Information Delivery Manual (IDM)

Size: px
Start display at page:

Download "Information Delivery Manual (IDM)"

Transcription

1 Piping Engineering - Confluence 1 af :21 Information Delivery Manual (IDM) Added by Jeffrey Wix, last edited by Jeffrey Wix on Jul 23, 2007 (view change) Labels: (None)

2 Piping Engineering - Confluence 2 af :21 Incorporates all IDM components that are about the development, design, fabrication and installation of piping systems. Process Maps Piping Engineering (PM) Exchange Requirements Under Construction Powered by Atlassian Confluence, the Enterprise Wiki. (Version: Build:#408 Jan 23, 2006) - Bug/feature request - Contact Administrators

3 Piping Engineering (PM) - Confluence 1 af :22 Information Delivery Manual (IDM) Added by Kjetil Espedokken, last edited by Kjetil Espedokken on May 11, 2006 (view change) Labels: pm, er-exchange-hvac-model-equipment

4 Piping Engineering (PM) - Confluence HVAC engineering deals with the overall process of planning, designing, installing, commissioning, operating and maintaining heating, ventilating and air conditioning (HVAC) systems for building projects. It deals with systems that distribute air through preformed or manufactured duct sections. Low velocity, medium velocity and high velocity air flow through ducts are all within the scope of this process. Six main process stages are considered within the HVAC Engineering lifecycle. These are shown in the high level process map below as: Plan HVAC Systems Design HVAC Systems Install HVAC Systems Test and Commission HVAC Systems Operate Elements and Systems 2 af :22

5 Piping Engineering (PM) - Confluence 3 af :22 6. Maintain Elements and Systems Plan HVAC Systems [ID:1] Plan HVAC Systems The objective of the planning activity is to: - prepare general outline of requirements (program or brief) and plan future action for the specific planning task concerned, - set up client organisation for programming (or briefing) - obtain program requirements (brief) from the client organisation, - appoint organisations to the project for carrying out work as appropriate to the specific planning task concerned. In this case, the planning activity is concerned with HVAC systems.

6 Piping Engineering (PM) - Confluence 4 af :22 Design HVAC Systems [ID:2] Sub-Process (collapsed) Design HVAC System The objective of the design activity for a project is the progressive development and refinement of the requirements expressed in the program (brief) and then to propose design solutions to those requirements including construction/installation methods, materials, technical solutions. Design solutions proposed should be validated against the provision of building codes and regulations for the specific location of the project and should be in accordance with sustainability criteria including environmental impact and service life. The cost of the design solutions proposed should be estimated and managed through the progressive development of a cost plan. In this case, the design activity is concerned with HVAC systems. Install HVAC Systems [ID:3] Install HVAC Systems The objective of the construct or install activity for a project is to translate proposed design solutions into actual constructed or installed solutions for the project. This activity includes all actions necessary for: - provision of production information including specifications and schedules outlining quality and type of materials and goods required to achieve the objective and constraints applicable to project execution. - planning and scheduling work tasks, - procurement actions for materials, goods and services including tendering actions - execution of construction and installation tasks up to the point at which the work can be tested, commisioned, inspected and/or determined as complete. In this case, the activity is concerned with installation of HVAC systems. Test and Commission HVAC Systems [ID:4] Test and Commission HVAC Systems The objective of the test, commisson and complete activity for a project is to: - provide for the testing of technical solutions to ensure that they will function with the required level of safety - set up technical solutions to operate according to the actual operating requirements of a project - ensure that construction or installation work has been properly executed and to remedy any defects

7 Piping Engineering (PM) - Confluence 5 af :22 - turn over project to the client of the clients operating agent In this case, the activity is concerned with testing, commissioning and completion of HVAC systems. Operate Elements and Systems [ID:5] Operate Elements and Systems The objective of the operate elements and systems activity for a project is to perform those actions and adjustments required to ensure the normal day to day operation of a project. Maintain Elements and Systems [ID:6] Maintain Elements and Systems The objective of the maintain elements and systems activity for a project is to perform those actions and adjustments required to return elements and systems to a satisfactory state (physical or functional) for continued operation. The activity is concerned both with planned and unplanned maintenance activities and considers requirements that may be state (failure or imminent failure), time or condition based. A maintenance requirement is triggered by an event which may be caused by either: - the amount of time that has elapsed since the previous maintenance operation was carried out has reached the planned interval between maintenance operations, or - the date on which a maintenance operation is planned has arrived, or - the current operating condition of an element, group of elements or system as determined by the values of one or more parameters has reached a level at which maintenance is set to occur, or - an operational failure (either complete or partial) has occurred that requires a maintenance operation to correct. In the context of the above, maintenance is also considered to encompass replacement where an element has reached the end of its working life. The stages identified are expected to be approximately mapped to specific project stages according to the table below: Note that this mapping splits the general project stage 'Construction' between the HVAC stages 'Install' and 'Test and Commission'. The primary roles shown in the process map diagram (as 'swimlanes') are defined as:

8 Piping Engineering (PM) - Confluence 6 af :22 HVAC Design HVAC Construction Facilities Management (in this case, concerned with the electrical engineering aspects of facilities management) Fundamental Design Process HVAC Engineering design follows the fundamental design process as outlined in the Electrical Emgineering process map. Stage 1: Plan HVAC Systems Not currently developed *Stage 2: Design HVAC Systems* Design HVAC Systems (Programming) [ID:2.1] Sub-Process (collapsed) Design HVAC Systems (Programming) The term "programming" is the process of developing a program. Programming includes the assessment of needs/requirements and delimitations/constraints. These are described as a program (e.g. in Norway usually according to Norwegian Standard NS3451). Delimitations can be

9 Piping Engineering (PM) - Confluence 7 af :22 physical (e.g. area type and size, space program), technical (e.g. number and type of outlets, or type of materials), time based (e.g. project progress) and financial (e.g. investment budget or LCC). The programming stage accounts for the client's assessment of the requirements to be met by the completed construction and forms the basis for determining the budget. For HVAC, the process includes determining: - Space program requirements for HVAC systems to meet technical requirements - Identification of requirement for technical spaces - Identification of requirement for vertical distribution spaces - Identify what types of system are relevant Design HVAC Systems (Sketch) [ID:2.2] Sub-Process (collapsed) Design HVAC Systems (Sketch) The term "sketch design" is the process of developing an interdisciplinary design where the propositions from the design team describe relevant alternative main principles and main system solutions (in Norway usually according to Norwegian Standard NS3451). The alternatives are presented with pros and cons. The design team's recommended design solutions for further study at the full concept stage are stated, along with proposed reports to be carried out at the full concept stage. For HVAC systems, this process includes determining: - Estimate of load to determine main flow moving device (fan) size - Identify main vertical routes using indicated spaces - Location, sizing and identification of technical spaces - Costing for presentation is by high level aggregation element - Specification of types of system and principles of operation. - Sketch design model showing technical spaces, vertical distribution routes, and key horizontal routes to describe principal routing. Specifics for Norwegian Practice - NS3451, Building element level of systems (down to level of whole system such as all lighting) - Costing uses NS3453 likely to be based on sq.m prices against known previous example buildings. NS3457 is standard table for building categories. Design HVAC Systems (Full Concept) [ID:2.3] Sub-Process (collapsed) Design HVAC Systems (Full Concept)

10 Piping Engineering (PM) - Confluence 8 af :22 The term "full concept design" is the process of developing an interdisciplinary design where the propositions from the design team describe a recommended solution (in Norway usually according to Norwegian Standard NS3451). At this stage all relevant principles and system solutions for all disciplines are stated, qualitatively and quantitatively. Estimated Life Cycle Cost (LCC) for the design shall be provided. All succeeding stages are in principle regarded as "production stages" (i.e. production drawings / models, the physical building, documentation). The full concept design level of detailing should be sufficient to avert later principle / system decisions with quality, progress or economic implications, unless a change is done in programming requirements. Further detailing and smaller changes of design solutions at later stages are considered to be normal and acceptable. Design HVAC Systems (Coordinated) [ID:2.4] Sub-Process (collapsed) Design HVAC Systems (Coordinated) The term "coordinated design" is the process of developing a detailed interdisciplinary coordinated design where design team deliverables include a building information model that contains characteristic product specification attributes (in Norway usually according to Norwegian Standard NS3420) suitable for a tender process, including supplementary demands for test procedures, component labeling, documentation etc. A number of additional reports may also be required (e.g. environmental issues reports, LCC according to Norwegian Standard NS3454, waste handling procedures, universal (handicapped friendly) design documentation etc).

