Heavy Component Replacement in Nuclear Power Plants

Size: px
Start display at page:

Download "Heavy Component Replacement in Nuclear Power Plants"

Transcription

1 Heavy Component Replacement in Nuclear Power Plants Steve Sills, Vice President Business Development, SGT Darren Wood, Manager Component Replacements, AREVA

2 Purpose and Process Goal Recent successes and lessons learned in AREVA and SGT Heavy Component Replacements Agenda IAEA NP-T Background Project Organization Steam Generator Replacements Reactor Vessel Closure Head Replacements Pressurizer Replacements Waste Disposition Payoff High level overview Initiate an information exchange 2 > 2

3 IAEA NP-T-3.2 Heavy Component Replacement in Nuclear Power Plants: Experience and Guidelines Why are we here? Component Aging and Plant License Extension Most Feasible Solutions Trends Share Lessons Learned US Market Steam Generators replaced at 47 units 9 planned Alloy 600 TT tubes unplanned Reactor Vessel Heads replaced at 37 units 13 planned 19 low-susceptibility unplanned Pressurizers replaced at 3 CE units Reactor Coolant Piping 2 planned at B&W units Experience Base Continues to to Grow 3 > 3

4 Project Composition 4 > 4

5 How does the Project Organization impact project success? Project Management Customer Scope/Contract Business Unit Integration Subcontractor Integration Engineering Design / Specification Analysis Metrology Services NDE Quality Field Implementation Component Fabrication Site Installation Outage Manager Resources Definitions of Success Safety Radiation dose Schedule Cost / budget performance Human performance Contributors to Success Dedicated team Strong structure - clear definition of responsibilities and communications N-3, 2, 1 Walk-downs Leverage technology Robust processes Clear contract Alignment of of goals Staffing of of key key positions Facilitating clear communications 5 > 5

6 Who is SGT? 50% 50% 6 > 6

7 Replacements since 2003 Schedule pressure from decreasing Outage durations Schedule pressure from decreasing Outage durations Schedule pressure from decreasing Outage durations SEQUOYAH 1 (W4) CALVERT CLIFFS 2 (CE) OCONEE 1 (B&W) PALO VERDE 2 (CE) OCONEE 2 (B&W) PRAIRIE ISLAND 1 (W2) OCONEE 3 (B&W) PALO VERDE 1 (CE) CALLAWAY (W4) ANO 1 (B&W) BEAVER VALLEY 1 (W3) WATTS BAR 1 (W4) COMANCHE PEAK 1 (W4) PALO VERDE 3 (CE) FORT CALHOUN (CE) ST. LUCIE 2 (CE) DIABLO CANYON 2 (W4) SALEM 2 (W4) DIABLO CANYON 1 (W4)

8 Outage schedules Each unit is unique different schedule challenges 2 SGs is not half as long as 4 Shortest schedule requires Commitment by customer Cost is probably higher Plant activities must also be optimized Extensive schedule review and Integration Extensive Planning and mock up training Coordination of cranes & space Clearly establish objectives align incentives Shorter Outage Trend Continues still still raising the the bar bar 8 > 8

9 SGT Just finished Diablo Canyon SGR Diablo Canyon Unit 1 Steam Generator Replacement Westinghouse four-loop PWR 1,150 MW Outage - January 25, 2009 to March 24, 2009 SGT performed Unit 2 SGR in 2008 Delivery of excellent performance: Safety Project achieved One Million Safe Hours 12/01/08 730,034 safe hours (w/o lost time) Unit 1 May 1, present Outage: 2 recordables SGT Dose actual goal Dose rates 30% higher than Unit 2; Unit 1 actual dose only 15% higher Schedule 58 d 1 hr B-B 12 hrs ahead of schedule Ready for ILRT 116 hrs early 11 days shorter than unit 2 Quality Document closeout excellent 8 of 8 RCS welds first time quality 28 of 29 large bore secondary welds first time quality 9 > 9

10 Future Steam Generator Replacement Lower volume Uncertain schedule SGR Alloy 600 TT SG tubes From the experience Extensive lessons learned Refined processes Continuous improvement 10 > 10

11 Keys to Success One clear vision for the entire team Early alignment of expectations and communication of those expectations to project participants The right team Get the needed mix of skills and experience Ensure clear roles and responsibilities More is not better, it just costs more Teamwork Help each other be successful What do you need to make it happen Don t accept we can t Treat each other with respect View as one team, top to bottom Communication is critical Teambuilding, including social events for the team Celebrate along the way 11 > 11

12 Keys to Success Effective Project Management Systems Effective Human Performance, Safety (industrial, radiation and nuclear) and Quality Culture Detailed Planning Mock-up and proficiency training High Quality Detailed Schedule to Focus Organization Early Involvement of Plant Personnel Formal and Proven Processes / Systems (Project planning, integration and Readiness Review, corrective action, detailed resource planning) Technology / innovation 3d modeling Metrology laser scanning & precision measurements Fit-up solution tools Computed Radiography Rigging equipment minimize plant modifications 12 > 12

