Environmental Management Sub-Plan. Management Plan. Appendix I Pollution Incident Response. Bringelly Road Upgrade Stage 1

Size: px
Start display at page:

Download "Environmental Management Sub-Plan. Management Plan. Appendix I Pollution Incident Response. Bringelly Road Upgrade Stage 1"

Transcription

1 Environmental Management Sub-Plan Appendix I Pollution Incident Response Management Plan Bringelly Road Upgrade Stage 1

2 DETAILS OF REVISION AMMENDMENTS TO POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Plan Control The latest version of this Plan will be available for all Project personnel, either electronically through the site network or in hard copy in the site files. The Project Environmental Site Representative (ESR) in conjunction with the Project Manager, will maintain, review and update this plan at least annually. Amendments Each new revision to the plan will be distributed to all relevant personnel. The revision number is noted in the footer of each page. The document will be allocated a new revision number when any changes are made. When a new revision to the document is created, a notification will be distributed to all project personnel by the Project Manager or Project Environmental Site Representative advising of the update. The Project Manager is responsible for the implementation of the plan and will approve all amendments as detailed above. Revision Date Description Page Clause A 03/03/2015 Initial Submission All All B 30/03/2015 Updated with RMS comments All All C 01/07/ month review All All D 09/11/2015 Reviewed after an environmental event All All E 02/05/2016 General review All All F 07/11/2016 General review All All G 15/06/2017 General Review All All Authorised by: Daniel Everett Date: 15/06/17 Rev. G (15/06/2017) Page 2 of 54

3 Pollution Incident Response Management Plan Bringelly Road Upgrade Stage 1 Table of Contents 1 Emergency Contacts Incident Anticipation, Planning and Response Background Preparedness; Risk Assessment and Pre-Emptive Actions to Prevent Pollution Incident Risks Summary of Pollution Types Risk Assessment Notification Incident Investigation Project Maps Incident Response Procedure Internal Communications - key names and contacts Emergency Response Planning Medical Emergency Spillage of Hazardous Liquids/Petroleum/Chemicals Excavation and Disposal of Contaminated Material Excavation Removal of sewage system Transport Personnel Refuelling or maintenance and clean of plant and equipment Sediment control resulting from large rainfall events Laden dirty water runoff, resulted from a unforeseeable event Excessive Dust Bush Fire Injured animals Early Warnings and Communications to Neighbours Website information Availability and Location of This Plan Privacy Protection Training Summary and Reference to Project Procedure Updating of Plan Testing and Implementation Rev. G (15/06/2017) Page 3 of 54

4 8.1 Testing of the PIRMP Implementation of the Plan Appendix 1 Project Map Appendix 2 Risk Assessments Appendix 3 St John s Ambulance First Responder Chart Appendix 4 Emergency Spill Response Procedure Table 1 PIRMP Requirements and Reference in this document... 9 Table 2 List of Typical Main Pollutants in Road Construction Table 3 POEO (General) Regulation 2009 Requirements Table 4 External Emergency Contacts - not an immediate threat Table 5 External Emergency Contacts - immediate threat Table 6 List of Typical Main Pollutants and Potential Neighbour Impacts and Early Warnings Rev. G (15/06/2017) Page 4 of 54

5 1 Emergency Contacts SITE LOCATION: Bringelly Road: King Street to Camden Valley Way MAIN COMPOUND LOCATION: 111 Cowpasture Road South; Leppington EMERGENCY NUMBERS FIRE BRIGADE 000 AMBULANCE 000 POLICE 000 LOCAL EMERGENCY SERVICES Fire Station Fire Brigade NSW 162 Greenway Drive Horningsea Park NSW Police Station Police Station 33 Moore St Liverpool NSW Medical Centre AllCare Carnes Hill Medical Centre Cnr Kurrajong & Cowpasture Rds Horningsea Park NSW Hospital Liverpool Hospital Elizabeth Street Liverpool NSW Rev. G (15/06/2017) Page 5 of 54

6 AGENCY/STAKEHOLDER CONTACT NUMBERS For Immediate Contact following a Pollution Incident (see section 2.5) EPA Pollution Hotline Dial Before You Dig 1100 NSW Fire and Rescue (000) Horningsea Park Fire Station, 162 Greenway Dr, Horningsea Pk (02) Poisons Information WorkCover (Parramatta) NSW Ministry of Health (Liverpool Public Health Branch) ( ) Liverpool Council Camden Council Other Useful contacts in an Emergency Dial Before You Dig 1100 Poisons Information Telstra Endeavour Energy Jemena Gas APA Water NSW Fisheries NSW POSITION NAME NUMBER Project Manager (PM) Daniel Everett Environmental Site Representative (ESR) Imtiaz Risha Safety Coordinator Bryan Fuller Superintendant Greg Goggins Adam Young General Foreman Scott MacIver Mitch Power Senior Project Engineers Michael Sherlock Jacob Dickson Frank George RMS Project Manager Roy Surace Rev. G (15/06/2017) Page 6 of 54

7 RMS Project Engineer Ragavan Vythilinkam RMS Surveillance Officer Steve Nedic Matt Graham Foremen Kelwin Sparks First Aid Officers Jessica Newton Roles and responsibilities BMD Constructions Project Team organisational structure and overall roles and responsibilities are outlined in the CEMP. Specific responsibilities for the implementation of this PIRMP are detailed below Project Manager and Environment Site Representative / Safety Manager General Requirements Be fully conversant with the requirements of this Plan Ensure the PIRMP is fully implemented, monitored and adjusted to suit the requirements of the operations system and the client s requirements Ensure the requirements of the Management System are fully complied with when administering the PIRMP Ensure all employees are conversant with their responsibilities and duties under the PIRMP Responsible to notify relevant stakeholders and government authorities Communication Ensure the spill response flowchart, emergency contact numbers and details and any other bulletin or information pertaining to emergency plans and management is placed on noticeboards Training Educate supervisory personnel in accordance with plan requirements, statutory obligations, and relevant procedures Ensure staff and s have been inducted into BMD safety and environmental management systems and procedures Superintendent / Foreman The Superintendent / Foreman are responsible for the day to day operations of the project, ensuring project operations comply with all relevant obligations for the period of this contract. The Superintendent / Foreman will be inducted into BMD Integrated Management Systems and Procedures, they will also receive a higher level of Project specific Emergency Preparedness and Incident Management training while onsite General Requirements Being familiar with the requirements of this PIRMP. Ensuring incidents are managed and strictly supervised in accordance with the PIRMP, company policies and procedures Being familiar with legislation and codes of practice relevant to this role, and ensuring the requirements of the same are bought to the attention of interested parties and implemented as is practicable across the Project site Understanding process and location of spill kits Rev. G (15/06/2017) Page 7 of 54

8 Communication Ensuring the requirements of the PIRMP are communicated to all personnel, subs and where appropriate, visitors to site through on site daily Pre Start meetings, Site Inductions, weekly Toolbox Meetings and Work Method Statement (WMS) review on commencement of new works with the potential to impact personnel and the environment Any external contact will be communicated to the client via the Project Manager or their delegate Employees, Contractors & Visitors On identification of an occurrence requiring emergency response each employee has the responsibility to immediately notify the site supervisor or delegate. In the event of a serious situation the employee shall utilise this Plan to make direct contact with the closest emergency service required (e.g. spill clean-up service) Rev. G (15/06/2017) Page 8 of 54

9 2 Incident Anticipation, Planning and Response 2.1 Background This Plan has been prepared in order to guide and direct the response by the Bringelly Road Upgrade Stage 1 Project Team to an incident or emergency, be it environmental or safety in nature. The Plan has been modified following a review by independent consultants to assess compliance with the POEO Act 1997 Part 5.7A; Duty to Prepare and implement Pollution Incident Response Management Plans, and POEO (General) Regulation 2009 Part 3A, carried out on the 5 th November Plan preparation is a requirement for holders of Environment Protection Licences (EPLs). BMD holds EPL for road construction on this Project. Key areas which this Plan covers are described in Table 1 below; PIRMP Requirements. Table 1 PIRMP Requirements and Reference in this document Section Description Reference POEO Act Part 5.7 Section 153A Duty of Licence holder to prepare PIRMP Whole document 153C Information to be included and procedures or actions to take after an incident and coordinating with authorities 2,3,4, 5 Appendix 3 153D Keeping of plan E Testing of plan F Implementation of plan 8.2 POEO (Gen) Reg C(a) Hazard Assessment 2.2, Appendix 2 98C(b) Likelihood assessment 2.2, Appendix 2 98C(c) Pre-emptive Action 2.2, Appendix 2 98C(d) An inventory of potential pollutants on the premises or used in carrying out the relevant activity 2.2, Appendix 2 98C(e) Pollutant Inventory Quantities 2.2, Appendix 2 98C(f) Safety equipment such storage containers, spill kits, and PPE will be located near the source of chemical/fuel for easy access. 2.2, Appendix 2 98C(g) Staff Contacts explanation 1 98C(h) Authority Contact 1, Rev. G (15/06/2017) Page 9 of 54

10 98C(i) Early Warnings to Neighbours 2.2, Appendix 1 98C(j) Minimising the risk of harm to any persons will be risk assessed daily as per activity within an area by the site Foreman. Items for consideration may include evacuation point, appropriate PPE requirements, site accessibility, etc. 2.2, Appendix 2 98C(k) Map locations of pollutants 3, Appendix 1 98C(l) Early Warnings General C(m) Training of Staff 6 98C(n) Timing of Testing C(o) Updating of Plan 7 98C(p) Plan Testing D(1) Availability of Plan D(2) Publishing Plan Parts D(3) Procedures under the Act 2.1, All Appendices 98D(4) Privacy Protection E(1) Testing of the Plan E(2) Minimum Testing Requirements 8.1 EPA Bunding and Spill Management Guidelines 4 Minimising the risk of spills to the environment 2.2 RMS Code of Practice for Water Management 2 Best Practice Principle Whole document 2.2 Preparedness; Risk Assessment and Pre-Emptive Actions to Prevent Pollution Incident Risks This chapter deals with the POEO (General) Regulation 2009 s sections 98(a) to 98(f) and partially covers s98(j). These sections deal with the hazard, likelihood and pre-emptive actions which are similar processes to undertaking a risk assessment and providing appropriate control measures to prevent or minimise these risks. The key to effective prevention of incidents is risk assessment, procedure development, monitoring and training. During construction activities, BMD s inspections and preventive actions will include: Risk Register updated on a 3-monthly basis; Rev. G (15/06/2017) Page 10 of 54

