1 Polllluttiion IInciidentt Response Managementt Pllan Forr Piinebrrook Grravell Quarrrry EPL numberr;; Date Description Reviewed by Approved by 12/08/2014 Initial plan Taylah Lein Glenn Lein 23/09/2014 Changed Lein Contracting to Sharmaine Cunningham Glenn Lein Lein Earthmoving updated logo 16/07/2016 Annual review Sharmaine Cunningham Glenn Lein

2 TABLE OF CONTENTS OVERVIEW INTRODUCTION ABBREVIATIONS PURPOSE SCOPE RESPONSIBILITIES DOCUMENTATION EVALUATION HAZARD, LIKELIHOOD AND PRE-EMPTIVE ACTIONS TO PREVENT POLLUTION INCIDENT RISKS OVERVIEW SUMMARY OF POLLUTION TYPES ADDITIONAL INFORMATION... 9 LISTING OF TABLES Table 1 - PIRMP Requirements... 8 Table 2 - Air based emissions... 9 Table 3 - Spill type emissions... 9 LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 2 of 9

3 1. Pollution Incident Response management plan 1.1 Overview The pollution Incident Response Management Plan has been written to comply with the legislative requirements under the Protection of Environment Operations Act 1997 (POEO Act) and the Protection of the Environment Operations (General) Regulation Under the legislation referred to above, the EPL also requires a PIRMP to clearly document pollution risks, communication procedures to authorities and community regarding pollution incident involving material harm or threatened material harm to human health or the environment, the PIRMP will be implemented. Lein Earthmoving has an environmental management plan to ensure operations and activities that have the potential to impact on the environment are managed in an environmentally responsible manner refer Lein MP04. The PIRMP contains the following sections as required by the regulation: 1.2 Introduction 1. Background describes main features of the regulation 2. Hazard, likelihood and pre-emptive actions to prevent pollution incident risks describes types of pollution incidents that may be possible and lists procedures that are already in place to minimise and manage pollution. Ranking of risks is included in appendices 3. Maps map of project to show location of potentially affected neighbours and environmentally sensitive areas 4. Emergency incident response procedures what to do in case of material harm 5. Early warnings and communication to neighbours when to contact neighbours in case of pollution incidents and info required for website 6. Training information to be passed on to staff and contractors 7. Updating of plan frequency of updates 8. Testing frequency of drills to test effectiveness of PIRMP 9. Implementing of plan reference to legislation requirement to carry out aspects of the plan during a pollution incident The Pinebrook Gravel Quarry is covered by an Environment Protection License (EPL) number for the scheduled activities extraction. The site has an overarching environmental management system supported by the Lein Earthmoving Work Health and Safety Policies. See following the Environmental Policy: LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 3 of 9

4 LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 4 of 9

5 1.3 Abbreviations PIRMP = Pollution Incident Response Management Plan EPL = Environmental Protection Licence POEO = Protection of the Environment Operations Act Purpose The purpose of this PIRMP is to improve the way pollution incidents are reported, managed and communicated to the general community. The purpose of this PIRMP is to: Ensure the comprehensive and timely communication about a pollution incident to staff at the premises, the Environment Protection Authority (EPA), other relevant authorities specified Act (such as local councils, NSW Ministry of Health, Work Cover NSW, and Fire and Rescue NSW) and people outside the facility who may be affected by the impacts of the pollution incident Minimise and control the risk of a pollution incident at the facility by requiring identification of risks and the development of planned actions Minimise and manage those risks Ensure that it is properly implemented by the trained staff, identifying persons responsible for implementing it and; Ensuring that the PIRMP is regularly tested for accuracy, currency and sustainability. 1.5 Scope This PIRMP is used by employees and Lein Earthmoving contractors involved in works carried out at Pinebrook Gravel Quarry. This PIRMP identifies ways to handle flooding & hazardous chemical spillages i.e. fuel and oil. The PIRMP plans to prevent material harm to human health and/or the environment. The Pinebrook Gravel Quarry site is located at Lot 82, DP, Jacks Creek NSW LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 5 of 9

6 Environmental Management at the site is subject to improvements in the processes and practises from time to time. To accommodate these ongoing changes and also to accommodate increases in site specific environmental assessment and management, the PIRMP will be progressively reviewed. This PIRMP is to clearly define the requirements of Lein Earthmoving staff to report and respond to pollution incidents in accordance with the 2011 and 2012 changes to the POEO Act 1997 and the POEO (General) Regulation Responsibilities All Lein Earthmoving staff and contractors are responsible for understanding and implementing this PIRMP as appropriately identified. The PIRMP identifies the general roles and responsibilities of Lein Earthmoving staff. Lein Earthmoving shall manage pollution incidents in accordance with this PIRMP. Glenn Lein (Managing Director) and Brock Lein (Supervisor) are responsible for ensuring that their employees are aware of the PIRMP and their roles where appropriate. They are also responsible for the training of their staff. Lein Earthmoving is responsible for: Assisting with advice, reporting and response process; Ensuring the plan is made available to staff responsible for implementing the plan and authorised officers under the POEO Act; Giving advice on whether environmental incidents need to be reported to external agencies; Assisting in the notification of pollution incidents to the relevant authorities Provision of maps associated with the plan; Assistance with the implementation of response actions to pollution incidents Assistance in communicating with neighbours and the local community about the Plan and when incidents of a certain nature occur; Ensuring that training responsible for activating about their roles in the Plan; Testing; Reviewing this plan LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 6 of 9

