1 TABLE OF CONTENTS CONTRACT DOCUMENTS Inside Title Page Table of Contents List of Drawings Invitation to Bid Instructions to Bidders Bid Agreement Construction Performance Bond Payment Bond One-Year Maintenance Bond General Conditions of the Construction Contract Supplementary Conditions TECHNICAL SPECIFICATIONS Division 1 General Requirements Summary of Work Use of Premises Potentially Contaminated Areas (Guide Specification) Change Order Procedures Measurement and Payment Schedule of Values Coordination and Meetings Construction Photographs Construction Schedule Submittal Procedures Shop Drawings, Product Data, and Samples TPDES Requirements Reference Standards Contractor s Quality Control Inspection Services Testing Laboratory Services Mobilization Temporary Facilities and Controls Temporary Field Office Traffic Control and Regulation Tree and Plant Protection Reinforced Filter Fabric Barrier 4 DOC. REV. 06/01/ Page 1 of 6 TABLE OF CONTENTS
2 Division 1 General Requirements Stabilized Construction Exit Waste Material Disposal Inlet Protection Barriers Control of Ground Water and Surface Water Project Identification Signs Basic Product Requirements Water Receiving Facility (WRF) Start-Up Field Surveying Cutting and Patching Restoration of Site Closeout Procedures Operations and Maintenance Data Project Record Documents 3 Division 2 Site Work Cast-In-Place Concrete Manholes Precast Concrete Manholes Frames, Grates, Rings, and Covers Valve Boxes, Meter Boxes, and Meter Vaults Adjusting Manholes, Inlets, and Valve Boxes to Grade Storm Water Brick Manholes Removing Existing Pavements, Structures and Buried Utilities Clearing and Grubbing Trench Safety System Roadway Excavation Excavation and Backfill for Structures Excavation and Backfill for Utilities Extra Unit Price Work for Excavation and Backfill Borrow Utility Backfill Materials Cement Stabilized Sand Embankment Lime-Stabilized Subgrade Lime/Fly-Ash Stabilized Subgrade Portland Cement Stabilized Subgrade Tunnel Shafts Tunnel Excavation and Primary Liner Tunnel Grout Dry and Slurry Augering of Pipe and Conduit 10 DOC. REV. 06/01/ Page 2 of 6 TABLE OF CONTENTS
3 Division 2 Site Work Horizontal Directional Drilling Drilled Shaft Foundations Ductile Iron Pipe and Fittings Steel Pipe and Fittings High Density Polyethylene Pipe (HDPE) Polyvinyl Chloride Pipe Prestressed Concrete Cylinder Pipe Water Lines Wet Connections Disinfection of Water Lines Hydrostatic Testing of Water Lines Cleaning and Flushing of Water Lines Water Line in Tunnels Steel Pipe and Fittings for Large Diameter Water Lines Flushing Hydrants Gate Valves Butterfly Valves Air Release and Vacuum Relief Valves Tapping Sleeves and Valves Polyurethane Coatings on Steel Pipe Polyethylene Wrap Electromagnetic Flow Meters Gravity Sanitary Sewers Bar Wrapped Steel Cylinder Pipe Geotextile Cast-in-Place Inlets, Headwalls and Wingwalls Precast Concrete Inlets, Headwalls, and Wingwalls Hot Mix Asphalt Base Course Cement Stabilized Base Course Recycled Crushed Concrete Base Course Asphaltic Concrete Pavement Prime Coat Concrete Pavement Joints Concrete Pavement Curing Concrete Driveways Colored Concrete for Medians and Sidewalks Blast Cleaning of Pavement Temporary and Removable Reflectorized Pavement Markings Thermoplastic Pavement Markings Curb, Curb and Gutter, and Headers 4 DOC. REV. 06/01/ Page 3 of 6 TABLE OF CONTENTS
4 Division 2 Site Work Concrete Medians and Directional Islands Concrete Sidewalks Chain Link Fences and Gates Topsoil Tree Planting Hydro-Mulch Seeding Sodding Pavement Repair and Resurfacing Dechlorination Activities 6 Division 3 Concrete Concrete (Pavement & Structures) Concrete Pavement Reinforcing Steel Concrete for Utility Construction 19 Division 4 Masonry Mortar Brick Masonry for Utility Construction 5 Division 5 Metals Division 6 Wood and Plastics Division 7 Thermal and Moisture Protection Division 8 Doors and Windows Division 9 Finishes Painting and Protective Coating Repainting and Repair of Existing Water Facilities 35 Division 10 Specialties Division 11 Equipment Gas Chlorination System Sodium Hypochlorite (Bleach) Chlorination System Liquid Ammonium Sulfate (LAS) System 13 DOC. REV. 06/01/ Page 4 of 6 TABLE OF CONTENTS
