i List of Tables... iii List of Figures... iii Abbreviations and Acronyms... v 7 Description of Development... 1 7.1 Introduction... 1 7.2 Development Area... 3 7.2.1 Location and

More information

Network of offshore wind farms connected by gas insulated transmission lines?

Network of offshore wind farms connected by gas insulated transmission lines? Network of offshore wind farms connected by gas insulated transmission lines? Anja Drews, ForWind, Carl von Ossietzky Universität Oldenburg, Institute of Physics, Carl-von- Ossietzky Str. 9-11, 29129 Oldenburg,

More information

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual [Type text] Heber Light & Power Developers & Excavators Electrical Service Requirements Manual May 2017 E.1.1 - GENERAL REQUIREMENTS PURPOSE This section was prepared to aid developers, contractors, engineers

More information

Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland

Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland 16 th September 2015 Overview 2 EirGrid s Role EirGrid is the Transmission System Operator

More information

Wind Power Development on Port of Corpus Christi Authority Property

Wind Power Development on Port of Corpus Christi Authority Property Wind Power Development on Port of Corpus Christi Authority Property Prepared for American Association of Port Authorities Harbors, Navigation and Environment Committees Seminar May 1, 2012 San Francisco,

More information

Transmission Losses Report 2015

Transmission Losses Report 2015 SP Energy Networks October 2015 Transmission Losses Report 2015 1. INTRODUCTION Special condition 2K of SPT s transmission licence requires SPT to publish an annual transmission losses report detailing

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION IEC/TS 62344 Edition 1.0 2013-01 colour inside Design of earth electrode stations for high-voltage direct current (HVDC) links General guidelines INTERNATIONAL ELECTROTECHNICAL

More information

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs RE integration workshop, Chennai January 23, 2018 Zakir H Rather, IIT Bombay Email: zakir.rather@iitb.ac.in Wind

More information

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008 ALL ISLAND GRID STUDY STUDY OVERVIEW January 2008 1 Study Overview The All Island Grid Study is the first comprehensive assessment of the ability of the electrical power system and, as part of that, the

More information

11. TRANSMISSION AND INTERCONNECTION FACILITIES

11. TRANSMISSION AND INTERCONNECTION FACILITIES 11. TRANSMISSION AND INTERCONNECTION FACILITIES Three transmission line corridors have been investigated in this report, but no route (or routes) has been recommended. One of the five possible configurations

More information

SCHEDULE ' A ' TECHNICAL SPECIFICATION FOR L.T.PVC POWER AND CONTROL CABLES FOR DISTRIBUTION NETWORK IN MAHARASHTRA

SCHEDULE ' A ' TECHNICAL SPECIFICATION FOR L.T.PVC POWER AND CONTROL CABLES FOR DISTRIBUTION NETWORK IN MAHARASHTRA SCHEDULE ' A ' TECHNICAL SPECIFICATION FOR L.T.PVC POWER AND CONTROL CABLES FOR DISTRIBUTION NETWORK IN MAHARASHTRA (SPECIFICATION NO.MM/I/LTPVC & CONTROL/2006) MAHARASHTRA STATE ELECTRICITY DISTRIBUTION

More information

Paimpol-Brehat tidal demonstrator project. Charles Bodel, EDF R&D Bruxelles (June 16th, 2016)

Paimpol-Brehat tidal demonstrator project. Charles Bodel, EDF R&D Bruxelles (June 16th, 2016) Paimpol-Brehat tidal demonstrator project Charles Bodel, EDF R&D Bruxelles (June 16th, 2016) Project key objectives Strategy Contribute to the building of a new industrial sector contributing to green

More information

A. Behaviour of the Wind

A. Behaviour of the Wind Preliminary Assessment of the Potential for Wind Farm Development in Southern Sri Lanka Supervised by: Nishantha Nanayakkara, Yushan De silva, Amila Fernando, Chamila Fernando, Nawoda Gunawardhana, Sandika

More information

10-SDMS-02 SPECIFICATIONS FOR BARE COPPER CONDUCTORS

10-SDMS-02 SPECIFICATIONS FOR BARE COPPER CONDUCTORS SPECIFICATIONS FOR BARE COPPER CONDUCTORS This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Page 1.0 SCOPE 3 2.0 CROSS REFERENCES 3 3.0 APPLICABLE