7 1.7 Documentation All environmental incidents are reported to the managing director or supervisor and then recorded on the incident register with a corrective action. See below. INCIDENT REGISTER Report number Report Date Description of incident Corrective Action Review date Completion date Completed by Excavator struck powerlines when moving to new Employee to check area for overhead lines and hazards before operating machinery. Update SWMS to include 1 6/03/2013 work site after unloading this as a hazard 13/03/ /13/13 Glenn Lein While placing logs with the excavator a branch 2 24/03/2013 dislodged and caused damage to the plant While turning off Newell Highway onto Old Mill 3 6/07/2013 Road a truck following overtook causing a near miss Protective cage to be installed on excavator. Exclusion zone to be extended to 30m. 24/04/ /03/2013 Glenn Lein Lodged hazard report to Santos to advise that more signage is required on Newell Highway 6/08/2013 7/07/2013 Glenn Lein 4 18/12/2013 2L of diluted hydraulic oil spilt at Tullamullen SAMB Spill kit used to removed the contaminated soil and put in a seal bag for disposal 19/12/ /12/2013 Glenn Lein 5 19/03/2014 Injury to Jordan Hannaford Stay alert and be aware of uneven surfaces 20/03/ /03/2014 Glenn Lein The Incident register is used to record and monitor all environmental incidents within Lein Earthmoving. The register will assist with record keeping, reporting and determining improvements to incident response and review of the Plan. The register is kept by the administration department. The Managing Director and Safety Officer are responsible for monitoring and measuring the effectiveness of incident management and of this PIRMP. 1.8 Evaluation This Pollution incident Response management Plan (The Plan) complies with the requirements under the: POEO Act 1997 Part 5.7A Duty to Prepare and implement Pollution Incident Response management plans POEO (General) Regulation 2009 Part 3A The requirements under the legislation are supported by the Environmental Guidelines: Preparation of pollution incident response management plans, which provides additional advice from the EPA on Plan preparation. Plan preparation is a requirement for holders of Environment Protection Licenses (EPLs). The Pinebrook Gravel Quarry operates under EPL no and is therefore required to prepare a PIRMP and implement the PIRMP if and when an incident occurs. Key areas which this Plan covers are described in table 1 PIRMP Requirements. LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 7 of 9

8 Table 1 - PIRMP Requirements PIRMP Legislation covered under this Plan Reference POEO Act Part A Duty of license holder to prepare pollution incident response management plan Whole document plus references 153C Information to be included in plan including 5 + references procedures on actions to take after incident and coordinating with authorities 153D Keeping of plan: E Testing of plan: 9 153F Implementation of plan: 10 POEO (General) Regulation C(a) Hazard assessment: C(b) Likelihood assessment: C(c) Pre-Emptive Action: C(d) Pollutant Inventory Types: C(e) Pollutant Inventory Quantities: C(f) Safety Equipment: C(g) Staff Contacts: C(h) Authority Contact: references 98C(i) Early Warnings Neighbours: 3.4 & 6 98C(j) Staff safety: C(k) Maps location of pollutants: 3.4 and 4 98C(l) Early Warnings General: 3.4 and 6 98C(m) Training and Staff: 7 98C(n) Timing of Testing: 9 98C(o) Updating of Plan: 8 98C(p) Plan Testing: 9 98D(1) Availability of Plan: D(2) Publishing Plan Parts: D(3) Procedures under Act: 5 + references 98D(4) Privacy Protection E(1) Testing of the Plan: 9 98E(2) Minimum Testing requirements: 9 2. Hazard, likelihood and pre-emptive actions to prevent pollution incident risks 2.1 Overview The Pinebrook Gravel Quarry site undertakes extraction activities. This PIRMP also considers both air and water based pollution incident impacts. Overall considerable design and written environment systems are in place to effectively minimise the likelihood and impact of a pollution incident. However, such incidents despite the best design and management methods can occur. Such accidental events are also covered in the plan by the use of incident response methods. LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 8 of 9

9 This PIRMP uses a modular approach to this risk assessment process. Each module represents an operation undertaken in extraction activities such as use and storage of hazardous chemicals and use and storage of non-hazardous chemicals vehicle movements. These modules are common across Lein Earthmoving operations. The risk assessment and control measure process includes impact on neighbours and crosses over with safety risk assessment processes. 2.2 Summary of Pollution Types Extraction by its nature has a limited list of typical pollution types which are required to be considered under the PIRMP. This list covers the main types found for the Pinebrook Gravel Quarry. Table 2 - Air based emissions Description Dust Fire Noise Odour Comments From surrounding dirt roads. Dust is covered under this Plan and also controlled by Lein Earthmoving s Jarmyn water taker. Fire is not considered an environmental incident, but the smoke from the fire can be and can affect neighbours. Fire management is covered under the Lein Earthmoving emergency manual (LEIN ENV 6.15) and any hazard reports that Lein Earthmoving employees forward to management frequently. Emitted by plant and equipment. Covered under the Lein Earthmoving employee and Contractor inductions. Noise is not considered a pollution incident and not covered further under this Plan. Odour is generally not associated with this site. Odour incidents are not considered to be material environmental harm, but are included in the PIRMP for consistency with the site EMS Table 3 - Spill type emissions Type Diesel Petrol Hydraulic oil Use For excavator and Prime mover and on occasion a hired dozer For pumps For excavator 3. Additional Information Contact: admin@leincontracting.com.au Phone: This plan is reviewed annually. LEIN MP03 Pollution Incident Response Management Plan 16 th July 2016 Page 9 of 9

