Small Generator Interconnection Procedures (SGIP) Customer Guide

Size: px
Start display at page:

Download "Small Generator Interconnection Procedures (SGIP) Customer Guide"

Transcription

1 Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission and distribution system. The SGIP and all required documents can be found on SCE&G s Open Access Same-time Information System (OASIS). This document is intended as a guide to help the Interconnecting Customer understand the SGIP. Should there be any discrepancies in this document and the SGIP, the SGIP will apply. FACILITY SIZE 1 APPLICABLE TARIFF PROCEDURE > 20 MW LARGE GENERATOR INTERCONNECTION PROCEDURE, PLEASE REFER TO THE SCE&G OASIS FOR MORE INFORMATION. QUALIFYING FACILITIES NOT PARTICIPATING IN THE STATE NET METERING PROGRAM STATE NET METERING PROGRAM >5 MW - 20MW, or <5 MW and ineligible for Fast Track or 10kW inverter process 10kW - up to 5 MW See table below for eligibility SGIP STUDY PROCESS SGIP FAST TRACK PROCESS (IF SCREENS ARE MET, OTHERWISE STUDY PROCESS) 0-10kW SGIP INVERTER PROCESS (IF SCREENS ARE MET, OTHERWISE STUDY PROCESS) 0-100kW PLEASE CONTACT SCE&G RENEWABLES PRODUCTS & SERVICES AT The SGIP contains four processes. The applicable process for each specific interconnection request depends on a number of factors. 1. Pre- Application Process An Interconnection Customer (IC) may submit a formal written request form along with a non-refundable fee of $300 for a pre-application report on a proposed project at a specific site. Transmission Provider (TP) shall provide pre-application report within 20 Business Days (BD) of receipt of the completed request form and payment of the $300 fee. The report need only include existing data. The report is non-binding, does not confer any rights, and the IC must still successfully apply to be interconnected to the TP s system. 1 Interconnection Requests shall be evaluated based on the Small Generating Facility s maximum rated capacity. 1 of 5

2 Customer Guide 2. Fast Track Process For Certified Small Generating Facilities as identified on Fast Track Eligibility table, Technical screens are used to quickly identify reliability and safety issues instead of the interconnection studies. Line Voltage Fast Track Eligibility for Inverter-Based Systems Fast Track Eligibility Regardless of Location Fast Track Eligibility on a Mainline 2 and 2.5 Electrical Circuit Miles from Substation 3 5kV 500kW 500kW 5kV and < 15kV 2MW 3MW 15kV and < 30kV 3MW 4MW 30kV and 69kV 4MW 5MW 3. Study Process Default method consisting of a scoping meeting, a feasibility study, a system impact study and a facilities study. Feasibility Study - This is a preliminary technical assessment of the proposed interconnection. 4 System Impact Study - This is a more detailed assessment of the effect the interconnection would have on the TP s electric system and Affected Systems. Facilities Study This determines what modification to the TP s electric system are needed, includes detailed costs and scheduled completion dates for these modifications. Once IC agrees to fund any needed upgrades, the Parties execute a Small Generator Interconnection Agreement (SGIA ) that, among other things, formalizes responsibility for construction and payment for Interconnection Facilities and Upgrades kw Inverter Process For Certified inverter-based Small Generating Facility no larger than 10kW Small Generator Interconnection Agreement (SGIA) does not apply to requests to interconnect submitted under the 10kW Inverter Process. The TP s evaluation of a project with multiple Points of Interconnection should be performed, using Good Utility Practice (TP has the option to either treat such projects separately for queuing and interconnection study purposes, or as a single Point of Interconnection), based on the project s unique engineering and geographic needs. 2 A main line is a three-phase backbone of a circuit; will typically constitute lines with wire sizes of 4/0 American wire gauge, kcmil, kcmil, 477 kcmil and 795 kcmil. 3 An Interconnection Customer can determine this information about it s proposed interconnection location in advance by requesting a pre-application report pursuant to section In the case an overlap between the feasibility study and the system impact study occurs, it may be reasonable to skip the feasibility study entirely where the distinction may not be enough to require that both studies be performed. 2 of 5

