US 69 RELIEF ROUTE STUDY

Similar documents
Lubbock Outer Route Feasibility Study Report Executive Summary

I-69 Angelina and Nacogdoches Counties Scoping Study Executive Summary

Texas State Highway 130 Proposed Routes

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

1RUWKZHVW#:LFKLWD 0DMRU#,QYHVWPHQW#6WXG\

SUPPLEMENTAL DRAFT ENVIRONMENTAL IMPACT STATEMENT NORTH BELT FREEWAY SUMMARY INTRODUCTION

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING MAY 25, 2017

U S H I G H W A Y 1 4 F I N A L E N V I R O N M E N T A L I M P A C T S T A T E M E N T ( F E I S

LOOP 9 SOUTHEAST WELCOME TO THE LOOP 9 CORRIDOR/FEASIBILITY STUDY. Presentation 6:30 p.m. to 7:00 p.m.

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

PUBLIC HEARING LOOP 9

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT

HIGHWAY 71 CORRIDOR IMPROVEMENT STUDY BELLA VISTA BYPASS MISSOURI STATE LINE BENTON COUNTY

12 Evaluation of Alternatives

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011

Outer Loop/Rail Bypass Study

TABLE OF CONTENTS. Section Section 2 Alternative A...7 Section 2 Alternative B...7

Sunrise Project South I-205 Corridor Improvement Project

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination

Interchange Justification Report (IJR) I-75 at Bethlehem Road Henry County

Chapter 2: Alternatives

Proposed Petone to Grenada Link Road Options

FASTLANE Grant Project US-69 through Calera. Oklahoma Traffic Engineering Association 2017 Fall Meeting

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

Table 2.3 Alternatives Considered by the ACT Interstate 73 EIS: I-95 to the Myrtle Beach Region

SUMMARY S.1 PROJECT DESCRIPTION AND LOCATION S.2 PURPOSE AND NEED

I-10 CONNECT. Public Meeting #1

Welcome to the Public Information Centre. Red Hill Business Park South Transportation Master Plan Addendum. June 25, :00 p.m. to 8:00 p.m.

I-70 East PACT DRAFT EVALUATION DATA

REQUEST FOR PROPOSAL KIPDA REGIONAL FREIGHT PLAN MARCH 30, 2018

LOCATION HYDRAULIC REPORT

REVIEW OF RURAL TRANSPORTATION AND CONNECTIVITY INITIATIVES

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

SH 34 Corridor Study & Environmental Assessment:

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA

Community Advisory Committee Meeting No. 2. June 22, 2006

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting.

INTERSTATE CORRIDOR PLANNING

MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia May 8,

D R A F T. SECTION 4(f) EVALUATION. INTERSTATE 73 From I-95 to the Myrtle Beach Region

Initial Alternative One: No Build

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District

Interchange Workshop Report (August 2004)

PARLEY S INTERCHANGE. I-80 /I-215 Eastside WELCOME. Parley s Interchange EIS. Public Scoping Meeting. March 6, :00pm 7:00pm

Project Prioritization for Urban and Rural Projects TEAM CONFERENCE March 7, 2018

Purpose of the Public Hearing

State Route 8 Bridge Replacement Project

2. Alternatives ENVIRONMENTAL ASSESSMENT US 52 OPERATIONAL IMPROVEMENTS. 2.1 Introduction

Ports to Plains Feasibility Study

Blacklands Corridor Feasibility Study

DRAFT. Draft Carbon Monoxide (CO) Traffic Air Quality Analysis

US 377 CRESSON RELIEF ROUTE

THIS PAGE INTENTIONALLY LEFT BLANK

Chapter 9: Vision Plan. Chapter 9. Vision Plan. Lake Loveland. Image 179 Credit: City of Loveland

ROUTE FEASIBILITY STUDY. PUBLIC MEETING January 26, 2010

<33 February OMF South Alternatives Evaluation Technical Memorandum

Current Trends in Traffic Congestion Mitigation

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting

APPENDIX H NEPA TRANSITION REPORT

ROGERSVILLE PROJECT FREEWAY: Progressive Right-of-Way and Partnering for Success

FHWA s Eco-Logical Process: Uses in Performance-Based planning

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

Request for Proposals and Bids for Civil Engineering Services for Off-site Improvements for a Residential Neighborhood

Charlottesville Albemarle MPO:

Derry-Londonderry I-93 Exit 4A Public Officials/Information Meeting

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.

