TRACK TOLERANCES NEETHU NARAYANAN B060128CE MURSHID B060471CE

Size: px
Start display at page:

Download "TRACK TOLERANCES NEETHU NARAYANAN B060128CE MURSHID B060471CE"

Transcription

1 TRACK TOLERANCES NEETHU NARAYANAN B060128CE MURSHID B060471CE 1

2 Introduction The safety and comfort of rail travel depend primarily on the track geometry and the standard to which it has been maintained. Parameters governing the track geometry have always certain variations due to various reasons. Track tolerance: - may be defined as the limit of variability of various parameters pertaining to track geometry. 2

3 TRACK PARAMETERS The tolerances are generally laid down for following track parameters, 1) Gauge variation: this is measured as deviation from nominal gauge which is 1676 mm for B.G. and 1000 mm for M.G. Gauge is measured as the minimum distance between running faces of two rails. 3

4 2) Unevenness: this is measured in terms of difference in the longitudinal levels over a fixed base. Unevenness is generally measured over a base of 3.5 meters of length and for left and right rails separately. 4

5 3) Cross level difference: this is measured in terms of relative difference in the level of two rail tops measured at the same point. Cross level difference also includes the variations in super elevation. If a1 and a2 are the absolute height of the 2 rails at the same point, then Cross level difference = a1- a2 5

6 4) Twist: this is measured in terms of change in cross levels per unit length of measurement. Twist is calculated by knowing the cross level difference between two points over a fixed base and dividing the cross level difference by the base length. This is normally denoted as mm/meter. 6

7 5) Alignment variation: this is measured in terms of variation in versines taken on successive chords of fixed length with overlaps of half chords. This is measured over a base of 7.5 meter length on left and right rail separately. *** versine = versed sine Versin (θ) = 1 cos (θ) 7

8 TOLERANCES UNDER LOADED OR FLOATING CONDITION The various parameters of track geometry can be measured under loaded or under floating( non load) condition. Normally there is not likely to be much difference in the measurement of gauge and alignment under loaded or floating condition. cross level, unevenness, and twist differ considerably when track is under loaded condition from the floating condition so the measurements of these parameters are taken under loaded condition. VALUE UNDER VALUE UNDER PARAMATERES FLOATING CONDITION LOADED CONDITION Cross levels 6 mm 10 mm Longitudinal levels 6 mm 12 mm Gauge G mm (G+1-1.5)mm Alignment A mm (A+1-1.5)mm 8

9 TYPE OF TRACK TOLERANCES -- different type of track tolerances are stipulated depending upon the purpose for which these are made. 1) SAFETY TOLERANCES: These are the limits of variations at which dangerous or unsafe conditions arise for the movement of the trains. Depends upon condition of track + type of vehicle, its riding characteristics and its maintenance standard. BUT. The factors governing the unsafe conditions are so variable and indeterminate that almost none of the railway systems in the world has laid down the safety tolerances. It is felt that the track has to deteriorate too much for reaching these unsafe limits. 9

10 2) SLOW DOWN TOLERANCES These are the tolerances which when reached call for slowing down of trains. It was considered that it is not necessary to fix these slow down tolerances for Indian railways in view of the past experience. but now slow down tolerances are fixed Investigations done by RDSO reveal that 4- wheeled wagon is the most critical rolling stock in empty condition. Depending upon the values of unevenness and twist the speed of 4 wheeler wagons should be reduced as per the table. Speed( Kmph) Peak value of unevenness on 3.6 m (mm) Peak value of twist on 3.6 m (mm)

11 3) SERVICE TOLERANCES OR GOOD RIDING TOLERANCES these are the tolerances to which the track parameters may vary any time during service. These tolerances are based on the acceptable limits of riding comfort in relation to the vehicles in use. SERVICE TOLERANCES FOR 120 KMPH ON B.G. 1. TRACK GAUGE: tolerance generally in isolated locations a) On straight track +6 mm mm b) On curves up to 4 o + 13 mm mm c) On curves > 4 o for introduction + 19 mm of high speeds. 11

12 SERVICE TOLERANCES Contd. 2. Unevenness measured under loaded condition on a 3.5 m base. tolerance generally in isolated locations a) On long term basis 6 mm 10 mm b) As an immediate measure 10 mm 15 mm 3. Twist measured under loaded condition on a 3.5 m base tolerance generally in isolated locations a) On straight and on curved 2 mm/m 3.5 mm/m b) track other than on transitions. 1 mm/m 2.1 mm/m 12

13 SERVICE TOLERANCES Contd. 4. Alignment measured as versine on 7.5 m chord tolerance generally in isolated locations a) On straight 5 mm 10 mm b) On curves 5 mm 7 mm 5. Cross level not specified on consideration that small but constant cross level difference do not matter much. 13

14 4) MAINTANANCE TOLERANCE These are the tolerances which are achieved immediately after the track is attended to. these tolerances depend upon the track structure, tools and equipment used, method of maintenance adopted, supervision available and such other factors. These tolerances are prescribed arbitrarily so that the results of maintenance can be assessed. The Tolerances laid down by Northern Railway Unevenness + or -2 mm over a 3.5 m base Alignment + 2 mm over a 7.5 m base Cross level + 2 mm 14

