1 Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017
2 OPENING REMARKS Kinney Poynter Moderator Executive Director NASACT Alan Pennington Speaker Vice President Matrix Consulting Group 2
3 PROGRAM OBJECTIVES Understand key phases of construction programs Understand approaches for managing change order Develop techniques for auditing change order Gain awareness of industry standards and best practices to utilize during the audit 3
4 Why Audit Construction Contracts? Construction projects are costly Delays can result in increased costs Provides a monitoring capacity not available elsewhere Provides a means of keeping projects on track or getting them back on track quickly The 2008 Association of Certified Fraud Examiners Report to the Nation on Occupational Fraud and Abuse noted that construction ranks as the 5th highest industry in median loss per fraud case ($330,000), and 8 th in terms of the number of fraud cases. 4
5 Goals of a Construction Audit Identify cost avoidance opportunities Ensure controls are developed and maintained Identify overcharges / undercharges Avoid litigation Identify opportunities to improve the future management of construction projects 5
6 Timing a Construction Audit: During Time Fix ongoing problems Implement internal controls Not getting in the way Safety - location After Memory recall Right to audit clause may expire Concentrate risks when you see the overall picture Quicker More efficient Getting to the contractor before he / she is gone More effective 6
7 Phases of Construction Projects Planning Conception Design Budget Estimates Contract development and administration Construction Change Orders Close out 7
8 How Should Projects Be Selected For A Construction Audit Size (dollar value, physical size, complexity) Type of project Cost Plus and Time and Materials versus Lump Sum Shared Services Features High profile or high risk projects Experience of owners representative / construction manager Experience with the General Contractor Number of change orders 8
9 Ability To Influence Project Costs Decreases Over Time Data Source: Construction Industry Institute Influence Relative Influence Cumulative Cost Cost Time 9
10 Composition of Contractor Project Costs 85% 90% OF COSTS Labor Materials Equipment (Contractor owned and 3 rd party rental Sub Contractors General Conditions 10 15% OF COSTS Insurance Bonds Bid, Performance, Payment, Warranty Small tools, expendables, and consumables Relocation and travel Home office charges Permits and licenses 10
11 Contract Risks (1) Labor Unlicensed workers Excess Reported Hours Unauthorized workers Time miscalculations Unauthorized rate changes Unauthorized rate changes Ghosts on the payroll Up-Billing Not-to-exceed limits ignored Materials Unauthorized material Substitute material versus specifications New versus like new Price extensions Trade and other discounts Excessive material Quantities not installed Improper construction methods / rework Materials Unauthorized material 11
12 Contract Risks (2) Equipment Charge exceeds purchase price or FMV Excess damage costs Sweetheart deals Taxes on fuel Equipment not on job Rental rebates not credited Rent-to-own Sub-Contractors Overbilling Invoicing Invoicing for material not used Invoicing / ordering material for other projects Back dated invoices Invoicing for material that was returned Reporting theft of material when no such loss occurred Time Schemes Unauthorized delay Phantom weather Change order to escape liquidated damages Charging for work performed on holidays or unauthorized overtime 12
13 Contract Risk (3) Duplicate Billing Invoice numbers out of sequence Date of invoice out-of-order for construction sequence Invoice date inconsistent with rest of invoices Duplicate invoice numbers Invoice numbers are backwards Time and Expense Expense Not justified for work performed Excessive/Elaborate expenses Invoices not consistent with expenses submitted Unauthorized delay Time Schemes Ordering OT for work that should be completed in normal course of business Change order to escape liquidated damages Charging for work performed on holidays or unauthorized overtime Phantom weather General Conditions Duplicate Charges Inaccurate prorating 13
14 Types of Contracts Lump Sum, Fixed Cost, Stipulated Sum Design, Bid, Build EPC (Engineer, Procure, Construct) Cost Reimbursable or Cost Plus Cost Plus with Fixed or Percentage Fee Cost Plus with Guaranteed Maximum (GMAX or GMP) Design Build Time and Material 14
15 Red Flags to Look for During the Audit Debarment or poor reputation Billing in a non-standard format Owner has no or an ineffective project management team Acceptance of poor performance Weak change order language Change orders unusually high Lack of clear lines of accountability Un-reconciled construction in progress account or incomplete reconciliation Repeated use of same supplier Use of liaisons or middlemen Close relationship with vendors Failure to obtain lien waivers and reconcile High commissions Disorganized work site Failure to disclose key information about key contractor stakeholders Contract omits right-to-audit clause 15
