Company. Southern (SCE)

Size: px
Start display at page:

Download "Company. Southern (SCE)"

Transcription

1 Stakeholder Comments Pay for Performance Regulati ion Straw Proposal Submitted by Company Date Submitted Kai Stephan (626) Alex Morris (626) Southern California Edison (SCE) December 19, 2011 SCE appreciates the opportunity to provide comments onn the Pay forr Performance Regulation straw proposal. SCE supports the general direction of the Californiaa Independent System Operator s (CAISO) proposal but believes this design effort should include a more comprehensive review of Regulation, its integration withh Flexible Ramping Products, and its intended role in grid reliability (addressing intra-rtd errors or system trending) ). In this design process, the CAISO s goal should be to design Regulation correctly. This goal should not be sacrificed in meeting FERC s timeframe. Elements off the ultimate design may need incremental implementationn to comply with FERC deadlines. I. SCE urges the CAISO to discuss critical elements not in the proposal. A. CAISO needs to disclose its Regulation dispatch algorithm to enable effective stakeholder input. Stakeholders need to better understand the CAISO s dispatch algorithm and how it operates with energy schedules in RTPD and RTD and with Flexible ramping dispatches. In the CAISO stakeholder conferencee call, the CAISO stated the objective function seek(s) to maximize future available ramp. 1 In order to provide effective input to help design an efficient Regulation product, the CAISO needs to disclose to stakeholders their Regulation dispatch algorithm. SCE also suggests the CAISO hold a technical workshop on the dispatch algorithm. B. Regulation should solve for intra-rtd uncertainty only, while flexible ramping services and imbalance energy markets resolvee trending, variability, and sub-rtpd uncertainty. Data providedd during the Regulation Energy Management (REM) stakeholder process indicates Regulation serves to meet system trending needs. In light of the developing roles for flexible ramping services, SCE recommends Regulation be designed specifically to resolve system noise the smaller random deviations resulting from intra-real-time 1 CAISO Stakeholder conference call on Frequency Regulation, 1:00pm December 12,

2 Dispatch uncertainties. Regulation should no longer be used for system trending. Instead, the Regulation signal should resolve small up and down fluctuations resulting in a zero-net-energy (ZNE) type of product. Separately, system trending and intra-rtpd uncertainties should be solved using the combination of Flexi-ramp and Real-time dispatch schedules. With a ZNE Regulation product, any residual energy would be settled at the resources default energy bid. This design immunizes resources from Real- Time energy price exposure. A ZNE product would likely require a single Regulation product design. SCE discusses this concept later in these comments. The CAISO should minimize the capacity procured for system variability. If the CAISO can manage longer term variability and uncertainty with products typically less expensive than Regulation, it should do so and end procurement of regulation capacity for such functions. Data and experience gained from the flexible ramping services should inform the CAISO s regulation design as a noise product. C. An efficient design requires costs are allocated properly. FERC set an important precedent by approving Westar s Portfolio s cost allocation methodology. CAISO should consider this precedent in forming its cost allocation proposals. Costs for integrating and balancing services should go to those causing the need. SCE recommends the CAISO calculate Regulation needs caused by each market participant (i.e. Load, VERs), and allocate procurement costs accordingly. Since Regulation and ramping procurement will increase through 2020 as the CAISO integrates VERs commensurate with the 33% Renewable Portfolio Standard goal 2, the CAISO should develop proper cost allocation structures now so goals are achieved most efficiently and at the least cost to ratepayers. SCE recommends the CAISO adopt the FERC approved cost allocation methodology developed by Westar 3. Westar s portfolio methodology logically allocates the costs of balancing products to those causing the need using a statistical analysis of historical performance data. A presentation discussing the Westar s Portfolio methodology is attached to these comments. 2 CAISO Summary of Preliminary Results of 33% Renewable Integration Study ; May 10, Westar s filing with FERC: ER Page 2

3 II. SCE s comments on the specific elements in the current Proposal. A. SCE supports multiple aspects of the current Proposal. Specifically, SCE supports the following: Calculating mileage as the absolute change in AGC set points between four-second intervals. Payments for actual mileage moved, rather than for an expected mileage movement. No-pay for non-performance to the CAISO s dispatch signal. Mileage calculations that incorporate four-second interval instructions. B. The current no-pay calculations may be overly fine and discrete. Any performance metric should primarily measure performance and not measure error including communications lag. In designing accuracy and no-pay provisions, the CAISO needs to discuss how Regulation is actually solving area-control error, and ensure its design aligns with actual grid operations. Four-second performance and response measurement may be too granular because of response times or other normal aspects of Regulation dispatch and response. If a resource is inaccurate to every four-second dispatch signal, yet on 30- second horizon the resource is accurate to the cumulative instructions, has the grid received comparable benefit to four-second accuracy? If yes, should the resource receive a comparable mileage payment? Understanding CAISO s Regulation dispatch algorithm will help stakeholders answer these questions. The CAISO should not design a system where the majority of resources will incur no-pay provisions for every interval. No-pay for non-performance should primarily result from actual non-performance, and not from an accumulation of system errors. This structure ensures that resources are properly compensated for their mileage provided. Additionally, the change to mileage payments should leverage existing systems and not trigger costly new communications infrastructure expenses. SCE believes the CAISO s current proposal could trigger new expenses. As a principle, resources should not be penalized for infeasible dispatch instructions. For example, if it takes more than four seconds to receive the dispatch signal from the CAISO, generators can never respond accurately. Any No-Pay from inherent system and communications lags within the AGC system should be minimal. To this end, some form of deadband accuracy adjustment appears necessary. Without such a structure, system communication lags may be misinterpreted as non-performance. SCE requests CAISO provide additional information on timing and communication lags in the AGC system before deciding upon the proper settlement interval. Page 3

