Darlington NGS 'A' - Outlet Feeder Dissimilar Metal Weld Leak-Before-Break Assessments - Update 2

Size: px
Start display at page:

Download "Darlington NGS 'A' - Outlet Feeder Dissimilar Metal Weld Leak-Before-Break Assessments - Update 2"

Transcription

1 ONTARIOFiiiiiER GENERATION Brian Duncan Senior Vice President Darlington Nuclear P.O. Box 4000 Bowmanville, ON L1 C3Z8 Tel: Fax: November 27,2012 NK P Mr. P.A. Webster Director, Darlington Regulatory Program Division Canadian Nuclear Safety Commission P.O. Box Slater Street OlTAWA, Ontario K1P 5S9 Dear Mr. Webster: Darlington NGS 'A' - Outlet Feeder Dissimilar Metal Weld Leak-Before-Break Assessments - Update 2 The purpose of this letter is to provide CNSC staff with the second update of the project activities associated with the Leak-Before-Break (LBB) assessments on Darlington feeder Dissimilar Metal Welds (DMW) regarding deterministic and probabilistic assessments as submitted in Reference 1. The update was also presented to CNSC Operational Engineering Assessment Division specialists and Licensing Staff at the meeting held on October 25, 2012 in Ottawa. As documented in Attachment 1 COG report, "Interim Deterministic Leak-Before-Break Assessment of DMWs in DNGS Outlet Feeders", sufficient margins on LBB in the base case are established for 40 out of 44 outlet feeders. The design loads at the flow elements are used together with an operational leak rate limit of 25 kg/h and a factor of five on detectable leak rate to account for the uncertainty in the leak rate calculation. Should the type of leaking through-wall crack studied in this report develop during an accident load, the crack growth due to the accident loading is not significant and could be detected with existing leakage detection capability and the reactor will be safely shutdown according to the operating procedure. The consequential leakage from the crack is bounded by the existing safety analysis. As documented in Attachment 2 COG report, "Probabilistic Leak-Before-Break Assessment of DMWS in DNGS Outlet Feeders", the probabilistic LBB assessment was carried out for 15 feeders, selected from Attachment 1 deterministic asse~sment and Ontario Power Generation Inc., This document has been produced and distributed for Ontario Power Generation Inc. purposes only. No part of this document may be reproduced. published, converted, or stored in any data retrieval system, or transmitted in any form or by any means (electronic, mechanical, photocopying, recording, or otherwise) without the prior written of Ontario Power Generation Inc. Associated with OPG-STD-0031, Correspondence Standards OPG-TMP-0007-R004 (Microsoft 2007)

2 Mr. P.A. Webster November 27, 2012 including the four feeders with reduced margin. The assessment has demonstrated that DMW rupture is a very low probability event. The calculated rupture frequency is significantly low and shall meet CANDU feeder pipe acceptable rupture frequency currently under development. The assessment also shows that the current 25 kg/h operational leak rate limit is critical to detect a leakage and to ensure reactor safe shutdown to avoid potential feeder rupture. Nonetheless, inspection of DMW every two or three years, a high dose activity, has little effect in reducing the rupture probability. As documented in Attachment 3 COG report, "Natural PWSCC Crack Growth Analysis for Circumferential Crack in Darlington Feeder Dissimilar Metal Weld': AFEA (Advance Finite Element Analyses) is used to simulate "natural" crack growth. The methodology allows the progression of a planar crack subjected to typical stress corrosion cracking growth laws by calculating stress intensity factors at every nodal point along the entire crack front. The calculation is incrementally advancing the crack front in a more natural manner which overcomes overconservatism in the semi-elliptical crack fronts used in the conventional fracture mechanics. The Welding Residual Stress (WRS) profile from welding simulation/measurement results was implemented in AFEA models. The results of this initial study have demonstrated that the time intervals from the assumed initial flaw size to the incipient leakage and from the incipient leakage to 125 kg/h (operational action leak rate of 25 kg/h with safety factor of five), as well as from 125 to 1800 kg/h (immediate shutdown limit) are all sufficiently long to ensure reactor safe shutdown as per the current Darlington operation procedures. As documented in Attachment 4 COG report, "Residual Stress Measurements of Dissimilar Metal Welds in Feeder Piping by Neutron Diffraction", residual stress measurements were performed on two 3.5" NPS piping items consisting of DMW similar to Darlington feeders. The measured residual stresses using both neutron diffraction and X-Ray diffraction techniques agree reasonably well with the predicted values from finite element simulation of the dissimilar metal weld. Further to Reference 1, Attachments 1, 3 and 4 are the final reports of the three draft COG reports OPG committed to providing CNSC staff. Please note that there are slight title and reference number changes to these reports as to what was originally documented in Reference 1. Based on the improved knowledge from DMW engineering assessments made in the past two years, OPG proposes to modify the original project plan in order to effectively achieve final LBB deliverables in The current project status and justifications to change some of original activities are provided in Attachment 5. WRS is well recognized in the literature and Operating Experience as one of the main contributors of DMW stress cracking. In addition, both probabilistic and initial AFEA assessments have identified that WRS amplitude and profile are key input parameters. At present, there is no WRS data for repaired welds which are present at Darlington DMW. WRS on repaired welds could be very different from the current measurement and simulation data made on non-repaired welds. Nonetheless, with realistic WRS (Microsoft 2007) Page 2 of 4

3 Mr. P.A. Webster November 27, 2012 inputs, further AFEA studies could close the gap between deterministic and probabilistic assessments. Therefore, future DMW work will focus on weld residual stress and refined AFEA including: 1. WRS study: literature review or modeling or measurement 2. Refined AFEA: implement WRS results in AFEA OPG will provide CNSC staff with an update by November 29, 2013 of the project activities listed in Attachment 5, including completed project reports and an updated schedule. A Regulatory Management Action Request will be raised to track the project update. This submission completes Regulatory Management Action Request Should you have any further questions, please contact Mr. Garry Lam, Acting Section Manager - Major Components and Equipment Department - Feeders, at (905) ext Sincerely, ~c1~~ Brian Duncan Senior Vice President Darlington Nuclear Ontario Power Generation Inc. Attach. cc: Mr. A. Ling - CNSC (Darlington) OPG-TMP-0007-R004 (Microsoft 2007) Page 3 of4

4 Mr. P.A. Webster November Reference: 1. OPG letter, B. Duncan to P.A. Webster, "Darlington NGS 'A' Outlet Feeder Dissimilar Metal Weld Leak-Before-Break Assessments - Update 1", November 21, 2011, CD# NK38-CORR OPG-TMP-0007-R004 (Microsoft 2007) Page 4 of4