13 Reactor Vessel Closure Head (RVCH) Replacements Recent decline in activity High and medium susceptibility heads 35 of 48 replaced Remainder planned Low-temperature heads 2 of 21 replaced Utilities are monitoring Fall 2009 Diablo Canyon 2 South Texas 1 Palo Verde 2 Spring 2010 South Texas 2 Palo Verde 1 Fall 2010 Diablo Canyon 1 There is is a good experience base to to learn from. 13 > 13

14 Many plants include service structure upgrades when replacing their RVCH Eliminate current rolling missile shield, ductwork and fans Current Service Structure separate from service structure, roll away, fly remaining to head stand Integrated Head Assembly fold cable trays, fly entire structure to head stand 14 > 14

15 Integrated Head Assembly CRDM Cooling Air Plenum - Easy maintenance access Integrated Missile Shield - Schedule and dose savings and safety feature Cable Bridges - Personnel access rated Permanent Tripod - Schedule savings and safety feature Integrated CRDM Cooling Ductwork - Schedule and dose savings and safety feature Permanent, Moveable, Double-door Radiation Shielding - Schedule and dose savings and safety feature -Easy access for inspections and maintenance 4 low-rpm CRDM Cooling Fans - Longer life / Low Amp Motor - Greater reliability - Reverse current air flow pattern Tripod / Fan Access Ladders- - Easy Access to Lift Eye / Fans Easy-disconnect and self-storing tie rods - Schedule and dose savings and safety feature External Ladder - Time saving and safety feature Personnel access platform - Schedule saving and safety feature Redesigned, upgraded dome and l-panel insulation - ports for 100% visual inspection and robot access - Schedule and dose savings Expected hrs hrs outage time time savings and and man-rem dose savings. Top Top Industry Practice Award Winner. 15 > 15

16 Applying Lessons Learned Continues to Improve Performance DC Cook 2 (Fall 2007) RVCH and Service Structure Upgrades 37 days vs 38 planned 11.8 person-rem vs 12.5 Second outage project execution much improved Customer support resources loaded into schedule Laydown space planning Suppliers were included as part of site team St. Lucie 2 (Fall 2007) RVCH, Enhanced Service Structure, Steam Generators 79 days versus 66 planned Total RVCHR dose 5.43 REM Controlled document station inside containment with fax and phone saved significant time Good coordination / information flow from original equipment manufacturer Pre-assembly / trial fit in the temporary assembly building CEDM welding tool performed flawlessly used generator versus off-site power (voltage drops previous outage) 24/7 vendor coverage for analytical support Fabrication and installation of ductwork 16 > 16

17 Three dimensional models and precision measurement minimize fit-up risks. 17 > 17

18 Pressurizer Replacements Market Status No additional pressurizer replacements are planned in the US market. Last AREVA replacement was at Millstone in 2006 Rhingals 4 is planned for 2011 during SGR Key Lessons Economical for pressurizers with greater than 100 heaters Civil scope and interference removal just a critical as heavy component scope Dedicated secondary cranes Proper design of insulation package Foreign material exclusion is a challenge NDE examination criteria Piping restraints and spring-back 18 > 18

19 Pressurizer Replacements 19 > 19

20 Waste Disposition continues to be a scope and cost that cannot be overlooked. Replaced components interim onsite storage facilities Build and license Low-level waste Disposal cost Component demolition Logistics of removal from reactor building Shipping container Successes Detailed waste removal plans Include in outage schedule Planning between disposal and rigging teams Transportation logistics Mechanism for release of bag Gasket material Contamination bag 20 > 20

21 Conclusions Every project is different the devil is in the details Establish a good plan early Clear communications and alignment of goals between stakeholders is key Second outages are typically more successful The scope is larger than the component replacement Apply lessons learned Leverage technology Precision measurements during early walk-downs 3-D modeling Integrated schedules 21 > 21

22 Wrap-Up Goal Recent successes and lessons learned in Heavy Component Replacements Agenda IAEA NP-T-3.2 Background Project Organization Steam Generator Replacements Reactor Vessel Closure Head Replacements Pressurizer Replacements Waste Disposition Payoff Share experiences and improve our performance»en j o y th e Co n fe r e n c e! 22 > 22

Hydratight Nuclear Projects STEAM GENERATOR APPLICATIONS

Hydratight Nuclear Projects STEAM GENERATOR APPLICATIONS www.hydratight.com Hydratight Nuclear Projects STEAM GENERATOR APPLICATIONS Client - Station Name (Country) Type and Application Description of tooling/services Year PSE&G Three Mile Island Babcock & Wilcox

More information

THE 14TH R EFUELING outage at Diablo

THE 14TH R EFUELING outage at Diablo Two of the new steam generators arriving by barge at Diablo Canyon s intake cove (Photos: PG&E) A four-steam-generator outage at Diablo Canyon-2 BY RICK MICHAL THE 14TH R EFUELING outage at Diablo Canyon

More information

Rick Libra, director of work management at Exelon Nuclear s Three

Rick Libra, director of work management at Exelon Nuclear s Three Interview: Libra T H E N U C L E A R N E W S I N T E RV I E W Rick Libra: A safe and successful outage About 2.5 million person-hours were worked during TMI-1 s recent outage, with no lost-time injuries.