4 In the CAISO s current proposal, the mileage provided by a resource s governor response system may be considered No-Pay. Mileage produced from governor response system is usually helpful to the CAISO in correcting ACE, and therefore should be included in a mileage payment. 4 C. CAISO should explore a procurement design that explicitly constrains mileage and capacity. The proposal assumes sufficient mileage capability will automatically result from the procured Regulation capacity, yet this outcome is not guaranteed. The CAISO needs to convince stakeholders that this approach will sufficiently meet mileage needs. The CAISO should consider a procurement target and constraint for mileage capability in its procurement objective function. This approach eliminates uncertainty about the mileage that results from procurement solely for capacity targets. Without a mileage constraint, the CAISO will be unable to ensure it has sufficient mileage capability. Additionally, several potential problems may result from the proposed Mileage Multiplier. The average mileage capability from a previous day s resource mix may not represent the mileage capability of the current mix. Without knowing how much mileage each resource can provide, and without having a mileage procurement target, the CAISO may procure insufficient mileage 5. SCE notes alternatives to the Mileage Multiplier later in these comments. D. A proper Regulation design should reduce costs. The CAISO should seek a Regulation design where procurement of faster ramping resources reduces regulation costs. FERC cited the ability of faster-ramping frequency regulation providers to lower costs to load. 6 This savings should result in part through ISO/RTO procurement of less regulation. 7 The Commission reiterated this in its Final 4 A governor will read the frequency at its specific resource, and automatically adjust the resource s generation such that it stays as close to 60Hz as possible. Given that this system reads the frequency at the resource itself, it often will begin to adjust the resource s generation to meet 60Hz before the CAISO s Regulation dispatch signal has been received. 5 Day 1 requires 100MW capacity for Regulation. The CAISO commits two 50MW resources that each have a ramp rate of 5MW/min, and a total maximum daily mileage amount of 14,400MW-4sec. Day 2 also requires 100MW capacity for regulation. Using the previous day s Mileage Multiplier, the CAISO believes it can get 14,400MW- 4sec worth of mileage. However, the CAISO now commits one 100MW resource with an 8MW/min ramp rate, and thus a maximum daily mileage amount of 11,520 MW-4sec. Although the CAISO has met its Regulation capacity requirement, it is now deficient in mileage capability. 6 In the Frequency Regulation Compensation in the Organized Wholesale Power Markets, Notice of Proposed Rulemaking (NOPR), February 17, 2011, 134 FERC 61,124, RM11-7, Page 20, Paragraph 32 7 Demonstrated by the Pacific Northwest National Laboratory study, also cited in the NOPR, Makarov, Y.V., Ma, J., Lu, S., and T.B. Nguyen, Assessing the Value of Regulation s Based on Their Time Response Characteristics, Pacific Northwest National Laboratory, PNNL-17632, June 2008 Page 4

5 Rule. 8 To SCE, an increase in regulation costs could imply an inefficient methodology or design. E. If the Mileage Multiplier calculation is pursued, it will require additional design. If the CAISO continues to use Regulation for system trending, the Mileage Multiplier should be calculated at least hourly rather than as a daily average. Calculating hourly would reduce the likelihood of procuring insufficient mileage for the entire day due to averaging out of the mileage need. Since capacity is the driver in the optimization process, mileage may be insufficient with a day-long mileage multiplier. Additionally, the Mileage Multiplier should be calculated separately for each class of resources (e.g. hydro, peaker, etc.), enabling more accurate representation in the procurement objective function. III. Rather than the proposed incremental changes to Regulation, the CAISO should consider a comprehensive redesign. SCE recommends the following ideas for consideration in this process. Alternative approaches on Pay for Performance Regulation design exist. SCE does not necessarily advocate for these alternatives but believes them worthy of stakeholder discussion. An attached presentation focuses on these concepts. A. CAISO should explore Regulation as a single product. As is done by all other ISO/RTO s, Regulation Up and Regulation Down can be combined into a single Regulation product. The current split product is somewhat artificial once a resource provides Regulation Up, it essentially provides Regulation Down when dispatched back to its original set point. s that only provide Regulation in a single direction could have their initial set-point biased to their upper or lower range, allowing provision of both up and down Regulation. A single Regulation product used in this way greatly reduces a resource s exposure to Real-time energy prices, reducing risk premiums. In this structure, all Regulation energy production/consumption should net to zero over time assuming the dispatch algorithm is designed accordingly. A resource s default energy bid could be used to pay/credit resources for net production/consumption. 8 In the Frequency Regulation Compensation in the Organized Wholesale Power Markets, Final Rule, October 20, 2011, 137 FERC 61,064, RM11-7, Page 12, Paragraph 19 Page 5

6 B. CAISO should discuss a turnaround rate as a measure of movement capabilities of resources. With a Regulation product designed to resolve noise, regulation needs and corresponding dispatch signals may move up and down multiple times within a 5-min interval. for such movements benefits from the use of a turnaround rate, defined as the maximum movement (up or down) a resource can achieve while still returning to its starting point within a five minute interval. The number of turns possible within the 5 minute interval would also be measured (i.e., a battery may be able to reach its max MW output and return to zero several times within 5 minutes). These turnaround metrics, in addition to a general capacity measure, better reflect a resource s mileage capability, now defined as its turnaround level multiplied by its potential number of turns. s would report their physical max turnaround level (in MW), and the number of times they can achieve that level within 5 minutes. The turnaround rate is preferable to the current Mileage Multiplier because it better reflects a resource s ability to move up and down. Therefore, the turnaround rate should be used to define a resource s mileage capability in the procurement objective function. C. Once constrained for mileage/turnaround, the objective function costs should be multiplied by an expected-use quotient that is resource class specific and calculated from historical data. Prior to real-time, the actual mileage a specific resource will provide is unknown. Thus, the procurement objective function needs to estimate a resource s mileage in order to minimize costs. To best estimate a resource s mileage, an expected-use quotient can be used based on that resource s class (i.e. hydro, battery, flywheel, CCGT, etc.). This quotient can be calculated by resource class from the rolling average of historical mileage production. This approach is preferable to a Mileage Multiplier because mileage expectations are more logically estimated and represented in the system optimization. Page 6

7 Summary comparison of CAISO s proposal and alternative designs. Feature CAISO Alternate Proposal Regulation Procurement Expected use of Reg product Real-Time Energy Cost Allocation Procurement constraints Defining resource s mileage capability Separate Reg Up and Reg Down products System trending and system noise Reg resources exposed to RT energy prices Load pays everything Only have a capacity targetassumes sufficient mileage will be provided Averages a previous day s mileage provided by one resource pool, assumes all resources can provide exactly previous day s average mileage Single Reg product System noise only- Zero Net Energy product Little excess energy due to ZNE dispatch algorithm, remaining excess settled at the resources default energy bid Costs allocated based on causation, per Westar s Portfolio methodology 9 Explicitly constrains procurement minimum on mileage and capacity requirements Specifies unique mileage capability for each resource using a turnaround rate- a physical characteristic of each resource 9 Westar s filing with FERC: ER Page 7