5 ATTACHMENT 5 OPG letter B. Duncan to P.A. Webster, "Darlington NGS 'A' - Outlet Feeder Dissimilar Metal Weld Leak-Before-Break Assessments - Update 2" CD# NK38-CORR Current Status of Project Activities and Justifications of Modification Prepared by: Checked by: M.Li R. Chelliah

6 Attachment 5 Status of Project Activities and Justifications for Modifications No. 1 1a Activity Residual stress measurements and modeling. AFEA analysis of PWSCC Crack Growth for Circumferential Cracks in Feeder Piping Girth Welds. Refined probabilistic LBB assessment. Characterization of tensile and fracture toughness properties. Refined deterministic LBB assessment. 5 EBSDIXRD analysis of DMW. 6 DMW component tests. Preliminary PWSCC growth 7 tests and plastic strain analysis. Status and Modification Justifications COG-JP-4401-V07 RO. Initial assessment report COG Completed. In deterministic assessment: elastic modulus (E), yield strength (S,) and tensile strength (Su) are code values. Flow strength is back calculated from the component test. Sensitivity study shows no effect on conclusions if flow strength of Alloy 600 flow strength code value is used (Table 15 in COG-JP-4401-V06 R1). In probabilistic assessment: elastic modulus (E), yield strength (Sy) and tensile strength (Su) are code values. Flow strength, and J-R curve are back calculated from the component test, Sensitivity study shows tensile properties and fracture toughness have little impact on conclusions (Table 16 in COG-JP-4401-V26 RO). Tensile & hardness test results: COG Completed. This work is aim to map the orientation of the crystallographic structure to very high resolutions. It may provide fundamental understanding of PWSCC in microscope level but it has no impact on the current enqineering assessments. The main purpose of tests is to support the net section collapse model be applicable to feeder pipes. Results from a 145' through wall hot commission and a 70' through-wall tests were all conservative and able to support the model application. Hot commission test: COG PWSCC crack growth rate for Alloy 82 and Alloy 600 became available in ASME Boiler and Pressure Vessel Section XI in Higher growth rates were also studied; results indicated no impact on the rupture frequency conclusions. Action Literature review or modeling or measurement on WRS is planned. Target Completion Date (TCD): June Further investigations are planned to implement WRS results in AFEA. TCD: October COG-JP-4401-V26 RO Update with WRS results if necessary. Completed fracture toughness test results will be documented in a COG report: TCD June COG-JP-4401-V06 R1. Preliminary EBSD results will be documented in a COG report: TCD June The 70' through wall test will be documented in a COG report: TCD June When US Dissimilar Metal Weld Pipe Fracture Program (N a 8" pipe test) results become available, OPG will review and assess. 8 9 Final PWSCC growth rate tests and post-ebsd analysis. Final engineering LBB assessments. Abbreviations: AFEA - Advanced Finite Element AnalysiS LBB - Leak-Before-Break DMW - Dissimilar Metal Weld J-R curve - Crack resistance fracture toughness curve JP-xxxx -Represents numbers assigned for projects by CANDU Owners Group EBSD - Electro Back Scatter Diffraction XRD X-ray Diffraction PWSCC - Primary Water Stress Corrosion Cracking WRS - Weld Residual Stress Same as items 5 and 7. November

Darlington NGS Integrated Implementation Plan (IIP) Change Control Process Principles

Darlington NGS Integrated Implementation Plan (IIP) Change Control Process Principles RETENTION: P ASSOCIATED AR: 28171984 November 7, 2014 File No.: CD#: NK38-00531 P NK38-CORR-00531-16991 MR. F. RINFRET Director Darlington Regulatory Program Division Canadian Nuclear Safety Commission

More information

Darlington NGS Integrated Implementation Plan (IIP) Change Control and Closeout Process

Darlington NGS Integrated Implementation Plan (IIP) Change Control and Closeout Process RETENTION: P Dietmar Reiner Senior Vice President Nuclear Projects 1855 Energy Drive, Courtice, ON L1E 0E7 Tel: 905-623-6670 ext. 5400 d.reiner@opg.com March 25, 2015 File No.: NK38-00531 P CD#.: NK38-CORR-00531-17309

More information

ONTARIOFiiWER GENERATION. Brian Duncan Senior Vice President. Darlington Nuclear. May 1, 2014 NK P NK38-CORR P

ONTARIOFiiWER GENERATION. Brian Duncan Senior Vice President. Darlington Nuclear. May 1, 2014 NK P NK38-CORR P ONTAROFiiWER GENERATON Brian Duncan Senior Vice President Darlington Nuclear P.O. Box 4000 Bowmanville, ON LlC 3Z8 Tel: 905-697-7499 Fax: 905-697-7596 brian.duncan@opg.com May 1, 2014 NK38-00531 P NK38-CORR-00531-16780

More information

Progress Report on OPG Heat Transport System Aging Safety Analysis

Progress Report on OPG Heat Transport System Aging Safety Analysis ONTARIOFiiiiiER GENERATION 889 Brock Road pa2-sa 1 Pickering. Ontario L lw 3J2 W. M. (Mark) Elliott, P. Eng. Senior Vice President Nuclear Engineeri ng and Chief Nuclear Engineer Telephone: (905) 839-6746

More information

Regulatory Perspective on CANDU Feeder Pipe Degradation due to FAC and IGSCC

Regulatory Perspective on CANDU Feeder Pipe Degradation due to FAC and IGSCC Regulatory Perspective on CANDU Feeder Pipe Degradation due to FAC and IGSCC John C. Jin, Specialist Raoul Awad, Director, Canadian Nuclear Safety Commission Commission canadienne de surete nucleaire IAEA

More information

Overview of NRC-EPRI PWSCC Initiation Testing - Status Update

Overview of NRC-EPRI PWSCC Initiation Testing - Status Update Overview of NRC-EPRI PWSCC Initiation Testing - Status Update Materials Reliability Program Industry-NRC Materials R&D Meeting June 2-4, 2015 Rockville, MD Presentation Outline Background on PWSCC Initiation

More information

PVP PVP EFFECTS OF WELD OVERLAYS ON LEAK-BEFORE BREAK MARGINS

PVP PVP EFFECTS OF WELD OVERLAYS ON LEAK-BEFORE BREAK MARGINS Proceedings of the ASME 2011 Pressure Vessels & Piping Division Conference PVP2011 July 17-21, 2011, Baltimore, Maryland, USA Proceedings of PVP2011 2011 ASME Pressure Vessels and Piping Division Conference