11 activity specific and daily risk assessments, inclusive of associated environmental risk, safety of workers, and emergency evacuation; development of work procedures, construction method statements and environmental work method statements in consultation with relevant BMD staff such as work teams, environment team members and senior management; daily inspections of active work sites; completion of routine environmental checklists; issue and quick close-out of non-compliance notices; ongoing environmental training; environmental audits of work sites, subs and compliance issues. Environmental and safety information on hazardous substances (e.g. SDS) will be available at the main site office and where such substances are stored. Personnel involved in emergency response activities will be provided with specific training. An up-to-date list of emergency response personnel and organisations will be maintained at the main office and compounds. Additionally, a more detailed assessment of the above issues and more are included in s2.4 and Appendix Summary of Pollution Types Road construction has by its nature a limited list of typical pollution types which require consideration (see Table 2 below). The Project CEMP addresses these in more detail. Table 2 List of Typical Main Pollutants in Road Construction Description Comments Air Based Emissions Dust Fire Noise Odour From use of plant and equipment, moving across dry surfaces. Covered under G36 and CEMP Sub Plan. Small bush fires and other fires are covered under G36 and CEMP. Fire is not considered an environmental incident, but the smoke from the fire can be and can affect neighbours. Emitted by plant and equipment. Covered under G36 and the CEMP Sub Plan. Noise is not considered a pollution incident and not covered further under this Plan. Odour is generally associated with laying of asphalt and is managed under the CEMP under complaints. Water Based Emissions Fuel (diesel and petrol), lubricants and hydraulic oils Paints and surface coatings Pesticides Concrete wash out For plant and equipment operations. Covered under G36 s6.12 and the CEMP Potential for lead based paint on existing bridge over the Upper Canal. Surface coatings in many cases must be applied on site. Covered under G36 and the CEMP Control of weeds and pests: Covered under G36 and the CEMP Wash out of concrete vessels: Covered under G36 and the CEMP, EWMS Rev. G (15/06/2017) Page 11 of 54

12 Bitumen materials Effluent Soils and erosion Bentonite slurry Potential Asbestos Containing Material Application of spray seal and laying of asphalt. Removal and relocation of sewage septic systems from existing properties. Effluent to be disposed as being Liquid Waste in accordance with the EPA Waste Classification Guidelines Part 1: Classification of waste. The demolition sub to be licence to manage the removal of the sewage septic system structure and dispose the material at a licence waste facility. General site issue for exposed soils: Covered under G36, G38 and G40, CEMP and Soil and Water Management Sub Plan. Project is guided by General road construction handbook, BLUE BOOK Managing Urban Stormwater: Soils and Construction. Produced as a result of underbore activity. Free liquid is recycled through the underbore process in a contained environment and the solid is removed to a designated stockpile area to be dried out and reused as general fill material. Excess liquid will be managed in accordance with G36, G38 and G40, CEMP and Soil and Water Management Sub Plan. The bentonite product is non-hazardous. Demolition of existing buildings/structures and unexpected finds: Covered under G36, G38, G40, Contractors Environmental Management Plan, Contaminated Land Management Sub-Plan and Soil and Water Management Sub-Plan. Works to be undertaken in accordance with The Code of Practice: How to Safely Remove Asbestos prepared by Safe Work Australia and WorkCover s guidelines to managing asbestos. 2.4 Risk Assessment To improve the effectiveness of the Plan, Table 3 below set out the requirements under the POEO (General) Regulation 2009: Table 3 POEO (General) Regulation 2009 Requirements Section Item heading Covered by 98C(a) 98C(b) 98C(c) 98C(d) Hazard assessment: Likelihood assessment: Pre-Emptive Action: Pollutant Inventory Types: Hazard and Likelihood Risk assessment and Corrective Control Measures tables Hazard and Likelihood Risk assessment and Corrective Control Measures tables Hazard and Likelihood Risk assessment and Corrective Control Measures Control measures and corrective action List Of Polluting Substance Storages/Uses At Site Initial Assessment Name/description, Covered under Hazardous Chemicals? 98C(e) Pollutant Inventory Quantities: List Of Polluting Substance Storages/Uses At Site Initial Assessment Amount Stored (maximum or estimated Maximums stored) Rev. G (15/06/2017) Page 12 of 54

13 98C(f) 98C(i) 98C(j) 98C(k) Safety Equipment: Early Warnings Neighbours: Staff Safety: Maps location of pollutants: List Of Polluting Substance Storages/Uses At Site Initial Assessment- Ref to Safety Coverage List Of Polluting Substance Storages/Uses At Site Initial Assessment Need for early warnings to neighbours List Of Polluting Substance Storages/Uses At Site Initial Assessment Ref to Safety Coverage List Of Polluting Substance Storages/Uses At Site Initial Assessment Location of Storage, Map reference (supports section 3 Maps and maps in Appendix 1) The controls are covered in Appendix 3 Risk Assessments. They are broken down into the following: Main Activities of Environmental Hazard: o Clearing and grubbing o Bridge demolition and construction o Building demolition o Road construction o Utility works o Erosion and sedimentation o Chemical storage and use o General Concrete Works Each activity in the above list is assessed on the types, quantities, usage and storages of potential pollutions listed by its: o Chemical type o Is it a Dangerous Good? o Max Quantity on site o Location description o Map Reference o Potential impact on neighbours o Pre-emptive measures o Use of safety equipment A risk assessment is undertaken based on the RMS risk matrix which considers: o Hazard identification o Risk assessment o More detailed control measures for specific hazard/incident If the risk assessment process was found to be unacceptable or review of an incident resulted in changes to the risks, alternative and improved pre-emptive measures will be considered. 2.5 Notification The ESR or Superintendent/Foreman will make a decision based on RMS Environmental Incident Classification and Reporting Procedure what level of notification and callout is initially required for the incident. Larger incidents may require higher levels of notification and the need for external resources to manage the incident and protect soil, water and biodiversity. The ESR or PM will immediately notify the authorities listed in the below table of pollution incidents on or adjacent to the site where material harm* to the environment is caused or threatened. *That is, environmental harm or potential harm to the health or safety of human beings (from environmental hazards) or to ecosystems that is not trivial; or that result in actual or potential loss or property damage of an amount over $10,000. Rev. G (15/06/2017) Page 13 of 54

14 If there is not an immediate threat to human health or the environment Table 4 External Emergency Contacts - not an immediate threat Emergency Contact / Organisation Contact Details EPA Pollution Hotline Liverpool / Camden Council / *Water NSW NSW Ministry of Health (Liverpool Public Health Branch) WorkCover Authority NSW Fire and Rescue *Only to be contacted in an event impacting on the Upper Canal If there is an immediate threat to human health or the environment Table 5 External Emergency Contacts - immediate threat Emergency Contact / Organisation Contact Details NSW Fire and Rescue 000 EPA Pollution Hotline *Water NSW NSW Ministry of Health (Liverpool Public Health Branch) WorkCover Authority Liverpool / Camden Council / *Only to be contacted in an event impacting on the Upper Canal The Principal will be verbally notified immediately (by phone) and, in any case in writing within 24 hours, of any incidents which have been reported to the EPA under Part 5.7 of the POEO Act. The Principal will be verbally notified of any Category 1 environmental incidents within 1 hour of the incident occurring. Category 1 incidents are potentially the most serious and generally reflect breaches of environmental legislation (refer RMS Environmental Incident Classification and Reporting Procedure Section 1 for more detailed information). 2.6 Incident Investigation All incidents will be documented, investigated and action plans established to prevent a reoccurrence. RMS incident classification categorisation is to be included within the BMD report form details. Where lessons are learnt from the investigation or current procedures are identified as being ineffective, the CEMP or associated documents will be revised by the ESR to include the improved procedures or requirement. An environmental investigation includes the following basic elements: identifying the cause, extent and responsibility of the incident identifying and implementing the necessary corrective action identifying the personnel responsible for carrying out the corrective action implementing or modifying controls necessary to avoid a repeat occurrence of the Rev. G (15/06/2017) Page 14 of 54

15 incident recording any changes in written procedures required advising the environmental authority (i.e. EPA) if any substantial pollution has occurred. All personnel are required to report all incidents or near hits (misses), as it is regarded as a valuable method of addressing shortcomings in procedures, training or equipment, and is an opportunity for improvement. Rev. G (15/06/2017) Page 15 of 54

16 3 Project Maps This section covers the POEO (General) Regulation s98e(k) requirements which are: A detailed map (or set of maps) showing the location of the premises to which the licence relates, the surrounding area that is likely to be affected by a pollution incident, the location of potential pollutants on the premises and the location of any stormwater drains on the premises. As the Project is staged the maps include: An overall map of the entire project area covered by the EPL Project Specification G36 requires that the prepare the necessary documentation including the detailed maps required under the POEO (General) Regulation Other maps for the project relevant to this PIRMP are listed in the Emergency Spill Response Plan for this project. Appendix 1 shows the entire project alignment and include the EPL boundary, outside premises likely to be affected by a pollution incident, location of potential pollutants outside project boundary, and site facilities. Rev. G (15/06/2017) Page 16 of 54

17 4 Incident Response Procedure 4.1 Internal Communications - key names and contacts Incident Occurs Is there a potential risk to environment, health and/or safety? No If possible, prevent/control/remove the risk and/or provide appropriate first aid/support. Yes Evacuate or isolate the area and prevent access if area unsafe. For environmental incidents involving spills follow Emergency Spill Response Plan. Call 000 in the event of a medical emergency and designate appropriate person to direct ambulance from the public road to the incident location. Immediately notify BMD supervisor via phone or radio. Foreman and ESR/Safety Co-ordinator to inspect the area/accident. Foreman and Project Manager to determine if further action is required. Project Manager and ESR/Safety Co-ordinator to determine if immediate reporting to EPA/WorkCover and other regulatory bodies is required. Note: to be immediately notified in the event of actual or potential harm to the environment or health of site personnel (see section 2.4) Complete the BMD and RMS Incident report No Yes Foreman to manage any works to prevent further damage/harm. Toolbox work crew and/or site personnel if required Immediately notify RMS of incident via phone. An incident report is to be provided within 48 hours. Complete the BMD and RMS incident report, undertake investigation and determine management and/or remediation measures to be implemented on site Rev. G (15/06/2017) Page 17 of 54

