PROGRESS REPORT MA RCH 2 019
SCOPE The scope of this document covers the all activities and the relevant tests and studies conducted to foresee the progress of The Gardens project, identify the problems and to analyze the project progress. TASK DESCRIPTION AREA (m3 ) Approx. Basement floor Common area & Parking area 1,619 Ground floor Maintenance store & office, Utility panel room, Staff mess, Kitchen, Indoor & outdoor cafe, Mini mart, Parking 1,633 Level 1 Commercial space, Utility space & Toilets 1,466 Level 2 Level 3 Commercial space, Garden Villa (1,2,3 ), Swimming pool-01, Changing room, Kids pool-01, Gym, Stores, Kids play area, Garden Garden Suite Apartments (1,2,3 ), Garden villa Apartments (1,2,3,4,5,6) Total 09 Nos Apartments, 04 Nos of plunge pools 1,466 1,418 Level 4 Villa Apartments (1,2,3,4,5,6), Suite Apartments (1,2,3,) Total 08 Nos Apartments,03 Nos of plunge pools 1,280 Level 5 Villa Apartments (1,2,3,4,5,6), Suite Apartments (1,2,3) Total 08 Nos Apartments,03 Nos of plunge pools 1,280 Level 6 Villa Apartments (1,2,3,4,5,6), Suite Apartments (1,2,3) Total 08 Nos Apartments,03 Nos of plunge pools 1,280 Level 7 Villa Apartments (1,2,3,4,6), Suite Apartments (1,2,3) Total 08 Nos Apartments,03 Nos of plunge pools 1,280 Level 8 Villa Apartments (1,2,3,4,6), Suite Apartments (1,2,3) Total 08 Nos Apartments,03 Nos of plunge pools 1,280 Level 9 Villa Apartments (1,2,3,4,5), Suite Apartments (3,4,5) Total 08 Nos Apartments,03 Nos of plunge pools 1,428 Level 10 Pent House Villa Apartments ( 1,2,3,4,5,), Sky Suite Apartments (1,2) Suite Apartment (3) Total 08 Nos Apartments,,07 Nos of plunge pools 1,352 Level 11 Sky suit Apartment (1,2 ), Open terrace, 02 Nos. Common pools including kids pool,01 Nos plunge pool 1,123 Roof terrace BBQ area, Open terrace, Kids play area, 01 Kids pool & 02 Common Swimming pool 1,123 17,562
PROJECT LAYOUT AND THE PLANS MASTER PLAN OF TYPICAL FLOORS
NOTES: PROJECT LAYOUT AND THE PLANS B C E F H K M O Q S U Z 3075 3079 3560 1650 3875 3855 3 3128 4540 4875 3741 4460 3360 B12 6935 B12 1240 3200 1375 3100 1400 2880 7930 B4 2550 B4 6078 4710 1860 7077 B4 CB4 800 [2'-7"] 2355 CB5 3800 1550 CB4 0 650 850 1300 1000 1 1300 1145 B4 B4 B4 B4 B4 B4 B4 1165 1065 1215 CB1 CB1 CB1 CB3 CB3 CB3 CB3 CB1 250 225 200 364 1000 CB3 200 50 0 1 CB1 B1 B1 B1 B1 B1 B1 B5 B5 1 850 B12 B12 B1 B1 200 1190 550 500 125 3261 B2 B1 B4 B4 B4 3750 B9 B1 2 B1 B1 B1 B1 B1 B1 B1 1225 6151 CB1 B6 B6 8276 200 550 550 200 200 650 1370 5 6 8 12 14 16 17 18 19 20 21 22 561 3575 686 620 1065 802 868 1194 868 4720 2786 1054 3837 1451 B1 B2 CB1 1000 CB1 B9 B1 CB1 B4 B1 995 100 100 B6 B12 400 3600 CB4 2355 1200 [3'-11"] 5646 B12 203 B10 B9 768 1842 1435 CB4 985 1200 VOID B6 B6 4411 1475 350 702 B3 B3 B3 B3 1189 1475 1402 178 1375 2576 200 B6 B6 4000 4188 B9 100 200 B3 B3 B6 B5 B5 B5 3962 1000 200 2000 100 B3 B3 1175 B4 2000 650 B3 2500 VOID B6 