5 Division 11 Equipment Chlorine Gas Leak Detector Chlorine Analyzers Ammonia Analyzers Chemical Analyzers Package Sanitary Sewer Lift Station for Analyzer Station By-Pass Flows Static Mixers and Appurtenances Emergency Eyewash and Shower Equipment 6 Division 12 Furnishings Division 13 Special Construction Polyethylene Chemical Storage Tanks Ground Storage Tank (GST) Modifications, Cleaning and Disinfection Primary Instrument Devices 22 Division 14 Conveying Systems Division 15 Mechanical Polyvinyl Chloride Pipe Less Than 4 in Diameter Chemical Piping Combination Flow Control Valve Air Release and Vacuum Release Valves For WRF and Plant Work Check Valve, Twin Disc Pressure Gauges, Transmitters and Elements Pipe Hangers, Supports, and Restraints Pipe and Equipment Insulation Basket Strainer Couplings and Coupling Adapters Heat Tracing Automatic Control Valve Insulated Enclosure (Hot Box) 8 Division 16 Electrical Electrical Construction Electrical Demolition Joint Bonding and Electrical Isolation Corrosion Control Test Stations Conduit, Fittings, and Bodies Precast Electrical Manholes and Pull Boxes Electrical Identification Low Voltage AC Surge Protective Devices (SPDs) Underground Duct Banks 6 DOC. REV. 06/01/ Page 5 of 6 TABLE OF CONTENTS
6 Division 16 Electrical Mini-Power Centers Programmable Logic Controllers, SCADA Interface Panels and Panel Mounted Equipment (WRF) Mechanical Equipment Manufacturer (MEM) Provided Control Panels Cathodic Protection for Pipelines AC Interference Mitigation Systems for Pipelines Gradient Control Systems 9 Division 17 Instrumentation DOC. REV. 06/01/ Page 6 of 6 TABLE OF CONTENTS
VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL
Page 312 VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS-12-01 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the IL ROUTE
More informationCITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION Edition
CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION PURPOSE, INTENT AND INTERPRETATION OF SPECIFICATIONS The purpose of these Specifications is to establish, where applicable, minimum acceptable standards
More informationDIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS
OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006
More informationSECTION MEASUREMENT AND PAYMENT
SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract
More informationBIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83
Item No. BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 DESCRIPTION EST. QTY. UNIT UNIT PRICE TOTAL PRICE GENERAL BID ITEMS 1 Per Plans and Specifications
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationDUCTILE IRON PIPE AND FITTINGS
Section 02501 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS
Section 02501 PART 1 GENERAL 1.01 SUMMARY This Section includes ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT
More informationSECTION STORM DRAIN
PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract
More informationPITTSBURGH TECHNOLOGY CENTER PUBLIC IMPROVEMENTS SITE PREPARATION CONTRACT NO. 11 BID TABULATION BID OPENING DATE: MARCH 11, 2008
BT-1 of 7 Clearing and Grubbing L.S. $50,000.00 $50,000.00 $5,335.00 $5,335.00 $14,560.00 $14,560.00 $20,000.00 $20,000.00 $10,600.00 $10,600.00 Class 1 Excavation 4300 C.Y. $20.00 $86,000.00 $15.00 $64,500.00
More informationThis section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.
NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and
More informationPASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017
SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSPECIAL SPECIFICATION 3504 Septic Tank System
1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for
More informationSERVICE LINES, METERS AND APPURTENANCES
AUGUST02 SECTION 02646 SERVICE LINES, METERS AND APPURTENANCES PART 1 - GENERAL 1.1 DESCRIPTION A. This section concerns materials and installation of corporation stops, curb stops, service lines, meters,
More informationM I N N E S O T A D O T BID TABULATION SUMMARY JOB PAGE 1 ON 03/16/94 MINNESOTA PROJECT NO.S: STP 5822(002)
BID TABULATION SUMMARY JOB 940094 PAGE 1 STATE PROJECT NO. 162-080-04 BIDS RECEIVED UNTIL 11:00 A.M. ON 03/16/94 MINNESOTA PROJECT NO.S: STP 5822(002) BETWEEN 2ND STREET NORTH AND 15 STREET NORTH IN ST.
More informationSECTION UTILITY MANHOLES AND STRUCTURES
SECTION 33 05 14 UTILITY MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Precast reinforced concrete manholes and structures with tongue-and-groove joints with masonry transition
More informationDrainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.
403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage
More informationE. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17
S&L Gravel, Section B: Proposal Page 10701.0 - TRAFFIC CONTROL - LUMP SUM 1.00 $6,425.00 $6,425.00 $6,425.00 $10,000.00 10720.0 - TRAFFIC CONTROL SIGN - PORTABLE ARROW BOARD - DAYS 25.00 $25.00 $625.00
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES
Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle
More informationSECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation
SECTION 33 40 00 STORM DRAINAGE UTILITIES 1. PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 00: Excavation and Fill B. Section 32 00 01: Site Restoration and Rehabilitation C. Special Conditions for
More informationENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)
EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY
More informationDESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General
DESIGN STANDARDS Division 02 Existing Conditions- Site Work General I. This Division includes: A. Demolition B. Clearing and Grubbing C. Excavation, Backfill and Compaction D. Pavement Base E. Paving and
More informationBID FORM (LUMP SUM CONTRACT)
BID FORM (LUMP SUM CONTRACT) Place County of El Paso Purchasing Department Date Project No. 11-016 Proposal of (hereinafter called Bidder), a corporation organized under the laws of the State of /a partnership/an
More informationPART 5 WATER SYSTEMS
PART 5 WATER SYSTEMS Abbreviations and Symbols Plan 501 Abbreviations and symbols for water... 205 Concrete Boxes and Hardware 502 27" Frame and cover... 207 503 38" Frame and cover... 209 505 Concrete
More informationVOLUME 4 DIVISION SPECIFICATIONS
Page 1 Section Title Consultant Pages VOLUME 4 DIVISION 00-01 SPECIFICATIONS Division 00 - Procurement and Contracting Requirements 00 01 07 SEALS PAGE All 5 00 01 11r6 TABLE OF CONTENTS All 7 00 21 13r1
More informationSUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation)
PART 1 GENERAL SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) 1.01 SCOPE This specification includes the materials and procedures required for the internal sealing of the frame-chimney
More informationCONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL
CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard
More informationMANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems
SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.
More informationINSPECTION AND ACCEPTANCE FOR MAINTENANCE
Inspection and Acceptance For Maintenance Page 1 (Last revised 6/29/10) INSPECTION AND ACCEPTANCE FOR MAINTENANCE SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Acceptance Sewer As Built Drwg Example
More informationSECTION 806 MANHOLE REHABILITATION
SECTION 806 MANHOLE REHABILITATION 806-1 DESCRIPTION: This specification consists of all work, materials, labor and equipment required for manhole rehabilitation for the purpose of eliminating infiltration
More informationSummary of the 2011 Changes
The following is a list of amendments to the Residential Site Improvement s, N.J.A.C. 5:21, adopted in 2011. The Notice of Adoption of these changes appeared in the New Jersey Register on May 16, 2011.
More informationConcrete Pressure Pipe
Concrete Pressure Pipe AWWA MANUAL M9 Third Edition Contents List of Figures, vii List of Tables, xi Acknowledgments, xiii Chapter 1 Purpose and Scope............................................... 1 Chapter
More informationCHECK THE LOWER RIGHT CORNER OF EACH DETAIL FOR THE LATEST REVISION.