More information

NRC LIAISON REPORT NRC SIGNS NUCLEAR SAFETY COOPERATION AGREEMENTS WITH SEVEN NATIONS

NRC LIAISON REPORT NRC SIGNS NUCLEAR SAFETY COOPERATION AGREEMENTS WITH SEVEN NATIONS NRC LIAISON REPORT NRC SIGNS NUCLEAR SAFETY COOPERATION AGREEMENTS WITH SEVEN NATIONS The U.S. Nuclear Regulatory Commission Chairman Gregory B. Jaczko signed agreements with representatives of seven countries

More information

New Builds Panel Discussion Moderated by: Jay Wileman

New Builds Panel Discussion Moderated by: Jay Wileman New Builds Panel Discussion Moderated by: Jay Wileman Senior Vice President, Nuclear Plant Projects and Chief Operating Officer, GE Hitachi Nuclear Energy February 4, 2014 Marilyn Kray Vice President Exelon

More information

A REPORT ON CANADA S LARGEST CLEAN POWER PROJECT DARLINGTON REFURBISHMENT

A REPORT ON CANADA S LARGEST CLEAN POWER PROJECT DARLINGTON REFURBISHMENT A REPORT ON CANADA S LARGEST CLEAN POWER PROJECT DARLINGTON REFURBISHMENT AUGUST 2016 READY TO EXECUTE The Darlington Nuclear Generating Station has been safely and reliably producing almost 20 per cent

More information

with a Forward by Dale Bridenbaugh by Daniel Hirsch and Dorah Shuey September 12, 2012

with a Forward by Dale Bridenbaugh  by Daniel Hirsch and Dorah Shuey September 12, 2012 FAR OUTSIDE THE NORM: The San Onofre Nuclear Plant s Steam Generator Problems in the Context of the National Experience with Replacement Steam Generators by Daniel Hirsch and Dorah Shuey with a Forward

More information

FOR SEVERAL YEARS now, industry

FOR SEVERAL YEARS now, industry U.S. capacity factors: A small gain to an already large number BY E. MICHAEL BLAKE Median DER net capacity factor 100 90 80 70 60 50 40 30 20 10 0 58.60 1974 1976 63.83 1977 1979 59.64 1980 1982 60.60

More information

PWROG Reactor Internals Projects

PWROG Reactor Internals Projects PWROG Reactor Internals Projects Industry/NRC Exchange Meeting June 2015 Glenn Gardner, Mike Burke, Heather Malikowski Topics Integrated Industry Approach, Processes and Tools Materials Applications Fleet-wide

More information

TEC WORKING GROUP WHITE PAPER: INTERMODAL TRANSPORTATION OF COMMERCIAL SPENT NUCLEAR FUEL (SNF) JULY 2008

TEC WORKING GROUP WHITE PAPER: INTERMODAL TRANSPORTATION OF COMMERCIAL SPENT NUCLEAR FUEL (SNF) JULY 2008 TEC WORKING GROUP WHITE PAPER: INTERMODAL TRANSPORTATION OF COMMERCIAL SPENT NUCLEAR FUEL (SNF) JULY 2008 Prepared for The Transportation External Coordination Working Group (TEC) Rail Topic Group, Intermodal

More information

Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction: Case Study of China and Romania

Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction: Case Study of China and Romania IAEA Workshop on Construction Technologies for Nuclear Power Plants: A Comprehensive Approach Paris, France 12 16 December, 2011 Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction:

More information

Reactor Internals Overview

Reactor Internals Overview 1 Reactor Internals Overview Mechanisms: Cracking due to Irradiation Assisted Stress Corrosion (IASCC) and Stress Corrosion (SCC) Reduction of Fracture Toughness due to Irradiation Embrittlement (IE) and

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

Regulatory Approach to Radiation Protection in new NPPs in Finland

Regulatory Approach to Radiation Protection in new NPPs in Finland Regulatory Approach to Radiation Protection in new NPPs in Finland ISOE European Workshop in Prague 20.-22. 6. 2012 Veli Riihiluoma Radiation and Nuclear Safety Authority (STUK) RADIATION AND NUCLEAR SAFETY

More information

Westinghouse SMR & Nuclear Fuel Overview

Westinghouse SMR & Nuclear Fuel Overview Westinghouse SMR & Nuclear Fuel Overview Carlos Leipner, Westinghouse VP Latin America Presented at LAS-ANS July 2014 Rio de Janeiro, Brasil 2014 Westinghouse Electric Company LLC, All Rights Reserved.