16 Elements of a Typical Construction Audit Program (1) Contract review Bid review Control assessment Contractor billing tests Labor rates, number of employees, and labor burden Materials quantities and use of new materials Equipment (Contractor owned and rented) Subcontractor charges Correct unit pricing 16
17 Elements of a Typical Construction Audit Program (2) Permits and licenses Miscellaneous charges (small tools and consumables) Overhead charges Contractor fee Retainage calculation Performance bond and insurance Payroll taxes Applied rates for G & A and for profit Relocation and travel 17
18 Elements of a Typical Construction Audit Program (3) Control verification Financial review Lead schedules Receivables Payables Construction in progress Fixed assets Change orders 18
19 A Construction Audit Is a Multi Disciplined Approach Conventional Audit Skills Knowledge of Construction and Construction Terms Ability to read and understand contract language Data Analytics 19
20 What is a change order? Called many things: Change Orders Change Directives Contract Modification Engineering Change Notice Field Change Request Scope Modification Technical Modification No matter what it is called, it represents the owner s authorization to change the contract s terms and conditions (typically related to the scope or timing of the project) 20
21 Impact of a change order? Scope change (increase or decrease) Quantity change Schedule change All of these modifications directly impact the contract between the owner and the contractor. Most importantly, schedule changes can have far reaching impacts on project completion and liquidated damages. 21
22 Why do change orders occur? Change in building codes / regulations Change in market conditions / requirements Change in field conditions Change in project specifications Change in construction conditions Contingency expenditures Unanticipated project work 22
23 Change Order Audit Program Planning: Documentation and control Authorization Staff approval Elected Official approval Price Analysis Scope Analysis Schedule 23
24 Change Order Audit Provisions: Clearly defined contract terms Definition of major versus minor change order Delineation of who approves each type Use of contingency budget prior to change order Documentation required for change orders 24
25 Change Order Documentation: Narrative on scope for change order What is covered? Why is it required? Relation to original scope of work Schedule revisions (if required) Who is conducting the work? Compensation approach Detail on rates, hours, and quantities of labor, equipment and materials required Profit 25
26 Change Order Evaluation Checklist Appropriately authorized by the appropriate entity Work not previously approved or rejected Approved and already paid for (original scope or prior change order) Rejected items resubmitted Evaluate change orders at the line item level Look for duplicate change orders / work tasks Verify all computations Ensure general conditions actually changed before accepting a GC fee adjustment 26
27 Change Order Pricing Evaluation Ensure materials covered at actual cost (or cost plus if provided for in contract). Verify quantities appropriate for scope of work and actually installed / utilized Be clear what is included in labor rate Are the rates utilized in alignment with contract? Are fringe benefits covered in labor rate or add ons? Is profit a separate line item? Evaluate hours charged By individual and classification Reasonable for work performed? Request supporting documentation for any lump sum payment 27
28 Change Order Audit Risks Unauthorized change orders Unnecessary change orders Work covered by original agreement Addresses risks assumed by contractor in original contract Not justified / authorized work Redundant or duplicate change orders Overpriced change orders 28
29 Unauthorized Change Orders No work should be performed, absent emergency situations outlined in the contract, without prior approval. Reasons these occur: Budget overrun Miscommunication between contractor and owner representative Procrastination Quality Issues / Rework Schedule delays Warranty work 29
30 Unnecessary Change Orders Change orders submitted without a valid business purpose. They may be approved but provide little value to owner. Key areas to evaluate: Existing scope of work Provision of unrequired add on services 30
31 Redundant or Duplicate Change Orders Change orders that have overlapping or poorly defined scopes of work. Key areas to evaluate: Existing scope of work Provision of unrequired add on services 31
32 Overpriced Change Orders Change orders that require compensation above reasonable level for scope of work covered. Key areas to evaluate overpricing: Inflated labor rates Inflated hours Excessive profit margins Inaccurate math (compounding calculations, incorrect fee add ons, inclusion of costs previously covered) 32
33 Contingency Budgets: Contractor s contingency: Contractors budget to cover in scope budget changes. Owner s contingency: Owner s budget to cover minor scope changes. 33