More information

Pressurized Water Reactor Materials Reliability Program (QA)

Pressurized Water Reactor Materials Reliability Program (QA) Pressurized Water Reactor Materials Reliability Program (QA) Program Description Program Overview Stress corrosion cracking and general environmental corrosion of reactor coolant system components have

More information

BACKGROUND TO PROCEDURES IN SECTION XI OF THE ASME CODE FOR EVALUATION OF FLAWS IN NUCLEAR PIPING

BACKGROUND TO PROCEDURES IN SECTION XI OF THE ASME CODE FOR EVALUATION OF FLAWS IN NUCLEAR PIPING BACKGROUND TO PROCEDURES IN SECTION XI OF THE ASME CODE FOR EVALUATION OF FLAWS IN NUCLEAR PIPING Douglas A. Scarth Kinectrics, Inc. Toronto, Ontario, Canada Keywords: ASME, Section XI, nuclear, pipe,

More information

Ontario Power Generation Darlington Fuel Channel Fitness for Service. June 2015

Ontario Power Generation Darlington Fuel Channel Fitness for Service. June 2015 Ontario Power Generation Darlington Fuel Channel Fitness for Service June 2015 2 Darlington Fuel Channel Fitness for Service Report 1.0 Introduction The purpose of any power station, regardless of type

More information

TARGET FLAW SIZE IN CANDU FERRIT PIPES THE CONSIDERATION OF TILTED AND SKEWED FLAW ANGLES

TARGET FLAW SIZE IN CANDU FERRIT PIPES THE CONSIDERATION OF TILTED AND SKEWED FLAW ANGLES TARGET FLAW SIZE IN CANDU FERRIT PIPES THE CONSIDERATION OF TILTED AND SKEWED FLAW ANGLES Songyan Yang, OPG Richard Yee, AMEC-NSS KiSang Jang, COG 1 June 15-17 2010 3rd. International

More information

CRACK GROWTH AT STRUCTURAL DISCONTINUITIES AND WELDS

CRACK GROWTH AT STRUCTURAL DISCONTINUITIES AND WELDS CREEP AND CREEP-FATIGUE CRACK GROWTH AT STRUCTURAL DISCONTINUITIES AND WELDS Prepared by: F. W. Brust G. M. Wilkowski P. Krishnaswamy K. Wichman Engineering Mechanics Corporation of Columbus (Emc 2 ) Creep

More information

C. MOSES, A. BLAHOIANU, T. VIGLASKY, CCSN

C. MOSES, A. BLAHOIANU, T. VIGLASKY, CCSN C. MOSES, A. BLAHOIANU, T. VIGLASKY, CCSN (Canada) Canadian Regulatory Approach towards Ageing Degradation and In-Service Surveillance at Canadian CANDU Nuclear Power Plants Colin Moses Canadian Nuclear

More information

OPG's Deep Geologic Repository for Low and Intermediate Level WasteAttendance at the February 21, 2012 Panel Orientation Session

OPG's Deep Geologic Repository for Low and Intermediate Level WasteAttendance at the February 21, 2012 Panel Orientation Session ONTARIOFiiiER GENERATION Albert Sweetnam Executive Vice President Nuclear Projects 700 University Avenue, Toronto, Ontario M5G 1X6 Tel: 416-592-7537 albert.sweetnam@opg.com February 14, 2012 File: 00216-00531

More information

Courriel anonyme. Anonymous CMD 18-H File / dossier: Date: Edocs: In the Matter of.

Courriel anonyme. Anonymous  CMD 18-H File / dossier: Date: Edocs: In the Matter of. CMD 18-H4.150 File / dossier: 6.01.07 Date: 2018-05-02 Edocs: 5531380 Anonymous Email Courriel anonyme In the Matter of À l égard de Bruce Power Inc. Bruce A and B Nuclear Generating Station Bruce Power

More information

December 21, Dear Mr. Hanson

December 21, Dear Mr. Hanson December 21, 2018 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 SUBJECT:

More information

PVP ALTERNATIVE ACCEPTANCE CRITERIA FOR FLAWS IN FERRITIC STEEL COMPONENTS OPERATING IN THE UPPER SHELF TEMPERATURE RANGE

PVP ALTERNATIVE ACCEPTANCE CRITERIA FOR FLAWS IN FERRITIC STEEL COMPONENTS OPERATING IN THE UPPER SHELF TEMPERATURE RANGE Proceedings of the ASME 2012 Pressure Vessels & Piping Conference PVP2012 July 15-19, 2012, Toronto, Ontario, CANADA PVP2012-78190 ALTERNATIVE ACCEPTANCE CRITERIA FOR FLAWS IN FERRITIC STEEL COMPONENTS

More information

Evaluation of Pipe Weld NDE Indications

Evaluation of Pipe Weld NDE Indications Evaluation of Pipe Weld NDE Indications Brasse, Markus Westinghouse Electric Germany Dudenstrasse 44, D-68167 Mannheim, Germany Markus.Brasse@de.westinghouse.com ABSTRACT This paper discusses the evaluation

More information

Report. Sheet Number: I Revision Number: I Page: N/A I R000 I 1 of 82

Report. Sheet Number: I Revision Number: I Page: N/A I R000 I 1 of 82 ONTARIOPiiiiiiER GENERATION Report P-REP-03680-00033 I PiCKERING NGS PERIODIC SAFETY REVIEW SUMMARY I ~ii:lassificalion: Sheet Number: I Revision Number: I Page: N/A I R000 I 1 of 82 Ontario Power Generation

More information

Structural Integrity Assessments of Class 1 CANDU Components. Xinjian Duan, Michael J. Kozluk Atomic Energy of Canada Limited

Structural Integrity Assessments of Class 1 CANDU Components. Xinjian Duan, Michael J. Kozluk Atomic Energy of Canada Limited Structural Integrity Assessments of Class 1 CANDU Components Xinjian Duan, Michael J. Kozluk Atomic Energy of Canada Limited Outline Observed Degradations Steam Generator Tubing Feeder Piping Fitness-for-Service

More information

Supplementary Information. Renseignements supplémentaires. Written submission from Frank R. Greening. Mémoire de Frank R. Greening CMD 18-H6.

