1 Supplier Management of hago Automotive Corp. Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 1 of 13
2 Table of Contents Table of Contents... 2 Table of Figures... 3 Abbreviations Introduction Escalation Procedure Escalation Steps Escalation Step E Escalation Step E Escalation Step E Escalation Step E Escalation Step E Controlled Shipping Level (CSL) Program CSL CSL Q Discussions Supplier Assessment Supplier Assessment of Coil, ZKTL, and LB Purpose, Method, and Assessment Criteria Assessment Ability Quality Performance Reactions on Complaint Reports or Objections Delivery Reliability Customer Satisfaction Deductions Based on Escalation Steps Rating and Measures Supplier Assessment of Logistic Providers Purpose, Method, and Assessment Criteria Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 2 of 13
3 4.2.2 Assessment Ability Quality Performance Reaction on Complaint Reports or Objections Invoice Reports Customer Satisfaction Deductions Based on Escalation Steps Rating Table of Figures Figure 1: 3-Points Program... 4 Figure 2: Escalation Procedure... 5 Abbreviations Coil CSL FPM LB PPM ZKTL Coil and sheet metal Controlled shipping level Freights per million Subcontracting (German: Lohnbearbeitung) Parts per million Purchased parts (German: Zukaufteile) Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 3 of 13
4 Supplier Management 1 Introduction As a TS16949-certified certified company and supplier for the automotive industry, hago holds hold its suppliers to the highest standards. Hago strives to meet the requirements of its global customers. Ass a result, all hago suppliers must know, fulfill, and continuously work on furthering furt all automotive industry processes. The 3-Points Points Program of our Supplier Management helps to meet individual customer requirements, supports consistent verification, and encourages continuous improvement. Figure 1: 3-Points Program The individual points are discussed in more detail as follows follows. 2 Escalation Procedure Whenever a supplier-caused problem occurs, hago reacts by employing a uniform method that ensures that appropriate actions are taken within defined due dates. dat All scheduled actions are documented during the Q discussions held at the respective escalation level levels. Escalation steps can also be assigned to a supplier following a negative supplier assessment assessment. Depending on the severity of the problem, hago reserves the right to skip entire escalation steps. steps For example, a serious problem can be directly categorized as an E2 escalation step. In return, the introduction of suitable actions can lead to the direct downgrading from step E2 to E0. All support measures performed by hago or hago appoinappoi tees, which are part of the escalation scalation procedure, procedure will be invoiced to the supplier. Should a supplier reach the E2 escalation scalation step, step hago reserves the right to notify the certification agency in charge of the supplier s certification. The following escalation process applies to all process suppliers (raw materials, purchased parts parts, shippers, subcontractors, etc.). on (dd.mm.yy) by (Name) 24/11/2016 L. Bendel on (dd.mm.yy) by (Name) 24/11/2016 J. Blumenstock on (dd.mm.yy) by (Name) Change 9999/ / 00 4 of 13
5 Supplier Escalation Steps hago Management Escalation Step E4 Escalation Step E3 Discontinuation Control Change of Supplier Action Catalog New Business On Hold Q Discussions Purchasing Management, Purchasing, and Quality Manager Management Escalation Step E2 Supplier Development Program CSL 2 Purchasing and Quality Manager Quality Manager Quality Management Employee Escalation Step E1 Escalation Step E0 Action and Development Plan Q Discussions Action Plan CSL 1 Q Discussions Action Plan Quality Management Employee and Purchasing Quality Management Employee Figure 2: Escalation Procedure 2.1 Escalation Steps Escalation Step E0 Escalation step E0 means that the supplier has a problem, which must be resolved with an action plan. For example, a problem is recognized during an inspection of the incoming goods. As a result, hago s respective quality department will specify special inspections which must be performed on the shipments of the supplier. These inspections must be documented in inspection reports. The processing and remediation of the problem must be documented in an 8-D report. This report must be submitted to hago within a specified period. This standard procedure applies to every supplier. Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 5 of 13
6 2.1.2 Escalation Step E1 Escalation step E1 is assigned if the supplier-caused issues increase in frequency or if the action plans from escalation step E0 are only implemented effectively in part or not at all within the specified period. In this case, hago may prescribe the CSL 1 Program (see 2.2.1) by notifying the supplier s quality officer in writing. If shipping dates and/or shipping quantities are frequently no met, hago will impose the E1 escalation step on the respective supplier. If the supplier-implemented actions are effective, and if there are no further quality or delivery complaints within a predefined period, the supplier is downgraded in writing from step E1 to E Escalation Step E2 An E2 escalation step is assigned if the supplier continues to experience quality and/or shipping problems while categorized as an E1. Hago can impose the CSL 2 Program (see 2.2.2) on the supplier by notifying the supplier s management in writing. As part of the supplier development, hago and the supplier will draw up an action catalog. Should the agreed action plans prove effective, and if there are no further quality and/or delivery reliability complaints, the supplier is downgraded in writing from E2 to E Escalation Step E3 Ongoing quality and/or shipment issues, as well as a poor forecast based on an extended duration within the E2 escalation step, can lead to an E3 escalation. The supplier s management is alerted in writing of the imposed New Business on Hold status (SAP status E3, blocked for inquiries). The supplier s management must submit a binding and signed action catalog within one week illustrating possible actions for returning to step E2. New orders are also on hold if the QM system certificate has expired or become invalid. In this case, the supplier will not be informed in writing. Should the supplier not yet be in possession of a new certificate, he can provide a letter by the certification agency confirming the positive recertification outcome in substitution. The supplier can also be blocked from new orders if there is no evident active and cooperative problem-solving behavior from the supplier or if the supply guarantee is strongly at risk. A blocked status can only be canceled after hago reviews the effectiveness of the defined actions and notifies the supplier s management accordingly in writing Escalation Step E4 If the entire escalation process does not lead to an improvement of the delivery quality and/or schedule/quantity reliability, the blocked status remains and hago will initiate a supplier change. 2.2 Controlled Shipping Level (CSL) Program In line with the escalation steps, the CSL Program is employed to control the quality of the delivered goods over a specified period and/or quantity. The following CSL levels are possible CSL 1 In addition to the regular inspections, before shipping, the supplier must perform at his expense a 100% inspection pertaining to the material numbers and characteristics. Type and expense of the inspections must be coordinated with hago. The inspected shipments must be marked. The type of marking and documentation (characteristic and quantity of separated parts) must be coordinated with hago. Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 6 of 13
