Document Control and Version Information

Size: px
Start display at page:

Download "Document Control and Version Information"

Transcription

1 Soham Station Capacity Assessment Registered in England No Document Control and Version Information Project Title Author Soham Station Ed Jeffery Version number 1.0 Status Final Date 1 st July 2016 pg. 1 Ed Jeffery Ltd Registered in England No

2 2 Soham Station 0 Executive Summary This study has considered the provision of a new station at Soham (funded by Cambridgeshire County Council) following the deferral of the planned doubling scheme between Ely and Soham. Different infrastructure options have been tested for Soham station against several potential future service increments on the route. The key finding is that the provision of a station at Soham has a minimal impact on available capacity (a 2% increase in capacity use of the single line with an hourly passenger service). Using a single platform station on the existing single track, a call can be provided in all of today s Ipswich Peterborough (and return) trains with only minimal impact to other services. Additional infrastructure is required in the Soham area and other parts of the network to accommodate 1 tph Ipswich to Peterborough and if the levels of freight increase from today s approximate one train per hour each way. This is true whether Soham station is provided or not. Although two freight trains per hour each way can be accommodated with the single platform station (and therefore the existing length of single track), the capacity use is very high and poses a high performance risk. The operation of three freight trains per hour each way would trigger a longer section of partial doubling. The high capacity use also results in a lack of timetable flexibility. This reduced flexibility combines with other constraints elsewhere, such as: Headways south of Kennett Single lead at Haughley Junction Single track sections between Cambridge and Chippenham Junction If the freight service is to be increased (particularly in conjunction with an increase to the Ipswich Cambridge/Peterborough passenger services), consideration should also be given to overcoming the highlighted constraints (the primary constraint being the signalling headways south of Kennett). This study has also considered the doubling of the service between Cambridge and Ipswich to two trains per hour. This is not possible on the current infrastructure due to the length of single track between Dullingham and Coldham Lane Junction, and the associated signalling. An intervention on this section is required to double the service, regardless of what happens on the route between Ely and Soham. pg. 2 Ed Jeffery Ltd Registered in England No

3 3 Soham Station 1 Document Control 1.1 Version History VERSION UPDATED SECTION(S) REASON FOR UPDATE UPDATED BY DATE 0.1 All First Draft Ed Jeffery 27/05/ All Incorporating comments Ed Jeffery 01/07/2016 Contents 0 Executive Summary Document Control Version History Introduction Objective Service Specification Other assumptions Findings Test 1 (current service levels) Test Test Test 4a Test 4b Soham Station Design Conclusions and Recommendations Summary of conclusions for each service level Soham station infrastructure Recommendations Appendix A: Test 3 sample timetable Appendix B: Test 4a sample timetable pg. 3 Ed Jeffery Ltd Registered in England No

4 4 Soham Station 2 Introduction The main route between Ipswich and Cambridge and Ely leaves the Great Eastern Main Line (GEML) at Haughley Junction, running via Bury St. Edmunds before splitting towards Cambridge and Ely at Chippenham Junction (Figure 1). Figure 1: Location map Passenger services on the route comprise an hourly service between Ipswich and Cambridge (calling at most stations) and a two-hourly service between Ipswich and Peterborough via Ely calling at main stations, which would potentially call additionally at Soham. There are currently no intermediate stations between Chippenham Junction and Ely. The route between Haughley Junction and Ely is also a vital part of the Felixstowe to Nuneaton (F2N) cross-country freight route. This provides an alternative route (as opposed to running via London) for intermodal freight traffic between Felixstowe and destinations in the midlands and north of Britain (via Ely, Peterborough, Leicester and Nuneaton). A large freight scheme (the F2N project) is currently involved in providing a significant upgrade to this whole route. The F2N project has identified that a key constraint to increasing freight traffic on the route is the section of single line between Soham and Ely Dock Junction. Early analysis proposed full doubling of this section to accommodate future freight growth, but engineering feasibility studies indicated that this would be very expensive. Since then, a series of capacity studies have been undertaken by Network Rail looking at various options for partial doubling (e.g. Ely Soham Doubling Report, November 2013). However, the Ely - Soham doubling scheme was deferred to CP6 in late 2015 as part of the Enhancement Delivery Plan (formed through the Hendy Review). pg. 4 Ed Jeffery Ltd Registered in England No

5 5 Soham Station A linked scheme is the provision of a new station at Soham between Ely and Chippenham Junction. This scheme is being promoted by Cambridgeshire County Council and is currently in GRIP 3. However, the deferral of the Ely Soham doubling scheme has meant additional analysis is required to understand the feasibility of the new station with and without the associated doubling scheme. 2.1 Objective The objective of this report is to summarise analysis undertaken into the feasibility of providing a station at Soham in several different scenarios (the existing layout is shown in Figure 2): A single platform on the existing railway (on the single line) before Ely - Soham doubling occurs A double platform station with either a shorter or a longer section of new double track in the Soham area (either before or in conjunction with a partial Ely Soham doubling) A double platform station in conjunction with or after the full Ely Soham doubling is delivered Figure 2: Current layout between Chippenham Junction and Ely (simplified) 2.2 Service Specification As well as the feasibility of trains calling at the station with the current service levels, there is a requirement to demonstrate that the station itself does not preclude the operation of a future service increase in the area. As such, a number of different service levels have been defined to be tested here (Table 1). Service Group Test 1 Test 2 Test 3 Test 4a Test 4b pg. 5 Ed Jeffery Ltd Registered in England No

6 6 Soham Station (today) Peterborough Ipswich Cambridge Ipswich Freight As today As today As today 2 2 Table 1: Numbers of trains per hour (tph) for defined service levels 2.3 Other assumptions The December 2015 timetable has been used as the base for this work All technical values in this report have been calculated using RailSys o All work is compliant with Version 3.0 of the RailSys Standards issued by Network Rail Passenger trains have been modelled as Class Freight trains have been modelled as Class t 1 It is worth noting that there may be changes to rolling stock subject to the East Anglia franchise announcement pg. 6 Ed Jeffery Ltd Registered in England No

7 3 Findings This section summarises the analysis undertaken as part of this project. Sections marked in bold represent key conclusions and recommendations. 3.1 Test 1 (current service levels) The starting point to test the current service levels is to see if the calls can be accommodated on a single platform station on the existing infrastructure. The station platform was assumed to be on the single line section just beyond the existing crossover at Soham (Figure 2). RailSys was used to calculate Technical Running Times (TRT) which was used to suggest new Indicative Running Times (IRT) (Table 2). In the future, these will need to be approved for use as new Sectional Running Times (SRT). Section Current SRT (passing) (min) Calculated TRT (stopping) (sec) Proposed IRT (stopping) (min) Chippenham - Soham Soham Ely Dock Jn Ely Dock Jn - Soham Soham - Chippenham Table 2: Current and proposed running times The running time penalty for calling at the station is therefore 30 seconds. This is because the linespeed is relatively low (50mph) and there is some excess time in the current SRTs. Combined with the Timetable Planning Rules (TPR) value of 30 seconds for a multiple unit dwell time, the total journey time penalty of a station call is therefore 1 minute. Table 3 shows how this can be accommodated in all of the current Ipswich Peterborough trains. In the off-peak, trains have up to 2 minutes pathing time approaching Ely in order to find a slot through the highly-used infrastructure at Ely and Ely North Junction. This can be reduced to accommodate the station call and therefore there is no overall journey time penalty. Only two amendments to other services are required and both require redistribution of additional allowance (for 1T17 King s Lynn Kings Cross and 1L48 Birmingham New Street Stansted Airport). pg. 7 Ed Jeffery Ltd Registered in England No

8 8 Soham Station For two trains (2E70 and 2E72) there is a 1 minute journey time extension as these do not have allowance to be reduced. Train ID Departure from Soham Station Comments Ipswich 2E Runs 1 minute later Ely - Peterborough 2E Runs 1 minute later Ely Peterborough. Allowances moved in 1T17 (from approaching Cambridge to approaching Ely) 2E Pathing time reduced 2E Pathing time reduced 2E Pathing time reduced 2E Pathing time reduced 2E Dwell reduced at Ely. Allowance moved in 1L48 (from approaching Cambridge to approaching Ely) 2E Pathing time reduced Table 3: Northbound services calling at Soham and amendments required to other services Table 4 shows how the station call can be accommodated in all of the current Peterborough Ipswich services. All trains have an additional 30 seconds dwell time at Ely which can be used to recover half of the time required. For the remainder of trains, they either have pathing time approaching Ipswich which can be reduced or an adjustment at Ipswich (to allow arrival on a whole number of minutes) which can be removed. Therefore, the call can be accommodated without journey time extension or amendment to other services. pg. 8 Ed Jeffery Ltd Registered in England No