Supplementary Information. Renseignements supplémentaires. Written submission from Frank R. Greening. Mémoire de Frank R. Greening CMD 18-H6. CMD 18-H6.155C File / dossier: 6.01.07 Date: 2018-06-05 Edocs: 5554444 Supplementary Information Written submission from Frank R. Greening Renseignements supplémentaires Mémoire de Frank R. Greening In

More information

Supplementary Information. Renseignements supplémentaires. Exposé oral. Oral Presentation. Presentation from Anna Tilman. Présentation de Anna Tilman

Supplementary Information. Renseignements supplémentaires. Exposé oral. Oral Presentation. Presentation from Anna Tilman. Présentation de Anna Tilman CMD 18-H6.24A File / dossier: 6.01.07 Date: 2018-06-11 Edocs: 5556828 Supplementary Information Oral Presentation Presentation from Anna Tilman Renseignements supplémentaires Exposé oral Présentation de

More information

Darlington Unit 2 CNSC Process for Return to Service

Darlington Unit 2 CNSC Process for Return to Service Darlington Unit 2 CNSC Process for Return to Service Public Meeting February 20, 2019 CNSC Staff Presentation e Doc 5723630 (PPTX) e Doc 5783914 (PDF) Introduction Darlington Nuclear Generating Station

More information

Introduction to the 2015 Darlington NGS Probabilistic Safety Assessment. Carlos Lorencez and Robin Manley Ontario Power Generation August 2015

Introduction to the 2015 Darlington NGS Probabilistic Safety Assessment. Carlos Lorencez and Robin Manley Ontario Power Generation August 2015 Introduction to the 2015 Darlington NGS Probabilistic Safety Assessment Carlos Lorencez and Robin Manley Ontario Power Generation August 2015 Introduction to the 2015 Darlington NGS Probabilistic Safety

More information

by NISHIKAWA Hiroyuki, KATSUYAMA Jinya and ONIZAWA Kunio

by NISHIKAWA Hiroyuki, KATSUYAMA Jinya and ONIZAWA Kunio [ 27 p. 245s-250s (2009)] by NISHIKAWA Hiroyuki, KATSUYAMA Jinya and ONIZAWA Kunio Numerical simulations by thermal-elastic-plastic-creep analysis using finite element method (FEM) have been performed

More information

Stress Corrosion Cracking in a Dissimilar Metal Butt Weld in a 2 inch Nozzle. Master of Engineering in Mechanical Engineering

Stress Corrosion Cracking in a Dissimilar Metal Butt Weld in a 2 inch Nozzle. Master of Engineering in Mechanical Engineering Stress Corrosion Cracking in a Dissimilar Metal Butt Weld in a 2 inch Nozzle by Thomas E. Demers An Engineering Project Submitted to the Graduate Faculty of Rensselaer Polytechnic Institute in Fulfillment

More information

Refurbishment of CANDU Reactors: A Canadian Perspective & Overview of Ontario s Current Program

Refurbishment of CANDU Reactors: A Canadian Perspective & Overview of Ontario s Current Program Refurbishment of CANDU Reactors: A Canadian Perspective & Overview of Ontario s Current Program Agenda What is a CANDU Reactor? Why is a mid-life refurbishment necessary? What steps are involved in CANDU

More information

SECTION 2.0 REFERENCES

SECTION 2.0 REFERENCES SECTION 2.0 REFERENCES 2.1 Standards... 1 2.2 Other References... 3 This page intentionally left blank. September 2010 API Recommended Practice 571 2-1 2.1 Standards The following standards, codes and

More information

Written submission from E.S. Fox Limited. Mémoire de E.S. Fox Limited CMD 18-H6.46. File / dossier: Date: Edocs:

Written submission from E.S. Fox Limited. Mémoire de E.S. Fox Limited CMD 18-H6.46. File / dossier: Date: Edocs: CMD 18-H6.46 File / dossier: 6.01.07 Date: 2018-05-07 Edocs: 5529012 Written submission from Mémoire de In the Matter of À l égard de Ontario Power Generation Inc., Pickering Nuclear Generating Station

More information

VIA . March 29, 2016

VIA  . March 29, 2016 March 29, 2016 VIA EMAIL Mr. Brian Torrie Director General Regulation Policy Directorate Canadian Nuclear Safety Commission 280 Slater Street Ottawa ON K1P 5S9 Dear Mr. Torrie: Re: Comments on the Canadian

More information

Oral Presentation. Exposé oral. Submission from the Toronto Region Board of Trade. Mémoire du Toronto Region Board of Trade CMD 18-H6.

Oral Presentation. Exposé oral. Submission from the Toronto Region Board of Trade. Mémoire du Toronto Region Board of Trade CMD 18-H6. CMD 18-H6.27 File / dossier: 6.01.07 Date: 2018-05-03 Edocs: 5528661 Oral Presentation Submission from the Toronto Region Board of Trade Exposé oral Mémoire du Toronto Region Board of Trade In the Matter

More information

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED

NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED NDT WITH THE STRUCTURAL WELD OVERLAY PROGRAM: RECENT FIELD EXPERIENCE AND LESSONS LEARNED Rick Rishel WesDyne International LLC I-70 Madison Exit Gate D P.O. Box 409 Madison, PA 15663 USA rishelrd@westinghouse.com

More information

Material Orientation Toughness Assessment (MOTA) for the Purpose of Mitigating Branch Technical Position (BTP) 5-3 Uncertainties

Material Orientation Toughness Assessment (MOTA) for the Purpose of Mitigating Branch Technical Position (BTP) 5-3 Uncertainties Westinghouse Non-Proprietary Class 3 2015 Westinghouse Electric Company LLC All Rights Reserved Global Expertise One Voice Material Orientation Toughness Assessment (MOTA) for the Purpose of Mitigating

More information

Benchmark Exercise on Risk-Informed In-Service Inspection Methodologies

Benchmark Exercise on Risk-Informed In-Service Inspection Methodologies 20th International Conference on Structural Mechanics in Reactor Technology (SMiRT 20) Espoo, Finland, August 9-14, 2009 SMiRT 20-Division 7, Paper 1841 Benchmark Exercise on Risk-Informed In-Service Inspection

More information

1340 Pickering Parkway, Fourth Floor, Pickering, Ontario L1V 0C4 Tel : Ext: 3400

1340 Pickering Parkway, Fourth Floor, Pickering, Ontario L1V 0C4 Tel : Ext: 3400 Laurie Swami Senior Vice President Decommissioning and Nuclear Waste Management 1340 Pickering Parkway, Fourth Floor, Pickering, Ontario L1V 0C4 Tel : 905-421-9494 Ext: 3400 laurie.swami@opg.com October