More information

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant

More information

Westinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant

Westinghouse s plant for the Nuclear Renaissance : AP1000. AP1000 Advanced Passive Plant Westinghouse s plant for the Nuclear Renaissance : AP000 Fernando Naredo Milan, January 30, 006 AP000 Advanced Passive Plant Designed to compete with other sources in deregulated power markets - Two loop,

More information

Zion Project Overview S. Chris Baker VP EH&S

Zion Project Overview S. Chris Baker VP EH&S Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel

More information

NUCLEAR. Nuclear Reactor Pressure Vessel Seals

NUCLEAR. Nuclear Reactor Pressure Vessel Seals NUCLEAR Nuclear Reactor Pressure Vessel Seals SEALING CONCEPT Technetics Group is the world s leading manufacturer of Nuclear Reactor Pressure Vessel (RPV) Closure Head Seals. In addition, Technetics Group

More information

S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry (USNRC) PSA 99

S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry (USNRC) PSA 99 INEEL/CON-99-00374 PREPRINT Westinghouse Reactor Protection System Unavailability, 1984 1995 S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry

More information

Best practices for preparing vessel internals segmentation projects

Best practices for preparing vessel internals segmentation projects Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse

More information

2017 Water Reactor Fuel Performance Meeting September 10 (Sun) 14 (Thu), 2017 Ramada Plaza Jeju Jeju Island, Korea

2017 Water Reactor Fuel Performance Meeting September 10 (Sun) 14 (Thu), 2017 Ramada Plaza Jeju Jeju Island, Korea Extended Storage Collaboration Program for Addressing Long-Term Dry Storage Issues Hatice Akkurt 1 1 Electric Power Research Institute (EPRI), 1300 W WT Harris Blvd, Charlotte, NC 28262, hakkurt@epri.com

More information

Small Modular Reactor Materials R&D Program Materials Coordination Webinar

Small Modular Reactor Materials R&D Program Materials Coordination Webinar Small Modular Reactor Materials R&D Program Materials Coordination Webinar William Corwin Office of Advanced Reactor Technologies U.S. Department of Energy August 2012 SMRs Are Strong Contenders to Augment

More information

Innovative Approaches to Large Component Packaging. A. Freitag, M, Hooper, E, Posivak, J. Sullivan WMG, Inc. Peekskill, NY USA

Innovative Approaches to Large Component Packaging. A. Freitag, M, Hooper, E, Posivak, J. Sullivan WMG, Inc. Peekskill, NY USA Innovative Approaches to Large Component Packaging A. Freitag, M, Hooper, E, Posivak, J. Sullivan WMG, Inc. Peekskill, NY 10566 USA ABSTRACT Radioactive waste disposal often times requires creative approaches

More information

The Materials Initiative NEI Overview

The Materials Initiative NEI Overview The Materials Initiative NEI 03-08 Overview Robin Dyle EPRI Annual Materials/NRC Technical Exchange June 2, 2015 Overview Primary system materials integrity is vital to plant performance and reliability

More information

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant 8 Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant KOZO TABUCHI *1 MASAYUKI TAKEDA *2 KAZUO TANAKA *2 JUNICHI IMAIZUMI *2 TAKASHI KANAGAWA *3 ATMEA1 TM is a 3-loop 1100

More information

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1

More information

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA An Integrated Equipment for Massive Segmentation and Packaging of Control Rod Guide Tubes 15161 Joseph Boucau*, Patrick Gobert** Sébastien Bonne *** * Westinghouse Electric Company, 43 rue de l Industrie,

More information

Fuel Reliability (QA)

Fuel Reliability (QA) Program Description Fuel Reliability (QA) Program Overview Fuel failures and other fuel-related issues can have significant operational impacts on nuclear power plants. Failures, for example, can cost

More information

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Leo Lessard Manager, Commercial Decommissioning Operations, AREVA Inc. 16th February 2016 International

More information

Nuclear Businesses. Sept 10, Session 3 NEA/MDEP Conference on the New Reactor Design Activities

Nuclear Businesses. Sept 10, Session 3 NEA/MDEP Conference on the New Reactor Design Activities Nuclear Businesses Sept 10, 2009 Session 3 NEA/MDEP Conference on the New Reactor Design Activities Sang Jin, Kim sangjinkim@doosan.com Doosan Heavy Industries and Construction Co., Ltd. Fully Integrated

More information

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C -1 SMUD SACRAMENTO MUNICIPAL UTILITY DISTRICT 7 P. 0. Box 15830, Sacramento CA 95852-1830, (916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA MPC&D 03-088 July 31, 2003 U. S. Nuclear Regulatory

More information

Poland Nuclear Program EPR Flamanville 3

Poland Nuclear Program EPR Flamanville 3 Poland Nuclear Program EPR Flamanville 3 Project Organization Design & Manufacturing activities On Site activities What We Are Learning from New Construction Experience September 29 th, 2010 Gilles Zask

