Vest Process Propane Cavern Project, Norway

Similar documents
TUNNEL CONSTRUCTION GUIDELINES 05 - GUIDANCE NOTE ON PRE-EXCAVATION GROUTING FOR

Ground Freezing for Tunnel, Shafts, and Adits

Sika Injection Systems for Concrete Structures. Concrete Structures

Injection Systems for Concrete Structures. Causes, Remedies and Repairs

Underground Waste Depositing at Odda, Norway

Tunnelling and Underground. Construction Technology

Wastewater Capital Projects Management Standard Construction Specification

SHREE DUJA SPRAY EQUIPMENTS

SikaInjectionSystemsfor ConcreteStructures

D&B versus TBM some case stories

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Groundwater management during the construction of underground hydrocarbon storage in rock caverns

SIKA EGYPT. Injection Systems. Scope: Highly expansion solvent free water-reactive two part Polyurethane foam injection system

Handling ground water ingress in underground storage cavern Saikat Pal, Gopi Kannan, A. Nanda

Solutions for. Coal Mining. Expanding Horizons Underground

Freezing techniques made a new tunnel possible

HA Flex LV AF /Flex SLV AF

CSI SPECIFICATIONS CRYSTALLINE WATERPROOFING LEAK REPAIR Section

WATER LINE IN TUNNELS

Key Technology for Grouting behind Wall of Single-formation Shaft Wall in the Surface Soil Segment of Waste Shaft

Forensics by Freezing

Specialising in Ground Engineering & Slope Stabilisation

Weber t unneling solut ions

HA Cut AF. Product Data Sheets. Product Description. Product Advantages. Field of Application

Part 30 MAPEI. OPC, MC or PUR III-2012

Section WATER LINE IN TUNNELS

Lessons Learned from a 60 CIPP Storm Sewer Liner Installation. Robert Stolt, PE Christopher Beranek, PE

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

Wassara Jet grouting hammer. - Enabling single fluid jet grouting in difficult formations!

Lessons learnt from constructing the FE tunnel incl. some monitoring results

Appendix VIII. Guidelines for groundwater bores and wells

MASTERFLEX 900-FUKO Injection System

Membrane for tunnels and underground construction

SSAB ERB - Expandable Rock Bolts

Grouting for Freezing

Application of airless shotcrete system to tunnel construction

Installation of RD pile wall in Peterhead harbour. Piet van Breukelen Helsinki,

Solutions for. Coal Mining. Expanding Horizons Underground

Injection. Solutions for Underground Construction

Spetec A worldwide standard in grouting

Solutions for tunneling and mining TBM. Expanding Horizons Underground

Artificial Ground Freezing: An Environmental Best Practice at Cameco s Uranium Mining Operations in Northern Saskatchewan, Canada

TBM rescue projects using shafts and ground freezing

Applications (As provided by Avanti International)

SECTION 39 - MANHOLES TABLE OF CONTENTS

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

MUD ROTARY TECHNIQUES. MUD Rotary Drilling Method 12/11/2017. Roger E. Renner, MGWC MUD ROTARY DRILLING. Rotary Well Rig

RESIN AND CEMENT GROUTING SOLUTIONS

DOPAS EPSP Experiment

Construction Technology B (CON4313)

Madewell Products Corporation December Industrial Court Alpharetta, GA Office: (770) Fax: (770)

Civil Engineering Construction I (CBE5031)

Rock mass grouting Author: Prof. Dr. habil. Heinz Konietzky (TU Bergakademie Freiberg, Geotechnical Institute)

Quality management system. Environmental management system. Occupational health and safety management system.

CSI SPECIFICATIONS SURFACE-APPLIED CRYSTALLINE WATERPROOFING Section

Appendix C. Construction Programme

water-powered drilling in mining

water-powered drilling in mining

Report. Corrosion protection of rock bolts with Pc-Coat. 100 years lifetime. Author(s) Pc-Bolt TM. NC-Bolt. SINTEF Industry. 2018: Restricted

CSC SPECIFICATIONS SURFACE-APPLIED CRYSTALLINE WATERPROOFING Section

CSI SPECIFICATIONS SURFACE-APPLIED CRYSTALLINE WATERPROOFING Section

GROUTING DURING THE DRIVING OF DRIFTS AND TUNNELS

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

REHABILITATION. Geopolymer & Hybrid Cements. > Manholes > Sewer & Storm Pipes > Other Civil Infrastructure. vortexcompanies.com