3 Section 1. Pre-Application/Request Note: 1. $300 non-refundable fee for a pre-application report on a proposed project at a specific site. 2. A complete IR includes a completed application form, $1,000 deposit, and demonstration of site control. IC deposit goes towards the cost of the feasibility study. A $500 processing fee is required under the Fast Track Process. A $100 non-refundable application fee is due under the 10kW Inverter Process. 3 of 5

4 Section 2. Fast Track Process (Only available for certified SGF s based on Fast Track eligibility ) 1 Notes: 1. A Certified Small Generating Facility is one that has been certified by a nationally recognized laboratory before the Interconnection Request is submitted to the TP. 2. The Fast Track Process is available to the IC if the SGF meets the requirements of Attachments 3 & 4 of the SGIP, or if the TP has reviewed the design or tested the SGF and is satisfied that it is safe to operate [2.1]. 3. If the IC does not sign the IA, or request that it be filed unexecuted within 30 BD, the IR is deemed withdrawn. 4 of 5

5 Section 3. Study Process Notes: 1. The Scoping Meeting may be omitted by mutual agreement. 2. The TP has 20 additional BD to complete a system impact study requiring review by Affected Systems. 3. In cases where upgrades are required, the facilities study must be completed within 45 BD. In cases where no upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 BD. 4. If the IC does not sign the IA, or request that it be filed unexecuted within 30 BD, the IR is deemed withdrawn. 5. Facilities Study Agreement, Section 9. 5 of 5

Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW)

Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW) Appendix C RM13-2-000 (Revised) Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW) Where to Send Comments on Public Reporting Burden The public reporting

More information

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14 FERC Electric Tariff Page 1 of 2 ATTACHMENT N Small Generator Interconnection Procedures and Agreement (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14

More information

An Introduction to Interconnection Policy in the United States

An Introduction to Interconnection Policy in the United States An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

Cluster Study Process

Cluster Study Process Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

PJM Queue Position Establishment Background and Support for Problem Statement

PJM Queue Position Establishment Background and Support for Problem Statement PJM Queue Position Establishment Background and Support for Problem Statement Presented by David Egan Manager, Interconnection Projects To the PJM Planning Committee June 11, 2015 Overview Establishing

More information

Wholesale DER Interconnections

Wholesale DER Interconnections Wholesale DER Interconnections David Egan / Susan McGill Manager, Interconnection Projects / Analysis July 30, 2018 Distributed Energy Resources Subcommittee Agenda Jurisdiction Pre-Applications: Formal

More information

Generator Interconnection Procedures Overview

Generator Interconnection Procedures Overview Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution

More information

SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW)

SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) The revisions to this document take effect August 28, 2006, per FERC Order No. 2006-B issued July 20, 2006, FERC Stats. & Regs. 31,221, which was published in the Federal Register July 27, 2006 (71 FR

More information

Generator Interconnection Process. Wholesale Distribution Overview

Generator Interconnection Process. Wholesale Distribution Overview 1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation

More information

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff.

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Upgrade Feasibility Study: A study conducted by the Transmission Provider

More information

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions After the study process, main contact becomes your ISO contract negotiator Reports will be issued using Resource Interconnection Management System database (RIMS). It is imperative that project owners

More information

PG&E s WDT Interconnection Reform Principles Document

PG&E s WDT Interconnection Reform Principles Document PG&E s WDT Interconnection Reform Principles Document The purpose of this document is to lay out PG&E s high-level objectives and to discuss the underlying principles behind the interconnection process

More information

ATTACHMENT P SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW)

ATTACHMENT P SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) ATTACHMENT P SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) Section 1 Application 1.1 Applicability 1.1.1 A request to interconnect a certified Small

More information

NYISO Governance Summary of Sector Definitions and Related Terms

NYISO Governance Summary of Sector Definitions and Related Terms NYISO Governance Summary of Sector Definitions and Related Terms There are five voting sectors that participate in the NYISO s shared governance. They are: Generation Owners Other Suppliers Transmission