Standard Drawings Index NOTE: The specifications for materials and workmanship shall conform to the latest edition or the "Standard Specifications for Public Works Construction" published by the North
More informationITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS
ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing
More informationGUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES
State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water
More informationFox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS
Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # 2016-04 PROJECT SPECIFICATIONS TABLE OF CONTENTS SECTION 100 GENERAL... 1 SECTION 200 MATERIALS... 1 CONSTRUCTION METHODS... 1 SECTION
More information1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings
SECTION 33 34 00 SANITARY FORCE MAIN PART 1 GENERAL 1.1 SCOPE OF WORK A. This section specifies the requirements for furnishing and installing sanitary force main and appurtenances. The pipe shall be of
More informationSECTION FACILITY SANITARY SEWERS
SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationFebruary 22, 2018 BIDDERS WILL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE PROPOSAL PAGE
February 22, 2018 Addendum No. 1/Bid Postponement DWM Sewer Improvement P-2017-06 Sewer Improvement Project PN-2017-06 SPECIFICATION NO. 292687 For which bids will be opened in the office of the Department
More informationSAN ANTONIO WATER SYSTEM 2013 REHABILITATION WORK ORDER CONSTRUCTION CONTRACT 4 SAWS Job No SAWS Solicitation No.
SAN ANTONIO WATER SYSTEM 2013 REHABILITATION WORK ORDER CONSTRUCTION CONTRACT 4 SAWS SAWS To Bidder of Record: ADDENDUM NO. 2 August 15, 2013 This addendum, applicable to work referenced above, is an amendment
More informationCIRCLE K SUB-CONTRACTOR BID FORM
CIRCLE K SUB-CONTRACTOR BID FORM Store No: 3308 Address: 8985 Will Clayton Pkwy Date: Bid Due September 17, 2014 Sub Contractor: Trade CONSTRUCTION TAX Construction Tax EXCAVATION / DIRT WORK Cut / Fill
More information2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationCONDUITS AND FITTINGS
CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit
More informationODOT District Bridge General Notes B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS
B401: DELETED B402: DELETED B403: DELETED B404: STRUCTURE/CULVERT IDENTIFICATION SIGNS B405: OBJECT MARKERS AND STRUCTURE/CULVERT IDENTIFICATION SIGNS B406: ITEM 514 - FIELD PAINTING, MISC.; REPAIR PAINTING
More informationConstruction Specification for Utility Adjustments
Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS
More informationForsyth County Procurement
August 1, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 Bid 17-72-3340 For: Providing all materials, equipment and labor for the Jot em Down Road Water Tank
More informationDIVISION 33 UTILITIES
DIVISION 33 UTILITIES This Article on Codes, Regulation and Standards shall apply to all Divisions of the Building Standards Table of Contents 33 05 13 MANHOLES AND STRUCTURES... 3 33 10 00 WATER UTILITIES...
More informationSECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES
SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and
More informationBILL NO. 1 GENERAL ITEMS. Item No. Description Lump Sum Prices Excluding HST
Page 1 SECTION 00 72 00 - GENERAL CONDITIONS BILL NO. 1 GENERAL ITEMS 1 Bonds... $ 2 Insurance... $ 3 Permits and fees... $ 4 Warranty certificates... $ 5 Supervision... $ SECTION 01 32 17 - SCHEDULE 6
More informationSTANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.
STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water
More informationSECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS
SECTION 334100 - STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY Section Includes: 1. Pipe and fittings. 2. Drain Basin. 3. De-chlorination tablet feeder. 4. Non-pressure transition couplings.
More informationCured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore
Cured-in-Place Pipe (CIPP) for Pressure Pipe Presented by: Mike Moore CIPP Proven Technology Introduced over 45 years ago Most used trenchless technology for the rehabilitation of gravity flow pipeline
More informationThe Contract Documents for the referenced project are hereby amended in the following particulars only, with all other conditions remaining unchanged.