8 APPENDIX Page 8

9 Westar s Portfolio Cost Allocation Methodology December 19, 2011 Jeffrey Nelson (626) Jeff.nelson@sce.com

10 Agenda Portfolio effect and basic stats review Westar- Portfolio Approach Presentation Objectives Gain understanding of various cost allocation methodologies Draw conclusions on what might work best for CAISO market Page: 1

11 Statistics Review Standard Deviation, σ σ 2σ 3σ 68.2% of values 95.4% of values 99.7% of values X Y X Y X Y Correlation, ρ High positive correlation, ρ 1 High negative correlation, ρ 1 No correlation, ρ 0 Y Y Y X X X Covariance, Page: 2

12 Big Picture General Problem: The total system regulation requirement is known, how do we allocate this total based on individual resource/ load contribution to need? Portfolio Benefits: System total sum of needs to manage each individual resource/ load Portfolio almost always less (rarely equal, never greater) This reduction is commonly called Portfolio Affect, Diversification, or Offsetting Errors Page: 3

13 Example: Portfolio of Wind and Load Load Wind Probability Probability 2σ 300 MW 2σ 110 MW MW Assume BAA is carrying enough Regulation reserves to cover 2σ of uninstructed movement (95% of all events) Without benefits of a portfolio, typical BAA would have to carry: However, due to offsetting errors, the BAA s portfolio needs less regulation reserves MW Example: 2 = 300 MW 2 = 110 MW = 410 MW Page: 4

14 Example: Portfolio of Wind and Load (cont.) To calculate adjusted variance, need standard deviation (σ) and covariance between resources Load Wind Adjusted Variance Load,, Wind,, The Portfolio s standard deviation is calculated as the sum of the adjusted variances:,, Example (cont.) Load Wind Adj Var Load 22,500 1,650 24,150 Wind 1,650 3,025 4,675 Assumed ,150 4,675 Procurement = MW The Portfolio s standard deviation is always less than or equal to the sum of the standard deviations of its individual components 1 : Note: Portfolio procurement quantity reduced to 340 MW from Standalone approach s quantity of 410 MW 1- See Backup slides for proof Page: 5

15 Example: Portfolio of Wind and Load (cont.) Each individual resource/ load is then allocated its share of the portfolio s regulation needs Pro-rata Formula (e.g. Wind s Share): Wind s Allocation = Page: 6

16 Example: Portfolio of Wind and Load (cont.) Each individual s share is a pro-rata based on adjusted variance: Load s Share: 2 Wind s Share: 2 Example (cont.) Total Regulation Procurement = MW Load s Share = MW Compared to 300 MW in Standalone approach Wind s Share = MW Compared to 110 MW in Standalone approach Page: 7

17 Westar- Portfolio Approach Uses correlation between individual resources/ load Same calculations as example on slides 4-6, but with 5 components instead of 2 Calculates total portfolio as: 2 System Diversity Ratio Westar s Results (as presented to FERC): Westar redacted the data in their public report 1 Share to wind drops to 7.25% Recall: share to wind from standalone approach was 7.8% 1 Puget Sound Energy adopted Westar s Portfolio methodology, and provides more data for their calculations: Page: 8

18 Westar Observations Only thing needed is historically deviation data CAISO already has 10-min generation data, 1-hr load data Load data can be profiled Very robust and easy methodology Allows for an unlimited number of buckets (can break down allocations to specific units) Calculated on an hourly basis Need to account for all instructed deviations i.e. instructed deviations should not be counted for cost allocation CAISO has data and can easily implement Page: 9

19 SCE: Current thinking on Frequency Regulation December 19, 2011 Jeffrey Nelson (626)

20 Overview Single Regulation product (not separate Reg Up and Reg Down) Regulation is used for noise not trending, thus it is expected to be Zero Net Energy (ZNE) CAISO determines the mileage capability of each unit as part of the selection process CAISO specifies both capacity needs and mileage needs Page: 1

21 Regulation Market Design Framework Regulation Dispatch Signal to continually cross zero Regulation should capture noise, and not be used for system trends Separate following product should be developed for broader trends Single Regulation Product: Combine Reg Up Reg Dn Reg energy production/consumption should net to zero Eliminates/ greatly reduces exposure to RT energy prices Procurement for Regulation Procure enough capacity for expected Reg magnitude - based on historical statistics Procure enough mileage for how much Regulation is expected to move- based on historical statistics Settlement for Regulation Paid for any non-net zero energy based on resource production cost/ default energy bid (not market) Pay for capacity, via (Capacity Market Clearing Price)*(Capacity Sold) Pay mileage, via (Movement Market Clearing Price)*(Movement Sold or Produced) Movement must comply with ISO dispatch signal (pay for performance) Operational Characteristics represents:1) total 10-min ramp capability [can substitute for other ancillary services], 2) 5-min Turnaround rate, and 3) number of turns in 5-min Based on true physical characteristics Bids Price to reserve capacity Price per MW moved ( mileage rate) Page: 2

22 Regulation Visual Real-time Ramping Energy Actual Load During this interval, Regulation is needed to peak Up AND return Down to near original set-point MW Regulation is used to fill the gaps between Real-time Ramping Energy and Actual Load Interval Page: 3

23 The Turnaround Constraint MW Real-time Ramping Energy Actual Load Reg Up Reg Dn min Interval CAISO currently does a ramping constraint calculated by how fast a resource could ramp up in 10 minutes In reality, a proper Regulation dispatch signal 1 will move up AND down during a 5-min interval Note: CAISO dispatches energy in 5-min blocks Use a Turnaround Rate rather than a Ramp Rate for mileage estimate i.e.: Starting at a set point, what MW max can a resource meet- and still return to the set-point- within 5 minutes 1- The Regulation dispatch signal should be designed to compensate for the system noise, whereas Flexi-Ramp should be used for all system trending/ ramping Page: 4

24 Turnaround Constraint Examples Conventional Ramp Up Turnaround 60 MW Here, the conventional resource can reach 60MW output in 5-min Capacity = 60 MW MW Minute 11 MW If that same resource needs to return to zero, its turnaround is the max output reached Turnaround = 11MW, 1 Turn MW Battery Ramp Up Turnaround Minute MW The battery reaches its full output in only 30-sec, but is limited by its capacity Capacity = 20 MW Using the turnaround constraint, it can reach its max output several times Turnaround = 20MW, 5 Turns Page: 5

