BULK ELECTRIC SYSTEM PLANNING CRITERIA

Size: px
Start display at page:

Download "BULK ELECTRIC SYSTEM PLANNING CRITERIA"

Transcription

1 Part 4 Attachment Kansas City Power & Light Company BULK ELECTRIC SYSTEM PLANNING CRITERIA Harold Wyble, Manager Transmission Planning March 15, 2016

2 Table of Contents 1.0 Introduction KCP&L Transmission Planning Transmission Contingency Analysis Base Case Analysis Loss of Single Component Analysis Loss of Two or More Transmission Components Extreme Contingency Events Required Studies Additional Study Requirements Power Flow Cascading Events Voltage Stability Transient Stability Transmission Planning for Serving New Customer Load Monitoring Transmission System Performance Transmission Reliability Indices Calculation of Available Transfer Capability ATC Calculation and Posting Timeframes Use of the KCP&L Open Access Transmission Tariff Protective Relaying System Restoration Blackstart Capability System Restoration Simulation Document Version History Transmission Planning 3/15/2016 Page 2 of 23

3 1.0 Introduction The primary purpose of the Company s (inclusive of Kansas City Power & Light Company (KCP&L) and KCP&L Greater Missouri Operations Company (GMO)) bulk electric system is to supply our customers with economic and reliable electrical energy. To achieve this objective Transmission Planning has developed minimum planning criteria, which provides the basis for the design and operating criteria of the Company s bulk electric system. This Criteria presents the characteristics of a well-planned bulk power electric system, describes the basis for model testing and lists the reliability and adequacy tests to be used to evaluate the performance of the Company s bulk electric system. Reliable operation of the Company s interconnected bulk electric system requires that the system comply with these Criteria. The Company s Bulk Electric System Planning Criteria meets or exceeds all North American Electric Reliability Corporation (NERC) Reliability Standards and Southwest Power Pool (SPP) Transmission Planning Criteria. Prior to July 2008, GMO was known as Aquila. With the acquisition of Aquila by Great Plains Energy (parent of KCP&L), these Criteria now applies to the former Aquila Missouri electric service territory. In this document KCP&L is inclusive of both KCP&L and GMO service areas. GMO will be used to refer to items only applying to KCP&L Greater Missouri Operations Company. KCP&L is a member of the SPP Regional Transmission Organization (RTO). SPP is one of the eight regional reliability council members of NERC. SPP performs the requirements of a Reliability Coordinator and Planning Coordinator function for KCP&L. KCP&L performs the requirements of a Transmission Operator and Transmission Planner function. The SPP Criteria is revised on an on-going basis as needed to incorporate the policies, standards, and principles by which the coordinated planning and operation of the interconnected electric system is achieved. In February 2005, the NERC Board of Trustees adopted Version 0 of the new NERC Reliability Standards with an effective date for implementation of April 1, These new Reliability Standards define the reliability requirements for planning and operating the North American bulk electric system. They were developed from the previous NERC Operating Policies and Planning Standards into a form that would fit the NERC Reliability Functional Model of the electric utility industry. In 2006, the Federal Energy Regulatory Commission (FERC) certified NERC as the Electric Reliability Organization (ERO), approved a base set of 83 reliability standards, and required NERC to develop a Compliance Monitoring and Enforcement Program (CMEP). In April 2007, FERC approved delegation agreements between NERC and eight (8) regional entities (RE), including SPP, responsible to perform the delegated reliability compliance and monitoring functions. The original set of approved Reliability Standards included four standards on Transmission Planning (TPL) with many requirements and sub-requirements on transmission system performance and regional reliability assessments. These TPL Transmission Planning 3/15/2016 Page 3 of 23

4 standards are applicable to the Planning Authority and Transmission Planner functions of the NERC Reliability Functional Model. In 2013, FERC approved a new Transmission Planning Reliability Standard, TPL-001-4, while simultaneously retiring the previous four standards. This standard establishes transmission system planning performance requirements within the planning horizon to develop a bulk electric system that will operate reliably over a broad spectrum of system conditions and following a wide range of probably contingencies. It is applicable to the Planning Coordinator and Transmission Planner functions. Transmission Planning 3/15/2016 Page 4 of 23

5 2.0 KCP&L Transmission Planning The interconnected transmission system should be capable of performing reliably under a wide variety of expected system conditions while continuing to operate within equipment and electric system thermal, voltage, and stability limits. Electric systems must be planned to withstand contingencies and maintenance outages. Extreme event contingencies, which measure the robustness of the electric systems, should be evaluated for risks and consequences. The NERC Reliability Standards define specific transmission planning requirements that provide reliability for the bulk interconnected electric system. SPP provides coordinated regional transmission planning requirements to promote reliability through its Criteria Section 3, Regional Transmission Planning, and related Attachment O, Coordinated Planning Procedures, in the SPP Open Access Transmission Tariff (OATT). It is the policy of KCP&L to maintain as high an interconnection capability with adjoining systems as is economically prudent. These interconnections with adjoining systems shall be designed such that KCP&L will remain interconnected following all of the more probable transmission and generation outage contingencies as described in the NERC Reliability Standards found in Table 1 of TPL It is recognized that emergencies that occur in adjoining systems can affect KCP&L, just as the emergencies within KCP&L can affect adjoining systems. Therefore, joint studies will be made on a regular basis to investigate various system emergencies that can occur and their effects on the various systems involved. In this way, the effectiveness of existing and planned interconnections will be periodically measured and the design of the system periodically updated so that the interconnection capability and reliability will be maintained. In these activities KCP&L will perform the requirements of the Transmission Planner function as defined in the NERC Reliability Functional Model. Transmission planning criteria for the KCP&L electric system shall at a minimum conform to the NERC Reliability Standards and SPP Transmission Planning Criteria Section 3 and meet the following: a. Excessive concentration of power being carried on any single transmission circuit, multi-circuit transmission line, or right-of-way, as well as through any one transmission station shall be avoided. b. Adequate transmission capability shall be maintained to provide for intraregional, inter-regional and trans-regional power flows under normal and more probable contingency conditions as defined in Table 1 of the NERC Reliability Standards. c. Switching arrangements shall be utilized that permit effective maintenance of equipment without excessive risk to the electric system. d. Switching arrangements and associated protective relay systems shall be utilized that do not limit the capability of a transmission path to the extent of causing excessive risk to the electric system. e. Sufficient reactive capacity shall be planned within the KCP&L electric system at appropriate places to maintain transmission system voltages Transmission Planning 3/15/2016 Page 5 of 23