The Stendafjellet Rock Quarry and Underground Waste Disposal site

Typical Specifications of Compaction Grouting Scope

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990

GMA. gma.se. Grouting and Injection Products. Ground Machinery Applications AB

DOLOMITE RISK MANAGEMENT PROCEDURE FOR IRENE GLEN HOMEOWNERS ASSOCIATION

Feasibility Study of Underground LNG Storage System in Rock Cavern

water-powered drilling in ground engineering

Injectable hose with integral valves for sealing construction joints in watertight structures

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

Application for Drilling Permit Instructions. last updated: 3/1/2018

COMMUNITY BOARD EIGHT

Cross Passage - 18 Cross Passage - 19

UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland

TECHNICAL SPECIFICATION FOR CURED-IN-PLACE MANHOLE REHABILITATION LINER SYSTEM

SECTION DRILLED CONCRETE PIERS AND SHAFTS

Water Management. Solutions for Underground Construction

The Rio Grande project - Argentina

MONTREAL AT WORK New tunnel construction starts across the city. NORTH AMERICAN EDITION October ~ November 2017

Construction. Injectable Hose for Sealing Construction Joints in Watertight Structures. Product Description. Tests. Product Data

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

San Antonio Water System Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

SECTION DRILLED CONCRETE PIERS AND SHAFTS

INTERNATIONAL SEMINAR LONG TUNNELS

Injectable Hose With Integral Valves for Sealing Construction Joints in Watertight Structures

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

MODERN PRE-INJECTIONS IN UNDERGROUND CONSTRUCTION WITH MICROCEMENTS AND LIQUID COLLOIDAL SILICA FOR WATER INGRESS REDUCTION AND GROUND IMPROVEMENT

Construction. Injectable hose with integral valves for sealing construction joints in watertight structures. Product Description. Product Data.

WEBAC 240. Technical Information. Range of application WEBAC 240. Examples

SPECIFICATION FOR JET GROUTING

Perfect Manhole Installation Manual May 2012 Rev 8 Perfect Manhole System Precast concrete manholes with load bearing elastomeric joints

Onshore terminal plants

Presentation Outline

Hydrophilic Polyurethane Grout

NARVIK VANN KF , THOMAS BRÆNDVIK, DEPT MANAGER PROJECTS, NARVIK VANN KF

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY

INNOVATING GROUND SUPPORT.

Transcription:

Vest Process Propane Cavern Project, Norway Fig 1: The rock cavern for propane storage. To meet the increasing demands for propane storage volume at the Mongstad reffinery plant, an additional underground rock cavern has been constructed. MIKA AS, a Norwegian contractor specialised in underground projects, was engaged by Statoil the operator for Vest Process to construct an underground gas storage cavern. The cavern is located at Statoil Mongstad, north of Bergen in Norway. The Project The civil contract was awarded MIKA AS in November 2001 and construction started immediately in December 2001. The contract value is 80 mill NOK. The Cavern/tunnelsystem To enable storage of liquified propane in an unlined rock cavern, the propane has to be stored at 42 o C. To prevent propane leaking out from the cavern, a water seal with ice surrounding the cavern has to be built up. To secure a ground water head larger than the gas pressure above the liquified propane, a total of 4000 meters of guided boreheads have been drilled to establish a water injection system above and around the cavern. The top of the cavern is situated 50 m below sea level. The water injection system (water curtain) consists of a horisontal drilled system, drilled from a chamber established besides the cavern, approx 20 m above the top of the cavern, and a vertical drilled system established from the surface. The used boreholediameter is 4. 1

To establish an efficient freezing zone surrounding the cavern, without ice building up inside the cavern, and at the same time have the water curtain system running, it is crusial to minimize the amount of water leaking into the cavern. The design criteria was set to 15 ltr per min, as a total for the cavern. To minimize construction costs, the cavern is shaped like a laying bottle, and entrance to the cavern through the bottle neck. During the construction phase, access to the cavern is through a 600 m long tunnel, constructed from the suface down to below sealevel. The cavern is sealed of with a concrete plug. The plug will have the same requirements to leakage as the cavern itself. The construction and sealing of the concrete plug is therefor an important technical challenge to be solved. Propane is filled into the cavern from the surface through vertical pipes brought down to the cavern through 70 m long raise drilled shafts. A total of 6 shafts were constructed to bring gas and necessary utility and instrumentation system into the cavern. The access tunnel will be filled with water before propane is filled into the cavern. The propane can now be injected to a spray system in the cavern. Fig 2: The concrete plug The working method The excavation of the cavern was carried out in different stages, first the top heading, then benches and invert. The final measurements of the rock cavern is a height of 34 meters, a with of 21 meters and a total length of 134 meters. The ground mass comprised of light and dark anorthosic gneiss, amphibolite and gabro. A program was developed for systematic pregrouting of all excavation stages (top heading, benches and invert). All grouting was completed using Rheocem 900 ultrafine cement with the superplasticiser Rheobuild 2000PF at 1.5% by weight of cement. The w/c of the grout varied between 0.8 to 1.0. Stop pressure for the grouting procedure could be up to 80 bars. Fig 3: The pre-grouting operation 2

