Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

Similar documents
Specification for UDC Electrical Testing

DEMOLITION TRADE SPECIFICATION

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

WESTERN WATER DESIGN AND CONSTRUCTION GUIDELINES FOR SUBDIVISIONAL WORKS

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

WHS Management Plans

Specifications. Supply and Installation of the Electrical Distribution Network for the Warialda Truck Wash

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:

OHS Management of Contractors in Capital Works and Maintenance

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION 33 PROJECT PRELIMINARIES. Table of Contents

GENERAL SPECIFICATION FOR ELECTRICAL WORK

PS 02 PLANT AND EQUIPMENT

REFURBISHMENT DEMOLITION

Ergon Energy Corporation Limited. Specification for UDC Design RSD01. Specification RSD01 Ver 7. Ergon Energy Corporation Limited ABN

Corporate Policy and Procedure

Supervision Guideline for Apprentice Lineworkers (Distribution)

LOADING UNLOADING OPERATIONS

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

GENERAL REQUIREMENTS

CONSTRUCTION SPECIFICATION

Work Health and Safety Management Systems and Auditing Guidelines

Clean TeQ Sunrise Project

SPPL RFQ Ref No.: REPLACEMENT OF BALL FLOAT VALVE FOR WATER TRANSFER TANK AT SINGAPORE POOLS BUILDING

Microgeneration Installation Standard MIS 3006

Work Health & Safety Procedure

Memorandum of Understanding

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY

Constraints on how the Contractor Provides the Works

National self-insurer OHS management system audit tool. Version 3

Table of Contents. Project Agreement Schedule 14

Municipality of the District of Lunenburg POLICY

Tucson Electric Power Company Rules and Regulations

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17

ELECTRICAL EQUIPMENT IN HAZARDOUS AREAS (EEHA) COMPETENCY STANDARD

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3

APPENDIX 5 UNSW STANDARD PRELIMINARIES TABLE OF CONTENTS

Microgeneration Installation Standard MIS 3006

Temporary Watercourse Crossing: Culverts

CORPORATE STANDARD ROUTINE MINOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS

Supervision Guideline for Electrician to Lineworker Apprentices

Safety & Environmental Orientation Program for Contractors

SECTION MAINTENANCE OF EXISTING CONDITIONS

COUNTY OF SUTTER ENCROACHMENT PERMIT

Design Governance Rules BOP325.23

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue

Certificate in Electrical Power Engineering - Underground Cables at SCQF Level 5 ( ) Unit Handbook

GENERAL NOTES REQUIRED NOTES ON ALL PLANS

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

Town of Whitby Public Works Department

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING

WORK IN THE VICINITY OF UNDERGROUND ASSETS

PROJECT: SUPPLY TO BERRY ROAD APARTMENT - SUVA SCHEME: G43-13

GENERAL SPECIFICATION FOR ELECTRICAL WORK

CORPORATE STANDARD ROUTINE MAJOR WORKS DEVELOPERS AND ACCREDITED SUPPLIERS VERSION: 1.0

MGD 001. Guidance Document for MCS 001. Version 1.0

Railway Interface Planning Scheme Rules (RIPS Rules)

CONSTRUCTION SPECIFICATION FOR REMOVAL OF ELECTRICAL EQUIPMENT AND MATERIALS

Level 5 NVQ Diploma in Controlling Lifting Operations Planning Lifts (Construction)

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities

Health & Safety Plan DEMOLITION WORKS: No 2 Substation

Objectives and Task Analysis for a Professional Small Wind Energy System Installer

Apply for Crane Permit

MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE. (Effective 1 December 2017)

The safe management and control of Temporary Works

Specifications for Electrical Underground Distribution Systems from Overhead Transformation, Apartments & Condominiums

Building Control (Amendment) Regulations MBCA Guidance Document

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

National Supervision Guideline for Electrotechnology Apprentices

Adelaide Airport Limited

Level 2 Diploma in Electrical Power Engineering - Underground Cables ( )

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003)

Rail Safety Management Procedure General Engineering and Operational Systems Railway Track Signals - Detonators

Environmental Roles and Responsibilities

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Skill Set CPCSS00004 Provide Building Surveying Services for Residential Buildings up to Three Storeys

This document sets out the rules applicable to all contract companies and their personnel when working on a CF Fertilisers UK Limited (CF) site.