B3 LIFT VOID 200 STAIR VOID B5 LIFT VOID LIFT VOID 2025 B6 2675 B1 VOID VOID STAIR VOID 1715 2064 1000 1717 B2 LIFT VOID 650 575 1027 200 1725 1100 2025 2935 1362 B2 855 550 1362 855 B2 B2 B2 B2 VOID VOID VOID VOID VOID B6 550 B6 B8 B8 B8 B8 B8 1000 1594 175 2350 550 1715 3473 1010 6200 B5 975 1155 200 B1 B1 B12 VOID 550 CB2 CB2 2081 2355 1445 174 280 529 1200 1100 200 811 3065 B12 1010 8438 3600 CB4 400 CB4 1135 2500 1725 2600 720 968 1260 1000 175 192 250 1260 1681 1010 1000 200 1100 1825 1715 1250 737 1069 B2 B2 1267 1267 B2 B1 1200 970 970 B5 1125 B1 B2 B1 444 200 B1 2305 550 B5 B5 B5 B5 B5 1490 550 B1 B1 1225 B1 650 B1 250 1225 1300 2513 2204 3750 1355 2205 306 11555 300 2205 798 715 773 5228 1132 2368 713 1687 2597 1645 800 618 670 3 4 7 9 15 22 23 No. Revision/Is GOOD CONSTRUCTIO Project Title : PROPOSED MI DEVELOPMEN HULHUMALE'. THE GARDEN Dwg. Title : Owner JAAH INVESTM 3523 3610 3215 3648 400 1283 3651 4325 4361 5675 3335 3065 3365 3960 1475 3333 3664 1305 1971 3741 3360 STRUCTURAL ELEMENTS OF TYPICAL FLOORS A D E G J L N P R W Z 3rd Floor, H. Mialani, Sosun Magu, Male Rep. of Maldives, Tel: (960)32 4959, (9 EMRil: tekton@tektondesign.com.mv, All designs are property of Tekton No part of this drawing shall be re their written permission. Do not sc are indicative, and must be confirme NOTE 100MM THICK RCC WALL 100MM THICK TURN DOWN SLAB Architect/Designer : ALI SHAREEF T Struct. Engineer : ASHRAF Drawn : THOMAS
PROJECT PROGRESS - INDIRECT WORKS Success arrangement of indirect works always supporting to boost up the Permanent/Direct works as it is providing basic and essential infrastructure of the permanent works. TASK PLANNED START PLANNED FINISH ACTUAL As @ 31/3/19 ACTUAL FINISHED REMARKS Installation of Temporary CCTV System 11/06/2018 20/06/2018 55% PENDING On Going Perimeter Scaffolding & Safety Net Arrangement 24/02/2019 04/07/2019 50% PENDING On Going
PROJECT PROGRESS PERMANENT WORK TASK PLANNED START PLANNED FINISH ACTUAL As @ 31/3/19 ACTUAL FINISHED REMARKS Fabrication & Fixing of Form Work Beams L06 26/02/2019 10/03/2019 100% 10/03/2019 Fabrication & Fixing of Form Work Slab L06 27/02/2019 10/03/2019 100% 10/03/2019 Cutting, Bending & Fixing of Reinforcement Beams L06 Cutting, Bending & Fixing of Reinforcement Slab L06 Floor Conduit Laying for Fire, Power & Lighting (L6 Slab) 03/03/2019 04/03/2019 100% 04/03/2019 04/03/2019 09/03/2019 100% 09/03/2019 06/03/2019 10/03/2019 100% 10/03/2019 Concrete Pouring Slab & Beams L06 11/03/2019 11/03/2019 100% 11/03/2019 Fabrication & Fixing of Form Work Staircase L5 L6 Cutting, Bending & Fixing of Reinforcement Staircase L5 L6 27/02/2019 09/03/2019 100% 09/03/2019 03/03/2019 09/03/2019 100% 09/03/2019 Concrete Pouring Staircase L5 L6 11/03/2019 11/03/2019 100% 11/03/2019 Cutting, Bending & Fixing of Reinforcement Column L6 L7 Fabrication & Fixing of Form Work Column L6 L7 11/03/2019 17/03/2019 100% 17/03/2019 13/03/2019 17/03/2019 100% 17/03/2019 Concrete Pouring Column L6 L7 14/03/2019 18/03/2019 100% 18/03/2019