18 5 Emergency Response Planning 5.1 Medical Emergency (SEE ST. JOHN S AMBULANCE FIRST AID RESPONDER CHART INCLUDED AT APPENDIX 3) 1. Check for any threatening situation and control it if safe to do so 2. Remain with casualty (unless there is no other option) and provide appropriate support 3. Do not move any casualties unless in a life threatening situation 4. Notify the Foreman and the first aider 5. Notify the ambulance if not already done and designate people to direct them from the public road to the incident location. 6. If necessary arrange clear path for emergency vehicles to the incident location, e.g. grader/dozer may clear path 7. Provide support to first aider and/or emergency services if required 5.2 Spillage of Hazardous Liquids/Petroleum/Chemicals (AS THE RISK OF SPILLAGE IS DEEMED ONE OF THE MORE LIKELY EMERGENCY EVENTS ON THIS PROJECT, A DEDICATED EMERGENCY SPILL RESPONSE PLAN IS INCLUDED AT APPENDIX 4 BELOW). 1. Identify the source and if possible minimise/stop further spillage. IN ALL CASES, ASCERTAIN FIRST WHETHER IT IS SAFE TO TACKLE THE SITUATION. IF UNCERTAIN, CONTACT EMERGENCY PERSONNEL AND EVACUATE AND SECURE THE AREA. 2. Stop work in the area and notify Foreman/Supervisor. 3. Under instruction of Foreman/Supervisor and if safe to do so, isolate the contaminated area to ensure that hazardous material does not spread to other areas. In the case of oil or other contaminant spill unable to be contained by adjacent spill kit, the immediate area shall be bunded to prevent spread of spill. 4. In the event of a spill from plant, the plant shall be shut down immediately, and shall not be moved until the spill can be contained and leaking part plugged / fixed. 5. If spillage occurs in the vicinity of creeks or stormwater drains, all measures must be taken to ensure that the creeks or inlets are protected (e.g. a temporary dam is acceptable) to restrict hazardous substance entering downstream. 6. Contaminant shall be soaked up with appropriate spill kit material and disposal of contaminated material shall occur at an approved disposal site. If hazardous materials cannot be completely restricted and removed from the site by equipment available then the local fire department is to be contacted. 7. Call: 000 or if using a digital mobile phone: Contaminated absorbent material shall be stored in a suitable bunded off and covered area or regulated waste bin within the site compound until disposal to an approved regulated waste disposal centre. 9. All spills shall be notified to the Site Superintendent and ESR as soon as practicable and incident report actioned. 5.3 Excavation and Disposal of Contaminated Material If the excavation and disposal of contaminated material is required, a toolbox meeting should be held to highlight the correct procedure. Refer to Unexpected Discovery of Contaminated Material Procedure within Soil and Water Management Plan Excavation Clean fill material to be separated from contaminated material. Do not stockpile contaminated material on pavements Attempt to prevent spillage of contaminated material onto pavements. Keep pavements clean where trucks are being loaded to prevent material being transported off site by wheels of truck. Rev. G (15/06/2017) Page 18 of 54

19 5.3.2 Removal of sewage system All liquid and solid waste to controlled pumped Transport Clean vehicles of dirt, if required, to prevent transport of material off site. Any spillages to be cleaned as quickly as practicable. Cover all loads securely. Chemical drums for disposal to be transported in accordance with the Dangerous Good Act Disposal receipts must be collected from landfill and returned to Foreman for each load Personnel No unauthorised personnel (i.e. not directly involved with the work) should enter excavation. Avoid direct contact with any contaminated soil or water that has come into contact with contaminated soil. Eating, drinking, smoking or any other hand to mouth practice should be avoided. Wash hands with cleaning agent prior to eating or drinking. Boots to be cleaned before leaving site. Symptoms of chemical exposure including headache, dizziness, nausea and irritation of the respiratory tract, eyes or skin should be reported to the Foreman or the first aider. 5.4 Refuelling or maintenance and clean of plant and equipment Fuel cart/truck operator and mechanic to contact BMD foreman on arrival before entering site to determine whether site access is permitted and the locations of plant and equipment for refuelling. Fuel cart/truck and mechanic to park parallel to the plant or equipment, away from any other obstructions. Refuelling and maintenance of all plant and equipment must be conduct on level impermeable surface, where possible. Plant or equipment must be switch-off before and during refuelling operation and maintenance. No refuelling or maintenance of plant and equipment near drainage inlets or the like, including swale drains and sediment basins. Spill kit, Safety Data Sheet and fire extinguisher must be accessible on the fuel cart/truck and mechanical truck. Drip tray or absorbent pads to be placed underneath where the nozzle refuels the machine/plant to contain leaks, including extracting oil and changing filters during maintenance. Dispose all waste material in accordance with legislative requirements. If a spill or leak occurs, contact BMD foreman who will inform BMD ESR for an initial investigation to determine the severity of the incident. RMS will be notified of the incident immediately, and written notification will be forwarded to the RMS within 24 hours. Designated concrete washout facility will be provided onsite or concrete agitators will be instructed to return back to their concrete batch yard for washout. Bitumen spray bars and asphalt pavers to cleaned of loose material at a location away from waterways before leaving site. Check and clean tyres before leaving site to minimise tracking of material on to public road. 5.5 Sediment control resulting from large rainfall events In the case of an environmental emergency event the Foreman shall be notified immediately and the following procedures shall be followed. Personal safety shall be given priority under all circumstances. Check all erosion and sediment control devices for conformance Diversion drains shall be cut into exposed batter slopes to direct sheet flows and divert concentrated runoff to stabilised channels. Rev. G (15/06/2017) Page 19 of 54

20 Emergency silt fence, straw bales, diversion drains or water runoff velocity check dams shall be placed to minimise impact. 5.6 Laden dirty water runoff, resulted from a unforeseeable event Such event may be a failed valve or gasket connected to an existing old watermain. Water cart and / or sucker truck to be available for immediate use to remove turbid water Stockpile of sandbags available to be used to create a dam like structure or diversion drain to minimise the turbid water from entering any waterbody or stormwater drains Contact Sydney Water immediately to provided assist by shutting down watermain upstream and downstream. 5.7 Excessive Dust In the case of excessive dust, water shall be applied to the areas causing dust problems. Operations shall not cease until such time as dust generation is controllable. Consider wind direction, strength and location of sensitive receptors. Utilise appropriate dust minimisation measures such as scraping haul roads / cuts to underlying wetter layers, proactive shut down of areas not being worked for extended periods of time, or using dust suppressing additives in water carts. 5.8 Bush Fire Should a bush or grass fire occur the local fire authorities shall be contacted. Water trucks may also be used, when safe, to assist in the case of such an event. 5.9 Injured animals Any fauna injured as a result of work operations should be notified to the ESR who will contact WIRES or the local vet (as per Flora and Fauna management Plan). A list of names and phone numbers of emergency services is prominently displayed in the Site Office, and crib hut for quick reference in the event of an emergency. The importance of this emergency response plan shall be reiterated during toolbox talks Early Warnings and Communications to Neighbours Key stakeholders and residents were sent a community update in January 2015 detailing the commencement and breakdown of project stages of the Bringelly Road Upgrade Stage 1. RMS have and will continue to provide key stakeholders and residents of project updates via the monthly Community Update newsletter. The will prepare an environment Action Table as part of the CEMP that details the cases where contact with community may be needed and how this contact will be managed. The project map in the Emergency Spill Response Plan shows the location of neighbouring properties. An assessment of the typical pollution incident types has been undertaken to consider the potential impacts on neighbours. This resulted in the early warning actions located in Table 7 below. Table 6 List of Typical Main Pollutants and Potential Neighbour Impacts and Early Warnings Air Based Emissions Description Potential Risks Early Warning actions Dust Air quality issues Loss of amenity Community complaints In extreme cases contact neighbours via doorknock process and ask them to close windows and doors and stay inside until further notice Rev. G (15/06/2017) Page 20 of 54

21 Fire Noise Odour Air quality issues Threat to safety Loss of amenity Community complaints Air quality issues Loss of amenity Community Complaints Spill type emissions Fuel including Water quality issues if spill enters waterway diesel and petrol Community complaints based fuels Lubricants and hydraulic oils Pesticides Paints and surface coatings Concrete alkali washings Bitumen and cutting products Other chemicals Soils and erosion Bentonite slurry Contaminated materials uncovered Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints In extreme cases contact neighbours via doorknock process and ask them to close windows and doors and stay inside until further notice. For larger fires, coordinate with combat agencies. Not required under PIRMP. Communicate with neighbours on as needs basis as per CEMP In extreme cases contact neighbours via doorknock process and ask them to close windows and doors and stay inside until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice. For larger spills coordinate with combat agency. In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice. For larger spills coordinate with combat agency. In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice Rev. G (15/06/2017) Page 21 of 54

22 Wastes Tannins Water quality issues if spill enters waterway Community complaints Water quality issues if spill enters waterway Community complaints In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice In extreme cases contact neighbours via doorknock process and ask them to avoid use of the water until further notice Ongoing community relations under the CEMP will ensure the community is kept up to date on pollution incidents and other matters. Such actions will also advise on the website information and how to respond to such incidents if required Website information This Pollution Incident Response Management Plan (PIRMP or Plan) will be uploaded on to the project BMD website as a requirements under the Protection of the Environment Operations Act 1997 (POEO Act) and the Protection of the Environment Operations (General) Regulation 2009 s98d: (2) A plan is also to be made publicly available in the following manner within 14 days after it is prepared: (a) in a prominent position on a publicly accessible website of the person who is required to prepare the plan, (b) if the person does not have such a website--by providing a copy of the plan, without charge, to any person who makes a written request for a copy. 3) Subclause (2) applies only in relation to that part of a plan that includes the information required under: (a) section 153C(a) of the Act, and (b) clause 98C (1) (h) and (i) or (2) (b) and (c) (as the case requires). The internet link below is where the PIRMP can be download and viewed by the public. Rev. G (15/06/2017) Page 22 of 54

23 Availability and Location of This Plan The POEO (General) Regulation 2009 s98d(1) states: (1) A plan is to be made readily available: (a) to an authorised officer on request, and (b) at the premises to which the relevant licence relates, or where the relevant activity takes place, to any person who is responsible for implementing the plan. This Plan is located at: The BMD Site office On the BMD project webpage ( In any event the availability of this Plan will be made available by locating printed copies in the same locations as the Environment Protection Licence (EPL) is located Privacy Protection Unlike the EPL this Plan is to only be available to those who are to implement the Plan. This is made clear by The POEO (General) Regulation 2009 s98d(3) which States 4) Any personal information within the meaning of the Privacy and Personal Information Protection Act 1998 is not required to be included in a plan that is made available to any person other than a person referred to in subclause (1). Where components of the Plan are considered to contain sensitive private information then only those cleared should be permitted access to the full Plan. Alternative Plans with such sensitive information removed (e.g. contact phone numbers and names) can be more widely distributed. Full plans will be made available to the relevant government agencies, on request or during an incident response activity. 6 Training Summary and Reference to Project Procedure As part of RMS G36 Environmental Protection (Management Systems) the Contractor s Environment Management Plan the following induction and training must include where applicable the following: Purpose and objections of the CEMP Requirement of due diligence and duty of care Condition of environmental licenses, permits and approvals Environmental emergency plans Management and reporting processes for environmental incidents Lessons leant from environmental incidents Environmental controls that are identified in the CEMP and its supplementary plan Site specific issues including, but not limited to erosion and sediment control, boundaries for vegetation clearing, locations of refuse bins, washing, refueling and maintenance of vehicles, plant and equipment. Environmentally sensitive areas Use of spill kits to contain any chemical, fuel or oil spills To also satisfy the requirements under this PIRMP the training is to also include: Awareness of the PIRMP Where this Plan can be accessed Pollution incident classification and reporting under this plan Spill response actions under this plan Other incident response actions under this plan Rev. G (15/06/2017) Page 23 of 54