7 2.2.2 CSL 2 In addition to the regular inspections, prior to shipping, the supplier must order at his expense an external service provider to perform a 100% inspection pertaining to the material numbers and characteristics. The supplier must issue appropriate inspection/sorting instructions for the external service provider. These instructions must be in advance by hago. The inspected shipments must be marked. The type of marking and documentation (characteristic and quantity of separated parts) must be coordinated with hago. 3 Q Discussions Q discussions with the supplier can be held/scheduled at any time. They not only assist in coordinating and documenting the escalation process, but also serve to document the operative business. Q discussions may involve rolling meetings to improve cooperation, for pricing, etc. 4 Supplier Assessment Hago defines three types of supplier assessments: Assessments for steel suppliers (COIL), for purchased parts (ZKTL) and subcontractors (LB), and for shippers. PPM is only calculated for ZKTL/LB parts, but not for COIL materials. 4.1 Supplier Assessment of Coil, ZKTL, and LB Purpose, Method, and Assessment Criteria This method evaluates the ongoing ability, performance, and readiness of the supplier for continuous improvement. The following assessment forms the basis for continuing the cooperation. Criteria Weighting 2.1 Ability (valid management system) 10 % 2.2 Quality (number of complaints) 40 % 2.3 Reactions to complaints 20 % 2.4 Delivery reliability (quantity and adherence to delivery schedules) 25 % 2.5 Customer satisfaction (service, reaction in daily business) 5 % Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 7 of 13
8 4.1.2 Assessment Ability The proof of the ability of an implemented management system is significant for the supplier s evaluation. A maximum of 100% is possible. Management System* Maximum 100 % ISO 9001 or VDA 75 % TS % Hago/customer audits (ISO or TS16949 not implemented) A=90% B=80% C=70 % ISO in addition 5 % Signed Service Level Agreement in addition 10 % * Proof must be provided in the form of a certificate by a DAkks, EA, IAF or ELAC-registered certifier. If a valid certificate is not submitted, the supplier is assigned a E3 status (blocked for inquiries) Quality Performance Quality performance is based on the quantity of non-conformances found during incoming goods inspection or in production. Non-conformances are communicated to the supplier in form of a complaint report, and the PPM figure is calculated accordingly. The number of complaints is also reflected in the assessment. PPM is not calculated for COIL suppliers. COIL supplier assessments reflect only the quantity of complaints. Quantity rejected PPM: x 1 Mio. Quantity shipped Assessment of the PPM figure: Actual PPM 100 = Value => = x %(whereas a max. of 100% is possible) Target PPM Value The target PPM must be coordinated with Feinwerktechnik hago s purchasing department at the beginning of a year. If the supplier fails to do so, hago will prescribe the supplier s annual target PPM as part of the annual assessment. Number of Complaints: Number of Complaints Assessment 0 complaints 100 % 1 complaint 90 % 2-3 complaints 80 % 4-5 complaints (Q discussions when indicated) 60 % > 5 complaints (Q discussions and Business on Hold status) 0 % Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 8 of 13
9 The quality performance is based on the PPM evaluation and the number of complaints. Both are incorporated in equal parts into the assessment. PPM assessment + assessment of number of complaints = x % = quality performance Reactions on Complaint Reports or Objections The reaction of a supplier following a complaint (8D report) is essential for damage analysis and the definition of actions so that future errors can be eliminated. The assessment is performed as follows: Reaction (8D-Report) Maximum 100 % None or not within the defined due date 0 % Completed in full within the defined due date 100 % Delivery Reliability Delivery reliability involves the deviation of specified or confirmed delivery dates/quantities compared to the actual delivery dates/quantities. It is automatically calculated by the SAP system in equally weighted parts. Adherence to delivery schedules: +/-10% +/-15% +/-20% +/-30% +/-40% +/-50% +/-75% +/-99,9% 100% 95% 90% 80% 60% 40% 20% 1% Example: A delivery date deviation between 20% and 30 % results in a score of 80%. Adherence to quantity stipulated: +/-10% +/-15% +/-20% +/-30% +/-40% +/-50% +/-60% +/-70% +/-80% +/-99,9% 100% 90% 80% 60% 50% 40% 30% 20% 10% 1% Example: A quantity deviation between 20% and 30 % results in a score of 60% Customer Satisfaction Customer satisfaction evaluates the reaction of the supplier in daily business. Flexibility, reaction time, quotation behavior, communication behavior and feedback, etc. are all important factors. Supplier Behavior Maximum 100 % Spontaneous, flexible, and strongly proactive % Less spontaneous, yet still proactive % Reactive behavior, supplier must frequently be reminded or cautioned % Little or no reaction, supplier must be continuously cautioned or admonished 0 % Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / 00 9 of 13
10 4.1.3 Deductions Based on Escalation Steps If the supplier is entered into the escalation process and has an assigned E1 to E4 status, the following percentage points will be deducted from the total of the supplier s assessment result: E0 = 0 percentage points deducted E1 = 11 percentage points deducted E2 = 21 percentage points deducted E3 = 31 percentage points deducted E4 = No further assessment => Discontinuation Rating and Measures The supplier is rated based on the assessment of the above-mentioned criteria. The following divisions apply: in % Step Measures A B < 80 C If one criterion is < 90%, the supplier must take actions. The supplier is not required to notify hago of actions taken. However, hago can inquire about actions during an audit. The supplier must develop and implement a concrete action plan within 4 weeks and advise Hago accordingly. If the action plan is not received on time, the supplier is blocked for new orders until the action plan is submitted. As part of the assessment, the supplier will be invited to a Q discussion in the near future. This Q discussion is intended to define a concrete action plan as a requirement for requalification. During the meeting, it is decided if the supplier is blocked for new orders and whether hago must perform an audit as a further requirement for the approval process. The audit must have an outcome of 90 points. If an audit is not required, the supplier can be temporarily until the next quarterly assessment. The temporary approval must be justified in the Q discussion protocol. 4.2 Supplier Assessment of Logistic Providers Purpose, Method, and Assessment Criteria This method evaluates the ongoing ability, performance, and readiness of the supplier for continuous improvement. The following assessment forms the basis for continuing the cooperation. Criteria Weighting 2.1 Ability (valid management system) 10 % 2.2 Quality (freight per million (FPM), number of complaints) 50 % 2.3 Reactions to complaints 20 % 2.4 Invoice reports 10 % 2.5 Customer satisfaction (service, reactions in daily business) 10 % Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / of 13