9 9 Soham Station Train ID Departure from Soham Station Comments Peterborough 2L Ely dwell reduced by 30s. Pathing at Ipswich reduced by 30s 2L Ely dwell reduced by 30s. Pathing at Ipswich reduced by 30s 2L Ely dwell reduced by 30s. Pathing at Ipswich reduced by 30s 2L Ely dwell reduced by 30s. 30s adjustment removed at Ipswich 2L Ely dwell reduced by 30s. 30s adjustment removed at Ipswich 2L Ely dwell reduced by 30s. 30s adjustment removed at Ipswich 2L Ely dwell reduced by 30s. 30s adjustment removed at Ipswich. 6M44 requires adjustment (runs later between Soham and Peterborough, no overall impact) Table 4: Southbound services calling at Soham and amendments required to other services A stop at Soham (on a single platform station) can be accommodated in all current Peterborough Ipswich (and return) services. Minimal amendments to other services are required and the majority of trains have no overall journey time increase despite the station call. The call at Soham will increase the occupation of the single line by marginally more than 30 seconds (the remainder of the penalty for calling is on the double-track section between Soham and Chippenham Junction). Even with two trains per hour calling, the overall impact on the capacity of this section is therefore low. The total 1 minute calling penalty has been accommodated by reducing excess allowances and dwell times elsewhere. This could potentially have a performance impact as the amount of buffer is reduced. However, given the relatively low reduction in buffer and relatively few trains impacted, the performance impact is likely to be low. pg. 9 Ed Jeffery Ltd Registered in England No

10 10 Soham Station 3.2 Test 2 The increment for Test 2 over Test 1 is an increase in the Ipswich Peterborough service to 1 tph instead of one train every two hours. The impact of Soham station on this increment is negligible. Currently, although the service is two hourly, the length of route means that trains cross just north of Chippenham Junction on the double track section. This would continue with an hourly service, and the findings for Soham station will be the same as for Test 1. The barrier to increasing the service to hourly will be the impact on other trains. Most other passenger services in the region operate on an hourly (or half-hourly) basis. Therefore, as the Peterborough - Ipswich trains can be accommodated within this pattern when they currently run two-hourly, they can also be accommodated when they run hourly. It is likely that non-standard paths may be required in the peak hours (as is done today) in order to fit around other peak service increases. Any significant potential conflicts will therefore occur with freight services, which use the released capacity when not currently used by passenger services. This is likely to occur in two ways: At Ely North Junction and through March/Whitemoor to Peterborough (outside the scope of this study) On the F2N route between Ipswich/Haughley Junction to Ely. The solution to the second point is likely to be the standardisation of freight paths. Currently, due to the lower occupancy of the route, trains operate in a non-standard way with different timings in most hours. This means that some freight trains use the spare passenger paths when they do not run today; therefore, most freight in these opposite hours are likely to conflict with an hourly passenger service. The F2N philosophy (driven by the increase in freight traffic) is to move to a standard hourly timetable with defined freight paths, however due to the complexity of freight schedules and the number of interacting geographical areas standardising freight paths is difficult. The ability to run more trains through Ely North Junction is also limited due to the number of trains that run over the Queen Adelaide and Kiln Lane level crossings throughout a 24 hour period, and thus an intervention would still be required here to allow any increase of service, be it freight or passenger. F2N projected the end of CP4 (2015) freight levels as 24 trains per day per direction (in practice this is lower as less growth has materialised). This equates to roughly 1 standard train per hour each direction (with 2 tph in some hours if an 18 hour traffic day is assumed). pg. 10 Ed Jeffery Ltd Registered in England No

11 11 Soham Station The current level of freight in the Working Timetable (WTT) is between 0 and 2 tph each direction during the day, although this averages to 1 tph. In some hours, a freight train runs in each direction through Soham as well as the passenger service (i.e. 4 tph total). Therefore, the current level of freight can be accommodated in an hourly path through Soham, however the constraints at Ely North would still need resolving alongside the adjustment of some current freight paths into a standardised path. The capacity to operate this level of service in a nonstandardised pattern is proven by the fact that it operates in some hours today. As an example of how this would work: Train 4M09 (Felixstowe Hams Hall) currently passes Haughley Jn at 1315 ½ in an hour when the passenger train does not run today This path would be used by the hourly Ipswich Peterborough train The previous hour, the Ipswich Peterborough train runs and an intermodal path passes Haughley Jn at 1230 ½. 4M09 could therefore use this path in the next hour, passing Haughley Jn at 1330 ½. With reduced pathing time and dwell time at Soham, there would only be a 5 minute difference at Ely The provision of a Soham station call has no impact on the ability to increase the Ipswich Peterborough (and return) service to hourly. This can be accommodated on a single platform station. However, the issues with level crossings at Ely North Junction would prevent any increase in freight and passenger services. Increasing the Ipswich Peterborough (and return) service to hourly will likely require the retiming of current freight paths into a standardised hourly path (although all current paths could be accommodated). This would require further feasibility analysis outside the current scope (e.g. at Ely North Junction). 3.3 Test 3 The increase from Test 2 is the increment for the Cambridge Ipswich service to 2 tph. Between Chippenham Junction and Coldham Lane Junction (outside Cambridge), the line is single track with a passing loop at Dullingham (Figure 3). pg. 11 Ed Jeffery Ltd Registered in England No

12 12 Soham Station Figure 3: Current layout (simplified) Chippenham Jn - Coldham Lane Jn The journey time between Coldham Lane Junction and Chippenham Junction is approximately 23 minutes (including dwell time). This means to operate a 2 tph service each way (4 tph total), trains must pass once on this section; the only opportunity to do this is at Dullingham. The Timetable Planning Rules (TPR) are specific for how passing at Dullingham occurs (due to a mixture of signalling and level crossing constraints): Down train arrives and departs 2.5 minutes later Up train arrives 2 minutes after Down train arrives; departs 1 minute later The running time between Coldham Lane Jn and Dullingham is 13 minutes (in both directions). Combined with the TPR values above, this means that the following events sequence represents the optimal situation: xx.00: Down train passes Coldham Lane xx:13: Down train arrives Dullingham xx:15: Up train arrives Dullingham xx.15 ½: Down train departs Dullingham xx:16: Up train departs Dullingham xx:29: Up train passes Coldham Lane However, the next Down train must pass Coldham Lane at xx.30 and therefore, as the junction margin is 3 minutes, this is not possible. In fact, to operate a 2 tph service each way would take 64 minutes every hour. Potential solutions to overcome this involve reducing the junction margins at Dullingham or reducing the time taken to transit the single line sections, such as: A signalling solution to allow simultaneous arrivals and departures at Dullingham pg. 12 Ed Jeffery Ltd Registered in England No

13 13 Soham Station Line Speed Improvements (LSI) to reduce the journey time between Dullingham and Coldham Lane Extension of Dullingham Loop towards Cambridge Doubling of Coldham Lane Junction and a section of the Dullingham line A new loop somewhere between Dullingham and Coldham Lane In order to provide 2 tph in each direction between Ipswich and Cambridge, an infrastructure intervention is required between Dullingham and Coldham Lane Junction. It is recommended that this is investigated further if the service increase is required. To assess the potential impact of Soham station on the 2 tph service, for the remainder of this section (and also Test 4b), it is assumed that some form of infrastructure intervention has been implemented between Coldham Lane and Dullingham. The journey time between Dullingham and Chippenham Junction (with an intermediate stop at Newmarket) is in the order of 10 minutes. Therefore, this means that the gap between a southbound train exiting the single line at Chippenham Junction and reoccupation of the single line by a northbound train needs to be around 10 minutes as well. This means the paths need to be changed from today s timetable (as they current cross at Chippenham Junction). The impact at Cambridge is beyond the scope of this work. A sample standard hour timetable is shown in section 5 (Appendix A) for Test 3. An approximate half-hourly service is provided between Ipswich and Cambridge in each direction (the exact timings will depend on the stopping patterns of the two trains). An hourly Ipswich Peterborough train (stopping at the single platform at Soham) and hourly freight service is also shown. The key constraints to improving this service are: Long signalling headways between Kennett and Haughley Junction The single lead junction at Haughley Junction Interaction with the Liverpool St Norwich trains The key constraint is actually the headway between Kennett and Haughley Junction (Table 5). Section Down Up Chippenham Junction - Kennett One train in section One train in section Kennett Bury St. Edmunds 7 8 pg. 13 Ed Jeffery Ltd Registered in England No