Pollution Incident Response Management Plan for Southern Roadbase Quarry

Pollution Incident Response Management Plan for Southern Roadbase Quarry Pollution Incident Response Management Plan for Southern Roadbase Quarry EPL number: 12045 Contents 1. OVERVIEW... 2 2. EVALUATION... 6 3. HAZARD, LIKELIHOOD AND PRE-EMPTIVE ACTIONS TO PREVENT POLLUTION

More information

BEVERAGE CANS REVESBY

BEVERAGE CANS REVESBY BEVERAGE CANS REVESBY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Environment Protection Authority License 643 Item ID: 8409 Version: 1.2 Page 1 of 16 1.0 OVERVIEW AND LEGAL REQUIREMENTS This Pollution

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN MET Recycling Pty Ltd Lease Areas 3 & 4 Corner of Newton St North & Carnarvon St Silverwater NSW 2128 Lot 1 in DP 713708 1 Revision History Revision Date Author/Reviewer

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,

More information

POLLUTION INCIDENT RESPONSE

POLLUTION INCIDENT RESPONSE Table of Contents Section 1. POLLUTION INCIDENT RESPONSE 1. Process..2 2. Definition of Pollution Incident..3 3. Description and Likelihood of hazards..3 4. Pre-emptive actions to be taken.4 5. Inventory

More information

Pollution Incident Response Management Plan - Summary. Medway Mine Medway

Pollution Incident Response Management Plan - Summary. Medway Mine Medway Pollution Incident Response Management Plan - Summary Medway Mine Medway Table of Contents 1. General Information... 3 1.1 Foreword... 3 1.2 Background and legislative requirements... 3 1.3 Definition

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Procedure Pollution Incident Response Plan Table of Contents Pollution Incident Response Plan... 2 1 Purpose & Scope... 2 2 Process... 2 2.1 Definition of Pollution Incident...2 2.2 Description and Likelihood

More information

WINGECARRIBEE SHIRE COUNCIL Southern Regional Livestock Exchange POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

WINGECARRIBEE SHIRE COUNCIL Southern Regional Livestock Exchange POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN WINGECARRIBEE SHIRE COUNCIL Southern Regional Livestock Exchange POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to

More information

ARDILL PAYNE & P a r t n e r s ABN:

ARDILL PAYNE & P a r t n e r s   ABN: ARDILL PAYNE & P a r t n e r s www.ardillpayne.com.au e:info@ardillpayne.com.au ABN: 51 808 558 977 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Submission to: NSW Environment Protection Authority At: Lot

More information

CCC-PLN-Pollution Incident Response Management Plan

CCC-PLN-Pollution Incident Response Management Plan CARROLL COTTON POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Page 1 of 10 1 PURPOSE The purpose of this plan is to: Ensure comprehensive and timely communication about a pollution incident to staff at the

More information

Pollution Incident Response Management Plan v1.1

Pollution Incident Response Management Plan v1.1 Tarmac Sawmilling Pty Ltd Pollution Incident Response Management Plan v1.1 Updated February 2016 Version control Date Description Name 20/1/16 v1.0 Draft PIRMP Jennifer Baldwin 11/2/16 V1.1 Approved PIRMP

More information

AMS holds an Environmental Protection Licence (EPL) No This was transferred from South East Fibre Exports P/L on 29 th February 2016

AMS holds an Environmental Protection Licence (EPL) No This was transferred from South East Fibre Exports P/L on 29 th February 2016 Page 1 of 7 1. Background Australian Marshalling Services (AMS) operates a chipmill and export facility on behalf of Allied Natural Wood Exports P/L on the shores of Twofold Bay at Eden on the far south

More information

JBS Pollution Incident Response Management Plan

JBS Pollution Incident Response Management Plan JBS Pollution Incident Response Management Plan JBS Australia Pty Limited Prime City Feedlot, NSW Document Owner Troy White, Group Environment Manager Printed copies of this document are deemed uncontrolled

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan 1 Document Control Revision Date Reason for review Nature of amendment Approved by 01 Aug 2015 New format Align with legislative requirements 02 Aug 2016 Annual

More information

Ingredion ANZ Pty Ltd

Ingredion ANZ Pty Ltd Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Lot 3 DP 619374, and Lots 102, 103, 110, 120 DP 755418 Buckaroo Lane, Mudgee Pollution Incident Response Plan 1 Oct 2012 Oct 2013 Minespex B Murdoch 2 Feb 2014

More information

Pollution Incident Response Management Plan (PIRMP)

Pollution Incident Response Management Plan (PIRMP) Pollution Incident Response Management Plan (PIRMP) November 2017 Document revision control and authorisation Date Revision Modification Prepared Reviewed Approved 20/01/2017 01 Original issue Shaun Daniels

More information

Pollution Incident Response Management Plan (PIRMP)

Pollution Incident Response Management Plan (PIRMP) Pollution Incident Response Management Plan (PIRMP) November 2017 Document revision control and authorisation Date Revision Modification Prepared Reviewed Approved 20/01/2017 01 Original issue Shaun Daniels

More information

Surface water run-off from the operational areas has the potential to provide a pathway for contamination to reach the waters of Twofold Bay.

