PJM Queue Process Challenges. Aaron Berner Manager, Interconnection Analysis Planning Committee July 14, 2016
|
|
- Geraldine Bridges
- 6 years ago
- Views:
Transcription
1 PJM Queue Process Challenges Aaron Berner Manager, Interconnection Analysis Planning Committee July 14, 2016
2 Applications Types of applications: Attachment N new generation and uprates to existing generation Attachment S merchant transmission requests Attachment Y new generation, less than 2 MW synchronous, 5 MW inverter and not seeking Capacity Interconnection Rights (CIRs) Attachment BB inverter based generation no larger than 10kW Attachment EE Upgrade Request (IARR request) Attachment FF Long term firm request 2
3 Interconnection Process Overview Queue open Build model Feasibility Study Customer review report and return Impact Study Agreement Impact Study Customer review report and return Facility Study Agreement Facility Study Customer review report and return ISA/WMPA (CSA) or UCSA PJM prepare CSA [Required only if CSA not tendered with ISA] Customer review and return CSA Remaining timeline defined by ISA/WMPA milestones, CSA/UCSA schedule and rights to suspend 3
4 Feasibility Study High level, initial evaluation of project Customer can select a primary and secondary Point of Interconnection (POI) Estimates are desk-side level estimates (no field evaluation) 4
5 System Impact Study Refinement of Feasibility Study results Generation customer must select a single POI (if two were evaluated in the Feasibility Study) Analysis incorporates any changes that occurred since the Feasibility Study analysis was performed Estimates are still desk-side 5
6 Current Queue Process New Service Request Studies Feas Imp Fac ISA/CSA/UCSA/ WMPA Execution ISA/CSA/UCSA Implementation Commercial Operation Feasibility Study (Long Term Firm - Initial Study (no reinforcements identified) ; Not performed for Upgrade Requests) Long Term Firm Transmission Service Receives initial study PJM identifies flowgates which may be impacted by service No involvement with Transmission Owners No reinforcements or costs identified PJM performs an initial impact study review after customer returns impact study agreement (might be before queue close) Provides costs to customers for reinforcements Upgrade Requests (IARR) No studies before System Impact Study Phase All other types of projects Initial review of constraints, specifying reinforcements, cost estimates, time to construct reinforcements 6
7 Current Queue Process New Service Request Studies Feas Imp Fac ISA/CSA/UCSA/ WMPA Execution ISA/CSA/UCSA Implementation Commercial Operation Impact Study (Start of analysis for Upgrade Requests) Long Term Firm Transmission Service Receives updated impact study Upgrade Requests (IARR) First study performed All other types of projects Refinement of feasibility study 7
8 Study Alignment Studies intended to be evaluated in coordinated queue Current individual processes for the transmission service and IARR requests do not provide customers with study refinements similar to other projects in queue 8
9 Cost Allocation Rules for upgrades which are estimated to cost less than $5 million PJM must determine if any project in the queue adds load to the element which is overloaded at the end of the queue to assign cost allocation to all customers who add load Requires PJM to wait for end of queue to begin to study projects Reduces the potential that a single customer will fund a reinforcement by themselves 9
10 Alternate Queue Attempt to move projects through process quicker by determining that no Tariff facilities are affected Requires PJM to wait for end of queue to begin to study projects Moves customers to a Wholesale Market Participation Agreement if project is qualified for the Alternate Queue and avoids re-tools 10
11 Potential Delays Less than $5M and Alternate Queue Requires PJM to wait for end of queue to begin to study projects Look for ways to restructure rules to reduce delays in obtaining results for smaller generation projects 11
12 Next Steps Problem statement PC sub-group 12
PJM Manual 14A Updates
PJM Manual 14A Updates Presented by Joseph Hay Project Manager, Interconnection Projects Presented to PJM Planning Committee June 8, 2017 Manual 14A Updates: Interconnection Projects Reasons for Updates:
More informationGeneration Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016
Generation Process SWANA Spring Conference Atlantic City, NJ April 18, 2016 www.pjm.com PJM process is FERC Pro Forma Customer enters queue to sell output into PJM wholesale market (regardless of size)
More informationComparison of interconnection study and market participation agreement processes for wholesale DER
Comparison of interconnection study and market participation agreement processes for wholesale DER Aaron Berner Manager, Interconnection Analysis Applicability These slides describe general processes for
More informationPJM Strawman Proposal
PJM Strawman Proposal Special MIC DER November 17, 2017 DER Proposal: General Overview 1. Not Demand Response, not Generation: proposal is for 3rd ruleset for DER. DER can choose to participate as either
More informationPJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department
PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7
More informationWholesale DER Interconnections
Wholesale DER Interconnections David Egan / Susan McGill Manager, Interconnection Projects / Analysis July 30, 2018 Distributed Energy Resources Subcommittee Agenda Jurisdiction Pre-Applications: Formal
More informationPJM Queue Position Establishment Background and Support for Problem Statement
PJM Queue Position Establishment Background and Support for Problem Statement Presented by David Egan Manager, Interconnection Projects To the PJM Planning Committee June 11, 2015 Overview Establishing
More informationPJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018
PJM Manual 14E: Additional Information for Upgrade and Transmission Revision: 05 Effective Date: April 1, 2018 Prepared by System Planning Division Department PJM 2018 Table of Contents Table of Contents
More informationAn Introduction to Interconnection Policy in the United States
An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator
More informationGeneration Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction
More informationPG&E s WDT Interconnection Reform Principles Document
PG&E s WDT Interconnection Reform Principles Document The purpose of this document is to lay out PG&E s high-level objectives and to discuss the underlying principles behind the interconnection process
More informationFirm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff.
Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Upgrade Feasibility Study: A study conducted by the Transmission Provider
More informationINCREMENTAL AUCTION REVENUE RIGHTS
Joint and Common Market INCREMENTAL AUCTION REVENUE RIGHTS Brian Chmielewski Manager, Market Simulation November 27, 2018 Overview Purpose Provide stakeholders with an update on the MISO-PJM plan for enhanced
More informationManual 21- Revision 13 Rules and Procedures for Determination of Generating Capability Changes
Manual 21- Revision 13 Rules and Procedures for Determination of Generating Capability Changes Jerry Bell Resource Adequacy Department Markets and Reliability Committee March 21 st, 2019 Manual 21 changes
More informationBusiness Practice Manual for Distributed Generation Deliverability. Version
Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:
More informationCapacity Resource versus Energy Resource
Capacity Resource versus Energy Resource Seasonal Capacity Resource Senior Task Force April 18, 2016 Capacity Resource or Energy Resource? When a new generator connects to PJM s system through the PJM
More informationContents. DRAFT Capacity Deliverability Fact Finding Summary Report
DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system
More informationGenerator Interconnection Process. Wholesale Distribution Overview
1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation
More informationGeneration Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038
Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy February / 2015 Introduction
More informationPJM s Implementation of Order 845
PJM s Implementation of Order 845 Susan McGill Manager, Interconnection Analysis Michelle Harhai PJM Legal Compliance Filing Update On September 24, 2018, the Edison Electric Institute on behalf of its
More informationWhat You Need to Know Before Requesting Interconnection
Connecting to the Utility Grid What You Need to Know Before Requesting Interconnection Peter Giannotti Southern California Edison August 16, 2017 Tampa Convention Center Tampa, Florida Why is Grid Interconnection
More informationRule 21 Tariff / Process Overview 6/17/2015
Rule 21 Tariff / Process Overview 6/17/2015 Rule 21/WDAT Overview Rule 21 Jurisdiction CPUC FERC WDAT Applicability Generator/storage retail interconnections (transmission or distribution); retail solicitations
More informationCoordinated Planning / Deliverability Studies
PJM-MISO Stakeholder JCM Briefing June 30, 2005 Coordinated Planning / Deliverability Studies Version 1.0 6/28/05 Discussion Overview Deliverability Study Processes in PJM and MISO Current Coordination
More informationregulations of the Federal Energy Regulatory Commission ( Commission or FERC ), 2 PJM
PJM Interconnection Valley Forge Corporate Center 955 Jefferson Avenue Norristown, PA 19403-2497 Jennifer H. Tribulski Senior Counsel 610.666.4363 fax 610.666.8211 tribuj@pjm.com Filing Via etariff Honorable
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. : Docket No. ER
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. : Docket No. ER19-982-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF PJM INTERCONNECTION, L.L.C. TO PROTEST
More informationMISO-PJM Joint and Common Market Drill Down Report
MISO-PJM Joint and Common Market Drill Down Report May 30, 2018 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan Timeline
More information2019 Project Prioritization and Budgeting Process
2019 Project Prioritization and Budgeting Process Brian Hurysz Manager, Market Products Budget and Priorities Working Group May 10, 2018, Krey Corporate Center Agenda Project Prioritization Process Project
More informationNV Energy s Open Access Transmission Tariff (OATT) Proposed Changes. November 2011
NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes November 2011 Proposed Tariff Changes More detailed Intra-hour scheduling language to be added Revisions to Attachment N (Large Generator
More informationQueue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012
Queue Management A look at queue reform and the queue process Jennifer Heintz and Janet Wheeler June 12, 2012 1a What is a queue? The interconnection queue (queue) refers to the process of getting a new
More informationJCM Drill Down Report -- Draft. March 21, 2014
JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill
More informationJoint and Common Market II. MISO/PJM FTR COORDINATION UPDATE
Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE 1 Background and Status At the September 20 th JCM, MISO and PJM discussed the approach for FTR coordination Outage Coordination Both PJM and
More informationGenerator Interconnection Procedures Overview
Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution
More informationMISO PJM Cross-Border Planning
MISO PJM Cross-Border Planning July 24, 2014 MISO-PJM JCM Planning Coordination Issues 2 At a previous JCM meeting, several issues related to planning coordination were raised: Market Efficiency Planning
More informationMust-Offer Exception Process Issue
