Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Similar documents
Week 5 Project Work Plan

6 PROJECT TIME MANAGEMENT

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Week 5 Project Work Plan

Week 5 Project Work Plan

Project Time Management

Planning & Scheduling

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

PMP Exam Preparation Course Project Time Management

Scheduling. Adapted from John Musser

Week 5 Project Work Plan

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

EXHIBIT 2-2-C SCHEDULES

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

Project Scope Management

East Central College

Project Forecast Survey Results Good Scheduling Practices June 2016

Views and Layouts for Program Management

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

Construction Planning and Scheduling

Time Management PLANNING

Estimating Project Schedule-Time and Cost

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include

Project Time Management

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Information Technology Project Management, Seventh Edition

Estimating and Scheduling

ENGINEERING MANAGEMENT (GE

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Meeting the Challenge of EPC Project Proposal Schedules. Project Proposal Schedules

Team Member Application

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

THE PMP EXAM PREP COURSE

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Exposition Metro Line Construction Authority CRITICAL PATH METHOD SCHEDULE AND COST/SCHEDULE INTEGRATION SYSTEM

Introduction to Project Management

Global Project Management, LLC

THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR CLARIFICATIONS:

Modern Systems Analysis and Design Seventh Edition

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE. CFS:BD 1 of 14 APPR:MB:JJG FHWA:APPR:

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

Planning & scheduling

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005

Information Systems. Rationale Aims & Objectives. Rationale Aims & Objectives. Introduction to Project management. Ruel Ellis

BASELINE SCHEDULING BASICS Part 2: May 3, 2007

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Dr. Richard Jerz rjerz.com

Project Time Management

Managing Projects with MS Project 2010

Geog 469 GIS Workshop. Project Management

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

Time has the least. amount of flexibility; Schedule issues are the main reason for

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

Project Management Framework

Guten Tag. (good day)

PROJECT PLANNING AND SCHEDULING

Chapter 3 Managing Systems Projects

Project Management Concepts, Tools & Techniques

Demystifying Microsoft Project

MAINTAINING & UTILIZING AN INTEGRATED MASTER SCHEDULE FOR A FEDERAL CONTRACT

CHAPTER 1. Basic Concepts on Planning and Scheduling

EVALUATION COPY. Unauthorized Reproduction or Distribution Prohibited THE OCCASIONAL PROJECT MANAGER

Value of Failure! Students Course! Module 4: Preventing Failure!

Developing a Project Plan

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Planning & Scheduling CSTM 102

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Project Time Management. Course Objectives. Outline

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

EGR 386W. Proposals & Project Management. Work Breakdown Structure (WBS) & Gantt Charts

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS]

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

The Project Planning Process Group

Principles of Planning for IT Projects

Scheduling Resources and Costs

CE2353-CONSTRUCTION PLANNING & SCHEDULING

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION CONSTRUCTION PROGRESS DOCUMENTATION

Information Technology Audit & Cyber Security

Transcription:

Project Planning & CPM Scheduling using MS Project APWA NorCal 2018 Annual Conference

What is Planning? Planning: A determination of the what, how, where and by whom ; the tasks that need to be completed to finish any project washing the car grocery shopping laying drainage pipe building a skyscraper

What is a schedule? Schedule: The when of planning. The planning information is necessary to organize, orchestrate and develop a schedule.

Gantt Chart or Bar Chart A simple presentation that show how major work activities are scheduled Primary Advantages Grind Exist. Striping and Conforms Roadway Overlay simple graphic representation to allow quick and easy Activity Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 insight to schedule information no extensive training is required to learn how to extract information from them Sweep and Roadway Prep AC Overlay Paving Shows operations and the time utilized by each operation. Can show the scheduled vs. actual progress Roller Compaction AC Set/Cure Place Striping

Work Breakdown Structure (WBS) Work Breakdown Structure (WBS) a systematic way of describing the component pieces of a project schedule. That is, the work is broken down to systems (i.e. Plumbing, Mechanical, Sitework, etc.) and the systems are further broken down into greater detail.

WBS (cont. d) Created from the top down approach, NOT the bottom up Breakdown of the project, i.e. Project task to subtask to sub-subtask, etc. Level of detail will be determined by the complexity and schedule needs WBS breaks project down to manageable pieces rather than one grandiose whole Requires input from various parties: PM, Supt., Subs, Suppliers, etc.

WBS (cont. d) NO SINGLE CORRECT WBS its development is directly dependent on who is developing the WBS. Logic may be similar but inherently there will be nuances. WBS is NOT a schedule, rather a breakdown of the various activities Similar to an outline for a paper or book

AC Overlay WBS AC Overlay WBS.xlsx

Schedule Definitions Resources Labor, materials, equipment and time Activity Duration time required to perform a specified quantity of work/productivity rate Critical Path A continuous chain of activities with the longest duration; it dictates the project completion

Definitions (cont. d) Early Start The earliest time that an activity can start Early Finish The earliest time that an activity can finish Late Start The latest time that an activity can start and not prolong the project Late Finish The latest time that an activity can finish and not prolong the project

Definitions (cont. d) Float The amount of free time or time difference between the calculated duration of the activity chain and the critical path is call float. It allows an activity to start later that its early start and not delay the project. Can be classified as free or total float Total Float The measure of time in starting and completing an activity; usually measured in days Free Float Also referred to as activity float because, unlike total float, free float is the property of the activity and not the network path. Free float is the amount of time the start of an activity may be delayed without delaying the start of successor activity. Lag The amount of time that exists between the early finish of an activity and the early start of a specified succeeding activity

Definitions (cont. d) Activities have 5 specific characteristics: Consumes time Consumes resources It has definable start and finish It is assignable It is measurable Construction projects are made up of numerous individual activities that must be accomplished to finish the project.

