NBP (ATG) IR 01 March 5, Reference: NBP 18.01

Size: px
Start display at page:

Download "NBP (ATG) IR 01 March 5, Reference: NBP 18.01"

Transcription

1 NBP (ATG) IR 01 March 5, 2015 Reference: NBP a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence at NB Power? a. NB Power intends to have a witness panel available that will include Dean Landers, Tony O Hara and Scott Brown. Please see Attachment A 1, A 2 and A 3 for their respective curriculum vitae. b. The evidence (Exhibit NBP 18.01) filed by NB Power was prepared by Dean Landers. As with all evidence filed with the NBEUB, the evidence was reviewed by numerous internal stakeholders, including Tony O Hara and Scott Brown. 1

2 NBP (ATG) IR-02 March 5, 2015 Reference: NBP-18.01; Page 2, Lines New Brunswick Power Corporation s (NB Power) position is that ATG s decision to upgrade its Tinker transformer is premature in light of the following three realities currently affecting the New Brunswick and northern Maine interconnection (the Interface ): the ongoing regulatory proceedings in Maine relating to reliability in northern Maine the existing queued transmission service reservation requests in the NB Power OASIS the uncertain need to upgrade the transformer See also Page 3, Line 15; Page 9, Line 12 a. Which of the above conditions changing, would result in the application of ATG not being premature? It is NB Power s opinion that the three conditions listed above are not mutually exclusive and each outcome or determination ought to be known before an upgrade to the transformer is considered. The key determinant is the outcome of the Maine PUC regulatory process. For example, should that process conclude that another competing option is the appropriate resolution to northern Maine reliability issues, the replacement and upgrade of the Tinker Transformer could result in New Brunswick ratepayers paying for an asset that is no longer useful. 2

3 NBP (ATG) IR 03 March 5, 2015 Reference: Document NBP18.01 Page 6, Line 14 to Page 7, Line 2 On January 30, 2015 the MPUC issued its redacted Bench Analysis report (Attachment F). This is an integral component of Maine s regulatory procedure where the MPUC and its staff provide an analysis of the information presented in a regulatory proceeding and a proposed process to address the particular subject. In this case, the report addresses the least cost resolution to the reliability concern of the northern Maine electricity market. This report supports the adoption of an incremental approach by addressing the least cost reliability option first and then determining how to address the market issues. The MPUC Bench Analysis identifies the Tinker transformer upgrade and the rebuilding of line 6901 from the Tinker transformer substation in New Brunswick to Flo s Inn substation in Maine as potentially the least cost solution when considered in the context of a proposed transmission connection between Houlton and New Brunswick. The report also highlighted ATG s application to the Board for approval of the transformer upgrade, this Matter 256, and the hearing scheduled for March a. Does NB Power agree with the Bench Analysis, Page 34, which states; Each of the above solution options resolves all of the violations under the MPD safe harbor standards; however the Tinker/Line 6901 solution is significantly less costly than the other options. b. If not, why not? c. Please provide any studies or analysis completed by NB Power? d. Is NB Power or any NB Power related party in the MPUC proceeding? e. Has any NB Power entity completed any analysis or studies related to the MPUC proceeding and the Tinker Transformer Upgrade or any reservations made by NB Power entities? Please provide a copy of those studies or analysis. a. It is NB Power s understanding that the Tinker/Line 6901 solution does satisfy the MPD safe harbor standards, but does not satisfy the N 1 1 requirements necessary for Emera Maine to meet NERC reliability requirements. Please refer to the response to NBP (NMISA) IR 6 for additional information. b. See response to a. above for the requested information. c. NB Power has not performed any studies or analysis on the reliability of the Northern Maine system. d. Yes. NB Power and NB Energy Marketing are interested parties in the MPUC proceeding. e. Please refer to Attachments B 1 through B 9 provided in response to NBP (ATG) IR 07 for the requested information. 3

4 NBP (ATG) IR-04 March 5, 2015 Reference: Document NBP page 4, lines Over a period of almost four years stakeholders in the region, including ATG, NB Power, and Emera Maine (formerly Maine Pubic Service) with coordination by the New Brunswick System Operator (NBSO) and NMISA, worked towards identifying a solution to resolve the reliability concern. That work resulted in a draft analysis document prepared by the NBSO and presented to the Market Advisory Committee in New Brunswick. Ultimately, the work to resolve the Interface issue was halted due to a failure to reach a consensus on allocation and recovery of costs in the northern Maine and New Brunswick jurisdictions. a. Please provide a copy of the draft analysis document presented by NBSO to the Market Advisory Committee. Please refer to the response provided in NBP (NBEUB) IR-02 for the requested information. 4

5 NBP (ATG) IR-05 March 5, 2015 Reference: Document NBP page 5, lines NB Power s evidence on these regulatory proceedings underscores the hastiness and prematurity of the ATG application before the Board. As noted below, there is considerable uncertainty regarding the best potential solution, or solutions, to the reliability concern in northern Maine. In fact, the solution(s) stemming from the MPUC process may negate the need for the transformer replacement or upgrade. Therefore, it is untimely for ATG to preempt the conclusion of these proceedings and assess the outcome as it is related to the future operation of its transmission facilities. The alternative may, in fact, result in New Brunswick transmission customers paying for a stranded assets. a. Are the New Brunswick Transmission assets of ATG regulated by MPUC? b. Are the New Brunswick Transmission assets of NB Power regulated by MPUC? a. and b. No. Decisions of the Maine PUC regarding reliability solutions in northern Maine can affect the prudence of investments in transmission assets located in New Brunswick which are used to serve load in northern Maine. 5

6 NBP (ATG) IR-06 March 5, 2015 References: NB Electricity Act Section 147 Transitional Transmission Tariff 147(2) The Corporation shall, with respect to transmission service and ancillary services, administer and comply with the transitional transmission tariff until that tariff is replaced by a new transmission tariff approved or fixed under subsection 113(12). a. Please confirm that under Section 147(2) of the Electricity Act it has been the obligation of NB Power since October 1, 2013 to administer transmission service requests according to the terms and conditions of the NB Transitional Transmission Tariff. a. Confirmed. 6