6 within plus or minus 5% under normal and within plus 5% or minus 10% for contingency conditions, for all busses. Certain transmission busses such as, Northeast, Bull Creek, and Osawatomie require higher voltage levels to provide for successful starting of combustion turbines located there. At those busses KCP&L will maintain additional reactive resources to meet the individual bus voltage requirements. f. KCP&L electric transmission facilities shall be rated, as a minimum, in accordance with KCP&L Transmission Facility Rating Methodology document. KCP&L uses 90 degrees C as the conductor temperature for normal transmission line ratings for ACSR conductors. The strategy for transmission planning at KCP&L is driven primarily by two main goals. The first goal is compliance with reliability standards at the national (NERC/FERC), regional (SPP) and local (KCP&L) levels. The second goal is to provide transmission capacity for existing and new loads and existing and new electric supply resources. Transmission planning for reliability standards compliance is performed for all planning horizons; operational (real time to 1year in future), near term (1 to 5 years in future), and long term (5 to 10 years in future). It generally involves the analysis of the transmission system under various operating conditions, the identification of any reliability standard violations, and the development of plans or actions to mitigate each violation. Transmission planning for capacity expansion to serve loads and new supply resources are performed for both the near term and long term planning horizons. Transmission planning must interface with the planning performed by the Distribution Provider and Resource Planner functions of the NERC Reliability Functional Model. The Distribution Provider provides input on the size and location of loads to the transmission planning process. The Resource Planner provides the size and locations of future resources through the SPP process. Long term transmission planning is performed to develop an overall plan for expansion of the transmission system. This would include the approximate capacity and location of transmission assets required for future operations. Near term transmission planning is performed to refine portions of the long-term transmission plan on localized areas and provide more definition of required transmission assets. Another part of transmission expansion is driven by transmission service requests and generation interconnection requests made to SPP as the RTO. KCP&L participates in SPP s transmission system planning process to assess the ability of the transmission system to provide these requested services in the near and long term planning horizons. This includes development of plans or new transmission asset additions that will be required to meet reliability standards if the requested services are granted. Transmission Planning 3/15/2016 Page 6 of 23

7 2.1 Transmission Contingency Analysis The KCP&L transmission system shall be planned and constructed so that the contingencies as set forth in these Criteria will meet the applicable NERC Reliability Standards for Table 1 of TPL and SPP Transmission Planning Criteria and their applicable requirements and measurements. Table 1 was developed to thoroughly search out the most severe, credible contingencies for study, creating the assurance that the many possible contingencies not studied are less severe. It lists the normal and contingency conditions under which the electric transmission system is to be analyzed. It also lists the limits or impacts that the transmission system can sustain and still meet an acceptable performance level Base Case Analysis KCP&L will support and participate in the SPP Model Development Working group (MDWG) development and verification of base case transmission system models. KCP&L base case models will maintain at least the following attributes: System facilities shall be modeled to reflect normal operating conditions and limits Line and equipment loading shall be within normal rating limits. Voltage levels shall be maintained within plus or minus 5% of nominal voltage All customer electrical demands shall be supplied, and all contracted firm (non-recallable reserved) transfers shall be maintained. Stability (dynamic and steady state) of the network shall be maintained. Cascading outages shall not occur Loss of Single Component Analysis KCP&L will perform single contingency studies under the following conditions: Initiating incident results in a single element out of service. Line and equipment loadings shall be within emergency rating limits. Voltage levels shall be maintained within plus 5% or minus 10% of nominal voltage for all busses. No loss of customer electric demand (except as allowed through Attachment 1 of TPL-001-4). No curtailment of contracted firm (non-recallable reserved) transfers shall be required. Stability (angular and voltage) of the network shall be maintained. Cascading outages shall not occur. Transmission Planning 3/15/2016 Page 7 of 23

8 2.1.3 Loss of Two or More Transmission Components KCP&L will perform contingency studies under the following conditions: Initiating incident may result in two or more (multiple) components out of service including common right-of-way and common structure circuits. Line and equipment loadings shall be within emergency thermal rating limits. Voltage levels shall be maintained within plus 5% or minus 10% of nominal voltage for all busses. Stability (angular and voltage) of the network shall be maintained. Planned outages of customer demand or generation (as noted in Table 1 of TPL-001-4) may occur. Contracted firm (non-recallable reserved) transfers may be curtailed. Cascading outages shall not occur Extreme Contingency Events KCP&L will perform contingency studies where extreme contingency events could lead to uncontrolled cascading outages or system instability. KCP&L shall document the measures and procedures to mitigate or eliminate the extent and effects of those events. 2.2 Required Studies KCP&L participates in all SPP coordinated planning studies and performs internal load flow, transient stability and voltage stability studies to meet NERC Reliability Standards compliance. These studies will consider all contingencies applicable to the appropriate NERC Table 1 of TPL-001-4, Category P1 through P7 events. Annually, KCP&L will perform summer and winter peak operating studies for the upcoming seasons. Intermediate range studies covering the two to five year planning horizons to address both intra- and interregional reliability will be performed as needed. A 10-year expansion planning study will be conducted no less than biannually. 2.3 Additional Study Requirements Power Flow Cascading Events As a proxy for cascading conditions, transmission facilities found to be loaded at 120% of the emergency rating (Rate B) or greater should be tripped offline. The removal of ten or more transmission branches will serve to indicate cascading. Similarly, bus voltages exceeding 70% to 120% nominal following an event should be tripped offline. The removal of five or more transmission buses will serve to indicate cascading. Transmission Planning 3/15/2016 Page 8 of 23