11 4.2.2 Assessment Ability The ability proof of an implemented management system is essential for the assessment of the supplier. A maximum of 100% is possible. Management System* Maximum 100 % ISO 9001 or VDA 85 % Hago/customer audits (ISO or TS16949 not implemented) A=90% B=80% C=70 % ISO in addition 5 % Signed Service Level Agreement in addition 10 % * Proof must be provided in the form of a certificate by a DAkks, EA, IAF or ELAC-registered certifier. If a valid certificate is not submitted, the supplier is assigned a E3 status (blocked for inquiries) Quality Performance Quality performance is based on technical, logistical, or administrative errors involving the movement of goods. These are communicated to the supplier in the form of a complaint report, and the FPM figure is calculated accordingly. The number of complaints is also reflected in the assessment. Shipments objected FPM: x 1 Mio. Total of shipments Assessment of the FPM figure: Actual FPM 100 = Value => = x %(whereas a max. of 100% is possible) Target FPM Value The target FPM must be coordinated with Feinwerktechnik hago s purchasing department at the beginning of a year. If the supplier fails to do so, hago will prescribe the supplier s annual target FPM as part of the annual assessment. Number of complaints: Number complaints Assessment 0 complaints 100 % 1 complaint 90 % 2-3 complaints 80 % 4-5 complaints (Q discussions when indicated) 60 % > 5 complaints (Q discussions and Business on Hold status) 0 % Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / of 13
12 The quality performance is based on the FPM evaluation and the number of complaints. Both are incorporated in equal parts in the assessment. FPM assessment + assessment of number of complaints = x % = quality performance Reaction on Complaint Reports or Objections The reaction of a supplier following a complaint (8D report) is essential for damage analysis and the definition of actions so that future errors can be eliminated. The assessment is performed as follows: Reaction (8D-Report) Maximum 100 % None or not within the defined due date 0 % Completed in full within the defined due date 100 % Invoice Reports The value of the invoice reports is determined by their quantity with the following grading: Number of Invoice Reports Assessment 0 invoice reports 100 % 1 invoice report 90 % 2 invoice reports 80 % > 2 invoice reports 60 % Customer Satisfaction Customer satisfaction evaluates the reaction of the supplier in daily business. Flexibility, reaction time, quotation behavior, communication behavior and feedback, etc. are all important factors. Supplier Behavior Maximum 100 % Spontaneous, flexible, and strongly proactive % Less spontaneous, yet still proactive % Reactive behavior, supplier must frequently be reminded or cautioned % Little or no reaction, supplier must be continuously cautioned or admonished 0 % Deductions Based on Escalation Steps If the supplier is entered into the escalation process and has an assigned E1 to E4 status, the following percentage points will be deducted from the total of the supplier s assessment result: E0 = 0 percentage points deducted E1 = 11 percentage points deducted E2 = 21 percentage points deducted E3 = 31 percentage points deducted E4 = No further assessment => Discontinuation Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / of 13
13 4.2.4 Rating The supplier is rated based on the assessment of the above-mentioned criteria. The following divisions apply: in % Step Measures 90 A If one criterion is < 90%, the supplier must take actions. The supplier is not required to notify hago of actions taken. However, hago can inquire about actions during an audit. 80 B < 80 C The supplier must develop and implement a concrete action plan within 4 weeks and advise Hago accordingly. If the action plan is not received on time, the supplier is blocked for new orders until the action plan is submitted. As part of the assessment, the supplier will be invited to a Q discussion in the near future. This Q discussion is intended to define a concrete action plan as a requirement for requalification. During the meeting, it is decided if the supplier is blocked for new orders and whether hago must perform an audit as a further requirement for the approval process. The audit must have an outcome of 90 points. If an audit is not required, the supplier can be temporarily until the next quarterly assessment. The temporary approval must be justified in the Q discussion protocol. Change 24/11/2016 L. Bendel 24/11/2016 J. Blumenstock 9999/ / of 13
SUPPLIER MANUAL Quality Policy
SUPPLIER MANUAL Quality Policy Prettl, Kurz Kasch is committed to providing our Customers with quality products. We will develop, maintain and continually improve our quality systems to ensure Customer
More informationTable of Contents. 1.0 Introduction 1.1 Overview 1.2 Customer Responsibilities
1400 Lunar Drive Wapakoneta, OH 45895 Supplier Manual Table of Contents 1.0 Introduction 1.1 Overview 1.2 Customer Responsibilities 2.0 Supplier Quality Expectations 2.1 Quality System Requirements 2.2
More informationSupplier Quality Manual
Supplier Quality Manual 1 1. Introduction Scope Purpose Application Implementation 2. Purchasing Expectations Terms and Conditions Engineering / Technical Support Customer Support Resources Pricing Consistent
More informationSupplier Quality Manual (QQS )
Monticello Spring Corporation Quality Management System Supplier Quality Manual (QQS 100.00) 1.0 Introduction 1.1 Scope The details stipulated in this manual are the minimum mandatory requirements for
More informationEge Fren SUPPLIER MANUAL D017
Page : 1 / 9 1. Purpose: This manual is formed in order to create a business environment based on a partnership understanding with our suppliers, determine and develop our relationships in this context
More informationGENERAL QUALITY REQUIREMENTS FOR PURCHASED PARTS
GENERAL QUALITY REQUIREMENTS FOR PURCHASED PARTS The following requirements shall apply to all the suppliers of the associated companies of SELCOM GROUP S.p.A., referred as SELCOM GROUP in the General
More informationMANUAL SUPPLIER S QUALITY MANUAL
MANUAL Raba Automotive Components Ltd Identification 50MR23003 1.8 Page 1/9 Coming into force 10.09.2015 SUPPLIER S QUALITY MANUAL Prepared/ Modified by Checked by Approved by Name Signature Date János
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL 2 TABLE OF CONTENTS PAGE 1. INTRODUCTION 3 2. SCOPE 4 3. REFERENCE MATERIAL 4 4. SUPPLIER APPROVAL PROCESS 4-6 5. PRODUCT APPROVAL PROCESS 6 6. ON-GOING PRODUCTION 6-7 7. SUPPLIER
More informationQUALITY AGREEMENT. 1. ISKRA MEHANIZMI, d.o.o., Lipnica 8, 4245 Kropa, Slovenia, represented by its Managing Director Dr.