Surface water run-off from the operational areas has the potential to provide a pathway for contamination to reach the waters of Twofold Bay. Page 1 of 9 1. Background Australian Marshalling Services (AMS) operates a chipmill and export facility on behalf of Allied Natural Wood Exports P/L on the shores of Twofold Bay at Eden on the far south

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FOR MT MAGOMETON QUARRY

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FOR MT MAGOMETON QUARRY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FOR MT MAGOMETON QUARRY EPA License No. 1152 Edition 1/Revision 0 Page i ABOUT THIS RELEASE: Document Number: Edition 1/Revision 0 Document Title: Coonamble

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC) Environmental Management System Integra Coal Operations Pty Ltd POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC) 2012 Doc No: Doc Owner: EMP_2014-2 Environmental Advisor Integra Coal Operations Approval:

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Southern Oil Refining Pty Ltd 42 Lewington St. Bomen. NSW. 2650 Table of Contents 1 INTRODUCTION 1.1 Facility details 1.2 Overview of Operations 1.3 Plan Objectives

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Gunnedah Quarry Products Pty Ltd Prepared by Tim MacKellar, Gunnedah Quarry Products Document created 13.10.13 Reviewed 10.10.14 Reviewed 12.10.15 Reviewed 02.02.18

More information

Sulcor Pollution Incident Response Management Plan (PIRMP)

Sulcor Pollution Incident Response Management Plan (PIRMP) Sulcor Pollution Incident Response Management Plan (PIRMP) The Sulcor Limestone open cut mine is located 30Km north-west of Tamworth NSW. The limestone mined by conventional drill and blast processes is

More information

SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) 1. PURPOSE Renewable Oil Services is licensed to conduct waste processing of hazardous and other wastes using non-thermal treatment and

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Austral Masonry NSW Prospect (EPL# 4664)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Austral Masonry NSW Prospect (EPL# 4664) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Austral Masonry NSW Prospect (EPL# 4664) Adapted from Horsley Park to suit Prospect PIRMP by M. Burns Reviewed 7/10/2016 Pollution Incident Response Management

More information

Clyde Junction Pollution Incident Response Management Plan Client

Clyde Junction Pollution Incident Response Management Plan Client 1/11 Pollution Incident Response Management Plan Pollution Incident Response Management Plan Document Title Clyde Junction Pollution Incident Response Management Plan Client Transport for NSW Client reference

More information

Pollution Incident Response Management Plan WETHERILL PARK RESOURCE RECOVERY FACILITY

Pollution Incident Response Management Plan WETHERILL PARK RESOURCE RECOVERY FACILITY Pollution Incident Response Management Plan WETHERILL PARK RESOURCE RECOVERY FACILITY Table of Contents Purpose... 2 Scope... 2 References... 2 Definitions... 2 Definition of Pollution Incident... 2 Hazards...

More information

Pollution Incident Response Management Plan. Newell Highway Trewilga Realignment

Pollution Incident Response Management Plan. Newell Highway Trewilga Realignment Pollution Incident Response Management Plan Newell Highway Trewilga Realignment Contents 1 Introduction... 2 1.1 Purpose and scope... 2 2 Statutory requirements... 3 2.1 Project approval... 3 2.2 Protection

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Regain Spent Potliner Reprocessing Facility Kurri Kurri Aluminium Smelter Regain Document Code Objectives Comprehensive and timely communication about a pollution incident to all recognised stakeholders

More information

Pollution Incident Response Management Plan Divall s Quarry

Pollution Incident Response Management Plan Divall s Quarry Pollution Incident Response Management Plan Divall s Quarry 1 P a g e Actions to be taken immediately, during and After an Incident on Site 1. Action 2. Shut down the emission source 3. Contain the emission

More information

Pollution Incident Response Management Plan BOMBALA QUARRY. Version Nine: 2nd July Bombala Quarry PIRMP_V9. 1 of 33

Pollution Incident Response Management Plan BOMBALA QUARRY. Version Nine: 2nd July Bombala Quarry PIRMP_V9. 1 of 33 Pollution Incident Response Management Plan BOMBALA QUARRY Version Nine: 2nd July 2018 Bombala Quarry PIRMP_V9 1 of 33 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision Details 01 20 Aug

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Table of Contents 1.0 Purpose... 3 2.0 Scope... 3 3.0 Distribution Policy... 4 4.0 Terms and Definitions... 4 5.0 Definition of a Pollution incident... 5 6.0 Duty to report a pollution incident... 5 7.0