15 5) INDEX TOLERANCES these are the tolerances which when exceeded, would call for attention of maintenance units to undertake maintenance work. These are also called maintenance schedule tolerances. Index tolerances are somewhat lesser than the service tolerances. Eastern railway proposed that index tolerances should be kept at % of service tolerances. Parameter index tolerance a) Cross level 3 mm b) Alignment on 7.5 m base 3 mm c) Sleeper to sleeper variation in gauge 2 mm 15

16 TOLERANCES FOR TRACK LAID WITH NEW TRACK MATERIALS SL NO parameter location value 1 Gauge Straight BG curves<4 o, MG<6 o NG<14 o +-2mm -3 mm,1 mm 2 Cross level straight +- 3 mm 3 Packing % sleepers loose 4 Alignment Straight(10 m chord) Curves of radius 600 m & 20 m chord Curves of radius 600 m & 20 m chord +-2 mm +-5mm +-10 mm 5 Sleeper spacing mm 6 Joints (not square) On straights On curves mm mm.5*pitch of fish bolt holes 7 Low joints Not permitted 8 High joints mm 9 Expansion gaps mm 16

17 6) NEW TRACK TOLERANCES These are tolerances prescribed for laying the new track These are meant for testing the quality of the work done Northern Railway has laid down desirable standards on an experimental basis for track laid with new track Parameter length of chord standard deviation 1. Unevenness 3.6 m Unevenness 9.6 m Twist 3.6 m Alignment 7.2 m

18 RIDE INDEX Ride index is a value which will represent the riding comfort experienced by a passenger in a coach R.I. is calculated as, R.I.= x (b 3 x (f)/f)^0.1 R.I.= ride index b = acceleration in cm/s^2 f = frequency in cycles/s (f)= correction factor R.I Appreciation very good good satisfactory tolerable dangerous 18

19 Reference: * Indian Railway Track M.M. Agarwal 6 th Edition 19

20 THANK YOU 20

Request for Information (RFI) Concerning SPART

Request for Information (RFI) Concerning SPART RFI No. RITES/CO/RSD/SPART-RFI/261 Request for Information (RFI) Concerning SPART (DMU trainsets for accident relief application) (Total 11 Pages) September 2014 Rolling Stock Design RITES Limited (India)

More information

PlAsMA intelligent track MeAsUReMent simple system AccURAte RhoMbeRG RAil

PlAsMA intelligent track MeAsUReMent simple system AccURAte RhoMbeRG RAil PLASMA intelligent TRACK MEASUREMENT simple system ACCURATE RHOMBERG RAIL PLASMA: System with Precision simply intelligent PLASMA A TAILOR-MADE SOLUTION FOR RAILWAY SURVEYING Modern railway engineering

More information

MTM DESIGN PRACTICE NOTE USE OF GUARD RAILS

MTM DESIGN PRACTICE NOTE USE OF GUARD RAILS Approval Amendment Record Approval Date Version Description 24/08/2016 1 Initial issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6 Table of Contents 1. Purpose...

More information

Infrastructure Standards Committee / Industry Standards Coordination Committee DATE: 6 January 2015 / 21 January 2015 SUBJECT:

Infrastructure Standards Committee / Industry Standards Coordination Committee DATE: 6 January 2015 / 21 January 2015 SUBJECT: MEETING: Infrastructure Standards Committee / Industry Standards Coordination Committee DATE: 6 January 2015 / 21 January 2015 SUBJECT: SPONSOR: AUTHOR: Agenda item 2.6 TSI / RGS / Network Rail initial

More information

Technical Specifications for Manufacture and Supply of 60E2 Rail R260 Grade

Technical Specifications for Manufacture and Supply of 60E2 Rail R260 Grade ISRAEL RAILWAYS LTD INFRASTRUCTURE DIVISION TRACK AND RIGHT OF WAY DEPARTMENT Technical Specifications for Manufacture and Supply of 60E2 Rail R260 Grade No. E-01-0002 June 2011 CONTENTS 1. SCOPE 2 2.

More information

RRB TECHNICAL EXAM PAPER. Railway Engineering

RRB TECHNICAL EXAM PAPER. Railway Engineering RRB TECHNICAL EXAM PAPER Railway Engineering 1. The bent-up length of rail used in front of nose of crossing which help in channelising the train wheels in their proper routes are known as: (a) lead rail

More information

City of Regina Standard Construction Specification SECTION 2350 PLACEMENT OF ASPHALTIC CONCRETE SURFACE 1.0 GENERAL. 1.1 Scope

City of Regina Standard Construction Specification SECTION 2350 PLACEMENT OF ASPHALTIC CONCRETE SURFACE 1.0 GENERAL. 1.1 Scope 1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of placing asphaltic concrete to a compacted thickness conforming to the lines, grades, and cross-sections as shown on the plan or as designated

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING 1. Define Permanent way. 2. List out the elements

More information

System DFF 21. Highly elastic rail fastening for conventional rail and metro the optimum single support point for slab track

System DFF 21. Highly elastic rail fastening for conventional rail and metro the optimum single support point for slab track System DFF 21 Highly elastic rail fastening for conventional rail and metro the optimum single support point for slab track System DFF 21 Highly elastic rail fastening for conventional rail and metro the

More information

UNIT 1 QUESTION BANK. Part A

UNIT 1 QUESTION BANK. Part A QUESTION BANK UNIT 1 Part A 1. Why is railway track termed as permanent way? 2. What is coning of wheels? What is its purpose? 3. Define Creep of rail and mention its causes. 4. Distinguish between double

More information

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK UNIT 1 RAILWAY PLANNING PART A 1. Define Permanent way. 2. List out the elements