14 14 Soham Station Bury St. Edmunds Haughley Jn 6 6 Table 5: Planning headways Chippenham Junction - Haughley Junction Although there are only four trains in each direction (and the headway is at worst 8 minutes), this acts as a constraint because of: The need to link a path over the single line sections at Dullingham or Soham to a path on the GEML The desire the have a reasonably spaced passenger service along the route (e.g. at Bury St. Edmunds) As can be seen from the sample timetable, the impact of the Soham call on these constraints are minimal due to the requirement to space paths out appropriately and the relatively low occupation of the route between Soham and Ely Dock Jn. Test 3 can be delivered south of Chippenham Junction (assuming infrastructure is provided between Dullingham and Coldham Lane Junction. The key constraint is the long signalling headway south of Kennett. Soham station has a minimal impact on these constraints. 3.4 Test 4a Test 4a includes an hourly Peterborough Ipswich service (although the Cambridge Ipswich service remains as today) and an increased 2 tph each way freight service on the F2N route. This represents the maximum level of service tested between Soham and Ely Dock Junction. On the option with a single platform at Soham station, the reoccupation of the single line when trains call at Soham was tested using RailSys and found to have a technical value of 2m44s. This therefore just fits within the standard value of 3 minutes (which is also applied at Ely Dock Junction). As both passenger and freight have a 6 minute transit time between Soham and Ely Dock Junction (including the dwell time for the passenger service), the theoretical capacity of the section can be calculated: Transit time of each train + reoccupation time = 9 mins Number of paths = 60 mins / 9 mins = 6.7 paths (rounded down to 6 paths per hour) This equates to 54 minutes every hour used (and hence 6 minutes spare). It is possible to increase the total number of paths to 8 per hour but this requires maximum flighting of trains (i.e. all trains in pg. 14 Ed Jeffery Ltd Registered in England No

15 15 Soham Station one direction in the first half hour, and the opposite direction in the second half hour). This is not realistic in terms of desired train service or the available capacity and service pattern south of Chippenham. The practical maximum number of trains on the single line between Soham and Ely Dock Junction (with calls at a single platform station) is 6 tph. This is also the service level required for Tests 4a and 4b. Therefore, these can be accommodated in theory on the single platform layout, albeit with 54 out of every 60 mins used. The impact of this is that there is relatively little flexibility in trains using the Ely-Soham section to be moved to meet constraints elsewhere. The high occupation represents a performance risk as well. It should also be noted that the current Timetabling Planning Rules require 1 minute of engineering allowance approaching Ely Dock Junction. This artificially increases the occupation of the single line. Although this would still allow 6 tph to operate, the hourly capacity usage would increase to 57 minutes and the amount of flexibility would be reduced further (and performance risk increased). It is essential that the location of engineering allowance on the single line section approaching Ely Dock Junction is reassessed and moved to a more practical location if possible (e.g. approaching Soham). A sample timetable is given in section 6 (Appendix B). The majority of the spare capacity each hour has been used to keep the Peterborough Ipswich paths in approximately their current slots (the southbound path runs slightly later south of Ely). This means the remainder of the hour mostly uses minimum margin reoccupations of the single line. This could be reduced if the passenger paths were moved, but this is outside the scope of this study (e.g. finding new paths over Ely North Junction). This lack of flexibility is shown in the single line occupation diagram (Figure 4) which shows trains occupying the single line for a standard hour. pg. 15 Ed Jeffery Ltd Registered in England No

16 16 Soham Station Northbound Southbound Freight Freight Freight Freight Freight Freight Freight Passenger Passenger Passenger Passenger Freight Physical occupation by train Required headway / reoccupation time Spare' capacity providing performance buffer Figure 4: Occupation of single line section between Soham and Ely Dock Junction. pg. 16 Ed Jeffery Ltd Registered in England No

17 17 Soham Station 3.5 Test 4b Test 4b overlays the 2 tph Cambridge Ipswich service onto Test 4a. As can be seen by comparison between the sample timetables in sections 5 and 6), the additional freight paths use some of the passenger paths south of Chippenham Junction. It is not possible to move either set of paths north of Chippenham Junction due to the constraints of the respective single line sections. It may be possible to find a solution, but this would require unfeasibly high amounts of pathing time. This is due to the same constraints identified for Test 3 in section 3.3. The key constraint is again the long block sections south of Kennett. Due to the constraints on the routes via Dullingham and Soham, there is not a suitable solution to deliver Test 4b. The key constraint is the long headways south of Kennett and this should be considered in more detail if increases in both freight and passenger (Ipswich Cambridge) are to be implemented. 3.6 Soham Station Design Sections 3.1 to 3.5 show that it is generally possible to deliver the required service levels using the single platform station at Soham (where it is not possible, the station layout is not a key constraint). However, when the levels of freight increase, the occupation of the single line between Soham and Ely Dock Junction increases and (as well as reducing timetabling flexibility) increases the performance risk. This is not driven by the need to call at Soham station (i.e. it would still potentially be an issue if Soham still were not provided), but modifications to Soham station and the single line station may help reduce performance risk. Four designs are considered here: A single platform station on the existing single track A double platform station with a short section of extra double track (assumed to be as far as the Soham side of Middlemere Level Crossing, about 700m from the station location) A double platform station with a longer section of extra double track (assumed to be as far as the Ely side of Middlemere Level Crossing, about 1100m from the station location) A double platform station with full double tracking between Soham and Ely RailSys has been used to calculate indicative margins for the reoccupation of the single line at Soham: Single platform: 3 minute reoccupation of the single line (2m 44s technical value) pg. 17 Ed Jeffery Ltd Registered in England No

18 18 Soham Station Short double track: 2.5 minute reoccupation of the single line (timed at Soham station, 2m00s technical value). Down passenger trains can depart 1 minute after Up train arrives (to allow time for route resetting due to lack of intermediate signals) Long double track: 2 minute reoccupation of the single line (timed at Soham station, 1m20s technical value). Down passenger trains can depart simultaneously with arrival of Up train (intermediate signal assumed to be provided) Double track: assumed to be timed as a single block (i.e. 6 minute headway). Likely to be pessimistic if a reduced headway is achievable (e.g. 3 minutes) These assumed values can then be used to calculate theoretical capacity use for a range of timetable specification / infrastructure combinations (Table 6 ). It should be noted that this is an indicative value and does not represent a full Capacity Utilisation Index (CUI) value. Infrastructure Service specification Minutes per hour used Capacity use (%) Today (no station) Today (no station) Single platform Single platform Short double track Long double track 1 freight, 1 passenger (no call at Soham) 2 freight, 1 passenger (no call at Soham) 1 freight, 1 passenger (call Soham) 2 freight, 1 passenger (call Soham) 2 freight, 1 passenger (call Soham) 2 freight, 1 passenger (call Soham) Full doubling 2 freight, 1 passenger (call Soham) Table 6: Calculated capacity usage of the single line section Soham - Ely Dock Junction pg. 18 Ed Jeffery Ltd Registered in England No

19 19 Soham Station Calling at Soham on a single platform station increases capacity use by approximately 2%. Adding an extra freight train in each direction increases capacity use by approximately 30%. Therefore, it is freight growth that is the primary driver for capacity use. Providing extra infrastructure at Soham does decrease capacity use (by approximately 10% for a short double track and 17% for a longer double track). This provides more timetabling flexibility and performance buffer. This applies whether Soham station is provided or not. Infrastructure Option Total paths for freight (sum of both directions) Today (no station) 4 Single platform station 4 Short double track 5 Long double track 6 Full double track 5 (in each direction) Table 7: Maximum freight capacity for each option (all options include 1 passenger each way and are rounded down to the nearest whole number). This represents the maximum capacity and therefore represents a performance risk in operating this level of service. In order to increase the number of freight paths to 3 tph each way (as may occur in the medium term), a minimum of the long double track option is required. pg. 19 Ed Jeffery Ltd Registered in England No

20 4 Conclusions and Recommendations The key conclusion from this analysis is that the provision of calls at Soham has a minimal impact on available capacity. The need for additional infrastructure at Soham is due to other factors (primarily freight growth) and would be required (in lieu of full doubling) even if Soham station were not provided. Calls can be provided at Soham in today s timetable with minimal impact on other services through reduction of existing excess allowance and dwell times. There is also minimal impact if an hourly Ipswich Peterborough service is provided, although this has other timetable impacts independent of Soham station (such as the need to standardise freight paths). Additional infrastructure only needs to be considered if the freight levels increase above today s approximate 1 path per hour in each direction. Even then the service can be provided, albeit at a high level of capacity use (and therefore performance risk). This is summarised in Table 8. Freight Service Level 1 tph each way (today) 2 tph each way 3 tph each way 1 platform station (before Ely-Soham doubling) 2 platform station & short double track (before Ely-Soham doubling) 2 platform station & long double track (before Ely-Soham doubling) 2 platform station (with/after Ely-Soham doubling) Table 8: Summary of impact of different infrastructure options on freight service level. Green = sufficient capacity and relatively low risk, Orange = potential performance risk, Red = not enough capacity pg. 20 Ed Jeffery Ltd Registered in England No