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan PURPOSE The purpose of the Pollution Incident Response Management Plan (PIRMP) is to illustrate how Nepean Building & Infrastructure will respond to a potential

More information

Pollution Incident Response Plan

Pollution Incident Response Plan for Pollution Incident Response Document Page 1 of 22 Table of Contents 1 Background & Scope... 3 2 Regulatory Requirements... 3 3 Premises Details... 6 3.1 Site Details... 6 3.2 Major Hazards... 6 3.3

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Moomin Gin Environment Protection Licence Namoi Cotton Limited

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Moomin Gin Environment Protection Licence Namoi Cotton Limited POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Moomin Gin Environment Protection Licence 10859 Namoi Cotton Limited (PUBLIC INFORMATION) P a g e 1 1. FACILITY DETAILS The Facility details are as follows:

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Merah North Gin Environment Protection Licence Namoi Cotton Limited

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Merah North Gin Environment Protection Licence Namoi Cotton Limited POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Merah North Gin Environment Protection Licence 10861 Namoi Cotton Limited (PUBLIC INFORMATION) P a g e 1 1. FACILITY DETAILS The Facility details are as follows:

More information

POLLUTION INCIDENT RESPONSE

POLLUTION INCIDENT RESPONSE Table of Contents Section 1. POLLUTION INCIDENT RESPONSE 1. Process.2 2. Description and Likelihood of hazards.3 3. Pre-emptive actions to be taken.4 4. Inventory of Pollutants 4 5. Safety Equipment..

More information

Pollution Incident Response Management Plan METZ QUARRY. Version Eight: 31 st August Metz Quarry PIRMP-V8. 1 of 31

Pollution Incident Response Management Plan METZ QUARRY. Version Eight: 31 st August Metz Quarry PIRMP-V8. 1 of 31 Pollution Incident Response Management Plan METZ QUARRY Version Eight: 31 st August 2018 Metz Quarry PIRMP-V8 1 of 31 1. DOCUMENT CONTROL SHEET Ver. Date Prepared by Approved By Revision Details 01 20

More information

DULUXGROUP DISTRIBUTION CENTRE. 3 Harris Avenue. Marsden Park NSW

DULUXGROUP DISTRIBUTION CENTRE. 3 Harris Avenue. Marsden Park NSW DULUXGROUP DISTRIBUTION CENTRE 3 Harris Avenue Marsden Park NSW Resources and Industrials Page 1 of 15 Contents 1 Introduction... 3 2 Abbreviations and Definitions... 4 3 Risk Management Framework... 5

More information

Surface water run-off from the operational areas has the potential to provide a pathway for contamination to reach the waters of Twofold Bay.

Surface water run-off from the operational areas has the potential to provide a pathway for contamination to reach the waters of Twofold Bay. Page 1 of 12 1. Background Australian Marshalling Services (AMS) conducts log storage and export activities on land controlled by NSW Maritime at William Allan Drive. The land occupied by this commercial

More information

Pollution Incident Response Management Plan (Addendum to Emergency Response Plan)

Pollution Incident Response Management Plan (Addendum to Emergency Response Plan) Pollution Incident Response Management Plan (Addendum to Emergency Response Plan) 3.3.1 Description and likelihood of hazards (clause 98c (1) (a) and (b) St George Motor Boat Club operates a 242 berth

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. 44 Beelbangera Road Beelbangera NSW 2680 EPL: 886

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. 44 Beelbangera Road Beelbangera NSW 2680 EPL: 886 POLLUTION INCIDENT RESPONSE MAGEMENT PLAN 44 Beelbangera Road Beelbangera NSW 2680 EPL: 886 July, 2018 POLLUTION INCIDENT RESPONSE MAGEMENT PLAN Table of Contents 1. Why do we need a PIRMP? 3 2. What needs

More information

Pollution Incident Response Management Plan CULCAIRN QUARRY. Version Six: 23 rd May Culcairn Quarry PIRMP_V6. 1 of 36

Pollution Incident Response Management Plan CULCAIRN QUARRY. Version Six: 23 rd May Culcairn Quarry PIRMP_V6. 1 of 36 Pollution Incident Response Management Plan CULCAIRN QUARRY Version Six: 23 rd May 2016 Culcairn Quarry PIRMP_V6 1 of 36 DOCUMENT CONTROL SHEET Ver. Date Prepared by Approved By Revision Details 01 20

More information

Summary of. Pollution Incident Response Management Plan. Boral Cement Berrima

Summary of. Pollution Incident Response Management Plan. Boral Cement Berrima Summary of Pollution Incident Response Management Plan Boral Cement Berrima Rev.4 September 2015 Table of Contents 1. General Information... 2 1.1 Foreword... 2 1.2 Background and legislative requirements...