More information

Berkeley Boilers Project. Studsvik Symposium April 2014

Berkeley Boilers Project. Studsvik Symposium April 2014 Berkeley Boilers Project Studsvik Symposium April 2014 Berkeley NPP Twin Magnox Reactors Operating 1962 1989 First UK commercial reactor to enter decommissioning Currently managed on behalf of the Nuclear

More information

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007 ANSTO s POLICY for MOATA & HIFAR Prepared by John Rowling November 2007 Content Australian Nuclear Regulatory Systems Compare to International Recommendations Licencing Transition Period Major Issues Requirements

More information

Nuclear Power A Journey of Continuous Improvement

Nuclear Power A Journey of Continuous Improvement Nuclear Power A Journey of Continuous Improvement Westinghouse Non Proprietary Class 3 Our Place in Nuclear History Innovation 1886 and forever Implementation & Improvement 1957 through Today Renaissance

More information

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) 1.3.2016 Prof.Dr. Böck Technical University Vienna Atominstitut Stadionallee 2, 1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at

More information

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT

AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT DESIGN ASSESSMENT AND SITE LICENSING OF THE EPR FOR THE HINKLEY POINT C PROJECT 10/2016 Stephen J Walls, EDF Energy Nuclear New Build 1 Olivier Bard, EDF HINKLEY POINT C (HPC) 2 HPC Financial Investment

More information

Boiler Chemical Cleaning- Valmet Approach. Presented by Dewey Johnson Valmet Boiler Chemical Cleaning Specialist and Advisor

Boiler Chemical Cleaning- Valmet Approach. Presented by Dewey Johnson Valmet Boiler Chemical Cleaning Specialist and Advisor Boiler Chemical Cleaning- Valmet Approach Presented by Dewey Johnson Valmet Boiler Chemical Cleaning Specialist and Advisor Valmet Expertise Planning Procurement On site preparations Cleaning execution

More information

NRC Activities. Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation

NRC Activities. Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation NRC Activities Matthew McConnell Senior Electrical Engineer Office of Nuclear Reactor Regulation Agenda Nuclear Power Plant Reviews Inspection News Regulatory Guide News Research Activities IEC/IEEE Joint

More information

Olkiluoto Infrastructure

Olkiluoto Infrastructure OL3 Olkiluoto Infrastructure 2 30.9.2008 Arguments for a New Nuclear Plant Unit - Covers partly the additional electricity demand and replaces old power plants - Enables, together with renewables, the

More information

Collection and safekeeping of TRIGA Spent Nuclear Fuel

Collection and safekeeping of TRIGA Spent Nuclear Fuel Collection and safekeeping of TRIGA Spent Nuclear Fuel Presented by Ken Whitham, US DOE-ID and Jim Floerke, CH2MWG Idaho 2013 Spent Nuclear Fuel at the Idaho Cleanup Project 2 Atoms for Peace Since the

More information

What Nuclear Reactor Companies Need

What Nuclear Reactor Companies Need September 6, 2017 What Nuclear Reactor Companies Need Scott Bailey Vice President, Supply Chain NuScale Nonproprietary Copyright 2017 NuScale Power, LLC Acknowledgement & Disclaimer This material is based

More information

OPERATING EXPERIENCE REGARDING THERMAL FATIGUE OF UNISOLABLE PIPING CONNECTED TO PWR REACTOR COOLANT SYSTEMS

OPERATING EXPERIENCE REGARDING THERMAL FATIGUE OF UNISOLABLE PIPING CONNECTED TO PWR REACTOR COOLANT SYSTEMS OPERATING EXPERIENCE REGARDING THERMAL FATIGUE OF UNISOLABLE PIPING CONNECTED TO PWR REACTOR COOLANT SYSTEMS ABSTRACT Paul Hirschberg John Carey Arthur F. Deardorff EPRI Project Manager Structural Integrity

More information

Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life

Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life Nuclear Fuels Storage & Transportation Planning Project Office of Fuel Cycle Technologies Nuclear Energy

More information

The MIT Research Reactor as a National User Facility for Advanced Materials and Fuel Research

The MIT Research Reactor as a National User Facility for Advanced Materials and Fuel Research The MIT Research Reactor as a National User Facility for Advanced Materials and Fuel Research Lin-wen Hu John Bernard IGORR-TRTR Joint Meeting September 12-16, 2005 Gaithersburg, MD Overview of the The

More information

Welcome to Taishan NP site

Welcome to Taishan NP site Welcome to Taishan NP site 1 Content Project Introduction Project Progress Main Tasks in 2011 2 Site Conditions TSNP is situated at Yaogu village of Chixi town in Taishan city, Guangdong province, 70km,

More information

Steam Generator Tube Inspection I

Steam Generator Tube Inspection I Steam Generator Tube Inspection I Regulatory Efforts to Manage Alloy 600 Materials Degradation in Korea S-C. Kang, H-S. Shin, J-K. Hong, Korea Institute of Nuclear Safety, Republic of Korea ABSTRACT The

More information

Westinghouse AP1000. Reactor

Westinghouse AP1000. Reactor Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment

More information

Small Modular Reactors The Real Nuclear Renaissance?