PROJECT PROGRESS PERMANENT WORK TASK PLANNED START PLANNED FINISH ACTUAL As @ 31/3/19 ACTUAL FINISHED REMARKS Fabrication & Fixing of Form Work Lift Walls L7 L6 11/03/2019 17/03/2019 100% 17/03/2019 Cutting, Bending & Fixing of Reinforcement Lift Walls L6 L7 13/03/2019 17/03/2019 100% 17/03/2019 Concrete Pouring Lift Walls L6 L7 14/03/2019 18/3/2019 100% 18/3/2019 Fabrication & Fixing of Form Work Beams L07 17/03/2019 24/03/2019 100% 24/03/2019 Fabrication & Fixing of Form Work Slab L07 17/03/2019 24/03/2019 100% 24/03/2019 Cutting, Bending & Fixing of Reinforcement Beams L07 Cutting, Bending & Fixing of Reinforcement Slab L07 Floor Conduit Laying for Fire, Power & Lighting (L7 Slab) 20/03/2019 26/03/2019 100% 26/03/2019 20/03/2019 26/03/2019 100% 26/03/2019 20/03/2019 26/03/2019 100% 26/03/2019 Concrete Pouring Slab & Beams L07 27/03/2019 27/03/2019 100% 27/03/2019 Fabrication & Fixing of Form Work Staircase L6 L7 Cutting, Bending & Fixing of Reinforcement Staircase L6 L7 17/03/2019 24/03/2019 100% 24/03/2019 20/03/2019 26/03/2019 100% 26/03/2019
PROJECT PROGRESS PERMANENT WORK TASK PLANNED START PLANNED FINISH ACTUAL As @ 31/3/19 ACTUAL FINISHED REMARKS Concrete Pouring Staircase L6 L7 27/03/2019 27/03/2019 100% 27/03/2019 Cutting, Bending & Fixing of Reinforcement Column L7 L8 Fabrication & Fixing of Form Work Column L7 L8 28/03/2019 03/04/2019 50% On Going 31/03/2019 03/04/2019 00% PENDING Concrete Pouring Column L7 L8 01/04/2019 04/04/2019 00% PENDING Fabrication & Fixing of Form Work Lift Walls L8 L7 28/03/2019 03/04/2019 00% PENDING Cutting, Bending & Fixing of Reinforcement Lift Walls L7 L8 31/03/2019 03/04/2019 00% PENDING Concrete Pouring Lift Walls L7 L8 01/04/2019 04/04/2019 00% PENDING
TOTAL PROGRESS 38%
PROGRESS PHOTOS
COLUMN HEAD KICKER PREPARATION (L6)
BEAM FORM WORK (L6)
BEAM REINFORCEMENT WORK (L6 SLAB)
BEAM REINFORCEMENT WORK (L6 SLAB)
SLAB FORM WORK (L6)
SLAB FORM WORK (L6)
SLAB REINFORCEMENT WORK (L6)
SLAB REINFORCEMENT WORK (L6)
ELECTRICAL & FIRE CONDUIT LAYING WORK (L6)
SLAB DROP PREPARATION WORK (L6)
STAIRCASE FORM WORK (L5 - L6)
STAIRCASE REINFORCEMENT WORK (L5 - L6)
CONCRETE PIPE LINE ARRANGING (L6 SLAB)
CONSULTANT SITE INSPECTION (L6 SLAB)
CONSULTANT ARCHITECT S SITE INSPECTION (L6 SLAB)
CONCRETE POURING (L6 SLAB)
CONCRETE POURING (L6 SLAB)
CURING WORK (L6 SLAB)
CURING WORK (L6 SLAB)
COLUMN SETTINGOUT WORK (L6 L7)
COLUMN SETTINGOUT WORK (L6 L7)
COLUMN KICKER PREPARATION (L6 L7)
COLUMN KICKER PREPARATION (L6 L7)
COLUMN REINFORCEMENT WORK (L6 L7)
COLUMN FORM WORK (L6 L7)
COLUMN CONCRETE WORK (L6 L7)
LIFT WALLS REINFORCEMENT WORK (L6 L7)
LIFT WALLS FORM WORK (L6 L7)
LIFT WALLS FORM WORK (L6 L7)
COLUMN & WALLS CURING WORK (L6 L7)
BEAM FORM WORK (L7)
BEAM REINFORCEMENT WORK (L7)