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) SEWAGE RETICULATION AND TREATMENT SYSTEM MANAGEMENT

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) SEWAGE RETICULATION AND TREATMENT SYSTEM MANAGEMENT POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) SEWAGE RETICULATION AND TREATMENT SYSTEM MANAGEMENT SITE: MERRY BEACH CARAVAN RESORT ADDRESS: 46 MERRY BEACH ROAD, KIOLOA, NSW CONTACT: 02 4457 1065

More information

Pollution Incident Response Management Plan CULCAIRN QUARRY. Version Eight: 26 th July Culcairn Quarry PIRMP_V7. 1 of 36

Pollution Incident Response Management Plan CULCAIRN QUARRY. Version Eight: 26 th July Culcairn Quarry PIRMP_V7. 1 of 36 Pollution Incident Response Management Plan CULCAIRN QUARRY Version Eight: 26 th July 2018 Culcairn Quarry PIRMP_V7 1 of 36 DOCUMENT CONTROL SHEET Ver. Date Prepared by Approved By Revision Details 01

More information

Wild Quarry Pollution Incident Response Management Plan

Wild Quarry Pollution Incident Response Management Plan Muswellbrook for Wild Pollution Incident Response Management Document Number: WQC PLN 0019 Status: Approved Version: 4.0 Effective: 23/11/2012 Review: 23/11/2016 Owner: Environment & Community Manager

More information

Management Plan. Environmental Management Strategy

Management Plan. Environmental Management Strategy 3-3544 No. 9 31 Oct 18 PSE Manager Management Plan Environmental Management Strategy Risk Statement: High This document will be reviewed on a yearly basis, unless a process change occurs earlier than this

More information

Pollution Incident Response Management Plan BERYL QUARRY. Version Nine: 15th March Beryl Quarry PIRMP-V9. 1 of 35

Pollution Incident Response Management Plan BERYL QUARRY. Version Nine: 15th March Beryl Quarry PIRMP-V9. 1 of 35 Pollution Incident Response Management Plan BERYL QUARRY Version Nine: 15th March 2018 Beryl Quarry PIRMP-V9 1 of 35 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision Details 01 20 Aug

More information

CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY

CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Issue date: April 2014 Page 1 of 9 Contents 1. PREVENTATIVE MECHANISMS: 1(a) Hazards to health and the environment Page 3 1(b) Pollutant Inventory Page 4 1(c)

More information

Pollution Incident Response Management Plan WIDEMERE RECYCLING. Version Nine: 8 th January Widemere Recycling PIRMP_V9.

Pollution Incident Response Management Plan WIDEMERE RECYCLING. Version Nine: 8 th January Widemere Recycling PIRMP_V9. Pollution Incident Response Management Plan WIDEMERE RECYCLING Version Nine: 8 th January 2018 Widemere Recycling PIRMP_V9 1 of 38 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision Details

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Auscott Marketing Pty Ltd Macquarie Valley Gin Operations Warren Gin 9706 Oxley Highway PO Box 303 Warren NSW 2824 Phone 02 6883 7306 Fax 02 6847 4399 Version: 2 Table

More information

Pollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 20 th September Seven Hills Asphalt PIRMP_V8.

Pollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 20 th September Seven Hills Asphalt PIRMP_V8. Pollution Incident Response Management Plan Seven Hills Asphalt Version Seven: 20 th September 2016 Seven Hills Asphalt PIRMP_V8 1 of 31 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Auscott Marketing Pty Ltd Macquarie Valley Gin Operations Trangie Gin Mitchell Highway Trangie PO Box 160 Warren NSW 2824 Phone 02 6888 7738 Fax 02 6888 7091 Table of Contents Contents Page Contents Page

More information

Asbestos Management Policy

Asbestos Management Policy ECM Document Set ID Number: 3428289 Revision Date: August 2016 July 2016 20 th July 2016 Risk Principal Approval Date: 20 th July 2016 Manager Works 20 th July 2016 Manager Building and Property Review

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Oakleigh Oakleigh Lane, Tichborne NSW 2870 Document number: ANL.IMP1.OK 1 Contents 1. Introduction. Page 3 2. Objectives... Page 3 3. Principles. Page 3 4. What

More information

Pollution Incident Response Management Plan Bungendore Sand Quarry

Pollution Incident Response Management Plan Bungendore Sand Quarry Pollution Incident Response Management Plan Bungendore Sand Quarry Pollution Incident Response Management Plan: Bungendore Sand Quarry Revised: October 2018 1 Holcim Bungendore Pollution Incident Response

More information

Midal Cables International Tomago NSW, Australia Pollution Incident Response Management Plan

Midal Cables International Tomago NSW, Australia Pollution Incident Response Management Plan MIDAL CABLES INTERNATIONAL PTY LTD TOMAGO, NSW AUSTRALIA POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 20 June 2014 Prepared for: Midal Cables Tomago, NSW Prepared by: Graham Taylor Ref: N:\800_Environmental\803

More information

INCIDENT MANAGEMENT PLAN

INCIDENT MANAGEMENT PLAN INCIDENT MANAGEMENT PLAN Tea Gardens 1 Contents 1. Introduction. Page 3 2. Objectives... Page 3 3. Principles. Page 3 4. What is an incident Page 3 5. Roles and Responsibilities. Page 4 6. Training in

More information

Pollution Incident Response Management Plan ST PETERS RECYCLING. Version Nine: 20 th November St Peters Recycling PIRMP_V9.