11 Piping Engineering (PM) - Confluence 9 af :22 *Stage 21: Design HVAC Systems (Programming)* Estimate Load [ID:2.1.1] Estimate Load For the project as proposed, make an estimate of the expected overall HVAC load so that a preliminary estimate of the size of the flow moving device (fan, pump etc.) can be made. Information for estimating loads at the programming stage will typically be derived from previous, similar projects or from collected 'rules of thumb' (which are effectively aggregated data from multiple previous, similar projects). Such calculations will make broad assumptions about contributions to load resulting from lighting or other energy sources rather than using information contributed to the building model from other roles.

12 Piping Engineering (PM) - Confluence 10 af :22 Estimate Space Requirements for Technical Spaces [ID:2.1.2] Estimate Space Requirements for Technical Spaces Makes a preliminary estimate of the space required for major technical spaces to serve the HVAC systems on a project. Major technical spaces are spaces that have a substantial impact on building consideration either in terms of their overall size or their structural implication (special floors etc.). Other (minor) technical spaces will be determined at the sketch design stage. Estimate of the space requirement may include height requirement (e.g. need for 5m height for the type of equipment being considered). Example: A major technical space could be for a chiller or cooling tower plant space or plant room. The estimate is based on experience, knowledge of previous projects, industry guidance etc. Typically, it is determined on a factor based method that takes into account total space area and space function. Non indicated spaces such as circulation space, storage space etc. may be accounted for in total building space by further parameters. This can also be used in accounting for space required to accommodate further expansion that may be mandated by the space program. Define Special Spaces [ID:2.1.3] Define Special Spaces Special spaces are spaces that may require more detailed elaboration at the programming stage. Typically, they are spaces that have particular, detailed requirements and are not represented as a space type within a libray of such types held by a client. Example: A 'Ship Simulation Room' at Tromso College is used to train ships officers by providing simulated views from the bridge of a ship. This space is modelled in detail even at the programming stage to enable consideration of the particular design requirements of the space. Agree Location and Size of Technical Spaces [ID:2.1.4] Agree Location and Size of Technical Spaces Propose the location and size of major technical spaces - from previous process (not minor technical spaces). This should be based on the space requirements previously identified. Location of spaces includes the configuration relative to adjacent spaces in the case of there being any constraints or requirements as to room type X adjacent to room type Y. E.g. plant room and fan chamber should be adjacent to each other.

13 Piping Engineering (PM) - Confluence 11 af :22 Estimate Cost [ID:2.1.5] Estimate Cost For the project as proposed, make an estimate of the order of magnitude cost of the electrical systems. Order of magnitude costing will largely be based on cost information from previous projects. Specifics for Norwegian Practice - Costing uses NS3453 and is likely to be based on sq.m prices against known previous example buildings. - NS3457 is standard table for building categories. *Stage 2.2: Design HVAC Systems (Design Stages)*

14 Piping Engineering (PM) - Confluence 12 af :22 Define Spaces [ID:2.2.1] Sub-Process (expanded) Define Spaces Confirm Requirements, Location, Shape and Size for Technical Spaces [ID: ] Confirm Requirements, Location, Shape and Size for Technical Spaces The task confirms and agrees the requirement for, location, shape and size of technical spaces as proposed at the previous project stage. This is based on the space requirements previously identified but expands the requirement in terms of the extended geometry information available for the space including height requirement where relevant, Technical spaces includes plant rooms, plenum chambers etc. as well as vertical distribution spaces. Identify Fire Compartmentation [ID: ] Identify Fire Compartmentation Zone Spaces into Systems [ID: ] Zone Spaces into Systems Identify spaces and group them into zones within which all entities of a given class (or range of classes) are grouped together to belong to a particular system. Determine Air Requirements [ID: ]

15 Piping Engineering (PM) - Confluence 13 af :22 Determine Air Requirements Establish the requirement for supply or extraction of air from spaces. Distribute this requirement to be met by terminals within spaces. Select and Locate Equipment [ID:2.2.2] Sub-Process (collapsed) Select and Locate Equipment For main items of equipment, select generic types and estimate their size, location and weight. Select, Size and Connect Distribution Routes [ID:2.2.3] Sub-Process (collapsed) Select, Size and Connect Distribution Routes

16 Piping Engineering (PM) - Confluence 14 af :22 Selection of distribution method, estimate of load and diversity, routing and sizing of ducts. Select Distribution Method [ID: ] Select Distribution Method Decide on the distribution method of the HVAC system. E.g. central air/air distribution, local air/water system etc. Note that several alternative sketch designs may be proposed, each design using an alternative distribution method. Final choice of the selected method is made at the full concept design stage. Decide Distribution Routes [ID: ]

17 Piping Engineering (PM) - Confluence 15 af :22 Decide Distribution Routes Using spaces allocated to systems decide main distribution routes. This is for main air ducts throughout the project only; branch ducts are not routed at this stage. The objective of determining the distribution route is to ensure awareness of main routes and sizes for distribution.. Estimate Loads at Significant Points [ID: ] Estimate Loads at Significant Points Estimate the load to be met at significant points along the main distribution routes. Sum Loads [ID: ] Sum Loads Add the estimated loads progressively back to the estimated point at which the fan will be located. This will provide an estimated load on each section of the main distribution route and a total estimated load which the fan(s) is required to meet. Calculate Distribution System Sizes [ID: ] Calculate Distribution System Sizes From the loads determined for the main distribution routes, estimate the required largest duct size. This is used for allocation of space within distribution zones and also for coordination purposes. Estimate Diversity Factor [ID: ] Estimate Diversity Factor

18 Piping Engineering (PM) - Confluence 16 af :22 Estimate a diversity factor for HVAC supply that considers the expected maximum simultaneous load on the system given that not all HVAC distribution may be required at the same time. Model Typical Space Layouts [ID: ] Model Typical Space Layouts Detailing of equipment layouts and duct branch routes in typical 'spaces' that enable cost models to be better informed. Connect System Elements [ID: ] Connect System Elements Make connections between distribution system elements and allocate flow directions. Regulate Systems [ID: ] Regulate Systems Deals with the selection,placement (where not already done through a prior process), sizing (by reference to the distribution elements to which regulating elements are connected) and establishment of regulation setting to achieve the degree of regulation required. For example, to achieve the required air flow through a branch air duct, a balancing damper must be set to be 30% closed. Note that the settings established by design at this stage may be subject to field modification when HVAC systems are commissioned. Assign Operational Information [ID:2.2.4] Assign Operational Information

19 Piping Engineering (PM) - Confluence 17 af :22 Preliminary assignment of operating and maintenance data about the systems and distribution routes that forms the basis for later operating and maintenance instruction information. Analyze System [ID:2.2.5] Analyze System Analyze the system in terms of flow requirements. The type of calculation (algorithm used) should be driven by the extent of information available from the model. The more information that is available then the more comprehensive the method that is expected to be used in analysis. Sizing Balancing Acoustics inc cross talk Estimate Cost [ID:2.2.6] Estimate Cost Estimate the cost of the proposed construction/installation at the current design stage Specifics for Norwegian Practice - NS3457 is standard table for building categories. Stage 2.3: Design HVAC Systems (Full Concept) Considered as a cyclical stage within the process at stage 2.2 above Stage 2.4: Design HVAC Systems (Coordinated) Considered as a cyclical stage within the process at stage 2.2 above Stage 3: Install HVAC Systems Not currently developed Stage 4: Test and Commission HVAC Systems Not currently developed Stage 5: Operate Elements and Systems Not currently developed Stage 6: Maintain Elements and Systems Not currently developed Specification of Data Objects

20 Piping Engineering (PM) - Confluence 18 af :22 HVAC Requirements Data Object Electrical Requirements Requirements for the provision of HVAC services. Previous Project Guidance Data Object Previous Project Guidance Previous projects of a similar nature from which guidance can be obtained. Industry Technical Guidance Data Object Industry Technical Guidance Industry technical guidance from which guidance can be obtained. Building Program Data Object Building Program This is the document that sets out what needs to be taken into account during the HVAC design process. It does not set down data requirements but it does set down the overall expectations that the client has of the HVAC engineer and therefore acts as a 'quality assurance' document. States the clients preferences. Space Regulations Data Object Space Regulations Local regulations on size and placement of technical spaces.