More information

REPORT OF EDUCATIONAL VISIT TO INDIAN RAILWAYS INSTITUE OF CIVIL ENGINEERIG PUNE

REPORT OF EDUCATIONAL VISIT TO INDIAN RAILWAYS INSTITUE OF CIVIL ENGINEERIG PUNE Visit to Indian railway institute of civil engineering Pune REPORT OF EDUCATIONAL VISIT TO INDIAN RAILWAYS INSTITUE OF CIVIL ENGINEERIG PUNE Class- TE (CIVIL) Date :-10 Sept. 2016 Time :- 9:30-2:00 Dr.D.Y.Patil

More information

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB)

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB) Rudolf Schilder Track Innovations by Austrian Railways (OEBB) Dr. Rudolf Schilder, former Head of Business Unit Railway Line and Station Management, OEBB-Infrastructure AG (Austrian Railways Infrastructure),

More information

The impact of the rail welds geometry on the noise in urban zones

The impact of the rail welds geometry on the noise in urban zones Urban Transport XII: Urban Transport and the Environment in the 21st Century 643 The impact of the rail welds geometry on the noise in urban zones S. Lakusic University of Zagreb, Faculty of Civil Engineering,

More information

Amberg Rail. The comprehensive solution for railway surveying. Why choose Amberg Rail surveying solutions?

Amberg Rail. The comprehensive solution for railway surveying. Why choose Amberg Rail surveying solutions? Amberg Rail The comprehensive solution for railway surveying Why choose Amberg Rail surveying solutions? Partnership Ease of use Scalability All-in-one Swiss quality AMBERG RAIL For all tasks in railway

More information

MEJA URJA NIGAM PVT. LIMITED

MEJA URJA NIGAM PVT. LIMITED MEJA URJA NIGAM PVT. LIMITED NAME OF WORK: TENDER AND CONTRACT DOCUMENT FOR Supply of PSC Sleepers, P-Way materials (except rails) including Points & Crossings, Laying and linking of track including Points

More information

EURAILSCOUT Inspection & Analysis

EURAILSCOUT Inspection & Analysis EURAILSCOUT Inspection & Analysis Your reliable partner to monitor the condition of the railway infrastructure INTRODUCTION To be able to ensure rail traffic safety and reliability, it is absolutely necessary

More information

RAILWAY, BRIDGE AND TUNNEL ENGINEERING

RAILWAY, BRIDGE AND TUNNEL ENGINEERING RAILWAY, BRIDGE AND TUNNEL ENGINEERING By Ketki B. Dalal (K. S. Rangwala) ` 350.00 BUY Edition : 2 nd Revised and Enlarged Edition : 2016 ISBN : 9789385039133 Size : 170 mm 240 mm Binding : Paperback Pages

More information

TRACK SPECIFICATION LOW PROFILE CONCRETE SLEEPERS

TRACK SPECIFICATION LOW PROFILE CONCRETE SLEEPERS Approval Amendment Record Approval Date Version Description 19/04/2013 1 Initial issue under MTM. 19/02/2014 2 Details for Train Stop sleepers added and figures updated 27/04/2015 3 Amended the design

More information

Use of Simulation in Railway Vehicle Acceptance Procedures

Use of Simulation in Railway Vehicle Acceptance Procedures Use of Simulation in Railway Vehicle Acceptance Procedures Javier Pérez & Paul Allen Bjorn Van Uem November 2004 Introduction Tests required for vehicle acceptance are expensive, complex and time consuming

More information

By Gorbel Inc. The Best in the Business is Better Than Ever!

By Gorbel Inc. The Best in the Business is Better Than Ever! By Gorbel Inc. The Best in the Business is Better Than Ever! Cleveland Tramrail by Gorbel: A Name Built on Quality Since 1977, Gorbel Inc. has specialized in overhead material handling solutions, providing

More information

GURU GHASIDAS VISHWAVIDYALAYA, BILASPUR (C.G.) INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING B.TECH

GURU GHASIDAS VISHWAVIDYALAYA, BILASPUR (C.G.) INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING B.TECH GURU GHASIDAS VISHWAVIDYALAYA, BILASPUR (C.G.) INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING B.TECH 3 rd YEAR, V th SEMESTER SUBJECT: TRANSPORTATION ENGINEERING-II COURSE CODE: 31CE05T MAXIMUM

More information

Characterization of Vertical and Lateral Wheel Loads

Characterization of Vertical and Lateral Wheel Loads Characterization of Vertical and Lateral Wheel Loads 2014 Committee 30 Meeting Orlando, PA 14 October 2014 Andrew Scheppe, Riley Edwards, Marcus Dersch Slide 2 Outline Method of Quantifying Loads Vertical

More information

Interpretive Article. 1 Introduction

Interpretive Article. 1 Introduction Interpretive Article Development of Low-maintenance Tracks Railway Track Structure Group Technical Center Research and Development Center JR East Group Kazuhiko Murao, Hirotaka Aihara The railway track

More information

Guide for the application of the INF TSI

Guide for the application of the INF TSI European Railway Agency According to Framework Mandate C(2010)2576 final of 29/04/2010 Reference in ERA: ERA/GUI/07-2011/INT Version in ERA: 3.00 Date: 14 December 2015 Document elaborated by Document