Pollution Incident Response Management Plan ST PETERS RECYCLING. Version Nine: 20 th November St Peters Recycling PIRMP_V9. Pollution Incident Response Management Plan ST PETERS RECYCLING Version Nine: 20 th November 2017 St Peters Recycling PIRMP_V9 1 of 38 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan MANAGEMENT PLAN Name Role Date Prepared by: Dr Keith Halford Snr Environmental Advisor 01/06/2018 Approved by: Denver D Angelo General Manager 02/06/2018 Reviewed

More information

DURALIE COAL MINE Pollution Incident Response Management Plan

DURALIE COAL MINE Pollution Incident Response Management Plan DURALIE COAL MINE Pollution Incident Response Management Plan DURALIE COAL MINE POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Revision Status Register Section/Page/ Annexure Revision Number Amendment/Addition

More information

JBS Pollution Incident Response Management Plan

JBS Pollution Incident Response Management Plan JBS Pollution Incident Response Management Plan JBS Australia Pty Limited Scone NSW Document Owner Troy White, Group Environment Manager Printed copies of this document are deemed uncontrolled JBS Australia

More information

Orica Australia Pty Ltd A.C.N MATRAVILLE NSW 2036

Orica Australia Pty Ltd A.C.N MATRAVILLE NSW 2036 ENVIRONMENTALLY HAZARDOUS CHEMICALS ACT 1985 Licence No: 26 EPA File No: EF13/2466 Name of licensee: Address of licensee: Commencement Date: 20 July 2018 In force until: 20 July 2021 Orica Australia Pty

More information

Pollution Incident Response Management Plan KOORAGANG RECYCLING. Version Six: 2 nd August Kooragang Recycling PIRMP_V7 1 of 33

Pollution Incident Response Management Plan KOORAGANG RECYCLING. Version Six: 2 nd August Kooragang Recycling PIRMP_V7 1 of 33 Pollution Incident Response Management Plan KOORAGANG RECYCLING Version Six: 2 nd August 2018 Kooragang Recycling PIRMP_V7 1 of 33 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision Details

More information

Pollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 3rd September Seven Hills Asphalt PIRMP_V9.

Pollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 3rd September Seven Hills Asphalt PIRMP_V9. Pollution Incident Response Management Plan Seven Hills Asphalt Version Seven: 3rd September 2018 Seven Hills Asphalt PIRMP_V9 1 of 30 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Bargo/Buxton Wastewater Scheme

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Bargo/Buxton Wastewater Scheme POLLUTION INCIDENT RESPONSE FOR Bargo/Buxton Wastewater Scheme Rev Date Revision Prepared Approved A 16 December 2013 Draft L O Hare B 25 January 2013 Draft L O Hare C 10 April 2013 Draft A.White D 24

More information

Pacific Blue Metal Pty Ltd ABN

Pacific Blue Metal Pty Ltd ABN Pacific Blue Metal Pty Ltd ABN 45 050 224 250 PO Box 6 NABIAC NSW 2312 Ph: 02 6554 3206 Fax: 02 6554 3250 Version 5.00 Date Issued: 08/08/2017 Review Date: 08/08/2018 POLLUTION INCIDENT RESPONSE MANAGEMENT

More information

R.W. CORKERY & CO. PTY. LIMITED

R.W. CORKERY & CO. PTY. LIMITED Pollution Incident Response Management Plan Multiquip Quarries ABN: 44 101 930 714 Pollution Incident Response Management Plan for Environment Protection Licence 13213 Ardmore Park Quarry Prepared by:

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Document Pollution Incident Response Management Table of Contents 1 Introduction... 3 1.1 Background and Scope... 3 1.2 Regulatory Requirements... 3 1.3 Definitions...

More information

INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016

INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016 INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016 DOCUMENT CONTROL Document Controller: Resilience Coordinator Date of last update: May 2016 Date of next update: May 2017 HPRM reference: HW2007-900/27/9.009 Version

More information

Pollution Incident Response Management

Pollution Incident Response Management For Notification Procedure, please turn to Section 5 for Pollution Incident Response Management Document Table of Contents 1 Introduction... 3 1.1 Background and Scope... 3 1.2 Regulatory Requirements...

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Peak Hill Gold Mine Revision 6. Peak Hill Gold Mine. Pollution Incident Response Management Plan

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Peak Hill Gold Mine Revision 6. Peak Hill Gold Mine. Pollution Incident Response Management Plan Peak Hill Gold Mine Pollution Incident Response Management Plan Peak Hill Gold Mine Pollution Incident Response Management Plan Table of Revisions Revision Number Revision Date Prepared By Approved By:

More information

Environmental Management Sub-Plan. Management Plan. Appendix I Pollution Incident Response. Bringelly Road Upgrade Stage 1

Environmental Management Sub-Plan. Management Plan. Appendix I Pollution Incident Response. Bringelly Road Upgrade Stage 1 Environmental Management Sub-Plan Appendix I Pollution Incident Response Management Plan Bringelly Road Upgrade Stage 1 DETAILS OF REVISION AMMENDMENTS TO POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Plan

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

WHS Change Management

WHS Change Management Page 1 of 6 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons in the mission / ministry

