Building the City of West Palm Beach s Stormwater Infrastructure Rehab Program June 15, 2018

Similar documents
Special Specification SS1- INTERNAL CIPP POINT REPAIR OF PIPELINES. A. General. 1. Scope

Specifying Trenchless Sewer Rehabilitation Projects. Presented by: Todd Stelmacher Visu-Sewer, Inc.

MWRD Infiltration and Inflow Control Program Compliance Update. Committee of the Whole Meeting April 3, 2018

Successfully Developing & Managing. Assessment & Rehabilitation Programs. Presented from a municipal perspective

A PENNEY (ROAD) SAVED IS A LESSON (L)EARNED

17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.

Infiltration and Inflow. Michael Sassaman Phone

Newberg Inflow and Infiltration Study WES 2017 PETER OLSEN, PE EMILY FLOCK, EI 1

Lessons Learned from a 60 CIPP Storm Sewer Liner Installation. Robert Stolt, PE Christopher Beranek, PE

Rowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project. TACWA Meeting

Infiltration & Inflow

SPECIFICATIONS FOR PREMIER-PIPE USA CURED-IN-PLACE TECH LINER

SECTION IRRIGATION PIPELINE LINING (CURED-IN-PLACE PIPE)

TECHNICAL SPECIFICATIONS FIBERGLASS/ULTRAVIOLET LIGHT CURED-IN-PLACE PIPE (CIPP) FOR MAINLINE RENEWAL

EXHIBIT A SCOPE OF SERVICES Districtwide Storm Sewer Inspection

INDIANAPOLIS DEPARTMENT OF CAPITAL ASSET MANAGEMENT COMBINED SEWER INFRASTRUCTURE ASSESSMENT. Final Report. Greeley and Hansen.

Project Specifications

International Aramoon Corp. Pipe Inspection and Rehabilitation By: Faiz Al-Elweet. SAWEA Al-Khobar KSA February 24, 2010

Clean Water 2020 Program

Service Lateral Rehabilitation

TECHNICAL SPECIFICATIONS FOR INTERCEPTOR AND SIPHON INSPECTION/CLEANING

PIPE USERS GROUP (PUG) July 11, Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company

SPECIAL SPECIFICATION 4411 Cured-In-Place Pipe (CIPP) (Drainage Structures)

Rehabilitation of Sanitary Sewer Collection Systems. Dan Beauchamp, P.E.

PROCESSING COMBINED LASER, SONAR AND HD IMAGING FOR BETTER EVALUATION DECISIONS

Specification Guidelines for Testing and Sealing Lateral Connections and Lateral Service Lines in Sanitary Sewer Systems

sewers ANd storm drains Storm Drain Under Construction, 1916

System-wide Sewer Rehabilitation: Efficiency in Design. May 5, 2011 OWEA Collection Systems Specialty Workshop Eric Dunn, PE Brown and Caldwell

PIPE REHABILITATION. Comply with Division 1 - General Provisions and Covenants, as well as the following:

4.1 Sewer System Mapping

State of Michigan Laws, Rules and Programs that relate to the Rehabilitation of Sanitary Sewer Collection System. By Thomas McDowell, P.E.

FLORIDA DEPARTMENT OF TRANSPORTATION

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS

LESSONS LEARNED DURING INSTALLATION OF LARGE DIAMETER CIPP LINING IN AN ENVIRONMENTAL MITIGATION AREA (TM1-T3-05)

Todd Eising, PE, Utilities Section Manager Environmental & Water Resources Department, City of Folsom

Sanitary Sewer. Infiltration & Inflow (I/I) Study. Presented by:

Key I/I Reduction Plan Components

City of St. Petersburg

STORMWATER ASSET MANAGEMENT:

ORWEF WATER ENVIRONMENT SCHOOL Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company

CITY OF TAMPA ADDENDUM NO. 1. DATE: September 15, Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place Pipe (C.I.P.P.

Section 8 System Evaluation and Capacity Assurance Plan (SECAP)

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

Fold & Form PVC Liners Sewer & Culvert Rehabilitation

COLLECTION SYSTEM O&M AND ASSET MANAGEMENT AT LACSD. Anthony Howard, PE Supervising Engineer Water Reclamation Plants Section

By Bryon Livingston, P.E. and Rich Blackmun, P.E.

ADDENDUM II BLOOMINGTON CITY COUNCIL AGENDA DECEMBER 15, 2014

Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation

Rehabilitation of the Coral Gables Wastewater Collection System

SPECIAL SPECIFICATION 4631 Cured-In-Place Pipe (CIPP)

EVALUATION SUBJECT: PERMA-LATERAL PULLED- IN-PLACE CURED-IN-PLACE PIPE LINING SYSTEM

Getting Started with Stormwater Asset Management in Westford, MA

SEWER TELEVISING & REPAIRS. Adam Tierney Business Development Manager Northern Pipe, Inc.

17/03/2017. Contents. Solutions. Customer s Needs. How Trenchless Rehabilitation Depends on Effective Condition Assessment. Performance.