25 Procurement/ Bidding Structure s would state their capacity, Turnaround, and number of Turnarounds s would bid their capacity price and movement or mileage rate Example: Physically Based Market Based Capacity Turnaround Number (#) of Turnarounds Capacity bid [$/MW] Speed bid [$/#MW] A 60 MW 11 MW 1 $0.75 $0.30 B 10 MW 10 MW 5 $1.20 $0.10 C 5 MW 5 MW 25 $1.00 $0.02 Page: 6

26 Mileage Performance Definition Mileage is the absolute value of instructed change in operating point No mileage payment 2 miles payment miles payment MW mile payment Minute Total mileage payment = = 6 MW * Rate Page: 7

27 Zero Net Energy Design Dispatch Algorithm designed to result in zero net energy for a unit over some time horizon Positive Energy MW Negative Energy Minute Set Point Positive and negative energy should net as close to zero as possible Remaining energy will be paid at resource s cost and charged to load Page: 8

28 Procurement Constraints ISO has Two Constraints: Total Capacity and Total 5-min Mileage Capability 1. Total 10-min uni-directional capacity e.g. 1100MW Reg Up, 1300MW Reg Down 10-min synchronizes well with other ancillary services 2. Total 5-min mileage capability 5 min e.g. total mileage CAISO needs over 5-min is: 15MW/min 10 ; 5 ; 15 /min If ISO purchases from a resource i, mileage calculated as: where,, Page: 9

29 Procurement Objective Function Sum of Capacity Payments Expected use See next slide Sum of Mileage Payments,,, Subject to: 1 2 Total mileage ISO finds a least-cost solution given constraints to determine marginal resources Shadow price of constraint = Capacity MCP Shadow price of constraint = Mileage MCP 1 2 Page: 10

30 Adjustment to Mileage Objective Function At time of resource selection, the actual mileage a resource will provide is unknown,, Adjustment factor for actual mileage Objective function cost should be adjusted based on expected use U i Either: 1. Set 1 for all resources Recognizes resources full capability won t be used on average 2. Define specific to each resource i or resource class i Use historic data to weight based on observations s are paid for their actual movement U i Page: 11

31 Procurement Example Bids Capacity Turnaround Number (#) of Turnarounds Capacity bid [$/MW] Mileage bid [$/#MW] A 60 MW 11 MW 1 $0.75 $0.30 B 10 MW 10 MW 5 $1.20 $0.10 C 5 MW 5 MW 25 $1.00 $0.02 CAISO Requirements: Capacity: 60MW Mileage: 50MW Capacity Awarded Capacity Cost Mileage Gained Mileage Cost A MW $ MW $3.30 B C MW $ MW $0.78 Sum MW $ MW $4.08 Page: 12

Regulation Energy Management Draft Final Proposal

Regulation Energy Management Draft Final Proposal Regulation Energy Management Draft Final Proposal January 13, 2011 Renewable Integration: Market and Product Review Phase 1 Regulation Energy Management (REM) Revised Draft Final Proposal Table of Contents

More information

Opportunity Cost of Flexible Ramping Constraint. Draft Final Proposal

Opportunity Cost of Flexible Ramping Constraint. Draft Final Proposal Opportunity Cost of Flexible Ramping Constraint Draft Final Proposal July 20, 2011 Opportunity Cost of Flexible Ramping Constraint Draft Final Proposal Table of Contents 1 Introduction... 3 2 Changes from

More information

Flexible Ramping Product Cost Allocation Straw Proposal

Flexible Ramping Product Cost Allocation Straw Proposal Flexible Ramping Product Cost Allocation Straw Proposal March 15, 2012 Flexible Ramping Product Cost Allocation Straw Proposal Table of Contents 1 Introduction... 3 2 Prior discussion on Flexible Ramping

More information

Flexible Ramping Products

Flexible Ramping Products Flexible Ramping Products Revised Draft Final Proposal August 16, 2012 Lin Xu, Ph.D. Senior Market Development Engineer Don Tretheway Senior Market Design and Policy Specialist Agenda Time Topic Presenter

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket Nos. ER12-1630 Operator Corporation ) ER14-971 Informational Report of the California Independent System

More information

Southern California Edison Approach to Renewable Integration June 7, 2011

Southern California Edison Approach to Renewable Integration June 7, 2011 Southern California Edison Approach to Renewable Integration June 7, 2011 Page: 0 SCE s 2010 Resource Mix Natural Gas All Resources 100% = 75 billion kwh/yr Renewable Resources 100% = 14.5 billion kwh/yr

More information

Submitted by Company Date Submitted

Submitted by Company Date Submitted Submitted by Company Date Submitted Christine Kirsten christine.kirsten@pacificorp.com 916-207-4693 PacifiCorp March 21, 2019 PacifiCorp s Comments on the Day-Ahead Market Enhancements Phase 1: Fifteen-Minute

More information

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3

More information

Southern California Edison Stakeholder Comments. PacifiCorp s Energy Imbalance Market (EIM) Entity Proposal Dated October 18, 2013

Southern California Edison Stakeholder Comments. PacifiCorp s Energy Imbalance Market (EIM) Entity Proposal Dated October 18, 2013 Stakeholder Comments PacifiCorp s Energy Imbalance Market (EIM) Entity Proposal Dated October 18, 2013 Submitted by Company Date Submitted Paul Nelson (626) 302-4814 Jeff Nelson (626) 302-4834 Southern

More information

Comments of Powerex Corp. on FRAC MOO Phase 2 Supplemental Issue Paper. Submitted by Company Date Submitted

Comments of Powerex Corp. on FRAC MOO Phase 2 Supplemental Issue Paper. Submitted by Company Date Submitted Comments of Powerex Corp. on FRAC MOO Phase 2 Supplemental Issue Paper Submitted by Company Date Submitted Mike Benn 604.891.6074 Powerex Corp. January 6, 2017 Powerex appreciates the opportunity to submit

More information

Ancillary Service. the WEM System Management. June 2018

Ancillary Service. the WEM System Management. June 2018 Ancillary Service Report for the WEM 2018-19 June 2018 System Management Important notice PURPOSE AEMO publishes the Wholesale Electricity Market Ancillary Services report under clause 3.11.13 of the Wholesale

More information

Stepped Constraint Parameters. Issue Paper

Stepped Constraint Parameters. Issue Paper Stepped Constraint Parameters May 5, 2016 Table of Contents 1. Introduction... 3 2. Plan for Stakeholder Engagement... 4 3. Transmission constraint relaxation parameter... 5 4. Shift factor effectiveness

More information

Day-Ahead Market Enhancements Phase 1: Fifteen-Minute Granularity. Second Revised Straw Proposal