21 21 Soham Station 4.1 Summary of conclusions for each service level Test 1 (today s timetable) o A stop at Soham (on a single platform station) can be accommodated in all current Peterborough Ipswich (and return) services. Minimal amendments to other services are required and the majority of trains have no overall journey time increase despite the station call. Test 2 (hourly Ipswich Peterborough) o The provision of a Soham station call has no impact on the ability to increase the Ipswich Peterborough (and return) service to hourly. This can be accommodated on a single platform station. However, the issues with level crossings at Ely North Junction would prevent any increase in freight and passenger services. o Increasing the Ipswich Peterborough (and return) service to hourly will likely require the retiming of current freight paths into a standardised hourly path (although all current paths could be accommodated). This would require further feasibility analysis outside the current scope (e.g. at Ely North Junction). Test 3 (doubling of Cambridge Ipswich service) o In order to provide 2 tph in each direction between Ipswich and Cambridge, an infrastructure intervention is required between Dullingham and Coldham Lane Junction. It is recommended that this is investigated further if the service increase is required (as well as the impact on Cambridge station). o Test 3 can be delivered south of Chippenham Junction (assuming infrastructure is provided between Dullingham and Coldham Lane Junction. The key constraint is the long signalling headway south of Kennett. Soham station has a minimal impact on these constraints. Test 4a (2tph freight each way between Soham and Ely) o The practical maximum number of trains on the single line between Soham and Ely Dock Junction (with calls at a single platform station) is 6 tph. This is also the service level required for Tests 4a and 4b. Therefore, these can be accommodated in theory on the single platform layout, albeit with 54 out of every 60 mins used. o The impact of this is that there is relatively little flexibility in trains using the Ely-Soham section to be moved to meet constraints elsewhere. The high occupation represents a performance risk as well. pg. 21 Ed Jeffery Ltd Registered in England No

22 22 Soham Station o It is essential that the location of engineering allowance on the single line section approaching Ely Dock Junction is reassessed, and moved to a more practical location if possible (e.g. approaching Soham). Test 4b (2 tph freight each way and doubling of Cambridge Ipswich service) o Due to the constraints on the routes via Dullingham and Soham, there is not a suitable solution to deliver Test 4b. The key constraint is the long headways south of Kennett and this should be considered in more detail if increases in both freight and passenger (Ipswich Cambridge) are to be implemented. 4.2 Soham station infrastructure Calling at Soham on a single platform station increases capacity use by approximately 2%. Adding an extra freight train in each direction increases capacity use by approximately 30%. Therefore, it is freight growth that is the primary driver for capacity use. Providing extra infrastructure at Soham does decrease capacity use (by approximately 10% for a short double track and 17% for a longer double track). This provides more timetabling flexibility and performance buffer. This applies whether Soham station is provided or not. In order to increase the number of freight paths to 3 tph each way (as may occur in the medium term), a minimum of the long double track option is required. 4.3 Recommendations The provision of Soham station does not significantly impact on the capacity between Soham and Ely. However, if an intermediate intervention is to be made (prior to full doubling), the two schemes should be considered together to maximise the delivered capacity. As the key driver for infrastructure is freight growth, the future forecasts should be reviewed against the growth that has materialised in order to determine the required infrastructure. The move to an hourly Peterborough Ipswich service will require amendment to existing freight paths (moving towards a standard hourly path) which would require further investigation outside this study area. If the service between Cambridge and Ipswich is to be doubled, infrastructure interventions need to be developed between Dullingham and Coldham Lane Junction, irrespective of the Soham station and Ely Soham doubling projects. pg. 22 Ed Jeffery Ltd Registered in England No

23 23 Soham Station In the medium- and long-term, should freight growth and passenger growth both materialise, the the following infrastructure would need to be considered: Headway reduction south of Kennett (highest priority) Doubling of Haughley Junction pg. 23 Ed Jeffery Ltd Registered in England No

24 5 Appendix A: Test 3 sample timetable From Cambridge Cambridge Norwich Freight P'boro Norwich From Ipswich Ipswich Liv St Ipswich Freight Liv St To Ipswich Ipswich Liv St Ipswich Liv St To Cambridge P'boro Norwich Cambridge Norwich T/load E350 75C66S E350 T/load E C66S16 E350 Ely Dock Jn p 13/17 H 13/35 H Europa Jn p 12/54 H 13/01 13/11 13/16 H 13/33 13/47 a 13:41 Needham Market d 13:23 Soham d 13/23 H 13:41 H Stowmarket a 13:02 H 13:09 13:27 H 13:54 H d 13:03 H 13:10 13/17 H 13:28 H 13:55 H Chippenham Jn p 12/53 13/22 13/31 H 13/48 H Haughley Jn p 13/07 13/13 H 13/19 H 13/32 13/45 13/58 H Elmswell d 13:37 Kennett a 12:56 H Thurston d [1](2) 13:42 H d 12:58 H 13/25 13/35 13/51 H [1] [1] [1](1) [1] [1] [1] (1) Bury St. Edmunds a 13:19 13:28 13:48 H d 13:20 13:29 13:49 H 14/01 H Bury St. Edmundsa 13:10 13:34 H 14:02 Kennett a 13:59 H d 13:11 13:35 H 13/48 H 14:03 d 13/29 H 13/38 H 14:01 14/15 Thurston d 13:17 <1> <1> Elmswell d 13:23 (1.5) Chippenham Jn p 13/32 H 13/41 H 14/05 14/18 (1) Haughley Jn p 13/29 13/47 H 13/56 14/05 H 14/16 H 14/26 Soham a 13:48 H (0.5) Stowmarket a 13:33 H 13:50 H {1.5} 14:19 H 14:28 H d 13:49 14/25 H d 13:34 13:51 H 13/57 H 14/09 14:20 H 14:29 H Ely Dock Jn p 13/54 H 14/31 H Needham Market d 13:39 H [1] [1] [1] [1] [1] Europa Jn p 13/45 H 14/00 H 14/04 H 14/17 H 14/29 H 14/38 pg. 24 Ed Jeffery Ltd Registered in England No

25 25 Soham Station 6 Appendix B: Test 4a sample timetable From Cambridge Norwich Freight Freight P'boro Norwich From Ipswich Liv St Freight Ipswich Freight Liv St To Ipswich Liv St Ipswich Liv St To P'boro Norwich Cambridge Norwich T/load 170 E350 75C66S16 75C66S E350 T/load 170 E350 75C66S C66S16 E350 Ely Dock Jn p 12/58 H 13/17 H 13/35 H Europa Jn p 13/01 13/11 13/15 13/23 13/33 13/47 a 13:41 Needham Market d 13:29 H Soham d 13/04 H 13/23 H 13:41 H Stowmarket a 13:09 13:34 13:54 H (3.5) d 13:10 13/17 H 13:35 13:55 H Chippenham Jn p 13/08 13/16 13/31 H 13/48 H Haughley Jn p 13/13 H 13/19 H 13/27 13/38 H 13/45 13/58 H Elmswell d 13:43 H Kennett a 13:11 H Thurston d [1] (1) [1] 13:49 d 13:12 13/19 H 13/35 13/51 H [1] [1] (0.5) [1] [1] [1] [1] (1) Bury St. Edmunds a 13:27 13:55 d 13:29 13/43 H 13:56 14/02 Bury St. Edmundsa 13:22 H 14:02 Kennett a 14:06 d 13:24 H 13/33 13/48 H 14:03 d 13/38 H 13/57 14:06 H 14/15 H Thurston d 13:30 H <1> (0.5) Elmswell d 13:36 H (1.5) Chippenham Jn p 13/41 H 14/00 14/11 H 14/19 Haughley Jn p 13/41 H 13/56 13:59 H 14/05 H 14/16 H 14/26 Soham a 13:48 H Stowmarket a 13:44 H {1.5} 14:19 H 14:28 H d 13:49 14/07 H 14/26 H d 13:45 13/57 H 14/04 H 14/09 14:20 H 14:29 H Ely Dock Jn p 13/54 H 14/13 H 14/32 H Needham Market d 13:50 H [1] [1] [1] [1] Europa Jn p 13/56 H 14/04 H 14/13 14/17 H 14/29 H 14/38 pg. 25 Ed Jeffery Ltd Registered in England No

Passenger service for the Dudding Hill line: brief for feasibility study

Passenger service for the Dudding Hill line: brief for feasibility study Appendix 1: Specification for a Study Passenger service for the Dudding Hill line: brief for feasibility study Introduction The West London Alliance is currently investigating ways of accommodating the

