LCA Case Study for O Hare International Airport Taxiway A &B Rehabilitation. Presented by: John Kulikowski, PMP, LEEDAP+ 12 April 2017

Similar documents
REHABILITATION OF RUNWAY 11/29 AT CFB BAGOTVILLE. Presented by: Marla Hughesman CAPTG Sunday Workshop 12 September 2010

Regional LCA Tool Development and Applications

Energy Use and GHG Emissions Basics for Pavement Materials and Construction Processes Energy Use and GHG Emissions for Pavement Preservation

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five

Concrete Pavement: Concrete Pavement Basics. Basic Components of a Concrete Pavement. Concrete Pavement Types. Jointed Plain

Mitigation Strategies for Reflective Cracking in Pavements. Mostafa Elseifi Nirmal Dhakal

Pavement Design. TTP Orientation Seminar 2017

12/11/ th Annual Illinois Bituminous Paving Conference December 11, 2013

Pavement Design. TTP Orientation Seminar 2013

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted June 21, 2018

CE 563 Airport Design

Pavement Management Systems

PRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW

SECTION PAVEMENT STRUCTURE ANALYSIS

Sustainability Strategies for Flexible Pavements

Integrated Pavement Solutions

Design and Rehabilitation Strategies for Sustainable Concrete Pavements

Evaluation of Concrete Pavement Repair Using Precast Technology in Virginia

Alligator Cracking. Light. Medium. High

Pavement Design. TTP Orientation Seminar 2013

Concrete Pavement Preservation Integrating Engineering, Economics and the Environment. John Roberts International Grooving & Grinding Association

SOM August 2009 Alaska

Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25

Maintaining your roads with Asphalt

Webinar on: Concrete Overlay Design Details and Joints. Dale S. Harrington P.E. March 5, 2015

Design of Illinois Tollway Composite Pavements

100 Pavement Requirements Pavement Design Concepts 200-1

CHAPTER 11 PAVEMENT TYPE DETERMINATION

Concrete Pavement Preservation. Integrating Engineering, Applications and the Environment

SEAUPG ANNUAL MEETING NOVEMBER 13, 2013

September 14, Coshocton County Regional Airport Authority Richard Downing Airport I Airport Rd. Coshocton, OH 43812

Environmental Assessment and Economic Analysis of Porous Pavement at Sidewalk

TECHNICAL PAPER

Contractor Experience with Precast Bridge Elements in Utah. Eric Wells. Granite Construction

The Role of Pavement in Reducing Greenhouse Gas Emissions

Best Practices in the Design and Construction of Airfield Composite Pavements. George Nowak, P.Eng.

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

Minnesota Airport System Pavement Evaluation 2010 Update

FEBRUARY 13, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $9,000,000.00) Bids. Kokosing Construction Company, Inc. $8,623,609.96

TABLE OF CONTENTS APPENDICES

Session 3: Concrete Pavement Evaluation

Accelerated Pavement Testing at the Geotechnical and Structures Laboratory

Special Specification 3005 Scrub Seal Treatment

MNDOT PAVEMENT DESIGN MANUAL

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Advisory Circular. Airport Pavement Management System

Hot Applied Chip Seal Design and Construction. NWPMA Vancouver, WA 2017

HAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003

Paved Areas: Standards and Maintenance Program

Airfield Pavement Life Cycle Assessment Framework and Guidelines

Life Cycle Cost Analysis July 2011 Materials Division Page 1 TABLE OF CONTENTS V. ASPHALT PAVEMENT CONSTRUCTION/RECONSTRUCTION...

Concrete ete Pavement s Ultra Thin Overlay

LIFE CYCLE COST ANALYSIS FOR USE OF PRECAST PRESTRESSED CONCRETE SLABS IN REPAIR OF CONCRETE PAVEMENT

DECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids

Environmental Assessment of Pavement Alternatives: Decision-Making in Light of Current Knowledge and Unresolved Questions

San Francisco Bay Area Green Initiatives. Theresa Romell, Principal Planner/Analyst, Metropolitan Transportation Commission October 12, 2016

Pavement Preservation: Theory and Treatments. APWA Norcal Conference Presented by: Telfer Pavement Technologies,LLC Cesar Lara

Concrete Pavement Preservation and Optimization

ERIC D. MOODY DISTRESS IDSTORY

STATUS REPORT Congestion-Relief Program. Steve Gillen Illinois Asphalt Pavement Association March 12, 2007

APPENDIX B RUNWAY PAVEMENT STRENGTHENING STUDY

MNDOT PAVEMENT DESIGN MANUAL

BOCA Project Suitability, Design and Construction

PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE

2010 Midwestern Pavement Preservation Partnership Conference

Green Concrete using Recycled Aggregate at International Airport

Concrete Pavement Preservation. Integrating Engineering, Economics and the Environment

Princeton Municipal Airport (PNM)

CHAPTER B TABLE OF CONTENTS

ODOT District Pavement General Notes P401: ITEM PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN

Department of Street Services

WSDOT Pavement Preservation Performance

BASE CONSTRUCTION MATERIALS A Aggregate

A Methodology for Sustainable Mechanistic Empirical Pavement Design

Innovative Sustainable Pavement Solutions

-Buried Treasure- Finding Innovative Solutions by Looking Beneath the Surface

PCC Pavement Rideability

Concrete Pavement Preservation 2018 TRC Transportation Engineering Conference May 16, 2018 Hot Springs, Arkansas

2399 Pavement Surface Smoothness

2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT

Cold In-Place Recycling In Sonoma County

Pavement Rehabilitation Options in Indiana. Dave Holtz Tommy E. Nantung Lisa Egler-Kellems Indiana Department of Transportation

STRUCTURAL EVALUATION & TREATMENT SELECTION FOR LOCAL ROADS. Nick Jones Local Technical Assistance Program Utah State University

SECTION ASPHALT PAVING AND SURFACING

RECONSTRUCTION OF DISTRESSED PAVEMENTS Full-Depth Rehabilitation (FDR) (Portland cement)

Section 505. CHIP SEALS

Rehabilitation of PCC Airfield Pavement with Asphalt. H Wayne Jones, P.E. Asphalt Institute

GlasGrid Asphalt Pavement Reinforcement. October 21, 2016

AASHTO-FHWA Technology Endorsement Construction Analysis for Pavement Rehabilitation Strategies

COMPOSITE PAVEMENT OVERLAY

TABLE OF CONTENTS APPENDICES

Implementing An effective Airport Pavement Management System

Rigid Pavement Climatic Effects in Illinois

550 Surface Treatments

District Five Concrete Pavement Update: 2010

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

VDOT MECHANSTIC EMPIRICAL PAVEMENT DESIGN (MEPDG) IMPLEMENTATION

Overview. Preventive Maintenance Concepts. What are thin and ultra thin mixes. Experience in Michigan with ultra thin

Federal Highway Administration Concrete Overlays Program. Sam Tyson, Office of Pavement Technology AASHTO Subcommittee on Construction August 2009

Transcription:

LCA Case Study for O Hare International Airport Taxiway A &B Rehabilitation Presented by: John Kulikowski, PMP, LEEDAP+ 12 April 2017

Overview Criticality of Airports LCA-AIR Overview Taxiway A&B Background Rehabilitation Options Results Future Research (www.wallpapersxl.com) Acknowledge: Mohammed Sawalha, Michael Sladek, Dr. Hasan Ozer, Dr. Jeffery Roesler and O Hare Modernization Program 2

Criticality of Airports Airports process 3.3B passengers w/3.6t passenger-miles Airports process 55M shorttons freight annually Accounts for 8.2% of Transportation Sectors greenhouse gas (GHG) emissions (U.S.) Accounts for 3% of world GDP (www.wired.com) 3

Limitations and Assumptions Jet fuel consumption is modeled as kerosene combustion in industrial equipment. Construction/mx equipment only consider the diesel fuel consumed Feedstock energy is not considered. 90% of the maximum take off weight was used for aircraft. The aircraft fuel consumption during flight is constant. Air resistance is constant. Airfield lights run 12 hrs/day Snow removal consumes fuel but deicing chemical impacts are not included in the LCA. 5-mile haul distance for concrete (PCC) and asphalt (AC) for initial construction. IRI adapted from roadways Sweeping assumed to occur 1 per week. 4

LCA-AIR Tool Overview 5

Taxiway A & B Constructed 1986-1988 11,088 by 75 (25 x 25 slab) 2011 PCI <75 (~40%<50) Longitudinal/transverse crack center lane (primary) Mx plan called for 75% reconstruction by 2013 Significant mx on 25% Issues with surface drainage and probable underdrain failure High vol of medium aircraft Group 1-4; <300 kips (90% traffic) 6

2018 Traffic Projections - Groups 1-4 67,749 68,472 57,526 4,296 40,773 76,974 11,727 76,070 N 100,191 76,043 2,300 33,093 4,873 99,939 246,157 80,992 104,812 8,359 5,333 108,767 33,080 100,656 31,606 247,055 109,002 16,045 107,745 21,671 125,001 8,411 259,535 63,698 50,041 124,072 163,827 40,010 172,423 204,308 210,693 114,905 58,689 10,808 272,331 171,883 180,492 39,304 82,520 81,758 54,993 180,597 145,306 174,331 154,203 8,421 54,800 148,357 51,291 269,436 214,600 22,238 7 229,851 374,133 420,035 410,275 439,506 411,363 404,214

Rehabilitation Options 3 selected for further analysis Rubbilization, Precast Concrete Panel (PCP), Reconstruction Impact to airlines (closures), longevity and elevation constraints to adjacent features Analysis included LCA as another decision data tool 8

LCA Implementation Rehabilitation occurs at the 30 yr point Extend pavement life to 50 yrs (20 yrs more) Rubbilization with mill/inlay receives mill/inlay 10 yrs later PCP & full-depth reconstruction has 20 yrs design life Scope include 200 keel section slabs on southern side of each taxiway (125,000 ft 2 ) Material production (MP) and construction, maintenance and rehabilitation (CMR) used functional unit of yd 2 Use phase used functional unit pound-mile 9