Chapter 6 Freight Plan

I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY)

9.0 I-26 & I-526 Interchange Improvements

Appendix C Presentation Slides with Script

Conceptual Design Report

HILLSBOROUGH COUNTY METROPOLITAN PLANNING ORGANIZATION

CHAPTER 26. SAN RAMON VALLEY FIRE PROTECTION DISTRICT ANNEX

Rail Division 2012 Annual Summary

HIGHWAY 412 EXECUTIVEXECUTIVE SUMMARYUMMARY FINAL ENVIRONMENTAL IMPACT STATEMENT. Benton and Washington Counties. October 2005

vi Figures viii Summary S.1

NORTH I-75 MASTER PLAN Summary Report

Blacklands Corridor Feasibility Study. Public Meeting March 20, 2014 Fletcher Warren Civic Center Greenville, TX

Public Meeting. US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County

Transportation Investment Act (TIA) Industry Forum for Batch 3 Design Advertisement. August 22, 2014

M D 355 [FR E D E R IC K R O A D] OVER

METROPOLITAN PLANNING ORGANIZATION FOR THE MIAMI URBANIZED AREA BLOCKS RIBBONS EXERCISE

South County Traffic Relief Effort (SCTRE) Draft Project Study Report (PSR)-Project Development Support (PDS)

Section 7 Environmental Constraints

State Highway 10A Improvements (from the SH-10 junction extending 6.18 miles east to the SH-100 junction, Muskogee and Sequoyah Counties, Oklahoma)

Kentucky River Area Development District

Final Air Quality Report

EIGHT PLANNING FACTORS

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

2004 FEASIBILITY STUDY UPDATE

PUBLIC HEARING US 69 WIDENING. Phase 1 (IH-10 to LNVA Canal) Phase 2 (LNVA Canal to Tram Road) Jefferson County, Texas

Shoulder Widening Prioritization Discussion

Willmar Wye Public Open House #4 and Public Hearing

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Transcription:

US 69 RELIEF ROUTE STUDY Jacksonville, Texas PUBLIC MEETING #3 August28 th 2018 1 Welcome to the final public meeting for the US 69 Relief Route Study in Jacksonville. This presentation will give a recap of the information that was presented at previous public meetings held on February 22 nd and May 29 th of 2018,as well an overview of the process considered to determine recommended corridors. 1

Purpose and Need NEED: US 69 is inadequate to meet current and future traffic volumes Increased travel times Reduced mobility Texas Highway Freight Network High crash rate Increased congestion and decline in efficiency during hurricane evacuations PURPOSE: Improve safety Enhance freight mobility Reduce travel time Increase mobility Improve the overall Level of Service Facilitate efficient hurricane evacuation 2 An early task for the project was the development of the purpose and need for a US 69 relief route. We found that US 69 is inadequate to meet the current and future traffic volumes. In the 200 miles between Tyler and Beaumont, there are 27 traffic signals on US 69 and almost a third of them, 8, are in Jacksonville. The most congested of these 8 intersections, at Loop 456, US 79 and SH 135, are operating with severe congestion The Jacksonville area is projected to have 30% population growth between 2010 to 2040, and traffic is expected to increase similarly. Additionally, US 69 is on the Texas Highway Freight Network and is expected to see an increase in truck traffic in the future In downtown Jacksonville, the crash rate along US 69 is up to 65% higher than statewide average. The purpose of the US 69 relief route will be to increase safety by reducing crashes, give through truck traffic along US 69 an alternate route around Jacksonville, instead of forcing the trucks through downtown, reduce congestion through Jacksonville, and in turn reduce the travel time and increase mobility and make hurricane evacuation through Jacksonville more efficient. 2

Universe of Alternative Corridors 3 At the second public meeting held on May 29 th, 2018, the study team presented a map of the alternative corridors. That map, with all of the alternative corridors, is shown here. At the meeting, the study team answered questions and gathered comments to the study. Additionally, people were encouraged to highlight their preferred route, if they had one, and submit that as a comment to the study team. 3

TRAFFIC ANALYSIS Truck Traffic Truck Traffic on Relief Route Western Alternatives 700 trucks 575 125 1,050 trucks 950 100 900 trucks 25 875 No Improvements Relief Route Projection 4 As a part of our traffic analysis, we looked at the number of trucks that would potentially use the relief route, and in doing so, reduce the number of trucks driving through downtown on US 69 Looking at the projected traffic for 2040, the left side shows the total number of trucks, including both northbound and southbound traffic, that would be traveling through Jacksonville on US 69 if no relief route was built. If nothing is done we project 700 trucks per day using US 69 north of US 175, 1,050 trucks between US 175 and US 79, and 900 trucks south of US 79. If a relief route was constructed on the western side of Jacksonville, our projections show that 575 trucks per day would use the relief route from US 69 to US 175, with 125 still using US 69 From US 175 to US 79, 950 trucks would use the relief route, leaving 100 trucks using US 69 And from US 79 to US 69 to the south, 875 trucks would use the relief route, leaving only 25 trucks per day on US 69. 4