STAIRCASE FORM WORK (L6 - L7)
SLAB FORM WORK (L7)
SLAB REINFORCEMENT WORK (L7)
CONCRETE PIPE LINE ARRANGING (L7 SLAB)
CONCRETE POURING WORK (L7 SLAB)
CONCRETE POURING WORK (L7 SLAB)
CURING WORK (L7 SLAB)
ERRECTION OF PERIMETER SCAFFOLDING SYSTEM
ERRECTION OF PERIMETER SCAFFOLDING SYSTEM
PLANNED WORK FOR MONTH OF APRIL 2019 TASK PLANNED START PLANNED FINISH CURRENT PROGRESS (%) PLANNED PROGRESS (%) Fixing of CCTV Cameras 19/08/2018 06/09/2018 55% 100% Perimeter Scaffolding & Safety Net Arrangement 24/02/2019 04/07/2019 50% 65% Cutting, Bending & Fixing of Reinforcement Column L7 L8 28/03/2019 03/04/2019 50% 100% Fabrication & Fixing of Form Work Column L7 L8 31/03/2019 03/04/2019 00% 100% Concrete Pouring Column L7 L8 01/04/2019 04/04/2019 00% 100% Fabrication & Fixing of Form Work Lift Walls L7 L8 28/03/2019 03/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Lift Walls L8 L7 31/03/2019 03/04/2019 00% 100% Concrete Pouring Lift Walls L7 L8 01/04/2019 04/04/2019 00% 100% Fabrication & Fixing of Form Work Beams L08 02/04/2019 16/04/2019 00% 100% Fabrication & Fixing of Form Work Slab L08 06/04/2019 16/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Beams L08 02/04/2019 15/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Slab L08 11/04/2019 15/04/2019 00% 100% Floor Conduit Laying for Fire, Power & Lighting (L8 Slab) 14/04/2019 16/04/2019 00% 100%
PLANNED WORK FOR MONTH OF APRIL 2019 TASK PLANNED START PLANNED FINISH CURRENT PROGRESS (%) PLANNED PROGRESS (%) Concrete Pouring Slab & Beams L08 17/04/2019 17/04/2019 00% 100% Fabrication & Fixing of Form Work Staircase L7 L8 02/04/2019 16/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Staircase L8 L7 02/04/2019 15/04/2019 00% 100% Concrete Pouring Staircase L7 L8 17/04/2019 17/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Column L8 L9 18/04/2019 21/04/2019 00% 100% Fabrication & Fixing of Form Work Column L8 L9 18/04/2019 21/04/2019 00% 100% Concrete Pouring Column L8 L9 19/04/2019 22/04/2019 00% 100% Fabrication & Fixing of Form Work Lift Walls L8 L9 18/04/2019 21/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Lift Walls L9 L8 18/04/2019 21/04/2019 00% 100% Concrete Pouring Lift Walls L8 L9 19/04/2019 22/04/2019 00% 100% Fabrication & Fixing of Form Work Beams L09 21/04/2019 28/04/2019 00% 100% Fabrication & Fixing of Form Work Slab L09 23/04/2019 30/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Beams L09 24/04/2019 30/04/2019 00% 100%
PLANNED WORK FOR MONTH OF APRIL 2019 TASK PLANNED START PLANNED FINISH CURRENT PROGRESS (%) PLANNED PROGRESS (%) Cutting, Bending & Fixing of Reinforcement Slab L09 25/04/2019 30/04/2019 00% 100% Floor Conduit Laying for Fire, Power & Lighting (L9 Slab) 28/04/2019 01/05/2019 00% 80% Concrete Pouring Slab & Beams L09 02/05/2019 02/05/2019 00% 00% Fabrication & Fixing of Form Work Staircase L8 L9 21/04/2019 28/04/2019 00% 100% Cutting, Bending & Fixing of Reinforcement Staircase L9 L8 24/04/2019 30/04/2019 00% 100% Concrete Pouring Staircase L8 L9 02/05/2019 02/05/2019 00% 00%