More information

1. The limiting value of super elevation of board gauge in Indian Railways is:

1. The limiting value of super elevation of board gauge in Indian Railways is: RRB JUNIOR ENGINEERS PRACTICE QUESTIONS Railway Engineering Exam Solved Questions: 1. The limiting value of super elevation of board gauge in Indian Railways is: (a) 16.50 cm (b) 30 cm (c) 15 cm (d) 10

More information

GRP System FX. The «all in one» railway surveying solution

GRP System FX. The «all in one» railway surveying solution GRP System FX The «all in one» railway surveying solution Rail traffic without limits New challenges for railway construction and operation Borders open, centres of economic activity spread, people and

More information

CENTRAL RAILWAY PROJECT. Appendix C - Maintenance Standards

CENTRAL RAILWAY PROJECT. Appendix C - Maintenance Standards CENTRAL RAILWAY PROJECT Appendix C - Maintenance Standards November 2017 Central Railway Project 2 / 39 INDEX 1. Maintenance Obligation... 4 2. Infrastructure Management... 5 2.1 General... 5 2.2 Network

More information

Flexbeam Guardrail Roadside Safety Barrier

Flexbeam Guardrail Roadside Safety Barrier Flexbeam Guardrail Roadside Safety Barrier Product Manual Release 09/15 www.ingalcivil.com.au Flexbeam Guardrail Roadside Safety Barrier 1.0 Introduction Roadside barriers have been developed over the

More information

A model for the life expectancy of railway switches and crossings for maintenance and renewal planning in asset management systems

A model for the life expectancy of railway switches and crossings for maintenance and renewal planning in asset management systems Computers in Railways XI 765 A model for the life expectancy of railway switches and crossings for maintenance and renewal planning in asset management systems W.-J. Zwanenburg EPFL: École Polytechnique

More information

The costing of rail transport is different from the costing of other commodities & services. It has many special features which create complex

The costing of rail transport is different from the costing of other commodities & services. It has many special features which create complex INTRODUCTION On Indian Railways the Traffic Costing was introduced in 1962. Since then methodologies for costing of Goods and Coaching Services have been developed. Traffic Costing is a continuous process

More information

Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances

Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances Uncontrolled When Printed Railway Group Standard Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances Synopsis This document mandates specific requirements and

More information

Switches and Crossings

Switches and Crossings Switches and Crossings Synopsis This document sets out general requirements for the design, inspection and maintenance of switches and crossings (S&C). It also defines particular requirements for fixed

More information

Draft. Not yet Approved. American Railway Engineering and Maintenance of Way Association Letter Ballot

Draft. Not yet Approved. American Railway Engineering and Maintenance of Way Association Letter Ballot American Railway Engineering and Maintenance of Way Association Letter Ballot 1. Committee and Subcommittee: Committee 4 Subcommittee 6 2. Letter Ballot Number: 04-17-03 3. Assignment: For Board Approval

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE 6604 - RAILWAYS AIRPORT AND HARBOUR ENGINEERING Regulation 2013 Academic Year

More information

DEPARTMENT: CIVIL ENGINEERING SEMESTER: III SUBJECT CODE / Name: CE2303/Railway, Airport and Harbor Engineering UNIT 1 TWO MARKS QUESTIONS AND ANSWERS

DEPARTMENT: CIVIL ENGINEERING SEMESTER: III SUBJECT CODE / Name: CE2303/Railway, Airport and Harbor Engineering UNIT 1 TWO MARKS QUESTIONS AND ANSWERS DEPARTMENT: CIVIL ENGINEERING SEMESTER: III SUBJECT CODE / Name: CE2303/Railway, Airport and Harbor Engineering UNIT 1 TWO MARKS QUESTIONS AND ANSWERS 1.What is meant by traffic survey The main aim of

More information

COST EFFECTIVE MEASURE FOR TRACK IMPROVEMENT. Phil Anderson and J. S. Mundrey

COST EFFECTIVE MEASURE FOR TRACK IMPROVEMENT. Phil Anderson and J. S. Mundrey Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK March 1995 Transport No. RW-11 COST EFFECTIVE MEASURE FOR TRACK IMPROVEMENT Phil Anderson and J. S. Mundrey Some developing

More information

MTST TRACK DESIGN AND CONSTRUCTION

MTST TRACK DESIGN AND CONSTRUCTION Engineering Standard Track and Civil Version: 2 Issued: November 2016 Owner: Chief Engineer Approved By: Phil Ellingworth Chief Engineer PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE

More information

S E C L TENDER NOTICE NO.RITES/GM/NGP/ T DATED 22/04/2014

S E C L TENDER NOTICE NO.RITES/GM/NGP/ T DATED 22/04/2014 S E C L TENDER NOTICE NO.RITES/GM/NGP/ T-19-2014DATED 22/04/2014 Name of work: Complete Track renewal/ renovation and other improvement works atchirimiri Railway Siding in Chirimiri area of M/s SECL (C.G).