Must-Offer Exception Process Issue Patrick Bruno Sr. Engineer, Capacity Market Operations Market Implementation Committee August 8, 2018 Background Issue brought forward by Exelon to investigate: Possible
More informationDISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET
DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION Purpose This fact sheet outlines the steps required for you to undertake an interconnection
More informationCRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR)
CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) Ethan D. Avallone Senior Market Design Specialist, Energy Market Design Management Committee March 28, 2018
More informationStakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012
Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business
More informationSmall Generator Interconnection Procedures
Small Generator Interconnection Procedures Thinh Nguyen Senior Manager, Interconnection Projects ICAP WG/MIWG/PRLWG September 28, 2018 Topics Determining the Applicable Interconnection Process for ERIS
More informationPJM s Experience with the RPM Capacity Market
PJM s Experience with the RPM Capacity Market 2013 Austin Electricity Conference Panel 1: Are Capacity Market Necessary to Ensure Adequate Generating Reserve Paul M. Sotkiewicz, Ph.D. Chief Economist PJM
More informationGeneration and Transmission Planning
Section 12 Planning Generation and Transmission Planning Overview Planned Generation and Retirements Planned Generation. As of June 30, 2016, 83,390.2 MW of capacity were in generation request queues for
More informationInterconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions
After the study process, main contact becomes your ISO contract negotiator Reports will be issued using Resource Interconnection Management System database (RIMS). It is imperative that project owners
More informationEnergy Efficiency in RPM. Adam Keech Director, Market Operations PJM January 13, 2015
Energy Efficiency in RPM Adam Keech Director, Market Operations PJM January 13, 2015 PJM Capacity Market PJM Capacity Market Reliability Pricing Model (RPM) PJM secures capacity on behalf of LSEs to satisfy
More informationPJM/MISO Joint and Common Market Stakeholder Meeting. June 2, 2005 Wilmington, DE
PJM/MISO Joint and Common Market Stakeholder Meeting June 2, 25 Wilmington, DE Agenda Morning Meeting Objectives Review of March 3, 25 FERC Order Market-to-Market Coordination Update Stakeholder Process
More informationGet Connected: Distributed Generation
Get Connected: Distributed Generation Our goal is to make sure your distributed generation project is connected safely and efficiently. Getting connected to our system is a six-phase process. Use this
More informationPJM Overview: PJM Structure and Cross-Border Examples PJM 2010
PJM Overview: PJM Structure and Cross-Border Examples 1 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 614 millions of people served 51 peak load in megawatts
More informationJCM Drill Down Report. February 19, 2015
JCM Drill Down Report February 19, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report
More informationPJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan
PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan David Schweizer Manager, Generation OC Meeting June 6, 2017 Overview PJM target for issuing next 5-Year RTO Wide Black Start RFP
More informationAEP Transmission Local Planning Assumptions, Models, and Criteria
AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States
More informationRevised Transmission Planning Process. Complete Final Proposal
Revised Transmission Planning Process Complete Final Proposal May 7, 2010 Complete Final Proposal 1. Introduction and Summary In this document the ISO provides a complete description of its revised transmission
More informationJoint and Common Market ITEM 4 PSEUDO TIES
Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM pseudo ties
More informationM14B Annual Review. Jonathan Kern Transmission Planning Planning Committee March 8 th, PJM 2018
M14B Annual Review Jonathan Kern Transmission Planning Planning Committee March 8 th, 2018 Background PJM performs an annual review of M14B to ensure that all procedural language is in line with current
More informationInterconnection Feasibility Study
XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY
More informationInterconnection Feasibility Study
XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION
More informationSmall Generator Interconnection Procedures (SGIP) Customer Guide
Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission
More informationSummary of Submitted Comments
Stakeholder Process: Generator Interconnection Procedures Phase 2 Summary of Submitted Comments Stakeholders have submitted four rounds of written comments to the ISO on the following dates: Round One:
More information1.3 Planning Assumptions and Model Development
Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission
More informationMothball Outages in Capacity Markets
Mothball Outages in Capacity Markets (preliminary review and summary for working group discussion purposes consult relevant ISO directly for latest and detailed legal requirements) September 13, 2017 NYISO
More informationCAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)
Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC
More informationOverview of Distributed Generation Interconnection Issues
Overview of Distributed Generation Interconnection Issues 50 State Street, Suite 3 Montpelier, Vermont USA 05602 Tel: 802.223.8199 Fax: 802.223.8172 Wayne Shirley Director The Regulatory Assistance Project
More informationReactive Power Requirements and Financial Compensation Draft Final Proposal Stakeholder Call
Reactive Power Requirements and Financial Compensation Draft Final Proposal Stakeholder Call November 19, 2015 November 19, 2015 stakeholder meeting agenda Time Topic Presenter 9:00-9:05 Introduction Kim
More informationISA FORM TEMPLATE (From Attachment O of the PJM Tariff)
ISA FORM TEMPLATE (From Attachment O of the PJM Tariff) Original Service Agreement No. [ ] Effective Date: [ ] (PJM Queue # ) INTERCONNECTION SERVICE AGREEMENT Among PJM INTERCONNECTION, L.L.C. And And
More informationJCM Drill Down Report. May 27, 2015
JCM Drill Down Report May 27, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report
More informationAddressing Affected System Impacts of Generator Interconnection: Processes and Principles
Addressing Affected System Impacts of Generator Interconnection: Processes and Principles August 5, 2013 Table of Contents 1 Executive Summary... 2 2 Introduction... 2 3 Stakeholder Process and Schedule...
More informationOrder 1000 Lessons Learned Analysis: Proposed Voltage Threshold Proposal Window Process
Order 1000 Lessons Learned Analysis: Proposed Voltage Threshold Proposal Window Process Planning Committee Suzanne Glatz December 3, 2015 Challenge Under PJM Model: Order 1000 Implementation Model For
More informationRTEP Structure & Timing
RTEP Structure & Timing Approach & Clarifications Summary: The purpose of this document is to provide supporting information for the RTEP Structure & Timing Diagrams. The first section describes the approach
More informationIs FERC s Generator Interconnection Policy really conducive to efficient generation development?
By Steven S. Garwood PowerGrid Strategies, LLC March 24, 2010 Is FERC s Generator Interconnection Policy really conducive to efficient generation development? Critical environment for efficient generation
More informationInterconnection Feasibility Study
XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION POST-TECHNICAL CONFERENCE COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent
More informationGeneration and Transmission Planning
Section 12 Planning Generation and Transmission Planning Overview Planned Generation and Retirements Planned Generation. As of June 30, 2015, 77,461.3 MW of capacity were in generation request queues for
More informationEast Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report
East Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report Updated January 25, 2013 Table of Contents Table of Contents INTRODUCTION... 1 EXECUTIVE SUMMARY... 3 KEY FINDINGS... 5 OBJECTIVE
More informationTransmission Expansion and Interconnection Manual. June 2017
MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection
More informationKentucky State Report
Kentucky State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions
More informationDistributed Energy Resources Roadmap
Distributed Energy Resources Roadmap Updates Overview James Pigeon Senior Market Design Specialist Distributed Resources Integration MIWG December 19, 2016 Krey Corporate Center - Rensselaer, NY 2000-2016
More informationMISO-PJM Joint and Common Market Drill Down Report
MISO-PJM Joint and Common Market Drill Down Report February 28, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan
More informationBonneville Power Administration Current Transmission Perspectives
Bonneville Power Administration Current Transmission Perspectives WSCC Operating Committee September 26, 2011 Lauren Nichols-Kinas lnichols@bpa.gov 1 BPA: A Brief Description Bonneville Power Administration
More informationGeneration and Transmission Planning
Section 12 Planning Generation and Transmission Planning Overview Planned Generation and Retirements Planned Generation. As of September 30, 2015, 79,603.8 MW of capacity were in generation request queues
More informationImpacts from Peak Load Reductions in Markets and Long-Range Planning
JUNE 21, 2016 BOSTON, MA Impacts from Peak Load Reductions in Markets and Long-Range Planning MA Energy Efficiency Advisory Council Eric Winkler, Ph.D. TECHNICAL MANAGER, SYSTEM PLANNING Overview of Presentation
More informationMISO-PJM Joint and Common Market Drill Down Report
MISO-PJM Joint and Common Market Drill Down Report August 22, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan
More informationThe State of Wind Energy in New England
JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New
More informationGrowing Wind. Final Report of the NYISO 2010 Wind Generation Study. John Adams Principal Electric System Planner New York Independent System Operator