More information

2) List of Commitments

2) List of Commitments Nuclear Operating Company South TeAvs Project Ekctric Genem1n$ Statoio? PO Box289 Wadswodrth Texas 77483 A/\ -- November 15, 2006 File No.: G25 10CFR50.55a Attention: Document Control Desk One White Flint

More information

Regulatory Guide An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping

Regulatory Guide An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping Regulatory Guide 1.178An Approach For Plant-S... Page 1 of 32 July 1998 Regulatory Guide 1.178 An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping Publication Information

More information

IAEA International Conference on Topical Issues in Nuclear Installation Safety

IAEA International Conference on Topical Issues in Nuclear Installation Safety IAEA International Conference on Topical Issues in Nuclear Installation Safety Guidance on the Implementation of Modifications to Mitigate Beyond Design Basis Accidents Fred Dermarkar Vice President Engineering

More information

Can Today s Fracture Mechanics address Future Pipelines Integrity?

Can Today s Fracture Mechanics address Future Pipelines Integrity? Can Today s Fracture Mechanics address Future Pipelines Integrity? Subsea Systems Integrity Conference Ali Sisan 18/11/2014 1 DNV GL 2014 18/11/2014 SAFER, SMARTER, GREENER 2 Global reach local competence

More information

Internal Use Only NK38-PLAN R000 Title: NUCLEAR REFURBISHMENT PROGRAM HEALTH AND SAFETY MANAGEMENT PLAN

Internal Use Only NK38-PLAN R000 Title: NUCLEAR REFURBISHMENT PROGRAM HEALTH AND SAFETY MANAGEMENT PLAN Document Number: NK38-PLAN-09701-10067 Sheet Number: 0016 R000 N/A Revision: Ontario Power Generation Inc., 2013. This document has been produced and distributed for Ontario Power Generation Inc. purposes

More information

Bruce Power. June 13, 2017 NK21-CORR NK29-CORR NK37-CORR

Bruce Power. June 13, 2017 NK21-CORR NK29-CORR NK37-CORR June 13, 2017 NK21-CORR-00531-13629 NK29-CORR-00531-1 4271 NK37-CORR-00531-02792 CNSC CCSN 1111111111111111111111111 5275647 ~ Bruce Power Mr. B. Torrie Director General, Regulatory Policy Directorate

More information

DARLINGTON NUCLEAR GENERATING STATION APPLICATION FOR LICENCE RENEWAL

DARLINGTON NUCLEAR GENERATING STATION APPLICATION FOR LICENCE RENEWAL DARLINGTON NUCLEAR GENERATING STATION APPLICATION FOR LICENCE RENEWAL December 2013 Table of Contents Page 1.0 OVERVIEW... 6 1.1 Introduction... 6 1.2 Darlington Nuclear Generating Station (NGS)... 6 1.3

More information

CANDU Inspection Qualification Bureau (CIQB)

CANDU Inspection Qualification Bureau (CIQB) More info ab CANDU Inspection Qualification Bureau (CIQB) The application of the European Qualification Method to Inspection of CANDU Nuclear components Jeff Weed, Program Manager, CIQB, COG KiSang Jang,

More information

Structural Integrity and NDE Reliability I

Structural Integrity and NDE Reliability I Structural Integrity and NDE Reliability I Influence of Uncertainties in NDT on the Assessment of the Integrity of Components S. Dugan, X. Schuler, G. Wackenhut, S. Zickler Materials Testing Institute

More information

Advances In ILI Allow Assessing Unpiggable Pipelines. By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston

Advances In ILI Allow Assessing Unpiggable Pipelines. By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston As seen in Pipeline & Gas Journal, August 2011 edition Advances In ILI Allow Assessing Unpiggable Pipelines By Lisa Barkdull and Ian Smith, Quest Integrity Group, Houston Advances in in-line inspection

More information

SI N C E T H E 1990S, stress corrosion

SI N C E T H E 1990S, stress corrosion Deep-hole drilling to measure residual stress BY DICK KOVAN A British company uses a technique known as deep-hole drilling to measure residual stresses in thick-section nuclear components. SI N C E T H

More information

Pressurized Water Reactor Materials Reliability Program

Pressurized Water Reactor Materials Reliability Program Pressurized Water Reactor Materials Reliability Program Program Description Program Overview Stress corrosion cracking and general environmental corrosion of reactor coolant system components have cost

More information

IMPROVEMENT OF ASME NH

IMPROVEMENT OF ASME NH STP-NU-013 Designator: Meta Bold 24/26 Revision Note: Meta Black 14/16 IMPROVEMENT OF ASME NH FOR GRADE 91 NEGLIGIBLE CREEP AND CREEP-FATIGUE Date of Issuance: September 3, 2008 This report was prepared

More information

Structural Performance of next-generation nuclear components: lessons from the UK's R5 and R6 structural integrity assessment procedures

Structural Performance of next-generation nuclear components: lessons from the UK's R5 and R6 structural integrity assessment procedures Structural Performance of next-generation nuclear components: lessons from the UK's R5 and R6 structural integrity assessment procedures MATISSE Workshop on cross-cutting issues in structural materials

More information

DESIGN REGISTRATION GUIDELINES FOR NUCLEAR PRESSURE RETAINING SYSTEMS AND COMPONENTS

DESIGN REGISTRATION GUIDELINES FOR NUCLEAR PRESSURE RETAINING SYSTEMS AND COMPONENTS Boilers and Pressure Vessels Safety Division Technical Standards & Safety Authority 14th Floor, Centre Tower 3300 Bloor Street West Toronto, Ontario Canada M8X 2X4 www.tssa.org DESIGN REGISTRATION GUIDELINES

More information

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities DRAFT Regulatory Document RD-152 Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities Issued for Public Consultation May 2009 CNSC REGULATORY

More information

NDE Inspection Qualification: An Inspection Service Provider s Perspective. June 18-20, 2012

NDE Inspection Qualification: An Inspection Service Provider s Perspective. June 18-20, 2012 NDE Inspection Qualification: An Inspection Service Provider s Perspective June 18-20, 2012 NDE Inspection Qualification: An Inspection Service Provider s Perspective by S. Sullivan, A. Fenuta, P. Kwan