9 2.3.2 Voltage Stability For voltage stability studies, stability shall be maintained under single and multiple contingencies throughout the KCP&L area. The performance and voltage stability criteria listed below will be followed: Critical voltage (voltage at bottom of V-Q curve) and reactive power margin should be sufficient such that stability is ensured following the loss of nearby reactive power sources and Reactive capacity shall be sufficient to ensure that transmission system voltage is maintained within plus 5% or minus 10% of nominal for single contingencies. Q 0 Negative Reactive power Positive Reactive Unstable Critical Voltage Marginally Stable Voltage (pu / kv) Reactive Margin Stable Nominal Voltage Collapse Point (Nose) Figure 1: V-Q Curve Transient Stability For transient stability studies, generator rotor angle and transient voltage stability shall be maintained between KCP&L and neighboring systems following the loss of an electric network component and associated equipment tripped by the protection scheme following a line-to-ground fault, a three-phase fault, or a breaker open resulting in an open-ended transmission line. For faults, normal and stuck breaker clearing times shown in Table 1 will be used to assess stability; backup clearing times will be used as needed per the TPL standard. Breaker clearing times are derived in Table 2, Table 3, and Table 4 per the KCP&L System Protection group. Times in Table 1 are rounded up to the nearest quarter-cycle due to limitations in simulation software. Transmission Planning 3/15/2016 Page 9 of 23

10 To develop the clearing times in Table 2 through Table 4, the KCP&L System Protection group evaluated the entire KCP&L system and provided the slowest clearing times for normal clearing, stuck breaker clearing, and backup clearing. Most KCP&L equipment utilizes faster clearing. Table 1 Simulated 345 kv and 161 kv Breaker Clearing Times used in Simulations Nominal Equipment Voltage (kv) Normal Clearing Time Stuck Breaker Clearing Time Backup Clearing Time cycles ( s) 21.0 cycles (0.350 s) cycles ( s) cycles ( s) 11.0 cycles (0.183 s) 5.0 cycles (0.083 s) Nominal Equipment Voltage (kv) Table 2: Normal Clearing Time Derivation Longest Primary Pickup Setting (cycles) Communications Delay (cycles) Breaker Clearing Time (cycles) Total Clearing Time (cycles) Nominal Equipment Voltage (kv) Table 3: Stuck Breaker Clearing Time Derivation Longest Primary Breaker Communications Pickup Clearing Time Delay (cycles) Setting (cycles) (cycles) Total Clearing Time (cycles) Nominal Equipment Voltage (kv) Table 4: Backup Clearing Time Derivation Longest Backup Pickup Setting (cycles) Communications Delay (cycles) Breaker Clearing Time (cycles) Total Clearing Time (cycles) For normal clearing time, the worst-case scenario is an internal breaker fault. Such a fault would be detected by the primary relaying and be communicated to adjacent breakers. Worst-case normal clearing times (including the delay for communication time) are used for TPL P0 through P3, P6, and P7 events. Transmission Planning 3/15/2016 Page 10 of 23

11 For stuck breaker clearing time, the fault is detected by the appropriate relay(s) and normal clearing time passes. When the relay detects that a trip signal was sent but the fault was not cleared, an instantaneous trip signal is communicated to the adjacent relays. Worst-case stuck breaker clearing times are used for TPL P4 and Extreme events. For most extreme events, the stuck breaker time is the longest that should be used. For backup clearing time, the only 100 kv and above elements on KCP&Ls system that does not have redundant relaying is a subset of bus differential relays. The clearing time for 345 kv is a great deal faster than that for the 161 kv system because the 345 kv system uses communication-assisted tripping on both the primary and backup relaying which allow faster detection and slightly slower-than-normal clearing in the event of a relay failure. The 161 kv system has communication on the primary relaying only which causes its backup relaying depend on Zone 2 clearing by distant relays. Backup clearing should only be used for those system elements which do not have redundant relays for TPL P5 and Extreme events Transient Stability Performance Requirements Transient stability analysis results will be evaluated using the SPP Disturbance Performance Criteria to identify events that may potentially cause system instability and uncontrolled separation. The SPP Criteria uses two components to define stability: generator rotor angle damping and transient voltage recovery. Machine Rotor Angles shall exhibit well damped angular oscillations (as shown in Figure 2) and acceptable power swings following a disturbance on the Bulk Electric System. Any time after a disturbance is cleared bus voltages on the Bulk Electric System shall not swing outside of the bandwidth of 0.70 per unit to 1.20 per unit (shown in Figure 3). Transient Voltage Recovery Following the clearing of a fault, if any KCP&L or first-tier neighbor bus voltage is unable to recover to 0.75 per-unit within 0.05 seconds (3 cycles; primary recovery) or 0.9 perunit within 2.5 seconds (150 cycles; secondary recovery), the initiating event will be considered potentially unstable. The primary criterion was chosen to help catch potential Fault Induced Delayed Voltage Recovery (FIDVR) events which may cause small single-phase motors to stall if voltages do not recover quickly and cause further voltage recovery issues. The secondary voltage recovery criterion was selected to help screen for issues which may require load shedding or cause tripping of generation. Transient Voltage Dip Following the clearing of a fault, if any KCP&L or first-tier neighbor bus voltage recovers to 0.9 per-unit or higher then drops below 0.9 per-unit for 0.25 seconds (15 cycles), the initiating event will be considered potentially unstable. This criterion was chosen to help flag areas of the system where initial voltage recovery is sufficient but sagging voltages may indicate deteriorating system stability. Transmission Planning 3/15/2016 Page 11 of 23

12 Figure 2: Example of Successive Positive Peak Ratio (SPPR) Requirements Voltage (per unit) Time (seconds) Figure 3: Example of Transient Voltage Recovery Requirements Cascading Event Requirements KCP&L uses several thresholds to determine if an event may potentially cause cascading. If an event causes facilities other than those specified by the protection scheme (or otherwise prescribed by the event definition) to trip and it meets one of the criteria thresholds, the event will be marked as potentially cascading and must be reviewed by an engineer. The criteria are defined as follows: Number of Additional Bus Trips Additional bus trips refer to buses which are not tripped as part of the protection scheme in order to clear a specified fault. TPL P1 events are not allowed to trip any additional buses Transmission Planning 3/15/2016 Page 12 of 23