7 NBP (ATG) IR 07 March 5, 2015 References: Document NBP page 8, lines 3 7 The NB Power OASIS currently has three queued transmission service requests, each with a delivery path into northern Maine, being studied by NBB Power. The details of the requests are as follows: Document NBP 8.06 Response to NBP (WKM) IR 14(a) a. Please confirm if these three queued transmission n service requests are still in study mode. b. Who are the individuals at NB Power who are responsible to complete these studies? c. Please provide any documentation relevant to each study, including; 1. Any description of the scope? 2. Any agreements related to the studies? 3. Any costing of the studies? 4. Internal or external corresponde ence related to the progress of the studies? 5. When does NB Power expect to complete the studies? d. With respect these communications between NB Power and the customers detailed in NBP (WKM) IR 14(a), please provide a copy of thatt correspondence. e. Has progress been made since December 12, that would change the response to NBP (WKM) IR 14 responsee to part e. is yes, pleasee provide thee specific changes for each of the for any of the three queued transmission service requests? f. If the seven responses to NBP (WKM) 1R 14( (a) for any affected service request. g. Please provide copies of any completed System Impact Studies and Facilities Studies for the three requests noted above. h. For any incomplete studiess please provide an indication of the status of the study and a projected date for completion. a. Confirmed. 7

8 NBP (ATG) IR 07 (cont d) March 5, 2015 b. Transmission Planning Engineers at NB Power Head Office perform System Impact Studies ( SIS ) in accordance with the New Brunswick Power Open Access Transmission Tariff for new Transmission Service Requests. These studies may include load flow, short circuit, stability, loss evaluation, economic and other analyses as appropriate. c. Information relevant to each study is as follows: For the 95 MW request 1. The scope is included in the Introduction section of Exhibit ATG 2.09 (Attachment C ATG (NBEUB) IR 11 Transmission Service Request). 2. An SIS agreement is not signed. Please refer to the response to NBP (ATG) IR 10 d. for further information. 3. NB Power s estimate of the cost to complete the SIS is $50, Please refer to the following items: 2013 NB to MPS Interface Upgrade Study (Attachment B 1) NB Power Meeting Minutes (Feb. 24, 2014) (Attachment B 2) Internal NBP Correspondence (Attachment B 3) Other Correspondence between ATG and NBP (Attachment B 4) Letter from ATG dated September 14, 2014 (Attachment B 5) Exhibit ATG 2.20 (Attachment N ATG (NBP) IR 14(9) Correspondence between ATG and NBP) 5. NB Power estimates that the studies will be completed in the next 90 days. For the 53 MW request 1. The scope of the study is similar to the 95 MW request. 2. An SIS agreement is not signed. 3. The cost is unknown at this time. 4. Please refer to Attachment B 6 (ATG IR 07) between NBP and Emera Maine for the requested information. 5. NB Power estimates that the studies will be completed in the next 90 days. 8

9 NBP (ATG) IR 07 (cont d) March 5, 2015 For the 22 MW request 1. Houlton Water Company wishes to be served directly from the NB Power system. The Feasibility Review can be found in Attachment B The Feasibility Review determined that a SIS was not required for this connection. A Facilities Study Agreement was signed and the Facilities Study completed. (Please refer to Attachment B 8). 3. The estimated cost of the Facilities Study is $25,000. d. There is no additional documented correspondence beyond that provided in the response to c. above. e. Yes. f. The Houlton Water Company Facilities Study has been completed. g. Please refer to the following for the requested information. 1. Exhibit ATG 2.09 (Attachment C ATG (EUB) IR 11 Transmission Service Request). 2. Attachment B 9 Additional MPS upgrade combinations (October 2013) h. Please refer to the response to c. above for the requested information. 9

10 NBP (ATG) IR 08 March 5, 2015 References: Document NBP Page 8 Lines 9 12 Whereas the outcome of the engineering studies required for each of these requests is not known and the results may either require the replacement, upgrade or, in fact, may negate the requirement of the transformer outright, it is premature for ATG to request approval of the Board at this time. Question: a. In the above referenced paragraph, who is responsible for the engineering studies? New Brunswick Power Corporation is responsible for these engineering studies. Other studies conducted by ISO New England or Maine PUC could also result in similar outcomes. 10

11 NBP (ATG) IR-09 March 5, 2015 References: Document NBP8.06 Response to NBP(WKM) IR-14(a) The 95 MW application 1) The 95 MW application was received on July 4, ) The customer was informed that a System Impact Study was necessary as required by the OATT. 3) No, a formal System Impact Study agreement was not issued for this application. The initial application for this request was issued in December 2012 by NB Power Generation Marketing. NBSO asked NB Power Transmission to conduct the System Impact Study without NBSO having to sign a new legal agreement. 4) No, a System Impact Study has not been completed 5) No, as it requires a completed System Impact Study. 6) No, as it requires a completed System Impact Study. 7) No, as it requires a completed System Impact Study. a. What happened to the original December 2012 application that required a new application queued on July 4, 2014? b. Wouldn t the rights and obligations with respect to an application under the OATT of NB Power Generation Marketing (a group within NB Power Genco) have transferred under the Electricity Act to New Brunswick Energy Marketing Corporation on October 1, 2013? c. If the response to part b. is yes why would a new application be required? d. If the response to part b. is no please explain why the request application obligations and rights would not be transferred. e. Was the original application withdrawn or altered in sufficient manner to make it be considered as a new application? If altered what are the changed conditions? f. Considering treatment of the July 4, 2014 application, what is the relevance of actions done or not done by NBSO with respect to the December 2012 application? a. The applicant chose to withdraw its December 12, 2012 application and submitted a new application with a new start and end date. b. With respect to this application, the answer is yes. c. and e. Please refer to the response to NBP (ATG) IR-09 a. above for the requested information. d. No response required. f. With respect to the July 4, 2014 application, actions with respect to the December 12, 2012 application does not have relevance. 11

