Attachment A Repair Knee Brace on High Arch Salt Building Fayette County, Mill Run Stockpile #24 Project # Building #PA

Similar documents
Attachment A Concrete Curb and Sidewalk Replacement Cambria County, Johnstown Driver s Exam Center Project# Building# 093DL01

Attachment A Project Specification Repair of a Salt Dome Building Philadelphia County, Betsy Ross Stockpile # Dome# Project #

Attachment A Exterior Building Improvements Susquehanna County, Roadside Rest Site #56, I-81 SB Project # Building # 045R561

ATTACHMENT A Sanitary Sewage Line Replacement Columbia County, Roadside Rest Site# 38, I-80 WB Project# Roadside Rest Grounds# 031R380

Attachment A Perry County Maintenance Facility 8-9 Floor Repair New Bloomfield

POST FRAME BUILDING STANDARDS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

REQUEST FOR PROPOSAL Asphalt & Concrete Repair

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

ENGINEERING BUILDING ROOF REPLACEMENT

ITEM 555 CHAIN LINK FENCING

RESIDENTIAL RE-ROOFING PERMIT APPLICATION

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

Specification Lightning Protection Systems

University of Delaware

SECTION UNDERGROUND STORAGE TANK REMOVAL

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION BORING AND/OR JACKING PIPE

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

City of Augusta SIDEWALK REPLACEMENT PROGRAM

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

DBI-SALA Uni 8 Horizontal Lifeline Cable System

CITY OF CHINO HILLS. Request for Proposals (RFP) for On-Call and Emergency Repair Services Including Water and Sewer Systems

PIPE CULVERTS. Construct pipe culverts, beveled ends, pipe aprons, and associated appurtenances.

02800 SHADE STRUCTURES

Job Order Sewer Repair Services

SECTION LIGHTNING PROTECTION SYSTEM

BULWARK BOLLARDS M30 & M50

ADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

SECTION STORM DRAINAGE

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION IRRIGATION WATER WELL

Minimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

TABLE OF CONTENTS Structural Library

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

SECTION TIMBER FLOATS

Section [ ] Storm Water Treatment Device

Project Address: Name of Person Completing Form:

Phenolic Exterior Wall Cladding

AMERICAN SAMOA POWER AUTHORITY Materials Management Office INVITATION FOR BIDS ( IFB ) EAST SIDE WELLS-BOOSTERS SECURITY FENCE REPLACEMENT

WEST BOUNTIFUL CITY, UTAH REQUEST FOR PROPOSAL. City Park Playground Equipment.

SECTION ORNAMENTAL ALUMINUM RAILING

Whapmagoostui & Waskaganish Addendum no AR01 August 15, 2017 Cree Daycare Centres Cree Nation Government RRA 1728 Page 1 of 6

SECTION STRUCTURE MOUNT RAILING SYSTEM

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

2012 International Building Code 2011 National Electrical Code Local amendments to the codes are in Chapter 6 of the Code of City Ordinances

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014

SPECIAL INSPECTION AGREEMENT

TOWN OF HOLLIS, NEW HAMPSHIRE

SECTION PORTLAND CEMENT CONCRETE

Section CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.

Re: Concrete Installation/Demolition and Bollards Request for Proposal # R-RFP. Addendum 1 Clarifications to Request for Proposal

San Antonio Water System Standard Specifications for Construction ITEM NO. 808 REINFORCED CONCRETE VAULTS

Commercial Submittal Packet

A. Drawings and general provisions of the Contract, including General Conditions Specification Sections, apply to this section.

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 REVISION 7 ITEM 516 INSTALLATION OF FLEX BEAM GUARDRAIL

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION

Finance & Technology Administrator (815) ext 223

SECTION PRECAST CONCRETE COVER SYSTEM

SECTION CANOPIES. Display hidden notes to specifier. (Don't know how? Click Here) Copyright ARCAT, Inc. - All rights reserved

SECTION DECORATIVE METAL FENCES AND GATES

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION IRRIGATION WATER WELL

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

QUOTE Quote Process City Of Taylor

Wall bracing panel requirements

SPECIAL INSPECTION AND TESTING AGREEMENT

INSTRUCTIONS AND GUIDELINES

Rapid Axial Load Testing of Drilled Shafts

LITHOCRETE ARCHITECTURAL CONCRETE PAVING

BID INSTRUCTIONS. Montour County Courthouse Retaining Wall Repair Project

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood.