ASSIGNED MAJOR PLANT, MACHINERIES AND EQUIPMENTS DESCRIPTION UNIT QTY Concrete Pump Car/ Static Pump Set 01 Tower Crane Nos 01 Diesel Concrete/ Mortar Mixture Nos 02 Kva/ 120Kw Diesel Generators Set 02 2.3 Kva Portable Generator Set 01 Steel Bar Bending Machine TB42 Set 02 Steel Bar Cutter Machine GQ45E Set 01 Digital Stirrup Bender TW22 Nos 02 Gasoline Plate Rammer ZBR755 Nos 01 Gasoline Tamping Rammer HRC Nos 03 Gasoline Concrete Vibrator Nos 06 DESCRIPTION UNIT QTY SUBMERSIBLE PUMP 3" Nos 06 Petrol Water Pump 3" Nos 02 Timber Saw Machine Set 01 MG 2500S Dumpy Level Set 02 GM 101 Total Station Set 01 Portable Rebar Cutter Rc22 Nos 02 Portable Rebar Cutter Rc16 Nos 04 High Pressure Water Gun Set 01 Vacuum Cleaner Set 01 Welding Plant 400A 3Phase Set 01 Welding Plant 315A 3Phase Set 02 Concrete Vibrate Motor ZN70A Nos 03 Fogging Machine Nos 01 Submersible Pump 4" Nos 06
MILESTONES
MOBILIZATION TASK BASELINE ACTUAL % Receipt of Letter of Acceptance 21/11/2017 21/11/2017 100% Receipt of Site Possession and Access to the Site 21/11/2017 21/11/2017 100% Site Office & Accommodation Establishment 29/01/2018 30/04/2018 100% Establishment of Water & Electricity Supply. 07/12/2017 31/12/2017 100% Establishment of Standby Power Supply by Generators (300 kva). 07/12/2017 21/04/2018 100% Installation of Batching Plant. 01/02/2018 09/04/2018 100% Installation of Tower Crane. 04/03/2018 17/05/2018 100% Fixing of Site Fence including Main Gate and Sign-age 13/12/2017 10/08/2018 100% Functioning of the Site Kitchen N/A 01/04/2018 100% Functioning of the Site Main Store N/A 31/03/2018 100%
SUBSTRUCTURE TASK BASELINE ACTUAL % Commencement of Permanent Works 28/01/2018 28/01/2018 100% Completion of Sheet Pilling 20/02/2018 16/02/2018 100% Completion of Excavation 06/03/2018 24/03/2018 100% De-Watering Completion 25/04/2018 04/02/2019 100% Completion of Screed Concrete 10/03/2018 28/06/2018 100% Completion of Water Proofing in Basement including R/Wall 05/07/2018 20/11/2018 100% Completion of Raft Foundation RC Work (Basement Level) 25/04/2018 16/08/2018 100% Completion of Retaining Wall RC Work 24/05/2018 15/09/2018 100% Removing of Sheet Piles 10/06/2018 16/02/2019 80% Completion of Ground Level RC Work 30/05/2018 19/10/2018 100%
SUPERSTRUCTURE TASK BASELINE R1 ACTUAL % Completion of Level 01 RC Work 11/11/2018 22/11/2018 100% Completion of Level 02 RC Work 05/12/2018 19/12/2018 100% Completion of Level 03 RC Work 27/12/2018 13/01/2019 100% Completion of Level 04 RC Work 14/01/2019 02/02/2019 100% Completion of Level 05 RC Work 01/02/2019 21/02/2019 100% Completion of Level 06 RC Work 19/02/2019 11/03/2019 100% Completion of Level 07 RC Work 09/03/2019 30/03/2019 100% Completion of Level 08 RC Work 27/03/2019-0% Completion of Level 09 RC Work 14/04/2019-0% Completion of Level 10 RC Work 02/05/2019-0% Completion of Level 11 RC Work 20/05/2019-0% Completion of Terrace Level RC Work 07/06/2019-0% Completion of Above Terrace Level RC Work 19/06/2019-0%