21 Piping Engineering (PM) - Confluence 19 af :22 Equipment Data Data Object Equipment Data Generic equipment size and weight specifications enabling testing of space allocation, structural provision and enabling preliminary coordination. Cost Data Data Object Cost Data Stored cost information from suppliers or other cost planning sources Data Data Object Data Stored information about operation and maintenance tasks that should be undertaken on systems and equipment, the skill expected to be able to undertake tasks, the expected frequency of tasks (enabling a proposed maintenance plan to be able to be derived). Exchange Requirement Data Objects er_exchange_hvac_model [programming] Data Object er_exchange_hvac_model [programming] HVAC model at the programming stage that can be added to overall building information model. Information at this stage is advisory based on speculative design. It includes the following advisory information provision: - overall size (area) of major technical spaces required, - minimum height requirement for technical spaces, - location of major technical spaces including constrained relationships to any other spaces that may be required for reasons of noise, safety, environmental considerations or other aspects, - required adjacency between major technical spaces considered to be in the vertical as well as in the horizontal plane; this may indicate the required strength of the adjacency (must be, should be, could be), - estimated HVAC load for the project,

22 Piping Engineering (PM) - Confluence 20 af :22 - indications of major equipment items to be located in identified spaces and information that may impact on regulation processes (e.g.planning), - list of special spaces for which special design provisions may apply. er_exchange_hvac_model [space] Data Object er_exchange_hvac_model [space] ** applicable to design stages cyclically ** Exchange of information about technical spaces for HVAC plant and equipment and how other spaces are grouped for system development and fire compartmentation. Used to coordinate with general zoning and spacing requirements with other roles. er_exchange_hvac_model [equipment] Data Object er_exchange_hvac_model [equipment] ** applicable to design stages cyclically ** Exchange of information about shape, size and location of HVAC components. HVAC systems information can then be brought together with equivalent information from other roles to ensure that items of equipment are in proper spatial and functional relationship to each other taking into account their size and location in terms of space allocation and structural provision. Information provided for equipment includes all that provided for prior exchange requirements including spaces information with the addition of: - types of component to be used and sizes - allocation of type information to occurrences of components - size of type and/or occurrence of component - shape representation of component (using an appropriate representation form that may be symbolic, 2D, 3D boundary representation etc.); the form of representation to be used and the extent of detail that is provided for the component may differ at different stages of the project. - location of occurrences of components. er_exchange_hvac_model [systems] Data Object er_exchange_hvac_model [systems] ** applicable to design stages cyclically **

23 Piping Engineering (PM) - Confluence 21 af :22 Exchange of information about configuration, size, location, connection and technical data of HVAC systems including both the components and the distribution elements. HVAC systems information can then be brought together with equivalent information from other roles to ensure that items of equipment are in proper spatial, functional and technical relationship to each other taking into account their size and location in terms of space allocation and structural provision. Information provided for systems includes all that provided for prior exchange requirements including spaces and components information with the addition of: - estimated or calculated loads for systems and for the project (the definition of estimate or calculation being dependent on project stage and the available technical detail to enable calculation to occur), - form of HVAC distribution (e.g. low velocity, high velocity etc.) - airflow requirements at components - simultaneous load diversity information required by the power supplier. - types of ductwork to be used and sizes - allocation of type information to occurrences of ductwork - types of flow terminal outlet (grille/diffuser) to be used, sizes and technical data - allocation of type information to occurrences of flow terminal outlet - types of flow control (dampers etc.) to be used, sizes and technical data - allocation of type information to occurrences of flow control - types of flow moving device (fan etc.) to be used, sizes and technical data - allocation of type information to occurrences of flow moving device - allocation of components and distribution elements to systems - types of flow treatment (filters etc.), heat exchange devices and other air distribution devices to be used, sizes and technical data - allocation of type information to occurrences of other air distribution devices - allocation of components and distribution elements to systems - distribution routes - connection details and flow directions The extent of system information exchanged will vary depending on the project stage, (1) Sketch design is expected to include only major routes and may be topologically represented (lines in 3D space) including edges as routes and vertices to represent changes in direction and with main components indicated. (2) Full concept design is expected to represent linear segments, fittings and components. Relevant information about routes is expected together with load information. Technical data will be provided but this may not be sufficiently complete for specification and procurement. (3) Coordinated design will include all system elements including jointing detail and connectivity and all associated detailed technical data required for specification and procurement. +*Coordination Point Gateways*+ Coordinate_plan

24 Piping Engineering (PM) - Confluence 22 af :22 Coordination Point Coordinate_plan Coordination and approval (or otherwise) of all planning work undertaken. Coordinate_design Coordination Point Coordinate_design Coordination and approval (or otherwise) of all design work undertaken. ** This coordination point may be considered as being synonymous with the 'Coordinate_coordinated_design' coordination point. Coordinate_program_design Coordination Point Coordinate_program_design Coordination and approval (or otherwise) of speculative design work undertaken at the programming stage. Coordinate_sketch_design Coordination Point Coordinate_sketch_design Coordination and approval (or otherwise) of design work undertaken at the sketch design stage. Coordinate_full_concept_design Coordination Point Coordinate_full_concept_design Coordination and approval (or otherwise) of design work undertaken at the full concept design stage. Coordinate_coordinated_design

25 Piping Engineering (PM) - Confluence 23 af :22 Coordination Point Coordinate_coordinated_design Coordination and approval (or otherwise) of design work undertaken at the coordinated design stage. Coordinate_equipment_location Coordination Point Coordinate_equipment_location This purpose here is to represent a point at which the model of the HVAC systems is brought together with equivalent models from other roles for coordination and approval. Coordination is concerned with ensuring that items of equipment are in proper spatial and functional relationship to each other taking into account their size and location in terms of space allocation and structural provision. For example: (1) major items of equipment applying a significant load on the structure need to have suitable structural support, (2) equipment requiring maintenance action should not have access restricted by other technical systems components, (3) visible items should be in appropriate locations for functional and aesthetic coordination. Coordinate_space Coordination Point Coordinate_space The purpose here is to bring together information that is currently available about the spaces as required for the technical systems designs to ensure that requirements are coordinated and that space allocations as required are made. Coordinate_systems Coordination Point Coordinate_systems At this point, the aim is to coordinate the HVAC systems design with other systems information and make adjustments that are necessary. The possibility for such adjustments is described by feedback provisions. Powered by Atlassian Confluence, the Enterprise Wiki. (Version: Build:#408 Jan 23, 2006) - Bug/feature request - Contact Administrators

26 Process Model Piping Engineering Identifier xxx IFC Release IFC 2x2 Addendum 1 Change Log Created jeffrey.wix@aec3.com Exchange Requirements er_exchange_piping_model (programming) er_exchange_piping_model (space) er_exchange_ piping _model (equipment) er_exchange_ piping _model (systems) Overview Piping engineering deals with the overall process of planning, designing, installing, commissioning, operating and piping systems for building projects. It deals with systems that distribute a fluid through pipe sections. Typically, water distribution systems are within the scope of this exchange requirement including low, medium and high temperature hot water heating, domestic hot water service, domestic cold water service (both mains connected and tank fed), chilled water, condenser water, refrigerant, compressed air, medical gases, fuel gas, oil and others. Six main process stages are considered within the Piping engineering lifecycle. These are shown in the high level process map below as: 1. Plan Piping Systems 2. Design Piping Systems 3. Install Piping Systems 4. Test and Commission Piping Systems 5. Operate Elements and Systems 6. Maintain Elements and Systems

27 H V A C e n g i n e e r i n g p r o c e s s m a p Plan Piping Systems [ID:1] Plan Piping Systems The objective of the planning activity is to: - prepare general outline of requirements (program or brief) and plan future action for the specific planning task concerned, - set up client organisation for programming (or briefing) - obtain program requirements (brief) from the client organisation, - appoint organisations to the project for carrying out work as appropriate to the specific planning task concerned. Design Piping Systems [ID:2] Install Piping Systems [ID:3] In this case, the planning activity is concerned with HVAC systems. Sub-Process (collapsed) Design Piping System The objective of the design activity for a project is the progressive development and refinement of the requirements expressed in the program (brief) and then to propose design solutions to those requirements including construction/installation methods, materials, technical solutions. Design solutions proposed should be validated against the provision of building codes and regulations for the specific location of the project and should be in accordance with sustainability criteria including environmental impact and service life. The cost of the design solutions proposed should be estimated and managed through the progressive development of a cost plan. In this case, the design activity is concerned with piping systems. Install Piping Systems The objective of the construct or install activity for a project is to translate proposed design solutions into actual constructed or installed solutions for the project. This 2