Day-Ahead Market Enhancements Phase 1: Fifteen-Minute Granularity. Second Revised Straw Proposal Day-Ahead Market Enhancements Phase 1: Fifteen-Minute Granularity August 27, 2018 Intentionally left blank D.Tretheway, M.Poage, E.Nethercutt Page 2 August 27, 2018 Day-Ahead Market Enhancements Phase

More information

Flexible Ramping Products and Cost Allocation

Flexible Ramping Products and Cost Allocation Flexible Ramping Products and Cost Allocation Revised Straw Proposal, December 5, 2011 Lin Xu, Ph.D. Senior Market Development Engineer and Donald Tretheway Senior Market Design and Policy Specialist Agenda

More information

California ISO. Discussion & Scoping Paper on Renewable Integration Phase 2. Renewable Integration: Market and Product Review Phase 2

California ISO. Discussion & Scoping Paper on Renewable Integration Phase 2. Renewable Integration: Market and Product Review Phase 2 Discussion & Scoping Paper on Renewable Integration Phase 2 Phase 2 April 5, 2010 Issue Paper - Phase 2 Renewable Integration Table of Contents 1 Introduction... 3 2 Candidate Elements for the Comprehensive

More information

Day Ahead Market Enhancements. Issue Paper/Straw Proposal

Day Ahead Market Enhancements. Issue Paper/Straw Proposal Day Ahead Market Enhancements February 28, 2018 Intentionally left blank CAISO/MDP/D.Tretheway & M.Poage Page 2 February 28, 2018 Day Ahead Market Enhancements Issue Paper & Straw Proposal Table of Contents

More information

Energy Imbalance Market Design Straw Proposal and Issue Paper. Stakeholder Meeting April 11, 2013

Energy Imbalance Market Design Straw Proposal and Issue Paper. Stakeholder Meeting April 11, 2013 Energy Imbalance Market Design Straw Proposal and Issue Paper Stakeholder Meeting April 11, 2013 Agenda Time Topic Presenter 10:00 10:10 Introduction Mercy Parker-Helget 10:10 10:45 Opening Remarks Don

More information

Flexible Ramping Products

Flexible Ramping Products Flexible Ramping Products Incorporating FMM and EIM Draft Final Proposal Lin Xu, Ph.D. Market Analysis and Development and Donald Tretheway Market and Infrastructure Policy December 4, 2014 CAISO/MA&D/LXU/MIP/DGT

More information

FERC Order 764 Settlements

FERC Order 764 Settlements FERC Order 764 Settlements Spring Release 2014 The information contained in these materials is provided for general information only and does not constitute legal or regulatory advice. The ultimate responsibility

More information

California ISO Draft Final Proposal Ancillary Services Procurement in HASP and Dispatch Logic

California ISO Draft Final Proposal Ancillary Services Procurement in HASP and Dispatch Logic California ISO Draft Final Proposal Ancillary Services Procurement in HASP and Dispatch Logic Redline Version August 25, 2009 Ancillary Services Procurement in HASP and Dispatch Logic Prepared for Discussion

More information

Integrating High Levels of Variable Renewable Energy Sources

Integrating High Levels of Variable Renewable Energy Sources Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning

More information

Energy Imbalance Market Year 1 Enhancements

Energy Imbalance Market Year 1 Enhancements Energy Imbalance Market Year 1 Enhancements Don Tretheway Lead Market Design and Regulatory Policy Developer February 18, 2015 Agenda Time Topic Presenter 10:00 10:15 Introduction Kristina Osborne 10:15

More information

June 21, Southwest Power Pool, Inc., Docket No. ER Order No. 755 Compliance Filing

June 21, Southwest Power Pool, Inc., Docket No. ER Order No. 755 Compliance Filing June 21, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No. ER13- -000 Order No.

More information

Energy Imbalance Market Year 1 Enhancements. Issue Paper and Straw Proposal

Energy Imbalance Market Year 1 Enhancements. Issue Paper and Straw Proposal Energy Imbalance Market Year 1 Enhancements Issue Paper and Straw Proposal November 10, 2014 Energy Imbalance Market Year 1 Enhancements Issue Paper and Straw Proposal Table of Contents 1 Introduction...

More information

Imbalance Conformance Enhancements. Draft Final Proposal

Imbalance Conformance Enhancements. Draft Final Proposal Imbalance Conformance Enhancements January 30, 2018 Intentionally left blank CAISO/M&ID/MDP/M.Poage Page 2 January 30, 2018 Issue Paper/Straw Proposal Imbalance Conformance Enhancements Issue Paper & Straw

More information

Pay for Performance Regulation Year 1 Design Changes. Draft Final Proposal

Pay for Performance Regulation Year 1 Design Changes. Draft Final Proposal Pay for Performance Regulation Year 1 Design Changes Draft Final Proposal September 26, 2014 Pay for Performance Regulation Year 1 Design Changes Draft Final Proposal Table of Contents 1 Introduction...

More information

Pay for Performance Stakeholder Comments Issue Paper and Straw Proposal

Pay for Performance Stakeholder Comments Issue Paper and Straw Proposal Pay for Performance Stakeholder Comments Issue Paper and Straw Proposal California Department of Water Resources State Water Project... 1 Summary... 1 Comments... 1 California Energy Storage Alliance...

More information

Extended Short-Term Unit Commitment. Draft Final Proposal

Extended Short-Term Unit Commitment. Draft Final Proposal Extended Short-Term Unit Commitment June 13, 2018 Intentionally left blank CAISO/MDP/M.Poage & B.Dean Page 2 June 13, 2018 Extended STUC Table of Contents 1. Purpose... 4 1.1. Changes to Proposal... 4

More information

Market Vision. Renewab. Company Jeffrey Nelson. Submitted by. Southern ( 626) ( SCE ) the future. Regulation. principle is an.

Market Vision. Renewab. Company Jeffrey Nelson. Submitted by. Southern ( 626) ( SCE ) the future. Regulation. principle is an. Stakeholder Comments Renewable Integration: Market & Product Review Phase 2 Renewab ble Integration: Market Vision & Roadmap Revised Straw Proposal Submitted by Company Date Submitted Jeffrey Nelson Southern

More information

Eligible Intermittent Resource Dispatch Operating Target EIR DOT

Eligible Intermittent Resource Dispatch Operating Target EIR DOT Eligible Intermittent Resource Dispatch Operating Target EIR DOT CSSA Training August 2018 Stakeholder Learning Objectives Explain the difference between an Operating Instruction and a Dispatch Instruction

More information

Extended Short-Term Unit Commitment. Issue Paper/Straw Proposal

Extended Short-Term Unit Commitment. Issue Paper/Straw Proposal Extended Short-Term Unit Commitment May 15, 2018 Intentionally left blank CAISO/MDP/M.Poage & B.Dean Page 2 May 15, 2018 Extended STUC Issue Paper & Straw Proposal Table of Contents 1. Purpose... 4 1.1.