Multi-Institutional Academic Health Science & Research Center Evansville, IN

SPECIFICATIONS FOR ON-SITE REBUILD OF TRAVELING WATER SCREENS

Automated Cantilevered Aluminum Sliding Gate

SPECIAL SPECIFICATION 5989 Settlement Gauge

SECTION 716 SIGN MATERIALS SCOPE

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

LAGRANGE TOWNSHIP 353 South center street p.o. box 565 lagrange ohio 44050

SECTION ROCK REMOVAL

UNISTRUT CORPORATION GENERAL NOTES 1. THIS UNISTRUT SUPPORT SYSTEM IS DESIGNED TO SUPPORT A MAXIMUM UNIFORM LOAD OF PSF.

ATTACHMENT A. Bid # 6793

Transcription:

I. Base Bidding Requirements This is a Base Bid project; the following describes the Base Bid requirements. Contractors are to provide bids for Base Bid #1. A. BASE BID #1: II. Work Included The following items are site specific requirements of the project. A. Contractor to repair, replace and install the necessary materials to complete the work identified below per each building identified in the Base Bid requirements. B. Contractor to engage the services of a structural engineer for design and installation guidance. C. Select demolition of existing bracing material, excavation for foundation work, and existing concrete foundation. D. Replacement of the building foundation to include epoxy coated reinforcing bar. E. Installation of new Knee Brace. F. Backfill and Paving to existing grades. III. GENERAL A. The Contractor shall provide all labor, materials, apparatus, trucking, tools, superintendence, and services required for completion of the work as described on the Statement of Work, Specifications, and Drawings. B. The Contractor is responsible for obtaining all necessary Permits from the Department of Labor and Industry (L&I) (http://www.dli.state.pa.us/), there are no fees for the Permits as long as the contractor notifies the L&I that this project is for the Commonwealth of Pennsylvania, PennDOT and is to be completed on state owned or state leased property. 1. Contractor shall provide all design, calculations, and final plans sealed by a Professional Engineer licensed in the state of Pennsylvania, as required. 2. This building does not have an occupancy permit. The Contractor will be responsible to obtain the occupancy permit for this building as part of the project. Page 1 of 7

C. Contractor shall maintain and log, all mail receipts regarding L&I correspondence and submittals, and provide copies to PennDOT upon request. D. Contractor to confirm all dimensions and quantities before bidding. Any stated dimensions/quantities are estimates only. IV SELECT DEMOLITION A. Remove damaged treated wood framing materials. B. Saw cut existing asphalt paving. C. Excavate to expose the foundation. D. Demolish the foundation concrete to expose the embedded wood framing members. 1) Contractor to legally dispose of all construction debris. V. MATERIALS A. New treated wood framing member(s) to be pressure treated for direct ground contact. B. Wood framing member(s) shall be solid sawn timbers or glue laminated timbers specified for outdoor exposure. C. Concrete to be 5000 PSI. D. Reinforcing bar to be grade 60, epoxy coated deformed round bars. E. Fasteners to be hot dipped galvanized. F. Asphalt paving to be hot mixed 19mm. G. Pipe Bollards shall be eight inch (8 ) schedule 40 galvanized steel pipe, eight feet (8 ) total length. VI. INSTALLATION A. Install new wood framing member(s) to the lines and angles as the existing framing member(s). B. Cross drill the embedded end of the timber to accept a # 6 X 16 (minimum) epoxy coated rebar. C. Install epoxy coated reinforcing bars as directed by engineer of record. D. Place new concrete so as to embed the new timber framing member(s) to a depth of the existing timber. E. Backfill excavation with 2A stone in compacted lifts in no more than eight inch (8 ) depths. F. Pave the area with 19mm hot asphalt paving to meet existing lines and grades. G. Seal all asphalt joints with liquid asphalt sealer. H. Install four (4) pipe bollards in front of the building. Page 2 of 7