More information

Pickering Nuclear Generating Station Licence Renewal

Pickering Nuclear Generating Station Licence Renewal Pickering Nuclear Generating Station Licence Renewal Commission Hearing (Part 2), June 25-29, 2018 CNSC Staff Presentation e-doc 5510377 (PPTX) e-doc 5558535 (PDF) PURPOSE OF PRESENTATION e-doc 5510377

More information

CANADIAN APPROACH ON REGULATORY ISSUES REGARDING AGEING MANAGEMENT, LONG TERM OPERATION AND PLANT LIFE MANAGEMENT

CANADIAN APPROACH ON REGULATORY ISSUES REGARDING AGEING MANAGEMENT, LONG TERM OPERATION AND PLANT LIFE MANAGEMENT CANADIAN APPROACH ON REGULATORY ISSUES REGARDING AGEING MANAGEMENT, LONG TERM OPERATION AND PLANT LIFE MANAGEMENT T. Viglasky, A. Blahoianu, K. Kirkhope Canadian Nuclear Safety Commission, Canada Email

More information

APPENDIX B STORAGE AT REACTOR SITES

APPENDIX B STORAGE AT REACTOR SITES APPENDIX B STORAGE AT REACTOR SITES Prepared By: M.W. Davis and N.C. Garisto SENES Consultants Limited 33826 November 2004 SENES Consultants Limited TABLE OF CONTENTS Page No. B1 B2 B3 B4 B5 B6 INTRODUCTION...B-1

More information

Activities of OECD/NEA in the Regulatory Aspects of Plant Life Management

Activities of OECD/NEA in the Regulatory Aspects of Plant Life Management Activities of OECD/NEA in the Regulatory Aspects of Plant Life Management Andrei Blahoianu NEA / CSNI / IAGE Chairman Andrei.Blahoianu@cnsc-ccsn.gc.ca ccsn.gc.ca Alejandro Huerta OECD/NEA Nuclear Safety

More information

Predicting the Crack Response for a Pipe with a Complex Crack

Predicting the Crack Response for a Pipe with a Complex Crack University of South Carolina Scholar Commons Theses and Dissertations 1-1-2013 Predicting the Crack Response for a Pipe with a Complex Crack Robert George Lukess University of South Carolina Follow this

More information

STRENGTH ANALYSES OF NUCLEAR POWER PLANT PRESSURE EQUIPMENT

STRENGTH ANALYSES OF NUCLEAR POWER PLANT PRESSURE EQUIPMENT GUIDE YVL E.4 / 15 November 2013 STRENGTH ANALYSES OF NUCLEAR POWER PLANT PRESSURE EQUIPMENT 1 Introduction 5 2 Scope of application 6 3 Strength analysis report 7 3.1 Contents and objective 7 3.2 Time

More information

Preliminary application of the draft code case for alloy 617 for a high temperature component

Preliminary application of the draft code case for alloy 617 for a high temperature component Journal of Mechanical Science and Technology Journal of Mechanical Science and Technology 22 (2008) 856~863 www.springerlink.com/content/1738-494x Preliminary application of the draft code case for alloy

More information

Claude FAIDY, EDF (France) Overview of EDF ageing management program of safety class components

Claude FAIDY, EDF (France) Overview of EDF ageing management program of safety class components program of safety class components Claude Faidy, Electricité de France - SEPTEN 12-14 Avenue Dutrievoz - 69628 Villeurbanne Cedex - France Tel: +33 4 7282 7279, Fax: +33 4 7282 7697 E-mail: claude.faidy@edf.fr

More information

A Basis for Improvements to ASME Code Section XI Appendix L

A Basis for Improvements to ASME Code Section XI Appendix L NUREG/CR-6934 PNNL-16192 Fatigue Crack Flaw Tolerance in Nuclear Power Plant Piping A Basis for Improvements to ASME Code Section XI Appendix L Pacific Northwest National Laboratory U.S. Nuclear Regulatory

More information

Experience in Qualifying an Ultrasonic Procedure as an alternate to Radiography

Experience in Qualifying an Ultrasonic Procedure as an alternate to Radiography Experience in Qualifying an Ultrasonic Procedure as an alternate to Radiography Laura White, OPG, NWMD John Baron, CIQB, COG Trek Hazelton, OPG, IM&CS Phil Ashwin, EPRI NDE Center 3 rd International CANDU

More information

ULTRASONIC MEASUREMENT OF RESIDUAL STRESSES IN WELDED SPECIMENS AND STRUCTURES

ULTRASONIC MEASUREMENT OF RESIDUAL STRESSES IN WELDED SPECIMENS AND STRUCTURES Proceedings of the ASME 2013 Pressure Vessels and Piping Conference PVP2013 July 14-18, 2013, Paris, France PVP2013-97184 ULTRASONIC MEASUREMENT OF RESIDUAL STRESSES IN WELDED SPECIMENS AND STRUCTURES

More information

N-CORR P CD#: N-CORR Dear Mr. Dallaire,

N-CORR P CD#: N-CORR Dear Mr. Dallaire, From: FLEET Barry -NUCLEAR [mailto:barry.fleet@opg.com] Sent: Friday, November 16, 2012 9:20 AM To: Consultation; Dallaire, Mark Cc: WILLIAMS Don -DNNP; MACEACHERON R J -NUCLEAR; HARRIS Elaine -NUCLEAR;

More information

Randy Lockwood, Senior Vice President CMD 18-H6.1A. PICKERING NUCLEAR GENERATING STATION Part I Hearing Licence Renewal April 4, 2018

Randy Lockwood, Senior Vice President CMD 18-H6.1A. PICKERING NUCLEAR GENERATING STATION Part I Hearing Licence Renewal April 4, 2018 Randy Lockwood, Senior Vice President CMD 18-H6.1A PICKERING NUCLEAR GENERATING STATION Part I Hearing Licence Renewal April 4, 2018 Presentation Outline Opening Remarks Performance Highlights Our Request

More information

Update on CANDU Safety Issues, COG Large LOCA and Severe Accident Projects

Update on CANDU Safety Issues, COG Large LOCA and Severe Accident Projects Excellence through Collaboration Update on CANDU Safety Issues, COG Large LOCA and Severe Accident Projects Krish Krishnan and Jeff Weed IAEA Workshop on Good Practices in HWR Operation Buenos Aires, Argentina,

More information

PWROG Reactor Internals Projects

PWROG Reactor Internals Projects PWROG Reactor Internals Projects Industry/NRC Exchange Meeting June 2015 Glenn Gardner, Mike Burke, Heather Malikowski Topics Integrated Industry Approach, Processes and Tools Materials Applications Fleet-wide