More information

Intertie Deviation Settlement. Straw Proposal

Intertie Deviation Settlement. Straw Proposal Intertie Deviation Settlement Straw Proposal October 8, 2018 Intertie Deviation Settlement Straw Proposal Table of Contents 1. Purpose... 4 1.1 Response to Stakeholder Comments... 4 2. References... 5

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) Docket No. RM Operator Corporation )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) Docket No. RM Operator Corporation ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. RM17-3-000 Operator Corporation ) COMMENTS OF THE DEPARTMENT OF MARKET MONITORING FOR

More information

20 MW Flywheel Energy Storage Plant

20 MW Flywheel Energy Storage Plant 1 20 MW Flywheel Energy Storage Plant Case Study for the: Advanced Energy 2010 Conference Chet Lyons, Director, Marketing and Sales November 8-9, 2010 3 Safe Harbor Statement This presentation contains

More information

Energy Imbalance Market Overview

Energy Imbalance Market Overview Energy Imbalance Market Overview Presentation to: Portland General Electric EIM OATT Stakeholder Meeting David Timson Account Manager CAISO Strategic Alliances October 14, 2016 Topics for Discussion ISO

More information

Reliability Services Initiative Phase 2: Revised Draft Final Proposal

Reliability Services Initiative Phase 2: Revised Draft Final Proposal Reliability Services Initiative Phase 2: Revised Draft Final Proposal July 7, 2016 CAISO/M&IP/IP/EKim/KMeeusen 1 Table of Contents 1. Executive summary... 3 2. Changes to proposal and stakeholder comments...

More information

3. Overview of Market Instruments

3. Overview of Market Instruments 3. Overview of Market Instruments 3.2 Ancillary Services Bids Four types of Ancillary Services are used by CAISO in its markets Regulation Up, Regulation Down, Spinning Reserve, and Non-Spinning Reserve.

More information

Energy Imbalance Market

Energy Imbalance Market IISii Energy Imbalance Market Draft Final Proposal September 23, 2013 CAIS[Type text] [TyIISIISIpe tiext]iso [Type text] Table of Contents 1. Executive Summary... 1 2. Introduction... 10 2.1. New Terms...

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: December 6, 2017 Re: Decision on contingency

More information

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments

CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments May 22, 2017 Public Generating Pool (PGP) and Public

More information

Day Ahead Market Enhancements. Revised Straw Proposal

Day Ahead Market Enhancements. Revised Straw Proposal Day Ahead Market Enhancements April 11, 2018 Intentionally left blank CAISO/MDP/D.Tretheway & M.Poage Page 2 April 11, 2018 Day Ahead Market Enhancements 1. Purpose... 4 1.1. Changes from Issue Paper/Straw

More information

Imbalance Conformance Enhancements. Issue Paper & Straw Proposal

Imbalance Conformance Enhancements. Issue Paper & Straw Proposal Imbalance Conformance Enhancements Issue Paper & Straw Proposal November 29, 2017 Intentionally left blank CAISO/M&ID/MDP/M.Poage Page 2 November 29, 2017 Imbalance Conformance Enhancements Issue Paper

More information

Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area

Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Regional Resource Adequacy Meeting December 16, 2015 Salt Lake City, Utah Keith Johnson Manager, Infrastructure Policy

More information

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets March 8, 2010 Revised Draft Final Proposal for Participation of Non- Generator Resources

More information

Local Market Power Mitigation Enhancements Issue Paper/Straw Proposal

Local Market Power Mitigation Enhancements Issue Paper/Straw Proposal Local Market Power Mitigation Enhancements Issue Paper/Straw Proposal Public Generating Pool Comments December 7, 2018 The Public Generating Pool (PGP) appreciates the opportunity to comment on the California

More information

Price Formation Education Session Day 1 Economic Dispatch

Price Formation Education Session Day 1 Economic Dispatch Slide 1 Price Formation Education Session Day 1 Economic Dispatch Anthony Giacomoni Melissa Maxwell Laura Walter December 4, 2017 Slide 2 Disclaimer Slide This is not a committee meeting. This session

More information

Comments of Powerex Corp. on Day-Ahead Market Enhancements Phase 2

Comments of Powerex Corp. on Day-Ahead Market Enhancements Phase 2 Comments of Powerex Corp. on Day-Ahead Market Enhancements Phase 2 Submitted by Company Date Submitted Mike Benn 604.891.6074 Powerex Corp. April 4, 2019 Powerex appreciates the opportunity to comment

More information

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response California Independent System Operator Corporation Executive Summary Straw Proposal Post-Release 1 MRTU Functionality for Demand Response The (CAISO) has a goal of helping to develop demand response resources

More information

Performance, Mileage and the Mileage Ratio

Performance, Mileage and the Mileage Ratio Performance, Mileage and the Mileage Ratio Scott Benner Sr. Engineer Markets Coordination Regulation Market Issues Sr. Task Force Nov. 11, 2015 Agenda Performance Scoring Signal Mileage Mileage Ratio and

More information

TESTIMONY OF MARK ROTHLEDER ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

TESTIMONY OF MARK ROTHLEDER ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: Exhibit No.: Witness: Mark Rothleder Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. TESTIMONY OF MARK ROTHLEDER BEFORE

More information

Bid cost recovery and variable energy resource settlement Straw proposal

Bid cost recovery and variable energy resource settlement Straw proposal Bid cost recovery and variable energy resource settlement Straw proposal April 9, 2015 Table of Contents 1. Background... 3 2. Schedule for policy stakeholder engagement... 3 3. Initiative scope... 3 4.