I. Install a pipe bollard at the outer most corners of the building and at both door edges of the main door opening. J. Set pipe bollards one foot six inches (1-6 ) out from the face of the building, inline from side to side. K. Pipe bollards to be installed with three feet (3 ) embedded in concrete, in the ground and five feet (5 ) exposed. (see attached drawing) L. Pipe bollards shall be filled with concrete. M. Pipe bollards shall receive a Safety Yellow PVC sleeve with Red & White reflective tape. VII. SUBMITTALS AND FINAL DELIVERABLE ITEMS A. Submittals and final Deliverable items 1. The Department will provide the awarded contractor a complete breakdown of the required submittals based off of the System identified, I.E. Roofing System 2. Contractor to provide three (3) copies of the entire project documentation in three (3) ring Binders. 3. Binders to include the following items: a. Bid Documents & Specifications b. All project meeting minutes (pre-bid, pre-job, Interim, and Final inspection) c. Email Correspondence d. Submittals e. L&I approved Engineered Drawings (Paper/CD) f. L&I Building Permits, Inspection Logs, Occupancy Permit, Other correspondence g. Certifications h. Certified Payrolls (Prevailing Wage rates) if applicable i. Waste receipts j. Photos Before, during and after 1) A sufficient amount of Photos is required for all phases of construction on all buildings, base on award. 2) Building Final-Exterior all four sides k. Operation and Maintenance manuals l. Contractors Warranty m. Manufactures Warranty VIII. SUBMITTAL PROCEDURE Page 3 of 7

A. Submit Two (2) copies of all items shown on submittal schedule except for "samples". B. Identify project number, project name and location, and contractor's name and address on all submittals. C. Provide space for review stamps of Contractor and Department. Put contractor stamp of approval on each item submitted. D. Revise and resubmit submittals as required, identify all changes made since previous submittal. E. No work shall be performed until all submittals are approved by the Department. Work performed prior to submittal approval is performed at the Contractor's risk and may be subject to repair, replacement or other corrective measures as deemed necessary by the Department with no additional contract time or money. F. Review of shop drawings will be general and for the limited purpose of checking for general conformance with the design; and shall not relieve the Contractor from the responsibility for proper fitting and construction of the work, nor from furnishing materials and work required by the Contract which may not be indicated on the shop drawings when reviewed. G. The submittals required by this contract are subject to reproduction for the Department's internal use only. By signature on this bid proposal, both the Contractor and the equipment manufacturer authorize the Department to reproduce any materials including printed literature and training aids, submitted in fulfillment of this contract. IX. MANUFACTURER'S INSTRUCTIONS A. When specified in individual specification sections, submit manufacturer's printed instructions for delivery, storage, assembly, installation, start-up, adjusting and finishing, and maintenance, in quantities specified for product data. B. Identify conflicts between manufacturer's instructions and contract documents. X. MANUFACTURER'S CERTIFICATES A. When specified in individual specification sections or on submittal schedule, submit manufacturer's certificates to for review. Page 4 of 7

B. Indicate that material or product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits and certifications as appropriate. C. Certificates may be recent or previous test results on material or product, but in all cases must be acceptable to Department. XI. SUBMITTAL SCHEDULE A. Abbreviations: SoSu - Source of Supply DeDa - Descriptive Data or Catalog Cuts ShDr - Shop or Installation Drawings CoCh - Color Chart Cert - Certificates Samp Samples B. Schedule: Description of items to be submitted SoSu DeDa ShDr CoCh Samp Cert 1. Cost Breakdown X X 2. Work Schedule X X 3. Engineered Stamped Drawings X X X X 4. L&I Permit Documents X X X 5. Waste receipts X 6. Digital Photos X 7. Final Deliverable Items 3 ring binder X 8. Wood framing timbers X X 9. Concrete X X 10. Epoxy coated Reinforcing bar X X X Page 5 of 7

Drawing for information only. Page 6 of 7

Drawings are for information only. Page 7 of 7