The pre-grouting operation required approx 30,000 m of borehole drilling. The holes with lengths from 13m to 21m were always planned and drawn in a special pattern to cover the correct area around the cavern. Grout consumptions was 410 tonnes of Rheocem 900. Due to the fast setting characteristics of the Rheocem 900 ultrafine cement, the construction cycle was not interrupted as with standard microcements. Measurements of the total ground water ingress after the excavation, showed a wateringress less than 2.0 l/min for the whole cavern. The shafts For technical installations and piping, 6 shafts with a diameter of 2,1 meters and length 70 meters length each, were raise drilled. Some grouting had to be done in the 450 m of vertical shafts passing (diameter 2.1 m). The shafts have steel lining with annulus concrete. Some water was trickling in the rock/concrete contact. To stop the water at the bottom part, 400 kg of MEYCO MP355 1K polyurethane foam was used. After this blockage was in place, a total of 500 l of MEYCO MP320 silica gel was injected. The injection hoses in the steel/concrete contact were also injected by MEYCO MP320. Fig 4: The shafts 3

Time schedule All blastings, sprayed concrete and injection works, "rock works" was completed in November 2002. The cavern is completed for propan april/may 2003. Freezing process: To allow storage of propane in liquid form, the gas has to be stored at -42ºC. The freezing sequence of the surrounding rock is started by air circulation and at the end by filling liquid propane. To work efficiently, gas storage caverns have to avoid leakages to the surroundings and water ingress with ice build-up. It is therefore crucial to tightly seal the rock during all stages of construction and operation. This has been achieved by systematic pre-excavation grouting. Fig 5: The freezing sequence inside the cavern The freezing period by air circulation, allowed us to check out leakages and eventual problems with cracking, rock before initiating propane to the cavern. Some ice will appear during this period and will be removed manually for safety reasons, tells Site Manager Sven Oen in a comment. When we reach the 0 gradient 3 meters into the rock, the air freezing period is finished and the temperature inside the cavern is 27 o C. MIKA has been responsible for detail engineering and performance of the freezing process with cooled air. Teknotherm AS, Oslo has participated with engineering and has delivered the necessary equipment to the freezing plant. From the freezing plant installed close to the access tunnel entrance, where ammonia is used as refrigerant, a secondary medium consisting of 29 % water calcium chloride (CaCI 2 ) is pumped down to the cavern through 6 pipes. Fig 5.2 The freezing plant The secondary circuit is cooled down in a wet surface evaporator, and pumped through 8 air coolers installed in the cavern. Before the air coding period is finished, and the propane filling can commence the air, comparative in the cavern shall be colder than 24 o C and the 0-isotherm should nowhere be closer to the cavern surface than 3 m and eventually ice build up in the surface removed. 4

To seal off the cavern, the last point finally, the concrete plug will be closed, and the access tunnel is filled with water. Highlights: Key technical description Volume blasted 100 000 m 3 including the access tunnels ShotCrete 2 000 m 3 Drilling for pregrouting 30 000 m Grouting 410 ton microcement Drilled shafts 420 m Ø2100 mm Construction concrete 1600 m 3 Guided drilling for a waterinjection system 4000 m Who is MIKA? MIKA is one of the leading contractors in hard rock tunnelling, cavern, shafts, diving and marine work in the Nordic countries. MIKA was established in 1988 Total amount of employees is 120 Annual turnover: 260 mill NOK 2003 (budjet) MIKA AS are certified by Det Norske Veritas (DNV) in both NS-EN ISO 9001:2000 (QA/QC) and NS-EN ISO 14001:1996 (HSE) The hard rock work is mainly located in Norway and Sweden, while the subsea department is working internationally with project experience from all over the world Web site: www.mika.no Contact persons: Project Manager: Axel B. Olsen Site Manager: Sven Oen 5