1700 East Iron Ave. Salina, KS 67401 785-827-0433 phone 785-827-5949 fax 6 March 2018 Arizona California Colorado Kansas Louisiana Missouri Nebraska New Mexico Texas Utah ADDENDUM NO. 2 RE: City of Kingman,
More informationSECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)
SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain
More informationSECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS
SECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS To prevent the contamination of the public water supplies from nearby sanitary sewers, the following State Water Resources Control Board Division
More informationElectrical Work. NOV Embankments Over Swamps and Compressible Soils
GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification
More informationSECTION BASIC ELECTRICAL MATERIALS AND METHODS
SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain
More informationSTANDARD DETAILS AND DETAIL SPECIFICATIONS
STANDARD DETAILS AND DETAIL SPECIFICATIONS [THIS PAGE LEFT INTENTIONALLY BLANK] APPENDICES [THIS PAGE LEFT INTENTIONALLY BLANK] APPENDIX 1 CRITERIA
More informationProtective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc.
Protective Coatings for Underground Utility Concrete Structures By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc. As our cities and municipalities grow older, the utility and wastewater
More informationSECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION
820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing
More informationTABLE OF CONTENTS Water/Wastewater Civil Library
Title DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000000 Procurement and Contracting Requirements 11/11 Outline Only: Single Document to specify procurement and Contract requirements. Includes
More informationAll service lines shall conform to the following requirements:
505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the
More informationWATER SUPPLY CODE. of Australia. WSA Version 2.3
WATER SUPPLY CODE of Australia WSA 03-2002 Version 2.3 Water Supply Code of Australia WSA 03 2002 Second Edition Version 2.3 Previous edition WSA 03: 1999 CONTENTS PREFACE 6 INTRODUCTION 9 PART 0: GLOSSARY
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES January 18, 2013 811.01 Conduit Description 811.02 Conduit Materials 811.03 Conduit Definitions
More informationCURRENT NORTH LAS VEGAS ADDENDA
SECTION 1 Section 1.01.73 Fire Service Meter ADD: Type I is not approved for installation in the City of North Las Vegas service area. Section 1.01.107 Pressure Reducing Valve (PRV) or Pressure Regulator
More informationMANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:
MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL EFFECTIVE DATE: OCTOBER 14, 2011 200.07 Contractor Quality Control - is replaced with the following: (a) (b) (c) Scope: These requirements
More informationTHE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR WATERMAINS
THE REGIONAL MUNICIPALITY OF PEEL STANDARD SPECIFICATIONS FOR WATERMAINS INDEX Page No. W.1. GENERAL...1 W.2 SCOPE...2 W.3 MATERIALS...2 W.3.1 General... 2 W.3.2 Concrete... 2 W.3.3 Pipe Bedding and Backfill
More informationStorm Drainage Systems
Storm Drainage Systems A. Description This work shall consist of furnishing, constructing and/or reconstructing catch basins, manholes; with frames, grates, or manhole covers; as shown on the plans. This
More informationCHAPTER 11 CONDUITS AND FITTINGS
CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1
More informationSECTION IV. PIPELINE EXCAVATION AND BACKFILL
SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include
More informationCHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS
CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS Storm Sewer System: 1. Detention/retention of stormwater runoff shall be provided in accordance with the requirements of the DuPage County Countywide Stormwater
More informationSTORM AND SURFACE WATER 4-1 GENERAL...4-1
SECTION 4 STORM AND SURFACE WATER SECTION DESCRIPTION PAGE 4-1 GENERAL...4-1 4-2 STORM DRAINAGE CONVEYANCE SYSTEM DESIGN CRITERIA...4-1 4-2.1 Overview...4-1 4-2.2 Design Flow and Route Requirements...4-2
More informationWASHINGTON UNION ROAD RECONSTRUCTION XENIA TOWNSHIP GREENE COUNTY, OHIO
WASHINGTON UNION ROAD RECONSTRUCTION XENIA TOWNSHIP GREENE COUNTY, OHIO 42 380 68 coddington ave ledbetter road shawnee creek s patton street ledbetter road wesley ave 68 starr drive 42 twist run 85 35
More informationTown of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects
2.0 ROADWAYS 2.1 Road Classification 2.1.1 Standard Drawing Classification All Road Widths and Road Allowances shall be designed in accordance with the most recent Town of New Tecumseth Standards: TNT.SD
More informationNOTICE OF ADDENDUM ADDENDUM 2 CONTRACT NO PROJECT NO UNIT WELL 31 WATER TREATMENT PLANT
February 20, 2017 NOTICE OF ADDENDUM ADDENDUM 2 CONTRACT NO. 7500 PROJECT NO. 10434 UNIT WELL 31 WATER TREATMENT PLANT Revise and amend the contract document(s) for the above project as stated in this
More informationEngineering Design Center. Standard Drawings. 1st Edition -January 2016
Engineering Design Center Standard Drawings 1st Edition -January 2016 Golden State Water Company Standard Drawings 1/11/2016 Table of Contents PART A STANDARD DRAWINGS Section I Pipeline Construction P-1
More informationAmendment to OPSS 493 (Nov 2015) Construction Specification for Temporary Potable Water Supply Services
Engineering & Construction Services Division Standard Specifications for Sewers and Watermains TS 493 September 2017 Amendment to OPSS 493 (Nov 2015) Construction Specification for Temporary Potable Water
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 850 SANITARY SEWER STRUCTURES
ITEM NO. 850 SANITARY SEWER STRUCTURES 850.1 DESCRIPTION: This item shall govern for the construction or rehabilitation of all concrete sanitary sewer structures other than standard sanitary sewer manholes
More informationSECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.
PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record
More informationITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.
AFTER MARCH 1, 2012 ITEM 460 REINFORCED CONCRETE PIPE 460.1 Description. This Item shall govern for the furnishing of reinforced concrete pipe. 460.2 Materials. A. Except as modified herein, materials,
More informationB. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.
SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More informationThis is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations.
COACHELLA VALLEY WATER DISTRICT DOMESTIC WATER CHECKLIST Tract/Parcel No: Project Common Name: Developer: Engineer: Engineer Signature: Date: Phone: Phone: Print: This is only a general checklist; please
More information2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.
General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting
More informationDOCUMENT ADDENDUM No. 2
DOCUMENT ADDENDUM No. 2 PART 1 GENERAL 1.1 DOCUMENT INCLUDES A. Clarifications 1.2 CONSTRUCTION CONTRACT A. The Construction Contract is known as SU095 9 th Street and SU096 Downs Drive Storm Drain Projects.
More informationRICHFIELD CITY CONSTRUCTION STANDARDS
CONSTRUCTION STANDARDS REVISED OCTOBER 2015 Jones & DeMille Engineering, Inc. [0711-211] 1535 South 100 West Richfield, UT 84701 Ph. 435-896-8266 Fax 435-896-8268 1675 South Highway 10 Price, UT 84501
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More informationCity of Wentzville. Standard Specifications and Construction Details Amendment List
Amendment No. 1 Standard Specifications and Construction Details Amendment List Date: September 21, 2009 Subject: SCD 700.23 - Residential Entrance Layout and drawing revised to more clearly show the location
More informationSECTION WATER DISTRIBUTION
SECTION 33 10 00 WATER DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY 1.02 CODES A. Section Includes: 1. Underground water service piping, watermains and appurtenances. A. All work shall comply with the most
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationA.2.a Random Riprap... Table
3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide
More informationCITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION
601.00 RIPRAP 600.00 GENERAL CONSTRUCTION 601.01 DESCRIPTION. This work shall consist of furnishing and placing riprap protection of the type specified at the locations and in reasonably close conformity
More informationCULINARY WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix B
CULINARY WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix B RIVERDALE CITY CAPITAL FACILITIES PLAN CULINARY WATER Engineer's Cost Estimate January 2009 Project Name: Culinary Water Reservoir - Tank
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS
PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment
More informationItem Name Description Unit of Measure Mobilization Per WSDOT Lump Sum
Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of
More informationAttachment D-1: Civil/Structural Scope of Work
Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,
More informationCHAPTER 6. Sanitary Sewer
CHAPTER 6 Sanitary Sewer A. Introduction All proposed developments, subdivisions, and buildings must have a properly designed and constructed sanitary sewer collection system. The system shall provide
More informationUnderground Piping for Private Hydrants & Sprinkler Supply Line
City of Brea Brea Fire Department Fire Prevention 1 Civic Center Circle Phone: (714) 990-7655 Underground Piping for Private Hydrants & Sprinkler Supply Line PURPOSE The provision of adequate water supplies