QUALITY AGREEMENT concluded between 1. ISKRA MEHANIZMI, d.o.o., Lipnica 8, 4245 Kropa, Slovenia, represented by its Managing Director Dr. Marjan Pogačnik (hereinafter referred to as: Customer) and 2. xxx
More informationSUPPLIER QUALITY MANUAL
SUPPLIER QUALITY MANUAL QD-SUPPLIER-QUALITYMANUAL 1 of 13 02.20.15 TABLE OF CONTENTS Page A. Goal 3 B. Purpose 3 C. Approach 3 D. Applicability 3 E. Implementation 3 F. Zero Defects Policy 3 Section 1:
More informationManual Supplier Qualification Supplier Evaluation Supplier Development
1/22 Manual Supplier Qualification Supplier Evaluation Supplier Development 2/22 Summary/Change Notification Change History Version - 15.08.2016/wsn, kle 1st version and release of manual Description 3/22
More informationMANUAL SUPPLIER S QUALITY MANUAL
MANUAL Rába Automotive Component Manufacturing Ltd Identification 1.3 1/8 Coming into force 28. 01. 2009 SUPPLIER S QUALITY MANUAL Prepared by Checked by Approved by Name Signature Date János KENYERES
More informationSupplier. Quality. Manual
DEPARTMENT: Quality Assurance Title: Supplier - Quality Manual ISSUED ON: 29-Jul-09 PAGE 1 of 12 Supplier Quality Manual Distribution to: Electronically controlled. If this document is in hard copy it
More informationQuality Manual ISO 9001:2008 ISO 9001:2015
Quality Manual ISO 9001:2008 ISO 9001:2015 SAE CIRCUITS, INC. 4820 63 rd Street Suite 100 Boulder, CO 80301 USA www.saecircuits.com Table of Contents 1. Company Information 3 2. QMS Scope and Exclusions
More informationQuality and Environmental Agreement
Quality and between Maschinenfabrik Bernard KRONE GmbH & Co. KG Heinrich Krone-Strasse 10 48480 Spelle Company XY Any Street Any Town hereinafter referred to as the supplier, jointly referred to as the
More informationSupplier. Quality Manual
Supplier Quality Manual Supplier Quality Manual TUBACEX Group 1. INTRODUCTION Vision, Mission and Values 2. New Supplier 3. New Product 4. Serial Production Quality System and/or Qualification Audit Environmental
More informationQuality Assurance Agreement
Quality Assurance Agreement between HBPO GmbH Rixbecker Str. 111, 59552 Lippstadt/Germany - hereinafter called HBPO - and - hereinafter called Supplier - Concerning the realisation of a joint quality management
More informationAA e-SAP Ausgabe Index M. Work instructions SAP Supplier evaluation Purchase parts & wage processing. Supplier Rating 1.
Supplier Rating 1. Purpose and Scope A supplier rating system will be used to measure the quality of a supplier s overall performance and changes thereto. The aim is to exploit improvements in areas with
More informationGENERAL QUALITY REQUIREMENTS
SUPPLIER QUALITY MANUAL Ref.: 05.04 LIR Ind. : 3 Date : 07.11.2012 Page : 1 / 10 Modified by : Dumitrita DALEA Validated by : Gelu MATEESCU Verified by : Adina Halinga GENERAL QUALITY REQUIREMENTS This
More informationSupplier Quality Manual
Supplier Quality Manual Approvals: Quality Manager: Patrick Eckrich Date: 08/18/2017 Materials Manager: Dennis Okocha Date: 08/18/2017 Supplier Quality Manual Rev. _E_, Dated _August 18, 2017 Page 1 of
More informationSupplier Quality Assurance Manual
Supplier Quality Assurance Manual Revised: 0128 January Jul 2014 2010 1. Introduction The purpose of the Supplier Quality Assurance Manual is to straightforwardly communicate to our current and potential
More informationSUPPLIER MANUAL SUPPLIER MANUAL
SUPPLIER MANUAL Rev.: 4, 01.11.2013 Page: 1 of 9 IER-QSF 003 TABLE OF CONTENTS PAGE 1. INTRODUCTION 2 2. SCOPE 3 3. REFERENCE MATERIAL 3 4. SUPPLIER APPROVAL PROCESS 3 5. PRODUCT APPROVAL PROCESS 5 6.