12 NBP (ATG) IR 10 March 5, 2015 References: NB Transitional Transmission Tariff (October 1, 2013) section 19.1 pages Notice of Need for System Impact Study After receiving a request for service, the Transmission Provider shall determine on a nondiscriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for completing a System Impact Study is provided in Attachment D. If the Transmission Provider determines that a System Impact Study is necessary to accommodate the requested service, it shall so inform the Eligible Customer, as soon as practicable. In such cases, the Transmission Provider shall within thirty (30) days of receipt of a Completed Application, tender a System Impact Study Agreement pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider for performing the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer shall execute the System Impact Study Agreement and return it to the Transmission Provider within fifteen (15) days. If the Eligible Customer elects not to execute the System Impact Study Agreement, its application shall be deemed withdrawn and its deposit, pursuant to Section 17.3, shall be returned with interest System Impact Study Procedures Upon receipt of an executed System Impact Study Agreement, the Transmission Provider will use due diligence to complete the required System Impact Study within a sixty (60) day period. The System Impact Study shall identify any system constraints and redispatch options, additional Direct Assignment Facilities or Network Upgrades required to provide the requested service. In the event that the Transmission Provider is unable to complete the required System Impact Study within such time period, it shall so notify the Eligible Customer and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. a. Is it the obligation of NB Power as the Transmission Provider since October 1, 2013 to comply with Sections 19.1 and 19.3 of the Transitional Tariff? b. Did NB Power the Transmission Provider tender a System Impact Study Agreement to NB Energy Marketing within 30 days of the receipt of the completed application on July 4, 2014? c. Does NB Power agree that under the Tariff a System Impact Study Agreement would normally be completed within 45 days following receipt of a Completed Application (ie 30 days to tender the System Impact Study Agreement plus 15 days for it to be executed)? d. As of Dec 12, 2014, 160 days after the receipt of the 95 MW request, the response to NBP (WKM) IR 14(a) indicates that a system impact study agreement was not executed. Please explain why? 12

13 NBP (ATG) IR 10 (cont d) March 5, 2015 e. Why did the Transmission Provider not deem the 95 MW application withdrawn as a result of not receiving an executed System Impact Study Agreement from NB Energy Marketing? f. Has an agreement been executed since Dec 12, 2014? If so please provide a copy of the agreement and indicate the date on which it was executed. g. Does NB Power agree that a System Impact Study according to the Tariff should normally be completed within 60 days following receipt of an executed System Impact Study Agreement which would be within 105 days following receipt of a Completed Application? h. It is apparent that the 105 day target for completion of the System Impact Study for the 95 MW Application has not been achieved as 105 days from July 4 would be October 17 which has passed. Has the Transmission Provider provided NB Energy Marketing with an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies? i. If the response to part h. is yes, please provide a copy of the notification indicating the completion date and explanation. j. If the response to part h. is no, please explain why not. k. As of the date of submission of these information requests (Feb 19, 2015) 230 days have passed since the receipt of the 95 MW Completed Application which is more than twice the normal target for System Impact Study Completion. 1. What amount of due diligence has NB Power undertaken to complete the study in a timely period? 2. Is the study being done by NB Power in house resources and if so, how many person hours of work to this date has been applied on the study? 3. If the response to 2 is yes, why has NB Power not considered contracting out the study? 4. If NB Power had contracted out the study could it have been completed within fewer than the 230 days that have elapsed since receipt of the request on July 4, 2014? l. Does NB Power monitor its compliance with the Tariff? m. If the response to part l. is yes, please explain how it is done. Is there a "Tariff Compliance Officer" or is compliance the responsibility of some other party? If so, who and what are their specific responsibilities? n. If the response to part l. is no, please explain why not? a. Yes. b. No. c. Yes. 13

14 NBP (ATG) IR 10 (cont d) March 5, 2015 d. Please refer to the Introduction section of Exhibit ATG 2.09 ATG (EUB) IR 11 Attachment C for details of the original Long Term Firm Point to Point Transmission Service request by NB Power Generation Marketing. On July 4th, 2014 NB Energy Marketing withdrew its prior application (December 2012) and submitted a new one with a different start date, the old start date being Nov. 1, There were no other requests for Long Term Firm Point to Point Transmission Service on the EM MPD/NB interface in the queue at this time. A System Impact Study agreement for this new request was not issued due to uncertainty regarding the Tinker Transformer as described below. On February 28, 2014 in a letter to NB Power Transmission (Exhibit ATG 2.20 ATG (NBP) IR 14 (9) Attachment N) Ed Howard of Algonquin Tinker Genco, citing various issues with the Tinker Transformer changed its allowable transfer levels. This letter, along with subsequent letters in March, September and November 2014, did not provide any certainty with respect to the actions that Algonquin Tinker Genco would be taking to remedy issues with the transformer, nor was there any certainty with respect to the timeline of those actions. The allowable transfer levels of the Tinker Transformer must be known in order to properly study and design upgrades to the EM MPD/NB interface. In Exhibit ATG 2.09 ATG (EUB) IR 11 Attachment C, seven of the nine upgrade options studied will be incorrect if the allowable transfer levels of the Tinker Transformer are not modeled properly. e. Please refer to the response in d. above for the requested information. f. No. g. Yes, with note that the Tariff does provide for flexibility that some System Impact Studies, due to their scope, will exceed 60 days. h. Yes. i. There was no written notification. The notification was verbal and provided at a meeting to discuss the request held on Feb. 27, 2015 between NB Power, NB Energy Marketing and Emera Maine. It is expected that the SIS will be completed within the next 90 days. j. No response required. 14

15 NBP (ATG) IR 10 (cont d) March 5, 2015 k. 1. NB Power was unable to obtain a long term rating of the Tinker Transformer from ATG. In order to assist in the resolution of this issue, and as noted in Exhibit ATG 2.20 ATG (NBP) IR 14 (9) Attachment N in the November 10, 2014 letter, several issues regarding the Tinker Transformer have been resolved. NB Power was able to assist Algonquin Tinker Genco with replacement of the transformer bushing and lightning arrestors. 2. No formal SIS study work has been undertaken at this time. The study will be performed jointly by NB Power and Emera Maine. The NB Power work will be carried out using NB Power Transmission Planning personnel. 3. Please see response to d. above for the requested information. 4. No. Please see response to d. above for the requested information. l. NB Power monitors compliance with all regulatory requirements to which it is subject. NB Power s compliance with the Tariff is ultimately the subject of the Board s jurisdiction under section 129 of the Electricity Act. m. No response required. n. Please see response to l. above for the requested information. 15

