Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Similar documents
SECTION HORIZONTAL DIRECTIONAL DRILLING

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

SECTION WASTEWATER FORCE MAINS

Design of a 7,000 LF, Single Insertion Slipline Rehabilitation Project

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE

ITEM NO SLIPLINING SANITARY SEWERS

LARGE DIAMETER HDPE SLIPLINING WHERE EXPERIENCE MATTERS

Pearl City Force Main Repair Uses Sliplining Installation Method

SECTION WASTEWATER FORCE MAINS

PIPE REHABILITATION. Comply with Division 1 - General Provisions and Covenants, as well as the following:

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Infrastructure Solutions Pressure Pipe Overview

Swagelining for Water Transmission & Sewer Force Main Renewal 16 through 65.

ITEM 432 TUNNEL CONSTRUCTION

TECHNICAL SPECIAL PROVISION PIPE BURSTING BISCAYNE ISLAND DRAINAGE IMPROVEMENTS PROJECT NO.: B-30588

Rowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project. TACWA Meeting

SECTION MEASUREMENT AND PAYMENT

7. Allowable Fittings.

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

City of Port Angeles Pulls Off Challenging Slipline to Divert CSOs

Pipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

SECTION 811 PIPE BURSTING

TA-T6-04 Slipline Method Used to Repair a Leaking Pipeline Installed with HDD

PARRIS ISLAND FORCE MAIN PROJECT CREATES RECORD HDD INSTALLATION FOR PLASTIC PIPE

Fully Structural Renewal of 39-inch PCCP Water Transmission Main with Swagelining and HDPE

Clay County Utility Authority Utilization of Trenchless Water & Wastewater Pipeline Installation

Todd Eising, PE, Utilities Section Manager Environmental & Water Resources Department, City of Folsom

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC

Large Diameter Pipe Bursting

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

Innovative Joint Proves Successful in Critical Slipline Project

Section 3 Fusible PVC Pipe Connections

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.

Fold & Form PVC Liners Sewer & Culvert Rehabilitation

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

1.02 RELATED WORK: Refer to the following sections for related work:

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

Sustainable Utility Construction: Methods and Techniques

SECTION TRENCHLESS INSTALLATION

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

Material Specification for. Large Diameter Watermains

Garrett Richardson Mission Clay Products

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Weholite LIGHTWEIGHT PIPE SYSTEM

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

CONSTRUCTION SPECIFICATION FOR CEMENT MORTAR LINING OF WATERMAINS

Paper MA-T4-04 Six Miles of Fusible PVC Pipe Used to Rehabilitate Water Line in Rural Wyoming via Trenchless Construction

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

DUCTILE IRON PIPE AND FITTINGS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

DIVISION 33 UTILITIES SPECIFICATION : HORIZONTAL DIRECTIONAL DRILLING

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Chapter 3: Permit Procedures and Requirements

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

Potable Water Static Pipe Bursting and How it Fits within Cheyenne, WY Board of Public Utilities Rehabilitation Strategy

A Trenchless Approach to Lift Station Elimination

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS)

PA P E R S. Andrew D. Seidel, Robert Walker

Pipe Bursting Water Mains

SUPPLEMENTAL SPECIFICATIONS TO STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION NO. 2611

H. Underground Transmission System Design

Customer Requirements Conduit Installations, High Voltage

The Metropolitan Sewer District of Greater Cincinnati

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS

Sliplining Provides the Perfect Trenchless Solution for the City of Del Mar, California

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

Pipe Bursting Rehabilitates Irrigation to Ogden Golf Courses

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.

Pipe-Bursting Success with AC Pipe

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

STANDARD SPECIFICATIONS SECTION JACKED CASING

PipeLine. Increasing Sewer Capacity. January 2015, Issue 72

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

16. Design of Pipeline Structures.

SECTION BORING AND/OR JACKING PIPE

Anacostia River Tunnel Briefing For: ANC 6B

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SECTION 1 GENERAL NOTES

Transcription:

North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' Ian Mead, CDM Smith, Providence, RI Steve Pinault, DC Water, Washington, D.C. Daniel Gilroy, CDM Smith, Fairfax, VA Richard (Bo) Botteicher, Underground Solutions Inc., Denver, CO 1. ABSTRACT The District of Columbia Water and Sewer Authority (DC Water) is implementing its Long Term Control Plan (LTCP) for the District s combined sewer system. The LTCP is divided into several contract divisions; the work under Division E is located on M Street SE, between 9th Street SE and 14th Street SE. Under this project, combined sewer overflows (CSOs) will be diverted from existing combined sewers to the future tunnel system along M Street SE through a series of large diameter diversion sewers constructed using trenchless methods. Due to concerns of potential damage during construction of the sewers, the work includes the rehabilitation of selected portions of the existing 36-inch Southeast Relief Water Main (SRWM). During design, the feasibility of several Class IV structural rehabilitation methods was evaluated for this prestressed concrete cylinder pipe (PCCP), and construction bid documents were prepared allowing contractors to choose one of three options. The rehabilitation of roughly 1800-feet of PCCP line was performed through a sliplining operation in which Fusible PVC pipe was fused together from 40-foot sections and pulled sequentially into the host pipe. This paper provides a case study of the design considerations and construction techniques which allowed successful installation and testing of the line. Material covered will include the selection of pit locations, survey and video of the host pipe for potential pinch points or obstacles, a brief description of the product pipe, equipment used to pull pipe through the host pipe, grouting methods and connections to DIP fittings, and challenges encountered during construction. 2. INTRODUCTION DC Water s Long Term Control Plan (LTCP) is comprised of a system of tunnels and diversion sewers for the capture of combined sewer overflows (CSOs) to Rock Creek and the Anacostia and Potomac rivers for treatment at DC Water s Blue Plains Advanced Wastewater Treatment Plant. Implemented under a Federal Consent Decree between the United States, District Government and DC Water, the LTCP is divided into several contract divisions; the entire project, however, will reduce CSOs annually by 96 percent throughout the system and by 98 percent for the Anacostia River alone. The work under Division E will occur on M Street SE, between 9th Street SE and 14th Street SE. Under the project, CSOs will be diverted from existing combined sewers using three diversion chambers, then conveyed to the future tunnel system along M Street SE through a series of 48-inch and 108-inch diameter diversion sewers constructed using trenchless methods. CSOs totaling 695 million gallons per day will be delivered to the LTCP tunnel system. Paper MA-T4-02 - 1

The work also includes the rehabilitation of selected portions of the existing Eastside Interceptor (ESI) sewer and the Southeast Relief Water Main (SRWM). Figure 1. Schematic of Division E Project Location (courtesy of DC Water). 3. DESIGN CONSIDERATIONS AND ALTERNATIVES ANALYSIS Construction of the M Street diversion sewer project includes 48-inch and 108-inch diversion sewers, CSO diversion chambers and manholes, and an open cut approach channel/junction sewer installed in close proximity to the existing ESI and SRWM. Based on geotechnical investigations and evaluations of potential construction methods, it was determined that an unacceptable amount of settlement and/or displacement of the 36-inch SRWM (from 11 th Street to Water Street) was possible. Therefore, structural rehabilitation was evaluated and designed to occur in advance of the construction of new facilities. The subject section of the SRWM transitions from 36-inch steel to prestressed concrete cylinder pipe (PCCP) on the east side of the 11 th Street intersection, and continues east beyond Water Street and the limits of this project. The proposed diversion sewer is located below and to the south of the SRWM from 11 th Street to Water Street. The SRWM was constructed in the early 1960s at a depth of cover from 4-feet to 12-feet, with the deepest section between 14 th Street and Water Street. There is an existing access manhole about 100-feet west of the steel-pccp transition. There are six existing connections (hydrants and connecting mains) to the SRWM within the section of concern, ranging in diameter from 4-inch to 12-inch, at various clock positions on the pipe (typically tangential to the pipe top or bottom), which must be maintained or restored following rehabilitation. Control valves for the 36- inch SRWM are located at 11 th Street and east of Water Street. All valves were assessed and confirmed operational ahead of design, and it was determined that this section of the SRWM may be taken out of service during the period of low demand, from October through April. For the purposes of finalizing the selection and design process in advance of project bidding, the feasibility of three specific rehabilitation options was evaluated, including sliplining and cured in place pipe (CIPP) lining by two separate systems/vendors. Each system met the requirement to provide a standalone, structural rehabilitation solution. In the case of sliplining, a new pipeline is inserted into the existing pipe. After the pipe is inserted, connections are made to the existing pipeline on both sides of the sliplined portion with transition couplings. Additionally, grout is pumped to fill the annular space that is created between the existing pipeline and the new pipe material. The grouting process locks the new pipe in place and also eliminates void space from around the new asset. Paper MA-T4-02 - 2