More informationSupplier Quality Manual
Supplier Quality Manual Ritbearing Corp. 15151 Prater Drive Covington, GA 30014 (800) 431-1980 www.ritbearing.com Page 1 of 12 Introduction Ritbearing Corp. is a leading wholesale distributor of ball and
More informationBATES SUPPLIER MANUAL
BATES SUPPLIER MANUAL 1 Bates, LLC 118 Rose Street Lobelville, TN 37097 The Supplier Requirements Manual Is a Controlled Document Any copies made of this document, in its entirety or in part, must be marked
More informationQuality Assurance Requirements (QAR) OTTO FUCHS Dülken GmbH & Co. KG. for suppliers of. Heiligenstraße 70 D Viersen
_ Quality Assurance Requirements (QAR) for suppliers of OTTO FUCHS Dülken GmbH & Co. KG Heiligenstraße 70 D-41751 Viersen - hereinafter referred to as the Buyer - 1. Preamble These Quality Assurance Requirements
More informationAB. OUR ISO CONFORMANCE AUDIT QUESTIONNAIRES 8. ASSESS HOW WELL YOU CONFORM TO ISO S REMEDIAL REQUIREMENTS
8.1 PLANNING REQUIREMENTS 1 Do you plan monitoring, measurement, and analytical processes? 2 Do you plan how monitoring will be used to ensure conformity and effectiveness? 3 Do you plan how it will be
More informationWork instructions Supplier evaluation
1. Purpose and scope of application The quality of the overall performance of a supplier and its changes are to be measured by using a supplier evaluation scheme. The objective is to achieve improvements
More information... Supplier Manual . REV 1. P d --KICKHAEFER MANUFACTURING COMPANY SUPPLIER MANUAL (PRINTED COPIES ARE UNCONTROLLED)
... Supplier Manual. REV 1 P-5.6.1 d --KICKHAEFER MANUFACTURING COMPANY SUPPLIER MANUAL (PRINTED COPIES ARE UNCONTROLLED) INTRODUCTION... 3 1.1 PURPOSE OF THIS SUPPLIER MANUAL... 3 1.2 SCOPE... 3 1.3 CONCEPT...
More informationSUPPLIER EVALUATION ON FINISHED GOODS-RELEVANT PRODUCTS, PROCESSES AND SERVICES SCHAEFFLER GROUP CALCULATION PRINCIPLES AND RULES
SUPPLIER EVALUATION ON FINISHED GOODS-RELEVANT PRODUCTS, PROCESSES AND SERVICES SCHAEFFLER GROUP CALCULATION PRINCIPLES AND RULES 2 1 TABLE OF CONTENTS 1 Table of contents 2 2 Overall Quality GKZ Q 3 Criterion:
More informationMetric Manufacturing Supplier Manual
Metric Manufacturing Supplier Manual This Manual applies to all suppliers of Metric Manufacturing Co. Compliance to all requirements within this manual, as well as the general terms and conditions, are
More informationPrice Electronics,LLC Quality Assurance Manual
Price Electronics,LLC QUALITY POLICY INTRODUCTION The purpose of this manual is to document the company s quality system, to instruct and guide employees whose actions affect product quality and to inform
More informationSupplier Quality Manual
including subsidiaries of Mexico and Canada Supplier Quality Manual Issue date: March 1, 2010 Revised: April 7, 2011 Page 1 of 14 Corporate Quality Statement Quality plays a vital role in SCHOTT Gemtron
More informationProcedures on Management System Certification
1. Purpose Procedure PR-005 describes the roles, responsibilities and processes in a certification body according to ISO 17021 involved in the certification of management systems (MS). The certification
More informationSupplier Expectation Manual
Supplier Expectation Manual Page 1 Sterling Spring Supplier Philosophy Products and services from external providers (suppliers) are intended for incorporation into Sterling Spring s own products and services
More informationQuality Assurance Agreement for MonLog GmbH suppliers Gewerbepark Aunkrichen Aunkirchen / Vilshofen
Page 1 of the Quality Assurance Agreement between MonLog GmbH and Suppliers Quality Assurance Agreement for MonLog GmbH suppliers Gewerbepark Aunkrichen 4 94474 Aunkirchen / Vilshofen The following Quality
More informationPrepared by: Checked by: Released by: Department LOQL Wagner LO-E Doelker LOQL Nuding Date Signature
Page 1 of 9 Prepared by: Checked by: Released by: Department LOQL Wagner LO-E Doelker LOQL Nuding Date Signature Page 2 of 9 Revision status 4 Copies to: LOQ; LOQL; LO-E; Supplier Contents: Page 1. Purpose...