16 NBP (ATG) IR-11 March 5, 2015 Reference: NBP Document 8.01 page 8 lines As demonstrated in Table 1 above, whether motivated by market demand or a reliability issue in northern Maine, the three requests provide positive evidence the mechanics of an Open Access Transmission Tariff is working... a. How does receipt of the three requests demonstrate that the mechanics of the OATT are working? b. Would the fact that the required system impact study for the 95 MW request was not completed within the targeted 105 day requirement under the OATT indicate that the mechanics of the OATT are working? c. Would the fact that the required system impact study for the 95 MW request has yet to be completed after 230 days indicate that the mechanics of the OATT are working? a. As identified in Exhibit NMISA 1.01, page 9, lines 5-12, there is a need for additional capacity to serve the NMISA market in order for the NMISA to meet its reliability standards without incurring expensive reliability must run contracts with its biomass plants. The three requests demonstrate that there are at least three different parties with proposals to provide additional capacity from New Brunswick via firm transmission service. b. The fact that the system impact study for the 95 MW request requires additional time outside of the target is indicative of: An extensive study scope for multiple levels of transfer involving an interconnection that is fully subscribed. Please refer to Exhibit ATG 2.09 Attachment C ATG (EUB) IR-11 Transmission Service Request. Uncertainty regarding the Tinker Transformer rating. Please refer to Exhibit ATG 2.20, Attachment N ATG (NBP) IR-14(9) Correspondence between ATG and NBP. Please refer to Attachment B-4 (ATG IR-07) Other correspondence between ATG and NBP. c. Please refer to the response to b. above for the requested information. 16

17 NBP (ATG) IR-12 March 5, 2015 References: Document NBP8.06 Response to NBP(WKM) IR-14(a) The 53 MW application 1) The 53 MW application was received on July 24, ) The customer was informed that a System Impact Study may be necessary but was dependent on the 95 MW application ahead of it in the queue. 3) No, the scope, timing and cost determination of this study has not been determined. a. Confirm that the 95 MW application ahead of the Emera Maine application for 53 MW in the queue is the NB Energy Marketing application of July 4, 2014? b. Confirm that, if NB Power the Transmission Provider had, according to Section 19.1 of the Transitional Tariff, deemed the NB Energy Marketing application withdrawn because of lack of an executed System Impact Study Agreement, then the 53 MW application of Emera Maine would not have been considered dependent on the 95 MW application ahead of it in the queue? c. If the 53 MW application was at the top of the queue would NB Power the Transmission Provider: 1. Have been able to determine the scope, timing and cost determination of a System Impact Study? 2. Require execution of a System Impact Study Agreement? d. Could the delay in processing Emera Maine s 53 MW Application because of the Transmission Provider s failure to fulfill its obligations under the Tariff be considered as discriminatory treatment of Emera Maine? e. Could the Transmission Provider s lack of applying Section 19.1 of the Tariff for the 95 MW request of NB Energy Marketing be considered as preferential treatment of its affiliate marketing entity? f. Has the Transmission Provider s treatment of the three service requests for delivery to northern Maine met the Comparability principle? a. Confirmed. b. Section 19.2 of the Transitional Tariff says that the System Impact Study Agreement will clearly indicate the Transmission Provider s estimate of the actual cost, and time for completion of the System Impact Study. Section 19.2 of the Transitional Tariff also states that in performing the System Impact Study, the Transmission Provider shall rely, to the extent reasonably practicable, on existing transmission planning studies. 17

18 NBP (ATG) IR-12 (cont d) March 5, 2015 Without any certainty with respect to the Tinker Transformer rating, the Transmission Provider cannot estimate the actual cost, time for completion, and the extent to which existing transmission planning studies can be used for the 95 MW request. Therefore, a System Impact Study Agreement was not issued to NB Energy Marketing for the 95 MW request submitted on July 4, Provided that the Transmission Provider can offer a System Impact Study Agreement to an eligible customer, and that agreement is not executed according to Section 19.1 of the Transitional Tariff, then an application would be considered withdrawn. c. 1. No. Please see response to NBP (ATG) IR-10 d. for the requested information. 2. Yes, unless there are existing transmission planning studies that can be used. d. No. NB Power does not agree with the statement that the Transmission Provider has failed to comply with obligations in the Tariff. Please refer to the response in b. above. e. No. NB Power does not agree with the statement that the Transmission Provider may be showing preferential treatment to its marketing entity. Please refer to the response in b. above. f. Yes. 18

19 NBP (ATG) IR 13 March 5, 2015 References: Document NBP8.06 Response to NBP(WKM) IR 14(a) The 22 MW application 1) The 22 MW application was received on September 30, ) No, the Feasibility Review determined that a System Impact Study is not required. 3) No, the Feasibility Review determined that a System Impact Study is not required. 4) No, the Feasibility Review determined that a System Impact Study is not required. 5) Yes, a Facilities Study Agreement was sent to the customer on Dec. 5, ) Yes, a Facilities Study Agreement was executed on Dec. 9, ) No, the Facilities Study is in progress. Transitional Transmission Tariff Section 32 ADDITIONAL STUDY PROCEDURES FOR NETWORK INTEGRATION TRANSMISSION SERVICE REQUESTS a. The time from receipt of the Application to tendering of the facilities Study Agreement was 64 days. Is this within the timelines set out in Section 32 of the Tariff for Network Service requests? b. Would completion of facilities and provision of Network Service for Houlton Water s 22 MW of load affect the system conditions for the 95 MW system impact study? c. If the response to part b. is yes, why wouldn t the higher queue position 95 MW application have its system impact study be completed prior to proceeding with the 22 MW request? a. Yes. b. No. The request from Houlton Water Company involves the complete separation of the Houlton Water system from the Northern Maine transmission system. If completed, it would reduce the amount of load on the Northern Maine system, but would not impact the request for an additional 95MW of transfer capability into the Northern Maine system. c. No response required. 19