13 TPL P2-P7 events are allowed to trip a generator and associated facilities only if that generator is tripped to clear the fault TPL Extreme and Other events allow up to 5 additional buses to be tripped before the event is considered potentially cascading Number of Additional Branch Trips Additional branch trips refer to branches which are not tripped as part of the protection scheme in order to clear a specified fault. TPL P1 events are not allowed to trip any additional branches TPL P2-P7 events are allowed to trip a generator and associated facilities only if that generator is tripped to clear the fault TPL Extreme and Other events allow up to 10 additional branches to be tripped before the event is considered potentially cascading Number of Additional Generator Trips If more than eight additional generators trip, an event will be considered potentially cascading. Amount of Generation Tripped If a MW amount equaling or greater than KCP&Ls largest generating plant trips offline, an event will be considered potentially cascading. Average Rate of Decline (ROD) for Generation Cascading may occur even if one of the previous generator criteria are not met. Therefore, it is desirable to determine an average rate at which generation can trip before it requires further investigation. The allowable average amount of generation which can be tripped by a certain number of generators is obtained using the following formula (assuming the maximum number of generator trips has not been recorded): Equation 1: Maximum Allowed Average Amount of Generation which can be tripped. The average amount must include only generation tripped as a result of out-of-step or angular stability conditions (not as prescribed by the event) and is the MW amount of generation tripped divided by the number of generators tripped. If the average value calculated is greater than the maximum average determined using Equation 1, the event should be flagged as potentially cascading. This limit is shown graphically in Figure 4 assuming the maximum allowable generation trip is 1700 MW. Transmission Planning 3/15/2016 Page 13 of 23

14 Figure 4: Graphical Representation of Maximum Average Generation Trip assuming a 1700 MW Maximum Amount of Load If 10 percent or more of the online KCP&L load is shed, an event will be considered potentially cascading. Voltage Thresholds As a proxy for cascading conditions, KCP&L will screen KCP&L and Tier-1 neighbor buses for voltage magnitudes exceeding the range of 120% - 70% of nominal at the end of a transient stability simulation. Such bus voltages may indicate sever voltage issues and delayed system recovery which could lead to potential system cascading and/or uncontrolled separation. Thermal Loading Thresholds As a proxy for cascading conditions, KCP&L will screen KCP&L and Tier-1 neighbor transmission lines and power transformers at the end of the transient stability simulation for facilities loaded at or above 120% of the emergency thermal limit (Rate B). Such facilities may indicate severe system conditions and delayed recovery which could lead to potential system cascading and/or uncontrolled separation. Crashed Simulations If a simulation crashes it will be regarded as potentially cascading and will be reviewed to determine why it crashed and if the event may cause cascading. Transmission Planning 3/15/2016 Page 14 of 23

15 Discovery of a Potentially Cascading Event Upon discovery of a potentially cascading event, Transmission Planning will review the event in greater detail to determine if it is a legitimate concern. This analysis may include but is not limited to: Checking the simulated event against switching one-lines to determine event accuracy Contacting system protection to determine that the clearing times used in the simulation were accurate for the prescribed event Rerunning the simulation for a longer period of time (e.g., 30 seconds) Checking modeled KCP&L load and generation dispatch Reviewing system topology for modeling errors If the detailed analysis determines the event was simulated properly and the system is modeled correctly, the event should be considered cascading. The following actions may be taken to mitigate the issues: 1. Revise breaker clearing times 2. Consider revising generator governor/exciter settings 3. Consider revising generator protection settings 4. Consider adding a power system stabilizer to one or several units 5. Consider EHV transmission projects at or near affected generator stations 6. Consider adding additional generation in the affected area Transmission Planning 3/15/2016 Page 15 of 23

16 2.4 Transmission Planning for Serving New Customer Load Distribution Planning Engineering has traditionally planned for serving existing and new load additions on the KCP&L distribution systems (<69kV). This includes deciding when new transmission sources are needed to meet increased demand on the distribution system due to overloaded distribution facilities or inadequate distribution voltage profiles. These new substations are incorporated into KCP&L s transmission expansion plan by optimizing the existing transmission system network or expanding the system into these areas. Historically KCP&L has provided new transmission sources for the distribution system by either inserting new load serving substations in existing transmission lines when possible or building new transmission lines to connect the new substations. In areas where expansion of the 34kV system is no longer the prudent solution, converting these 34kV loads to 12kV requires new 161/12kV substations. Inserting new substations in existing lines was done for reasons of economics and site requirements. This practice has led to transmission lines with numerous two terminal load serving substations along their length. Operational and reliability problems can arise from this practice when the amount of total load served by these substations exceeds the capability of the transmission lines serving them with the outage of one end of the line. To avoid these problems KCP&L has established the following planning criteria for the number of two-terminal substations between source substations and building the second transmission line into a radial substation: During normal or contingency conditions, when the amount of connected load-serving transformer capacity on a transmission path serving only two terminal substations exceeds the normal rating of any of the transmission lines between the source substations or when the third two-terminal substation is added between source substations, a third transmission source shall be required that connects into one of the two-terminal substations. However, the installation of this new line is dependent on site, availability of right-of-way and environmental considerations. A second transmission source shall be required for a radial substation when the radial substation load cannot be served from backup distribution sources for the outage of the radial transmission line. The timing of this new transmission line is also dependent on site, availability of right-of-way and environmental considerations. At the time of the acquisition of Aquila, the GMO system was reviewed to determine if it met the requirements of section 2.4 of the Criteria. There were areas of the GMO system identified that did not meet the requirements of section 2.4. Plans will be developed in the future to bring those areas into accord with these Criteria, subject to siting, availability of right-of-way and environmental considerations. Transmission Planning 3/15/2016 Page 16 of 23

17 3.0 Monitoring Transmission System Performance An important part of transmission planning is monitoring transmission system performance. This includes monitoring the performance of sections Line, Transformer, Switchgear, and Substations within the transmission system and benchmarking the overall performance of the KCP&L transmission system against past performance. To accomplish this effort KCP&L s Transmission Planning has an interdepartmental work group which analyzes transmission outages on a monthly basis. This group produces an annual report entitled KCP&L Transmission System Reliability Indices Report. 3.1 Transmission Reliability Indices Five Transmission Reliability Indices have been established to monitor Transmission System performance: (1) Frequency of Outages - SAIFI T, (2) Duration of Outages SAIDI T, (3) Transmission System Availability - Availability T, (4) Forced Outages per Hundred-line Mile Year - FOHMY, and (5) Transmission Minutes of Load Unserved - TMLU. These indices provide quantitative measures of transmission system reliability annually. All of the above reliability indices are based on only automatic forced outages in the transmission system for 69kV, 161kV, 230kV, and 345kV facilities. Transmission reliability indices are evaluated monthly, quarterly, and annually to monitor transmission system performance and are used to recommend corrective measures to maintain and/or improve transmission system reliability. Transmission outages are broadly classified by Transmission Availability Data System (TADS) cause codes. All transmission outages are recorded including those due to Major Event Days (MED). Some outages may be excluded if they meet the following exclusion criteria to provide comparability and meaningful results for transmission reliability improvement analysis and recommendations. Exclusion Criteria: IEEE 1366 MED s plus storm days preceding/following a MED, if the impact was significant. All Class II storms were included, provided they did not exceed the Institute of Electrical and Electronics Engineers (IEEE) 1366 Tmed level. The IEEE outlines a statistically based threshold based on a company s own daily outage data (up to 5 immediately preceding years). This threshold (labeled Tmed, for Threshold major event day) is labeled a MED, or Major Event Day. The IEEE is a Distribution Reliability Criteria standard. Transmission Planning 3/15/2016 Page 17 of 23