More informationTransition Strategy for VDA 6.1, VDA 6.2 and VDA 6.4. Revision January Contents. 1. Foreword
Transition Strategy for.1,.2 and.4 Revision 1.0 --- 06. January 2017 Contents 1. Foreword 2. Transition timing requirements to the relevant.x standards 3. Transition audit requirements to the relevant.x
More informationBlue Chip Engineered Products Supplier Quality Manual
Blue Chip Engineered Products Supplier Quality Manual Revision Date 07/09/2013 Page 1 Table of Contents A. Goal B. Purpose C. Approach D. Applicability E. Implementation F. Zero Defects Policy Section
More informationGuidelines for suppliers (quality assurance agreement)
Guidelines for suppliers (quality assurance agreement) of Oberaigner Powertrain GmbH, A-4155 Nebelberg, Daimlerstraße 1 Oberaigner Automotive GmbH, D-18299 Laage, Roman-Oberaigner-Allee 1 and amended on
More informationPURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe
Page 1 of 12 DOCUMENT TITLE Supplier Quality Assurance Manual PURPOSE To establish a quality requirements and guidelines for Suppliers doing business with Orchid Monroe REVISION HISTORY Revision Change
More informationSupplier Quality Manual
Supplier Quality Manual between: SaarGummi technologies International GmbH Eisenbahnstrasse 24 D-66687 Wadern and the subsidiaries of CQLT SaarGummi Technologies (hereinafter referred to as the SG Group)
More informationQuality Assurance Agreement
Quality Assurance Agreement between Preh GmbH, Schweinfurter Strasse 5-9, 97616 Bad Neustadt an der Saale, Germany Preh, - hereinafter referred to as the Customer and, - hereinafter referred to as the
More informationDECISION TO ACCREDIT
DECISION TO ACCREDIT Determine the requirements of the regulator, legislation and customer s needs prior to deciding on the standard to implement. Process is based on the following: Top management s decision
More informationSupplier Quality Manual
Supplier Quality Manual Issue 05 March 2018 2018-03-12 05 2 / 15 Contents 1. HISTORY OF CHANGES... 3 2. INTRODUCTION... 4 3. DEFINITIONS AND ABBREVIATIONS... 4 4. GENERAL INFORMATION... 5 4.1 QUALITY ASSURANCE
More informationQuality Policy Manual
AS 9100C / ISO 9001 J & J SPRING ENTERPRISES, 14100 23 Mile Road Shelby Township, Mi 48315 PAGE: 2 OF 41 TABLE OF CONTENTS Information Page Introduction Quality Policy Quality Objectives SECTION 1 SECTION
More informationQuality Management Agreement
Quality Management Agreement (QMA) between the Johann Borgers GmbH Borgersstraße 2-10 D-46395 Bocholt including all affiliated companies as defined in 15 AktG (German Stock Corporation Act) - hereinafter
More informationWestern Diversified Plastics, LLC. Supplier Requirements Manual
Western Diversified Plastics, LLC. Supplier Requirements Manual Revision Date: 12/10/2019 TABLE OF CONTENTS 1.0 Introduction.. 3 2.0 WDP Supplier Policy.. 4 3.0 Scope... 4 4.0 Launch Readiness Measures...
More informationQUALITY ASSURANCE GUIDE FOR SUPPLIERS
QUALITY ASSURANCE GUIDE FOR SUPPLIERS Version of 01/03/2017 Index INDEX 2 INTRODUCTION 3 GOAL 3 1. Request for Quotation RFQ 4 2. Selection and evaluation 5 3. Development of New Products 7 3.1. Inputs
More informationQAA1, Appendix 2. APQP Elements. Customer order. 1.1 Customer specifications
QAA1, Appendix 2 APQP Elements The objectives, expectations and requirements for documenting individual elements of the APQP Status Reports (see QSR-1, Appendix 3) are described as follows: Customer order
More informationReplaces: Not applicable.
Page 1/12 SCOPE - defines the quality requirements for purchasing materials, parts and services that may affect product quality of Airborne items. does not include requirements for design and development
More informationQuality Assurance Agreement for Suppliers (QAA)
between Precision Motors Deutsche Minebea GmbH Auf Herdenen 10 D-78052 Villingen-Schwenningen Germany - hereinafter referred to as PMDM or customer - and [contractual partner please insert] - hereinafter
More informationPos Service Holland (SA) Pty Limited
1. Definitions 1.1 In these general conditions it is understood under: Supplier: Customer: Pos Service Holland (SA) Pty Ltd T/A PSH-SA Every natural or legal person with whom supplier negotiates concerning
More informationMaterion AMTS Supplier Quality Manual
Advanced Materials Technologies and Services Inc. Materion AMTS Supplier Quality Manual Supplier Name: Supplier Address: Suppliers shall review the attached Supplier Quality Manual and acknowledge receipt
More informationQuality Assurance Requirements (QAR) OTTO FUCHS KG. for suppliers of. Derschlager Straße 26 D Meinerzhagen
Quality Assurance Requirements (QAR) for suppliers of OTTO FUCHS KG Derschlager Straße 26 D-58540 Meinerzhagen - hereinafter referred to as the Buyer - QAR_ OTTO FUCHS KG_ rev.3_february 2016 1. Preamble
More informationArbeitsanweisung Supplier Rating
AA 11-05 Issue 02.14 Index D Arbeitsanweisung Supplier Rating AA11-05 Lieferantenbewertung_engli sch.docx Name: Prepared by: Checked by: Approved by: Zentraleinkauf Mr. Vollmer Mr. Stöber Date: February
More informationBufab document Page 0/11 Date Version 1.1 BUFAB SUPPLIER MANUAL
Bufab document Page 0/11 Version 1.1 BUFAB SUPPLIER MANUAL Bufab document Page 1/11 Contents Inquiry/offer... 3 Order... 3 Sales confirmation... 3 Transport... 3 Invoice... 3 Delivery delays... 4 Packaging
More informationFSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT
FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT FSC36 Safe Feed/Safe Food (www.safefeedsafefood.org) is a facility certification program for the American Feed Industry Association (www.afia.org) Version 7.0
More informationSUPPLIER QUALITY REQUIREMENTS
SUPPLIER QUALITY REQUIREMENTS TABLE OF CONTENTS 1) PURPOSE PG 2 2) KINNEAR PURCHASE ORDER PG 2 3) USE AND COMMUNICATION PG 2 4) SUPPLIER APPROVAL PG 2 5) GENERAL REQUIREMENTS PG 3 SQD Rev 2 2014-08-13
More informationISO 9001:2000 What does it mean in the supply chain?