More information

Rule 21 Tariff / Process Overview 6/17/2015

Rule 21 Tariff / Process Overview 6/17/2015 Rule 21 Tariff / Process Overview 6/17/2015 Rule 21/WDAT Overview Rule 21 Jurisdiction CPUC FERC WDAT Applicability Generator/storage retail interconnections (transmission or distribution); retail solicitations

More information

What You Need to Know Before Requesting Interconnection

What You Need to Know Before Requesting Interconnection Connecting to the Utility Grid What You Need to Know Before Requesting Interconnection Peter Giannotti Southern California Edison August 16, 2017 Tampa Convention Center Tampa, Florida Why is Grid Interconnection

More information

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

Small Generator Interconnection Procedures

Small Generator Interconnection Procedures Small Generator Interconnection Procedures Thinh Nguyen Senior Manager, Interconnection Projects ICAP WG/MIWG/PRLWG September 28, 2018 Topics Determining the Applicable Interconnection Process for ERIS

More information

effective date 1/8/01

effective date 1/8/01 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical

More information

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I

More information

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201 TARIFF FOR WHOLESALE TRANSMISSION SERVICE 1900 North Akard Dallas, Texas 75201 Applicability: Entire System Sheet No. 1 Effective Date: May 25, 2018 Revision: 17 Availability Wholesale Transmission Service

More information

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012 Queue Management A look at queue reform and the queue process Jennifer Heintz and Janet Wheeler June 12, 2012 1a What is a queue? The interconnection queue (queue) refers to the process of getting a new

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager:

Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: FAQs from 2017-08-30 Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: PSCo2017AllSource@xcelenergy.com Q:

More information

Is FERC s Generator Interconnection Policy really conducive to efficient generation development?

Is FERC s Generator Interconnection Policy really conducive to efficient generation development? By Steven S. Garwood PowerGrid Strategies, LLC March 24, 2010 Is FERC s Generator Interconnection Policy really conducive to efficient generation development? Critical environment for efficient generation

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Stanly County, NC Total Output Requested By Customer: 30 MW Commercial Operation Date Requested By Customer: 12/1/2019 Feasibility

More information

Union Power Cooperative

Union Power Cooperative Union Power Cooperative INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities of the local

More information

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Submitted by Company Date Submitted Kevin T. Fox Keyes & Fox, LLP 436 14 th

More information

NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes. November 2011

NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes. November 2011 NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes November 2011 Proposed Tariff Changes More detailed Intra-hour scheduling language to be added Revisions to Attachment N (Large Generator

More information

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT)

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Program Overview August 8, 2013 1 ReMAT Schedule Date (2013) July 23 July 24 August 8 August 16 TBD TBD October 1 November 1 Event E-PWF &

More information

Transmission Expansion and Interconnection Manual. June 2017

Transmission Expansion and Interconnection Manual. June 2017 MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection

More information

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 1. ELIGIBILITY FOR SERVICE RETAIL WHEELING SERVICE All Special Contract Customers, and all Schedule 48 Customers as of March 9, 2001,

More information

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) This application, terms, and conditions, and Interconnection Agreement is for Xcel Energy customers requesting the installation of a small generation

More information

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018 PJM Manual 14E: Additional Information for Upgrade and Transmission Revision: 05 Effective Date: April 1, 2018 Prepared by System Planning Division Department PJM 2018 Table of Contents Table of Contents

More information

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007 ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007 Rev. No. Revision Description Date Reviewed By Approved By 0 Initial Issue 3/1/2007 - TL 1 Cover Page Updated 10/24/2008 - BKW 2 Revised Format, Updated

More information

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:

More information

Interconnection of New Generation Facilities

Interconnection of New Generation Facilities Interconnection of New Generation Facilities Jennifer Heintz Chief Counsel Public Service Commission of Missouri February 7, 2013 Abu Dhabi, U.A.E. Generation and Transmission in the United States In the

More information

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016 Generation Process SWANA Spring Conference Atlantic City, NJ April 18, 2016 www.pjm.com PJM process is FERC Pro Forma Customer enters queue to sell output into PJM wholesale market (regardless of size)

More information

September 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report

September 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report September 30, 2011 The Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Louisville Gas & Electric Company, et al., Docket No.

