Laney College Childcare Center Renovation 900 Fallon Street Oakland, CA 94607

Similar documents
Request for Proposal # 1703 Water Damage Repair of Murray Mansion

CLARIFICATION #4 HARRISON / DEVER CRIB COMPLEX STRUCTURAL RENOVATIONS. SPECIFICATION Number:

DOCUMENT ADDENDA AND MODIFICATIONS

SECTION HOLLOW METALWORK. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

Request for Quotation: S&E Door replacement

ITEM 555 CHAIN LINK FENCING

FENCE PERMIT APPLICATION

REVISED BID FORM WILLIAM PATERSON UNIVERSITY OF NEW JERSEY. PROJECT NAME: Renovations & Addition to Hunziker Hall & Wing

MECHANICAL M-1 LEGEND AND DETAILS M-2 FLOOR PLAN - DUCTWORK M-3 FLOOR PLAN - PIPING

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.

PORTLAND COMMUNITY COLLEGE SW 49 th Avenue Portland, Oregon ADDENDUM NO. 4

TOWN OF EAST HADDAM INVITATION TO BID EAST HADDAM COMPANY #1 FIREHOUSE INTERIOR RENOVATIONS ADDENDUM NO. 1 TO CONTRACT DOCUMENTS

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Bear Exhibit Fence Upgrades. The following modifications are hereby made part of the contract documents:

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO.

ATTACHMENT A. Bid # 6793

SECTION MEASUREMENT AND PAYMENT

SECTION MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN

Phone Joan Daniels. Line # Item Number Item/Description Category Co Item UOM Contract Price

Addendum! Project No: HFX A0 Client Project No: MISC Project: MacAulay Sports Field Project Date: March 23, 2015 Addendum No: 2

Section , Article 4 of the Zoning Ordinance December 14, 2012 Page 1 of 8

REQUEST FOR BIDS METROPOLITAN PARK DISTRICT OF TACOMA Northwest Trek Core Area Fence Upgrade SWR BID NO. T Request for Bids

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

ADDENDUM NUMBER 1: Portsmouth City Boiler Plant Improvements Project Bid Proposal # Issued: May 23, 2011

A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION ALBERTVILLE, ALABAMA

Kelly Village Apartments 3118 Green Houston, Texas 77020

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1

CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS

Exterior Door & PA System Replacement, Domestic Water Piping System and B/F Access Upgrades

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

ADDENDUM 1. Request for Proposals City of Minot, North Dakota Structure Demolition and Site Restoration Project, # Round 3.

Addendum No. 3 pg. 1. Project: Prolift Project No.: Subject: Addendum No. 3 Date: Monday, July 18, 2016

COUNTY OF SAN JOAQUIN

CITY OF SANTA ANA PROPOSAL PROJECT NOS.: , , , DOWNTOWN PARKING FACILITY IMPROVEMENTS

CITY OF ST. PETERSBURG PLANNING & ECONOMIC DEVELOPMENT DEPT

SECTION NON--STRUCTURAL METAL FRAMING

INVITATION TO BID. Prospective bidders are encouraged to conduct a pre-bid site visit to aid in their bidding assessments.

ALL PROSPECTIVE CONTRACTORS, PLAN ROOMS AND SUPPLIERS

ADDENDUM #1 TO THE SPECIFICATION FOR THE CONSTRUCTION OF THE 115KV STONEBREAK RD. TRANSITION STATION THE TOWN OF MALTA AND A PORTION OF THE 115KV

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT

Delaware Street

Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION CHAIN LINK FENCING

PROJECT: GROVECENTER ELEMENTARY SCHOOL RELOCATION OF 1-24x40 AND 1-36x40 RELOCATABLE BLDG. AND PLAY EQUIPMENT.

RENOVATION OF THE VIA BUILDING FOR THE GUELPH TRANSIT TERMINAL FROM THE PRE- QUALIFIED GENERAL CONTRACTORS Reference Number:

ST. PETERSBURG COLLEGE ADDENDUM #1

Modifications or clarifications to original plans and specifications: 1. ATTENDEES OF THE PRE-BID CONFERENCE ARE ON THE ATTACHED LIST

PURCHASING DEPARTMENT. Project # Addendum # # of Pages Original Issue Date. 7 (including title page) March 3, 2017

327 King Street Exterior Repairs & Interior Renovations Project No. H15-N200-PG

SECTION CHAIN LINK FENCING

BORTOLOTTO ADDENDUM #2

Whitley Shower Locker Toilet Facilities

Special Provision No. 541S01 October OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced with the following:

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

June 12, 2017 Addendum #6 RFP # Modular Relocation & Site Development

SECTION 1043 FENCE MATERIAL

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

Addendum No. 1 Page 1 of 2

AN OFFERING OF 1661 EAST OGLETHORPE HIGHWAY FLEMINGTON, LIBERTY COUNTY, GEORGIA PRESENTED BY WHITLEY AND ASSOCIATES, INC.