More information

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Wei Zhou (wei.zhou@sce.com) SCE May 17, 2018 Please use this template to provide your comments on the FRACMOO Phase 2 stakeholder initiative

More information

Real-Time Imbalance Energy Offset (RTIEO)

Real-Time Imbalance Energy Offset (RTIEO) Real-Time Imbalance Energy Offset & Price Inconsistency Caused by Intertie Constraints Comments Real-Time Imbalance Energy Offset (RTIEO) Submitted by Jeffrey Nelson (626)302-4834 Company Southern California

More information

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units Draft Final Proposal Pricing Logic Under Flexible Modeling of Constrained Output Generating Units April 14, 2008 This is the third CAISO paper on this issue. An Issue Paper was posted on February 1, 2008

More information

Stakeholder Comments Template. Day-Ahead Market Enhancements Phase 1 Initiative

Stakeholder Comments Template. Day-Ahead Market Enhancements Phase 1 Initiative Stakeholder Comments Template Day-Ahead Market Enhancements Phase 1 Initiative This template has been created for submission of stakeholder comments on the third revised straw proposal that was published

More information

Local Market Power Mitigation Enhancements

Local Market Power Mitigation Enhancements Local Market Power Mitigation Enhancements Issue Paper/Straw Proposal Working Group October 10, 2018 10:00 am 4:00 pm Market Design Policy Purpose of working group: Review flow reversal and economic displacement

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE ELECTRICITY STORAGE ASSOCIATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE ELECTRICITY STORAGE ASSOCIATION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Frequency Regulation Compensation ) in the Organized Wholesale Power Markets ) ) Docket Nos. RM 11-7/AD10-11 COMMENTS OF THE ELECTRICITY

More information

Initial Comments on SPP s Draft Ramp Product Report

Initial Comments on SPP s Draft Ramp Product Report DRDdR Initial Comments on SPP s Draft Ramp Product Report PREPARED FOR PREPARED BY Johannes Pfeifenberger John Tsoukalis Judy Chang Kathleen Spees August 30, 2018 Notice These comments reflect the perspectives

More information

Day Ahead Market Enhancements: Issue Paper/Straw Proposal

Day Ahead Market Enhancements: Issue Paper/Straw Proposal Day Ahead Market Enhancements: Issue Paper/Straw Proposal Don Tretheway Senior Advisor, Market Design Policy Megan Poage Senior Market Design & Regulatory Policy Developer March 7, 2018 Agenda Time Topic

More information

California ISO. Q Report on Market Issues and Performance. November 1, Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. November 1, Department of Market Monitoring California Independent System Operator Corporation California ISO Q3 2018 Report on Market Issues and Performance November 1, 2018 Department of Market Monitoring TABLE OF CONTENTS Executive summary...

More information

EIM Settlements Load Customer Training September 13, 2016

EIM Settlements Load Customer Training September 13, 2016 EIM Settlements Load Customer Training September 13, 2016 EIM Settlements Customer Training Review EIM 101 EIM terminology Participating / Non-Participating Base Schedules and etags Settlements and Disputes

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Storage Participation in ) Markets Operated by Regional ) Docket Nos. RM16-23; AD16-20 Transmission Organizations and )

More information

California ISO. Issue Paper. Renewable Integration: Market and Product Review Phase 1

California ISO. Issue Paper. Renewable Integration: Market and Product Review Phase 1 Issue Paper Renewable Integration: Market and Product Review Phase 1 September 30, 2010 Issue Paper Phase 1 Table of Contents 1 Introduction and Overview... 3 2 Themes from the Issues Forum and Proposed

More information

Commitment Costs and Default Energy Bid Enhancements Revised Draft Final Proposal

Commitment Costs and Default Energy Bid Enhancements Revised Draft Final Proposal Commitment Costs and Default Energy Bid Enhancements Revised Draft Final Proposal Cathleen Colbert, Sr. Policy Developer Brittany Dean, Policy Developer Bradford Cooper, Manager Market and Infrastructure

More information

Imbalance Conformance Enhancements. Revised Draft Final Proposal

Imbalance Conformance Enhancements. Revised Draft Final Proposal Imbalance Conformance Enhancements March 14, 2018 Intentionally left blank CAISO/M&ID/MDP/M.Poage Page 2 March 14, 2018 Imbalance Conformance Enhancements Table of Contents 1. Purpose... 5 2. Scope Changes

More information

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Working Group Meeting. Karl Meeusen, Ph.D. June 18, 2018

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Working Group Meeting. Karl Meeusen, Ph.D. June 18, 2018 Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2 Working Group Meeting Karl Meeusen, Ph.D. June 18, 2018 FRACMOO 2 Working Group Meeting Agenda 6/18/2018 Time Topic Presenter 10:00

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Solving the Dual Constraint A Physical Counterflow Feasibility Run

Solving the Dual Constraint A Physical Counterflow Feasibility Run Solving the Dual Constraint A Physical Counterflow Feasibility Run April 30, 2012 Alex Morris Southern California Edison Alexander.Morris@sce.com MARKET STRATEGY & RESOURCE PLANNING Page 1 Objectives and

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

A Market Solution to the Duck Curve

A Market Solution to the Duck Curve WHITEPAPER Rick Hoefer, Utilicast A Market Solution to the Duck Curve I. INTRODUCTION In the operation of today s power systems, renewables (especially solar and wind) are becoming a larger and larger

More information

Payment Acceleration Meter Data Estimation

Payment Acceleration Meter Data Estimation Payment Acceleration Meter Data Estimation Jill Powers Manager, Operations Data and Compliance Stakeholder Conference Call September 18, 2008 Purpose of Today s Meeting Clarify where we are at in the process

More information

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2013 Report on Market Issues and Performance February 10, 2014 Prepared by: Department of Market Monitoring Department of Market Monitoring

More information

Regional Flexibility Markets

Regional Flexibility Markets CAISO Contingency Modeling Alternative: Regional Flexibility Markets March 2014 Southern California Edison Outline Concerns with the CAISO s N-1-1 proposal Alternative approach: Regional Flexibility Markets

More information

Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting

Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting Karl Meeusen, Ph.D. September 26, 2017 2017 CAISO - Public Page 1 FRACMOO 2 Working Group Meeting Agenda 9/26/2017 Time

More information

Ancillary Service Markets

Ancillary Service Markets Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;

More information

EIM Offer Rules Workshop Resource Sufficiency Test and EIM Mitigation

EIM Offer Rules Workshop Resource Sufficiency Test and EIM Mitigation EIM Offer Rules Workshop Resource Sufficiency Test and EIM Mitigation Stakeholder Workshop July 19, 2018 Megan Poage & Brittany Dean Market Design Policy Agenda Time Topic Presenter 10:00 10:15 am Welcome