More information

EAST COAST MAINLINE TIMETABLE DEVELOPMENT DECEMBER 2006 TIMETABLE. 1 of 20

EAST COAST MAINLINE TIMETABLE DEVELOPMENT DECEMBER 2006 TIMETABLE. 1 of 20 EAST COAST MAINLINE TIMETABLE DEVELOPMENT DECEMBER 2006 TIMETABLE 1 of 20 CONTENTS 1.0 Executive Summary 2.0 Introduction 3.0 Background 4.0 Method Pathing Exercise Performance Evaluation Operational Assessment

More information

The case for the Digital Railway. Patrick Bossert. Digital Railway Transformation Director. Agenda

The case for the Digital Railway. Patrick Bossert. Digital Railway Transformation Director. Agenda The case for the Digital Railway Patrick Bossert Digital Railway Transformation Director Agenda A railway that delivers better economic return for every invested in the network up to +40% seats at 30%

More information

UK Road Pricing Feasibility Study: Modelling the Impacts Elizabeth Cox 1 UK

UK Road Pricing Feasibility Study: Modelling the Impacts Elizabeth Cox 1 UK Abstract UK Road Pricing Feasibility Study: Modelling the Impacts Elizabeth Cox 1 UK In July 2003, the UK government set up a comprehensive study to examine how a new system of charging for road use could

More information

Freight Action Plan Summary. A Catalyst for Change The Regional Transport Strategy for the west of Scotland

Freight Action Plan Summary. A Catalyst for Change The Regional Transport Strategy for the west of Scotland Freight Action Plan Summary A Catalyst for Change The Regional Transport Strategy for the west of Scotland 2007-2021 Strathclyde Partnership for Transport Contents Purpose...2 Issues, Constraints and Opportunities...2

More information

Simulation of freight train operations with departures ahead of schedule

Simulation of freight train operations with departures ahead of schedule Computers in Railways XIV 239 Simulation of freight train operations with departures ahead of schedule A. Lindfeldt & H. Sipilä Department of Transport Science, Royal Institute of Technology (KTH), Sweden

More information

Customer-centric transportation network modelling

Customer-centric transportation network modelling www.pwc.com.au Customer-centric transportation network modelling Agent-based modelling in (Australia) Insight Analytics Introduction Public Transportation Services across Australia are undergoing transformation

More information

ViziRail Description

ViziRail Description ViziRail Description Table of Contents ViziRail Train Scheduling Software... 3 Timetabling and Trains... 4 Train Graphing... 9 Possessions... 14 Speed Restrictions... 16 Train Notices... 17 Train Control

More information

IPSWICH NORTHERN ROUTES STUDY. Stage 1 Progress

IPSWICH NORTHERN ROUTES STUDY. Stage 1 Progress IPSWICH NORTHERN ROUTES STUDY Stage 1 Progress 17 th January 2017 STUDY CONTEXT 2 The study is being funded in partnership with the Suffolk district and borough councils. Work forms part of the Suffolk

More information

DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES

DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES Disclaimer: This discussion paper does not prejudge the existing or future positions of the European Commission and its services

More information

Forecasting robustness of timetables

Forecasting robustness of timetables Forecasting robustness of timetables W. Barter First Class Partnerships, UK Abstract Ultimately, the timetable is proof of the capacity of a rail network. If a train can be pathed, then capacity exists.

More information

Joint design standard for running times, dwell times and headway times

Joint design standard for running times, dwell times and headway times Computers in Railways X 611 Joint design standard for running times, dwell times and headway times V. A. Weeda & P. B. L. Wiggenraad Department of Transport & Planning, Delft University of Technology,

More information

City of Brantford Chapter 3 TABLE OF CONTENTS

City of Brantford Chapter 3 TABLE OF CONTENTS Chapter 3 The Land Use & Transportation Connection TABLE OF CONTENTS 3.1 THE LAND USE & TRANSPORTATION LINK... 1 3.2 POPULATION & EMPLOYMENT GROWTH FORECASTS... 3 3.2.1 Proposed Places to Grow Plan Forecasts

More information

SECTION 5 SERVICES 5.1 LEGAL FRAMEWORK. see section CLASSIFICATION OF SERVICES

SECTION 5 SERVICES 5.1 LEGAL FRAMEWORK. see section CLASSIFICATION OF SERVICES SECTION 5 SERVICES 5.1 LEGAL FRAMEWORK see section 1 5.2 CLASSIFICATION OF SERVICES 5.2.1 BASIC ACCESS PACKAGE - Processing of infrastructure capacity applications for the purpose of concluding the contracts;

More information

This paper outlines the carbon footprint and greenhouse gas assessment for HS2 Phase One.

This paper outlines the carbon footprint and greenhouse gas assessment for HS2 Phase One. HIGH SPEED TWO INFORMATION PAPER E10: CARBON This paper outlines the carbon footprint and greenhouse gas assessment for HS2 Phase One. It will be of particular interest to those potentially affected by

More information

March to Wisbech Rail Study Capital Cost of Re-opening the Line Cambridgeshire County Council. 4 April 2014

March to Wisbech Rail Study Capital Cost of Re-opening the Line Cambridgeshire County Council. 4 April 2014 Cambridgeshire County Council 4 April 2014 Notice This document and its contents have been prepared and are intended solely for Cambridgeshire County Council s information and use in relation to the March

More information

CROSSRAIL INFORMATION PAPER H3 CROSSRAIL ACCESS OPTION

CROSSRAIL INFORMATION PAPER H3 CROSSRAIL ACCESS OPTION CROSSRAIL INFORMATION PAPER CROSSRAIL ACCESS OPTION This paper explains how it is intended that access rights for running Crossrail services are obtained. It will be of particular relevance to those interested

More information

Rail Passenger Demand Forecasting Methodology TAG Unit

Rail Passenger Demand Forecasting Methodology TAG Unit TAG Unit 3.15.4 April 2009 Department for Transport Transport Analysis Guidance (TAG) This Unit is part of a family which can be accessed at www.webtag.org.uk Contents 1. Summary 1 2. Introduction 1 3.

More information

UIC CODE 406. Capacity. 1st edition, June 2004 Original. La Capacité Kapazität

UIC CODE 406. Capacity. 1st edition, June 2004 Original. La Capacité Kapazität UIC CODE 1st edition, June 2004 Original Capacity La Capacité Kapazität Leaflet to be classified in Volume: IV - Operating Application: With effect from 1 June 2004 All members of the International Union

More information

TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (INQUIRIES PROCEDURES) RULES 2004 NETWORK RAIL (WERRINGTON GRADE SEPARATION) ORDER

TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (INQUIRIES PROCEDURES) RULES 2004 NETWORK RAIL (WERRINGTON GRADE SEPARATION) ORDER The Network Rail (Werrington Grade Separation) Order NR/PoE/1.2 TRANSPORT AND WORKS ACT 1992 TRANSPORT AND WORKS (INQUIRIES PROCEDURES) RULES 2004 NETWORK RAIL (WERRINGTON GRADE SEPARATION) ORDER NEEDS

More information

Oxford, Milton Keynes, Cambridge Northampton Growth Corridor

Oxford, Milton Keynes, Cambridge Northampton Growth Corridor Oxford, Milton Keynes, Cambridge Northampton Growth Corridor National Infrastructure Commission Transport Infrastructure Assessment: Final Report November 2017 Our ref: 23142501 Client ref: CCCC17A41 Oxford,

More information

Template Framework Freight Track Access Agreement and HS1 Freight Access Terms: Conclusions Document. Date: June

Template Framework Freight Track Access Agreement and HS1 Freight Access Terms: Conclusions Document. Date: June Subject: Date: June 2012 Template Framework Freight Track Access Agreement and HS1 Freight Access Terms: Conclusions Document 1. Executive Summary In 2011, HS1 Limited ( HS1 Ltd ) held detailed discussions

More information

Capacity estimation of new single track stations. Solomon Kinfe

Capacity estimation of new single track stations. Solomon Kinfe Capacity estimation of new single track stations Solomon Kinfe Master of Science Thesis Stockholm, Sweden 2012 TCS-MT 12-036 Capacity estimation of new single track stations Solomon Kinfe Master thesis

More information

Transactions on the Built Environment vol 34, 1998 WIT Press, ISSN

Transactions on the Built Environment vol 34, 1998 WIT Press,  ISSN Improving the Dutch railway services by network-wide timetable simulation Jurjen S. Hooghiemstra", Dick M. Middelkoop", Maurice J.G. Teunisse^ " Railned, Dept. of Innovation, P.O.Box 2025, 3500 HA Utrecht,

More information

Iterative train scheduling in networks with tree topologies: a case study for the Hunter Valley Coal Chain

Iterative train scheduling in networks with tree topologies: a case study for the Hunter Valley Coal Chain 22nd International Congress on Modelling and Simulation, Hobart, Tasmania, Australia, 3 to 8 December 2017 mssanz.org.au/modsim2017 Iterative train scheduling in networks with tree topologies: a case study

More information

Planning Application Supporting Document. The Need Case for New Railway Sidings at Ditton Junction. Prepared by MDS Transmodal Limited

Planning Application Supporting Document. The Need Case for New Railway Sidings at Ditton Junction. Prepared by MDS Transmodal Limited Planning Application Supporting Document The Need Case for New Railway Sidings at Ditton Junction Prepared by MDS Transmodal Limited Date: May 2007 Ref: New Sidings Need Case CONTENTS 1. Introduction 2.