#2 Daniel Drive O Fallon, Missouri BaalmanArchitects.com

SPECIAL ADMINISTRATIVE BOARD OF THE TRANSITIONAL SCHOOL DISTRICT OF THE CITY OF ST. LOUIS

SECTION 1208 CHAIN LINK FENCING DESCRIPTION

Purchasing and Property Services AOC East Fowler Avenue Tampa, Florida (813)

BID # College Center EXTERIOR DOOR REPLACEMENT SECTION "C" TECHNICAL SPECIFICATIONS OWNER

C. Samples: For each door face material, at least 3 by 5 inches (75 by 125 mm) in size, in specified finish.

Addendum #1. January 22, 2018

Installation of Metering System for Monitoring Based Commissioning Program Under Prop. 39 & CCC/IOU

ARCHITECTURAL RULES INDEX

CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS DOCUMENT 00085B ADDENDUM ADDENDUM NO. 1

Chapter WALLS AND FENCES

Minimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS

4.1.3 Project Manual

ADDENDUM NO. 1. This addendum consists of 13 pages

PART II - CODE OF ORDINANCES Chapter 16 - CONSTRUCTION, REHABILITATION AND PROPERTY MAINTENANCE REGULATIONS ARTICLE VIII. PROPERTY MAINTENANCE

RESIDENTIAL GARAGE AND DRIVEWAY

11/1/2016. Smoke detectors will be furnished by MHA and installed by contractor.

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

ADDENDUM NO. 1 FOR ROADWAY RECONSTRUCTION RFP # June 7, 2016

CITY OF OCEAN CITY COUNTY OF CAPE MAY, NEW JERSEY ADDENDUM #1 FEBRUARY 16, 2016 CITY CONTRACT NO

REQUEST FOR PROPOSAL DEMOLITION & REMOVAL OF THE OLD TOWN HALL 2278 US ROUTE 4 EAST

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

BID ADDENDUM. 1 of 1. State Project No: H27-Z381 ADDENDUM NO.: PROJECT NAME: 1600 Hampton St. Building Roof Replacement

City of New Haven. 101 FRONT STREET PO BOX 236 NEW HAVEN, MO Phone * * Fax

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209)

DETAILED METAL DOOR SPECIFICATION. UNIVERSITY CONTACT: Mark Golden, Supervisor of Structural Services (302)

Delaware Street

QBE Restoration Program Highlights

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT Pavement Rehabilitation Clear Zone Improvements MM 64.4 to MM 68.5

Fences, Wall and Hedge Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

Whapmagoostui & Waskaganish Addendum no AR01 August 15, 2017 Cree Daycare Centres Cree Nation Government RRA 1728 Page 1 of 6

PROFESSIONAL DESIGN MANUAL INDEX

R-M MANUFACTURED HOME RESIDENCE DISTRICT.

ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB # RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN

City of North Mankato 1001 Belgrade Avenue North Mankato, MN (507)

Re: Concrete Installation/Demolition and Bollards Request for Proposal # R-RFP. Addendum 1 Clarifications to Request for Proposal

Arts Center- Building needs

Revised Drawings A, E, and M dated 11/13/18 (that include additional specifications)

TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE

ARCHITECTURE, PLANNING AND HISTORIC PRESERVATION, INC. ADDENDUM NO. 1. September 9, to the BIDDING DOCUMENTS for

Transcription:

LANEY COLLEGE CHILDCARE CENTER RENOVATION DOCUMENT 00 9113 ADDENDA BID NO. 18-19/09 Peralta Community College District Laney College Childcare Center Renovation 900 Fallon Street Oakland, CA 94607 October 15, 2018 ADDENDUM No. 1 This addendum supersedes items of the original contract documents wherein it is inconsistent with it. All other conditions remain unchanged. The following changes, modifications, corrections, additions or clarifications shall apply to the contract documents and shall be made a part of and subject to all of the requirements thereof as if originally specified or shown. It is the responsibility of the proposer to review the list of attachments to ensure that the addendum is full and complete. This Addendum modifies the original RFP Documents for the above RFP. Acknowledge receipt of this addendum in the space provided on the Proposal Form. Failure to do so may subject Proposer to disqualification. Revisions/Additions to bid documents: 1. Section 01 1000 Scope of Work (Please see attachment). 2. Section 01 1100 Summary of Work (Please see attachment). 3. Drawing for Ornamental Iron Fence including Floor Plan of Mesh Chain Link (See Attachment). END OF SECTION