Small Modular Reactors The Real Nuclear Renaissance? Small Modular Reactors The Real Nuclear Renaissance? Institute of Physics, Nuclear Industry Group Birchwood, 25 May 2016 Juan Matthews FInstP Dalton Nuclear Institute and School of Materials The University

More information

Decommissioning of Nuclear Facilities. Waste Management

Decommissioning of Nuclear Facilities. Waste Management Decommissioning of Nuclear Facilities Waste Management Lesson Objectives Describe the requirements and methods for managing waste from decommissioning Review IAEA and US waste classification systems Review

More information

Nuclear Power Advocacy in California

Nuclear Power Advocacy in California Nuclear Power Advocacy in California Eric L. Harvey Senior Engineer ERIN Engineering, Inc. February 27, 2014 Plant Bowen in Cartersville, GA The largest coal plant in the US, which consumes 1100 tons coal

More information

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576 Factors Impacting Decommissioning Costs 13576 Karen Kim*, Richard McGrath* *Electric Power Research Institute, 342 Hillview Ave., Palo Alto, California. USA. kkim@epri.com, rmcgrath@epri.com ABSTRACT The

More information

nalcofabtech.com A Nalco Champion Company

nalcofabtech.com A Nalco Champion Company nalcofabtech.com A Nalco Champion Company 2 CONTENTS Goal Zero - Safety Culture...4 About Us...6 Capabilities...8 Services...24 Equipment and Facilities... 36 3 4 At Nalco FabTech, our programs ensure

More information

Project Management. Section Six: Turnover Process

Project Management. Section Six: Turnover Process Project Management Section Six: Turnover Process 1 Performance Objectives 1. Define turnover 2. Implement steps necessary for smooth turnover 3. Use a checklist to facilitate a turnover meeting for a new

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

Large University Central Chiller Plant Design Considerations

Large University Central Chiller Plant Design Considerations Carrier Engineering Newsletter Volume 5, Issue 3 Large University Central Chiller Plant Design Considerations Large campus chilled water plants have unique constraints and need careful evaluation for successful

More information

Overview for a feasibility study

Overview for a feasibility study Overview for a feasibility study What, Why & Objectives of Feasibility Study? International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready to

More information

OUR EXPERIENCE: BALLAST WATER MANAGEMENT SYSTEM (BWMS) RETROFIT

OUR EXPERIENCE: BALLAST WATER MANAGEMENT SYSTEM (BWMS) RETROFIT OUR EXPERIENCE: BALLAST WATER MANAGEMENT SYSTEM (BWMS) RETROFIT Presented By: Chandru Sirumal Rajwani (CEO of N-KOM) PREFERRED SHIPYARD DELIVERING SOLUTIONS ERHAMA BIN JABER AL JALAHMA SHIPYARD CONTENTS

More information

Dissimilar Metal Welds (DMW) in German LWR s. Design Types, Disbonding, NDT. W. Mayinger, K.J. Metzner E.ON Kernkraft, Hannover, Germany

Dissimilar Metal Welds (DMW) in German LWR s. Design Types, Disbonding, NDT. W. Mayinger, K.J. Metzner E.ON Kernkraft, Hannover, Germany Dissimilar Metal Welds (DMW) in German LWR s Design Types, Disbonding, NDT W. Mayinger, K.J. Metzner E.ON Kernkraft, Hannover, Germany 2 Scope Scope Flaws/Cracks in Dissimilar Metal Welds (DMW) 1. Interfacial

More information

Best Construction Practices and Splicing for Fiber Networks

Best Construction Practices and Splicing for Fiber Networks Best Construction Practices and Splicing for Fiber Networks Simon Salamanca Sr Systems Engineer, Carrier Networks Engineering Services Corning Optical Communications 07/26/2016 Agenda 1 Cable 101 2 Splicing-

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) Direct Testimony of David A. Schlissel Synapse Energy Economics, Inc.

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) Direct Testimony of David A. Schlissel Synapse Energy Economics, Inc. BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE PETITION OF ENTERGY ARKANSAS, INC. FOR A DECLARATORY ORDER APPROVING REPLACEMENT OF THE STEAM GENERATORS AND REACTOR VESSEL CLOSURE HEAD

More information

TVA Women In Nuclear Se2ng the Bar to Power Our Future

TVA Women In Nuclear Se2ng the Bar to Power Our Future TVA Women In Nuclear Se2ng the Bar to Power Our Future Camille Stringfellow Nuclear Reactor Operator, WBN WIN Site Chair Victoria Dennis Online Work Control Superintendent, TVA WIN Chair January 30, 2015

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

Nuclear Costs in Context

Nuclear Costs in Context Nuclear Costs in Context Prepared by the Nuclear Energy Institute August 2017 The Nuclear Energy Institute is the nuclear energy industry s policy organization. This white paper and additional information