More information

DUNMORE SAND AND SOIL

DUNMORE SAND AND SOIL Pollution Incident Response Management Plan DUNMORE SAND AND SOIL Version Nine: 27 July 2018 1 of 38 Table 1: Document Control Sheet DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision Details

More information

RE: PROTECTION OF THE ENVIRONMENT OPERATIONS AMENDMENT BILL 2014 A FEW MINOR ISSUES

RE: PROTECTION OF THE ENVIRONMENT OPERATIONS AMENDMENT BILL 2014 A FEW MINOR ISSUES 18 September 2014 Robert Stokes MP Barry Buffier Mark Gifford Minister for the Environment Chief Executive Chief Environmental Regulator Environment Protection Authority RE: PROTECTION OF THE ENVIRONMENT

More information

APPENDIX B9 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

APPENDIX B9 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN APPENDIX B9 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Site Details Client: Site Name: NSW Roads and Maritime Services The Northern Road Upgrade Between Mersey Road and Eaton Road Revision Number: 0 ID

More information

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI Traffic Management Plan Environmental Management and Monitoring Program Appendix VI Gunlake Quarries December 2009 Olsen Consulting Group Pty Ltd 6/25 Victoria Street WOLLONGONG 2500 PO Box 353 FIGTREE

More information

Pollution Incident Response Management Plan. Boral Cement Prestons

Pollution Incident Response Management Plan. Boral Cement Prestons Pollution Incident Response Management Plan August 2018 1. General Information 1.1 Foreword This document was prepared to fulfil the requirements of the NSW Protection of the Environment Legislation Amendment

More information

HFM Asset Management Contractor Induction Queens Riverside Apartments

HFM Asset Management Contractor Induction Queens Riverside Apartments HFM Asset Management Contractor Induction Queens Riverside Apartments Contents Purpose About HFM Asset Management HFM Asset Management s Responsibilities Contractors Responsibilities Commencing Work Working

More information

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT ORICA KURRI KURRI ANE PLANT ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2014 Revision Date Description Author Approver 0 2014 Annual Environmental Report D Horne Manufacturing Superintendent Kurri R Powell

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan 2017 Pollution Incident Response Management Plan Port Kembla Gateway Pty Ltd Complaints Line: (02) 4276 3566 1 1. CONTENTS 1. Background... 4 1.1 Objectives of this Plan... 5 2. Legislative requirements...

More information

Pollution Incident Response Management Plan. Boral Cement Prestons

Pollution Incident Response Management Plan. Boral Cement Prestons Pollution Incident Response Management Plan Boral Cement Prestons Febuary 2017 1. General Information 1.1 Foreword This document was prepared to fulfil the requirements of the NSW Protection of the Environment

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN CONTENTS Introduction... 2 Scope... 3 Definitions... 3 Notification to the Authority... 3 High or Extreme Risk Environmental Hazards... 4 Contact Information... 4 Reporting and Notification Protocol...

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Air Quality Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Farm Safety Starter Kit overview

Farm Safety Starter Kit overview Farm Safety Starter Kit overview The Farm Safety Starter Kit is designed to assist in getting your safety system underway, or improve your existing system. Getting started: Complete the safety checklist

More information

ENVIRONMENTAL MANAGEMENT MANUAL

ENVIRONMENTAL MANAGEMENT MANUAL Distribution: Admin Fld PK Control Room Ops Fld PK Upstairs Lab PK Company Website MORGAN CEMENT INTERNATIONAL PTY LTD ENVIRONMENTAL MANAGEMENT Page 1 of 21 INDEX 1 INDUCTION 3 2 DEFINITIONS 4 3 EPA LICENCE

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

Environmental Management Strategy - Operations

Environmental Management Strategy - Operations Orica Ammonium Nitrate Emulsion Project, Richmond Vale Orica Australia Pty Ltd Environmental Management Strategy - Operations Orica, Richmond Vale Ammonium Nitrate Emulsion Plant AECOM Orica Ammonium Nitrate

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Environmental Specialist Responsible Manager: Head of Environment Responsible Executive:

More information

BROADWATER QUARRY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

BROADWATER QUARRY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN BROADWATER QUARRY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Prepared for: Quarry Solutions Pty Ltd Date: 15 October 2018 Reference: 1899.610.004R1 Resources Environment Planning Laboratories www.groundwork.com.au

More information

Operation Environmental Management Plan

Operation Environmental Management Plan Boral Cement Limited Berrima Works Operation Environmental Management Plan Document Filename: Document Owner: Approved By: CMT-ENV-002 Berrima Operation Environmental Management Plan HSE Advisor, Berrima

More information

Environment Management A TENANT INFORMATION HANDBOOK

Environment Management A TENANT INFORMATION HANDBOOK Environment Management A TENANT INFORMATION HANDBOOK 3 Avro Street Bankstown Airport NSW 2200 T 02 9796-2300 F 02 9791-0230 www.sydneymetroairport.com.au SYDNEY METRO AIRPORTS E N V I R O N M E N T M A

More information

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015 1.0 Summary of Changes 1.1 This is a new joint procedure/sop for Essex Police and Kent Police. 2.0 What this Procedure is about 2.1 This document identifies how Essex Police and Kent Police shall manage

More information