18 4.0 Calculation of Available Transfer Capability The calculation of Available Transfer Capability (ATC) is a very complex and dynamic procedure. KCP&L realizes that there are many technical and policy issues concerning the calculation of ATC that will evolve with industry changes. A key element of NERC s ATC principles is Regional or wide-area coordination is necessary to develop and post information that reasonably reflects the ATC s of the interconnected transmission network. Therefore, KCP&L will follow SPP guidelines and methodology as outlined in Section 4.0 of SPP Criteria. SPP takes a regional approach in the determination of Available Transfer Capability (ATC). The regional approach calls for SPP to evaluate the inter-area transfer capability of its Transmission Owners (i.e. KCP&L). This approach provides a high level of coordination between ATC reported by SPP and Transmission Owners on SPP Open Access Same-time Information Network (OASIS) nodes. The SPP utilizes a constrained element approach in determining ATC. This approach is referred to as a Flowgate ATC methodology. Constrained facilities, termed flowgates, used in this approach are identified primarily from a non-simultaneous transfer study using standard incremental transfer capability techniques that recognize thermal, voltage and contractual limitations. Stability limitations are studied as needed. Flowgates serve as proxies for the transmission network and are used to study system response to transfers and contingencies. Using flowgates with pre-determined ratings, this process is able to evaluate the ATC of specific paths on a constrained element basis (flowgate basis) while considering the simultaneous impact of existing transactions. The calculation of ATC is a very complex and dynamic procedure. SPP realizes that there are many technical and policy issues concerning the calculation of ATC that will evolve with industry changes. Therefore, the SPP Operating Reliability Working Group and the SPP Transmission Working Group will have the joint authority to modify the implementation of Section 4 of the Criteria based on experience and improvements in technology and data coordination. Any changes made by these groups will be subject to formal approval as outlined in the SPP By-laws at the first practical opportunity. The determination of ATC via Flowgates utilizes proxy elements to represent the power transmission network. This process depends on the selected Flowgates to act as predetermined limiting constraints to power transfer. The process by which ATC will be determined when using the Flowgate proxy technique incorporates the Definitions and Concepts within SPP Criteria 4. Transmission Planning 3/15/2016 Page 18 of 23

19 Determination of ATC via Flowgates adheres to the following approach: Establishes a network representation (power flow model). Identifies potential limits to transfer (thermal, voltage, stability, contract). Determines response factors of identified limits relative to transfer directions (Transfer Distribution Factor - TDF). Determines impacts of existing commitments (Firm, Non-Firm) Applies margins (Transmission Reliability Margin - TRM, Capacity Benefit Margin - CBM, a & b multipliers). Determines maximum transfer capabilities allowed by limits and applied margins (ATC, Firm ATC, and Non-Firm ATC). 4.1 ATC Calculation and Posting Timeframes To assist Transmission Providers with Short-Term service obligations under FERC Order 888 and 889, SPP will calculate the monthly path ATC for the upcoming 16- months for all potential commercial paths for Transmission Providers in the SPP Region. This data will be posted for use in evaluating the SPP OATT requests. Daily and Weekly ATC is calculated on a daily basis and posted at the time of run. SPP will also provide control area/balancing areas (CA/BA) to CA/BA path conversions to any individual providers needing that information to administer their own tariff. Hourly calculations are done hourly for anywhere from 12 to 36 hours ahead depending on time of day. SPP has a firm-scheduling deadline at 12:00 noon, day prior to start. At this point all firm schedules are known and the hourly non-firm request window opens for the next day. Then, SPP calculates hourly ATC for HE 14 of the current day through HE 24 of the next day. This process continues dropping the current hour each resynchronization until 12:00 noon the next day when the cycle starts again. 4.2 Use of the KCP&L Open Access Transmission Tariff SPP functions as KCP&L s Transmission Service Provider under the SPP OATT. Grandfathered transmission service schedules that used the KCP&L Open Access Transmission Tariff have been converted to the SPP OATT. New requests for transmission service must be arranged through the Southwest Power Pool. Transmission Planning 3/15/2016 Page 19 of 23

20 5.0 Protective Relaying Protective relaying, communications and instrumentation play an important role in maintaining the reliability of the bulk electric system. Protective Relay Systems (PRS) requirements shall be taken into account during the planning and design of generation, transmission and substation configurations. If configurations are proposed that require PRS that do not conform to SPP criteria or to accept IEEE/ANSI practices, then the entities affected shall negotiate a solution. The principles for planning additions in these categories are set forth in SPP Criteria. a. The bulk power protective relay system design shall have as its objective rapid clearing of all faults, with no fault permitted to remain uncleared despite the failure of any single protective system component. To accomplish this, transmission protection systems shall be installed as specified in the SPP Transmission Protection Systems Criteria 7.2. b. Transmission Operators shall maintain communications systems to their generating stations, operation centers and to neighboring utilities, which shall provide adequate communication in the event of failure of any one element of the systems. In general, such communication systems should not be susceptible to failure during an interruption of the A.C. power supply in any part or all of their areas. c. Loading on the bulk electric system shall be monitored continually to insure that operation is within safe limits. d. Suitable instrumentation, and/or other devices, shall be installed to measure appropriate quantities at key points in the electric system with appropriate automatic alarms. e. Fault recording devices as described in SPP Criteria 7.1 shall be installed at appropriate points within KCP&L so that outages and short circuits can be analyzed and protective relay performance studied. In addition, Disturbance Monitoring Equipment shall be provided to meet SPP Criteria 7.1 so those system disturbances may be analyzed. f. Underfrequency Load Shedding (UFLS) equipment shall be installed pursuant to SPP Criteria 7.3 for the purpose of maintaining a stable operating frequency. g. Given the requirements of SPP Criteria 7.6, Automatic Restoration of Load schemes may be installed by KCP&L to expedite load restoration. These systems shall be coordinated with all other schemes such as system protection, Underfrequency Load Shedding, Undervoltage Load Shedding, and Generation Control and Protection. These systems shall operate only after underfrequency and/or undervoltage events. h. Generation Control and Protection schemes shall be designed pursuant to SPP Criteria 7.7 to provide a reasonable balance between the need for the generator to support the interconnected electric systems during abnormal conditions and the need to adequately protect generator equipment from damage. Transmission Planning 3/15/2016 Page 20 of 23