34 Red Flags related to Change Orders Too few change orders Too many change orders Changing contractors during construction Excessive material / equipment substitutions Project end change orders Bids prepared prior to availability of 100% construction documents No negotiated / rejected change orders Change order value greater than 10% of original budget Unclear narrative justification for change order 34
35 Key Resources American Institute of Architects (AIA) Model Contracts Starting point but may favor architect and contractor not owner AASHTO Cost of Construction Guidelines RS Means Construction cost estimating data source TRA SER (Trade Service by Trimble Company) Provides trades pricing data and product information Audits completed by peer auditors 35
36 Contractors know the impact of Change Orders! 36
37 Thank You 37
38 QUESTIONS AND ANSWERS Kinney Poynter Moderator Executive Director NASACT Alan Pennington Speaker Vice President Matrix Consulting Group 38
Managing Fraud Risks. Procurement & Contacting. John J. Hall, CPA (970)
Managing Fraud Risks in Procurement & Contacting The IIA Los Angeles Chapter October 2, 2017 John J. Hall, CPA (970) 926-0355 John@JohnHallSpeaker.com 1 Four Categories 1. Theft 2. Results Manipulation
More informationConstruction Auditing: Where To Start And How to make It Work For Your Organization. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,
Construction Auditing: Where To Start And How to make It Work For Your Organization Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International.
More informationWhat You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President
What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives
More informationCreating value through vendor management. 16 April 2014
Creating value through vendor management 16 April 2014 Agenda Vendor management risk Contract risk Audit planning Contract compliance auditing Value add for Company and Internal Audit EY Major Capital
More informationIIA San Diego Chapter Government Auditing Seminar
IIA San Diego Chapter Government Auditing Seminar Capital Project Performance Auditing November 2013 Introduction In today s contracting environment, it is important to understand the risks when embarking
More informationThe Practitioner s Blueprint to Construction Auditing Ron Risner, MBA, CIA, CCA, CCP 2012, The IIA Research Foundation.
The Practitioner s Blueprint to Construction Auditing Ron Risner, MBA, CIA, CCA, CCP 2012, The IIA Research Foundation Table of Contents List of Figures Executive and Preface Acknowledgments About the
More informationAudio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program
Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications
More informationAUDITING INVOICES 101
AUDITING INVOICES 101 AUDITING CONSULTANT INVOICES Definitions MCA: Master Consulting Agreement parent agreement that contains general terms and conditions by which consultants provide services CSA: Consultant
More informationFRAUD SCHEMES. South Carolina HFMA Finance & Reimbursement Forum. November 13, 2012 WITH RELATED INTERNAL CONTROLS
FRAUD SCHEMES WITH RELATED INTERNAL CONTROLS South Carolina HFMA Finance & Reimbursement Forum November 13, 2012 2 Fraud Facts: Estimated loss of 5% of annual revenues to occupational fraud Financial statement
More informationConstruction controls. Capital project controls for owners
Construction controls Capital project controls for owners TABLE OF CONTENTS The three constraints... 4 Common issues... 5 Construction project audit methodology... 6 Construction controls and oversight
More informationLake County School District s. Construction Audit for. Eustis Heights Elementary School. Executive Summary & Detailed Audit Report
1 Lake County School District s Construction Audit for Eustis Heights Elementary School Executive Summary & Detailed Audit Report Fiscal Year 2014 2015 Completed By: Thomas A. Mock, CIA Date: August 27,
More informationContract and Procurement Fraud
Contract and Procurement Fraud Performance Schemes 2018 Association of Certified Fraud Examiners, Inc. Invoicing Schemes Vendor submits fraudulent invoices to generate false payments. False invoices Inflated
More informationAll American Asphalt Annual Street Improvement Contract Audit
All American Asphalt Annual Street Improvement Contract Audit The contractor was paid $2.5 million for projects outside of set contract pricing in a nine- month period. Not all of these projects adhered
More informationBottom-line Savings through Contract Compliance and Cost Recovery
Bottom-line Savings through Contract Compliance and Cost Recovery Presenters: George Albarelli, John Fiore, Chris Fejko and Tarek Ibrahim November 13, 2012 General Information Share the webinar Ask a question
More informationOBJECTIVES, SCOPE, AND METHODOLOGY
OBJECTIVES, SCOPE, AND METHODOLOGY Pursuant to our approved annual plan, we have completed an audit of the University Major Construction Project, specifically Student Academic Success Center Capital Project.