More information

Materials Assessment Services

Materials Assessment Services Materials Assessment Services ANSTO is a specialist materials assessment provider offering an integrated service concentrated on maximizing the performance of capital assets and infrastructure. With over

More information

CNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria

CNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria CNSC Fukushima Task Force E-doc 3743877 July 2011 Executive Summary In response to the March 11, 2011 accident at the Fukushima Daiichi Nuclear Power Plant (NPP), the CNSC convened a Task Force to evaluate

More information

IAEA-J4-TM TM for Evaluation of Design Safety

IAEA-J4-TM TM for Evaluation of Design Safety Canadian Nuclear Utility Principles for Beyond Design Basis Accidents IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects Ontario Power Generation Overview

More information

THE EFFECTS OF FLAW SIZE AND IN-SERVICE INSPECTION ON CASS PIPING RELIABILITY

THE EFFECTS OF FLAW SIZE AND IN-SERVICE INSPECTION ON CASS PIPING RELIABILITY THE EFFECTS OF FLAW SIZE AND IN-SERVICE INSPECTION ON CASS PIPING RELIABILITY T. J. Griesbach, D. O. Harris, H. Qian, D. Dedhia, J. Hayden, Structural Integrity Associates, Inc. A. Chockie, Chockie Group

More information

Boiling Water Reactor Vessel and Internals

Boiling Water Reactor Vessel and Internals Boiling Water Reactor Vessel and Internals Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared, first in

More information

Safety Standards. of the Nuclear Safety Standards Commission (KTA)

Safety Standards. of the Nuclear Safety Standards Commission (KTA) Safety Standards of the Nuclear Safety Standards Commission (KTA) KTA 36 (14-11) Break Preclusion Verifications for Pressure-Retaining Components in Nuclear Power Plants (Nachweise zum Bruchausschluss

More information

Failure Assessment Diagram Constraint Used for Integrity Analysis of Cylindrical Shell with Crack

Failure Assessment Diagram Constraint Used for Integrity Analysis of Cylindrical Shell with Crack Failure Assessment Diagram Constraint Used for Integrity Analysis of Cylindrical Shell with Crack Musthafa Akbar, a,* and Rachman Setiawan, b a) Mechanical Engineering, Universitas Riau, Indonesia b) Mechanical

More information

High Temperature Effects on Vessel Integrity. Marc Levin, Ayman Cheta Mary Kay O Connor Process Safety Center 2009 International Symposium

High Temperature Effects on Vessel Integrity. Marc Levin, Ayman Cheta Mary Kay O Connor Process Safety Center 2009 International Symposium High Temperature Effects on Vessel Integrity Marc Levin, Ayman Cheta Mary Kay O Connor Process Safety Center 2009 International Symposium Outline Motivation Basics / Basis for Pressure Vessel Design Conditions

More information

Severe Accident Progression Without Operator Action

Severe Accident Progression Without Operator Action DAA Technical Assessment Review of the Moderator Subcooling Requirements Model Severe Accident Progression Without Operator Action Facility: Darlington Classification: October 2015 Executive summary After

More information

Subject Index. Bending equation for surface cracks, 597 surface crack growth, Birefringent coatings, dynamic fracture behavior

Subject Index. Bending equation for surface cracks, 597 surface crack growth, Birefringent coatings, dynamic fracture behavior STP969-EB/Jul. 1988 Subject Index A ADINA computer program, 74, 77 Aircraft landing wheels, fatigue crack growth, 872-874 analysis verification, 875-876 depth direction of, 881 fatigue life prediction,

More information

INVESTIGATIVE STUDY OF 2-D VS. 3-D WELD RESIDUAL STRESS ANALYSES OF THE NRC PHASE II MOCKUP

INVESTIGATIVE STUDY OF 2-D VS. 3-D WELD RESIDUAL STRESS ANALYSES OF THE NRC PHASE II MOCKUP Proceedings of the ASME 212 Pressure Vessels & Piping Conference PVP212 July 15-19, 212, Toronto, Ontario, CANADA PVP212-7876 INVESTIGATIVE STUDY OF 2-D VS. 3-D WELD RESIDUAL STRESS ANALYSES OF THE NRC

More information

Thomas D. Gatlin. February 24, 2014 RC Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC

Thomas D. Gatlin. February 24, 2014 RC Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC Thomas D. Gatlin Vice President, Nuclear Operations 803.345.4342 A SCANA COMPANY February 24, 2014 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Dear Sir / Madam: Subject:

More information

IAEA-TECDOC-1361 Assessment and management of ageing of major nuclear power plant components important to safety

IAEA-TECDOC-1361 Assessment and management of ageing of major nuclear power plant components important to safety IAEA-TECDOC-1361 Assessment and management of ageing of major nuclear power plant components important to safety Primary piping in PWRs July 2003 The originating Section of this publication in the IAEA

More information

413 March Road Ottawa, Ontario Canada K2K 0E4 Tel: June 8, 2012

413 March Road Ottawa, Ontario Canada K2K 0E4 Tel: June 8, 2012 413 March Road Ottawa, Ontario Canada K2K 0E4 Tel: 613-591-2100 June 8, 2012 Canadian Nuclear Safety Commission P.O. Box 1046, Station B 280 Slater Street Ottawa, Ontario, Canada K1P 5S9 Subject: Comments

More information

C. PROCEDURE APPLICATION (FITNET)

C. PROCEDURE APPLICATION (FITNET) C. PROCEDURE APPLICATION () 63 INTRODUCTION INPUTS ANALYSIS FAD AND CDF ROUTES GUIDANCE ON OPTION SELECTION SPECIAL OPTIONS 64 INTRODUCTION INTRODUCTION: The Fracture Module is based on fracture mechanics

More information

COMPARISON BETWEEN DUCTILE TEARING ANALYSIS AND LINEAR ELASTIC FRACTURE MECHANICS ANALYSIS

COMPARISON BETWEEN DUCTILE TEARING ANALYSIS AND LINEAR ELASTIC FRACTURE MECHANICS ANALYSIS COMPARISON BETWEEN DUCTILE TEARING ANALYSIS AND LINEAR ELASTIC FRACTURE MECHANICS ANALYSIS Mr. Quinton Rowson Consultant Structural Integrity, Quest Integrity NZL Ltd., New Zealand Mr. Michael Rock Engineering