ISO 9001:2000 What does it mean in the supply chain? What is ISO 9001:2000? ISO 9001:2000 is an international standard that gives requirements for an organization s Quality Management System ( QMS ). It
More informationbetween Süddeutsche Gelenkscheibenfabrik GmbH Co. KG Graslitzer Strasse Waldkraiburg - hereinafter known as SGF or the Customer - and
between Süddeutsche Gelenkscheibenfabrik GmbH Co. KG Graslitzer Strasse 14 84478 Waldkraiburg - hereinafter known as SGF or the Customer - and ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
More informationAddendum No. 1 to the CSTBat Certification Reference System: Connection hoses
CERTIFICATION Addendum No. 1 to the CSTBat Certification Reference System: Connection hoses Identification No.: QB 10 Addendum No. 1, approved by the CSTB Technical Management on: 02/08/2016 Application
More informationSupplier Quality Manual
Supplier Quality Manual Table of Contents Challenge Quality Policy... 4 Challenge Objectives... 4 Expectations & Philosophy... 5 SECTION 1- Introduction... 6 A. Policy and Vision... 6 B. Purpose... 6 C.
More informationEdition: Revision 09, February 19, This document is controlled by: Mayco International, LLC. Edited by
Working together as a team QUALITY AT THE SOURCE Page: 2 of 24 Supplier Quality Standard Edition: Revision 09, February 19, 2018 This document is controlled by: Mayco International, LLC Edited by Mayco
More informationSAM automotive production GmbH SAM automotive GmbH Kolomanstr D Böhmenkirch
Quality Guidelines For Suppliers Of The SAM automotive group SAM automotive production GmbH SAM automotive GmbH Kolomanstr. 16 20 D 89558 Böhmenkirch www.sam-automotive.com contact@sam-automotive.com Page
More informationSUPPLIER PROFILE INFORMATION. Company Name : Address : Telephone: Fax: Internet Homepage: Duns Number: Parent Company : Address :
SUPPLIER PROFILE INFORMATION Company Name : Address : Telephone: Fax: Internet Homepage: Duns Number: Parent Company : Address : Key Contact ( Including phone numbers and email addresses ) President /
More informationThe supplier evaluation will in future be sent out every six months.
1. Supplier assessment - Introduction Within the framework of permanent improvement of the relationships between KOSTAL and its suppliers, we have now comprehensively reworked and extended the Supplier
More informationConfidentiality and Rights Maintenance of Audit Standards. Detail Fee Structure for Program Participants Audit Access System Security
PROGRAM GOVERNANCE PROGRAM GOVERNANCE Issue Date: 06/10/17 Issue and Revision Number: 3 Governance Elements Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8 Section 9 Section
More informationQuality Assurance Agreement with Production Material Suppliers
Quality Assurance Agreement with Production Material Suppliers Preface Ernst Scherzinger GmbH & Co. KG, as well as its associated companies, hereinafter named Scherzinger Pump Technology or we, wants to
More informationCSA Group Products, Processes and Services Scheme
1. CONTACT CSA CSA Group Products, Processes and Services Scheme 1.1 Getting started is easy. There are three ways to contact us: Call 866 797 4272 Email client.services@csagroup.org Complete a request
More informationProgressive Metal Forming, inc Hall Road Hamburg, MI 48139
SUPPLIER QUALITY MANUAL Progressive Metal Forming, inc. 10850 Hall Road Hamburg, MI 48139 www.pmfdraw.com Rev. 1/30/17 Page 1 of 11 TABLE OF CONTENTS 1.0 INTRODUCTION. 3 2.0 SUPPLIER QUALITY GUIDELINES...3
More informationISO 9001:2000 expires globally after November 12, 2010
February 18, 2010 Attention NSF-ISR ISO 9001:2000 certified customers, This is a reminder that ISO 9001:2000 expires globally after November 12, 2010. Consistent with the initial transition arrangements
More informationV02 SUPPLIER GUIDELINES
V02 SUPPLIER GUIDELINES 1. Introduction Our product quality is crucial to our position on the world market. The quality of the goods you supply directly affects our products. As our partners, our suppliers
More informationGlobal Supplier Quality Process Manual. Quality Processes for Suppliers to Merkle-Korff Industries. Abstract
Global Supplier Quality Process Manual Quality Processes for Suppliers to Merkle-Korff Industries Abstract This document contains quality requirements for suppliers to Merkle-Korff Industries and provides
More informationEX0-114_Wins_Exam. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0
EX0-114_Wins_Exam Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ 20000 IT Service Management Foundation Bridge based on ISO/IEC Total Questions: 78
More informationISO 9001 QUALITY MANUAL
ISO 9001 QUALITY MANUAL Origination Date: 10/01/14 Document Identifier: AIF quality control manual Date: 10/01/14 Project: Customer review Document Status: Released Document Link: www.aeroindfast.com Abstract:
More informationSupplier Quality Manual
Supplier Quality Manual SC-002 Revision: 09/24/2018 Table of Contents Challenge Quality Policy. 3 Challenge Quality Objectives..3 Expectations and Philosophy...4 Section 1- Introduction.... 5-6 A. Policy
More informationIT Service Management Foundation based on ISO/IEC20000
IT Service Management Foundation based on ISO/IEC20000 Number: EX0-115 Passing Score: 60 Time Limit: 90 min File Version: 4.0 http://www.gratisexam.com/ Exin EX0-115 IT Service Management Foundation based
More informationOPW Engineered Systems
1 of 5 1.0 Purpose 1.1 The purpose of this manual is to promote a clear understanding of OPW Engineered Systems (OPW-ES) expectations and requirements for suppliers. This manual explains the process OPW-
More informationVernay Quality System Supplier Quality Manual
Table of Contents Revision: G Approvals: Manager, Quality Systems/Improvements NA Purchasing Manager Section A Overview Revision: G Page Approval 1 Table of Contents 2 Section A Section B Section C Section
More informationSupplier Quality Manual
Supplier Quality Manual DuraTech Industries Supplier Quality Manual Page 2 of 13 Table of Contents 1.0 Introduction 1.1. Overview 1.2. Scope 1.3. Customer Responsibilities 3 3 3 2.0 Supplier Quality Expectations
More informationMicrogeneration Installation Standard: MCS 001. MCS Contractor certification Scheme requirements Issue 3.0
Microgeneration Installation Standard: MCS 001 MCS Contractor certification Scheme requirements Issue 3.0 This Microgeneration Installation Standard is the property of Department of Energy and Climate
More informationQUALITY MANUAL ISO 9001 QUALITY MANAGEMENT SYSTEM
QUALITY MANUAL ISO 9001 QUALITY MANAGEMENT SYSTEM APPROVED BY: JOSE ALBERTO APPROVED ON: 08/10/2017 Rev.: 1 M001 QUALITY MANAGEMENT SYSTEM PAGE: 1 of 20 TABLE OF CONTENTS SECTION TITLE PAGE Table of Contents
More informationSUPPLIER QUALITY MANUAL
IMT-SQM 1 OF 6 Rev: 11/10/10-01 INTRODUCTION In today s lean, just-in-time manufacturing environment, product found to be nonconforming can cause serious manufacturing disruptions. In our continuing efforts
More informationQuality Guideline for Suppliers. 1. Purpose
Quality Guideline for Suppliers 1. Purpose The Quality Guideline (QGL) of Aumann Beelen GmbH forms an integral part of the purchase orders and is thus binding for all Suppliers, hereinafter referred to
More informationRules for Ship Recycling Management System Certification
Rules for Ship Recycling Management System Certification Effective from July 1 st 2009 RINA Società per azioni Via Corsica, 12-16128 Genova - Italy Tel.: +39 01053851 - Fax: +39 0105351000 www.rina.org
More informationSTANDARD. S P-O Svedlund UTDH Markku Backholm. SDT Eva Ivrell Hedensjö UTDH Iréne Klingberg
1(13) SCANIA CUSTOMER SPECIFIC REQUIREMENTS Contents Changes from previous issue... 1 General... 1 1 General requirements... 2 2 Human rights... 2 3 REACH legislation... 3 4 Environmental protection...