More information

Railway technology. PhD CE Jarosław Zwolski. 1. Technology of building a new line. 2. Track geometry measurement. 3. Maintenance and auxiliary works

Railway technology. PhD CE Jarosław Zwolski. 1. Technology of building a new line. 2. Track geometry measurement. 3. Maintenance and auxiliary works Railway technology 1. Technology of building a new line 2. Track geometry measurement 3. Maintenance and auxiliary works 4. Existing lines modernization PhD CE Jarosław Zwolski sleepers spacing rail ballast

More information

Signature of the tenderer

Signature of the tenderer PART 2 FINANCIAL BID SCHEDULE (BILL) OF QUANTITIES 2 PART 2 SCHEDULE (BILL) OF QUANTITIES (PERCENTAGE RATE TENDER) ABSTRACT OF COST (PERCENTAGE TO BE QUOTED BY THE BIDDER) SCHEDULE DESCRIPTION TOTAL ESTIMATED

More information

The impact of the geometry of rail welds on noise level in urban environments

The impact of the geometry of rail welds on noise level in urban environments The impact of the geometry of rail welds on noise level in urban environments Stjepan Lakusic (1), Roman Kecur (2) (1) University of Zagreb, Faculty of Civil Engineering, Kaciceva 26, Zagreb, Croatia (2)

More information

Guidance on Gauging. Withdrawn Document Uncontrolled When Printed. Signatures removed from electronic version

Guidance on Gauging. Withdrawn Document Uncontrolled When Printed. Signatures removed from electronic version Railway Group Guidance Note Guidance on Gauging Synopsis This Guidance Note forms a compendium of knowledge and advice relating to all aspects of gauging. Signatures removed from electronic version Submitted

More information

CROSSRAIL INFORMATION PAPER D10 GROUNDBORNE NOISE AND VIBRATION

CROSSRAIL INFORMATION PAPER D10 GROUNDBORNE NOISE AND VIBRATION CROSSRAIL INFORMATION PAPER GROUNDBORNE NOISE AND VIBRATION This paper explains the measures that will be put in place to control the effects of groundborne noise and vibration that might otherwise arise

More information

EN 14363:2016 A new and feasible way of homologating vehicles from a running dynamics point of view

EN 14363:2016 A new and feasible way of homologating vehicles from a running dynamics point of view EN 14363:2016 A new and feasible way of homologating vehicles from a running dynamics point of view - Mikael Wrang Presentation for the 19th Nordic Seminar on Railway Technology 14 September 2016 EN 14363

More information

STANDARD PRACTICE INSTRUCTION

STANDARD PRACTICE INSTRUCTION STANDARD PRACTICE INSTRUCTION DATE: March 1, 2001 SUBJECT: Scaffolding Safety Program. REGULATORY STANDARDS: 29 CFR 1910.28 Safety Requirements For Scaffolding. 29 CFR 1910.29 Manually Propelled Mobile

More information

1. Introduction. 2. Features of accelerating walkways

1. Introduction. 2. Features of accelerating walkways The accelerating walkway, which was developed by NKK, travels as slowly at the entrance as a conventional moving walkway (30 40 m/min), but then moves at its highest speed (54 72 m/min) in the middle of

More information

LINK 500 CONCEPT RAILTRACK LAYER. Making railway tracks easier, safer and faster to construct in emerging economies like India

LINK 500 CONCEPT RAILTRACK LAYER. Making railway tracks easier, safer and faster to construct in emerging economies like India LINK 500 CONCEPT RAILTRACK LAYER Making railway tracks easier, safer and faster to construct in emerging economies like India Indian Railways has grown 10-fold in the last 50 years, but rail track length

More information

A study on the prediction of the noise reduction performance according to applying the rail web-damper in curved track section

A study on the prediction of the noise reduction performance according to applying the rail web-damper in curved track section A study on the prediction of the noise reduction performance according to applying the rail web-damper in curved track section Jinho KIM 1 1 Korea Railroad Research Institute, Korea ABSTRACT This research

More information

tracks for building maintenance units (BMU)

tracks for building maintenance units (BMU) 1/11 A track at roof level is required to allow the machine to traverse. Two different types of track may be considered: one in concrete and the other with two metal rails. 1. Concrete track During the

More information

Dynamic Axle Loads as a Main Source of Railway Track Degradation

Dynamic Axle Loads as a Main Source of Railway Track Degradation Geotechnical Safety and Risk V T. Schweckendiek et al. (Eds.) 2015 The authors and IOS Press. This article is published online with Open Access by IOS Press and distributed under the terms of the Creative

More information

ONRSR Guideline. Road/Rail Vehicle Management & Operations

ONRSR Guideline. Road/Rail Vehicle Management & Operations Document control Objective Document ID: A444000 Version number: 1.2 Approved by: Format review Date approved: December 2017 Guideline changes to 1.2 Minor formatting Office of the National Rail Safety

More information

Corrugation Study KELTRACK Trackside Transit

Corrugation Study KELTRACK Trackside Transit Corrugation Study KELTRACK Trackside Transit Evaluation of KELTRACK Trackside Friction Modifier on Rail Corrugation Mitigation at Merseyrail, Liverpool, UK. Author: Neil Harvey. Issue Date: 30 th September,

More information

Uncontrolled When Printed Superseded by GEGN8573 Iss 4 on 05/03/2016

Uncontrolled When Printed Superseded by GEGN8573 Iss 4 on 05/03/2016 GN This document contains guidance that is amended under the Railway Group Standards Code (Issue Three) as a small scale change. Reference to the amended section is made in the Issue record. All other

More information

DEVELOPMENT OF PROVISIONS COVERING INFRASTRUCTURE

DEVELOPMENT OF PROVISIONS COVERING INFRASTRUCTURE Commission d experts techniques Fachausschuss für technische Fragen Committee of Technical Experts TECH-17045-WGT34-5c 17.01.2018 Version 2 Original: EN DEVELOPMENT OF PROVISIONS COVERING INFRASTRUCTURE