TRAFFIC ANALYSIS Truck Traffic Truck Traffic on Relief Route Eastern Alternatives 575 700 trucks 125 1,050 trucks 475 550 900 trucks 350 No Improvements Relief Route Projection 5 If a relief route was constructed on the eastern side of Jacksonville, our projections show that 575 trucks per day would use the relief route from US 69 to US 79, with 125 still using US 69 From US 175 to US 79, 475 trucks would still use US 69 And from US 79 to US 69 to the south, 550 trucks would use the relief route, leaving 350 trucks per day on US 69. 5

Factors Considered Meets All Aspects of Purpose and Need Potential Environmental Impacts Parks Cemeteries Affected Structures Cultural Resources Wetlands Floodplain Farm Soils Streams Hazardous Material Sites Historical Environmental Justice Public Opinion Cost 6 To help us determine if a corridor should be brought forward for further study in the next phase of the project, we scored the corridors using several factors. First, was whether or not the corridor met all aspects of the purpose and need Next, we looked at the potential environmental impact of each 1,000-foot corridor. These include potential impacts to: parks, cemeteries, residential and other structures, cultural resources, wetlands, floodplains, farmland, streams, hazardous material sites, potential historical sites and markers, and low income and minority population areas. Following that, we gauged public opinion based on comments that were submitted to the team, as well as tallying the preferred routes that were highlighted and submitted to the team. Finally, we looked at the potential construction costs for each corridor. We then ranked the corridors based on their scores in each of the four categories; purpose and need, potentially adverse environmental impacts, public opinion and construction cost. 6

Recommended Corridors 7 We averaged the rankings and made the determination that it is appropriate to bring the top two ranked corridors forward for further study. These two corridors are both on the west side of Jacksonville. They both tie-in to US 69 south of Craft, the turn north near Gum Creek. The two corridors diverge northwest of Jacksonville., with the southern corridor tying into US 69 near Love s Lookout, and the other recommended corridor tying into US 69 about 1.5 miles further north. We have also included the connection to US 69 along Loop 456. This connection would use the existing corridor and promote connectivity to the Loop east of US 69. In general, public opinion that was expressed during the May 29 th Open House comment periodwas evenly divided between western and eastern corridors. However, each of the western corridors better addressed the purpose and need for the project by enhancing freight mobility through the greater number of trucks forecasted to use the facility. The western corridors also better addressed the purpose and need through the greater facilitation of hurricane evacuation due to the connection to US 175. The recommended corridors both ranked at the top for the least amount of potentially adverse environmental impacts The combination of these factors is what brought these two corridors forward to be considered for further study. The corridors shown here, and in the exhibits in the main room, show 1,000-foot corridors. The 1,000-foot width is for this analysis only. As the project moves forward, analysis will be done on narrower alignments within the corridors, with a typical width of 400-feet. These alignments will be developed to avoid and minimize potential impacts. 7

Project Development Process We Are Here Route Study Schematic Design & Environmental Study (2-3 3 Years) Right-of of-way Acquisition, Utility Relocations, and Final Design (2-3 3 Years) Construction (3-5 5 Years) Purpose and Need Environmental Resources Corridor Option Locations Corridor Evaluation Public Input Possible Identification of Recommended Corridor(s) Build and No-Build/ Alternatives Analysis Schematic Development Environmental Effects Public Input Environmental Decision Offers and Negotiations with Property Owners Right-of-Way Acquisition Utility Relocations Detailed Design Plans, Specifications and Estimates Bid Ready Contract Award Construct Facility Open to Operations The Project Development Process timeline shown is approximate and based on available funding. 8 Following this meeting, the study team will prepare the final report. This report will serve as the conclusion for the route study phase of the project. The next stage would be the schematic design and environmental study. This phase can last from 2 to 3 years, and includes the preliminary design of the facility. Following environmental clearance of the project, assuming that funding is identified, the final design would begin. This phase, which also includes right-of-way acquisition and utility relocations, can take from 2 to 3 years. Once the facility has been designed, right-of-way is acquired and utilities are cleared, construction can begin. We estimate that construction of this facility would last from 3 to 5 years. 8

US 69 RELIEF ROUTE STUDY Jacksonville, Texas PUBLIC MEETING #3 August 28 th, 2018 9 This concludes the presentation. Thank you for attending the US 69 Relief Route Study public meeting. In the main room, you will find maps with the recommended corridors and project team members that can answer your questions. Each of the tables in the main room has the same information on it, so please go to whichever table you prefer. Please remember that comments to the project can be made via comment card or email. Have a safe and enjoyable evening. 9