RYDE TOWN COUNCIL QUOTATION DOCUMENTATION TOWN MAP AND EVENTS POSTER

Guide for Loading and Unloading Concrete Pipes

Management Plan: Hazardous Materials Removal & Demolition

Appendix 3. POLICY & PROCEDURE No

STATE OF NORTH CAROLINA B DEPARTMENT OF ADMINISTRATION February 1, 2013 PURCHASE AND CONTRACT DIVISION A MARCH 8, 1995

ISO 9001:2015 ISO 14001:2015 OHSAS

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Please contact us if you would like a hard-copy of the Model Standing Offer, and we will mail you a copy.

TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP

University of Edinburgh. Engineering Services. Guidelines

ISO /TS 29001:2010 SYSTEMKARAN ADVISER & INFORMATION CENTER SYSTEM KARAN ADVISER & INFORMATION CENTER

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE

SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland

CEOP CONNECTION POLICY CONNECTION CHARGES. 1 July 2015

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW

Process for LV and HV connections activities under SPEN and ICP s DSR s

Property and Public Protection Plan

NP001.4 General Specification for Overhead Rural Residential Subdivisions

Auckland Transport Code of Practice 2013

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

Level 3 NVQ Diploma in Controlling Lifting Operations Supervising Lifts (Construction)

The Corporation of The City of London

Transcription:

Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification and scope of works required by this RFQ. Proponents are to read and fully understand Council s requirements and propose a response that fully satisfies the detailed requirements. Page 1 of 14

Table of Contents Table of Contents 2 1. Introduction 3 2. Scope of Works 3 3. General Requirements 5 4. Supply and Metering 9 5. Service Levels & Key Performance Indicators (KPI s) 11 6. Table of Attachments 12 Appendix 1 Site Photos of Warialda Truck Wash 12 Page 2 of 14

1. Introduction The Principal has is currently seeking quotations for the construction of the Level 1 electrical work for the Warialda Truck Wash. This Scope of Work provides information on the key details of the Principals requirements. Respondents may provide pricing for one, or all portions of the scope of work outlined below. The Principal is not obligated to accept Submissions from one Respondent only and will consider awarding a combination of contracts to Suppliers who are able to meet the Principals requirements. 2. Scope of Works The newly proposed Truck Wash will be located east of Warialda, adjacent to the newly proposed alignment for the Warialda High Productivity Vehicle (HPV) Route. The route will connect the Gwydir Highway, east of Warialda, to Warialda Road, north of Warialda. The Truck Wash location is shown in Figure 3.1 below. Photographs of the Truck Wash site are shown in the Appendix of this document. Figure 1 Proposed site cadastral locality map. The work carried out shall comprise the manufacture, supply, delivery, installation, testing, commissioning and maintenance of the Electrical Services for this project. Page 3 of 14

All work shall be carried out in accordance with the Specification, Drawings and such details and instructions as are issued by the Superintendent or his representative during the progress of the work. This Specification shall be read in conjunction with the Drawings, all of which are intended to be mutually explanatory. All work called for by the one even if not by the other, shall be fully executed. The Drawings and Specification show the general intent and do not necessarily show all equipment required to complete the electrical works. Minor items as used in normally accepted trade practice with installations of this type and which are not specifically mentioned, shall be included in the Tender and installation. 2.1 Investigation The contractor shall be responsible for ensuring that sufficient and adequate investigation is carried out for the Truck Wash design to meet the requirements of this specification. If, in the opinion of the contractor, insufficient information has been provided by the principal, the contractor shall arrange to carry out whatever additional investigation the contractor deems necessary. Where investigations have been carried out by the principal, Respondents shall be solely responsible for determining whether or not the principal s investigation is both satisfactory and adequate for the design of the works and for interpreting the results. If a Respondent is not satisfied with the principal s investigation, it shall include an allowance in its quoted price for any additional investigation the Respondent deems necessary. 2.2 Construction 2.2.1 In Scope The work includes but is not limited to the following main elements: Demolition, disconnection and removal. Liaison with DNSP and Energy Retailer for the installation of new pole mount transformer, HV cables and metering. Substation works to DNSP requirements. Page 4 of 14