21 6.0 System Restoration NERC Reliability Standard EOP-005 deals with system restoration. A blackout is a condition where a major portion or all of an electrical network is de-energized resulting in loss of electric supply to a portion or all of that network s customer demand. Blackouts will generally take place under two typical scenarios: Dynamic instability, and Steady-state overloads and/or voltage collapse. Blackouts are possible at all loading levels and all times in the year. Changing generation patterns, scheduled transmission outages, off-peak loadings resulting from operations of pumped storage units, storms, and rapid weather changes among other reasons can all lead to blackouts. Systems must always be alert to changing parameters that have the potential for blackouts. Actions required for system restoration include identifying resources that will likely be needed during restoration, determining their relationship with each other, and training personnel in their proper application. Actual testing of the use of these strategies is seldom practical. Simulation testing of restoration plan elements or the overall plan is essential preparation toward readiness for implementation on short notice. From a planning standpoint, it is critical that any overall system restoration plans include adequate generating units with system blackstart capability. It is also important that adequate facilities are planned for the interconnected transmission systems to accommodate the special requirements of system restoration plans such as switching and sectionalizing strategies, station batteries for dc loads, coordination with underfrequency and undervoltage load shedding programs and Regional or area load restoration plans, and facilities for adequate communications. KCP&L has developed its own specific plans to deal with Capacity and Energy Emergency, Load Shedding Emergency, and Transmission System Emergency. 6.1 Blackstart Capability Following the complete loss of system generation (blackout), it will be necessary to establish initial generation that can supply a source of electric power to other system generation and begin system restoration. These initiating generators are referred to as system blackstart generators. They must be able to self-start without any source of offsite electric power and maintain adequate voltage and frequency while energizing isolated transmission facilities and auxiliary loads of other generators. Generators that can safely reject load down to their auxiliary load are another form of blackstart generator that can aid system restoration. Transmission Planning 3/15/2016 Page 21 of 23

22 From a planning perspective, a system blackstart capability plan is necessary to ensure that the quantity and location of system blackstart generators are sufficient and that they can perform their expected functions as specified in overall coordinated Regional system restoration plans. In the event that the KCP&L Load Shedding Emergency Procedures are unsuccessful in reducing customer load to maintain system voltage and frequency, KCP&L may be faced with a situation where generating units are isolated serving only its own auxiliaries or units are not on line and all customer loads has been interrupted. Interruption of service may encompass the KCP&L service territory or possibly the entire region and many utilities. A KCP&L System Restoration Plan has been developed to systematically restore generation and customer load to the KCP&L service territory (including GMO). Detailed generating unit startup procedures and transmission switching instructions can be found in the KCP&L System Restoration Plan. 6.2 System Restoration Simulation Requirement R6 of NERC Reliability Standard EOP is stated below. R6. Each Transmission Operator shall verify through analysis of actual events, steady state and dynamic simulations, or testing that its restoration plan accomplishes its intended function. This shall be completed every five years at a minimum. Such analysis, simulations or testing shall verify: R6.1. The capability of Blackstart Resources to meet the Real and Reactive Power requirements of the Cranking Paths and the dynamic capability to supply initial Loads. R6.2. The location and magnitude of Loads required to control voltages and frequency within acceptable operating limits. R6.3. The capability of generating resources required to control voltages and frequency within acceptable operating limits. KCP&L Transmission Planning performs dynamic and steady state system restoration simulation studies using the PSSE power flow model every five years at a minimum. These simulation studies verify that the KCP&L Blackstart Resources are capable to meet the real and reactive power requirements along the primary transmission restoration path and the dynamic capability to supply initial loads. Study results also verify the location and magnitude of loads, and the capability of generating resources required to control voltages and frequency within acceptable operating limits. Transmission Planning 3/15/2016 Page 22 of 23

23 Document Version History The following table documents changes to this document and its predecessors. Date Document Description KCP&L Planning Criteria.pdf Minor formatting changes; added clarity to breaker clearing times; added cascading criteria for load flow and transient stability; split study requirements into required studies and additional requirements KCP&L Planning Criteria.pdf Reviewed and updated document to reflect new TPL standard and disturbance performance criteria KCP&L Planning Criteria.pdf Removed Section 5 of Bulk Electric System Planning Criteria to its own document. Reviewed and updated entire document as necessary KCP&L Planning Criteria.pdf Reviewed and updated Bulk Electric System Planning Criteria KCP&L Planning Criteria.pdf Reviewed and updated Bulk Electric System Planning Criteria; included addition of section clarifying rating of substation infrastructure facilities KCP&L Planning Criteria.pdf Reviewed and updated Bulk Electric System Planning Criteria KCP&L Planning Criteria.doc Reviewed and updated Bulk Electric System Planning Criteria KCP&L Planning Criteria.doc Reviewed and updated Bulk Electric System Planning Criteria FINAL 2003 KCPLcriteria.doc Reviewed and updated Bulk Electric System Planning Criteria Final 2002 KCPLcriteria.doc Reviewed and updated Bulk Electric System Planning Criteria FINAL 2001 KCPLcriteria Reviewed and updated Bulk Electric System Planning Criteria FINAL1998 KCPLcriteria Reviewed and updated Bulk Electric System Planning Criteria. Transmission Planning 3/15/2016 Page 23 of 23