More informationTRICO PRODUCTS PUR-C-P106-A
TRICO PRODUCTS PUR-C-P106-A October 9, 2009 Supplier Guide Page 1 of 14 TRICO PRODUCTS PUR-C-P106-A October 9, 2009 Page 2 of 14 NAME: TRICO Supplier Guide PURPOSE: The purpose of this document is to communicate
More informationSupplier Manual Quality
Supplier Manual Quality Document: LH_001 Issue date: 30.04.2018 Page: 0 / 13 Status: V0.3 Revision Date Site Reason for change / Comment V0.0 01/07/2013 1-13 Creation of supplier manual V0.1 24/02/2014
More informationSections of the Standard. Evidence / Comments. (Y) / Nonconforming (NC)
Date: Sections of the Standard 4 Context of the Organization 4.1 Understanding the organization and its context 4.2 Understanding the needs and expectations of interested parties 4.3 Determining the scope
More informationFAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM
FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM 1 QA.101 rev. 3-2012 PURPOSE OF THIS STANDARD Fairfield is committed to continuous product quality improvement. Our management team is convinced that only with
More informationAccounts Payable-Vendor Partnership
Accounts Payable-Vendor Partnership Can we work together to pay you more quickly? The City of Miami values its relationship with you, our supplier. Our Purchasing Department and Accounts Payable have designed
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 6/26/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationGLB QM 02. Supplier Quality Manual 05. 3/2/18 Supplier Quality 1 of 19. Issue Date Issuing Department Page
3/2/18 Supplier Quality 1 of 19 3/2/18 Supplier Quality 2 of 19 Table of Contents 1.0 Introduction 3 2.0 Manual 4 2.1 Application 4 2.2 Quality Management System of the Supplier 4 2.3 Quality Management
More informationAlternative Resource Account Governance Process
Alternative Resource Account Governance Process Document Author: Alternative Resource Account Manager Date Approved: 26 th September 2018 Document Reference PO Alternative Resource Account Governance Process
More informationMicrogeneration Installation Standard: MCS 001. MCS Contractor certification scheme requirements Issue 2.5
Microgeneration Installation Standard: MCS 001 MCS Contractor certification scheme requirements Issue 2.5 This Microgeneration Installation Standard is the property of Department of Energy and Climate
More informationSUPPLIER MANUAL. Griffith Rubber Mills - HQ 2625 Northwest Industrial Street Portland, Oregon 97210
SUPPLIER MANUAL Griffith Rubber Mills - HQ 2625 Northwest Industrial Street Portland, Oregon 97210 TABLE OF CONTENTS Page Title 1... Introduction, Purpose, Scope Quality Policy, Certification & Exemptions
More informationQuality Assurance Agreement (QAA)
1 Quality Assurance Agreement (QAA) between WESTFALIA-Automotive GmbH (WAM) Am Sandberg 4 33378 Rheda-Wiedenbrück and XXXX, XXXX, XXXXXX (SUPPLIER) 2 I. Introduction 1. The Contract Parties (SUPPLIER and
More informationSUPPLIER EVALUATION ON FINISHED GOODS-RELEVANT PRODUCTS, PROCESSES AND SERVICES SCHAEFFLER GROUP ZERO DEFECTS, CONTINUOUS IMPROVEMENT, COLLABORATION
SUPPLIER EVALUATION ON FINISHED GOODS-RELEVANT PRODUCTS, PROCESSES AND SERVICES SCHAEFFLER GROUP ZERO DEFECTS, CONTINUOUS IMPROVEMENT, COLLABORATION 2 1 GENERAL The supplier evaluation is a normative requirement
More informationSupplier Quality Manual CHASSIX Inc.
Supplier Quality Manual CHASSIX Inc. SQM-001 rev 8/2/17 Page 1 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 CHASSIX QUALITY POLICY 1.2 CHASSIX SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS 1.3 CHASSIX SUPPLIER
More informationSupplier Quality System Survey
Supplier Division Address Date: Quality Contact: Reports to: Title: Title: Phone Fax e-mail Plant size (ft 2 ): Union: Contract expires: Total Employment: Direct Labor: Shifts: QA employees: This report
More information