Part 4. Sidewalk Construction and Repair

Similar documents
Municipality of Waterville Public Sidewalk Repair Policy

Maintaining a Walkable Sacramento: SIDEWALK MAINTENANCE PROGRAM HANDBOOK

SECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

SIDEWALK CONSTRUCTION AND REPAIR

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines.

CITY OF WINDSOR STANDARD SPECIFICATIONS JULY 2012 S-31 KEYHOLE EXCAVATION TABLE OF CONTENTS

SECTION 10.0 PIPE TRENCHES Excavation and Preparation of Trench

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

Stanford University Facilities Design Guidelines SECTION STONE FINES PAVING. American Society for Testing and Materials.

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION CAST-IN-PLACE CONCRETE

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

Homeowner s Do-It Yourself Guide for Hazardous Sidewalks

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

Sidewalk Replacement Criteria The following are the criteria used to determine if sidewalk needs to be replaced in the City of Watertown:

CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES

FOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 3 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS

SECTION ASPHALT PAVING

SECTION RIGID PAVEMENT

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION ~ CURB AND SIDEWALK PART 1.00 ~ GENERAL

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

SECTION BITUMINOUS CONCRETE PAVING AND ATHLETIC SURFACING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

CHAPTER 11 - RESTORATION OF SURFACE IMPROVEMENTS

CHAPTER 904. Sidewalks, Curbs, Gutters, and Driveway Approaches

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

Paragraph Description Page No General Materials Concrete Masonry Work Altitude Valve Vault Cover 25-4

SECTION MINOR CONCRETE

Sidewalk Regulations. Table of Contents

CHAPTER 3 EXCAVATIONS

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

Allen & Sherriff Architects, Inc Yonge Street, S202, Richmond Hill, Ontario L4C 5K9 Tel: Fax: File Ref.

SECTION CONCRETE PAVING

Construction Specification 62 Grouted Rock Riprap

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL PART 2 - MATERIALS AND METHODS

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

CHANCEFORD TOWNSHIP, YORK COUNTY, PENNSYLVANIA ORDINANCE NO

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS. A. Formwork complete with shoring, bracing and anchorage.

SIDEWALK PROBLEMS AND REPAIR

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF MANITOWOC SECTION 500 PORTLAND CEMENT CONCRETE CONSTRUCTION 501 CONCRETE - GENERAL

Section CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.

Stanford University Facilities Design Guidelines SECTION ASPHALT UNIT PAVING. A. ASTM C-33 Standard Specification for Concrete Aggregates.

MONTEZUMA COUNTY COLORADO ROAD AND BRIDGE STANDARD SPECIFICATIONS

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

CITY OF LAWRENCE RESIDENTIAL DRIVEWAY PERMIT CHAPTER 16, ARTICLE 3, ADOPTED BY THE CITY COMMISSION ON JULY 10, 1996.

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

SECTION INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING

(D) Surface Slope Bituminous patch in front of the truncated domes must not exceed 5% measured perpendicular to the flow line or edge of roadway.

SECTION ASPHALT PAVEMENT

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS

SIDEWALKS, SHARED USE PATHS, AND DRIVEWAYS

CUT, RE SECTION VI. (Sub-section 290) Cut, Removal, and Replacement of Paved Surfaces. 1. Description Bituminous Pavements thru 290-2

Fence and Wall Requirements

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

SECTION 503 TEMPORARY PAVEMENT RESTORATION

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

GENERAL DESCRIPTION OF WORK CONSTRUCTION WITH EXTRUDING EQUIPMENT OPENINGS AND ALTERATIONS 6

CONSTRUCTION SPECIFICATION FOR KEYHOLE EXCAVATION AND PERMANENT REINSTATEMENT OF KEYHOLE CORES TABLE OF CONTENTS

SECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 850 CEMENT TREATED FREE DRAINING BASE APRIL 18, 2008

SECTION MORTAR

1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows:

SIDEWALK REPAIR GUIDE

CONCRETE PAVEMENTS GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 7 WATER RECLAMATION PROJECT JUNE 2013

CITY OF FARGO SPECIFICATIONS ASPHALT LEVELING COURSE

SECTION BITUMINOUS CONCRETE PAVING

ITEM 247 FLEXIBLE BASE

I. STREET CONSTRUCTION AND RECONSTRUCTION

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND SECTION 500 CONCRETE CONSTRUCTION 502 MATERIAL SPECIFICATIONS - GENERAL