More information

Appendix B5 PT Model Validation

Appendix B5 PT Model Validation Appendix B5 PT Model Validation PT Model Validation Report Sheffield and Rotherham Public Transport Model Report for Sheffield City Council August 2009 Document Control Project Title: MVA Project Number:

More information

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis Port Jervis Line Service Strategy Report Appendix C: Port Jervis Line Capacity Improvements Analysis January 2018 TABLE OF CONTENTS Introduction... 1 1. Future PJL Service... 1 2. Project Alternatives...

More information

US & USRC Track Capacity Study Train Capacity Analysis Present to Maximum Capacity and Beyond

US & USRC Track Capacity Study Train Capacity Analysis Present to Maximum Capacity and Beyond Transportation Metrolinx US & USRC Track Capacity Study Prepared by: AECOM 5080 Commerce Boulevard 905 238 0007 tel Mississauga, ON, Canada L4W 4P2 905 238 0038 fax www.aecom.com AECOM Project Number:

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 CONTROL, COMMAND AND COMMUNICATION

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 CONTROL, COMMAND AND COMMUNICATION THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 17 CONTROL, COMMAND AND COMMUNICATION Control centre optimises the positions of trains in real time Drivers receive information to optimise

More information

David King, Railway Procurement Agency 14 th November 2012

David King, Railway Procurement Agency 14 th November 2012 Bus Rapid Transit for Dublin Hugh Creegan, National Transport Authority David King, Railway Procurement Agency 14 th November 2012 Topics Core Dublin BRT Network System Concept BRT in the Transport System

More information

2. Opportunities and problems involved in implementing ETCS Levels 2 and 3

2. Opportunities and problems involved in implementing ETCS Levels 2 and 3 Concept for Combining ETCS Levels 2 and 3 Reiner Dachwald, Lars Kupfer, Bernhard Ptok 1. Introduction Several pilot projects are currently underway to prepare for the introduction of ERTMS/ ETCS, the new

More information

Data aggregation for detailed analysis of train delays

Data aggregation for detailed analysis of train delays Computers in Railways XIII 239 Data aggregation for detailed analysis of train delays T. Richter Operations Monitoring and Analysis, Rail Net Denmark, Denmark Abstract The classical approach to analysis

More information

Modeling Truck Traffic Volume Growth Congestion

Modeling Truck Traffic Volume Growth Congestion Modeling Truck Traffic Volume Growth Congestion By Mr. Gregory Harris, P. E. (Principal Investigator) Office of Freight, Logistics and Transportation The University of Alabama in Huntsville Huntsville,

More information

HS1 Link The View from London

HS1 Link The View from London HS1 Link The View from London For HS2 Growth and Connectivity Conference 12 September 2014 Contents 1. TfL Position on HS2 & Hybrid Bill Petition 2. HS1 Link Issues & Possible Options 2 HS2 Progress To

More information

SCHEDULE 1 CONDITIONS OF USE RELATING TO FALKIRK BUS STATION (THE BUS STATION )

SCHEDULE 1 CONDITIONS OF USE RELATING TO FALKIRK BUS STATION (THE BUS STATION ) SCHEDULE 1 CONDITIONS OF USE RELATING TO FALKIRK BUS STATION (THE BUS STATION ) These Conditions of Use set out the terms on which all operators (including First) ( Operator(s) ) who use, or wish to use

More information

SP3 Framework development for capability trade-offs C4R Workshop M18 report 11 June 2015

SP3 Framework development for capability trade-offs C4R Workshop M18 report 11 June 2015 Capacity for Rail SP3 Framework development for capability trade-offs C4R Workshop M18 report 11 June 2015 Magnus Wahlborg Trafikverket, Swedish transport administration Working status Conclusion research

More information

DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES. Article 1. Subject matter

DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES. Article 1. Subject matter DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES Disclaimer: This discussion paper does not prejudge the existing or future positions of the European Commission and its services

More information

18 TRAFFIC AND TRANSPORTATION

18 TRAFFIC AND TRANSPORTATION 18 TRAFFIC AND TRANSPORTATION 18.1 EXISTING ENVIRONMENT 18.1.1 Poole is relatively well connected to the main road network. The most direct access into Poole from the Port is across the lifting bridge

More information

One Agenda. One Economy. One North.

One Agenda. One Economy. One North. Northern Freight & Logistics Report Technical Appendices One Agenda. One Economy. One North. Northern Freight & Logistics Report: Technical Appendices 1 Contents 1 Technical Appendices 5 1.1 Overview 5

More information

Determining the Causes of Train Delay

Determining the Causes of Train Delay Determining the Causes of Train Delay Mark Dingler *, Amanda Koenig, Sam Sogin and Christopher P.L. Barkan Railroad Engineering Program, Department of Civil and Environmental Engineering, University of

More information

Review of the Technical Specification for High Speed Rail in the UK. A report to Government by HS2 Ltd

Review of the Technical Specification for High Speed Rail in the UK. A report to Government by HS2 Ltd Review of the Technical Specification for High Speed Rail in the UK A report to Government by HS2 Ltd January 2012 Although this report was commissioned by the Department for Transport (DfT), the findings

More information

Comparing Roundabout Capacity Analysis Methods, or How the Selection of Analysis Method Can Affect the Design

Comparing Roundabout Capacity Analysis Methods, or How the Selection of Analysis Method Can Affect the Design Comparing Roundabout Capacity Analysis Methods, or How the Selection of Analysis Method Can Affect the Design ABSTRACT Several analysis methods have been proposed to analyze the vehicular capacity of roundabouts.

More information

Management Incentive Plan

Management Incentive Plan Management Incentive Plan 2016/17 Effective from 1 April 2016 Contents Foreword The Challenges of Delivering CP5 A Remuneration Framework to Deliver CP5 Scheme Participants Incentive Plan Overview CP5

More information

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need Environmental Impact Statement (EIS) Revised Purpose and Need June 23, 2017 1.0 What is the Proposed Action? The consists of potential improvements to the Long Bridge and related railroad infrastructure

More information

UK rail transport: a review of demand and supply

UK rail transport: a review of demand and supply Loughborough University Institutional Repository UK rail transport: a review of demand This item was submitted to Loughborough University's Institutional Repository by the/an author. Citation: FROST, M.W.,

More information

INTEROPERABILITY UNIT

INTEROPERABILITY UNIT EUROPEAN RAILWAY AGENCY INTEROPERABILITY UNIT TAF TSI - ANNEX A.5 :FIGURES AND SEQUENCE DIAGRAMS OF THE TAF TSI REFERENCE: ERA-TD-100 DOCUMENT TYPE: TECHNICAL DOCUMENT VERSION: 2.0 (DRAFT) TAF TSI DATE:

More information

One Public Transport System for Cornwall. Project Details

One Public Transport System for Cornwall. Project Details One Public Transport System for Cornwall Project Details Integrated Transport and Technology Team Version 3.3 www.cornwall.gov.uk One Public Transport System for Cornwall (OPTSfC) The One Public Transport

More information

The changing face of London and Southeast Railway Architecture. Tony Ramanathan Systems Design Engineer Network Rail

The changing face of London and Southeast Railway Architecture. Tony Ramanathan Systems Design Engineer Network Rail The changing face of London and Southeast Railway Architecture Tony Ramanathan Systems Design Engineer Network Rail 1 Agenda What are the drivers Network Rail mandate Network Rail Project Governance (GRIP)

More information

Traffic management in moving block railway systems: the results of the EU project COMBINE

Traffic management in moving block railway systems: the results of the EU project COMBINE Traffic management in moving block railway systems: the results of the EU project COMBINE M. Giannettoni & S. Savio Dipartimento di Ingegneria Elettrica - Universita di Genova (Italy) Abstract In this

More information

Automating rolling stock diagramming and platform allocation

Automating rolling stock diagramming and platform allocation Loughborough University Institutional Repository Automating rolling stock diagramming and platform allocation This item was submitted to Loughborough University's Institutional Repository by the/an author.