More information

FOR SINGRAULI (M.P.) LIMITED. RITES LIMITED Enterprise) OFFICE, Tender. Name of Tenderer Address of Tendererr

FOR SINGRAULI (M.P.) LIMITED. RITES LIMITED Enterprise) OFFICE, Tender. Name of Tenderer Address of Tendererr NORTHERN COALFIELDS LIMITED TENDER AND CONTRACT DOCUMENT FOR NAME OF WORK: COMPLETE TRACK RENEWAL OF SPUR SIDING, NCL, SINGRAULI (M.P.) TENDER NO. : - RITES/RPO-LKO/ /5925/NCL/CTR-SPURR PART 2 FINANCIAL

More information

MTSP MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS

MTSP MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS Engineering Specification Track MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS Version: 2 Issued: December 2015 Owner: Engineering Division Approved By: Liam Palmer Cannon A/Head of Engineering Track

More information

INTORODUCTION BRIDGE:

INTORODUCTION BRIDGE: INTORODUCTION Transportation systems are backbone for the development of any country. There are mainly three type of surface transport system. Road Transportation system and Railway transportation system

More information

Platforms, track & trains

Platforms, track & trains Platforms, track & trains Neil Gofton March 2018 Image: Extract from 'Requirements for Passenger Lines and Recommendations for Goods Lines, Ministry of Transport, 1950 Topics to cover Platform X&Y Context

More information

EDDY CURRENT & RAIL MILLING 1 NEW TOOLS IN THE RAIL MANAGEMENT ENGINEER S BOX

EDDY CURRENT & RAIL MILLING 1 NEW TOOLS IN THE RAIL MANAGEMENT ENGINEER S BOX EDDY CURRENT & RAIL MILLING 1 NEW TOOLS IN THE RAIL MANAGEMENT ENGINEER S BOX Sorin L Castravete Senior Asset Engineer (Support) [Track] Route London North East, Network Rail, United Kingdom 1 Network

More information

SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS PREFACE

SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS PREFACE SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS Standard ADOPTED 1939; ADVANCED TO STANDARD, 1945. PREFACE The specifications have been prepared on the basis that they will be used

More information

LANH42 SQA Unit Code H52X 04 Install flexible flag surfaces

LANH42 SQA Unit Code H52X 04 Install flexible flag surfaces Overview This standard is one of six which covers installation of the various forms of hardstanding surfaces that are used within the landscaping industries. This standard is targeted at operatives working

More information

F2: INFRASTRUCTURE MAINTENANCE DEPOT STRATEGY

F2: INFRASTRUCTURE MAINTENANCE DEPOT STRATEGY HIGH SPEED TWO INFORMATION PAPER F2: INFRASTRUCTURE MAINTENANCE DEPOT STRATEGY This paper outlines the reasons for the proposed infrastructure maintenance depot strategy for HS2. It will be of particular

More information

Specification for Road Works Series Road Restraints Systems (Vehicle and Pedestrian)

Specification for Road Works Series Road Restraints Systems (Vehicle and Pedestrian) Specification for Road Works Series 400 - Road Restraints Systems (Vehicle and Pedestrian) CC-SPW-00400 March 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Turnouts and Yard Tracks TM 2.1.8 Prepared by: Signed document on file 21 June 09 George Harris Date Checked by: Signed document on file 15 July 09 Thomas Carroll Date Approved by:

More information

ESTIMATION OF ROLLING CONTACT FATIGUE IN RAILWAY VEHICLES

ESTIMATION OF ROLLING CONTACT FATIGUE IN RAILWAY VEHICLES Int. J. Mech. Eng. & Rob. Res. 2014 Goutam Nayak and Piyush Verma, 2014 Research Paper ISSN 2278 0149 www.ijmerr.com Special Issue, Vol. 1, No. 1, January 2014 National Conference on Recent Advances in

More information

Calculating the Contact Stress Resulting from Lateral Movement of the Wheel on Rail by Applying Hertz Theory

Calculating the Contact Stress Resulting from Lateral Movement of the Wheel on Rail by Applying Hertz Theory IJR International Journal of Railway Vol. 6, No. 4 / December 01, pp. 148-154 The Korean Society for Railway Calculating the Contact Stress Resulting from Lateral Movement of the Wheel on Rail by Applying

More information

The safety measures against deformation of the track

The safety measures against deformation of the track The safety measures against deformation of the track 1 2 1 2 S. Chang, K. Y. Chang, R. J. T. Chen & L.-C. Wang 1 China Engineering Consultants, Inc., Taiwan 2 Technology Dept. of Civil Engineer, National

More information

Key Words Longitudinal sleeper, Ladder sleeper, Ladder track, Ballasted track, Continuously welded rail, Track Buckling, Lateral stability

Key Words Longitudinal sleeper, Ladder sleeper, Ladder track, Ballasted track, Continuously welded rail, Track Buckling, Lateral stability Lateral Stability Analysis of Ladder Sleeper Track Systems By Ernest J. Barenberg Professor Emeritus-Civil Engineering University of Illinois 205 N. Mathews; Urbana, Illinois 61801, U.S.A. Tel. 217-333-6252;

More information

Analysis of Girder Bridge with IRC and IRS Loadings A Comparative Study

Analysis of Girder Bridge with IRC and IRS Loadings A Comparative Study Analysis of Girder Bridge with IRC and IRS Loadings A Comparative Study Abdul Rashid 1, P.Veerabhadra Rao 2 P.G. Student, Department of Civil Engineering, GVP College of Engineering (A), Visakhapatnam,