CIPP rehabilitation systems typically entail the insertion of a resin-soaked liner into the existing pipe. The liner is than expanded against the inner wall of the existing host pipe, which acts as a form for the CIPP material. The liner is then cured with water or steam, providing a fully structural solution, following which end connections are made. For the sliplining option, concerns were raised regarding reduction of the inside diameter of the pipe, relative to maintaining operating pressure and flow. Fusible polyvinylchloride pipe (FPVCP) was identified in a 30-inch, ductile iron pipe (IP) size, DR 25, pressure class 165 psi, with an outside diameter (OD) of 32-inches. This meant that it could be inserted into the existing PCCP, which had an inside diameter of 36-inches. Additionally, due to the material characteristics, the required wall thickness for the given pressure class meant that the new FPVCP pipe would have an average inner diameter of approximately 29.2-inches. Other pipe materials, such as high density polyethylene (HDPE), are regularly used in sliplining and other trenchless technologies. However, in order to maintain a similar flow area or inside diameter with a similar pressure rating, a nominal 36-inch IP size HDPE would be required. This would preclude sliplining as a rehabilitation option. Further, it was determined that a smaller 34-inch IP size HDPE section would result in an unacceptable flow reduction (see Figure 2). Therefore, FPVCP was selected as the acceptable material for the sliplining option. Sliplining and pressure CIPP installation methods were bid competitively on this project, and the sliplining solution was provided by the successful bidder. 36" ID PCCP 36" ID PCCP OD= 32.00" ID= 29.29" OD= 34.00" ID= 27.45" 30" DR 25 Fusible C-905 34" DR 11 HDPE Figure 2. Comparison of potential sliplining pipe materials. For the same pressure class and outside diameter constraints, the inside diameter of the FPVCP section is about 2-inches larger than the HDPE section. 4. SLIPLINE INSTALLATION PROCESS Rehabilitation of the 1,800-foot pipe length was completed in three sections, with conventional connections made to reconnect the pipeline in between segments and at the ends. Four access pits were excavated at points along the line as required. The first pit was the connection point for the west end of the project. The second pit served as a pipe fusion and launch pit for the pipe, to be pulled west to the first pit, and then also east towards the third pit location. This pit was placed at the location of a horizontal bend, which required excavation to facilitate installation. The third pit location coincided with a vault that was to be constructed, along with about 200-feet of pipe with several direction changes which was completed using direct bury installation techniques. The fourth pit coincided with the eastern end of the project. Connections were restored to the existing steel pipeline on the western end, and the existing PCCP at the eastern end. Allowable pit locations were defined in the bid documents, as shown in Figure 3. Prior to the beginning of the sliplining process, a closed-circuit television (CCTV) survey was completed to make sure that there were no unknown obstructions, alignment issues or appurtenances in place that would obstruct the sliplining insertion process. There were several locations where vertical deflection of the existing alignment was verified during this survey, to ensure that the bend radius of the FPVCP could be accommodated. This was accomplished by calculating whether the bend radius of the FPVCP would be capable of navigating the deflection within the annular space available between the existing PCCP pipeline and the new FPVCP sliplined pipe. Figure 4 shows an example calculation for one of the vertical deflection locations, estimated at 2.7 degrees of deflection. Paper MA-T4-02 - 3