Southwest Power Pool CRITERIA

Southwest Power Pool CRITERIA Southwest Power Pool CRITERIA LATEST REVISION: April 28, 2015 FOREWORD... i INTRODUCTION... ii 1.0 LOAD AND ENERGY FORECASTS...1-1 2.0 CAPACITY MARGIN...2-1 2.1 Definitions...2-1 2.1.1 Load Serving Member...2-1

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

NERC Reliability Functional Model

NERC Reliability Functional Model NERC Reliability Functional Model Function Definitions and Responsible Entities Version 3 Approved by Standing Committees: Operating Committee: December 6, 2006 Planning Committee: December 6, 2006 Standards

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Standard TPL-004-0a System Performance Following Extreme BES Events

Standard TPL-004-0a System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-0a 3. Purpose: System simulations

More information

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard TPL-002-0b System Performance Following Loss of a Single BES Element A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically

More information

Standard TPL System Performance Under Normal Conditions

Standard TPL System Performance Under Normal Conditions Standard TPL-001-0.1 System Performance Under rmal Conditions Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when

More information

Standard TPL (i) System Performance Under Normal Conditions

Standard TPL (i) System Performance Under Normal Conditions Standard TPL-001-0.1(i) System Performance Under rmal Conditions A. Introduction 1. Title: System Performance Under rmal ( Contingency) Conditions (Category A) 2. Number: TPL-001-0.1(i) 3. Purpose: System

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 Project 2014-03 Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 This mapping document showing the translation of Requirements in the following currently-enforceable

More information

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated Standard FAC-008-1 Facility Ratings Methodology Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Statement of Compliance Registry Criteria (Revision 5.2) Summary This document describes how the North American

More information

Approved by Standing Committees Approved by Board of Trustees

Approved by Standing Committees Approved by Board of Trustees Reliability Functional Model Function Definitions and Responsible Entities Prepared by the Functional Model Working Group Version 4 Approved by Standing Committees Approved by Board of Trustees August

More information

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating ALR1-1 Generator Reactive Limit Metric:Voltage schedules How many times did generators encounter var limits associated with holding voltage schedule. 10 3 2 1 1 3 1 Initial pilot effort completed, reaching

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

Reliability Coordinator Area System Operating Limit Methodology

Reliability Coordinator Area System Operating Limit Methodology Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Standard EOP System Restoration from Blackstart Resources

Standard EOP System Restoration from Blackstart Resources A. Introduction 1. Title: System Restoration from Blackstart Resources 2. Number: EOP-005-2 3. Purpose: Ensure plans, Facilities, and personnel are prepared to enable System restoration from Blackstart

More information

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities These definitions will be posted and balloted along with the standard, but will not be restated in the standard. Instead, they will be included in a separate Definitions section containing definitions

More information

Standard EOP System Restoration from Blackstart Resources

Standard EOP System Restoration from Blackstart Resources A. Introduction 1. Title: System Restoration from Blackstart Resources 2. Number: EOP-005-2 3. Purpose: Ensure plans, Facilities, and personnel are prepared to enable System restoration from Blackstart

More information

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper Toward Ensuring Reliability: Reliability Performance Metrics A NERC Staff White Paper Table of Contents Table of Contents Table of Contents... 2 Executive Summary... 3 Metrics Objective... 5 Metrics Background...

More information

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

Criteria. C~/v~ ~ ~ ~ G!  A1A ~ Tg'~10N COr'P''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria A1A "~"" T"""g"'~10N COr'P""''~ Criteria Department: Document No: System Planning and Strategic Projects P LG -C R-0001-V 19.2 T~c~e: Transmission System Planning Criteria issue gate: Previous Date: February

More information

Security Guideline for the Electricity Sector: Identifying Critical Assets

Security Guideline for the Electricity Sector: Identifying Critical Assets Note: The guideline was developed for CIP-002-1 but is also applicable to CIP- 002-2 and CIP-002-3. Security Guideline for the Electricity Sector: Identifying Critical Assets Disclaimer: This supporting

More information

by the Transmission Planner or Planning Coordinator.

by the Transmission Planner or Planning Coordinator. A. Introduction 1. Title: Undervoltage Load Shedding 2. Number: PRC 010 2 3. Purpose: To establish an integrated and coordinated approach to the design, evaluation, and reliable operation of Undervoltage

More information

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions Seminar on African Electrical Interconnection Module 8 - Interconnected Systems Operating Conditions Module 8 - Interconnected Systems Operating Conditions Contents 1) Technical Operating Agreements 2)

More information

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403 AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination

More information

PRC Under Voltage Load Shedding

PRC Under Voltage Load Shedding A. Introduction 1. Title: Undervoltage Load Shedding 2. Number: PRC-010-2 3. Purpose: To establish an integrated and coordinated approach to the design, evaluation, and reliable operation of Undervoltage

More information

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log Revision Log Page 2 of 13 Revision or Change Number Effective Date Affected Page Numbers Description of Revision/Change 0000 03-26-2011 All Converted TPD document to SPP format 0001 03-26-2012 All Annual

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

TPL 001 AB 0 System Performance Under Normal Conditions

TPL 001 AB 0 System Performance Under Normal Conditions Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure

More information

Standard FAC System Operating Limits Methodology for the Planning Horizon

Standard FAC System Operating Limits Methodology for the Planning Horizon Standard FAC-010-1 System Operating Limits Methodology for the Planning Horizon Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy

More information

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria 5/1/2018 OC Meeting PJM Manual M36 System Restoration A.1 Critical Black Start Criteria A.1.1 Goal PJM and its stakeholders have developed requirements for the amount and redundancy of Black Start generation

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

Glossary of Terms Used in Reliability Standards

Glossary of Terms Used in Reliability Standards Version 0 Draft 3 November 1, 2004 Adequacy Adjacent Balancing Authority Agreement The ability of the electric system to supply the aggregate electrical demand and energy requirements of the end-use customers

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0 No. RC0610 SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 1.0 By California Independent System Operator (CAISO RC) No. RC0610 Table of Contents A. Conventions... 5 B. Introduction

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

Glossary of Terms Used in Reliability Standards

Glossary of Terms Used in Reliability Standards Version 0 Draft 4 January 7, 2005 Adequacy Adjacent Balancing Authority Agreement The ability of the electric system to supply the aggregate electrical demand and energy requirements of the end-use customers