20 NBP (ATG) IR-14 March 5, 2015 References: Document NBP page 7 lines 8-12 As demonstrated above, the uncertainty in the ultimate solution in northern Maine and whether or not the Tinker transformer is material in that solution will not be determined until the completion on Docket Any decision to upgrade the transformer until a decision has been made may result in stranded costs to be borne by New Brunswick customers. a. Do decisions or actions regarding reliability in an external jurisdiction alter the obligations of NB Power under the NB Transitional Tariff to handle a Completed Application for Long Term Firm Point-to-Point transmission service from NB? b. Please indicate and explain the terms and conditions in the Transitional Tariff that provide the Transmission Provider with the option not to fulfill its obligations regarding a Completed Application for transmission service dependent on the outcome of a hearing in an external jurisdiction. c. If a Transmission Customer executes an agreement for new transmission service that meets the pricing conditions of Attachment K, would this not eliminate the potential for stranded costs to be borne by New Brunswick customers? d. If the response to part c is no, please explain how the suggested stranded costs would occur. a. Yes. The transfer capability limit on an interconnection, for both real-time operations as well as planning, must be agreed to by the Transmission Provider in each jurisdiction. In cases were the transfer capability limits determined by each Transmission Provider are not the same, then the lower limit is chosen in order to meet the reliability requirements for both jurisdictions. Requests for additional transfer capability on an interconnection must therefore involve the Transmission Provider in each jurisdiction to ensure that the design and construction of any upgrades will achieve the requested service. b. Please refer to Section 20 of the New Brunswick Transitional Tariff, PROCEDURES IF THE TRANSMISSION PROVIDER IS UNABLE TO HAVE A TRANSMITTER COMPLETE NEW TRANSMISSION FACILITIES FOR FIRM POINT-TO-POINT TRANSMISSION SERVICE. c. Yes, except that this reference to stranded costs is not about new transmission service under Attachment K of the NB Power OATT. Rather, it is the risk that the Tinker Transformer may not be material to the ultimate solution for Northern Maine in Docket d. Please refer to the response in c. above for the requested information. 20

21 NBP (ATG) IR-15 March 5, 2015 References: Document NBP Page 10; Line In the event that the Tinker transformer is unable to perform for any reason, the short-term solution is that electricity transfers on the Interface are curtailed until transmission operators, under the direction of NB Power, reconfigure the transmission system transmission to a post-event state that would return electricity transfers to pre-event levels. This is a studied and reliable state for transmission system operations. a. Please provide a copy of these studies. b. How would the transmission system be re-configured? c. What would the effect be on the reliability of the system (including the New Brunswick and Northern Maine systems)? a. Please refer to NBP (NMISA) IR-2 (e). for the requested information. b. Please refer to NBP (NMISA) IR-4 (a) and (b). for the requested information. c. Please refer to NBP (NMISA) IR-2 (e). for the requested information. 21

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff.

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Upgrade Feasibility Study: A study conducted by the Transmission Provider

More information

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. SEVEN-YEAR OUTLOOK: AN ASSESSMENT OF THE ADEQUACY OF GENERATION AND TRANSMISSION FACILITIES ON THE NORTHERN MAINE TRANSMISSION SYSTEM April 2019 ME1

More information

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. SEVEN-YEAR OUTLOOK: AN ASSESSMENT OF THE ADEQUACY OF GENERATION AND TRANSMISSION FACILITIES ON THE NORTHERN MAINE TRANSMISSION SYSTEM April 2017 INTRODUCTION

More information

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations New Brunswick Electricity Business Rules Chapter 3 Reliable Operations TABLE OF CONTENTS CHAPTER 3 RELIABLE OPERATIONS... 2 3.0 System Operator Roles and Responsibilities... 2 3.1 Reliability Assessments...

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013 MISO MODULE B TRANSMISSION SERVICE MISO I INTRODUCTION The Transmission Provider shall provide Point-To-Point and Network Integration Transmission Service pursuant to the applicable terms and conditions

More information

Relevant changes will be made to corresponding sections of OA and RAA.

Relevant changes will be made to corresponding sections of OA and RAA. PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010

More information

Southern California Edison Company SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF

Southern California Edison Company SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF Original Sheet No. TABLE OF CONTENTS. Applicability.... Definitions.... Nature of Distribution Service.... Term.... Distribution

More information

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14 FERC Electric Tariff Page 1 of 2 ATTACHMENT N Small Generator Interconnection Procedures and Agreement (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14

More information

APPENDIX B PLANNING FRAMEWORK. This Appendix B describes the process to be used by the Midwest ISO in planning

APPENDIX B PLANNING FRAMEWORK. This Appendix B describes the process to be used by the Midwest ISO in planning FERC Electric Tariff, First Revised Rate Schedule No. 1 Original Sheet No. 103 I. Overview. PLANNING FRAMEWORK This Appendix B describes the process to be used by the in planning the Transmission System.

More information

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 1. ELIGIBILITY FOR SERVICE RETAIL WHEELING SERVICE All Special Contract Customers, and all Schedule 48 Customers as of March 9, 2001,

More information

Transmission Expansion and Interconnection Manual. June 2017

Transmission Expansion and Interconnection Manual. June 2017 MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection

More information

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015 Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

PLATTE RIVER POWER AUTHORITY OPEN ACCESS TRANSMISSION TARIFF. May 1, 2009

PLATTE RIVER POWER AUTHORITY OPEN ACCESS TRANSMISSION TARIFF. May 1, 2009 PLATTE RIVER POWER AUTHORITY OPEN ACCESS TRANSMISSION TARIFF May 1, 2009 Original Sheet No.1 TABLE OF CONTENTS I. COMMON SERVICE PROVISIONS... 8 1 Definitions... 8 1.1 Ancillary Services... 8 1.2 Annual

More information

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3.

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. PSEI EIM Participating Resource Application and Processing 3.1 Application

More information

Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b

Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b [Appendix 9C1B, Interchange Transaction Reallocation During TLR Levels 3a and 5a ] [Appendix 9C1C, Interchange Transaction

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Small Generator Interconnection Procedures (SGIP) Customer Guide

Small Generator Interconnection Procedures (SGIP) Customer Guide Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission

More information

KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF)

KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF) KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF) TABLE OF CONTENTS I. COMMON SERVICE PROVISIONS 1 Definitions 1.1 Ancillary Services

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Ancillary Service Requirements Protocol (ASRP)... 2 PART A CERTIFICATION FOR REGULATION... 2 A 1... 2 A 2... 3 A 3... 3 A 4... 3 A 5... 3 A 6... 4 A 7... 4 A 8... 4 A 9... 4 A 10... 4

More information

Introduction to RRG Drafting Team Proposal

Introduction to RRG Drafting Team Proposal November 17, 2003 Introduction to RRG Drafting Team Proposal SUMMARY This introduction will review the overall task the RRG drafting team took on, set out the overall guiding principles it used, and describe

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

AMENDMENT REPORT. STC Proposed Amendment CA039 Amendment of outage planning timescales to enable more coordinated outage planning