LANEY COLLEGE CHILDCARE CENTER RENOVATION SECTION 01 1000 SCOPE OF WORK PART 1 GENERAL 1.01 SUMMARY A. Section includes SCOPE OF WORK including: 1. Outline of Scope of Work 2. Broad Description of Scope of Work 3. Itemization of Work Items, 4. List of Equipment & Accessories 1.02 BROAD DESCRIPTION OF SCOPE OF WORK A. Work comprises of general construction and installation of various items at the Owner s Laney College Childcare Center located at 900 Fallon Street, Oakland, CA 94606. Construction and installation work are outlined below. B. Work comprises of: (1) FENCE (I) Ornamental Iron: Furnish and install approximately 30 lineal feet (LF) of 8 feet high, curved top, pressed point ornamental iron fence with 1 each 42 inches wide and 7 feet high pedestrian gate with transom, the ornamental metal fence should be of standard gauge with spacing of vertical square-shaped tubular bars of at 4¾ inches OC; All material pre-galvanized with black power coated finish. (II) Chain Link Fence: Furnish and install approximately 41 lineal feet (LF) of 8 feet high, galvanized, 1 inch mesh chain link fence and 1 each 4 feet wide by 8 feet high pedestrian gate; All Posts set in ground in concrete footings. (2) DOORS (I) Replace the Closers in thirteen (13) Interior doors and ten (10) Exterior doors; (II) Replace set of doors Hinges in order to reduce the gap between door and frame when door is in the open position; (III) Replace the bottom stainless steel Kick-plate on all exterior doors; (IV) Install door Chimes on all twenty-three (23) doors, chime type to be specified and/or allowance amount allocated as set-aside amount. (3) FLOORING (I) Remove existing carpets from the entire center and replace with Resilient Vinyl Composite Tile (VCT) floor covering over a total Area of 2,610sf. The specified type will be Tarkett, Armstrong VCT or similar (4) PAINTING (I) Touch-up Exterior Painting of area of approximately 2,000sf; (II) Paint 20 Exterior wood panel after beveling of the edges have been done. (5) CEILING (I) Replace about 12-15 Acoustic Ceiling Panels that are water damaged. (6) WOOD WORK (I) Beveling of splinters along the edges of 20 Exterior Wood Panels measuring 1ft wide by 2inches thick with an average length of 15ft. Beveling is required to smoothen the edges and improve safety for the kids; (II) Install 4inch wide wood strip along 110ft length of the wood ½ wall at the back of the Childcare Center the wood strip is intended to narrow the existing opening for child safety reasons; (III) Re-anchor approximately 4ft section of the top wood cap plate located along the 110ft length of the ½ wall. (7) LANDSCAPE (I) Trim hanging tree branches over fence line; (II) Dig up and remove wild plants along fence line abutting Brick wall on E. 10th street; (III) Add tan Bark (certified for use in children playground) to small area by water fountains on the Main Yard; (IV) Install Artificial grass (approved for use in children playground) in Main Yard in an area of approximately 630sf and add Sand to sand boxes in an area of approximately 885sf of an average depth of about 6in or the equivalent of 444 cubic feet. Scope of Work 01 11 00-1