More information

Appendix 5B. Statement of Compliance Registry Criteria

Appendix 5B. Statement of Compliance Registry Criteria Appendix 5B Statement of Compliance Registry Criteria Revision 5.1 Effective: July 1, 2014 (as noted below) The highlighted terms Bulk Electric System and Load in this document will become effective as

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

SPP RTO Compliance Forum TPL Jason Terhune

SPP RTO Compliance Forum TPL Jason Terhune SPP RTO Compliance Forum TPL-001-4 Jason Terhune 501-688-8261 jterhune@spp.org 1 TPL Standards have been Consolidated TPL-001-0.1 TPL-002-0b TPL-003-0b TPL-004-0a TPL-001-4 R1 R2 R3 R4 R5 R6 R7 R8 2 Overview

More information

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS Draft 7/15/14 rev7 1 B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS A. Reliability Rule NYCA transmission facilities in the NYS Bulk Power System shall be planned to operate reliably over a

More information

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY

More information

NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System

NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System Version 18 January 5, 2007 NYSRC RELIABILITY RULES For Planning and Operating the New York State Power System Version

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Transmission Planning Procedures and Planning Criteria TDOG108

Transmission Planning Procedures and Planning Criteria TDOG108 Transmission Division Operating Guidelines Transmission Planning Procedures and Planning Criteria TDOG108 Page 1 of 33 Approved by: William R. Kaul, Vice President Transmission Approved date: 10/13/16

More information

FERC Directives in Order 693 Addressed in IROL Implementation Plan

FERC Directives in Order 693 Addressed in IROL Implementation Plan The following Interconnection Reliability Operating Limit (IROL) standards were under development when the Version 0 project was initiated: IRO-008 Reliability Coordinator Operational Analyses and Real-time

More information

Northwest Power Pool Processes

Northwest Power Pool Processes Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed

More information

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards Mapping Document Project 2007-06.2 Phase 2 of System Protection Coordination Revisions or Retirements to Already Approved Standards This mapping document explains how each of the existing Requirements

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA The following information submitted for this Part 4 of FERC Form No. 715 consists of PJM's current Planning Criteria, and each member

More information

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering 2017 ITPNT 2 0 1 7 I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e June 15, 2016 Engineering Revision History Date or Version Number Author Change Description Comments

More information

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households

More information

Methodology PLG-METH-0002-V1

Methodology PLG-METH-0002-V1 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V1 Title: Transmission Planning Assessment Practices Issue Date: September 27, 2012 Previous Date: Nov. 18, 2011

More information

Meeting Agenda Adequate Level of Reliability Task Force

Meeting Agenda Adequate Level of Reliability Task Force Meeting Agenda Adequate Level of Reliability Task Force June 28, 2012 8:00 a.m. to 3:00 p.m. ET APPA Offices (in the Universal North Building) 1875 Connecticut Avenue NW 12th Floor Main Conference Room

More information

Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1

Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1 Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1 Proposed Draft Standard The drafting team proposes to revise existing standard EOP-005 to incorporate IV.A.M2 and IV.A.M3. IV.A.M2 is translated into requirements

More information

A. Introduction. B. Requirements and Measures

A. Introduction. B. Requirements and Measures A. Introduction 1. Title: System Restoration from Blackstart Resources 2. Number: EOP-005-3 3. Purpose: Ensure plans, Facilities, and personnel are prepared to enable System restoration from Blackstart

More information

Project Single Points of Failure TPL-001 Cost Effectiveness

Project Single Points of Failure TPL-001 Cost Effectiveness Project 2015-10 Single Points of Failure TPL-001 Cost Effectiveness Known Outages FERC Order No. 786 FERC Order No. 786 Paragraph 40 directs a change to address the concern that the six month threshold

More information

Consequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis

Consequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis Consequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis VIJAY VITTAL, FELLOW, IEEE Invited Paper The electric utility industry is undergoing

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic Load shedding (UFLS) to support

More information

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Conforming Changes to Requirements in s None Coordination with revisions proposed in other standards projects The IROL SDT proposes retiring

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic underfrequency Load shedding

More information

NSPI BULK POWER FACILITIES CONNECTION GUIDE Report number NSPI-TPR-002-2

NSPI BULK POWER FACILITIES CONNECTION GUIDE Report number NSPI-TPR-002-2 NSPI BULK POWER FACILITIES CONNECTION GUIDE Report number NSPI-TPR-002-2 July, 2010 TABLE OF CONTENTS DOCUMENT APPROVAL...ii REVISION RECORD...iii 1.0 INTRODUCTION... 1 2.0 APPLICATION OF THIS GUIDE...

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

Technical Report Supporting Definition of Adequate Level of Reliability

Technical Report Supporting Definition of Adequate Level of Reliability Technical Report Supporting Definition of Adequate Level of Reliability 1.0 Introduction The Adequate Level of Reliability Task Force (ALRTF or Task Force) was formed in May 2011 under the auspices of

More information

Project System Operating Limits

Project System Operating Limits Project 2015-09 System Operating Limits Technical Conference Background Materials These background materials were prepared by members of the Standard Drafting Team solely for use in conjunction with the

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards

Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Draft for Planning Committee Review 3353 Peachtree Road

More information

SPP at a Glance. Located in Little Rock. Approximately 600 employees

SPP at a Glance. Located in Little Rock. Approximately 600 employees SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Statement of Compliance Registry Criteria (Revision 3.1)

Statement of Compliance Registry Criteria (Revision 3.1) Statement of Compliance Registry Criteria (Revision 3.1) Summary Since becoming the Electric Reliability Organization (ERO), NERC has initiated a program to identify candidate organizations for its compliance

More information

Definition of Adequate Level of Reliability

Definition of Adequate Level of Reliability Definition approved by Operating Committee and Planning Committee at their December 2007 OC and PC meetings Definition of Adequate Level of Reliability 116-390 Village Boulevard, Princeton, New Jersey

More information

Load Shed Philosophy

Load Shed Philosophy APPLICABILITY: Reliability Coordinator I. Background While time limits exist for mitigation of the exceedance of certain types of system operating limits, events can occur quickly necessitating a responsive

More information

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite

More information