Definitions (cont. d) Concurrent Activities Activities that are logically independent of one another and can be performed at the same time Predecessor Activities An activity that must be completed prior to the next activity starting. Successor Activities An activity that cannot start until the preceding activity is completed.

Definitions (cont. d) Milestones - The Schedule has a single activity defining the start and a single activity defining the finish of the schedule Note: Activities consume time, Milestones simply occur at a point in time (i.e. Zero duration)

Definitions (cont. d) Relationship Types: Finish to Start (FS) the predecessor activity finishes before the successor activity starts Start to Start (SS) the predecessor activity and successor activity start at the same time Finish to Finish (FF) the predecessor activity and successor activity finish at the same time Start to Finish (SF)** typically used with a lag, the predecessor activity finishes when the successor activity starts ** - Note that this relationship is available but not widely used.

Reasons for Planning and Scheduling in Construction Contract requirement Provides proof to the Owner that the Contractor has thought the project through Provides the Owner the tool by which to hold the Contractor accountable Provides the Contractor the tool by which to hold the Owner accountable

Reasons for Planning and Scheduling in Construction Aids in identifying potential problems Available labor Available equipment Material procurement lead time, etc. Site Logistics Too many activities in one area Working hours Local City/State Requirements Union Requirements Environmental Requirements

Developing a Network Model The development of the network model is perhaps the most important step in using a network as a scheduling tool. Fundamental concept: - The network represents a time-oriented model of a system, not unlike a physical scale model of a project. NOTE: Scheduling is a mathematical analysis based on duration and dates.

Steps in Building a Network Model 1. Define Activities 2. Order Activities 3. Establish activity relationships and draw a network diagram 4. Determine quantities and assign durations to activities 5. Assign resources and costs, if applicable 6. Calculate early and late start/finish times 7. Compute float values and identify the critical path 8. Schedule activity start/finish times

Network Model development key points: Typically an iterative process Should continue throughout the life of the project Must be updated to reflect changes by Owner, Site Conditions, etc. sequence must be reflect the changes NOTE: Step 5 Resources & Costs is only utilized when resources and cash flow need to be addressed. This step is not utilized by many schedulers The model should be updated to reflect the actual construction activities is it is to be a useful construction tool.

Defining Activities Anything that must be accomplished in order for the project to be completed may warrant inclusion in the network Activities are regardless of: Who is responsible What resources are required Costs Duration

Primary Activity Types Production/Construction relate directly to the physical effort of creating the project Excavate/Place/Backfill Trench Frame Interior Walls Plumb 1st Floor Water Lines

Primary Activity Types (cont. d) Procurement relate to arranging for the acquisition of materials, money, equipment and manpower Order Signal Standards Obtain Remodeling Loan Execute Concrete Purchase Order

Primary Activity Types (cont. d) Management the support and administrative tasks that often directly impact the project schedule Submit Rebar Shop Drawings Submit Inspection Reports Approve SWPPP

Ordering Activities Based on the timing of certain activities relative to other activities. Guide to ordering: Which activities must precede it? Which activities must follow it? Which activities can be concurrent with it?

Ordering Activities (cont. d) Immediately Preceding Activities (IPA) identify which activities must precede the subsequent. When this is performed, all subsequent activities will have been identified and concurrent activities will show themselves, unless there are constraints. Constraints Dictate the order in which activities are performed

Types of Constraints: Physical relate to the physical process of construction, i.e. dig trench before placing pipe Resource preclude activities from occurring at the same time as a result of insufficient resources, i.e. only 1 piece of equipment, finite amount of material delivered, etc. Safety preclude unsafe conditions from occurring Financial preclude from too large or small of financial obligation

Types of Constraints (cont. d) Environmental preclude work from being performed until certain environmental issues are addressed Management typically uncategorized constraints, i.e. holidays, training requirements, etc. Contractual Owner imposed constraints, i.e. time of completion, impacting adjacent operations, etc. Regulatory Local, State & Federal regulations, i.e. permits, working hours, etc.

Assigning Duration to Activities Duration estimated time required to complete an activity Typical unit of measure is days Determination is more of an art form than science Frequently directly related to labor cost estimates

Assigning Duration to Activities (cont. d) Major factor: productivity rate which can be influenced by the following: Labor skill ( A team vs. C team) Weather (hot/cold/windy/wet/etc.) Working Conditions (limited physical constraints) Quantity of Work (learning curve)

Determining Activity Durations - Estimating Accurate Estimate depends on: The accuracy of the quantity take-off Includes the cost of: Labor, Equipment and Material Overhead & Profit The Project Schedule either directly affects OR is directly affected by each of these components!

Other Estimate/Schedule Factors Contract Specifications Dates or durations / Specific Milestones Working hours Required access/impact to the area Regulations Permits Local Agencies Environmental

Units of Time Working Days vs. Calendar Days Rule of Thumb: Working days are typically associated with project that may be affected by weather Concrete Cure, Administration Tasks, etc. Weekends & Holidays Weather Delays Holidays

Progress Schedule Like the Plans and Specifications, the Project Schedule is an integral tool for the Contractor and Owner regarding the status of the Project, it should be updated and maintained regularly

Questions?