More information

TAKEN FROM A DOE TECHNOLOGY SUMMARY ON THE CONCRETE SHAVER DEMONSTRATED AT THE HANFORD SITE, RICHLAND, WA

TAKEN FROM A DOE TECHNOLOGY SUMMARY ON THE CONCRETE SHAVER DEMONSTRATED AT THE HANFORD SITE, RICHLAND, WA The Marcrist Industries Limited Concrete Shaver is an electrically driven, selfpropelled concrete and coating removal system that can be used for radiological decontamination of large areas or hot spots

More information

WM 00 conference, February 27 March 2, 2000, Tucson, AZ

WM 00 conference, February 27 March 2, 2000, Tucson, AZ WM 00 conference, February 27 March 2, 2000, Tucson, AZ REACTOR PRESSURE VESSEL REMOVAL AT A BOILING WATER REACTOR WITH SPENT FUEL IN THE ADJACENT FUEL POOL By Albert A. Freitag, WMG, Inc Greg Harttraft,

More information

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS Todd Brumfield World Association of Nuclear Operators (WANO) Atlanta, Georgia, USA ABSTRACT: The requirements for performance of pre-startup reviews

More information

Dry storage systems and aging management

Dry storage systems and aging management Dry storage systems and aging management H.Issard, AREVA TN, France IAEA TM 47934 LESSONS LEARNED IN SPENT FUEL MANAGEMENT Vienna, 8-10 July 2014 AREVA TN Summary Dry storage systems and AREVA Experience

More information

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants 2016 OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants The company is certified according to three management systems: Certificate stn en iso 9001:2008 Quality management system

More information

EGCSA May 2017 WORKSHOP

EGCSA May 2017 WORKSHOP EGCSA May 2017 WORKSHOP DAY 1 AGENDA (22 nd May 2017) 9.00hrs REGISTRATION & REFRESHMENTS 9.20hrs Workshop introduction, H&S, Document and contacts update 9.30hrs BALTEC MARINE RETROFIT INSTALLATION EXPERIENCE

More information

OUTAGE OM&A NUCLEAR. This evidence presents nuclear operations outage OM&A costs for the period

OUTAGE OM&A NUCLEAR. This evidence presents nuclear operations outage OM&A costs for the period Filed: 0-0- Page of.0 PURPOSE OUTAGE OM&A NUCLEAR This evidence presents nuclear operations outage OM&A costs for the period 0-0..0 OVERVIEW Outage OM&A costs vary year over year depending on the number

More information

FRANCE LWR activities

FRANCE LWR activities FRANCE LWR activities Norbert NICAISE with contributions from AREVA-NP ASN French Nuclear Safety Authority, IRSN French Institute for Radiation Protection and Nuclear Safety (TSO of ASN), CEA French Atomic

More information

Niagara Falls Storage Site Safety Measures During Remediation

Niagara Falls Storage Site Safety Measures During Remediation Niagara Falls Storage Site Safety Measures During Remediation On-Site Worker Protection Community and Environmental Protection Transportation and Disposal Safety Fully enclosed Retrieval Facility Regular

More information

Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201

Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201 Nuclear Aircraft Carrier Inactivation Approach for Waste Management and Exposure Reduction 14201 ABSTRACT Irin P. Hall, Kimberly Grubb and Ashley Williams Newport News Shipbuilding Since 2007, Newport

More information

An Unprecedented Marvel of Science, Technology and Engineering

An Unprecedented Marvel of Science, Technology and Engineering An Unprecedented Marvel of Science, Technology and Engineering B Reactor a major contributor to world history, science, technology and engineering The world s first largescale nuclear reactor Part of the

More information

27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs

27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 27 June 2013 Warsaw, Poland Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 1 Procurement for New Nuclear Programs Nuclear power programs risk and opportunity Supplier

More information

Entergy Nuclear. Simulates nuclear plant maintenance with DS PLM solutions and services

Entergy Nuclear. Simulates nuclear plant maintenance with DS PLM solutions and services DS plm success story Entergy Nuclear Simulates nuclear plant maintenance with DS PLM solutions and services Entergy Nuclear Objectives Upgrade existing nuclear plants to double lifespan Reduce business

More information

Ensure full compliance of your nuclear plant s air- and motor-operated valve program.