28 Test and Commission Piping Systems [ID:4] Operate Elements and Systems [ID:5] Maintain Elements and Systems [ID:6] H V A C e n g i n e e r i n g p r o c e s s m a p activity includes all actions necessary for: - provision of production information including specifications and schedules outlining quality and type of materials and goods required to achieve the objective and constraints applicable to project execution. - planning and scheduling work tasks, - procurement actions for materials, goods and services including tendering actions - execution of construction and installation tasks up to the point at which the work can be tested, commissioned, inspected and/or determined as complete. In this case, the activity is concerned with installation of piping systems. Test, Commission and Complete Piping Systems The objective of the test, commission and complete activity for a project is to: - provide for the testing of technical solutions to ensure that they will function with the required level of safety - set up technical solutions to operate according to the actual operating requirements of a project - ensure that construction or installation work has been properly executed and to remedy any defects - turn over project to the client of the clients operating agent In this case, the activity is concerned with testing, commissioning and completion of piping systems. Operate Elements and Systems The objective of the operate elements and systems activity for a project is to perform those actions and adjustments required to ensure the normal day to day operation of a project. Maintain Elements and Systems The objective of the maintain elements and systems activity for a project is to perform those actions and adjustments required to return elements and systems to a satisfactory state (physical or functional) for continued operation. The activity is concerned both with planned and unplanned maintenance activities and considers requirements that may be state (failure or imminent failure), time or condition based. A maintenance requirement is triggered by an event which may be caused by either: - the amount of time that has elapsed since the previous maintenance operation was carried out has reached the planned interval between maintenance operations, or - the date on which a maintenance operation is planned has arrived, or - the current operating condition of an element, group of elements or system as determined by the values of one or more parameters has reached a level at which maintenance is set to occur, or - an operational failure (either complete or partial) has occurred that requires a maintenance operation to correct. In the context of the above, maintenance is also considered to encompass replacement where an element has reached the end of its working life. The stages identified are expected to be approximately mapped to specific project stages according to the table below: EE Stage Project Stage 1 Plan Piping Systems 2 Outline Feasibility 3 Substantive Feasibility 2 Design Piping Systems 4 Outline conceptual design 3

29 H V A C e n g i n e e r i n g p r o c e s s m a p 5 Full conceptual design 6 Coordinated design and procurement 3 Install Piping Systems 7 Production information 4 Test and Commission Piping Systems 8 Construction 8 Construction 5 Operate Elements and Systems 9 Operation and maintenance 6 Maintain Elements and Systems 9 Operation and maintenance Note that this mapping splits the general project stage Construction between the piping stages Install and Test and Commission. Fundamental Design Process Piping engineering design follows the fundamental design process as outlined in the Electrical engineering process map. Stage 1: Plan Piping Systems Not currently developed Stage 2: Design Piping Systems Design Piping Systems (Programming) [ID:2.1] Sub-Process (collapsed) Design Piping Systems (Programming) The term programming is the process of developing a program. Programming includes the assessment of needs/requirements and delimitations/constraints. These are described as a program (e.g. in Norway usually according to Norwegian Standard NS3451). Delimitations can be physical (e.g. area type and size, space program), technical (e.g. number and type of outlets, or type of materials), time based (e.g. project progress) and financial (e.g. investment budget or LCC). The programming 4

30 H V A C e n g i n e e r i n g p r o c e s s m a p stage accounts for the client s assessment of the requirements to be met by the completed construction and forms the basis for determining the budget. For piping, the process includes determining: - Space program requirements for piping systems to meet technical requirements - Identification of requirement for technical spaces - Identification of requirement for vertical distribution spaces - Identify what types of system are relevant Design Piping Systems (Sketch) [ID:2.2] Design Piping Systems (Full Concept) [ID:2.3] Design Piping Systems (Coordinated) [ID:2.4] Sub-Process (collapsed) Design Piping Systems (Sketch) The term sketch design is the process of developing an interdisciplinary design where the propositions from the design team describe relevant alternative main principles and main system solutions (in Norway usually according to Norwegian Standard NS3451). The alternatives are presented with pros and cons. The design team s recommended design solutions for further study at the full concept stage are stated, along with proposed reports to be carried out at the full concept stage. For piping systems, this process includes determining: - Estimate of load to determine storage, delivery or flow moving device (pump, compressor) types - Identify main vertical routes using indicated spaces - Location, sizing and identification of technical spaces - Costing for presentation is by high level aggregation element - Specification of types of system and principles of operation. - Sketch design model showing technical spaces, vertical distribution routes, and key horizontal routes to describe principal routing. Specifics for Norwegian Practice - NS3451, Building element level of systems (down to level of whole system such as all lighting) - Costing uses NS3453 likely to be based on sq.m prices against known previous example buildings. NS3457 is standard table for building categories. Sub-Process (collapsed) Design Piping Systems (Full Concept) The term full concept design is the process of developing an interdisciplinary design where the propositions from the design team describe a recommended solution (in Norway usually according to Norwegian Standard NS3451). At this stage all relevant principles and system solutions for all disciplines are stated, qualitatively and quantitatively. Estimated Life Cycle Cost (LCC) for the design shall be provided. All succeeding stages are in principle regarded as production stages (i.e. production drawings / models, the physical building, documentation). The full concept design level of detailing should be sufficient to avert later principle / system decisions with quality, progress or economic implications, unless a change is done in programming requirements. Further detailing and smaller changes of design solutions at later stages are considered to be normal and acceptable. Sub-Process (collapsed) Design Piping Systems (Coordinated) The term coordinated design is the process of developing a detailed interdisciplinary coordinated design where design team deliverables include a building information model that contains characteristic product specification attributes (in Norway usually according to Norwegian Standard NS3420) suitable for a tender process, including supplementary demands for test procedures, component labeling, documentation etc. A number of additional reports may also be required (e.g. environmental issues reports, LCC according to Norwegian Standard NS3454, waste handling procedures, universal (handicapped friendly) design documentation 5

31 H V A C e n g i n e e r i n g p r o c e s s m a p etc). Stage 21: Design Piping Systems (Programming) Estimate Load [ID:2.1.1] Estimate Load For the project as proposed, make an estimate of the expected overall load that the system is intended to meet (based on functional requirements) so that a preliminary estimate of the size of the storage, delivery and/or flow moving device can be made. For instance: - for a heating system, load will be based on expected energy per unit area or per unit volume, - for a domestic water service system, load will be based on the number of people expected to be served Information for estimating loads at the programming stage will typically be derived from previous, similar projects or from collected 'rules of thumb' (which are effectively aggregated data from multiple previous, similar projects). Estimate Space Requirements for Technical Spaces [ID:2.1.2] Estimate Space Requirements for Technical Spaces Makes a preliminary estimate of the space required for major technical items serving the piping systems on a project. Such spaces may be part of a technical space (such as a tank room or pump room) or may be part of a more general space. Major technical spaces are spaces that have a substantial impact on building consideration either in terms of their overall size or their structural implication (special floors etc.). Other (minor) technical spaces will be determined at later design stages. Estimates of space requirement may include height requirement and will be based on experience, knowledge of previous projects, industry guidance etc. Typically, the 6

32 Define Special Spaces [ID:2.1.3] Agree Location and Size of Technical Spaces [ID:2.1.4] H V A C e n g i n e e r i n g p r o c e s s m a p requirement is determined on a factor based method that takes into account total space area and space function. Non indicated spaces such as circulation space, storage space etc. may be accounted for in total building space by further parameters. This can also be used in accounting for space required to accommodate further expansion that may be mandated by the space program. Define Special Spaces Special spaces are spaces that may require more detailed elaboration at the programming stage. Typically, they are spaces that have particular, detailed requirements and are not represented as a space type within a library of such types held by a client. Example: A 'Ship Simulation Room' at Tromso College is used to train ships officers by providing simulated views from the bridge of a ship. This space is modelled in detail even at the programming stage to enable consideration of the particular design requirements of the space. Agree Location and Size of Technical Spaces Propose the location and size of major technical spaces - from previous process (not minor technical spaces). This should be based on the space requirements previously identified. Estimate Cost [ID:2.1.5] Location of spaces includes the configuration relative to adjacent spaces in the case of there being any constraints or requirements as to room type X adjacent to room type Y. Estimate Cost For the project as proposed, make an estimate of the order of magnitude cost of the systems. Order of magnitude costing will largely be based on cost information from previous projects. Specifics for Norwegian Practice - Costing uses NS3453 and is likely to be based on sq.m prices against known previous example buildings. - NS3457 is standard table for building categories. Stage 2.2: Design Piping Systems (Design Stages) 7

33 H V A C e n g i n e e r i n g p r o c e s s m a p Define Spaces [ID:2.2.1] Sub-Process (expanded) Define Spaces Confirm Requirements, Location, Shape and Size for Technical Spaces [ID: ] Identify Fire Compartmentation [ID: ] Zone Spaces into Systems [ID: ] Determine Air Requirements [ID: ] Confirm Requirements, Location, Shape and Size for Technical Spaces The task confirms and agrees the requirement for, location, shape and size of technical spaces as proposed at the previous project stage. This is based on the space requirements previously identified but expands the requirement in terms of the extended geometry information available for the space including height requirement where relevant, Technical spaces include plant rooms, plenum chambers etc. as well as vertical distribution spaces. For piping systems, complex junctions (e.g. ceiling space above corridor junction) are also considered to be technical spaces. Identify Fire Compartmentation Identify fire and other compartmentation that bounds system provision. Zone Spaces into Systems Identify spaces and group them into zones within which all entities of a given class (or range of classes) are grouped together to belong to a particular system. For example, spaces are zoned for sprinkler system provision. Determine Functional Load 8