24 Early warnings internally and to neighbours where appropriate Specific procedures in dealing with potential pollution incidents e.g. pump out of sedimentation basins Section 13 of the CEMP outlines the requirement for all project personnel, subs, consultants and visitors to be familiar with the environmental management obligations and requirements of the project, especially the requirements of this plan. The information will be communicated at the site specific induction, on occasion a specific environmental training (as per Table 14 of the CEMP) will be carried out, discussed at the daily site briefing, and monthly mentioned at toolbox talks. All records of induction, training, site briefing and toolbox talks will be held on file for at least four years after the date of Final Completion and will be available to the RMS and to the EPA officers on request. 7 Updating of Plan Effective date: April 2015 Review date This Plan will be updated according to the following: One month after the Contractor Environment Management Plan has been accepted by RMS; or 12 months from the last update; or Within one month of a Category 1 Incident; or As identified after testing of the Plan (see section 8). 8 Testing and Implementation 8.1 Testing of the PIRMP The POEO (General) Regulation E states for testing of the Plan: 1) The testing of a plan is to be carried out in such a manner as to ensure that the information included in the plan is accurate and up to date and the plan is capable of being implemented in a workable and effective manner. 2) Any such test is to be carried out: (a) routinely at least once every 12 months, and (b) within 1 month of any pollution incident occurring in the course of an activity to which the licence relates so as to assess, in the light of that incident, whether the information included in the plan is accurate and up to date and the plan is still capable of being implemented in a workable and effective manner Testing of the Plan will be integrated into other emergency and incident testing and training programs. Testing of the Plan cannot be properly undertaken or designed until the CEMP has been prepared for that Stage of development of the project. Initial testing of the plan will be undertaken within 6 months of the acceptance of the CEMP. Design of the testing will be undertaken 1 month before the testing is conducted. Records of the testing will be required by the RMS on the. Testing dates This Plan will be updated according to the following: Initially 6 months month after the Contractor Environment Management Plan has been accepted by RMS, or 12 months from the last update, or Design of the testing method will be 1 month before the initial test date Or before one month after a Category 1 Incident. Rev. G (15/06/2017) Page 24 of 54

25 Further details will be available under the Incident and Emergency Response Management Plan for the Project. Recording of Testing A detailed record of the testing of the Plan will be prepared after each testing of the plan is undertaken. If the test identifies any shortcomings in the Plan, especially the implementation of the spill response procedures, the Plan will be corrected or appropriate non-conformance actions will be undertaken. This plan was last tested in June Implementation of the Plan The POEO Act 1997 s 153F requires the Plan be implemented if a pollution incident occurs. A pollution incident is defined under clause 147 of part 5.7 of the POEO Act 1997 as: Meaning of material harm to the environment 1. For the purposes of this Part: a. harm to the environment is material if: i. it involves actual or potential harm to the health or safety of human beings or to ecosystems that is not trivial, or ii. it results in actual or potential loss or property damage of an amount, or amounts in aggregate, exceeding $10,000 (or such other amount as is prescribed by the regulations), and b. loss includes the reasonable costs and expenses that would be incurred in taking all reasonable and practicable measures to prevent, mitigate or make good harm to the environment. 2. For the purposes of this Part, it does not matter that harm to the environment is caused only in the premises where the pollution incident occurs. $2 million maximum fines apply for failing to implement the Plan. Hence if a pollution incident occurs: It must be responded to according to this Plan and its reference documents. An incident response report/audit must be completed Rev. G (15/06/2017) Page 25 of 54

26 Appendix 1 Project Map Rev. G (15/06/2017) Page 26 of 54

27 Bonds Creek Northern Site Facility Fuel Storage Facility SCA Upper Canal Kemps Creek Main Site Compound Scalabrini Creek EPL Boundary Rev. G (15/06/2017) Page 27 of 54

28 Appendix 2 Risk Assessments This Plan uses a risk assessment process to demonstrate the existing risk control methods are effective in preventing and minimising environmental harm from pollution incidents. If unacceptable risks are identified new control measures will be introduced. The modular format permits the use of common activities associated with road construction to be used in future PIRMP documents. The modules used for this Plan for the Project include: Clearing and grubbing Road construction Soil and water management Chemical storage and use Each module uses a standard risk matrix used by RMS in its REF. Each module lists the type of use or storage for the pollutant/s being considered. Each of the above is considered for a range of hazards and their control method considered. Also considered in the above process is: Risk Matrix Impact on neighbours Safety Location If the pollutant is a hazardous chemical Environmental risks associated with RMS and its s activities use the following table. RMS Environmental Risk Matrix Severity (level of impact) Insignificant Minor Moderate Major Catastrophic Probability (Likelihood) 5 Almost Certain H H E E E 4 Likely M H H E E 3 Moderate L M H E E 2 Unlikely L L M H E 1 Rare L L M H H Risk Factors: E =Extreme, H = High, M = Moderate, L = Low The hazards, likelihood and pre-emptive measures assessments which follow the above table in assessing the environmental risks associated with the hazards identified. Rev. G (15/06/2017) Page 28 of 54

29 Clearing and Grubbing Purpose This risk module forms part of the PIRMP for the Bringelly Road Upgrade Stage 1 project. The activities associated with this module are related only to clearing and grubbing. Activities Clearing and Grubbing involves: Clearing of vegetation Clearing of minor built structures Clearing of rubbish and other Grubbing of trees and stumps Mulching Stockpiling of mulch Removal of Mulch This risk module describes the main hazards to human health or the environment associated with clearing and grubbing. The first table in the risk module lists the potential pollutants. The second table describes the potential pollution incidents with pre-emptive actions to be taken to minimise or prevent any risk of harm to human health or the environment. In the case of actual or threatened material harm to the environment or human health procedures must be followed for contacting authorities as in RMS Environmental Incident Classification and Reporting Procedure. For incidents where pollution has the potential to impact on the community, early warning systems as described in section 6 of this document are to be initiated. Further details on the risk assessment and appropriate control methods can be found in the following documents: CEMP Review of Environmental Factors (REF) 2011 and addendum REF 2013 Environmental Work Method statements The module has been written to cover general environmental hazards and their controls. As the construction process is fluid, new documentation may better reflect the risks and controls. Primarily this will be captured in the CEMP. Rev. G (15/06/2017) Page 29 of 54

30 LIST OF POLLUTING SUBSTANCE STORAGES/USES AT SITE INITIAL ASSESSMENT CLEARING AND GRUBBING Project Name: Bringelly Road Upgrade Stage 1 Responsible person: Engineers, Foreman, ESR Date March 2015 Name / description Hazardous Chemicals Amount stored Location of storage Map reference CHEMICALS (raw materials and products which can cause pollution) Need for early warning 1 Pre-emptive action ref Ref to safety coverage Noxious Weeds No variable variable variable no See CEMP, G36 N/A See item 1 Oils and fuel from vehicles Ref to Hazard and likelihood assessment Yes < 1000 L variable variable no See CEMP, G36 See SMP See road construction and chemical module MATERIALS (eg stockpiles, silos, bulk solids etc.) Mulch no variable variable variable Only in extreme wind where dust threatens to impact on community Soil Erosion no variable variable variable Only in extreme cases where erosion materials threaten to impact on health of waterway rubbish and other Only for asbestos waste Unexpected find of contaminates Asbestos containing materials variable variable variable If asbestos is found and fibres enter waterway or become airborne and threaten to impact on community variable variable variable If asbestos is found to be airborne, it may impact See CEMP, G36, G38 See CEMP, G36, G38 See CLMP, G36 See CLMP, G36 CEMP, SWMP, CEMP, SWMP, N/A See item 2 and 3 N/A See item 4 See SMP See item 5 See SMP See item 6 1 Early warnings relate to informing neighbors who may be affected by the emission of this substance. If this substance is of a type and quantity which may reach neighbors then early warning assessment of actions is required to be undertaken. Rev. G (15/06/2017) Page 30 of 54

31 the environment and community. Rev. G (15/06/2017) Page 31 of 54

32 HAZARD AND LIKELY HOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES CLEARING AND GRUBBING Project Name: Bringelly Road Upgrade Stage 1 Responsible person: Engineers, Foreman, ESR Date March 2015 Name / ref of pollutant/ chemicals 1.Noxious weeds Description of Hazard / Incident leading to hazard Improper disposal of noxious weeds causing contamination of land Level of impact Likely hood Priority Impact on neighbours 2.Mulching Generation of dust 2 3 M Unlikely but possible Control Measures Corrective Action 2 2 L Negligible. Contractor to remove and dispose in accordance with Camden council regulations Staff training CEMP G to write clearing and grubbing plan Contractor waste management plan Ecologist report prepared on location of weeds and marked in drawings as per G40 CEMP clearing and grubbing plan Staff training Responsible Person Generation of tannins contaminating waterway with high BOD 3 3 H Unlikely but possible Reduce volume of mulch to be managed at any one time -RMS Enviro Direction Management of Tannins from Vegetation Mulch CEMP Staff Training 3.Mulch Stockpiling Dust 2 3 M Unlikely but possible CEMP clearing and grubbing plan RMS Stockpile site management guideline EMS-TG-10 Staff training Rev. G (15/06/2017) Page 32 of 54

33 Name / ref of pollutant/ chemicals 3.Mulch Stockpiling Description of Hazard / Incident leading to hazard Generation of tannins contaminating waterway with high BOD Level of impact Likely hood Priority Impact on neighbours 3 3 H Unlikely but possible Control Measures Corrective Action Reduce volume of mulch to be managed at any one time -RMS Enviro direction Management of Tannins from Vegetation Mulch Stockpile management plan and layout to be developed prior to stockpiling to ensure location of piles. Responsible Person CEMP Staff Training Fire 3 2 M Unlikely but possible RMS Stockpile site management guideline EMS-TG-10 CEMP Staff Training in turning stockpiles 4.Soil Erosion Erosion from cleared land entering waterway 3 2 M Unlikely but possible clearing not to be done within 15m water courses until immediately before construction in that area CEMP soil and water plan G38 Erosion and sediment control 5.Rubbish and other Improper disposal of waste causing contamination of land or water 2 2 L Unlikely but possible Contractor to remove and dispose in accordance with council regulations Staff training CEMP G40 to write clearing and grubbing plan Contractor waste management plan 6. Unexpected find of contaminates Clearing of vegetation, topsoil stripping, and illegal dumping 3 2 M Unlikely but possible Unexpected Discovery of Contamination Procedure to be enacted Staff training Rev. G (15/06/2017) Page 33 of 54