More information

New York Independent System Operator System Reliability Impact Study Criteria and Procedures

New York Independent System Operator System Reliability Impact Study Criteria and Procedures New York Independent System Operator System Reliability Impact Study Criteria and Procedures Note: Project Developers are advised that these documents do not address cost allocation Approved by the Operating

More information

Dated: April 16, 2002

Dated: April 16, 2002 Central Hudson Gas & Electric Corporation (CHG&E) Application Process for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System Dated: April 16,

More information

Transmission Planning Process Phase 3 Competitive Solicitation

Transmission Planning Process Phase 3 Competitive Solicitation 2018 2019 Transmission Planning Process Phase 3 Competitive Solicitation Scott Vaughan Lead Grid Assets Engineer Chris Hillman Lead Grid Assets Engineer April 11, 2019 Transmission Planning Process Phase

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction

More information

Relevant changes will be made to corresponding sections of OA and RAA.

Relevant changes will be made to corresponding sections of OA and RAA. PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59933-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 59625-E Rule 21 Sheet 7 A. TABLE OF CONTENTS Hh. Smart Inverter Generating

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The

More information

Request for Proposal

Request for Proposal Request for Proposal RFP # SPP-RFP-000001 RFP ISSUED DATE: May 5, 2015 RFP ORIGINATION STUDY: 2015 Integrated Transmission Planning 10-Year Study ( 2015 ITP10 ) Table of Contents Table of Contents... 2

More information

Procedure: Station Power Portfolio Application

Procedure: Station Power Portfolio Application Overview Introduction FERC has established a policy that allows a single corporate entity that owns one or more Generating Units to self-supply Station Power over a monthly netting period using Energy

More information

Defining Outage States to Include a Mothball Outage

Defining Outage States to Include a Mothball Outage Defining Outage States to Include a Mothball Outage Emilie Nelson Director, Operations Josh Boles Manager ICAP Market Market Issues Working Group November 7, 2013 2013 New York Independent System Operator,

More information

Smart Grid Small Generator Interconnection Procedure (SGIP) Updates. December 06, 2016

Smart Grid Small Generator Interconnection Procedure (SGIP) Updates. December 06, 2016 Smart Grid Small Generator Interconnection Procedure (SGIP) Updates December 06, 2016 1 Agenda Background on Interconnection Procedure Modification on SGIP process Interconnection Online Application Portal

More information

COMBINED HEAT AND POWER CALL FOR CHP PROJECTS PROJECT SUBMISSION FORM

COMBINED HEAT AND POWER CALL FOR CHP PROJECTS PROJECT SUBMISSION FORM COMBINED HEAT AND POWER CALL FOR CHP PROJECTS PROJECT SUBMISSION FORM THE PURPOSE OF THIS FORM IS TO OBTAIN BASIC INFORMATION TO DETERMINE ELIGIBILITY OF PROJECTS TO RECEIVE INCENTIVES UNDER THE PECO CHP

More information

Requirements For Generation and Transmission Interconnections

Requirements For Generation and Transmission Interconnections Requirements For Generation and Transmission Interconnections Table of Contents 1.0 INTRODUCTION... 1 2.0 INTERCONNECTION POLICY... 2 3.0 STANDARD INTERCONNECTION PROCESS... 3 3.1 ASSUMPTIONS... 3 3.2

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And DECADE ENERGY, LLC

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And DECADE ENERGY, LLC Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 952 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

Queue Management Process

Queue Management Process SPP and MISO Queue Management Process By: Noumvi G. Ghomsi Utility Engineering Specialist II Missouri Public Service Commission 200 Madison Street Jefferson City, MO 65102 (573) 526-9681 Noumvi.Ghomsi@psc.mo.gov

More information

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X Fifth Revised Page No. 59 908 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X A. AVAILABILITY Available to members of the Cooperative for purchases of electricity by the Cooperative from qualified

More information

Revised Transmission Planning Process. Complete Final Proposal

Revised Transmission Planning Process. Complete Final Proposal Revised Transmission Planning Process Complete Final Proposal May 7, 2010 Complete Final Proposal 1. Introduction and Summary In this document the ISO provides a complete description of its revised transmission

More information

NBP (ATG) IR 01 March 5, Reference: NBP 18.01

NBP (ATG) IR 01 March 5, Reference: NBP 18.01 NBP (ATG) IR 01 March 5, 2015 Reference: NBP 18.01 a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 970 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

83D Q & A Set #8. Answer: Please see response to question 117.