(8) BATHROOMS (I) Remove existing set of grip bars and replace with high quality rust-proof stainless steel bars -4 pieces total; (II) Replace rusted stainless steel collapsible shelving with similar kind but of high quality rust-proof stainless steel grade; (III) Replace rusted stainless steel toilet cover dispenser with high grade rust-proof stainless steel. C. NOTE: Please refer to the attached photos and drawings for more details and specifications. 1.03 ITEMIZATION OF CONSTRUCTION OR INSTALLATION WORK A. Description of Items in construction and Installation: See attached photos for specifications. Item 1 FENCE (I) Ornamental Iron: Furnish and install about 30 LF of 8ft high, curved top, pressed point ornamental iron fence with 1 each 42inch wide and 7ft high pedestrian gate with transom; (II) Chain Link Fence: Furnish and install approx. 41 LF of 8ft high, galvanized, 1 inch mesh chain link fence and 1 each 4ft wide by 8ft high pedestrian gate; All Posts set in ground and in concrete footings. Item 2 DOORS (I) Replace Closers in 13 Interior doors and 10 Exterior doors; (II) Replace some door hinges at locations where the gap between door frame and door panel is wide enough for kids hand to go through; (III) Replace the bottom Sealers in all exterior doors; (IV) Install Door Chimes on all 23 doors. Item 3 FLOORING (I) Remove existing carpets from the entire center (study/sleep area; offices & storage closets) and Replace with Resilient floor covering (PVC tiles). Total area to be converted to resilient flooring is approximately 2,610sf. Item 4 PAINTING (I) Touch up exterior painting over an area that is approximately 2,000sf; (II) Paint 20 exterior wood panels measuring 1ftx15ftx2inches only two surfaces requires painting, and its mainly along the edges that will be beveled to prevent splinters. Item 5 CEILING (1) Replace about 10-15 acoustic ceiling tiles that have suffered water damage. Item 6 WOOD WORK (I) Bevel the edges of about 20 exterior wall mounted decorative wood panels to minimize the risk of splinter injury to toddlers and young teens; (II) Install 4 inch wide wood strip along 110LF length of wood ½ wall at the rear of the building; (III) Re-anchor a 4ft section of the wood cap (at joint where its warped, and pulling apart) along the length of the ½ wall at the rear of the building; Item 7 LANDSCAPE (I) Trim hanging Tree branches over fence line; (II) Dig up and remove wild plants along fence line abutting the main street; (III) Add tan Bark to small area by water fountains on the Main Yard; (IV) Install artificial grass in Main Yard and add sand to Sand Boxes. Item 8 BATHROOMS (I) Remove and replace existing rusted stainless steel Grip Bars with a high quality rust-proof material; (II) Replace rusted stainless steel retractable shelving with high quality, rust-proof stainless steel kind; (III) Replace rusted stainless steel toilet paper cover dispenser with high quality rust-proof stainless steel. 1.04 LIST OF EQUIPMENT & ACCESSORIES A. Description of Items: See attached photos and drawings for details and specifications. END OF SECTION Scope of Work 01 11 00-2

LANEY COLLEGE CHILDCARE CENTER RENOVATION SECTION 01 1100 SUMMARY OF WORK PART 1 GENERAL 1.01 SUMMARY A. Section includes Summary of Work and Work Restrictions including: 1. List of Sections 2. Work Covered By Contract Documents 3. Bid Item, Allowances and Alternates 4. Work Days and Hours 5. Contractor Use of Site 1.02 WORK COVERED BY CONTRACT DOCUMENTS A. Work comprises of construction and installation at Owner s Laney College Childcare Center located within the college campus at 900 Fallon Street, Oakland, CA 94606. Laney College Childcare Construction and Installation work is per the scope of work attached and specifications provided by Peralta s Facilities Maintenance and Operations Department. B. The Work of this Contract comprises construction of all the Work indicated, described in the Specifications, or otherwise required by the Contract Documents. Unless provided otherwise in the Contract Documents, all risk of loss to Work covered by Contract Documents shall rest with Contractor until Final Acceptance of the Work. Cost of maintenance of systems and equipment prior to Final Acceptance will be considered as included in prices Bid and no direct or additional payment will be made therefore. C. For all Bid items, furnish and install all Work, including connections to existing systems, indicated and described in Specifications and all other Contract Documents. Work and requirements applicable to each individual Bid item, or unit of Work, shall be deemed incorporated into the description of each Bid item (whether Lump Sum or Unit Price). Any Bid item may be deleted from the Work and Contract Sum, in total or in part, prior to or after award of Contract without compensation in any form or adjustment of other Bid items or prices therefore. D. Allowance Work shall be done as Change Orders and as specified in Section 01 2600 (Modification Procedures). Identify Allowance Items (See Document 00 4000 [Bid Form]) work on the Progress Schedules and on Applications for Payment. The Amount given on Document 00 4000 (Bid Form) under each Allowance Item is the sum of money set aside for each Allowance Item. These amounts shall be included in the Contract Sum on the Bid Form. If the cost of Work done under any Allowance Item is less than the amount given on the Bid Form under that Allowance Item, the Contract Sum shall be reduced by the difference between the amount given in the Bid Form and the cost of Work actually done. 1.03 BID ITEMS, ALLOWANCES AND ALTERNATES A. Descriptions of Items on Bid Form 00 4113 (listed by Bid item numbers): Bid Item 1 FENCE (I) Ornamental Iron - Furnish and install pressed point ornamental iron and one pedestrian gate with transom all materials pre-galvanized with black power coated finish; (II) Chain Link Fence Furnish and install galvanized 1 inch mesh chain link fence and 1 gate; All Posts set in ground in concrete footings. Bid Item 2 DOORS (I) Replace Closers in 13 interior doors and 10 exterior doors; (II) Replace some door hinges at locations where the gap between frame and door panel is too wide: (III) Replace door bottom stainless steel kick-plate in all exterior doors; (IV) Install chimes on 23 doors, chime type to be specified and/or allowance amount allocated as set-aside amount. Bid Item 3 FLOORING (I) Remove existing carpets from entire center and replace with new Resilient floor VCT (Vinyl Composition Tile) covering in an area of approximately 2,610sf. Summary of Work 01 11 00-1