SECTION 813 SEWER FLOW CONTROL

LARGE DIAMETER HDPE SLIPLINING WHERE EXPERIENCE MATTERS

ITEM NO SLIPLINING SANITARY SEWERS

2.3.3 Defining Metrics Refining Survey Questions Arranging Data in a Matrix Reviewing Performance Indicators 18

AI-04-CCTV INSPECTION OF CONSTRUCTION WORKS

LS 2760 CURED-IN-PLACE SEWER LINING

City of Guelph Transfer of Review Procedures 7 March, 2017

Table 1 Description of Work Pipe Size (mm) 1 Sunshine Way A/C No. A/C Yes

A CASE STUDY IN CURED-IN-PLACE PIPE (CIPP) FOR STORMWATER PIPE REPAIR. By John Featherstone, P.E

SECTION TRAFFIC MAINTENANCE AND PROTECTION

GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS

Inland Pipe Rehabilitation. August 17 OAWWA Canton, OH

SECTION 808 CURED-IN-PLACE-PIPE (CIPP)

PROJECT UNDERSTANDING

Appendix A SURVEY QUESTIONNAIRE

Project Type: Drainage and Storm Systems

All Cracked Up! Condition Assessment Protocols for Stormwater Infrastructure

Using GIS to Assess Risk and Prioritize Storm Sewer Maintenance, Repair and Replacement

ALMEDA TUNNEL PAST, PRESENT AND FUTURE

Pearl City Force Main Repair Uses Sliplining Installation Method

INTERFIT LATERAL SEALING SYSTEM INSTALLATION GUIDELINE SPECIFICATION

CREATING A CAPITAL PLAN USING MST AND THE NASSCO PIPELINE ASSESSMENT PROGRAM. Michael A. Schober, PE, BCEE T&M Associates

SECTION 501 GRAVITY SEWERS. U. No pipe length used shall be less than 5 feet.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 834 CONDUIT RENEWAL USING RESIN BASED LINER.

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Preparing Your Agency for an Electro Scan Water CIPP Certification Field Demonstration

Condition Assessment and Rehabilitation of Large Sewers: Chambers Creek Interceptor Tunnel Ohio Water Environment Association

Technical Memorandum. Trenchless Technology Options for Rehabilitation of the Yambury Road Drainage Culvert

PART B SPECIAL PROVISIONS

SECTION XXXXX CHEMICAL GROUTING

SEwEr rehabilitation Spr technologies

City of Madison: 2017 Capital Budget Capital Improvement Plan

Improved Inflow & Infiltration (I&I) Monitoring Program

Project Summary

The Rehabilitation of Existing Building Drains and Building Sewers by the

SSES Implementation and SSES Pilot Study Program Large-Scale Rehabilitation in Multiple Towns

Force Main Condition Assessment. Water Environment School March 2017

Charbonneau Consolidated Infrastructure Improvement Plan 2017 APWA OREGON CHAPTER SPRING CONFERENCE SEASIDE, OREGON APRIL 12, 2017

BIDS WILL BE CONSIDERED NON-RESPONSIVE WITHOUT THE REQUIRED SIGNATURE ACKNOWLEDGING THE FOLLOWING:

Trenchless Technology

SAMPLE DESCRIPTION OF BID ITEMS. Description of Bid Items including their respective measurement for payment are listed below:

Installation Practice InnerSeal

EVALUATION MEMORANDUM NO. 4 Existing Pipeline Evaluation

Transcription:

Building the City of West Palm Beach s Stormwater Infrastructure Rehab Program June 15, 2018 2018 HDR, Inc., all rights reserved.

Data Evaluation and Literature Review Presentation Outline Condition Assessment Methodologies and Decision Logic Rehabilitation Methodologies and Decision Logic Next Steps Questions

01 Data Evaluation and Literature Review

Data Evaluation and Literature Review City s policies, activities, and processes Stormwater Master Plan and project recommendations Geodatabase of storm sewers FDOT manuals and specifications Compile list of storm sewer inspection and rehabilitation bids Contractor interviews

Data Evaluation and Literature Review Stormwater Asset Summary City of West Palm Beach Stormwater System 60 square mile watershed 600 sub-basins 186 miles of storm pipe, up to 96 diameter Pipe materials o 60% reinforced concrete (RCP) o 16% vitrified clay (VCP) o 7% corrugated metal (CMP)

Data Evaluation and Literature Review Storm Sewer CCTV Inspection and Rehabilitation Bids Budgeting tool for future work Data grouped by pipe diameter and location (Florida, regional, and national) Costs obtained for: o CCTV inspection o Pipe cleaning o CIPP lining o Sliplining

Data Evaluation and Literature Review Interview with Local Contractors National Association of Sewer Service Companies (NASSCO) rating system can effectively be applied to storm sewers Cured-in-place pipe (CIPP) lining is the preferred option for repairs, as it can be installed in larger runs and larger diameters