34 Select and Locate Equipment [ID:2.2.2] Select, Size and Connect Distribution Routes [ID:2.2.3] H V A C e n g i n e e r i n g p r o c e s s m a p Establish the functional load requirements for a space or needing to be satisfied by delivery within a space. Sub-Process (collapsed) Select and Locate Equipment Select equipment types and estimate their size and weight.. Locate occurrences of equipment types appropriate to the current design stage. - At sketch design, major items of equipment will be selected and located. - At full concept design, terminals and main control items will be selected and located. - At coordinated design, small discrete accessories and components will be selected and located. Sub-Process (collapsed) Select, Size and Connect Distribution Routes Selection of distribution method, estimate of load and diversity, routing and sizing of pipes. Select Distribution Method [ID: ] Decide Distribution Routes [ID: ] Select Distribution Method Decide on the distribution method to be used. Note that several alternative sketch designs may be proposed, each design using an alternative distribution method. Final choice of the selected method is made at the full concept design stage. Decide Distribution Routes 9

35 Estimate Loads at Significant Points [ID: ] Sum Loads [ID: ] Calculate Distribution System Sizes [ID: ] Estimate Diversity Factor [ID: ] Model Typical Space Layouts [ID: ] Connect System Elements [ID: ] Regulate Systems [ID: ] Assign Operational Information [ID:2.2.4] Analyze System [ID:2.2.5] Using spaces allocated to systems decide distribution routes. 10 H V A C e n g i n e e r i n g p r o c e s s m a p Estimate Loads at Significant Points Estimate the load to be met at significant points along the distribution routes. Sum Loads Add the estimated loads progressively back to the estimated point at which the fan will be located. This will provide an estimated load on each section of the distribution route and a total estimated load for the system. Calculate Distribution System Sizes From the loads determined for the distribution routes, estimate the required pipe sizes. This is used for allocation of space within distribution zones and also for coordination purposes. Estimate Diversity Factor Estimate a diversity factor for piped system that considers the expected maximum simultaneous load on the system. Model Typical Space Layouts Detailing of equipment layouts and branch routes in typical 'spaces' that enable cost models to be better informed. Connect System Elements Make connections between distribution system elements and allocate flow directions. Regulate Systems Deals with the selection, placement (where not already done through a prior process), sizing (by reference to the distribution elements to which regulating elements are connected) and establishment of regulation setting to achieve the degree of regulation required. Note that the settings established by design at this stage may be subject to field modification when piping systems are commissioned. Assign Operational Information Preliminary assignment of operating and maintenance data about the systems and distribution routes that forms the basis for later operating and maintenance instruction information. Analyze System Analyze the system in terms of flow requirements. The type of calculation (algorithm used) should be driven by function of the system and the extent of information available from the model. The more information that is available then the more comprehensive the method that is expected to be used in analysis.

Information Delivery Manual (IDM) for Quantity Takeoff for Cost Estimating

Information Delivery Manual (IDM) for Quantity Takeoff for Cost Estimating Information Delivery Manual (IDM) for Quantity Takeoff for Cost Estimating Version: 1.0 -- 30-May-11 IDM for Design to Quantity Takeoff for Cost Estimating Page 2 Table of Contents 1 Process Model... 3

More information

Change Log Created er_exchange_mep_qto (order_of_magnitude) er_exchange_ MEP_QTO (approximate_quantities)

Change Log Created er_exchange_mep_qto (order_of_magnitude) er_exchange_ MEP_QTO (approximate_quantities) Process Model Identifier MEP Quantity Take Off xxx Change Log 2008-08-01 Created jdw@aec3.com Exchange Requirements er_exchange_mep_qto (order_of_magnitude) er_exchange_ MEP_QTO (preliminary_quantities)

More information

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED EVERY ITEM WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON- APPLICABILITY (NA). 1. HEATING SYSTEMS: A. GENERAL

More information

TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify,

TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, TDP Catalog TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, sell, and apply HVAC equipment in commercial

More information

Technical Development Program

Technical Development Program TDP Catalog TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, sell, and apply HVAC equipment in commercial

More information

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort TDP-101 HVAC Industry Overview This TDP provides a general overview of the commercial HVAC industry and provides an awareness of the design process and construction. The documents involved in construction,

More information

General Objectives of Phase. Phase Task Checklist Integral Consulting Page 1 Schematic Design Checklist. Action

General Objectives of Phase. Phase Task Checklist Integral Consulting Page 1 Schematic Design Checklist. Action Project Number: Prepared By: Action General Objectives of Phase Drawings and other documents indicating the scale and relationships of Project components in conformance with program Building areas and

More information

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service Installation Service - 1 - InfraStruXure InRow SC Assembly and Start-Up Statement of Work 1.0 Executive Summary InfraStruXure InRow SC Assembly & Start-Up Service Table of Contents 1.0 Executive Summary

More information

Great Ocean Rd Ice Creamery

Great Ocean Rd Ice Creamery Great Ocean Rd Ice Creamery BCA Section J - JV3 Compliance Report Revision: 01 Job No: 2171 Date: 7 July 2015 ADP Consulting Pty Ltd Level 10, 10 Queens Rd, Melbourne Vic 3004 www.adpconsulting.com.au

More information

ANSI/ASHRAE STANDARD , METHODS OF TESTING CHILLED BEAMS

ANSI/ASHRAE STANDARD , METHODS OF TESTING CHILLED BEAMS ANSI/ASHRAE STANDARD 200-2015, METHODS OF TESTING CHILLED BEAMS NEMIC 2017 Agenda 1. Foreword 2. Purpose & Scope 3. Definitions 4. Instrumentation & Facilities 5. Test Methods 6. Reporting 7. Normative

More information

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section. SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply

More information

4th Class Power Engineering (PEN) Curriculum Mapping

4th Class Power Engineering (PEN) Curriculum Mapping Curriculum Mapping Program Curriculum A collection of 25 CTS courses have been developed to align with the revised (2017) 4th Class Power Engineering course outline. These courses, when combined, cover

More information

Project Name: Example Building OFPC Project No.: 12345

Project Name: Example Building OFPC Project No.: 12345 Energy Impact Statement Project Name: Example Building OFPC Project : 12345 Building Description and Assumptions: The design professional shall provide a brief narrative describing various building related

More information

Mechanical Systems Proposal

Mechanical Systems Proposal Mechanical Systems Proposal Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option December

More information

Georgetown University New Science Center

Georgetown University New Science Center Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical

More information

Air distribution and temperature control in classrooms

Air distribution and temperature control in classrooms Air distribution and temperature control in classrooms Jarek Kurnitski D.Sc., Docent HELSINKI UNIVERSITY OF TECHNOLOGY Laboratory of Heating, Ventilation and Air Conditioning Swegon Air Academy 11.6.2008

More information

Life Cycle Costing as part of decision making - use of building information models

Life Cycle Costing as part of decision making - use of building information models Life Cycle Costing as part of decision making - use of building information models G. Krigsvoll SINTEF Building and Infrastructure/Oslo University College ABSTRACT: Building Information Modelling (BIM)

More information

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing. PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 230593 TESTING, ADJUSTING, AND BALANCING A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

County of Yolo Development Services Building Inspection Division

County of Yolo Development Services Building Inspection Division County of Yolo Development Services Building Inspection Division 292 W. Beamer Street Woodland, CA. 95695 www.yolocounty.org (530) 666-8775 Mechanical Plan Review Comments Plan Review No. Owners Name Job

More information

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER Page 1 / 15 Ver. 1.1 TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER Abstract The experimental fusion reactor ITER will require the European supply of the Poloidal

More information

Ehsan Soltani. Date of Birth: 1 Sep, 1980 Nationality: Iranian Marital Status: Married Mobile :(+98)

Ehsan Soltani. Date of Birth: 1 Sep, 1980 Nationality: Iranian Marital Status: Married   Mobile :(+98) Ehsan Soltani Date of Birth: 1 Sep, 1980 Nationality: Iranian Marital Status: Married E-mail: ehsan.soltani@gmail.com Mobile :(+98) - 912-1501764 CAREER BRIEF: Having over 15 Years Work Experience in Iran

More information

Siemens PLM Software. NX for shipbuilding. An integrated environment for design, planning and manufacturing. siemens.com/nx

Siemens PLM Software. NX for shipbuilding. An integrated environment for design, planning and manufacturing. siemens.com/nx Siemens PLM Software NX for shipbuilding An integrated environment for design, planning and manufacturing siemens.com/nx 2 Shipbuilders are being called upon to improve their designs to be more energy-efficient,