More information

10 RECAP Waste Management Design Guide Toolkit

10 RECAP Waste Management Design Guide Toolkit 10 RECAP Waste Management Design Guide Toolkit 43 How to use the Toolkit 10.1 The purpose of the RECAP Waste Management Design Toolkit (referred to as the Toolkit) is to allow the effective assessment

More information

Network Rail s consultation on its methodology for allocating fixed costs to train operators in Control Period 6 (CP6) 22 September 2017

Network Rail s consultation on its methodology for allocating fixed costs to train operators in Control Period 6 (CP6) 22 September 2017 Network Rail s consultation on its methodology for allocating fixed costs to train operators in Control Period 6 (CP6) 22 September 2017 1 Executive summary 1.1 The purpose of this consultation is to set

More information

committee report SPT response to InterCity West Coast Franchise Consultation

committee report SPT response to InterCity West Coast Franchise Consultation committee report SPT response to InterCity West Coast Franchise Consultation Committee Operations Date of Meeting 11 March 2011 Date of report 16 February 2011 Report by Assistant Chief Executive (Business

More information

Long Term Planning Process: Freight Market Study. October 2013

Long Term Planning Process: Freight Market Study. October 2013 Long Term Planning Process: Freight Market Study What s inside this document Network Rail Long Term Planning Process: Freight Market Study 02 Foreword 03 Executive Summary 04 01. Background 07 02. Study

More information

JRC SIDING SPACING AND THE INCREMENTAL CAPACITY OF THE TRANSITION FROM SINGLE TO DOUBLE TRACK

JRC SIDING SPACING AND THE INCREMENTAL CAPACITY OF THE TRANSITION FROM SINGLE TO DOUBLE TRACK Proceedings of the 2014 Joint Rail Conference JRC2014 April 2-4, 2014, Colorado Springs, CO, USA JRC2014-3831 SIDING SPACING AND THE INCREMENTAL CAPACITY OF THE TRANSITION FROM SINGLE TO DOUBLE TRACK Ivan

More information

Appendix H. Millennium Hollywood Project Trip Cap and Mitigation Triggers

Appendix H. Millennium Hollywood Project Trip Cap and Mitigation Triggers Appendix H Millennium Hollywood Project Trip Cap and Mitigation Triggers MILLENNIUM HOLLYWOOD PROJECT TRIP CAP AND MITIGATION TRIGGERS Crain and Associates Introduction The Millennium Hollywood Project

More information

Draft. 1. For grade crossing warning devices, see Manual Part Recommended Guidelines for Grade Crossing Warning Devices.

Draft. 1. For grade crossing warning devices, see Manual Part Recommended Guidelines for Grade Crossing Warning Devices. 2017 Part 3.1.10 Recommended Functional/Operating Guidelines for Interconnection Between Highway Traffic Signals or Other Traffic Control Devices and Grade Crossing Warning Systems Reaffirmed 2017 Revised

More information

Consultation Paper. Proposed Removal of Ashchurch Rail Freight Facility Scheme from Gloucestershire s Local Transport Plan

Consultation Paper. Proposed Removal of Ashchurch Rail Freight Facility Scheme from Gloucestershire s Local Transport Plan Consultation Paper Proposed Removal of Ashchurch Rail Freight Facility Scheme from Gloucestershire s Local Transport Plan June 2014 Consultation Paper Proposed Removal of Ashchurch rail freight facility

More information

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening;

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; 5 TRAFFIC AND TRANSPORT 5.1 SUMMARY OF RESIDUAL IMPACTS The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; be outside of the

More information

Congestion Management Process 2013 Update

Congestion Management Process 2013 Update OVERVIEW OF THE DALLAS-FORT WORTH CONGESTION MANAGEMENT PROCESS Traffic Congestion In The Dallas-Fort Worth Region With the Dallas-Fort Worth (DFW) urban area as its center, the North Central Texas region

More information

Deviation from a Railway Group Standard

Deviation from a Railway Group Standard Deviation from a Railway Group Standard (In accordance with the Railway Group Standards Code, Issue Four, part 7 and the Standards Manual, part 16) Deviation number: 16-009-DEV 1. Problem statement Installation

More information

Developments in Transport Policy

Developments in Transport Policy Journal of Transport Economics and Policy, Volume 36, Part 2, May 2002, pp. 341±354 Developments in Transport Policy The Evolution of Capacity Charges on the UK Rail Network Stephen Gibson, Grahame Cooper,

More information

System Operator. Strategic Business Plan. February 2018

System Operator. Strategic Business Plan. February 2018 System Operator Strategic Business Plan February 2018 1. Foreword by Jo Kaye, Managing Director, System Operator I am pleased to set out, in this Strategic Business Plan, our plan and vision for the railway

More information

1 Traffic information for applicants and traffic operators

1 Traffic information for applicants and traffic operators Traffic Information 1 Traffic information for applicants and traffic operators The information is supplied to applicants or traffic operators via a number of different channels, including e-mail, the internet,

More information

Transport in the Liverpool City Region: Update for TravelWatch

Transport in the Liverpool City Region: Update for TravelWatch Transport in the Liverpool City Region: Update for TravelWatch Frank Rogers Deputy Chief Executive, Merseytravel 9 October 2014 Agenda Bus Quality Partnerships Long Term Rail Strategy & Committed Schemes

More information

A LOW EMISSION ZONE FOR LONDON.

A LOW EMISSION ZONE FOR LONDON. A LOW EMISSION ZONE FOR LONDON. Lucy Sadler 1, David Hutchinson 1, Paul Watkiss 2, David Carslaw 3. 1 Greater London Authority, City Hall, The Queen's Walk, London, SE1 2AA, UK lucy.sadler@london.gov.uk,

More information

Project Initiation Form

Project Initiation Form Meeting Date: The Project Initiation Form should be completed in conjunction with the Level 2 Screening Form. Process Leads and/or Planners should complete the Project Initiation Form to document coordination

More information

TRAFFIC IMPACT STATEMENT SOUTHERN WASTEWATER TREATMENT WORKS

TRAFFIC IMPACT STATEMENT SOUTHERN WASTEWATER TREATMENT WORKS TRAFFIC IMPACT STATEMENT SOUTHERN WASTEWATER TREATMENT WORKS MARCH 2015 Prepared by: Royal HaskoningDHV (Pty) Ltd RHDHV Pinetown 6 Payne Street Pinetown 3610 VERIFICATION PAGE PROJECT NAME: Traffic Impact

More information

Use of Simulation to Evaluate Performance of Timetable Concepts

Use of Simulation to Evaluate Performance of Timetable Concepts Use of Simulation to Evaluate Performance of Timetable Concepts New Timetable for the Oslo-area Elin Reitan Sven-Jöran Schrader NSB Passenger Trains, Planning & Analysis Agenda Background: The new Oslo-area

More information

Readily Implementable Signal Phasing Schemes for Diverging Diamond Interchanges

Readily Implementable Signal Phasing Schemes for Diverging Diamond Interchanges Tian, Xu, de-camp, Kyte, and Wang Readily Implementable Signal Phasing Schemes for Diverging Diamond Interchanges Zong Tian*, Ph.D., P.E. Hao Xu, Ph.D Center for dvanced Transportation Education and Research

More information

Unidirectional Simulation Objectives

Unidirectional Simulation Objectives Performance Evaluation of Two Conceptual Designs for Rail Service to Transbay Terminal Bi-Directional Unidirectional Bi-Directional R. Shiloh AREMA CONFERENCE Tuesday, September 12, Unidirectional Simulation

More information

Response of the Road Haulage Association to Transport for London. Consultation on Mayor s Transport Strategy.

Response of the Road Haulage Association to Transport for London. Consultation on Mayor s Transport Strategy. Response of the Road Haulage Association to Transport for London. Consultation on Mayor s Transport Strategy. Background about the RHA 2 October 2017 1. The Road Transport Industry is a dynamic, business

More information

West Midlands Combined Authority Roadside Information Recharging Scheme

West Midlands Combined Authority Roadside Information Recharging Scheme This document is important and requires your immediate attention. It contains details of the Roadside Information Recharging Scheme introduced by West Midlands Combined Authority on 1 December 2016. West

More information

FREIGHT ON RAIL. Rail is part of the road congestion solution to the A14 2 nd March Philippa Edmunds

FREIGHT ON RAIL. Rail is part of the road congestion solution to the A14 2 nd March Philippa Edmunds FREIGHT ON RAIL Rail is part of the road congestion solution to the A14 2 nd March 2012 Philippa Edmunds members DB Schenker Freightliner Rail Freight Group Campaign for Better Transport Network Rail www.freightonrail.org.uk

More information

Liverpool City Region Candidate Major Schemes April 2013

Liverpool City Region Candidate Major Schemes April 2013 Region Candidate April 2013 Sponsoring Halton Borough Halton Borough Halton Borough Scheme Name: Detail: Estimated Silver Jubilee Bridge Major Maintenance M56 J11A Daresbury Enterprise Zone / East Runcorn