CONSTRUCTION SPECIFICATION FOR BRICK GUTTER INDEX TS SCOPE...3 TS REFERENCES...3 TS DEFINITIONS...3

General Brick Installation Instructions

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section

Construction Specification for General Excavation

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION 14 EMBANKMENT

SECTION 3200 CONCRETE CURB AND GUTTER

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

Sidewalk Repair Program. Charter Township of Canton Engineering Services

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

DRIVEWAYS & CURB CUTS (INCLUDING DRIVEWAY EXTENSIONS) BUILDING PERMIT APPLICATION

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

SPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section CEMENT STABILIZED BASE COURSE. 1. Foundation course of cement stabilized crushed stone.

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK

SPECIAL SPECIFICATION 2042 Decorative Colored Pattern Concrete Paving

.1 Concrete mix shall be in accordance with the following:.1 The average of all tests shall exceed 25 MPa.

Zoning Permits 11-1 ZONING PERMITS

APPLICANT any person who makes application for a permit. BOROUGH Borough of Elizabethtown, Lancaster County, Pennsylvania.

Transcription:

Part 4. Sidewalk Construction and Repair 604.01. Permit Required. No sidewalk or curb and gutter shall be constructed on any street, alley, avenue, or other public property in this city without first having obtained a permit from the city council. Application for such permit shall be made on forms to be approved by the city council, and shall sufficiently describe the contemplated improvements, the contemplated date of the beginning of work, and the length and time of completion of the same, provided, that no permit shall be required for any such improvement ordered to be installed by the city. 604.02. Sidewalk Construction and Repair. Whenever the city council shall deem it necessary and expedient to construct or rebuild any sidewalk in the city, it may adopt a resolution to that effect, which resolution shall specify the place or places where such sidewalk shall be constructed or rebuilt, the kind and quality of materials to be used therein, the width, the size and manner of construction thereof, and the time within which the same shall be completed. The council shall hold a public hearing on the proposed improvement following two publications in the newspaper of a notice stating the time and place of the hearing, the general nature of the improvement, the estimated cost, and the area proposed to be assessed. The two publications shall be a week apart, and the hearing shall be at least 3 days after the last publication. The hearing may be adjourned from time to time, and a resolution ordering the improvement may be adopted at any time within 6 months after the date of the hearing by a vote of four-fifths of all members of the council; provided that where owners of not less than 35% of the property fronting petition for such improvement only a majority vote of council is necessary. The cost of any improvement, or any part thereof, may be assessed upon property benefitted by the improvement, whether the property abuts on the improvement, or not, based upon the benefits received. The area assessed may be less than, but may not exceed the area proposed to be assessed as stated in the notice of hearing on improvement. The city may pay such portion of the cost of the improvement as the council may determine from general ad valorem tax levies or from other revenues of funds of the city available for the purpose. At any time after a contract is let or the work ordered by day labor, the expense incurred in its making shall be calculated under the direction of the council. The council shall then determine by resolution the amount of the total expense the city will pay, other than the amount, if any, which it will pay as a property owner, and the amount to be assessed. Thereupon the clerk with the assistance of an engineer or other qualified person selected by the council shall calculate the proper amount to be specially assessed for the improvement against every assessable lot, piece or parcel of land without regard to cash valuation. The proposed assessment roll shall be filed with the clerk and be open to public inspection. The clerk shall thereupon under the council's direction, publish notice that the council will meet to consider the proposed assessment. Such notice shall be published in the newspaper at least once, not less than two weeks prior to such meeting of the council, and shall state the date, time, and place of such meeting, and general nature of the improvement, the area proposed to be assessed, and that written or oral objections will be considered. At such meeting, or at any adjournment thereof, the council shall hear and pass upon all objections to the proposed assessment, if any, and may amend the proposed assessment as to