83D Q & A Set #8. Answer: Please see response to question 117. 83D Q & A Set #8 (15) Section 2.2.1.8 Please confirm that bidding projects are only required to demonstrate the ability to meet the requirements for Forward Capacity Auction Qualification in their proposal.

More information

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business

More information

SPP at a Glance. Located in Little Rock. Approximately 600 employees

SPP at a Glance. Located in Little Rock. Approximately 600 employees SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment

More information

ISA FORM TEMPLATE (From Attachment O of the PJM Tariff)

ISA FORM TEMPLATE (From Attachment O of the PJM Tariff) ISA FORM TEMPLATE (From Attachment O of the PJM Tariff) Original Service Agreement No. [ ] Effective Date: [ ] (PJM Queue # ) INTERCONNECTION SERVICE AGREEMENT Among PJM INTERCONNECTION, L.L.C. And And

More information

KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF)

KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF) KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF) TABLE OF CONTENTS I. COMMON SERVICE PROVISIONS 1 Definitions 1.1 Ancillary Services

More information

PJM Strawman Proposal

PJM Strawman Proposal PJM Strawman Proposal Special MIC DER November 17, 2017 DER Proposal: General Overview 1. Not Demand Response, not Generation: proposal is for 3rd ruleset for DER. DER can choose to participate as either

More information

RATE DS-4 LARGE GENERAL DELIVERY SERVICE

RATE DS-4 LARGE GENERAL DELIVERY SERVICE d/b/a Ameren Illinois 5 th Revised Sheet No. 14 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 14) AVAILABILITY Service under this Rate is available for any eligible non-residential

More information

UNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY

UNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/REG/2004/22 30 June 2004 REGULATION NO.

More information

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015 Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating

More information

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION Purpose This fact sheet outlines the steps required for you to undertake an interconnection

More information

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3.

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. PSEI EIM Participating Resource Application and Processing 3.1 Application

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 884 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

Mothball Outages in Capacity Markets

Mothball Outages in Capacity Markets Mothball Outages in Capacity Markets (preliminary review and summary for working group discussion purposes consult relevant ISO directly for latest and detailed legal requirements) September 13, 2017 NYISO

More information

Renewable Generation - REFIT and Grid Connection

Renewable Generation - REFIT and Grid Connection Renewable Generation - REFIT and Grid Connection Ivan Codd Renewable Planning Manager, Asset Management, ESB Networks IrBEA National Bioenergy Conference 4 th February 2015 AGENDA Introduction ESB Networks

More information

FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION

FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION FERC Electric Tariff 8th Rev. Volume No. 7 Original Sheet No. 1 FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION OPEN ACCESS

More information

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy February / 2015 Introduction

More information

The State of Wind Energy in New England

The State of Wind Energy in New England JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New

More information

Water & Energy Consulting Lon W. House, Ph.D.

Water & Energy Consulting Lon W. House, Ph.D. Water & Energy Consulting Lon W. House, Ph.D. 530.409.9702 (cell) lonwhouse@waterandenergyconsulting.com www.waterandenergyconsulting.com 2795 East Bidwell Street 10645 N. Oracle Rd. Suite 100-176 Suite

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION SECTION II ATTACHMENT H UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Entergy Services, Inc., ) ) on behalf of the Entergy Operating ) Docket No. RT01-75 Companies: Entergy

More information

BC Hydro Open Access Transmission Tariff Effective: April 18, 2013 OATT Terms and Conditions First Revision of Page i

BC Hydro Open Access Transmission Tariff Effective: April 18, 2013 OATT Terms and Conditions First Revision of Page i First Revision of Page i BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (OATT) ACCEPTED: ORDERNO.. G_-_59_-_13 First Revision of Page ii Table of Contents Part I. COMMON SERVICE PROVISIONS... 1 1. Definitions...