Bid item 4 PAINTING (I) Touch up exterior painting over an area of about 2,000sf; (II) Paint 20 exterior wood panels measuring 1ftx15x2in. Bid item 5 CEILING (I) Replace about 10-15 acoustic ceiling panels that have water damage. Bid Item 6 WOOD WORK (I) Bevel the edges of about 20 exterior wall mounted wood panels; (II) Install 4 inch wide wood strip along 110LF length of wood ½ wall at the rear of the building; (III) Re-anchor a 4ft section of the wood cap along the ½ wall. Bid item 7 LANDSCAPE (I) Trim hanging tree branches over fence line, maximum of ten (10) trees; (II) Dig up and remove wild plants along Brick fence abutting E. 10th street; (III) Add tan Bark (certified for children playground) to small area by water fountains on the main yard; (IV) Install artificial grass (approved for use in children playground) in main yard and add sand to sand boxes. Bid item 8 BATHROOMS (I) Remove and replace existing rusted stainless steel grip bars with a high grade and quality kind; (II) Replace rusted stainless steel collapsible shelving with high grade and quality kind; (III) Replace rusted stainless steel Toilet Cover Dispenser with high grade and quality kind. The Labor portion for all of the work described in Section 1.02, A. above, the drawings provided and all other contract documents. B. Bid Alternates (listed by Bid item numbers): (Not Used) C. Bid Allowances (listed by Bid item numbers): (Not Used) 1.04 WORK DAYS AND HOURS A. Work Days and hours: See paragraph B and C. B. Work at the Site on weekends, holidays, or other than normal business hours is permitted with approval by Owner. C. Any activity, especially demolition that produces loud disruptive noise shall not be performed between the hours of 8am and 8pm on Monday-Friday. Contractor shall consult with Campus and District staff prior to commencement of potential disruptive noise activities. All other work can be performed during normal working hours. Daytime Saturday and Sunday work is acceptable with permission by the District. Early morning demolition work and cleanup must be completed prior to 8 am. 1.05 CONTRACTOR USE OF SITE A. Confine operations at Site to areas permitted by Contract Documents, permits, ordinances, and laws. Do not unreasonably encumber Site with materials or equipment. B. Assume full responsibility for protection and safekeeping of products stored on premises. Move any stored products that interfere with operations of Owner or other contractor. C. Coordinate parking, storage, staging, and Work areas with Owner. Owner will provide a storage area for Contractor's equipment and materials. Do not store construction materials in the dripline of any tree. D. Prior to commencement of Work or excavation, Contractor and Owner shall jointly survey the area adjacent to the Project area making permanent note and record of such existing damage such as cracks, sags or other similar damage. This record shall serve as a basis for determination of subsequent damage to structures, conditions or other existing improvements due to Contractor s operations. All parties making the survey shall sign the official record of existing damage. Cracks, sags or damage of any nature to the adjacent Project area, not noted in the original survey but subsequently noted, shall be reported immediately to Owner. E. The Contractor shall follow all city ordinances in force during the duration of this Contract. F. It is essential that the Contractor perform the Work with as little interference and disturbance as possible to the surrounding neighborhood. Summary of Work 01 11 00-2

G. When suspect materials, outside the scope of Work, are encountered during the Work or restoration process, the Contractor shall immediately contact the Project Manager for evaluation and approval of the methods for dealing with the material. PART 2 PRODUCTS- NOT USED PART 3 EXECUTION NOT USED END OF SECTION Summary of Work 01 11 00-3