any parcel and by resolution adopt the same as the special assessment against the lands named in the assessment roll. Notice of any adjournment of the hearing shall be adequate if the minutes of the meeting so adjourned show the time and place when and where the hearing is to be continued, or if 3 days notice thereof be published in the newspaper. 604.03. Specifications and Regulations. All sidewalks and curbs and gutters constructed upon any street, alley, avenue, or other public property in this city shall be constructed according to the plans and specifications herein provided. 604.04. The Sub grade. Sub grade for sidewalks and curb and gutter shall be firm, compact and of uniform density. All soft, spongy material or vegetative matter must be removed and replaced with suitable material. The sub grade shall be finished to a uniform surface at the required depth below the established grade of the improvement. 604.05. Forms. All forms shall be made of rigid metal or straight and sound lumber not less than 1 1/2 inches in thickness. Forms shall be free from warp and of sufficient strength to resist springing out of shape. All forms shall be thoroughly cleaned and oiled before the concrete is placed. The forms shall be securely staked to the established line and grade. 604.06. Materials. Subdivision 1. Cement: The quality of the cement used shall conform to the latest "Standard Specifications for Standard Portland Cement" of the American Society of Testing Materials. Subd. 2. Fine Aggregate: The fine aggregate shall be sand consisting of particles of sound, durable rock washed clean and free from an injurious amount of organic matter, lumps of clay and other deleterious substances. Subd. 3. Coarse Aggregate: The coarse aggregate shall be screened gravel or crushed quarry rock of the proper size. It shall be clean and free from shale or injurious organic matter. Subd. 4. Water: The water used in the concrete shall be reasonably clear, and shall be free from oil, acid, injurious alkali or vegetable matter. Not more than 6 gallons of water per bag of cement shall be used. 604.07. Methods. Subdivision 1. The Mixture: The materials used in each batch shall be weighed or accurately measured so as to get a uniform product. The materials shall be proportioned so as to produce a uniform, dense, workable concrete which will have a compressive strength of not less than 2000 lbs. per square inch at 28 days. In no case will a mixture be used which has less than 6 bags of cement for each cubic yard of concrete. Subd. 2. Mixing and Placing: The mixing shall be done in an approved batch mixer until the cement is uniformly distributed, and the mass is uniform in color and consistency. The mixing period shall be not less than 90 seconds after all ingredients are in the mixer, The concrete shall be placed in the forms before it begins to set, tamped and struck off to the proper grade.

Subd. 3. Curing: The concrete shall be cured by covering with a wet burlap or other approved covering for 3 days or by using an admixture of calcium chloride. If the work is placed in weather when freezing temperatures may be expected, the concrete shall be given adequate protection. Subd. 4. Moistening: The sand base for concrete walks and the sub grade for curb and gutter shall be moistened before the concrete is placed. 604.08. Sidewalks. Subdivision 1. Width: The walks in the business district shall be not less than 10 feet in width except that where it joins an existing sidewalk it shall be the same width; and shall be not less than 5 feet in width in the residential district except where the council shall by resolution order different widths. The widths of new walks shall conform as far as possible to that of adjacent walks. Subd. 2. Thickness: The sidewalk shall consist of two parts; referred to as the base and the surfacing. The surfacing of the walk shall be not less than 4 inches thick where used by pedestrians only, and not less than 6 inches in thickness where crossed by vehicles. Subd. 3. Base: The base shall consist of a layer of pit run sand or gravel not less than 4 inches in thickness and shall be thoroughly tamped to a uniform grade. The base of the walk shall be not less than 4 inches in thickness, except where the nature of the soil is such that the city council shall order a thicker base. Subd. 4. Surface: The surfacing of the walk shall be concrete having not less than the thickness prescribed herein, laid to a slope of one-eighth inch per foot downward towards the street, and shall be composed of materials and placed according to the methods described above. Subd. 5. Joints: Contraction joints shall be made not more than 5 feet apart, perpendicular to the center line and to the surface of the sidewalk, and shall, where possible, align with joints of abutting or adjacent work. Expansion joints may be pre-formed or poured type. They shall be one-half inch wide placed on all property lines, and at uniform intervals not to exceed 30 feet apart. Expansion joints shall also be placed between the walk and all abutting curbs, buildings and other masonry and concrete work. 604.09. Inspection and Surfacing. The council shall require inspection and supervision of all work done hereunder as deemed necessary. Any work not done according to specifications shall be corrected or removed at the expense of the permit holder. Any unsatisfactory work in the process of being constructed shall be stopped by the inspector as soon as discovered. 604.10. Cost Allocation. The city will pay for repair to sidewalks, curb, and gutter that is under 20 years old. Any curb and gutter over 20 years old will be the responsibility of the owner of the abutting property, and they will be assessed for the cost of repair.