Figure 3. Excerpt from Pre-Bid plan sheet set noting allowable pit locations. Figure 4. Sample calculation to evaluate deflection of FPVC pipe within host pipe. This example shows that at a deflection angle of 2.7 degrees, the 30-inch FPVCP is capable of navigating the deflection within the allowable bending limitations of the pipe. For each slipline insertion, the FPVCP was assembled in an excavated pit which was aligned with the host pipe on one end. A McElroy T900 fusion machine was placed in the excavated pit and used to thermally butt-fuse the pipe joint for the given insertion (See Figure 5). This required an excavation sized for the fusion operation, but also limited the footprint of the excavation as compared to the required pit and tail ditch that would have been needed if Paper MA-T4-02 - 4

the pipe was fused at grade and then pulled into the alignment at one time. This also limited the project area needed to fuse pipe lengths together prior to insertion. Figure 5. Length of FPVCP being thermally butt-fused within the pit. Each 40-foot section of pipe was fused to the previous section, allowed to cool, and then pulled from the fusion machine into the host pipe, which then allowed the next 40-foot length to be lowered into the pit. The fusion unit was located within the pit, and situated such that, upon exiting the fusion machine, the new pipe lined up directly with the existing pipe (see Figure 6). Figure 6. Close up view of new FPVCP inserted into the existing PCCP. Paper MA-T4-02 - 5

The pipe was pulled into place through the existing 36-inch PCCP host pipe using static pipe bursting equipment (TT Technologies Grundoburst 800G) as shown in Figure 7. After each fusion joint was completed, the Grundoburst unit pulled the 40-foot pipe string into the existing pipe, setting up the next fusion joint. The steel bursting rods were connected to the FPVC pipe via tie rods placed through-wall at the end of the pipe, with a nylon strap woven through the cross connection of the tie-rods on the inside diameter of the pipe. After each pipe length was inserted and connections were made at the pit excavations, grout was used to fill the annular space between the FPVCP and the existing PCCP. The grout filled in the void space, locking the sliplined pipe in place and eliminating voids along the alignment. The pipe was bedded and backfilled within the excavated pit locations as per typical direct bury process. Figure 7. Grundoburst 800G static bursting unit set up and blocked in place in the receiving pit to pull in the new pipe. The steel rods are shown in the machine as well as in their storage packs for removal from the pit. 5. OTHER CONSTRUCTION CONSIDERATIONS During preliminary construction of the M Street improvements, the SRWM was exposed in one location due to the configuration of the shoring system for the deeper sewer work. Field condition assessment of the PCCP indicated that bracing of the line was required before additional excavation could occur. A steel frame was erected within the shoring and the PCCP was braced and protected through a system of cables, steel members, grating and timber. With this system in place (Figure 8), the deeper work continued. Paper MA-T4-02 - 6

Figure 8. Protection of the 36-inch PCCP within the shoring system. In addition, although modeling of the water system confirmed that the 36-inch SRWM could be taken out of service for a longer period than initially indicated, the rehabilitation work required removal of pipe segments adjacent to existing valves which were closed to isolate flow. The need for thrust restraint at these locations led to the development of a concrete thrust block system, which encased both the pipe and a set of helical tension anchors installed in the ground on either side of the SRWM. This system also allowed the work to proceed safely. Another challenge that occurred during construction involved ground settlement. Due to the location of an old streambed along the project site, ground settlement of 4-feet was encountered during drilling and tunneling of the deeper sewer work. Chemical grouting and compaction grouting techniques were subsequently employed to stabilize the area and allow construction to continue. Additional sections of the rehabilitated SRWM were removed and restored in this case through open cut techniques, though connections were simplified by the use of the FPVCP material. 6. CONCLUSIONS Significant planning was involved in the design, bidding, and construction of improvements to the utilities within the Division E project. Sliplining of the 36-inch PCCP SRWM with fusible polyvinylchloride pipe (FPVCP) was found to be the most cost effective Class IV structural solution applicable to the project per the bid, and it also accommodated the necessary pressures and flows. The sliplined pipe was installed in three segments using four excavated pits. The FPVCP was reconnected to the existing system as well as all required appurtenances using standard DI fittings and connections. Several techniques were used to protect the existing PCCP from issues related to the tunneling work adjacent to the rehabilitation project site and ensure that the PCCP remained in service. 7. REFERENCES DC Water Website, Anacostia River Tunnel Project - Project Information Sheet Section, CSO 015/016/017, accessed 10/30/13: http://www.dcwater.com/workzones/projects/anacostia_river_information_sheet.cfm Paper MA-T4-02 - 7