Conduits and trenching for DNSP cables and Telecommunications Carrier cables. Mobile elevated work platforms. Lifting equipment such as crane, hoist and personnel lift. Underground utilities locating. Liaison with other trades. Maintenance Manuals. As-Installed Drawings. 2.2.2 Work In Other Trades Related work in connection with the Electrical Services (performed by other trades) includes the following: 2.2.2.1 By Main Contractor/Builder Coordination of all trades. Site facilities and ablutions. Disposal of spoil & rubbish from site. Storage space for tools and materials on site. Site temporary water and electrical services. Fixed elevated work platforms, scaffolding, edge protection and the like. 3. General Requirements 3.1 General This section outlines general requirements which are applicable to all sections of this specification and the works. 3.2 Standards and Regulations Conform to the latest editions of all standards and regulations. The following standards and regulations are always applicable: Page 5 of 14

BCA AS/NZS3000 AS CCM AS3008.1 AS3012 AS60529 AS/NZS3017 Building Code of Australia latest issue before commencement of the building design Wiring Rules Communication Cabling Manual for Telecommunications Systems For Electrical Cables For Construction and Demolition Sites For Degrees of Protection of Enclosures For Testing for Safety of Low Voltage Electrical Systems State Workplace/Occupational Health and Safety Legislation Electrical Safety Act and Regulations. All other relevant Acts and Regulations, Local Authority Requirements, Australian Standards and Codes having jurisdiction. 3.3 Quality of Materials and Workmanship All materials shall be new, of the best quality and of the class most suitable for the purpose specified. All equipment shall have a verified history of successful use in the commercial environment. No prototype equipment will be accepted. All work on the site shall be supervised by a competent tradesman supervisor who shall be present on site when requested by the Superintendent, for all phases of the project. A representative shall be nominated, who shall be present and responsible for the day to day running of the project. The entire electrical installation shall be executed by licensed, experienced tradesmen, and shall be completed in a neat and first-class tradesman-like manner to the satisfaction of the Superintendent. 3.4 Uniformity All fittings, accessories and equipment of the same type shall be of the same manufacture and catalogue number. 3.5 Manufacturer s Warranty Provide manufacturer s warranty agreements where applicable. Page 6 of 14

Complete all necessary documentation on the Owner s behalf. Include copies of warranties in the maintenance manuals. 3.6 Certification Certify that the works have been installed to the requirements of all applicable rules and regulations. 3.7 Electromagnetic Compatibility Ensure that the entire installation covered by this specification meets the Electromagnetic Compatibility requirements of the Australian Communications and Media Authority. 3.8 Site Conditions and Precautions Where shutdowns of systems are required: Provide the Superintendent and Owner with written notification at least 5 days in advance of the intended shutdown time. Keep each shutdown time to a minimum. For each shutdown, complete the works and ensure that the systems are fully operational prior to leaving the site for the day. Carry out the work in such a manner as to interfere as little as possible with other trades and persons having access rights. Ensure that normal access ways within the buildings are unobstructed. Check existing site services, both underground and overhead, prior to commencing work. Plan work practices based on these existing conditions to minimise risk and maximise workplace safety. Wherever possible locate all existing services prior to excavation or working on existing structures. 3.9 Access to Site No traffic access will be available to the general public at the proposed location of the new Truck Wash. Proposed HPV Route has not yet been fully constructed and will not be completed prior to the Page 7 of 14

completion of the Truck Wash concrete works. Current access to the site is via an unformed general vehicle track provided from the northern side of Gwydir Highway. Provision for pedestrians is not required. 3.10 Exclusion Zones Exclusion zones surrounding the work area will be delineated. Under no circumstances is any personnel or equipment to enter the exclusion zones without permission from the principal. 3.11 Packing Storage and Protection Plant equipment, apparatus, materials and parts shall be delivered to the site in as- new condition and properly packed and protected against damage due to handling or adverse weather or other circumstances. Arrange suitable storage areas for materials, plant and equipment. Storage shall be on purpose made racks, mounts, etc., to ensure no damage or deformation of items. Any items suffering damage in transit or whilst on site shall be rejected and replaced without cost to the Contract. 3.12 Setting Out The positioning of equipment as shown on the Drawings is approximate and diagrammatic only, and these Drawings shall not be used for exact setting out. Locations of all equipment shall be confirmed on site by means of a formal and documented process such as drawing mark up, dimensioning or onsite mark up with as a minimum the Superintendent and Contractor in attendance. This coordination process shall be the responsibility of the Contractor to organise and it shall be carried out prior to rough-in. 3.13 Clean Up At completion clean all electrical equipment to as-new condition. Remove all waste and debris on a continuous basis. Page 8 of 14