More informationTopics. Current Environment and Relevant Risks. Speakers. Contract and Compliance Monitoring Building a Successful Program
Speakers Contract and Compliance Monitoring Building a Successful Program January 21, 2016 Alyssa G. Martin, CPA Executive Partner, Advisory Services 25+ years of public accounting experience, with a practice
More informationIIA Springfield IL Chapter
Adding Value with Data Analytics IIA Springfield IL Chapter October 14, 2010 0 Jan Beckmann, CPA, ACL Certified Trainer, ACDA jbeckmann@bswllc.com 314.983.1254 1050 N. Lindbergh Blvd. St. Louis, Missouri
More informationSage MyAssistant - Construction Tasks
Sage MyAssistant - Construction Tasks Accounts Payable Invoice Management Banks with insufficient cash Commitments with unsigned change orders and are selected to be paid Invoices from the same vendor,
More informationHow to stop improper payments: A focus on government vendor risk
How to stop improper payments: A focus on government vendor risk TODAY S SPEAKERS Nichole Gable SENIOR MANAGER KEARNEY & COMPANY Nonie Dalton SENIOR PRODUCT MANAGER, PUBLIC SECTOR, ACL IN TODAY S WEBINAR
More informationLong Beach City Auditor s Office
Long Beach City Auditor s Office Contract Administration Audit Limited Scope Review Report 7 of 10 Utiliworks Consulting, LLC July 1, 2016 Laura L. Doud City Auditor Audit Team: Deborah K. Ellis Assistant
More informationEXAMINATION REPORT Wastewater Management Division Contractor Hiring & Payment Practices
EXAMINATION REPORT Wastewater Management Division Contractor Hiring & Payment Practices July 2017 Office of the Auditor Audit Services Division City and County of Denver Page 1 The Auditor of the City
More information2/20/2014. Agenda. Allen Still & Ryan Merryman March 31, CLAconnect.com CliftonLarsonAllen LLP Continuous Auditing Programs
Continuous Auditing Programs Allen Still & Ryan Merryman March 31, 2014 CLAconnect.com Agenda Presentation Objectives Defining Continuous Auditing Programs The Benefits of Continuous Auditing Demonstration
More informationContract and Procurement Fraud
Contract and Procurement Fraud Fraud in Procurement Without Competition 2018 Association of Certified Fraud Examiners, Inc. Sole-Source Awards The procurement process is noncompetitive through the solicitation
More informationChicago Department of Transportation CDOT Professional Services Voucher Payment Process
Agenda Welcome Introductions Commissioner s message CDOT s Mission Statement Overview (Professional Services Voucher Payment Process) History Audit CDOT changes Objectives Benefits CDOT s New Invoice Process
More informationROLES AND RESPONSIBILITIES
Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationOffice of the City Auditor. Committed to increasing government efficiency, effectiveness, accountability and transparency
Office of the City Auditor Committed to increasing government efficiency, effectiveness, accountability and transparency Issue Date: TABLE OF CONTENTS Executive Summary... ii Recommendation... iv Background...1
More informationConnecticut Housing Finance Authority
Connecticut Housing Finance Authority Cost Certification Preparation Guideline 2019 This Guideline is effective COST CERTIFICATION PREPARATION GUIDELINE I. Purpose The purpose of the cost certification
More informationTHE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES
THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES INTRODUCTION The purpose of this guide is to document general procedures a contractor might implement for the (1) Bidding, Planning and Scheduling Functions,
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationCharges to sponsored projects are classified as either non-salary or salary.