More information

Flexible Ramping Products Straw Proposal Incorporating FMM and EIM

Flexible Ramping Products Straw Proposal Incorporating FMM and EIM Flexible Ramping Products Straw Proposal Incorporating FMM and EIM Lin Xu, Ph.D. Lead Market Development Engineer Don Tretheway Lead Market Design and Policy Specialist August 20, 2014 Agenda Time Topic

More information

EIM Greenhouse Gas Enhancement. Draft Final Proposal

EIM Greenhouse Gas Enhancement. Draft Final Proposal EIM Greenhouse Gas Enhancement Draft Final Proposal May 24, 2017 EIM Greenhouse Gas Enhancement Draft Final Proposal Table of Contents 1 Introduction... 3 2 Stakeholder Process and Timeline... 4 3 Changes

More information

Submitted by Company Date Submitted. Pacific Gas and Electric Company

Submitted by Company Date Submitted. Pacific Gas and Electric Company Comments of Pacific Gas and Electric Company on Commitment Costs and Default Energy Bid Enhancements Revised Straw Proposal and 8/11 Stakeholder Meeting Submitted by Company Date Submitted Cristy Sanada

More information

Business Requirements Specification

Business Requirements Specification Business Requirements Specification Energy Imbalance Market Enhancements 2018 Document Version: 1.21.3 Doc ID: GNFDMDEHU6BB-46-53 Page 1 of 20 Revision History Date Version Description 4/18/2018 1.0 Initial

More information

2014 Grid of the Future Symposium

2014 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Concepts and Practice Using Stochastic Programs for Determining Reserve Requirements

More information

Impact of Convergence Bidding on Interties. Draft Final Proposal

Impact of Convergence Bidding on Interties. Draft Final Proposal Impact of Convergence Bidding on Interties Draft Final Proposal July 29, 2011 Impact of Convergence Bidding on Interties Table of Contents 1 Introduction... 3 2 Plan for Stakeholder Engagement... 3 3 Issue

More information

APPENDIX F FLEXIBLE RESERVE STUDY

APPENDIX F FLEXIBLE RESERVE STUDY Introduction This 2017 Flexible Reserve Study ( FRS ) estimates the regulation reserve required to maintain PacifiCorp s system reliability and comply with North American Electric Reliability Corporation

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: August 29, 2018 Re: Decision on the

More information

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources Market Issues Bulletin Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources March 10, 2015 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400

More information

Market Design Concepts to Prepare for Significant Renewable Generation

Market Design Concepts to Prepare for Significant Renewable Generation Market Design Concepts to Prepare for Significant Renewable Generation Flexible Ramping Product Ethan D. Avallone SENIOR MARKET DESIGN SPECIALIST ENERGY MARKET DESIGN Market Issues Working Group April

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...

More information

Load Granularity Refinements Issue Paper

Load Granularity Refinements Issue Paper Load Granularity Refinements Issue Paper September 22, 2014 Table of Contents I. Introduction... 3 II. Background... 3 III. Scope of Initiative and Plan for Stakeholder Engagement... 4 IV. FERC s Reasons

More information

2. Market Operations Overview

2. Market Operations Overview 2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static

More information

Stakeholder Comments Template. Subject: SCE Comments on Dynamic Transfer Revised Final Draft 2/18/11

Stakeholder Comments Template. Subject: SCE Comments on Dynamic Transfer Revised Final Draft 2/18/11 Stakeholder Comments Template Subject: SCE Comments on Dynamic Transfer Revised Final Draft 2/18/11 Submitted by Company Date Submitted Rich Mettling 626.302.9712 rich.mettling@sce.com SCE Mar 15, 2011

More information

Intertie Deviation Settlement. Draft Final Proposal

Intertie Deviation Settlement. Draft Final Proposal Intertie Deviation Settlement Draft Final Proposal December 12, 2018 Intertie Deviation Settlement Draft Final Proposal Table of Contents 1. Purpose... 4 1.1 Response to Stakeholder Comments... 4 2. References...

More information

EIM Resource Sufficiency Evaluation

EIM Resource Sufficiency Evaluation EIM Resource Sufficiency Evaluation Megan Poage & Don Tretheway Market Design Policy Stakeholder Call September 26, 2018 ISO proposes resource sufficiency evaluation improvements in response to stakeholder

More information

Three Policies Make Storage Market. October 12, 2011

Three Policies Make Storage Market. October 12, 2011 Three Policies Make Storage Market October 12, 2011 Overview Repeated use of MW-scale battery Storage started in 2009 in Hawaii with requirement on renewables. FERC rulemaking for compensation of fast

More information

Comments of Pacific Gas & Electric Company Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2 Revised Straw Proposal

Comments of Pacific Gas & Electric Company Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2 Revised Straw Proposal Comments of Pacific Gas & Electric Company Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2 Revised Straw Proposal Submitted by Company Date Submitted Kristin Charipar (415-973-6177)

More information

Day Ahead Market Enhancements: Revised Straw Proposal. April 18, 2018

Day Ahead Market Enhancements: Revised Straw Proposal. April 18, 2018 Day Ahead Market Enhancements: Revised Straw Proposal April 18, 2018 Agenda Time Topic Presenter 10:00 10:15 Welcome and Introductions Kristina Osborne 10:15 11:00 General Overview Megan Poage 11:00 12:00

More information

Strategic Selection of Capacity and Mileage Bids in California ISO Performance-based Regulation Market

Strategic Selection of Capacity and Mileage Bids in California ISO Performance-based Regulation Market 1 Strategic Selection of Capacity and Mileage Bids in California ISO -based Regulation Market Ashkan Sadeghi-Mobarakeh and Hamed Mohsenian-Rad Department of Electrical and Computer Engineering, University

More information

Storage as a Transmission Asset Stakeholder Comment Template

Storage as a Transmission Asset Stakeholder Comment Template Storage as a Transmission Asset Stakeholder Comment Template Submitted by Company Date Submitted Omar Martino Director, Transmission Strategy T: 1.303.568.1273 Omar.Martino@EDF-RE.com EDF-Renewables (EDF-R)

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ELECTRIC STORAGE PARTICIPATION ) IN REGIONS WITH ORGANIZED ) DOCKET NO. AD16-20-000 WHOLESALE ELECTRIC MARKETS ) ) RESPONSE OF THE

More information

165 FERC 61,050 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING PROPOSED TARIFF REVISIONS. (Issued October 29, 2018)

165 FERC 61,050 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING PROPOSED TARIFF REVISIONS. (Issued October 29, 2018) 165 FERC 61,050 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur and Richard Glick. California Independent System Operator

More information