More information

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE Operating Companies of the Sixth Revised Sheet No. 1 Supersedes Fifth Revised Sheet No. 1 OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM AEP Texas Central Company AEP Texas

More information

Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects

Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects Date, Venue, etc..( Arial, Font size 18 ) 3 rd April 2012 1 Renewable Energy Portfolio of Tata Power Mithapur 25 MW Samana 50 MW Mulshi

More information

GRENLEC s Renewable Standard Offer

GRENLEC s Renewable Standard Offer GRENLEC s Renewable Standard Offer Version: 1.1 Last Updated: September 10 th, 2011 This document provides as a general overview of the Customer-owned Renewable Generation Standard Offer, for the purchase

More information

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges. SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And RADIANT BMT, LLC

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And RADIANT BMT, LLC Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 1002 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM Appalachian Power Company as of 4/9/2018 Electric TCS and MBR Open Access Transmission Tariff Effective Date: 06/20/2017 Status: Effective FERC Docket: ER17-01500-000 696 FERC Order: Delegated Letter Order

More information

SCHEDULE 12 Transmission Enhancement Charges

SCHEDULE 12 Transmission Enhancement Charges SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. One or more of the Transmission Owners may be designated to construct and own and/or finance Required

More information

Interconnection Application

Interconnection Application Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013 MISO MODULE B TRANSMISSION SERVICE MISO I INTRODUCTION The Transmission Provider shall provide Point-To-Point and Network Integration Transmission Service pursuant to the applicable terms and conditions

More information

Transmission Interconnection Requirements. Table of Contents

Transmission Interconnection Requirements. Table of Contents Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection Agreement III. Facility Requirements IV. Interconnection Initiation I. Introduction A. Purpose and Scope

More information

PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF

PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY FERC Electric Tariff First Revised Volume 4 Original Sheet No. 1 TABLE OF CONTENTS 1. Preamble and Applicability...4

More information

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016)

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016) (Modifications Issued on August 11, 2016) 1 List of Contents Introduction Purpose of Document Overview of Transmission Services in New England Definitions Applicable Schedules Services Applicable to these

More information

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION PLATEAU ELECTRIC COOPERATIVE INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION Policy B32 1 P a g e TABLE OF CONTENTS PAGE 1. GENERAL PROCEDURES & STANDARDS 3 1.1 Scope 1.2 Application for Interconnection

More information

PJM Business Practices for Hudson Transmission Service

PJM Business Practices for Hudson Transmission Service PJM Business Practices for Hudson Transmission Service Table of Contents Page About These Practices... 1 1. Valid Paths for the HUDSON Reservations on the PJM OASIS... 1 2. Acquiring Hudson Service...

More information

BGE Smart Energy Savers Program Combined Heat and Power Program Manual

BGE Smart Energy Savers Program Combined Heat and Power Program Manual BGE Smart Energy Savers Program Combined Heat and Power 2015-2017 Program Manual Page 1 of 20 Table of Contents Introduction... 3 Purpose... 3 Goal... 3 ICF s Role... 3 Overview of BGE... 3 BGE Service

More information

ATTACHMENT DD. Reliability Pricing Model

ATTACHMENT DD. Reliability Pricing Model OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.

More information

Distributed Generation. Technical Requirements and Interconnection Agreements

Distributed Generation. Technical Requirements and Interconnection Agreements Distributed Generation Technical Requirements and Interconnection Agreements February 2005 Table of Contents Section 1: Interconnection Process for Distributed Generation Systems (17 pages) Section 2:

More information

Financial Transmission Rights

Financial Transmission Rights PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM

More information

Capacity Market. Overview RPM Capacity Market. Market Design

Capacity Market. Overview RPM Capacity Market. Market Design Section 4 Capacity Capacity Market Each organization serving PJM load must meet its capacity obligations through the PJM Capacity Market, where load serving entities (LSEs) must pay the locational capacity

More information