More information

UIC ERTMS Conference 2004 ERTMS Planning for the Future. M. Pottendorfer Alcatel TSD Austria December 2004

UIC ERTMS Conference 2004 ERTMS Planning for the Future. M. Pottendorfer Alcatel TSD Austria December 2004 UIC ERTMS Conference 2004 ERTMS Planning for the Future M. Pottendorfer Alcatel TSD Austria December 2004 > Business Aspects > ERTMS General aspects > Migration Presentation Outline > ERTMS benefits Railways

More information

High Speed Rail London to the West Midlands and Beyond. A Report to Government by High Speed Two Limited. PART 7 of 11

High Speed Rail London to the West Midlands and Beyond. A Report to Government by High Speed Two Limited. PART 7 of 11 High Speed Rail London to the West Midlands and Beyond A Report to Government by High Speed Two Limited PART 7 of 11 While High Speed Two (HS2) Limited has made every effort to ensure the information in

More information

Traffic Impact Analysis Guidelines. Town of Queen Creek

Traffic Impact Analysis Guidelines. Town of Queen Creek Traffic Impact Analysis Guidelines Town of Queen Creek January 2016 1. INTRODUCTION The purpose of this document is to outline the procedures and requirements for preparing a Transportation Impact Analysis

More information

2. Specific criteria will be applied in order to determine whether or not a discount will be offered;

2. Specific criteria will be applied in order to determine whether or not a discount will be offered; Subject: HS1 Discount Policy: Conclusions Date: February 2012 Context and overview On 3 October 2011, HS1 Limited published a consultation document on its proposed policy on offering discounts on access

More information

RAILWAY TRAFFIC OPERATION

RAILWAY TRAFFIC OPERATION doc. Ing. Jozef Gašparík, PhD. prof. Ing. Jozef Majerčák, PhD. doc. Ing. Jaromír Široký, Ph.D. doc. dr. sc. Borna Abramović Ing. Pavol Meško, PhD. Ing. Petr Nachtigall, Ph.D. Ing. Vladislav Zitrický PhD.

More information

Adam Mantzos Brockley Consulting. Review of cost attribution and cost allocation approaches. A report for Network Rail

Adam Mantzos Brockley Consulting. Review of cost attribution and cost allocation approaches. A report for Network Rail Adam Mantzos Brockley Consulting Review of cost attribution and cost allocation approaches A report for Network Rail 18 March 2015 Contents Summary... 3 Introduction... 8 Cost allocation principles...

More information

Transport Challenges in 2012

Transport Challenges in 2012 Transport Challenges in 2012 Issue One July 2011 Contents Page Introduction to the Challenge 2 Traffic Management Timetable 4 Business Impact & Planning 5 Policy Update 7 Further Information 8 Introduction

More information

Central Corridor Passenger Rail Feasibility Study. Prepared for Massachusetts Department of Transportation June 2017

Central Corridor Passenger Rail Feasibility Study. Prepared for Massachusetts Department of Transportation June 2017 Central Corridor Passenger Rail Feasibility Study Prepared for Massachusetts Department of Transportation June 2017 EXECUTIVE SUMMARY The Central Corridor Line Passenger Rail Feasibility Study (Study)

More information

3.6 GROUND TRANSPORTATION

3.6 GROUND TRANSPORTATION 3.6.1 Environmental Setting 3.6.1.1 Area of Influence The area of influence for ground transportation consists of the streets and intersections that could be affected by automobile or truck traffic to

More information

Content of the module

Content of the module Content of the module Methodology approach Planning process Definition of working area Population and territorial context Supply Infrastructure Transport service Demand On board / at the stations or bus

More information

10.0 AIR QUALITY AND CLIMATIC FACTORS

10.0 AIR QUALITY AND CLIMATIC FACTORS .0 AIR QUALITY AND CLIMATIC FACTORS.1 ASSESSMENT METHODOLOGY.1.1 General Section 39 (2) (b) (ii) of the Transport (Railway Infrastructure) Act 2001, requires that proposed developments are examined in

More information

Woodburn Interchange Project Transportation Technical Report

Woodburn Interchange Project Transportation Technical Report Final Report Woodburn Interchange Project Transportation Technical Report Prepared for Oregon Department of Transportation April 212 Prepared by DKS Associates Contents Methodologies... 4 Volume Development...

More information

TECHNICAL MEMORANDUM I-710 EIR/EIS INITIAL FEASIBILITY ANALYSIS (IFA) TECHNICAL APPENDIX WBS TASK ID:

TECHNICAL MEMORANDUM I-710 EIR/EIS INITIAL FEASIBILITY ANALYSIS (IFA) TECHNICAL APPENDIX WBS TASK ID: FINAL REPORT TECHNICAL MEMORANDUM I-710 EIR/EIS INITIAL FEASIBILITY ANALYSIS (IFA) TECHNICAL APPENDIX WBS TASK ID: 165.10.09 Prepared for Los Angeles County Metropolitan Transportation Authority December

More information

OPERATIONAL PLANNING AND PERFORMANCE: WHO, WHAT & WHY?

OPERATIONAL PLANNING AND PERFORMANCE: WHO, WHAT & WHY? OPERATIONAL PLANNING AND PERFORMANCE: WHO, WHAT & WHY? The Operational Planning process plans 215,000 train paths every week for UK Train Operators. (34k each weekday, 30k on Saturdays and 17k on Sundays).

More information

MIC Core Pre-Schematic Program Analysis

MIC Core Pre-Schematic Program Analysis MIC Core Pre-Schematic Program Analysis April 2001 MIAMI INTERMODAL CENTER (MIC) PROGRAM Work Program Item No. 6113820 State Project No. 87000-1528 Financial Management Item No. 249643 PRE-SCHEMATIC DESIGN

More information

THE NORTH EAST OF SCOTLAND PARTNERSHIP WRITTEN SUBMISSION

THE NORTH EAST OF SCOTLAND PARTNERSHIP WRITTEN SUBMISSION THE NORTH EAST OF SCOTLAND PARTNERSHIP FREIGHT TRANSPORT IN SCOTLAND WRITTEN SUBMISSION The Scottish Parliament s Infrastructure and Capital Investment Committee has announced that it will undertake an

More information

The Transportation dividend

The Transportation dividend Prepared by AECOM Technical Appendices report February 2018 The Transportation dividend Transit investments and the Massachusetts economy Technical Appendix A economic Benefits Methodology and Results

More information

CALTRAIN S PTC SOLUTION FOR 2015 CBOSS

CALTRAIN S PTC SOLUTION FOR 2015 CBOSS CALTRAIN S PTC SOLUTION FOR 2015 CBOSS (COMMUNICATIONS BASED OVERLAY SIGNAL SYSTEM) SYSTEM DESCRIPTION 1. INTRODUCTION This document provides the system level description of the Communications Based Overlay

More information

Re: EX16.1. Developing Toronto's Transit Network Plan to Attachment 6

Re: EX16.1. Developing Toronto's Transit Network Plan to Attachment 6 Re: EX16.1 Developing Toronto's Transit Network Plan to 2031 1 Contents 1. Executive Summary... 3 2. Background and Context... 7 Problem Statement:... 7 Decision History on Options Development... 8 Relief

More information

ETCS & CBTC Interfaces Crossrail Signalling

ETCS & CBTC Interfaces Crossrail Signalling ETCS & CBTC Interfaces Crossrail Signalling David Milburn, Technical Head Signalling & Control Systems Network Rail Consulting (NRC) MENA Conference, December 2015 Contents 1 Overview of Network Rail and

More information

Roadmaps to 2050 FFE (Madrid, Spain) 21 September 2017

Roadmaps to 2050 FFE (Madrid, Spain) 21 September 2017 Capacity for Rail Roadmaps to 2050 FFE (Madrid, Spain) 21 September 2017 Vijay Ramdas SP5 Task Leader European Rail Journey 2020 Framework for multi-modal transport information management & payment system

More information

2017 Marine Cargo Forecast and Rail Capacity Analysis

2017 Marine Cargo Forecast and Rail Capacity Analysis 2017 Marine Cargo Forecast and Rail Capacity Analysis Appendix A Rail Capacity Analysis August 2017 Prepared for Washington Public Ports Association and Freight Mobility Strategic Investment Board Prepared

More information

THE UK PORTS INDUSTRY:

THE UK PORTS INDUSTRY: THE UK PORTS INDUSTRY: Forecasting Growth & Developing Capacity by MDS Transmodal 205024_presentationv5 1. AGENDA Past trends, 1965-2004 Ports & Public policy - History and forthcoming review Forecasting

More information

White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306

White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306 Appendix C2 White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306 Berths 302-306 [APL] Container Terminal Project December 2011 ADP# 081203-131

More information