SITE SAFETY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 NO ACCIDENT MINOR ACCIDENT MAJOR ACCIDENT FATAL ACCIDENT
DELAYS IN HIGH CONCERN TASK PLANNED DATE ACTUAL DATE DELAY (DAYS) REMARKS Construction Land Handing over -HDC 1-May-17 31-Oct-17 183 Temporary Land Handing over - HDC 31-Oct-17 21-Nov-17 21 Confirmation of Building line by HDC 31-Oct-17 21-Nov-17 21 Excavation below Ground level 9-Jan-18 28-Feb-18 50 Delayed surveying works by HDC. Effected to starting of Mobilization Shifted building line to front side due to lack of working space. Effected to starting of excavation. Delayed confirmation of boundary line by the HDC Workers Visa Approval 28-Feb-18 5-Apr-18 36 Delays of visa processing by the Maldives immigration for Indian expat. Required days in Normal condition 5 days Tower Crane Installation 05-May-18 5-Jun-18 31 Delays of Business visa arranging for installation team due to processing delays in Maldives immigration. Required days in normal condition - 5 Working days
DELAYS IN HIGH CONCERN TASK PLANNED DATE ACTUAL DATE DELAY (DAYS) REMARKS Workers Visa Approval & Custom Clearances Etc. 15-May-18 5-Jun-18 20 Ramadan Festival Adverse Weather Condition 1-May-18 31-May-18 13 Continuous Rains with heavy Winds (Refer weather Records ). Mechanical Problem in the Custom/ Ship Crane Workers Visa Approval delayed due to SL Embassy official visit and the facility observation 09 20-May-18 7-Jun-18 17 Steel shipment #02 delayed in the Custom clearance due to breakage of the Ship s Crane. Attestation hold until Sri Lanka embassy official visit and the facility observation on the Site. Adverse Weather Condition June 18 1-June-18 30-June- 18 05 Continuous Rains with heavy Winds (Refer weather Records). Effected to Water proofing work. Adverse Weather Condition July 18 1-July-18 31-July-18 08 Adverse Weather Condition Sep 18 1-Sep-18 30-Sep-18 02 Continuous Rains with heavy Thundering (Refer weather Records). Effected to Water proofing & RF works. Continuous Rains with heavy Winds (Refer weather Records). Effected to Form works.
DELAYS IN HIGH CONCERN TASK PLANNED DATE ACTUAL DATE DELAY (DAYS) REMARKS Adverse Weather Condition Oct 18 1-Oct-18 31-Oct-18 09 Adverse Weather Condition Nov 18 1-Nov-18 30-Nov-18 10 Adverse Weather Condition Dec 18 31-Dec-18 02 Continuous Rains with heavy Winds (Refer weather Records). Effected to Form work & Reinforcement work. Continuous Rains (Refer weather Records). Effected to Form work & Reinforcement work. Continuous Rains (Refer weather Records). Effected to Structural work.
RAIN FALL REPORT
798 7733 info@jaahinvestments.mv www.thegardens.mv