Ensure full compliance of your nuclear plant s air- and motor-operated valve program. Ensure full compliance of your nuclear plant s air- and motor-operated valve program. QUIKLOOK 3-FS Valve Diagnostic System Achieve greater efficiency, improve safety, and reduce operations and maintenance

More information

NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS

NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS James K. (Jim) Liming ABSG Consulting Inc. (ABS Consulting) 300

More information

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 Tim Beville Office of Nuclear Energy U.S. Department of Energy Administration

More information

SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND

SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND SEVERE ACCIDENT FEATURES OF THE ALTERNATIVE PLANT DESIGNS FOR NEW NUCLEAR POWER PLANTS IN FINLAND Risto Sairanen Radiation and Nuclear Safety Authority (STUK) Nuclear Reactor Regulation P.O.Box 14, FI-00881

More information

Remote Monitoring of Equipment in Small Modular Reactors

Remote Monitoring of Equipment in Small Modular Reactors A publication of CHEMICAL ENGINEERING TRANSACTIONS VOL. 33, 2013 Guest Editors: Enrico Zio, Piero Baraldi Copyright 2013, AIDIC Servizi S.r.l., ISBN 978-88-95608-24-2; ISSN 1974-9791 The Italian Association

More information

APR1400 Safe, Reliable Technology

APR1400 Safe, Reliable Technology APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics

More information

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT Z.K. Jankovsky The Ohio State University Columbus, USA Email: jankovsky.3@osu.edu

More information

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA OKTOBER 3-6, 2016 1 ANPP * ANPP is located in the western part of Ararat valley 30 km west of Yerevan close to

More information

Database Enhancements for Improved AREVA NP LWR Deposition Model BG Lockamon 11/17/ p.1

Database Enhancements for Improved AREVA NP LWR Deposition Model BG Lockamon 11/17/ p.1 Database Enhancements for Improved AREVA NP LWR Deposition Model BG Lockamon 11/17/2010 - p.1 Database Enhancements for Improved AREVA NP LWR Deposition Model Brian G. Lockamon AREVA NP Inc., Plant Chemistry

More information

Nuclear Services. Put Our Expertise To Work As Your Single Source For Industrial Cleaning And System Maintenance Solutions.

Nuclear Services. Put Our Expertise To Work As Your Single Source For Industrial Cleaning And System Maintenance Solutions. Nuclear Services Put Our Expertise To Work As Your Single Source For Industrial Cleaning And System Maintenance Solutions. Water Blasting Wet and Dry Vacuuming Pneumatic Hydro-Vacuum Excavation Digital

More information

SmartSPEND. KBR SmartSPEND SM. The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns

SmartSPEND. KBR SmartSPEND SM. The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns SM Your Capital Optimized : Project Delivery Execution Strategy Capacity Operations KBR SM The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns KBR SM Approach

More information

High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities

High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities Marina Roewekamp GRS ggmbh, Germany Nicholas Melly,

More information

Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance

Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance Advanced Design of Mitsubishi PWR Plant for Nuclear Renaissance October 28, 2009 Etsuro SAJI General Manager, Reactor Core Engineering Department Mitsubishi Heavy Industries, Ltd. GEN-HSW-9102-0 Contents

More information

Heavy Intermodal Lift & Transport Engineering Considerations

Heavy Intermodal Lift & Transport Engineering Considerations Heavy Intermodal Lift & Transport Engineering Considerations Host: Mike Parnell ITI President/CEO ASME B30 Vice Chair (Cranes & Rigging) ASME P30 Chair (Lift Planning) Guest Speaker: Jim Yates, P.E. SVP

More information

NAVSEA STANDARD ITEM NUMERICAL INDEX

NAVSEA STANDARD ITEM NUMERICAL INDEX NAVSEA STANDARD ITEM NUMERICAL INDEX FY-18(CH-2) ITEM NO. 009-01 General Criteria; 009-02 Environmental Compliance Report for Material Usage at Naval Facility; 009-03 Toxic and Hazardous Substance; control

More information

Construction Technologies and Management of NPP

Construction Technologies and Management of NPP Construction Technologies and Management of NPP Nuclear Power Division Ki Sig Kang International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready

More information

A Discussion of Power Plant Loads and Load Combinations

A Discussion of Power Plant Loads and Load Combinations Technical Paper BR-1893 A Discussion of Power Plant Loads and Load Combinations Authors: D.F. Six Babcock & Wilcox Power Generation Group, Inc. Barberton, Ohio, U.S.A. Presented to: ASCE Structures Congress

More information

AECON POWERS THE INDUSTRY

AECON POWERS THE INDUSTRY POWER GENERATION AECON POWERS THE INDUSTRY For nearly a century, Aecon has worked on numerous power generation projects, from hydroelectric to nuclear plants to the latest in solar power. And over the

More information

Pratt & Whitney. Power Systems MOBILEPAC. Gas Turbine Package. It s in our power.

Pratt & Whitney. Power Systems MOBILEPAC. Gas Turbine Package. It s in our power. Power Systems Pratt & Whitney Power Systems MOBILEPAC Gas Turbine Package TM It s in our power. Pratt & Whitney FT8 MOBILEPAC Gas Turbine Package The MOBILEPAC gas turbine package requires the smallest

More information

Innovation. AREVA Nuclear Products. Delivering the Nuclear Promise. Every. Has a Mission

Innovation. AREVA Nuclear Products. Delivering the Nuclear Promise. Every. Has a Mission Every Innovation Has a Mission AREVA Nuclear Products Delivering the Nuclear Promise 1 Every Innovation Has a Mission Ensuring safe and reliable operations is the driving force for the nuclear industry.

More information