34 Contaminated Land Management Plan Soil and Water Management Plan Name / ref of pollutant/ chemicals 7.Plant and equipment leaks and spills Description of Hazard / Incident leading to hazard Spills into waterways from plant and equipment (e.g. hydraulic hose leaks, concrete loading, leaks from vehicles and road plant.) Level of impact Likely hood Priority Impact on neighbours 3 3 H May impact on surface water quality if it goes off site Control Measures Corrective Action Project Team to ensure that chemical, fuel and lubricant storage areas must be suitably located inside a HazChem container in a secure protected area with an impermeable floor to minimise the impact of any spillage or contamination on the Site and adjoining areas. The HazChem container must be able to contain 120% of the total volume of the stored materials. Do not locate storage areas within 40 metres of natural or built drainage lines, flood prone areas, or on slopes steeper than 1:10. The Hazchem container is be located within the boundary of the main site compound and at nominated satellite site facilities. A fully equip spill kit shall be available and accessible and all the material safety data information for any chemical or fuel to be used or stored adjacent to the HazChem container. Responsible Person Contractor Sedimentation basins act as capture / additional containment Spill response measures implemented as per CEMP or Appendix 3 of this Plan Auditing of implementation of G36 by Rev. G (15/06/2017) Page 34 of 54

35 Soil and Water Management Purpose This risk module forms part of the PIRMP for the Bringelly Road Upgrade Stage 1 project. The activities associated with this module are related only to soil and water management. Activities Soil and water management involves: waste water discharge from dewatering, surface washing, grit blasting, saw cutting, drilling, washing vehicles and plant, batching plants, casting yards, washing out of concrete mixers and concrete trucks and any other activities which add pollutants to water; prevention of mud and litter being deposited on trafficked roadways; maintenance and cleaning of sediment control works; protection of soil and other stockpiles from erosion by wind and rain; extraction of water for construction purposes; and excavation in waterways. management of any sedimentation basins including measures for flocculation and dewatering Sensitive crossings This risk module describes the main hazards to human health or the environment associated with soil and water management. The first table in the risk module lists the potential pollutants. The second table describes the potential pollution incidents with pre-emptive actions to be taken to minimise or prevent any risk of harm to human health or the environment. In the case of actual or threatened material harm to the environment or human health procedures must be followed for contacting authorities as in RMS Environmental Incident Classification and Reporting Procedure. For incidents where pollution has the potential to impact on the community, early warning systems as described in section 6 of this document are to be initiated. Further details on the risk assessment and appropriate control methods can be found in the following documents: CEMP Review of Environmental Factors (REF) 2011 and addendum REF 2013 Environmental Work Method statements The module has been written to cover general environmental hazards and their controls. As the construction process is fluid, new documentation may better reflect the risks and controls. Primarily this will be the CEMP, sub-plans and/or Environmental Work Method Statements. Rev. G (15/06/2017) Page 35 of 54

36 LIST OF POLLUTING SUBSTANCE STORAGES/USES AT SITE INITIAL ASSESSMENT SOIL AND WATER MANAGEMENT Site Name: Bringelly Road Upgrade Stage 1 Responsible person: Engineer, Foreman, ESR Date March 2015 Name / description Hazardous Chemicals Amount stored Location of storage CHEMICALS (raw materials and products which can cause pollution) Map ref Need for early warning* hydrocarbon spills Yes variable variable variable Only in extreme cases where spills threaten to impact on health of waterway stabilised pavements precoat aggregates and spray sealing No variable variable variable Only in extreme cases where spills threaten to impact on health of waterway Yes variable variable variable Only in extreme cases where spills or run off threaten to impact on health of waterway Bentonite slurry No variable variable variable Only in extreme cases where spills or run off threaten to impact on health of waterway MATERIALS (eg stockpiles, silos, bulk solids etc.) sediment no variable variable variable Only in extreme cases where sediment threatens Pre-emptive action ref Ref to safety coverage See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, Environmental Fact Sheet 09 plant refuelling, RTA environmental handbook for road and bridge works See CEMP, G36, RTA Environmental Handbook for road and bridge works See CEMP, G36, RTA Environmental Handbook for road and bridge works See CEMP, G36, RTA Environmental Handbook for road and bridge works See CEMP, G36, RTA Environmental Handbook for road and bridge works See SMP See SMP See SMP See SMP Ref to Hazard and likelihood assessment See chemical module, road construction module and item 1. See chemical module See chemical module and items 1 and 3 See chemical module N/A See items And 3. Rev. G (15/06/2017) Page 36 of 54

37 to impact on health of waterway Name / description earthworks in soils with naturally occurring issues such as acid sulphate soils, saline soils or high levels of other sulphide minerals (which may result in high concentrations of heavy metals in runoff). Hazardous chemical Amount stored Location of storage Map ref Need for early warning no variable variable variable Only in extreme cases where odour threatens to impact on community or run off materials threaten to impact on waterway Pre-emptive action ref Ref to safety coverage See CEMP, G36, RTA Environmental Handbook for road and bridge works N/A See item 4 Ref to Hazard and likelihood assessment general earthworks in soils with contamination issues no variable variable variable Only in extreme wind where dust threatens to impact on community or erosion materials threaten to impact on waterway See CEMP, G36, RTA Environmental Handbook for road and bridge works See SMP See item 5 concrete works (including batching operations) variable variable variable Only in extreme cases where spills threaten to impact on health of waterway See CEMP, G36, RTA Environmental Handbook for road and bridge works See SMP See item 6 Rev. G (15/06/2017) Page 37 of 54

38 Name / description Hazardous chemical Amount stored Location of storage AQUEOUS (eg dams, wastewater tanks, other water storage area) waste water discharge from surface washing waste discharge dewatering water from waste water discharge from grit blasting waste water discharge from saw cutting waste discharge drilling water from Only if it contains a hazardous chemical spill Only if it contains a hazardous chemical spill Map ref Need for early warning variable variable variable Only in extreme cases where spills threaten to impact on health of waterway variable variable variable Only in extreme cases where spills threaten to impact on health of waterway no variable variable variable Only in extreme cases where spills threaten to impact on health of waterway no variable variable variable Only in extreme cases where spills threaten to impact on health of waterway no variable variable variable Only in extreme cases where spills threaten to impact on health of waterway Pre-emptive action ref See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works Ref to safety coverage Ref to Hazard and likelihood assessment N/A See items And 3. N/A See items And 3. N/A See items And 3. N/A See items And 3. N/A See items And 3. Rev. G (15/06/2017) Page 38 of 54

39 Name / description waste discharge washing and plant water from vehicles waste water discharge from batching plants, waste discharge casting yards water from washing out of concrete mixers and concrete trucks waste water discharge from any other activities which add pollutants to water Hazardous chemical Amount stored Location of storage Map ref Need for early warning no variable variable variable Only in extreme cases where spills threaten to impact on health of waterway Pre-emptive action ref See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works Ref to safety coverage Ref to Hazard and likelihood assessment (next table) See COH and SMP See items And 3. no N/A N/A N/A N/A N/A N/A N/A no N/A N/A N/A N/A N/A N/A N/A no variable variable variable Only in extreme cases where spills threaten to impact on health of waterway no variable variable variable Only in extreme cases where spills threaten to impact on health of waterway See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works See CEMP, G36, Environmental Fact Sheet 03 Spill Management and Response, RTA Environmental Handbook for road and bridge works N/A See items And 3. See COH and SMP See items And 3. Rev. G (15/06/2017) Page 39 of 54

40 Name / description Hazardous chemical Amount stored Location of storage Map ref SUBSTANCES IN PROCESSES (substances which could be emitted) rubbish and litter Only for asbestos waste Need for early warning variable variable variable If asbestos is found and fibres enter waterway or become airborne and threaten to impact on community Pre-emptive action ref Ref to safety coverage Ref to Hazard and likelihood assessment See CEMP, G36 See SMP See item 5 * Early warnings relate to informing neighbours who may be affected by the emission of this substance. If this substance is of a type and quantity which may reach neighbours then early warning assessment of actions is required to be undertaken. HAZARD AND LIKELIHOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES SOIL AND WATER MANAGEMENT Site Name: Bringelly Road Upgrade Stage 1 Responsible person: Engineer, Foreman, ESR Date March 2015 Name / ref of pollutant/ chemicals 1.Wastewater discharge off site from sediment basins Description of Hazard / Incident leading to hazard Insufficient treatment with gypsum leading to Breach of EPA licence limit of Solids 50mg/L Level of impact Likely hood Priority Impact on neighbours 4 4 E Unlikely but possible Control Measures Corrective Action CEMP and SWMP, G38 Use of BLUE BOOK during design Staff induction and training Environment Incident Classification and reporting procedure Responsible Person Incorrect lime or HCl addition leading to low ph discharge and breach of EPA licence 4 2 H Unlikely but possible CEMP and SWMP, G38 Use of BLUE BOOK during design Staff induction and training Environment Incident Classification and reporting procedure Rev. G (15/06/2017) Page 40 of 54

41 Incorrect lime or HCl addition leading to high ph discharge and breach of EPA licence 4 2 H Unlikely but possible CEMP and SWMP, G38 Use of BLUE BOOK during design Staff induction and training Environment Incident Classification and reporting procedure Insufficient oil/grease removal leading to breach of EPA licence condition of no visible oil/grease 4 3 E Unlikely but possible CEMP and SWMP, G38 Use of BLUE BOOK during design Staff induction and training Environment Incident Classification and reporting procedure 1.Wastewater discharge off site from sediment basins cont. Discharge of chemical spill material from sediment basin eg pesticides 5 1 H possible CEMP and SWMP, G38 Use of BLUE BOOK during design Staff induction and training Environment Incident Classification and reporting procedure Pumping of water containing solids higher than 50 mg/l eg by pump being left unattended 4 4 E possible CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure 2.Wastewater overflow from sediment basins Failure / collapse of basin wall causing sediment laden material to move off site Failure / collapse of basin wall causing excessive erosion Failure/ collapse of basin wall causing contamination of waterway 4 2 H Unlikely but possible 4 2 H Unlikely but possible 3 3 H Unlikely but possible 1.CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure 1.CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Rev. G (15/06/2017) Page 41 of 54

42 Environment Incident Classification and reporting procedure Insufficient emptying of basin prior to previous rain event causing overflow off site 2 2 L Unlikely but possible CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure Rev. G (15/06/2017) Page 42 of 54

43 HAZARD AND LIKELY HOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES SOIL AND WATER MANAGEMENT Name / ref of pollutant/ chemicals 2.Wastewater overflow from sediment basins cont. Description of Hazard / Incident leading to hazard Insufficient emptying of basin prior to previous rain event causing overflow off site Extreme rain event causing overflow off site Overflow of basin containing chemical spill leaving site Overflow incident contained on site Level of impact Likely hood Priority Impact on neighbours 2 2 L Unlikely but possible 1 2 L Unlikely but possible 4 1 H Unlikely but possible Control Measures Corrective Action CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure 4 1 M no CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting p Responsible Person Rev. G (15/06/2017) Page 43 of 54