More information

XRD RESIDUAL STRESS MEASUREMENTS ON ALLOY 600 PRESSURIZER HEATER SLEEVE MOCKUPS

XRD RESIDUAL STRESS MEASUREMENTS ON ALLOY 600 PRESSURIZER HEATER SLEEVE MOCKUPS XRD RESIDUAL STRESS MEASUREMENTS ON ALLOY 6 PRESSURIZER HEATER SLEEVE MOCKUPS J. F. Hall, J. P. Molkenthin - ABB-Combustion Engineering Nuclear Power Paul S. Prevéy Lambda Research ABSTRACT Alloy 6 penetrations

More information

ASME BPVC.CC.BPV.S Approval Date: October 7, 2015

ASME BPVC.CC.BPV.S Approval Date: October 7, 2015 CASE Approval Date: October 7, 2015 Code Cases will remain available for use until annulled by the applicable Standards Committee. Case Manufacture of a Hoop-Wrapped, Wire-Reinforced Cylindrical Pressure

More information

Prediction of Residual Stresses after Local Post-Weld Heat Treatment

Prediction of Residual Stresses after Local Post-Weld Heat Treatment GROUP SPONSORED PROJECT OUTLINE PR 21964 July 2013 Summary Residual stresses caused by fabrication or repair welding can affect the resistance to fracture or corrosion damage of a thick component. Post-weld

More information

NUGENIA position on fracture mechanics assessment. Fracture Mechanics Assessment The European view of the State of the Art

NUGENIA position on fracture mechanics assessment. Fracture Mechanics Assessment The European view of the State of the Art NUGENIA position on fracture mechanics assessment Fracture Mechanics Assessment The European view of the State of the Art Compiled by John Sharples (Amec Foster Wheeler), Elisabeth Keim (AREVA GmbH) and

More information

Boiling Water Reactor Vessel and Internals Project (QA)

Boiling Water Reactor Vessel and Internals Project (QA) Boiling Water Reactor Vessel and Internals Project (QA) Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared,

More information

A discussion about P-T limit curves and PTS evaluation

A discussion about P-T limit curves and PTS evaluation Transactions of the 13th International Conference on Structural Mechanics in Reactor Technology (SMiRT 13), Escola de Engenharia - Universidade Federal do Rio Grande do Sul, Porto Alegre, Brazil, August

More information

Reporting Requirements for Operating Nuclear Power Plants: Compliance Monitoring RD-99.2

Reporting Requirements for Operating Nuclear Power Plants: Compliance Monitoring RD-99.2 Reporting Requirements for Operating Nuclear Power Plants: Compliance Monitoring RD-99.2 November 2010 Reporting Requirements for Operating Nuclear Power Plants: Compliance Monitoring Draft Regulatory

More information

Austenitic and Bimetallic Weld Inspection II

Austenitic and Bimetallic Weld Inspection II Austenitic and Bimetallic Weld Inspection II MRP-139 Recommendations: Inspection of Dissimilar Metal Welds in Reactor Pressure Vessels in Spain J.R. Gadea, A. Willke, J.J. Regidor, Tecnatom, Spain ABSTRACT

More information

Steam Turbine Critical Crack Evaluation and Ranking Cracks to Prioritize Inspection

Steam Turbine Critical Crack Evaluation and Ranking Cracks to Prioritize Inspection Steam Turbine Critical Crack Evaluation and Ranking Cracks to Prioritize Inspection G. Thorwald, V. Garcia, R. Bentley, and O. Kwon Quest Integrity Abstract: The objective of this paper is to evaluate

More information

Structural Integrity and NDE Reliability I

Structural Integrity and NDE Reliability I Structural Integrity and NDE Reliability I Assessment of Failure Occurrence Probability as an Input for RI-ISI at Paks NPP R. Fótos, University of Miskolc, Hungary L. Tóth, P. Trampus, University of Debrecen,

More information

Probabilistic Safety Assessment Safety & Regulatory Framework

Probabilistic Safety Assessment Safety & Regulatory Framework Probabilistic Safety Assessment Safety & Regulatory Framework Presentation to the CNSC August 2017 Dr. V.G. Snell 1 Purpose To summarize work done under CNSC contract 87055-16-0251: Role of the Probabilistic

More information

Welding simulations: assessment of welding residual stresses and post weld heat treatment

Welding simulations: assessment of welding residual stresses and post weld heat treatment Welding simulations: assessment of welding residual stresses and post weld heat treatment Etienne Bonnaud and Jens Gunnars, Inspecta Technology AB Third Nordic Conference on Design and Fabrication of Welded

More information

Gear Tooth Bending Fatigue Life Prediction Using Integrated Computational Material Engineering (ICME)

Gear Tooth Bending Fatigue Life Prediction Using Integrated Computational Material Engineering (ICME) Gear Tooth Bending Fatigue Life Prediction Using Integrated Computational Material Engineering (ICME) Eaton: Carlos Wink, Nikhil Deo VEXTEC: Sanjeev Kulkarni, Michael Oja, Robert McDaniels, Robert Tryon,

More information

Coordinated Research Project(CRP) - Qualification, Condition Monitoring, and Aging Management of Low Voltage Cables in NPPs

Coordinated Research Project(CRP) - Qualification, Condition Monitoring, and Aging Management of Low Voltage Cables in NPPs Coordinated Research Project(CRP) - Qualification, Condition Monitoring, and Aging Management of Low Voltage Cables in NPPs 1 August 2011 Ki Sig Kang International Atomic Energy Agency What is Coordinated

More information

Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS

Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS Appendix J STEAM GENERATOR TUBE INTEGRITY FINDINGS SIGNIFICANCE DETERMINATION PROCESS 1.0 INTRODUCTION The significance determination process (SDP) provides a method to place inspection findings in context

More information

PRESSURE-TEMPERATURE LIMIT CURVES

PRESSURE-TEMPERATURE LIMIT CURVES Training School, 3-7 September 2018 Polytechnic University of Valencia (Spain) PRESSURE-TEMPERATURE LIMIT CURVES Carlos Cueto-Felgueroso This project received funding under the Euratom research and training

More information

Industry Comments on draft REGDOC-2.7.2, Dosimetry, Volume II: Technical and Management System Requirements for Dosimetry Services

Industry Comments on draft REGDOC-2.7.2, Dosimetry, Volume II: Technical and Management System Requirements for Dosimetry Services Industry s on draft REGDOC-2.7.2, Dosimetry, Volume II: Document/ Excerpt of Section 1. 2.5.1 Although Section 2.5.1 states that routine performance tests should be conducted monthly for bi-weekly issue

More information