AMENDMENT REPORT. STC Proposed Amendment CA039 Amendment of outage planning timescales to enable more coordinated outage planning AMENDMENT REPORT STC Proposed Amendment CA039 Amendment of outage planning timescales to enable more coordinated outage planning The purpose of this report is to assist the Authority in their decision

More information

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO This Proposal outlines the terms and conditions in a proposed Appendix to the Southwest Power Pool's ("SPP's") Membership Agreement

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

Louisville Gas & Electric Co./Kentucky Utilities Co. OPEN ACCESS TRANSMISSION TARIFF BUSINESS PRACTICES

Louisville Gas & Electric Co./Kentucky Utilities Co. OPEN ACCESS TRANSMISSION TARIFF BUSINESS PRACTICES Louisville Gas & Electric Co./Kentucky Utilities Co. OPEN ACCESS TRANSMISSION TARIFF BUSINESS PRACTICES MAINTAINED BY: The Independent Transmission Organization PUBLISHED: 7/13/2007 LATEST REVISION: 7/13/2007

More information

DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890

DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890 DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890 OVERVIEW AND PURPOSE This strawman proposes enhancements to NYISO s existing reliability and economic planning processes

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles Addressing Affected System Impacts of Generator Interconnection: Processes and Principles August 5, 2013 Table of Contents 1 Executive Summary... 2 2 Introduction... 2 3 Stakeholder Process and Schedule...

More information

Maine Public Service Transmission System Reliability

Maine Public Service Transmission System Reliability Maine Public Service Transmission System Reliability Presentation at the Northern Maine Planning Advisory Group 5/15/13 Today s Presentation will cover: Part I Assumptions & Methodology Assumptions used

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

effective date 1/8/01

effective date 1/8/01 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical

More information

ISO New England - ISO New England Inc. Transmission, Markets and Services Tariff

ISO New England - ISO New England Inc. Transmission, Markets and Services Tariff ATTACHMENT K REGIONAL SYSTEM PLANNING PROCESS TABLE OF CONTENTS 1. Overview 2. Planning Advisory Committee 2.1 Establishment 2.2 Role of Planning Advisory Committee 2.3 Membership 2.4 Procedures (a) Notice

More information

Eligible Intermittent Resource Dispatch Operating Target EIR DOT

Eligible Intermittent Resource Dispatch Operating Target EIR DOT Eligible Intermittent Resource Dispatch Operating Target EIR DOT CSSA Training August 2018 Stakeholder Learning Objectives Explain the difference between an Operating Instruction and a Dispatch Instruction

More information

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201 TARIFF FOR WHOLESALE TRANSMISSION SERVICE 1900 North Akard Dallas, Texas 75201 Applicability: Entire System Sheet No. 1 Effective Date: May 25, 2018 Revision: 17 Availability Wholesale Transmission Service

More information

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7

More information

ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD

ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD 1. Metering And Communications Equipment: Data retrieval requirements, procedures, and schedules shall

More information

Vector Pipeline L.P. Original Sheet No. 30 FERC Gas Tariff First Revised Volume No. 1 v0.0.0 RATE SCHEDULE FT-1 FIRM TRANSPORTATION SERVICE

Vector Pipeline L.P. Original Sheet No. 30 FERC Gas Tariff First Revised Volume No. 1 v0.0.0 RATE SCHEDULE FT-1 FIRM TRANSPORTATION SERVICE Vector Pipeline L.P. Original Sheet No. 30 1. AVAILABILITY RATE SCHEDULE FT-1 FIRM TRANSPORTATION SERVICE This FT-1 Rate Schedule is available to any party (hereinafter called "Shipper"), for firm transportation

More information

The State of Wind Energy in New England

The State of Wind Energy in New England JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New

More information

Tarifs et conditions des services de transport d'hydro-québec (version anglaise)

Tarifs et conditions des services de transport d'hydro-québec (version anglaise) Demande R-3903-2014 Tarifs et conditions des services de transport d'hydro-québec (version anglaise) Version finale suite à la décision D-2015-031 Original : 2014-08-01 HQT-12, Document 6 Révisé : 2015-03-23

More information

Tarifs et conditions des services de transport d'hydro-québec (version anglaise)

Tarifs et conditions des services de transport d'hydro-québec (version anglaise) Demande R-3903-2014 Tarifs et conditions des services de transport d'hydro-québec (version anglaise) Suite à la décision D-2015-017 Original : 2014-08-01 HQT-12, Document 6 Révisé : 2015-03-13 En liasse

More information

Must-Offer Exception Process Issue

Must-Offer Exception Process Issue Must-Offer Exception Process Issue Patrick Bruno Sr. Engineer, Capacity Market Operations Market Implementation Committee August 8, 2018 Background Issue brought forward by Exelon to investigate: Possible

More information

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016)

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016) (Modifications Issued on August 11, 2016) 1 List of Contents Introduction Purpose of Document Overview of Transmission Services in New England Definitions Applicable Schedules Services Applicable to these

More information

ATTACHMENT DD. Reliability Pricing Model

ATTACHMENT DD. Reliability Pricing Model OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.

More information

Network Integration Transmission Service Agreement (NITSA) and Network Operating Agreement (NOA)

Network Integration Transmission Service Agreement (NITSA) and Network Operating Agreement (NOA) Network Integration Transmission Service Agreement (NITSA) and Network Operating Agreement (NOA) 1. Please complete the NITS Application as follows and execute one (1) original: a. MISO will fill in the

More information

AESO Practices for System Access Service. May 31, 2013

AESO Practices for System Access Service. May 31, 2013 AESO Practices for System Access Service May 31, 2013 Table of Contents 1 Purpose... 3 2 Introduction... 3 3 Practices for System Access Service... 4 3.1 Conditions for System Access Service... 4 3.2 Rationale

More information

DEMANDE RELATIVE À LA MODIFICATION DES TARIFS ET CONDITIONS DES SERVICES DE TRANSPORT D'HYDRO-QUÉBEC. DOSSIER : R , Phase 2 EVIDENCE OF

DEMANDE RELATIVE À LA MODIFICATION DES TARIFS ET CONDITIONS DES SERVICES DE TRANSPORT D'HYDRO-QUÉBEC. DOSSIER : R , Phase 2 EVIDENCE OF DEMANDE RELATIVE À LA MODIFICATION DES TARIFS ET CONDITIONS DES SERVICES DE TRANSPORT D'HYDRO-QUÉBEC DOSSIER : R-3669-2008, Phase 2 EVIDENCE OF WILLIAM K MARSHALL HYDRO QUÉBEC TARIFF RELATIVE TO FERC ORDER

More information

September 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report

September 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report September 30, 2011 The Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Louisville Gas & Electric Company, et al., Docket No.