44 HAZARD AND LIKELY HOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES SOIL AND WATER MANAGEMENT Name / ref of pollutant/ chemicals 3.Untreated run off 4.Acid sulphate soils Description of Hazard / Incident leading to hazard Failure of erosion or sediment controls causing sediment laden material to leave site Failure of erosion or sediment controls but run off remains on site Acid sulphate soils not identified and run off leaves site and contaminates land Acid sulphate soils not identified and run off leaves site and contaminates waterway Level of impact Likely hood Priority Impact on neighbours 3 3 H Unlikely but possible Control Measures Corrective Action CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training Environment Incident Classification and reporting procedure 2 3 M no CEMP and SWMP, G38 Use of BLUE BOOK during design regular inspections Staff induction and training 4 2 H Unlikely but possible 4 2 H Unlikely but possible Environment Incident Classification and reporting procedure CEMP and SWMP, G38 Staff induction and training Environment Incident Classification and reporting procedure RTA Environmental Handbook for road and bridge construction CEMP and SWMP, G38 Staff induction and training Environment Incident Classification and reporting procedure RTA Environmental Handbook for road and bridge construction Responsible Person Rev. G (15/06/2017) Page 44 of 54

45 HAZARD AND LIKELY HOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES SOIL AND WATER MANAGEMENT Name / ref of pollutant/ chemicals 5.Rubbish and other 6. concrete first flush Description of Hazard / Incident leading to hazard Improper disposal of waste material found in soil, causing contamination of land or water Not reused in plant or treated in situ and leaves site causing contamination of land Discharged to sediment basin and contaminates waterway Level of impact Likely hood Priority Impact on neighbours 3 2 M Unlikely but possible Control Measures Corrective Action Contractor to remove and dispose in accordance with council regulations Staff induction and training CEMP and SWMP, G38 Contractor waste management plan Environment Incident Classification and reporting procedure 2 3 M no CEMP and SWMP, G38 Staff induction and training Washout facility provided onsite or instruct concrete agitator truck to wash at their concrete batch yard. Environment Incident Classification and reporting procedure 3 3 H Unlikely but possible CEMP and SWMP, G38 Staff induction and training Washout facility provided onsite or instruct concrete agitator truck to wash at their concrete batch yard. Environment Incident Classification and reporting procedure Responsible Person Rev. G (15/06/2017) Page 45 of 54

46 HAZARD AND LIKELY HOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES SOIL AND WATER MANAGEMENT Name / ref of pollutant/ chemicals 7.Plant and equipment leaks and spills Description of Hazard / Incident leading to hazard Spills into waterways from plant and equipment (e.g. hydraulic hose leaks, concrete loading, leaks from vehicles and road plant.) Level of impact Likely hood Priority Impact on neighbours 3 3 H May impact on surface water quality if it goes off site Control Measures Corrective Action G-36 s6.12 requires: CEMP to ensure that chemical, fuel and lubricant storage areas must be suitably located inside a HazChem container in a secure protected area with an impermeable floor to minimise the impact of any spillage or contamination on the Site and adjoining areas. The HazChem container must be able to contain 120% of the total volume of the stored materials. Do not locate storage areas within 40 metres of natural or built drainage lines, flood prone areas, or on slopes steeper than 1:10. The Hazchem container is be located within the boundary of the main site compound and at nominated satellite site facilities. A fully equip spill kit shall be available and accessible and all the material safety data information for any chemical or fuel to be used or stored adjacent to the HazChem container. Responsible Person Contractor Sedimentation basins act as capture / additional containment Spill response measures implemented as per CEMP or s4.5 of this Plan Auditing of implementation of G36 by 8.Sensitive Crossings Contamination of waterway during construction activities for crossing of waterway 4 3 E Possible Staging of construction activities Follow hierarchy of erosion prevention 1 st and trapping and removing sediment 2nd RTAs code of practice for Water Management CEMP Erosion and Sediment Control Plans, G38 Rev. G (15/06/2017) Page 46 of 54

47 Managing Urban Stormwater: Soils and Construction Vol 1 (Landcom 2004) Vol 2D Main Road Construction (DECCW, 2008) Progressive Erosion and Sediment Control Plans prepared and implemented prior to works commencing at or near waterways in accordance with relevant EWMS Rev. G (15/06/2017) Page 47 of 54

48 Road Construction Purpose This risk module forms part of the PIRMP for the Bringelly Road Upgrade Stage 1 project. The activities associated with this module are related only to Road Construction. Activities Road Construction: Excavation; Removal of material to spoil, filling, compacting, construction and trimming; paving; sweeping; Line marking Setting up site compound This risk module describes the main hazards to human health or the environment associated with road construction. The first table in the risk module lists the potential pollutants. The second table describes the potential pollution incidents with pre-emptive actions to be taken to minimise or prevent any risk of harm to human health or the environment. In the case of actual or threatened material harm to the environment or human health procedures must be followed for contacting authorities as in RMS Environmental Incident Classification and Reporting Procedure. For incidents where pollution has the potential to impact on the community, early warning systems as described in section 6 of this document are to be initiated. Further details on the risk assessment and appropriate control methods can be found in the following documents: CEMP Review of Environmental Factors Environmental Work Method statements The module has been written to cover general environmental hazards and their controls. As the construction process is fluid, new documentation may better reflect the risks and controls. Primarily this will be the CEMP. Rev. G (15/06/2017) Page 48 of 54

49 LIST OF POLLUTING SUBSTANCE STORAGES/USES AT SITE INITIAL ASSESSMENT ROAD CONSTRUCTION Site Name: Bringelly Road Upgrade Stage 1 Responsible person: Engineer, Foreman, ESr Date March 2015 Name / description Hazardous chemicals Amount stored Location of storage Map reference Need for early warning Pre-emptive action ref. Ref to safety coverage CHEMICALS (raw materials and products which can cause pollution) Oils and fuel from vehicles (bulk stores see chemicals section) Yes variable Up to 10,000L in tanker, 100L max in plant, 20L container In tankers, mobile plant and equipment, HazChem container Only when spill occurs directly into waterways leaving site. Rare event MATERIALS (eg stockpiles, silos, bulk solids etc.) Fill No variable variable variable Only in extreme wind where dust threatens to impact on community Road base No variable variable variable Only in extreme cases where erosion materials threaten to impact on health of waterway Sand and Gravel No variable variable variable Only in extreme wind where dust threatens to impact on community Bitumen and asphalt Partial Yes for hot mix Class 9 variable variable variable Only in extreme wind where dust threatens to impact on community Ref to Hazard and likelihood assessment See CEMP, G36 See SMP Plant and equipment or See chemical module for bulk quantities See CEMP, G36 See SMP See item 1, 2, 3 See CEMP, G36 See SMP See item 1, 2, 3 See CEMP, G36 See SMP See item 1, 2, 3 See CEMP, G36 See SMP See item 4 Concrete No variable variable variable No See CEMP, G36 See SMP See item 4 Line marking paint/ surface coatings Yes possibly Class 3 variable variable variable No See CEMP, G36 See SMP See chemicals module details Rubbish and See CEMP, G36 See SMP other Only for asbestos waste variable variable variable Low Waste materials are generally solid. Litter or spills in to waterways most at issue. * Early warnings relate to informing neighbours who may be affected by the emission of this substance. If this substance is of a type and quantity which may reach neighbours then early warning assessment of actions is required to be undertaken. Rev. G (15/06/2017) Page 49 of 54

50 HAZARD AND LIKELY HOOD RISK ASSESSMENT AND CORRECTIVE CONTROL MEASURES ROAD CONSTRUCTION Name / ref of pollutant/ chemicals 1.Earthmoving: Road base Sand Gravel and soils during movement Description of Hazard / Incident leading to hazard Potential impacts on waterways from erosion, contamination, etc. From various activities e.g. culvert extension and reconstruction, sediment basins, spills Level of impact Likely hood Priority Impact on neighbours 3 2 M Unlikely but possible Control Measures Corrective Action 1. CEMP soil and water plan 2. G38 Erosion and sediment control 3. Staff training Responsible Person 2.Stockpiles: Road base Sand Gravel And soils Erosion and Sediment 3.Dust from Earth-moving and stockpiles Large scale excavation works, large batters, Spoil Stockpiling, Road Base Stockpiling, Sand and gravel Stockpiling Dust due to Large scale excavation works and Stockpiles 3 3 H Unlikely but possible 1. CEMP 2. RMS Stockpile site management guideline EMS-TG Staff training 4. G38 Erosion and Sediment Control 4 2 H Likely 1. CEMP 2. G38 Erosion and sediment control 3. RMS Stockpile site management guideline EMS-TG Staff training Rev. G (15/06/2017) Page 50 of 54

51 Name / ref of pollutant/ chemicals 4.Plant and equipment leaks and spills Description of Hazard / Incident leading to hazard Spills into waterways from plant and equipment (e.g. hydraulic hose leaks, concrete loading, leaks from vehicles and road plant.) Level of impact Likely hood Priority 3 3 H Impact on neighbours May impact on surface water quality if it goes off site Control Measures Corrective Action G-36 s6.12 requires: CEMP to ensure that chemical, fuel and lubricant storage areas must be suitably located and HazChem container in a secure protected area with an impermeable floor to minimise the impact of any spillage or contamination on the Site and adjoining areas. The bunded area must be able to contain 120% of the total volume of the stored materials. Do not locate storage areas within 40 metres of natural or built drainage lines, flood prone areas, or on slopes steeper than 1:10. The Hazchem container is be located within the boundary of the main site compound and at nominated satellite site facilities. A fully equip spill kit shall be available and accessible and all the material safety data information for any chemical or fuel to be used or stored adjacent to the HazChem container. Sedimentation basins act as capture / additional containment Spill response measures implemented as per CEMP or s4.5 of this Plan Auditing of implementation of G36 by Responsible Person Contractor 5.Setting up site compound Litter or sewerage causing pollution of land or waterway 2 2 L Negligible G4 CEMP Licence sewage sucker truck to be engaged. Contractor Erosion run off from clearing of land 2 3 M Unlikely 1. G4 2. CEMP Contractor Dust from vehicles 2 3 M Unlikely 1. Sealed access roads 2. Gravel parking areas 3. G4 4. CEMP Contractor Rev. G (15/06/2017) Page 51 of 54

52 Appendix 3 St John s Ambulance First Responder Chart Rev. G (15/06/2017) Page 52 of 54

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

Pollution Incident Response Management Plan. Newell Highway Trewilga Realignment

Pollution Incident Response Management Plan. Newell Highway Trewilga Realignment Pollution Incident Response Management Plan Newell Highway Trewilga Realignment Contents 1 Introduction... 2 1.1 Purpose and scope... 2 2 Statutory requirements... 3 2.1 Project approval... 3 2.2 Protection

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

Site EMP Kit- Guidance Notes

Site EMP Kit- Guidance Notes Site EMP Kit- Guidance Notes Introduction This Guide has been designed to assist applicants to understand council s requirements for Site Environmental Management Plans (Site EMP s) for subdivisions. The

More information

Water Pollution Control for Work in Sensitive Areas

Water Pollution Control for Work in Sensitive Areas Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Austral Masonry NSW Prospect (EPL# 4664)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Austral Masonry NSW Prospect (EPL# 4664) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Austral Masonry NSW Prospect (EPL# 4664) Adapted from Horsley Park to suit Prospect PIRMP by M. Burns Reviewed 7/10/2016 Pollution Incident Response Management

More information

Pollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 20 th September Seven Hills Asphalt PIRMP_V8.