Data Evaluation and Literature Review Interview with Local Contractors Challenges of working in a coastal environment: o Cleaning barnacles/heavy sedimentation, and working in water to inspect/repair outfalls due to boat traffic o Extensive dewatering required due to high groundwater table o Working in tidally-influenced areas makes work possible at only certain times of the day

02 Condition Assessment Methodologies and Decision Logic

Condition Assessment Methodologies and Decision Logic Cleaning requirements Dewatering and bypass pumping requirements Condition assessment technology options Decision model Condition rating scale Technical specifications o Inspection equipment requirements o Inspection data and reporting requirements

Condition Assessment Methodologies and Decision Logic Cleaning Requirements Mechanical o Rodding primary application is small diameter pipe o Bucket machine typically cylindrical drive with jaws to pull debris from pipe or structure Hydraulic o Jetting high velocity water used to wash sediment from pipe; typically used on smaller diameter pipe in parallel with vacuum truck

Condition Assessment Methodologies and Decision Logic Dewatering and Bypass Pumping Requirements If water level is greater than 10 to 20 percent of pipe diameter, dewatering is required to complete a comprehensive inspection using conventional CCTV Submerged or partially submerged pipes require an upstream and downstream plug Bypass pumping may be required if upstream segment of pipe surcharges and has potential to cause surface flooding

Condition Assessment Methodologies and Decision Logic Technology Options Closed Circuit Television (CCTV) Subaqueous CCTV Zoom Camera Laser Profiling Sonar

Condition Assessment Methodologies and Decision Logic Tiered Approach for Inspection and Decision Logic Tier 1: Preliminary Inspection Qualitative screening No condition rating Technology o Subaqueous CCTV o Zoom camera Tier 2: Condition Assessment Detailed visual inspection over length of asset Produces structural and O&M condition rating Data can be used to define limits of more intensive Tier 3 inspections Technology o CCTV (convention or subaqueous) o Zoom camera (for manholes/inlets) o Visual inspection (for large culverts) Tier 3: Inspection to Support Engineering Design Activities Detailed data inputs for engineering analysis to define appropriate rehab technique Technology o CCTV o Laser profiling

Condition Assessment Methodologies and Decision Logic Condition Rating Scale Recommend applying a modified version NASSCO condition rating system for the City s stormwater assets to standardize the inspection process Rating scale takes into account number, type, and severity of defects

Condition Assessment Methodologies and Decision Logic Technical Specifications Inspection equipment and software technical requirements o CCTV camera o Camera for manhole/inlet inspections o Zoom camera for inspection o Compatibility with City s current CCTV software (GraniteNet) Data and reporting requirements o Data acquisition (mandatory fields) o Video, images, and measurement o Deliverables o Quality control and acceptance of deliverables

03 Rehabilitation Methodologies and Decision Logic

Rehabilitation Methodologies and Decision Logic Technical Specifications CIPP lining Sliplining Grouting Pipe bursting (replacement) Open cut (replacement)

Rehabilitation Methodologies and Decision Logic Guidance for Technical Issues Plugging Bypass pumping Mechanical/hydraulic cleaning Coffer damming (outfalls)

Rehabilitation Methodologies and Decision Logic Rehabilitation Method: Cured-in-Place Pipe (CIPP) Lining Key components o Insertion of a liner impregnated with thermosetting resin within an existing host pipe Advantages o o o Fully structural replacement Small reduction in cross-sectional area minimal impact to hydraulics No entrance or exit pits required minimal surface disruption Disadvantages o o Dewatering/bypassing required during construction Sometimes more costly compared to other lining methods

Rehabilitation Methodologies and Decision Logic Condition Assessment Programs: Typical Workflow 1. Plan and Prioritize Inspections 2. Conduct Field Inspections 3. Analyze Data and Generate Initial Recommendations 4. Develop and Execute Improvement Projects 5. Leverage Data To Manage Assets

Rehabilitation Methodologies and Decision Logic Develop High-Quality Decision Process Failure History Maintenance Type & Frequency Inspections and Condition Data Decision Process Repair Rehabilitate Maintenance History Replace

Key Key Questions / Decision or Points Decision Points that influence implementation Was a defect requiring rehab identified during inspection? Has storm sewer been identified as being undersized? Impact on Decision Logic If yes, enter rehab decision logic If yes, pipe bursting or open cut required Frequency of point defects? If high frequency, consider lining rather than point repair What is the existing pipe material? Impacts feasibility of certain rehab methods What is the existing pipe size? Impacts feasibility of certain rehab methods Is existing pipe deformed or sagging? Open cut may be required What are surface conditions above existing pipe? Open cut may be less cost-effective

04 Next Steps

Next Steps Inspect priority 5,000 LF of storm sewer and review submittals Select rehabilitation approach using decision model Rehabilitate storm sewers included in pilot project Incorporate lessons learned from pilot to methodologies and decision logic Apply methodologies and decision logic to remaining 35,000 LF of priority storm sewer

Questions? Raul Mercado, PE, CFM RMercado@wpb.org Dan Suarez, PE Daniel.Suarez@hdrinc.com