More information

Craig Glazer Vice President Federal Government Policy PJM Interconnection

Craig Glazer Vice President Federal Government Policy PJM Interconnection On behalf of the RTOs that submitted comments in this proceeding, we wanted to express again our appreciation for your reaching out to us to discuss the Reliability Safety Valve proposal embodied in our

More information

ARTICLE 29: GRIEVANCE PROCEDURE

ARTICLE 29: GRIEVANCE PROCEDURE ARTICLE 29: GRIEVANCE PROCEDURE A. General Conditions 1. A grievance is a written complaint by an individual employee, a group of employees, or the Union that the Employer has violated a specific provision

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

regulations of the Federal Energy Regulatory Commission ( Commission or FERC ), 2 PJM

regulations of the Federal Energy Regulatory Commission ( Commission or FERC ), 2 PJM PJM Interconnection Valley Forge Corporate Center 955 Jefferson Avenue Norristown, PA 19403-2497 Jennifer H. Tribulski Senior Counsel 610.666.4363 fax 610.666.8211 tribuj@pjm.com Filing Via etariff Honorable

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

- 1 - IM Scope of Work Activities September 1, 2008

- 1 - IM Scope of Work Activities September 1, 2008 SCOPE OF WORK ACTIVITIES FOR INDEPENDENT MONITOR SERVICES RELATING TO ENTERGY SERVICES, INC. S JANUARY 2009 WESTERN REGION REQUEST FOR PROPOSALS FOR LONG-TERM SUPPLY-SIDE RESOURCES IN THE WESTERN REGION

More information

Chapter 5 Embedded Generation Information Pack

Chapter 5 Embedded Generation Information Pack Chapter 5 Embedded Generation Information Pack 27.04.18 27.04.18 1 Table of Contents 1. Connection Framework... 3 2. Negotiated Standards Chapter 5... 5 3. Connection Process... 6 4. Key Documents... 7

More information

PJM Queue Position Establishment Background and Support for Problem Statement

PJM Queue Position Establishment Background and Support for Problem Statement PJM Queue Position Establishment Background and Support for Problem Statement Presented by David Egan Manager, Interconnection Projects To the PJM Planning Committee June 11, 2015 Overview Establishing

More information

Reliability Pricing Model (RPM) DRAFT Business Rules

Reliability Pricing Model (RPM) DRAFT Business Rules Definition and Purpose of Reliability Pricing Model (RPM) 1. The purpose of the RPM is to develop a long term pricing signal for capacity resources and LSE obligations that is consistent with the PJM Regional

More information

Procedures for designating a Scheduling Entity & Operating and Scheduling Protocols For Scheduling Entities

Procedures for designating a Scheduling Entity & Operating and Scheduling Protocols For Scheduling Entities Procedures for designating a Scheduling Entity & Operating and Scheduling Protocols For Scheduling Entities Listed below are the procedures for becoming a Scheduling Entity for a Transmission Customer

More information

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018 Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process Planning Advisory Committee September 26, 2018 Discussion Today Discuss Stakeholder response to MISO proposed process

More information

Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW)

Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW) Appendix C RM13-2-000 (Revised) Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW) Where to Send Comments on Public Reporting Burden The public reporting

More information

Regional Transmission Organizations. D. William VanderLaan Illinois Commerce Commission January 30, 2014

Regional Transmission Organizations. D. William VanderLaan Illinois Commerce Commission January 30, 2014 Regional Transmission Organizations D. William VanderLaan Illinois Commerce Commission January 30, 2014 History of Regional Transmission Organizations (RTOs) RTOs grew out of FERC Order Nos. 888/889 where

More information

SASKPOWER OPEN ACCESS TRANSMISSION TARIFF

SASKPOWER OPEN ACCESS TRANSMISSION TARIFF Effective September 1, 2011 SASKPOWER OPEN ACCESS TRANSMISSION TARIFF TABLE OF CONTENTS I. COMMON SERVICE PROVISIONS 1 1 Definitions 1 1.1 Ancillary Services: 1 1.2 Annual Transmission Costs: 1 1.3 Application:

More information

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM Appalachian Power Company as of 4/9/2018 Electric TCS and MBR Open Access Transmission Tariff Effective Date: 06/20/2017 Status: Effective FERC Docket: ER17-01500-000 696 FERC Order: Delegated Letter Order

More information

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

New York Independent System Operator System Reliability Impact Study Criteria and Procedures

New York Independent System Operator System Reliability Impact Study Criteria and Procedures New York Independent System Operator System Reliability Impact Study Criteria and Procedures Note: Project Developers are advised that these documents do not address cost allocation Approved by the Operating

More information

PacifiCorp Contract Review. Discussion Paper

PacifiCorp Contract Review. Discussion Paper PacifiCorp Contract Review Discussion Paper June 24, 2016 M&ID/D. Le Vine Page 1 Table of Contents 1 Executive Summary... 4 2 Introduction... 5 3 Stakeholder Process Next Steps... 7 4 Agreements PacifiCorp

More information

Table of Contents. Trailblazer Pipeline Company LLC 6th Revised Volume No. 1. Rate Schedules. Rate Schedule FTS. Rate Schedule ITS.

Table of Contents. Trailblazer Pipeline Company LLC 6th Revised Volume No. 1. Rate Schedules. Rate Schedule FTS. Rate Schedule ITS. 6th Revised Volume No. 1 Table of Contents Rate Schedules Rate Schedule FTS Rate Schedule ITS Rate Schedule FTB Rate Schedule Wheeling Service Rate Schedule PALS Rate Schedules 6th Revised Volume No. 1

More information

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system

More information

An Introduction to Interconnection Policy in the United States

An Introduction to Interconnection Policy in the United States An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator

More information

2018 Open Access Transmission Tariff (OATT) Rate Case

2018 Open Access Transmission Tariff (OATT) Rate Case 2018 Open Access Transmission Tariff (OATT) Rate Case October 10, 2017 Report 2018 Rate Case Filing Report - Service Colorado Springs Utilities (Utilities) is a transmission provider and provides nondiscriminatory

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

ARTICLE 22 GRIEVANCE AND ARBITRATION

ARTICLE 22 GRIEVANCE AND ARBITRATION ARTICLE 22 GRIEVANCE AND ARBITRATION 22.1 General Provisions. The grievance/arbitration procedure provides the means by which disputes or problems between the parties concerning the application, meaning

More information

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE Operating Companies of the Sixth Revised Sheet No. 1 Supersedes Fifth Revised Sheet No. 1 OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM AEP Texas Central Company AEP Texas

More information

NYISO Pilot Program Guide

NYISO Pilot Program Guide NYISO Pilot Program Guide October 2017 Table of Contents ABOUT THE NYISO... 4 NYISO PILOT PROGRAM... 5 Overview of the Pilot Program... 5 Value of the Pilot Program to NYISO Stakeholders and Pilot Participants...