More information

Draft Indian Standard. GENERAL REQUIREMENTS FOR THE SUPPLY OF METALLURGICAL MATERIALS AND METALS INCLUDING STEEL (Third Revision of IS 1387)

Draft Indian Standard. GENERAL REQUIREMENTS FOR THE SUPPLY OF METALLURGICAL MATERIALS AND METALS INCLUDING STEEL (Third Revision of IS 1387) Doc: MTD 4(4669) For comments only Draft Indian Standard GENERAL REQUIREMENTS FOR THE SUPPLY OF METALLURGICAL MATERIALS AND METALS INCLUDING STEEL (Third Revision of IS 1387) ICS 77.140.01 ICS 77.150.01,

More information

NTPC Ltd. KORBA VOLUME-II (FINANACIAL BID) Consultants

NTPC Ltd. KORBA VOLUME-II (FINANACIAL BID) Consultants NTPC Ltd. KORBA OPEN TENDER NOTICE NO.RITES/GGM/NGP/T-07-2015, DATED 05.03.2015 Name of work: Earthwork in Drain Foundation, construction of minor bridges and RCC drain, P-Way works etc for the construction

More information

Guide for the application of the CR INF TSI

Guide for the application of the CR INF TSI European Railway Agency According to Framework Mandate C(2007)3371 final of 13/07/2007 Reference in ERA: ERA/GUI/07-2011/INT Version in ERA: 1. 00 Date: 26 August 2011 Document elaborated by Document Type:

More information

Special Specification 6148 Inverted Profile Pavement Marking (Audible)

Special Specification 6148 Inverted Profile Pavement Marking (Audible) Special Specification Inverted Profile Pavement Marking (Audible) 1. DESCRIPTION 2. MATERIALS Furnish and install an Inverted Profile Pavement Marking (Audible) that is hot applied to the pavement surface.

More information

Low Carbon Railways Zac : Sakdirat Kaewunruen

Low Carbon Railways Zac : Sakdirat Kaewunruen Low Carbon Railways Zac : Sakdirat Kaewunruen BE Hons (Civil), ME, PhD, GCert (Business) MIEAust, CPEng, NPER, RPEQ Senior Lecturer in Railway and Civil Engineering TRANSPORT CO 2 Kaewunruen et al. (2016)

More information

Uncontrolled When Printed

Uncontrolled When Printed Project title 09/003 - Review and Rationalisation of Gauging and Clearance Requirements 12/018 - Refine freight gauges and locomotive gauges in GE/RT8073 New and revised documents Document Document title

More information

Important: Before You Start

Important: Before You Start Advantage ICF System Advantage ICF System TM Field Guide Important: Before You Start Does Your Building Inspector Know You Are Building with the Advantage ICF System? You are required to check with your

More information

Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations

Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations 1 Metrolink Overview Commuter Railroad with Mixed Passenger and Freight Traffic 1. Most lines are former

More information

Transport policy, Horizon 2020 and rail research

Transport policy, Horizon 2020 and rail research Transport policy, Horizon 2020 and rail research European Commission Kick-off meeting of the IT2Rail, In2Rail and Roll2Rail projects, 7 May 2015 EU Policy context Regulatory Approaches (incl. technical

More information

Transportation Engineering -II Dr. Rajat Rastogi Department of Civil Engineering Indian Institute of Technology - Roorkee. Lecture - 11 Sleepers

Transportation Engineering -II Dr. Rajat Rastogi Department of Civil Engineering Indian Institute of Technology - Roorkee. Lecture - 11 Sleepers Transportation Engineering -II Dr. Rajat Rastogi Department of Civil Engineering Indian Institute of Technology - Roorkee Lecture - 11 Sleepers Dear students, I welcome you back to the course material

More information

Paving the way for increased safety. MULTIRAIL Technology. Measuring, checking, monitoring and sand filling.

Paving the way for increased safety. MULTIRAIL Technology. Measuring, checking, monitoring and sand filling. Paving the way for increased safety. MULTIRAIL Technology. Measuring, checking, monitoring and sand filling. A sign of our times: more and more people and materials need to reach their destinations faster

More information

Application note 5 Relationship of Yellow Book with European Directives

Application note 5 Relationship of Yellow Book with European Directives Railway Safety Management Yellow Book 4 Application note 5 Relationship of Yellow Book with European Directives Published by RSSB on behalf of the UK rail industry C:\Documents and Settings\djohnson\Desktop\KJWYBrelationshipwithEUDirectives.doc

More information

Bridge Deck Drainage

Bridge Deck Drainage Bridge Deck Drainage Introduction The presence of bridge barriers, curbs, and raised medians impedes the ability of rainfall runoff to drain off of bridge decks into ditch systems, as it does on a typical

More information

Flexible Pavement Preservation Treatment Construction Thin Functional and Maintenance Overlay Projects AT-TC3PP T1-JA01

Flexible Pavement Preservation Treatment Construction Thin Functional and Maintenance Overlay Projects AT-TC3PP T1-JA01 Suggested Field Considerations The following field considerations are a guide for the important aspects of planning a thin functional overlay project. Thorough answers to these questions should be determined

More information

Siting. Supporting the Chassis. Craning. Siting. Procedure

Siting. Supporting the Chassis. Craning. Siting. Procedure SITING Craning... 12 Siting... 12 Supporting the chassis... 12 Jacking... 13 Anchors... 16 Snow Loading... 16 Chassis Specification... 17 Typical support and holding down points... 18 Craning Given the