Pollution Incident Response Management Plan. Seven Hills Asphalt. Version Seven: 20 th September Seven Hills Asphalt PIRMP_V8. Pollution Incident Response Management Plan Seven Hills Asphalt Version Seven: 20 th September 2016 Seven Hills Asphalt PIRMP_V8 1 of 31 DOCUMENT CONTROL SHEET Rev. Date Prepared by Approved By Revision

More information

AIRCRAFT MAINTENANCE PTY LTD

AIRCRAFT MAINTENANCE PTY LTD AIRCRAFT MAINTENANCE PTY LTD Operational Environmental Management Plan Prepared by Chief Engineer Date: 30 th December 2008 Version 1.0 INTRODUCTION is an aircraft engineering business that has been operating

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan EMP for the Stage 1 Construction and Operation of the Trainers Allotment Area at the Pakenham Racecourse located at Nar Nar Goon / Longwarry Road, Tynong Pty Ltd abn: 44 706

More information

SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) SOP-002 (OP) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) 1. PURPOSE Renewable Oil Services is licensed to conduct waste processing of hazardous and other wastes using non-thermal treatment and

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

Hazardous Waste Management

Hazardous Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK APPENDIX D Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project Description...

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a

More information

A positive, collaborative airport-wide approach is essential to minimise pollution. Heathrow Pollution Prevention Code of Practice

A positive, collaborative airport-wide approach is essential to minimise pollution. Heathrow Pollution Prevention Code of Practice A positive, collaborative airport-wide approach is essential to minimise pollution. Heathrow Pollution Prevention Code of Practice Contents EXECUTIVE SUMMARY 03 INTRODUCTION _ 1.0 04 GENERAL REQUIREMENTS

More information

TABLE OF CONTENTS. Process Owner: ESR Verifiers: Jenna Marett; Andrew Raal Status: Approved Version: 1.3 Issue Date: 07/01/2014 Page: 1 of 21

TABLE OF CONTENTS. Process Owner: ESR Verifiers: Jenna Marett; Andrew Raal Status: Approved Version: 1.3 Issue Date: 07/01/2014 Page: 1 of 21 PLN-08-004 TABLE OF CONTENTS 1. PURPOSE... 2 2. SCOPE... 2 3. RELATED DOCUMENTS... 2 4. Property Ownership... 3 5. DEFINITIONS... 3 5.1 Pollution Incident... 4 5.2 Major Pollution Incident... 4 5.3 Ranking

More information

INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016

INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016 INCIDENT RESPONSE MANAGEMENT PLAN MAY 2016 DOCUMENT CONTROL Document Controller: Resilience Coordinator Date of last update: May 2016 Date of next update: May 2017 HPRM reference: HW2007-900/27/9.009 Version

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Environmental Management Plan Attachment 5 Environmental Incident Response Plan

Environmental Management Plan Attachment 5 Environmental Incident Response Plan Victorian Desalination Plant Response Plan Document No: ENV-000-PL-005 This Document is the property of Watersure and is protected by copyright. Other than for the purposes and subject to the conditions

More information

Canberra Airport. Construction Environmental Management Plan for Airside works (EPBC 2008/4170 and EPBC 2009/4748)

Canberra Airport. Construction Environmental Management Plan for Airside works (EPBC 2008/4170 and EPBC 2009/4748) Canberra Airport Construction Environmental Management Plan for Airside works (EPBC 2008/4170 and EPBC 2009/4748) 3 February 2010 Canberra Airport 2010 Construction Environment Management Plan for Airside

More information

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities. Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems

More information

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary

More information

Central NSW Regional Contaminated Land Policy Template

Central NSW Regional Contaminated Land Policy Template Central NSW Regional Contaminated Land Policy Template Contamination Central: Supporting safe, stable and sustainable redevelopment of land in Central West NSW. Funded by the New South P a g e 1 {Instruction

More information

Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Attachment C Management of the Installation

Attachment C Management of the Installation Table of Contents Attachment C Management of the Installation C1.1 Organisational Chart C1.2 Quality, Safety and Environmental (QSE) Policy Statement C1.3 Roles & Responsibilities of Key Environmental

More information

Evaluation of Occupational Health & Safety Management System

Evaluation of Occupational Health & Safety Management System Section 1 Legal Obligation Employers have a duty of care to provide a safe workplace and systems of work, to consult with workers, to identify and manage workplace hazards and to keep them informed about

More information

WHS Management Plans

WHS Management Plans WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the

More information

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 NOVEMBER 2012 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041

Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041 Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041 March 2014 NSW Public Works Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 Level

More information

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY STATE OF COLORADO GENERAL PERMIT APPLICATION Updated 11/04 STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY This application is for use by all stormwater dischargers engaged in construction

More information

Date of Inspection 13/09/2017 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz Aaron Hawkins

Date of Inspection 13/09/2017 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz Aaron Hawkins Manildra Solar Farm ER Site Inspection Report Manildra Solar Farm Construction Environmental Representative (ER) Inspection Report For internal project use only. Document not for external release or use.

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Upgrade of Schofields Road between Tallawong Road and Veron Road. Pollution Incident Spill Response Plan

Upgrade of Schofields Road between Tallawong Road and Veron Road. Pollution Incident Spill Response Plan Upgrade of Schofields Road between Tallawong Road and Veron Road For NSW Roads and Maritime Services Pollution Incident Spill Response Plan Document No: 428 PL004-10 Copy No. Revision Registered Holder

More information

National self-insurer OHS management system audit tool. Version 3

National self-insurer OHS management system audit tool. Version 3 National self-insurer OHS management system audit tool Version 3 Release Date: 4 August 2014 Next Review Date: 2016 Approval Status: Prepared by: Approved by Heads of Workers Compensation Authorities WorkCover

More information

Waste Management Plan

Waste Management Plan Boral Cement Limited Berrima Works Waste Management Plan Document Filename: Document Owner: Approved By: CMT-ENV-006 Berrima Waste Management Plan HSE Advisor, Berrima Works Operations Manager, Berrima

More information

Environmental Management Programme (EMP)

Environmental Management Programme (EMP) Appendix D Environmental Management Programme (EMP) Please note that although Construction and Operational Phase measures are included in this EMP they are relevant to the issued Waste Management Licence

More information

The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations

The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations ENVIRONMENTAL MANAGEMENT 1 ENVIRONMENTAL CODE ADOPTION) E-10.22 REG 2 The Environmental Management and Protection (Saskatchewan Environmental Code Adoption) Regulations being Chapter E-10.22 Reg 2 (effective

More information

THE COMPLETE GUIDE TO ISO14001

THE COMPLETE GUIDE TO ISO14001 THE COMPLETE GUIDE TO ISO14001 1. Introduction... 3 Plan Do Check Act... 5 2. Requirements... 7 Environmental Policy... 7 Environmental Aspects... 7 Legal and Other Requirements... 8 Objectives & Targets...

More information

CONTRACTORS ENVIRONMENTAL RESPONSIBILITIES PACKAGE FOR: CONSTRUCTION, OPERATION, MAINTENANCE & SERVICE ACTIVITIES HIRED EQUIPMENT CONSULTANTS

CONTRACTORS ENVIRONMENTAL RESPONSIBILITIES PACKAGE FOR: CONSTRUCTION, OPERATION, MAINTENANCE & SERVICE ACTIVITIES HIRED EQUIPMENT CONSULTANTS CONTRACTORS ENVIRONMENTAL RESPONSIBILITIES PACKAGE FOR: CONSTRUCTION, OPERATION, MAINTENANCE & SERVICE ACTIVITIES HIRED EQUIPMENT CONSULTANTS Version February 2018 TABLE OF CONTENTS 1.0 Purpose... 1 2.0

More information

Construction Environmental Management Plan

Construction Environmental Management Plan Document Control Title: General Description: Document Path: Construction Environmental Management Plan Document No/Ref: NCX-LLB-07-0001-NN-PL-0001 Revision History Revision Date Description Section/Page

More information

Loy Yang B Environment Improvement Plan

Loy Yang B Environment Improvement Plan Loy Yang B Environment Improvement Plan 2017 Table of Contents 1 Endorsement 1 2 Environment Policy 2 3 Operating Arrangements 3 4 Site Management and Business Systems 4 5 Environmental Impacts and Risks

More information

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES

More information

Tighes Hill Remediation Project Update

Tighes Hill Remediation Project Update 3 September 2015 Tighes Hill Remediation Project Update This presentation includes forward-looking statements. Actual future conditions (including economic conditions, energy demand, and energy supply)

More information

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES 1. COVERAGE UNDER THIS GENERAL PERMIT Area of Coverage: This permit covers all areas of the Commonwealth

More information

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL 1st Edition January 2007 RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL GUIDANCE ON COMPLYING WITH THE OCCUPATIONAL HEALTH AND SAFETY (ASBESTOS) REGULATIONS 2003 The information presented in Recycling

More information

Appendix General Environmental Risk Analysis

Appendix General Environmental Risk Analysis Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified

More information

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control Inspecting Construction Site BMPs Kristin Kerr EOA, Inc. Outline of Presentation Back to Basics Erosion and Sediment Control Good Site Non-Stormwater Run-on and Run-off Control Construction Inspection

More information

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group Environmental Management System Integrated Pollution Control Document No. 5.2.1 Version no. 1 Origination Date 1 st February 2017 Area: The Group Approval: Group Services & Facilities Last Revision Date

More information

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 1 July 2014 Approved Plan Jon Fahie This, the University

More information

Hydrocarbon Management PROCEDURE

Hydrocarbon Management PROCEDURE Hydrocarbon Management PROCEDURE Doc No: Approved: PRO-0380 Operations Manager Table of Contents 1. PURPOSE... 3 2. SCOPE... 3 3. REFERENCES... 3 3.1 LEGISLATION/STANDARDS... 3 4. DEFINITIONS... 3 5. HYDROCARBON

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,

More information

PREMIUM DISCOUNT SCHEME AUDIT TOOL

PREMIUM DISCOUNT SCHEME AUDIT TOOL PREMIUM DISCOUNT SCHEME AUDIT TOOL 2003 WorkCover. Watching out for you. Disclaimer This publication contains information regarding occupational health, safety, injury management or workers compensation.