3.14 Practical Completion Practical Completion will be granted after the following is provided: Finalisation of all testing and commissioning Certification that the installation complies with the specified requirements and all applicable Statutes and Standards Authorities approval obtained as required Preliminary instruction on safe plant operation has been provided Critical defects have been rectified Operation and Maintenance Manuals and As-Installed drawings have been provided 4. Supply and Metering 4.1 Definitions & Abbreviations DNSP NER Distribution Network Service Provider National Electricity Rules 4.2 General Works are described within the attached documentation. All works are to be completed to the standards and guidelines of the DNSP. 4.3 Supply Supply will be to Network Standards 3 phase, 230/400V, 50Hz, 4 wire, MEN earth system. 4.4 Distribution Network Services Provider (DNSP) The DNSP is: Essential Energy DNSP Project Reference (i.e. Work Request) Number: 116218 4.5 Standards Comply with all regulations, standards and requirements of the Local Electricity Act & Regulations, DNSP requirements, local council and BCA. Page 9 of 14

4.6 HV/LV Substation The DNSP works are outlined within the tender forms as a part of this Level 1 specification these works will include the supply and install a HV Supply and provide a pole mount transformer rated at 100 kva. Liaise with the DNSP to ensure provision of all substation works and supply of electricity as required by the project program. The DNSP works include but not limited to the following: Incoming HV and LV cables Pole mount transformer This contractor shall supply and install the following for use by the DNSP: HV and LV connections, all to DNSP standards. Ensure all required inspections are carried out. Pole mount transformer foundations, paving, thresholds, access, retaining walls, earthing arrangement and any other works as required by the DNSP to enable installation of their pole mount substation transformer. Engage suitably qualified specialist contractors to perform the work as required by the local DNSP. 4.7 Applications Coordinate the actions required by all parties including owner, tenants, electricity retailer, metering provider and DNSP to ensure the electricity service and all required metering is installed to meet project timeframes. This includes The completion and lodgement of all application forms Lodging and managing the electricity application on the DNSP s online portal 4.8 Phase Rotation Check phase rotation with the DNSP and provide uniform phase rotation in the project cabling system. 4.9 Supply Shutdowns Co-ordinate all shutdowns of supply with the Customer (Owner) and DNSP. Arrange all shutdowns in advance (a minimum of 5 working days) so that alternative operational arrangements can be made. Keep supply shutdowns to a minimum. Page 10 of 14

Pay all costs associated with shutdown of supply. 4.10 Statutory Requirements 4.10.1 General The contractor shall comply with all the terms and conditions of any licence or permit obtained. 4.10.2 Environmental The contractor shall comply with the recommendations of any environmental reports. The contractor shall ensure erosion and sediment controls are in place throughout construction and are maintained after construction until the banks have stabilised, where disturbed by the contractor. The contractor shall prepare and implement a revegetation plan for all areas of soil disturbed or exposed as a result of the contractor s work, where applicable. Notwithstanding any other provision in this clause, the contractor shall carry out all operations in such a manner as to avoid or minimise damage to the environment and in compliance with the Review of Environmental Factors that can be provided by the Principal. 4.11 Project Timelines Respondents shall submit a proposed program of work with their Submission in Part 4. As a minimum, the program shall show the planned durations and details of the following activities: Investigation Mobilisation Construction Practical Completion Site Clean-Up 5. Service Levels & Key Performance Indicators (KPI s) This contract will be performance managed by the project manager during regular site inspections. Page 11 of 14

6. Table of Attachments The attached documents are provided to be read in conjunction with Part 3 to provide Respondents with complete detail relating to the requirements of the Submission. Attachment No. Attachment Title 1 17-1907 E001 - Legend, Notes, and Site Layout 2 17-1907 E002 - Electrical Reticulation 3 17-1907 E003 - Truck Wash Amenities 4 17-1907 E004 - Schematics Appendix 1 Site Photos of Warialda Truck Wash Figure 2 View of proposed site, taken from northern end looking south towards Gwydir Highway. Page 12 of 14

Figure 3 View of southern end of proposed site. Figure 4 View of HPV Route alignment, Truck Wash location left. Taken from southern end looking north. Page 13 of 14

END OF PART 3 Page 14 of 14