EXPENDITURE APPROVAL AND CONTROL INITIATING CHARGES TO SPONSORED PROJECTS Charges to sponsored projects are classified as either non-salary or salary. Non-salary charges are initiated via: 1. Pcard; 2.
More informationDocument B105. Standard Form of Agreement Between Owner and Architect for a Residential or Small Commercial Project
TM Document B105 2007 Standard Form of Agreement Between Owner and Architect for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.)
More informationCONSTRUCTION DOCUMENTS Part 1
Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationUNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT PURCHASE CAPITAL GOODS
The following control objectives provide a basis for strengthening your control environment for the process of purchasing capital goods. When you select an objective, you will access a list of the associated
More informationMetropolitan Council
2011-A17 Program Evaluation and Audit Metropolitan Council Professional Services Contracts Review August 15, 2011 INTRODUCTION Background Program Evaluation and Audit (Audit) recently conducted a review
More informationCHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS
CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical
More information9/12/2013. CAPITALIZE ON YOUR PURCHASING CARD PROGRAM September 20, Agenda. With a card payment you can:
CAPITALIZE ON YOUR PURCHASING CARD PROGRAM September 20, 2013 Agenda Why Use a Commercial Card? Review the benefits of a card solution Travel Cards Automate expense reporting and gain visibility into spend
More information6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents
Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3
More informationContract and Procurement Fraud. Fraud in Procurement without Competition
Contract and Procurement Fraud Fraud in Procurement without Competition Sole-Source Awards Noncompetitive procurement process through the solicitation of only one source Procurement through sole-source
More informationG , Request for Proposal Land Survey
G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994
More informationDocument B252TM 2007
Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation
More informationEJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center
EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationREQUEST FOR PROPOSALS FOUR YEAR CONTRACT FOR TEMPORARY EMPLOYEE SERVICES BID NO: Addendum 1: August 16, 2018
REQUEST FOR PROPOSALS FOUR YEAR CONTRACT FOR TEMPORARY EMPLOYEE SERVICES BID NO: 18-2050 : August 16, 2018 has been issued to address the following: 1. Modify one requirement to the Scope of Service. 2.
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationBidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue
Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued
More information2013 Small & Emerging Contractor Webinar Series. Estimating and Bidding
2013 Small & Emerging Contractor Webinar Series Estimating and Bidding What is an Estimate? The first step to obtaining work. Includes costs for the following Material Labor Equipment Types of Estimate
More informationAudit Department Report for June 2014
Report Report Office of the General Auditor Audit Department Report for June 2014 Summary Three reports were issued during the month: Gas Card Program Audit Report and Management Response ABSG Consulting,
More informationCHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,
More informationFraud Prevention Training
Fraud Prevention Training The Massachusetts Collectors and Treasurers Association Sixty-Sixth Annual Education Conference June 15, 2015 Presented By: Eric Demas, CFE Melanson Heath edemas@melansonheath.com
More informationOracle ERP Cloud Period Close Procedures
Oracle ERP Cloud Period Close Procedures Release 13 O R A C L E W H I T E P A P E R A U G U S T 2 0 1 7 Table of Contents Introduction 8 Chapter 1 Period Close Dependencies 9 Chapter 2 Subledger Accounting
More informationFinancial Controls Checklist
Financial Controls Checklist Board of Health: Board of Health for the Leeds, Grenville & Lanark District Health Unit Period ended: Dec. 31/17 Objective: The objective of the Financial Controls Checklist
More informationPayables Management. 2 nd Edition. Steven M. Bragg
Payables Management 2 nd Edition Steven M. Bragg Chapter 1 Overview of Payables... 1 Learning Objectives... 1 Introduction... 1 Transaction Cycles... 1 Organizational Structure of the Accounting Department...
More informationCan You Spot Fraudsters?