604.11. Property Owner s Responsibility. It is made the duty of all owners of land adjoining any street in the city to construct, reconstruct and maintain in good repair such sidewalks along the sides of the streets, next to the lands of said owners respectively as may have been or shall hereafter be constructed. The construction or reconstruction shall be directed by the City Council and be built of such material and width and upon such place and grade as the City Council may prescribe. No sidewalks shall be permanently removed without the express authority of the City Council. (09/19/16) 604.12. SIDEWALK REPLACEMENT PROGRAM (11-20-17) 1. Pink paint means that our inspector/city supervisor has determined the sidewalk, driveway approach, or curb & gutter needs to be repaired or replaced. The criteria for marking defective sidewalk is based on evidence of deterioration and potential safety hazards due to concrete being broken, tilted, raised, settled, chipped, or displaced through overall use, freeze and thaw action, or tree root issues. A sidewalk that may appear in good condition on the surface may still need repair if it does not drain properly. a. DEFECTIVE SIDEWALK. Any of the following: (1) Vertical separations of ¾ inch or more; (2) Horizontal separations of ¾ inch or more; (3) Holes or depressions of 3 inches or more in diameter and ¾ inch or more in depth; spanning over 50% of a five-foot by six-foot square or panel of the sidewalk with one or more depressions of ¾ inch or more; (4) A single square or panel of sidewalk cracked in such a manner that no part thereof has a piece greater than one square foot, or is cracked in such a manner that it constitutes a danger or a potential danger to public safety; or (5) A sidewalk with any part thereof missing to the full depth. 2. Property Owners are responsible to pay for the repair or replacement of defective sidewalk along their property frontage. If non-defective sidewalk is impacted by utility construction (for example a water service replacement) and needs to be replaced, the property owner will not be responsible for the cost of this sidewalk replacement. The Property Owner is only responsible for sidewalk immediately adjacent to their property frontage. Replacement of the sidewalk ramps at street intersections will not be billed to Property Owners. 3. If you receive a notice and pink markings from the City of Hayfield for sidewalk repair or maintenance, you have until August 1 st 2020 (revised 10-15-18) to make the necessary

repairs. If the repairs to the sidewalk are not made by that date, the city s contractor will make the necessary repairs and you will be billed for the work. 4. If you receive a notice for sidewalk repair or maintenance, there are three general repair options available: (Please read all options including the important notes following the listed options) Option 1: Property owners may choose to repair their own sidewalk, providing repaired sidewalk is in compliance with the City Sidewalk Specifications. Property owners must arrange for the work to be completed by the deadline specified in the notice. Option 2: Property owners can arrange for a private contractor to repair their sidewalk, providing the repair is in compliance with the City Sidewalk Specifications. Property owners must arrange for work to be completed by the deadline specified in the notice and shall pay the private contractor directly. Option 3: Property owners can choose to have the City replace their sidewalk utilizing the City s Contractor. Once the work is completed, the cost of the installation will be assessed against the property. NOTE any repairs or replacements performed by Property Owners or Private Contractors that do not meet the requirements of the City s Sidewalk Specifications will be replaced by the City s Contractor and the Property Owner will be assessed for the sidewalk replacement completed by the City s Contractor. (City Sidewalk Specifications available on the City s website) 5. Payment options for sidewalk replacement if the City s contractor performs the work. After the work is completed you will be sent an assessment / bill. You will have the following payment options: Option 1: Pay the assessment/bill in full within 30 days of receipt of the invoice. Option 2: Include and pay for the full amount of the assessment/bill on your next property tax bill, at an interest rate of 6% beginning thirty (30) days after the date of the invoice for a period of 2 years. 6. Permanent sidewalk repairs cannot be made with asphalt. Asphalt is only allowed as a temporary measure to alleviate trip hazards until the acceptable concrete repair is made by the deadline. Only concrete raising ( mud-jacking or foam-jacking ); concrete grinding, sawing, or shaving; or full replacement of concrete sidewalk panel(s) are acceptable repair methods. 7. Per City Ordinances the maintenance and removal of trees in the boulevard is the responsibility of the property owner. The City will only pay for the removal of a tree when it is necessary for street rehabilitation or reconstruction. 8. Only the portion of the sidewalk abutting (in front of) each property is assessed to the corresponding Property Owner. So, if 2 feet of the panel abut your property and 3 feet

of the panel abut your neighbor s property, you will pay for 2 feet and your neighbor will pay for 3 feet. 11/20/17 (revised 10-15-18) Rich Fjerstad, Mayor David Subbert, Council member Linda Pack, Council member AJ Anderson, Council member Steven Feist, Council member