More information

CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS

CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS 108 CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS 6.1 INTRODUCTION Planning and development of power system infrastructure to cater to the needs of the people is

More information

Conclusion Power Grid Development Plan 2025, Version 2015, 2 ND Draft

Conclusion Power Grid Development Plan 2025, Version 2015, 2 ND Draft Seite 1 von 11 Conclusion Power Grid Development Plan 2025, Version 2015, 2 ND Draft Presented for the first time using its target year in the title and not the year of publication, the Grid Development

More information

Galloper Wind Farm Project Environmental Statement Chapter 28: Electric and Magnetic Fields October 2011 Document Reference

Galloper Wind Farm Project Environmental Statement Chapter 28: Electric and Magnetic Fields October 2011 Document Reference Galloper Wind Farm Project Environmental Statement Chapter 28: Electric and Magnetic Fields October 2011 Document Reference 5.2.28 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Environmental

More information

Explanatory notes to the import and export of electricity

Explanatory notes to the import and export of electricity Onderwerp Explanatory notes to the import and export of electricity Explanatory notes to the import and export of electricity Facts, TenneT s view and answers to key questions: - How do imports and exports

More information

Rampion Offshore Wind Farm Frequently Asked Questions (FAQs)

Rampion Offshore Wind Farm Frequently Asked Questions (FAQs) Rampion Offshore Wind Farm Frequently Asked Questions (FAQs) February 2012 Q: Why renewable energy? A: Renewable energy involves generating electricity from natural sustainable energy sources, which do

More information

Technical and economical analysis of the wind turbines interconnection with the windfarm substation

Technical and economical analysis of the wind turbines interconnection with the windfarm substation Technical and economical analysis of the wind turbines interconnection with the windfarm substation NICOLAE COROIU Faculty of Electrical Engineering and Industrial Management University of Oradea Oradea,

More information

GB Translated English of Chinese Standard: GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA

GB Translated English of Chinese Standard: GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA Translated English of Chinese Standard: GB50169-2016 www.chinesestandard.net Buy True-PDF Auto-delivery. Sales@ChineseStandard.net GB NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA UDC P GB 50169-2016

More information

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV Network(s): Summary: ENGINEERING INSTRUCTION EI 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV EPN, LPN, SPN This engineering instruction details the minimum requirements acceptable for the installation

More information

Alternative Connection Application and Offer Process Proposal

Alternative Connection Application and Offer Process Proposal Alternative Connection Application and Offer Process Proposal Decision Paper 31 May 2016 Table of Contents 1. Executive Summary... 4 2. Introduction... 7 2.1 Purpose of the Paper... 7 2.2 Structure of

More information

Galileo Research. Distributed Generation

Galileo Research. Distributed Generation Galileo Research Distributed Generation 2001-2013 Distributed, or small generation units, typically less than 30MWs, strategically located near consumers and load centers can provide benefits to customers

More information

DS3: Voltage Control Workstream

DS3: Voltage Control Workstream DS3: Voltage Control Workstream EirGrid and SONI, 2011 Page 1 BACKGROUND The system voltage is determined by the balance of reactive power production and absorption. Generators have traditionally been

More information

Lightning Protection Practice for Large-Extended Photovoltaic Installations

Lightning Protection Practice for Large-Extended Photovoltaic Installations 202 International Conference on ightning Protection (ICP), Vienna, Austria ightning Protection Practice for arge-extended Photovoltaic Installations Dr. Nikolaos Kokkinos Research and Development Department

More information

Wind Research for North Sea wind Energy. Secure sustainable electricity supply

Wind Research for North Sea wind Energy. Secure sustainable electricity supply Wind Research for North Sea wind Energy Secure sustainable electricity supply Jan Vorrink Topics overview TenneT short overview Key tasks of a TSO New tasks TenneT The Energy market is changing Offshore

More information

MATERIAL STANDARD FOR CABLES AND WIRES

MATERIAL STANDARD FOR CABLES AND WIRES MATERIAL STANDARD FOR CABLES AND WIRES CONTENTS : PAGE No. 1. SCOPE... 2 2. SERVICE CONDITIONS... 2 3. REFERENCES AND STANDARDS... 2 4. UNITS... 3 5. CABLE DESIGN AND CONSTRUCTION... 3 5.1 Applicable Cable

More information

TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP

TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP July 2015 GENERAL SPECIFICATION 1. The contractor shall quote for the complete

More information