More information

Capital Projects Group Testing, Adjusting and Balancing Specification

Capital Projects Group Testing, Adjusting and Balancing Specification Capital Projects Group Testing, Adjusting and Balancing Specification Specification 20 05 50 Revision 0 Date: August 2018 Testing, Adjusting and Balancing Specification Specification 20 05 50 Publication

More information

REPORT ON THE BENEFITS OF ICE- BASED THERMAL STORAGE FOR DISTRICT COOLING IN THE UAE MARKETS

REPORT ON THE BENEFITS OF ICE- BASED THERMAL STORAGE FOR DISTRICT COOLING IN THE UAE MARKETS REPORT ON THE BENEFITS OF ICE- BASED THERMAL STORAGE FOR DISTRICT COOLING IN THE UAE MARKETS Prepared by: Brady Consulting Services, Inc. SUMMARY ADVANTAGES OF THERMAL STORAGE WITH 1.1ºC WATER SUPPLY 1)

More information

Proposal: Mechanical System Redesign

Proposal: Mechanical System Redesign Proposal: Mechanical System Redesign The 959 Eighth Avenue 10019 Faculty Advisor: Dr. James Freihaut December 12, 2005 Table of Contents 1.0 Executive Summary 2.0 3.0 Proposal Obectives 4.0 Preliminary

More information

Thesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin

Thesis Proposal. Clemson University Advanced Material Research Laboratory Anderson, SC. David Anderson Mechanical Option. Photo by Fred Martin Thesis Proposal Photo by Fred Martin Clemson University Advanced Material Research Laboratory Anderson, SC David Anderson Mechanical Option Friday, December 15, 2006 Table of Contents 1. Executive Summary

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

SECTION AIR TERMINAL UNITS

SECTION AIR TERMINAL UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

Thule Prototype BIM Manual for Dormitories. February 5, 2010

Thule Prototype BIM Manual for Dormitories. February 5, 2010 Thule Prototype BIM Manual for Dormitories February 5, 2010 TABLE OF CONTENTS INTRODUCTION Executive Summary 2 Goals 2 Scope and Use 2-4 Program Assumptions Kit of Parts GUIDELINE INTEGRATION Site Design

More information

Ducts in Conditioned Space High Performance Attics

Ducts in Conditioned Space High Performance Attics 2016 Title 24 Codes & Standards Enhancement (CASE) Proposal Ducts in Conditioned Space High Performance Attics May 8, 2014 Matt Christie (TRC) Abhijeet Pande (TRC) Stakeholder Meeting: Agenda Code change

More information

MINISTRY OF CULTURE, GENDER, ENTERTAINMENT AND SPORT JAMAICA NATIONAL HERITAGE TRUST TERMS OF REFERENCE

MINISTRY OF CULTURE, GENDER, ENTERTAINMENT AND SPORT JAMAICA NATIONAL HERITAGE TRUST TERMS OF REFERENCE MINISTRY OF CULTURE, GENDER, ENTERTAINMENT AND SPORT JAMAICA NATIONAL HERITAGE TRUST TERMS OF REFERENCE CONSULTANCY: ENGINEER FOR PROJECT TO DESIGN AIR CONDITION SYSTEM, PROCURE WORKS FOR SUPPLY AND INSTALLATION

More information

Colorado Mountain College: Sustainable Design Standards

Colorado Mountain College: Sustainable Design Standards Colorado Mountain College: Sustainable Design Standards Objective: Design and build to the highest energy and water standards in order to meet the College s Carbon Neutrality Objective in the most cost-effective

More information

Baffled Openings at Chain Link Fencing: Design shall consist of two end-posts set 4 feet apart, and a 10 foot wide chain-link fence panel equal in height as the adjacent fence. Chain link fence panel shall

More information

WINERY ENERGY SAVER TOOLKIT SUPPLIER CHECKLIST COMPRESSED AIR

WINERY ENERGY SAVER TOOLKIT SUPPLIER CHECKLIST COMPRESSED AIR Supplier Checklist WINERY ENERGY SAVER TOOLKIT SUPPLIER CHECKLIST COMPRESSED AIR The following checklist provides guidance on which information to collect from within the winery and from the equipment

More information

RECITALS TERMS AND CONDITIONS. The scope of work is contained in Exhibit A, attached hereto and incorporated herein.

RECITALS TERMS AND CONDITIONS. The scope of work is contained in Exhibit A, attached hereto and incorporated herein. FIFTH AMENDMENT TO MASTER CONTRACT FOR PROFESSIONAL SERVICES FOR WASTEWATER TREATMENT PLANT ENGINEERING FINAL DESIGN SERVICES FOR THE DURHAM ADVANCED WASTEWATER TREATMENT FACILITY PRIMARY TREATMENT AND

More information

Engineering Design & Power Training Institute

Engineering Design & Power Training Institute Engineering Design & Power Training Institute Recognition & Approvals Association of Power & Design Engineers (APDE) An ISO 9001: 2008 Certified Institute Courses P G Diploma in Piping Design & Details

More information

Element Z General Design Requirements Existing Facilities Information

Element Z General Design Requirements Existing Facilities Information Anderson Central 100B, PART 1 - INTRODUCTION 1.01 OVERVIEW A. This Section provides general information for building systems and components. B. Refer to the Owner s Design Guideline Elements A though G

More information

Terminal. 3 Las Vegas, NV

Terminal. 3 Las Vegas, NV McCarran International Airport Terminal 3 Thesiss Proposal Mechanical Systems Project Proposal December 18, 2007 Prepared By: Jason A. Witterman Faculty Advisor: Dr. William Bahnfleth, Ph.D., P..E. Table

More information

Kinetics Noise Control

Kinetics Noise Control Kinetics Noise Control Vibron Products Group Noise Control Products and Systems for HVAC, Industrial and Environmental Applications www.kineticsnoise.com/vibronproducts/ Commercial (HVAC) & Industrial

More information

HVAC SYSTEM SCHEMATIC DESIGN

HVAC SYSTEM SCHEMATIC DESIGN HVAC SYSTEM SCHEMATIC DESIGN Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 1 HVAC System Design Process Establish HVAC-related owner s project requirements (OPR: design issues/intents/criteria;

More information

Building Services Engineer (mechanical) model career pathway Version 1.0

Building Services Engineer (mechanical) model career pathway Version 1.0 April 2013 Building Services Engineer (mechanical) model career pathway Version 1.0 AIRAH Strategic aim #2 - Closing the skills gap Prepared by: The Australian Institute of Refrigeration Air Conditioning

More information

SPARTANBURG COUNTY BUILDING CODES DEPARTMENT

SPARTANBURG COUNTY BUILDING CODES DEPARTMENT SPARTANBURG COUNTY BUILDING CODES DEPARTMENT PLAN REVIEW CHECK LIST REQUIREMENTS FOR COMMERCIAL BUILDING PERMITS Plan Review Coordinator Kris Brannon 864-596-3180 366 N. Church St Room 500 Spartanburg,

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND STATE UNIVERSITY CONSTRUCTION FUND The following checklist show the general items required by the Agreement and the Program Directives. Unless included in the lump sum fee or the Schedule B of the Consultant

More information

Generic AEC/FM BIM View Specification Architectural Design to Spatial Program Validation

Generic AEC/FM BIM View Specification Architectural Design to Spatial Program Validation Generic AEC/FM BIM View Specification Architectural Design to Spatial Program Validation Reference GSA-001 Version 1.0 Status Final History Authors Document Owner Description Document created 1-Mar-06;

More information

2.3.6 Design Development

2.3.6 Design Development 2.3 Management of the Project 2.3.6 Design Development Canadian Handbook of Practice for Architects 2.3.6 Introduction Design Development Tasks Engineering Services for Design Development Structural Mechanical

More information

Space Conditioning System Airflow Rate

Space Conditioning System Airflow Rate (Page 1 of 3) A. Ducted Cooling System Information System Identification or Name 02 System Location or Area Served 03 System Installation Type 04 Nominal Cooling Capacity (tons) of Condenser 05 Condenser

More information

BID PACKAGES 3-21, Addendum No. 03

BID PACKAGES 3-21, Addendum No. 03 WEBER MURPHY FOX Addendum Date: January 23, 2018 Bid Due Date: January 26, 2018 BID PACKAGES 3-21, Addendum No. 03 to the Plans and Specifications for Cuyahoga Community College West Science and IT Labs

More information

Commercial Building Performance Evaluation System for HVAC Diagnostics and Commissioning

Commercial Building Performance Evaluation System for HVAC Diagnostics and Commissioning Commercial Building Performance Evaluation System for HVAC Diagnostics and Commissioning Stuart S. Waterbury and Donald J. Frey, Architectural Energy Corporation Karl F. Johnson, Electric Power Research

More information

Homesol Passive House Design Process

Homesol Passive House Design Process Homesol Passive House Design Process Passive Houses are residential, commercial and institutional buildings in which a comfortable temperature can be achieved year round with a 75% 85% reduction in energy

More information

Mechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion

Mechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion Mechanical Systems Redesign Proposal Thesis Proposal Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth December 12, 2014 Revised: January 16, 2015 Revised:

More information

Engineering Management Manual

Engineering Management Manual Engineering Management Manual Configuration Management ED0014 Document Category: DMS: Document Control: Procedure CRN-EPR-ENG-014 Version Date Author/discipline Reviewer Approver Remarks 1.0 13/12/2011

More information

City of Omaha Plans and Permits Commercial Alterations and Conversions Building Permit Submittal Checklist

City of Omaha Plans and Permits Commercial Alterations and Conversions Building Permit Submittal Checklist City of Omaha Plans and Permits Commercial Alterations and Conversions Building Permit Submittal Checklist This checklist contains the standard information required on submittals for commercial construction

More information

Chilled Beams. The new system of choice?