Growing Wind Final Report of the NYISO 2010 Wind Generation Study John Adams Principal Electric System Planner New York Independent System Operator National Wind Coordinating Collaborative Transmission
More informationSolar Integration into the PJM Grid
Solar Integration into the PJM Grid Ken Schuyler Manager, Renewable Services PJM Interconnection September 14, 2017 Integrating Solar in PJM PJM Background PJM Initiatives to Address Impacts Analysis of
More informationManaging the Reliability of the Electric Grid While the Power Industry Undergoes Rapid Transformation
SEPTEMBER 19, 2014 BOSTON, MA Managing the Reliability of the Electric Grid While the Power Industry Undergoes Rapid Transformation Massachusetts Restructuring Roundtable Gordon van Welie PRESIDENT & CEO
More informationExpanding Transmission Capacity: Options and Implications. Jennifer Curran Director Transmission Strategy April 30, 2009
Expanding Transmission Capacity: Options and Implications Jennifer Curran (jcurran@midwestiso.org) Director Transmission Strategy April 30, 2009 The Transmission Design Challenge General Problem Statement
More informationRelevant changes will be made to corresponding sections of OA and RAA.
PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010
More informationOverview of PJM: Looking Back to Look Forward Tokyo Power Market Summit
Overview of PJM: Looking Back to Look Forward Tokyo Power Market Summit Craig Glazer Vice President, Federal Government Policy PJM Interconnection June, 2018 Topics 1. PJM Overview 2. Evolution of PJM
More informationTransmission Expansion Advisory Committee Meeting Market Efficiency Analysis Preliminary Input Assumptions
Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis Preliminary Input Assumptions March 6, 2014 Study Years Market Simulation Input Data 2015 and 2019 to study approved RTEP
More informationSCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013
SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:
More informationPJM Planning Process Strawman
PJM Planning Process Strawman State Agreement Approach RPPTF September 28, 2011 Steve Herling State Agreement Approach Framework Defines communications options for states with respect to RTEP process Allows
More informationCapacity Deliverability. May 27, 2015 MISO-PJM JCM
Capacity Deliverability May 27, 2015 MISO-PJM JCM Key Takeaways and Objective Capacity deliverability seeks to eliminate barriers for capacity transactions across the seam MISO is evaluating options to
More informationStatus Update Assessment of ICT/RTO Options and Issues
JULY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESS Session 5 Status Update Assessment of ICT/RTO Options and Issues Kurt Castleberry July 15, 2010 1 JULY 2010 PRELIMINARY TECHNICAL CONFERENCE
More informationBenefits from Generation and Storage on the Distribution System
Benefits from Generation and Storage on the Distribution System Andrew Levitt Senior Market Strategist Emerging Markets Special MRC Meeting DER Aug 24, 2016 Generation/Storage Resource Location and Types
More informationMISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN
MISO SPP Interregional Stakeholder Advisory Committee April 8 th, 2014 Carmel, IN 1 Agenda Introductions Discussion on Draft Coordinated System Plan (CSP) Study Scope Lunch Continue Discussion on Draft
More informationStakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting
Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Leslie Padilla Submitted by Company Date Submitted lpadilla@semprageneration.com
More informationThird Incremental Auction shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates.
Definitions T U - V Tangible Net Worth: Tangible Net Worth shall mean all assets (not including any intangible assets such as goodwill) less all liabilities. Any such calculation may be reduced by PJMSettlement
More informationAttachment M3 and Sub-Regional RTEP Process Improvements. TRPSTF September, 27, 2017
Attachment M3 and Sub-Regional RTEP Process Improvements TRPSTF September, 27, 2017 PJM s Sub Regional Planning Process FERC Order No. 890 Requirements: Transmission providers must meet with their transmission
More informationFinancial Transmission Rights
PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM
More information2017 Project Prioritization & Budgeting Process
2017 Project Prioritization & Budgeting Process Ryan Smith Senior Manager Budget & Priorities Working Group June 24, 2016 Krey Corporate Center 2000-2016 New York Independent System Operator, Inc. All
More informationINFORMATION RELEASE. TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates
INFORMATION RELEASE TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates OVERVIEW This Information Release is intended to provide an overview of the transmission constraints
More informationDISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS
DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION FortisAlberta s Distributed Energy Resource (DER) Process explains what is required
More informationCAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)
Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC
More information