More information

MMM MASONRY, INC. Employee Safety Guidelines

MMM MASONRY, INC. Employee Safety Guidelines MMM MASONRY, INC. Employee Safety Guidelines This manual represents common hazards associated with masonry construction and is no way intended to replace the OSHA 29CFR 1926 Safety Standards. It is the

More information

the way to go. RheDa city ballastless TRack system

the way to go. RheDa city ballastless TRack system The way to go. RHEda City ballastless track system RHEDA CITY The city as living space An intelligent system of public transit is the nervous system of our cities. Costefficient and ecological solutions

More information

O&M MANUAL STANDARD FLOWPLATE PART NO NMFP - 03

O&M MANUAL STANDARD FLOWPLATE PART NO NMFP - 03 O&M MANUAL STANDARD FLOWPLATE PART NO NMFP - 03 STANDARD FLOW PLATE Standard Flow Plate Product Overview 366 A The standard flow plate is an ideal solution for smaller car parks with a low to medium yield

More information

STRAIL level crossing systems & STRAILastic track damping systems

STRAIL level crossing systems & STRAILastic track damping systems pontistrail - installation instructions Subject to technical changes / February 2010 STRAIL level crossing systems & STRAILastic track damping systems Gummiwerk KRAIBURG Elastik GmbH / D-84529 Tittmoning

More information

This is an uncontrolled copy. Before use, make sure that this is the current version by visiting NWT 304

This is an uncontrolled copy. Before use, make sure that this is the current version by visiting   NWT 304 Purpose General To prescribe the rules for authorising, issuing and using a (TOA). A TOA authorises occupancy of track within specified limits, for or track vehicle movements. A TOA may be authorised for:

More information

Effect of Physical Changes in Aging on Driving Performance

Effect of Physical Changes in Aging on Driving Performance University of Iowa Iowa Research Online Driving Assessment Conference 2001 Driving Assessment Conference Aug 15th, 12:00 AM Effect of Physical Changes in Aging on Driving Performance Hideaki Nemoto Nissan

More information

HC-Omega (Sinus Slide ) armour joints

HC-Omega (Sinus Slide ) armour joints HENGELHOEF CONCRETE JOINTS A new era in industrial flooring technology () armour joints Technical sheet Technical sheet joint page. 1 of 18 Table of Contents: Description... 3 Characteristics... 4 Product

More information

Quality Regulations for Sandwich Panels

Quality Regulations for Sandwich Panels Quality Regulations for Sandwich Panels October 2012 Quality Regulations for Sandwich Panels Page 2/19 Contents Preface... 3 1. Terms and Definitions... 4 1.1 Third parties... 4 1.2 Independent laboratories...

More information

Rail Transportation in Sub Saharan Africa. CC Africa Africa Rising Conference

Rail Transportation in Sub Saharan Africa. CC Africa Africa Rising Conference Rail Transportation in Sub Saharan Africa CC Africa Africa Rising Conference Name Derrick Lichti Date March 19, 2013 City Montreal Introduction Consultant with CPCS Infrastructure consultancy specializing

More information

Investigating railway track asset management using a Markov analysis

Investigating railway track asset management using a Markov analysis Original Article Investigating railway track asset management using a Markov analysis Proc IMechE Part F: J Rail and Rapid Transit 2015, Vol. 229(4) 402 416! IMechE 2013 Reprints and permissions: sagepub.co.uk/journalspermissions.nav

More information

A Stochastic Model for Railway Track Asset Management

A Stochastic Model for Railway Track Asset Management A Stochastic Model for Railway Track Asset Management John Andrews 1, Darren Prescott 1 and Florian De Rozières 2 1 - Nottingham Transportation Engineering Centre, University of Nottingham, UK, 2 - Grenoble

More information

SLAB TRACK PERFORMANCE UNDER HEAVY HAUL REVENUE CONDITION AND ITS REMEDIATION METHOD

SLAB TRACK PERFORMANCE UNDER HEAVY HAUL REVENUE CONDITION AND ITS REMEDIATION METHOD SLAB TRACK PERFORMANCE UNDER HEAVY HAUL REVENUE CONDITION AND ITS REMEDIATION METHOD Adrian Karsten Project Manager Australian Rail Track Corporation (ARTC), Hunter Valley Corridor, NSW, Australia Ralph

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 806 ASPHALT CONCRETE WITH JOINT DENSITY FOR MULTI-LANE HIGHWAYS March 2, 2015 806.01 Description 806.02 JMF Field Adjustments 806.03

More information

Chapter 4. Wheel Load Data Analysis

Chapter 4. Wheel Load Data Analysis Chapter 4 Wheel Load Data Analysis This chapter explains the methods used for analyzing the wheel load data. The analyses of the data in the time and frequency domains are addressed. The effects of various

More information

Withdrawn Document MARSHALLING AND COMPOSITION OF FREIGHT TRAINS. Contents

Withdrawn Document MARSHALLING AND COMPOSITION OF FREIGHT TRAINS. Contents Section B MARSHALLING AND COMPOSITION OF FREIGHT TRAINS Contents Page Latest Issue Contents B1 April 98 B1 Braking Requirements B2 April 98 B2 Brake Vans B3 April 98 B3 Braking Arrangements - Multi- B4

More information