Can You Spot Fraudsters? CACUBO Workshop March 22, 2018 Eric Conforti, CPA, CFE 1 Who Are We? A One-Firm Firm: Over 2,200 industry experts to partner with when specific industry knowledge is needed during
More informationImplementing effective third-party frameworks in the life sciences industry leading practices and challenges
Implementing effective third-party frameworks in the life sciences industry leading practices and challenges Introduction The recent enforcement environment has reinforced the risks associated with third-party
More informationINTERNAL AUDIT DEPARTMENT
CONSTRUCTION CONTRACT AUDIT Craig Hametner, CPA, CIA, CMA, CFE City Auditor Prepared By: Randall Mahaffey, CIA, CGAP Senior Audit Analyst Jed Johnson Audit Analyst Stephen Culpepper, CPA Audit Analyst
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationThe documents in the A-Series relate to various forms of agreement between an owner and a contractor.
A-Series A- S E R I E S The documents in the A-Series relate to various forms of agreement between an owner and a contractor. A101 Owner-Contractor Agreement Form Stipulated Sum Basis of payment is a stipulated
More informationIMPORTANCE OF FINANCIAL PROCESSES INCLUDING CHART OF ACCOUNTS AND PRICING THE PRODUCT. By CA Ketoki Basu
IMPORTANCE OF FINANCIAL PROCESSES INCLUDING CHART OF ACCOUNTS AND PRICING THE PRODUCT By CA Ketoki Basu Financial Process-Methods Visuals/Detailed flow charts Accounts Manual Purchase/Procurement Manual
More informationBIDDING AND ESTIMATING
BIDDING AND ESTIMATING Chapter Survey ð Bid Documents ð Ethics in Bidding ð Estimate Planning ð Estimating Framework ð Determining Estimated Costs ð Other Methods of Estimating ð Estimating Pitfalls ð
More informationWhat Happens When Internal Controls Fail
What Happens When Internal Controls Fail 1 Your Presenters Brian Sanvidge Principal Baker Tilly Ellen Labita Partner Baker Tilly Danielle Callaci Manager Baker Tilly 2 Today s Agenda > What are Internal
More informationADDENDUM NO. 3. Item 3 NOTICE OF OPPORTUNITY - REPLACE in its entirety with the attached ***REVISED 08/03/2018
Construction Contracts Administration, Procurement Contracts & Materials Management (PCMM) Oregon State University 644 SW 13 th Ave. Corvallis, Oregon 97333 P 541-737-4261 F 541-737-5546 oregonstate.edu
More informationMT.SAC 1 Mt. San Antonio College
MT.SAC 1 Mt. San Antonio College Guidelines Employee vs. Independent Contractor Background Since 1987, the Internal Revenue Ruling 87-41 used twenty common law factors for determining independent contractor
More informationWhat Are Your Sage 100 Contractor Financial Reports Telling You?
What Are Your Sage 100 Contractor Financial Reports Telling You? Presented by: Leslie Shiner Owner, The ShinerGroup L.Shiner@ShinerGroup.com Copyright Notice 2013 Sage Software, Inc. All rights reserved.
More informationNeighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
More informationEMPLOYEE FRAUD OPPORTUNITIES CHECKLIST
Page 128 of 174 EMPLOYEE FRAUD OPPORTUNITIES CHECKLIST Recognizing Warning Signs and Preventing Problem Situations Why are consistent internal controls important? Management decisions, financial reports,
More informationSMALL BUSINESS FRAUD ASSESSMENT INTERNAL CONTROL QUESTIONNAIRE Download your risk assessment form at
SMALL BUSINESS FRAUD ASSESSMENT INTERNAL CONTROL QUESTIONNAIRE Download your risk assessment form at www.businessfraudprevention.org/forms.html Owner: Date: Discussed with: Question Yes No N/A Comments
More informationRecommended mitigating controls
1. SELECTION OF APPLICANTS Overarching controls Secondary panel could review individual decisions or a sample of decisions made by the evaluation panel. Adequate training courses on ethics and integrity,
More informationUNIVERSITY OF CALIFORNIA, MERCED INTERNAL AUDIT SERVICES. Construction Audit (Systemwide) Report No. M12A002. April 13, 2012
UNIVERSITY OF CALIFORNIA, MERCED INTERNAL AUDIT SERVICES Construction Audit (Systemwide) Report No. M12A002 April 13, 2012 Work Performed by: Todd Kucker, Internal Audit Director Introduction A construction
More informationEmployee Expense Audit
Employee Expense Audit June 12, 2018 ISC: Unrestricted THIS PAGE LEFT INTENTIONALLY BLANK ISC: Unrestricted Table of Contents Executive Summary... 5 1.0 Background... 6 2.0 Audit Objectives, Scope and
More informationUsing Data Analytics as a Management Tool to Identify Organizational Risks
2013 CliftonLarsonAllen LLP Using Data Analytics as a Management Tool to Identify Organizational Risks Government Finance Officers Association of South Carolina October 13, 2014 cliftonlarsonallen.com
More informationInternal Control Checklist
Instructions: The may be used to document a review of the existing procedures and activities that make up your internal control system, or serve as a guide in developing additional controls. The provides
More informationMini Summit VI - MANAGING THIRD PARTY RELATIONSHIP RISKS
Mini Summit VI - MANAGING THIRD PARTY RELATIONSHIP RISKS Third-party risks FCPA prosecutions frequently cite use of local agents to pay bribes and conceal payments FCPA prohibits both direct or indirect
More informationREQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services
REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request
More informationODP Year 3 Transportation Cost Report Instructions. Prospective Payment System Rating Period: Fiscal Year 2011/2012 (July 1, 2011 June 30, 2012)
December 10, 2010 ODP Year 3 Transportation Cost Report Instructions Prospective Payment System Rating Period: Fiscal Year 2011/2012 (July 1, 2011 June 30, 2012) Commonwealth of Pennsylvania Office of
More informationYes No. Yes. Yes. Firm Name. What form of business entity is your firm? When is your firm s fiscal year end (FYE)? (mm/dd/yyyy)
Please answer each question fully to the best of your ability. Incomplete forms will be returned for additional information. If firm has already completed the AASHTO ICQ, please provide that instead of
More informationConstruction Family of Documents
Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications
More informationProject Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP
Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction
More informationImproper Billing of Costs on Progress Payments 1
Improper Billing of Costs on Progress Payments 1 1 Progress payments are not interim vouchers or invoices that the government pays based on the allowable costs incurred and charged to the contract. Instead,
More informationBidding & Estimating Course Syllabus
Bidding & Estimating Course Syllabus 2 Hours (Interactive) Introduction & Overview to Bidding & Estimating Review Sundt/Walsh Abstracting Process Estimating Templates Introduction to Estimating Bid Documents
More informationYour School District Procurement Card. Staff Guide Staff Agreement & Board Policy
Your School District Procurement Card Staff Guide Staff Agreement & Board Policy OVERVIEW The Procurement Card Program is intended to streamline and simplify the Procurement and Accounts Payable functions.