Chilled Beams. The new system of choice? Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams

More information

MSC Guidelines for Review of Ventilation System Plans

MSC Guidelines for Review of Ventilation System Plans K. B. FERRIE, CDR, Chief, Hull Division Purpose: This Plan Review Guideline (PRG) explains the requirements for seeking plan approval of ventilation systems from the Marine Safety Center (MSC) for most

More information

ANNEX A.1 TECHNICAL SPECIFICATIONS. Open Call for Tender. No F/SE/10/05. Provision of Building Inspection, Maintenance, Alteration and Repair services

ANNEX A.1 TECHNICAL SPECIFICATIONS. Open Call for Tender. No F/SE/10/05. Provision of Building Inspection, Maintenance, Alteration and Repair services ANNEX A.1 TECHNICAL SPECIFICATIONS Open Call for Tender No F/SE/10/05 Provision of Building Inspection, Maintenance, Alteration and Repair services Building Inspection, Maintenance, Alteration and Repair

More information

European KEYMARK Scheme

European KEYMARK Scheme European KEYMARK Scheme Heat Pumps Revision Number: 2 (2017-03-10) Page: 2 of 12 Date Description of modification Revision number 01/05/2016 Initial version 1.1 10/03/2017 Addition of air/air product Editorial

More information

MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE

MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE ROYAL BOROUGH OF GREENWICH MECHANICAL & ELECTRICAL ENGINEER S SERVICES SCOPE PROJECT xxx status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: role: signed:

More information

Advanced Ventilation Technologies

Advanced Ventilation Technologies Building Advanced Ventilation Technological examples to demonstrate materialised energy savings for acceptable indoor air quality and thermal comfort in different European climatic regions. Advanced Ventilation

More information

CONSTRUCTION REQUIREMENTS

CONSTRUCTION REQUIREMENTS CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary

More information

CSIRO Energy Centre Newcastle, New South Wales, Australia

CSIRO Energy Centre Newcastle, New South Wales, Australia CSIRO Energy Centre Newcastle, New South Wales, Australia Trevor Moody BE, BEc Commonwealth Scientific and Industrial Research Organisation (CSIRO), Australia. PO Box 227 Dickson ACT 2602 Australia. Telephone:

More information

THERMAL AND RELATIVE HUMIDITY MAPPING OF A SAMPLING ROOM

THERMAL AND RELATIVE HUMIDITY MAPPING OF A SAMPLING ROOM WORLD JOURNAL OF PHARMACY AND PHARMACEUTICAL SCIENCES Gangadharappa et al. SJIF Impact Factor 6.041 Volume 5, Issue 4, 1563-1572 Research Article ISSN 2278 4357 THERMAL AND RELATIVE HUMIDITY MAPPING OF

More information

Achieving acoustical standards in the classroom Study of HVAC systems and classroom acoustics

Achieving acoustical standards in the classroom Study of HVAC systems and classroom acoustics Achieving acoustical standards in the classroom Study of HVAC systems and classroom acoustics Trane believes the facts and suggestions presented here to be accurate. However, final design and application

More information

CFD ANALYSIS OF CONVECTIVE FLOW IN A SOLAR DOMESTIC HOT WATER STORAGE TANK

CFD ANALYSIS OF CONVECTIVE FLOW IN A SOLAR DOMESTIC HOT WATER STORAGE TANK International Journal of Scientific & Engineering Research Volume 4, Issue 1, January-2013 1 CFD ANALYSIS OF CONVECTIVE FLOW IN A SOLAR DOMESTIC HOT WATER STORAGE TANK Mr. Mainak Bhaumik M.E. (Thermal

More information

BSc. BE & CM Courses Brief Description

BSc. BE & CM Courses Brief Description BSc. BE & CM Courses Brief Description 2801010-BUILDING MATERIALS, (3, 0, 0: 3) This course will cover the engineering properties of basic and modern building materials to materials such as plastics, synthetic

More information

1. How the research adds to the understanding of the area investigated

1. How the research adds to the understanding of the area investigated Final Scientific/Technical Report Project Title: CID #: Recipient: Eagan Civic Arena DE-EE0002807 Cherryl Mesko City of Eagan Minnesota 3830 Pilot Knob Road Eagan, MN 55122 cmesko@cityofeagan.com 651-675-5505

More information

Construction Engineering Research Laboratory. Ontology for Life-Cycle Modeling of Heating, Ventilating, and Air Conditioning (HVAC) Systems

Construction Engineering Research Laboratory. Ontology for Life-Cycle Modeling of Heating, Ventilating, and Air Conditioning (HVAC) Systems ERDC/CERL CR-12-2 Ontology for Life-Cycle Modeling of Heating, Ventilating, and Air Conditioning (HVAC) Systems Model View Definition Hitchcock Consulting 6049 Shoo Fly Road Kelsey, CA 95667 March 2012

More information

Sample Duct Design. Prepared by Victor Carroll: 7401 Alabama St. Louis, MO

Sample Duct Design. Prepared by Victor Carroll: 7401 Alabama St. Louis, MO Sample Duct Design Prepared by Victor Carroll: 7401 Alabama St. Louis, MO. 63111 800-527-0896 victor@unicosystem.com www.unicosystem.com/yourplans -Page 2 DISCLAIMER The attached sizing and layout design

More information

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 Page 1 Page 2 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) ROLES AND RESPONSIBILITIES The CLIENT must: 1. Be satisfied that all

More information

European KEYMARK Scheme

European KEYMARK Scheme European KEYMARK Scheme Heat Pumps Revision Number: 3 (2017-09-12) Page: 2 of 12 Date Description of modification Revision number 01/05/2016 Initial version 1.1 10/03/2017 Addition of air/air product Editorial

More information

SIMULATION VERSUS REALITY 4 CASE STUDIES. Anthony Calderone Aurecon, Melbourne, Australia

SIMULATION VERSUS REALITY 4 CASE STUDIES. Anthony Calderone Aurecon, Melbourne, Australia SIMULATION VERSUS REALITY 4 CASE STUDIES Anthony Calderone Aurecon, Melbourne, Australia calderonea@ap.aurecongroup.com ABSTRACT This paper will focus on four completed projects that have gone through

More information

Quality Assurance for Systems Engineering (INSE 6280/2-WW)

Quality Assurance for Systems Engineering (INSE 6280/2-WW) Course Outline Quality Assurance for Systems (INSE 6280/2-WW) Preliminary Notions Systems Life Cycle Processes Course Project 2 Instructor: Dr. J. Bentahar Office: EV007.630 Lectures: Thursday, 17h45 20h15

More information

Energy modeling in IDA ICE according to ASHRAE , app. G

Energy modeling in IDA ICE according to ASHRAE , app. G Energy modeling in IDA ICE according to ASHRAE 90.1-2007, app. G About this document This document is a user s guide for a relatively experienced IDA ICE operator for using the 90.1 add-in and for performing

More information

System Engineering. Instructor: Dr. Jerry Gao

System Engineering. Instructor: Dr. Jerry Gao System Engineering Instructor: Dr. Jerry Gao System Engineering - System Engineering Hierarchy - System Modeling - Information Engineering: An Overview - Product Engineering: An Overview - Information

More information

Ground-Coupled Heat Pump And Energy Storage

Ground-Coupled Heat Pump And Energy Storage Ground-Coupled Heat Pump And Energy Storage By Ed Lohrenz, Member ASHRAE; and Sergio Almeida, P.Eng., Member ASHRAE Ground-coupled heat pump (GCHP) systems consume less purchased energy than an HVAC system

More information

(PROJECT STANDARDS AND SPECIFICATIONS)

(PROJECT STANDARDS AND SPECIFICATIONS) Page : 1 of 19 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia DESIGN AND PROJECT EXECUTION TABLE

More information

New Suggestions for Centrifugal Chiller Technologies to Realize High Efficiency and High Functionality

New Suggestions for Centrifugal Chiller Technologies to Realize High Efficiency and High Functionality 38 New Suggestions for Centrifugal Chiller Technologies to Realize High Efficiency and High Functionality YASUSHI HASEGAWA *1 MASAHARU NITTA *1 KAZUKI WAJIMA *1 KENJI UEDA *2 The efficiency and functionality

More information

EXPERIMENTAL AND NUMERICAL STUDY OF SMOKE CONDITIONS IN AN ATRIUM WITH MECHANICAL EXHAUST

EXPERIMENTAL AND NUMERICAL STUDY OF SMOKE CONDITIONS IN AN ATRIUM WITH MECHANICAL EXHAUST , Volume 1, Number 3, p.183-187, 1999 EXPERIMENTAL AND NUMERICAL STUDY OF SMOKE CONDITIONS IN AN ATRIUM WITH MECHANICAL EXHAUST G.V. Hadjisophocleous and G. Lougheed Fire Risk Management Program, Institute

More information

HYDROCARBON REFRIGERANT CONVERSION REPORT FOR CITIBANK HOUSE 37 ST. GEORGES TERRACE PERTH, W.A.