More information

Pollution & Environmental Harm

Pollution & Environmental Harm Pollution & Environmental Harm Fact Sheet 27 Updated December 2010 An introduction to Pollution and Environmental Harm There are a large range of activities that can lead to pollution or cause environmental

More information

FEEDLOT DESIGN AND CONSTRUCTION. 39. Agricultural and veterinary chemical storage. AUTHORS: Orla Keane and Peter Watts

FEEDLOT DESIGN AND CONSTRUCTION. 39. Agricultural and veterinary chemical storage. AUTHORS: Orla Keane and Peter Watts 39. Agricultural and veterinary chemical storage AUTHORS: Orla Keane and Peter Watts Introduction Agricultural and veterinary chemicals used in a feedlot must be stored in a way that maintains product

More information

Appendix B4 Construction Soil and Water Management Plan

Appendix B4 Construction Soil and Water Management Plan Appendix B4 Project: Keepit Dam Work Package 2 - Post Tensioning Works Location: Keepit Dam, Namoi River, Northern NSW Client: WaterNSW Contract: 04532F31 Page 2 of 26 Document Acceptance and Release Notice

More information

Community & Client Services. Health & Regulatory Services

Community & Client Services. Health & Regulatory Services Position Title: Team Leader Environmental Health Level: Salaried 6 Department: Program: Position Numbers: Community & Client Services Health & Regulatory Services HRS011 Position Objective Contribute to

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) Tararua District Council Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) NOTE: This is a draft ESCP in current preparation. Additional and updated information will

More information

GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS

GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 180 NOVEMBER 2005 GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS TABLE OF CONTENTS 180.01 SCOPE 180.02 REFERENCES 180.03 DEFINITIONS

More information

Environmental and Social Management Plan

Environmental and Social Management Plan Environmental and Social Management Plan Capital Works State Highway 205 / Schist Street Intersection Upgrade 21 September 2015 NZTA142200 Page ii Record of amendment Amendment number Description of change

More information

GUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY

GUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY GUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY A working plan is an essential document and consists of a written statement accompanied by plans, drawings and specifications detailing

More information

Quality, Health, Safety & Environment Manual

Quality, Health, Safety & Environment Manual Page 1 of 14 DOCUMENT RELEASE AUTHORIZATION Prepared, Reviewed and Issued by: Management Representative: ( ) Approved by: Chairman and Managing Director ( ) Issued as: CONTROLLED COPY / UNCONTROLLED COPY

More information

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction 9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of

More information

Health and Safety Management Standards

Health and Safety Management Standards Management Standards Curtin University Sept 2011 PAGE LEFT INTENTIONALLY BLANK Management Standards Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Documents... 4 2. Management System Model...

More information

COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY NEVADA COUNTY CDA GUIDELINES FOR ASH AND BURN DEBRIS CLEAN UP AND REMOVAL AFTER A FIRE

COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY NEVADA COUNTY CDA GUIDELINES FOR ASH AND BURN DEBRIS CLEAN UP AND REMOVAL AFTER A FIRE COUNTY OF NEVADA COMMUNITY DEVELOPMENT AGENCY Environmental Health Department 950 MAIDU AVENUE, SUITE 170 NEVADA CITY, CA 95959-8617 (530) 265-1222 FAX (530) 265-9853 http://mynevadacounty.com Amy Irani,

More information

Escondido Best Management Practices (BMP s)

Escondido Best Management Practices (BMP s) Escondido Best Management Practices (BMP s) GROUNDS MAINTENANCE & GOOD HOUSEKEEPING Regularly dry sweep paved areas including parking lots, outdoor areas and dumpster areas. Do NOT use a hose. Collect

More information

The City of Calgary, Environmental & Safety Management, under the terms of the ECO Plan Framework Memorandum of Understanding (EXT 03 ECO MOU).

The City of Calgary, Environmental & Safety Management, under the terms of the ECO Plan Framework Memorandum of Understanding (EXT 03 ECO MOU). Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for

More information

Pollution prevention (land and water)

Pollution prevention (land and water) 1 Purpose This document provides information on how to effectively manage pollutants for those working in Design, Construction and Maintenance activities. This guidance is to support the Level 2 Environment

More information

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance

More information

City of Tacoma Surface Water Management Manual

City of Tacoma Surface Water Management Manual City of Tacoma Surface Water Management Manual Volume IV Source Control BMPs Prepared by: Tacoma Public Works Environmental Services January 2003 Table of Contents Chapter 1 Introduction to Volume IV...

More information

The plan covers Girraween NSW site operated by Industrial Galvanizers Pty Ltd located at Amax Avenue, Girraween NSW 2145.

The plan covers Girraween NSW site operated by Industrial Galvanizers Pty Ltd located at Amax Avenue, Girraween NSW 2145. 1. PURPOSE The purpose of this Pollution Incident Response Management (PIRMP) is to describe Industrial Galvanizers response to a potential pollution incident and to meet requirements of the Protection

More information

Section 75J of the Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning and Assessment Act 1979 Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, approve the project referred to in Schedule 1, subject to the conditions in Schedule 2.

More information

Relevant legislation (Administering Authority Commonwealth legislation

Relevant legislation (Administering Authority Commonwealth legislation Commonwealth legislation Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) [Commonwealth Department of Sustainability, Environment, Water, Population and Communities (SEWPaC)] New

More information

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN Zitholele Consulting Reg. No. 2000/000392/07 PO Box 6002 Halfway House 1685 South Africa Thandanani Park, Matuka Close Halfway Gardens, Midrand Tel + (27) 011 207 2079 Fax + (27) 011 805-2100 E-mail :

More information

Draft Protocol for managing asbestos during resource recovery of construction and demolition waste.

Draft Protocol for managing asbestos during resource recovery of construction and demolition waste. Draft Protocol for managing asbestos during resource recovery of construction and demolition waste www.epa.nsw.gov.au 2014 State of NSW and Environment Protection Authority The State of NSW and Environment

More information

INJURY AND ILLNESS PREVENTION PROGRAM. Adopted June 25, 1991 by Board Resolution 91-95

INJURY AND ILLNESS PREVENTION PROGRAM. Adopted June 25, 1991 by Board Resolution 91-95 INJURY AND ILLNESS PREVENTION PROGRAM Adopted June 25, 1991 by Board Resolution 91-95 Latest Annual Review/Revision December, 2012 TABLE OF CONTENTS 1.0 Introduction... 1 2.0 Definitions... 1 3.0 Policy...

More information

Occupational Health and Safety. Improvement Standard

Occupational Health and Safety. Improvement Standard Premier s Department New South Wales Occupational Health and Safety Improvement Standard A tool for measuring OHS performance within NSW Government Agencies OHS IMPROVEMENT STANDARD NSW GOVERNMENT - REVIEW

More information

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT 13 J:\Jobs\42626220\07 Deliverables\EIS\FINAL for Public Release\13. LNG Facility Environmental Management Plan\13 LNG Facility EMP () FINAL PUBLIC track.doc GLNG Project - Environmental Impact Statement

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 20593 20-December Licensee HI-QUALITY QUARRY (NSW) PTY LTD PO BOX 42 KEMPS CREEK NSW 2171 Premises HI QUALITY KEMPS CREEK CENTRAL 1503-1519 ELIZABETH DRIVE KEMPS

More information

CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11

CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11 CS-OHS-11 (Amd 09/11) CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11 Responsible Officer: Group Manager Health and Safety Approved: EGM Corporate CONTENTS 1 Purpose... 3 2 Context...

More information

Best Management Practice (BMP) Water Quality Protection Guideline Commercial Landscaping and Lawn Care Services. Section 1.

Best Management Practice (BMP) Water Quality Protection Guideline Commercial Landscaping and Lawn Care Services. Section 1. WQ-11 Best Management Practice (BMP) Water Quality Protection Guideline Commercial Landscaping and Lawn Care Services For the purpose of this Water Quality Protection Guideline, Commercial Landscaping

More information

WHS Manual Insert Business Name & Logo

WHS Manual Insert Business Name & Logo WHS Manual Insert Business Name & Logo Version5 Work Health & Safety Manual INDEX OVERVIEW 4 1. WORK HEALTH AND SAFETY POLICY 5 2. PLANNING, REVIEW AND EVALUATION 9 3. HAZARD IDENTIFICATIO, ASSESSMENT

More information

CHAS Assessment Standards

CHAS Assessment Standards CHAS Assessment Standards Section 1 - All Prosecutions or Enforcement Notices The Supplier has provided details of any enforcement notices or prosecutions served on them in the last three years by the

More information

HFM Asset Management Contractor Induction Queens Riverside Apartments

HFM Asset Management Contractor Induction Queens Riverside Apartments HFM Asset Management Contractor Induction Queens Riverside Apartments Contents Purpose About HFM Asset Management HFM Asset Management s Responsibilities Contractors Responsibilities Commencing Work Working

More information

NORTHERN IRELAND AMBULANCE SERVICE ENVIRONMENTAL MANAGEMENT POLICY

NORTHERN IRELAND AMBULANCE SERVICE ENVIRONMENTAL MANAGEMENT POLICY NORTHERN IRELAND AMBULANCE SERVICE ENVIRONMENTAL MANAGEMENT POLICY April 2014 Version 2.0 Title: Purpose of Policy: Environmental Management Policy To set out NIAS policy on Environmental Management across

More information

EROSION AND SEDIMENT CONTROL PLAN (ESCP) FOR PROJECT TITLE

EROSION AND SEDIMENT CONTROL PLAN (ESCP) FOR PROJECT TITLE EROSION AND SEDIMENT CONTROL PLAN (ESCP) FOR PROJECT TITLE Project Street Address City, St. Zip PREPARED BY ADD LOGO DATE: Month Day, Year REVISED: Estimated Construction Dates: Construction Start Date:

More information

Stormwater Pollution Prevention Plan (SWPPP) For Single Family Residential Construction within a larger plan of development

Stormwater Pollution Prevention Plan (SWPPP) For Single Family Residential Construction within a larger plan of development COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Tel. (434) 296-5832 Fax (434) 972-4126 Stormwater Pollution Prevention Plan (SWPPP)

More information

Appendix B7 Construction Waste Management Plan

Appendix B7 Construction Waste Management Plan Appendix B7 Project: Keepit Dam Work Package 2 - Post Tensioning Works Location: Keepit Dam, Namoi River, Northern NSW Client: WaterNSW Contract: 04532F31 Page 2 of 27 Document Acceptance and Release Notice

More information

version 1 / 96 R Green Stars Hotel Environmental Management System

version 1 / 96 R Green Stars Hotel Environmental Management System Environmental Management Manual for Hotels in Hong Kong version 1 / 96 R Green Stars Hotel Environmental Management System 2002 Acknowledgements: This document is a revised version of the manual published

More information

Builder s enviro guide

Builder s enviro guide BC3337 Builder s enviro guide Preventing pollution from your building project Find out more: phone Auckland Council on 09 301 0101 or visit aucklandcouncil.govt.nz Contents Why compliance matters 2 The

More information

Management of health and safety is very important to us and given the appropriate priority.

Management of health and safety is very important to us and given the appropriate priority. Health and Safety Policy Statement Management of health and safety is very important to us and given the appropriate priority. Compliance with health and safety legislation is regarded as the minimum standard

More information

Town of Fortville Utility Street Standards

Town of Fortville Utility Street Standards Town of Fortville Utility Street Standards SECTION 02101 - TEMPORARY EROSION AND DUST CONTROL PART 1 - GENERAL 1.1 DESCRIPTION A. Temporary Erosion and Dust Control measures must meet the current Town

More information