More informationMaintenance and Operations 1302 Service Road Tustin, California (714) CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20
Maintenance and Operations 1302 Service Road Tustin, California 92780 (714) 730-7515 CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20 The Tustin Unified School District ( District ) has determined that
More informationUniversity System of Maryland University of Baltimore
Audit Report University System of Maryland University of Baltimore January 2018 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY For further information concerning
More informationAudit Report 2019-A-0001 Town of Lake Clarke Shores Water Utility Cross-Connection Program October 18, 2018
PALM BEACH COUNTY John A. Carey Inspector General Inspector General Accredited Enhancing Public Trust in Government Audit Report Town of Lake Clarke Shores Water Utility Cross-Connection Program October
More informationModule 1: Safeguarding District Resources: Roles & Responsibilities
Module 1: Safeguarding District Resources: Roles & Responsibilities Presenter: Jamie P. McPherson Leadership Development Manager New School Board Member Mandated Training Day Two: Fiscal Oversight Training
More informationDon't Get Lost in the Labyrinth of Supplier Cost Flows into Projects. Dina Rotem John Sasali
Don't Get Lost in the Labyrinth of Supplier Cost Flows into Projects Dina Rotem John Sasali About RAFAEL About E-Business Suite in RAFAEL RAFAEL is an Israeli company. About 5100 employees. Revenue of
More informationPre-Engagement Activities and Audit Planning By: Tariq Mahmood FCA, ACMA
Model Audit Practice Manual Pre-Engagement Activities and Audit Planning By: Tariq Mahmood FCA, ACMA Today s Learnings Pre-Engagement Activities Audit Planning Procedures Completion of Sample Forms (Annexures)
More informationINTERNAL AUDIT EFFECTIVENESS. Conducting Fraud Investigations Conducting Internal Audit
INTERNAL AUDIT EFFECTIVENESS Conducting Fraud Investigations Conducting Internal Audit Conducting Fraud Investigations Why Fraud? Fraud is the product of three factors: Supply of motivated offenders; The
More informationUsing Data Analytics to Detect Fraud
Using Data Analytics to Detect Fraud Data Analysis Tests for Detecting Payroll and Expense Reimbursement Schemes 2018 Association of Certified Fraud Examiners, Inc. Payroll Schemes Fraudsters cause their
More informationChapter 6, Construction
Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference
More informationTen Payment Fraud Protections
Ten Payment Fraud Protections 1. Payee Positive Pay a. Provided by banks b. Banks match check serial numbers and dollar amounts against a company provided list of checks issued and only pays those checks
More informationIRVINE UNIFIED SCHOOL DISTRICT CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20
CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20 The Irvine Unified School District ( District ) has determined that bidders on an annual basis must be prequalified prior to submitting a bid on a project
More informationBidding Conditions Attachment C
Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS
More informationLGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP
PMO-RALG ENHANCEMENT OF PROCUREMENT CAPACITY OF LOCAL GOVERNMENT AUTHORITIES PROJECT (EPC LGAP) LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PROCUREMENT COMPLIANCE & PERFORMANCE AS PER
More informationCity Property Damage Claims Processing and Collection
City Property Damage Claims Processing and Collection March 30, 2016 Report 201602 City Auditor: Jed Johnson, CIA, CGAP Major Contributor: Marla Hamilton Staff Auditor Jonna Murphy Staff Auditor Contents
More informationSeveral unallowable expenditures and exceptions to policy were noted.
Several unallowable expenditures and exceptions to policy were noted. In our testing of 16 disbursement/pcard transactions, 12 travel transactions, and 9 gift transactions, we noted 6 transactions contained
More informationRevenew s Cost Recovery and Cost Containment services return dollars to your budgets. We recover over $100 million for our clients annually.
Revenew s Cost Recovery and Cost Containment services return dollars to your budgets. We recover over $100 million for our clients annually. COST RECOVERY Contract Compliance Reviews Supplier Payment Reviews
More informationBFSv9 Internal Controls Guidance
presented by: Hans Gude, MBA, CIA Barbara VanCleave Smith, PhD, CPA Office of Ethics, Compliance, and Risk Management Presented May 10 and 17, 2010 LMS Course Number BECTR306 1 Today s Topics 1. Overview
More informationDefective Pricing- Material Pricing Deficiencies. Next Slide
Defective Pricing- Material Pricing Deficiencies Table of Contents Risk Assessment Research and Planning Risk Assessment - Initial Data Obtained from Contractor Risk Assessment Overrun or Underrun Analysis
More informationCOAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee
COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract
More informationTransportation and Infrastructure Renewal: Mechanical Branch Management
4 Transportation and Infrastructure Renewal: Mechanical Branch Management Summary The Department of Transportation and Infrastructure Renewal s management of mechanical branch operations is deficient.
More informationExhibit MSD 84W ENGINEERING TIME AND MATERIALS CONTRACT REVIEW
Exhibit MSD 84W ENGINEERING TIME AND MATERIALS CONTRACT REVIEW February 2011 February 11, 2011 Audit Committee Metropolitan Sewer District 2350 Market Street St. Louis, MO 63103 Re: Dear Audit Committee
More information