HYDROCARBON REFRIGERANT CONVERSION REPORT FOR CITIBANK HOUSE 37 ST. GEORGES TERRACE PERTH, W.A. HYDROCARBON REFRIGERANT CONVERSION REPORT FOR CITIBANK HOUSE 37 ST. GEORGES TERRACE PERTH, W.A. Prepared by: MR SELWYN WALLACE ENGAS AUSTRALASIA DR LADAS TAYLOR ENGAS AUSTRALASIA INITIAL INSPECTION OF

More information

SOLAR COOLING WITH SMALL SIZE CHILLER: STATE OF THE ART

SOLAR COOLING WITH SMALL SIZE CHILLER: STATE OF THE ART SOLAR COOLING WITH SMALL SIZE CHILLER: STATE OF THE ART F. Asdrubali, G. Baldinelli, A. Presciutti University of Perugia (Italy) - Industrial Engineering Department 14 th European Conference - Renewable

More information

Aalborg Universitet. CLIMA proceedings of the 12th REHVA World Congress Heiselberg, Per Kvols. Publication date: 2016

Aalborg Universitet. CLIMA proceedings of the 12th REHVA World Congress Heiselberg, Per Kvols. Publication date: 2016 Aalborg Universitet CLIMA 2016 - proceedings of the 12th REHVA World Congress Heiselberg, Per Kvols Publication date: 2016 Document Version Publisher's PDF, also known as Version of record Link to publication

More information

10 Thorough examination and test

10 Thorough examination and test 10 Thorough examination and test Key points Every employer s LEV system requires statutory thorough examination and testing by a competent person. The examination and testing report should have a prioritised

More information

Energy Savers: Air-Source Heat Pumps

Energy Savers: Air-Source Heat Pumps 1 of 5 4/25/2009 8:55 AM U.S. Department of Energy - Energy Efficiency and Renewable Energy Energy Savers Air-Source Heat Pumps An air-source heat pump can provide efficient heating and cooling for your

More information

SEISMIC EXPECTATIONS

SEISMIC EXPECTATIONS SEISMIC EXPECTATIONS John Callea Manager Professional & Advisory Services Department Planning, Transport & Infrastructure What tonight's about, Earthquake Risk DPTI Expectations Seismic Compliance Ministers

More information

European KEYMARK Scheme

European KEYMARK Scheme European KEYMARK Scheme Heat Pumps Revision Number: 4 (07/03/2018) Page: 2 of 12 Date Description of modification Revision number 01/05/2016 Initial version 1.1 10/03/2017 Addition of air/air product Editorial

More information

Easy. Safe. Simple. Access for Maintenance to Cooling Towers

Easy. Safe. Simple. Access for Maintenance to Cooling Towers Easy. Safe. Simple. Access for Maintenance to Cooling Towers Paul Davies Representing Clint Lewis Representing Introduction Types of Cooling Towers typically offered in the HVAC Industry Overview of Cooling

More information

HVAC SYSTEM DESIGN PROCESS

HVAC SYSTEM DESIGN PROCESS HVAC SYSTEM DESIGN PROCESS Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Summer 2011 Grondzik 1 HVAC System Design Process Establish design intents/criteria (including code/standard compliance) Establish

More information

GAUTENG DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT

GAUTENG DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT GAUTENG DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT HVAC FOR ABSA Building OCTOBER 2014 Report for Gauteng Department of Infrastructure Development HVAC Services Preliminary Report:

More information

Passiv Haus Institut. Certification as "Quality Approved Passive House" Criteria for Non-Residential Passive House Buildings

Passiv Haus Institut. Certification as Quality Approved Passive House Criteria for Non-Residential Passive House Buildings Passiv Haus Institut Dr. Wolfgang Feist Rheinstr. 44/46 D-64283 Darmstadt www.passiv.de Certification as "Quality Approved Passive House" Criteria for Non-Residential Passive House Buildings Passive Houses

More information

Higher National Unit Specification. General information for centres. Building Services: An Introduction. Unit code: DW4P 33

Higher National Unit Specification. General information for centres. Building Services: An Introduction. Unit code: DW4P 33 Higher National Unit Specification General information for centres Unit title: Building Services: An Introduction Unit code: DW4P 33 Unit purpose: This Unit seeks to provide the candidate with knowledge

More information

Noise Control. Commercial, Industrial, and Environmental Products and Solutions.

Noise Control. Commercial, Industrial, and Environmental Products and Solutions. Noise Control Commercial, Industrial, and Environmental Products and Solutions www.kineticsnoise.com Commercial Duct Silencers Kinetics Noise Control offers the design and engineering assistance to integrate

More information

Retro-commissioning and on-going commissioning 23 November 2016

Retro-commissioning and on-going commissioning 23 November 2016 Retro-commissioning and on-going commissioning 23 November 2016 1 CONTENTS 1. Needs for Retro-Commissioning (RCx) 2. Retro-Commissioning (RCx) Definition and Scope 3. Briefing of RCx Process 4. Alternative

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

Thermodynamics: An Engineering Approach, 6 th Edition Yunus A. Cengel, Michael A. Boles McGraw-Hill, 2008

Thermodynamics: An Engineering Approach, 6 th Edition Yunus A. Cengel, Michael A. Boles McGraw-Hill, 2008 Thermodynamics: An Engineering Approach, 6 th Edition Yunus A. Cengel, Michael A. Boles McGraw-Hill, 2008 Chapter 5 MASS AND ENERGY ANALYSIS OF CONTROL VOLUMES SUMMARY 1 CONSERVATION OF MASS Conservation

More information

Trane Water-Source Variable Refrigerant Flow

Trane Water-Source Variable Refrigerant Flow Trane Water-Source Variable Refrigerant Flow Trane Water-Source Variable Refrigerant Flow Energy Efficiency Meets Expertise TRANE IS THE GLOBAL LEADER IN HVAC EQUIPMENT, SYSTEMS, AND SERVICES, PROVIDING

More information

ILEVE Institute of Local Exhaust Ventilation Engineers

ILEVE Institute of Local Exhaust Ventilation Engineers ILEVE Institute of Local Exhaust Ventilation Engineers Presenter Jane Bastow CMIOSH MILEVE ILEVE has been established to promote competence in the practical application of local exhaust ventilation. Competence

More information

High Technology Energy Savings Guide

High Technology Energy Savings Guide High Technology Energy Savings Guide The high-tech industry is a crucial and dynamic part of Oregon s economy that is expected to grow faster than other industries over the next decade. Working in a highly

More information

Capturing the Stakeholder Values of a Construction Project

Capturing the Stakeholder Values of a Construction Project Capturing the Stakeholder Values of a Construction Project Ken Dooley Sustainability Consultant Olof Granlund Oy Finland ken.dooley @granlund.fi Piia Sormunen Manager, Energy and Environment Olof Granlund

More information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes

More information

TELECOMMUNICATIONS ROOMS. Table of Contents PART 1 GENERAL 2 A. LOCATION: 2 B. SIZE 2 C. STRUCTURAL 3 D. ENVIRONMENTAL 3 E. ELECTRICAL AND LIGHTING 3

TELECOMMUNICATIONS ROOMS. Table of Contents PART 1 GENERAL 2 A. LOCATION: 2 B. SIZE 2 C. STRUCTURAL 3 D. ENVIRONMENTAL 3 E. ELECTRICAL AND LIGHTING 3 UNIVERSITY CONTACT: Network Services (302) 831-3722 TELECOMMUNICATIONS ROOMS Table of Contents PART 1 GENERAL 2 A. LOCATION: 2 B. SIZE 2 C. STRUCTURAL 3 D. ENVIRONMENTAL 3 E. ELECTRICAL AND LIGHTING 3

More information