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III FERC ELECTRIC TARIFF Sheet No. 691 (a) (b) (c) adjust interchange transaction schedules (ITSs) as required under Existing Contracts in accordance with the procedures in the SBP and the SP for the management

More information

ORLANDO UTILITIES COMMISSION Open Access Transmission Tariff Original Sheet 91 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service The Transmission Customer shall compensate

More information

Financial Transmission Rights

Financial Transmission Rights PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM

More information

NYISO Governance Summary of Sector Definitions and Related Terms

NYISO Governance Summary of Sector Definitions and Related Terms NYISO Governance Summary of Sector Definitions and Related Terms There are five voting sectors that participate in the NYISO s shared governance. They are: Generation Owners Other Suppliers Transmission

More information

Power System Operation Procedure: Facility Outages

Power System Operation Procedure: Facility Outages ELECTRICITY INDUSTRY ACT ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES Power System Operation Procedure: Facility Outages Commencement: This Market

More information

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business

More information

Kinder Morgan Illinois Pipeline LLC Original Sheet No. 15 FERC Gas Tariff First Revised Volume No. 1

Kinder Morgan Illinois Pipeline LLC Original Sheet No. 15 FERC Gas Tariff First Revised Volume No. 1 Kinder Morgan Illinois Pipeline LLC Original Sheet No. 15 RATE SCHEDULE FTS FIRM TRANSPORTATION SERVICE 1. AVAILABILITY This Rate Schedule FTS is available to any entity (hereinafter called Shipper) which:

More information

Request for Proposal

Request for Proposal Request for Proposal RFP # SPP-RFP-000001 RFP ISSUED DATE: May 5, 2015 RFP ORIGINATION STUDY: 2015 Integrated Transmission Planning 10-Year Study ( 2015 ITP10 ) Table of Contents Table of Contents... 2

More information

PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF

PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY FERC Electric Tariff First Revised Volume 4 Original Sheet No. 1 TABLE OF CONTENTS 1. Preamble and Applicability...4

More information

UNITED STATES OF AMERICA 87 FERC 61,299 FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA 87 FERC 61,299 FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA 87 FERC 61,299 FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: James J. Hoecker, Chairman; Vicky A. Bailey, William L. Massey, Linda Breathitt, and Curt Hébert, Jr.

More information

ARN2016 Procurement Regulations Utility Sectors 2016

ARN2016 Procurement Regulations Utility Sectors 2016 ARN2016 Procurement Regulations Utility Sectors 2016 Preamble - Special sector companies are obliged to award assignments in accordance with the provisions of the Aanbestedingswet 2012 (Netherlands Procurement

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

Northern Maine Reliability Tie

Northern Maine Reliability Tie NEW HAMPSHIRE TRANSMISSION Northern Maine Reliability Tie New Hampshire Transmission s Solution in Response to MPUC s Reliability Investigation January 2014 Table of Contents Executive Summary... 1 Section

More information

96 FERC 61, 275 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

96 FERC 61, 275 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 96 FERC 61, 275 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, Linda Breathitt, and Nora Mead Brownell. Dynegy Power Marketing,

More information

Planned and Unplanned Changes Language Webinar

Planned and Unplanned Changes Language Webinar Planned and Unplanned Changes Language Webinar Modifications to the CIP Standards Project 2016-02 CIP SDT February 14, 2018 NERC Antitrust Guidelines It is NERC s policy and practice to obey the antitrust

More information

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016 Generation Process SWANA Spring Conference Atlantic City, NJ April 18, 2016 www.pjm.com PJM process is FERC Pro Forma Customer enters queue to sell output into PJM wholesale market (regardless of size)

More information

Chemical Inhibitor Approval Scheme (CIAS) Audit Procedure

Chemical Inhibitor Approval Scheme (CIAS) Audit Procedure Page 1 of 5 Chemical Inhibitor Approval Scheme (CIAS) Audit Procedure 1. Introduction This audit procedure defines the ongoing requirements for NSF Licence holders of CIAS approved products during their

More information

CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR)

CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) Ethan D. Avallone Senior Market Design Specialist, Energy Market Design Management Committee March 28, 2018

More information

ARN Procurement Regulations Utility Sectors 2016

ARN Procurement Regulations Utility Sectors 2016 ARN 2016 Procurement Regulations Utility Sectors 2016 Preamble - Special sector companies are obliged to award assignments in accordance with the provisions of the Aanbestedingswet 2012 (Netherlands Procurement

More information

ONTARIO LABOUR RELATIONS BOARD

ONTARIO LABOUR RELATIONS BOARD ONTARIO LABOUR RELATIONS BOARD INFORMATION BULLETIN NO. 38 Card Based Certification of Trade Unions in Specified Industries This Information Bulletin describes the procedures that must be followed when

More information

Union Power Cooperative

Union Power Cooperative Union Power Cooperative INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities of the local

More information

Reforms to Improve Gas-Electric Coordination Mark R. Haskell, Floyd L. Norton, IV, Brett A. Snyder April 29, 2014

Reforms to Improve Gas-Electric Coordination Mark R. Haskell, Floyd L. Norton, IV, Brett A. Snyder April 29, 2014 Reforms to Improve Gas-Electric Coordination Mark R. Haskell, Floyd L. Norton, IV, Brett A. Snyder April 29, 2014 www.morganlewis.com Presentation Overview Revisions to the operating and scheduling processes

More information

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES 303-571-2794 1 1 FIRE SAFETY Proceed out of the building to the designated meeting location. Do not use the elevators. Stairs are located

More information