Material Production and Initial Construction MP impacts are the same for each strategy Initial construction equipment impacts Fuel consumption for PCC: 15,794 gal Fuel consumption for AC: 11,899 gal Mx activities vary greatly around aircraft (24/7/365) Activities were aggregated over time as occurred at specific intervals for analysis 10

Developed Mx Schedule PCC Restriping airfield markings every ten years Joint and crack sealing every eight years Full and partial depth repairs every fifteen years Brooming every other day AC & AC Shoulders Restriping airfield markings every ten years Crack sealing every ten years Asphalt patching every fifteen years Mill/inlay every fifteen years Mill/inlay 10 years after the initial rubblization with mill/inlay section 11

CMR Phase - Rubblization w/mill & Inlay Rubblization consumed: 954 gal AC inlays (no shoulders) consumed: 553 Brooming critical; 1/5 days shows a 10% redux (weigh FOD!!) Crack sealing time & energy intensive Total fuel consumed: 204.6K gals 12

CMR Phase - Rubblization w/mill & Inlay Reused/left in place the most material of strategies Used 24% less energy than PCP Used 30% less energy than reconstruction Used 43% less GWP than PCP Used 37% less GWP than reconstruction 13

CMR Phase - Rubblization w/mill & Inlay Unlike roadways, increase fuel consumption doesn t dominate.limited time for tire pavement interaction Including fuel consumed in flight Use phase is more dominant than roadways CMR Phase Mat l Prod Phase Use Phase ΔIRI CMR Phase Mat l Prod Phase Use Phase ΔIRI 14

CMR Phase - Precast concrete Panels Slab lift-out method Additional 523 gal demolition of PCC PCP placement added 2,973 gal Steel and leveling sand added (Fischer, 2002) work/material to impacts Diamond grinding (whole area) added 761 gal Work w/manufacture can increase tolerance = spot grinding Reduction in crack sealant and patching operations Total fuel consumed CMR: 206.1K gal (2,052 gal more than rubbilization) (Kulikowski,2015) 15

CMR Phase - Precast concrete Panels Cast on airfield Used 8% less energy than reconstruction Installation is less intensive Used 9% more GWP than reconstruction Attributed to the two mats of steel in the PCP Open to traffic after placement (no curing) (Illinois Tollway) (Tsubokawa Y., 2015) 16

CMR Phase - Precast concrete Panels Chart shows and increase in the CMR phase impacts Full-depth PCC and steel CMR Phase Mat l Prod Phase Use Phase ΔIRI CMR Phase Mat l Prod Phase Use Phase ΔIRI 17

CMR Phase - Reconstruction Most material removed Removal of PCC, AC base course and aggregate subbase Hydraulic hammer on excavator - rapid breakage and removal More activities, but fairly rapid.except curing! Can t reopen next day Total fuel: 205.2K gal 1,175 gal more than rubbilization 877 less than PCP (Kulikowski,2015) 18

Strategy Summary Breakdown Per Phase (ΔIRI) 20

Quantified Impacts Rank 1 Strategy Rubblization w/mill/ac Inlay 2 Reconstruction 3 Precast Concrete Panel Impact category Global warming Global warming Global warming Unit Rank Strategy Impact category Unit 1 2 Rubblization w/mill/ac Inlay Precast Concrete Panel 3 Reconstruction Primary energy consumption (renewable + nonrenewable) Primary energy consumption (renewable + nonrenewable) Primary energy consumption (renewable + nonrenewable) Total Impact Per yd 2 Total Impact Per lb-mile Total Impact Per yd 2 (ΔIRI Only) Total Impact Per lb-mile (ΔIRI Only) kg CO2 eq 2.395E+03 4.31E-10 2.00E+02 3.93E-11 kg CO2 eq 2.409E+03 4.73E-10 2.15E+02 4.22E-11 kg CO2 eq 2.413E+03 4.74E-10 2.18E+02 4.29E-11 Total Impact Per yd 2 Total Impact Per lbmile Total Impact Per yd 2 (ΔIRI Only) Total Impact Per lb-mile (ΔIRI Only) TJ 0.1861 3.58E-08 0.00518 1.02E-09 TJ 0.1863 3.66E-08 0.00540 1.06E-09 TJ 0.1864 3.66E-08 0.00547 1.07E-09 21

Further Research Areas LCA Tools for Airports! Develop complex components of use phase Aircraft tire-pavement interaction Roughness impacts on fuel burn Air resistance/density for in-flight Fuel burn intensity for various flight status Establish allocation standard for aircraft fuel burn Attribute ½ and ½ to each airfield or... other method to account for fuel burn impacts Partnership with aircraft manufacturers Account for tug (plane & freight) and ground equipment End of life phase unique opportunities and timeline which differ from roadways 22

Questions 23

Backup Slides 24

LCA-AIR Use Phase - Aircraft Fuel Consumption Vehicle tire-pavement interaction is heavily researched for fuel consumption increase from ΔIRI not the case aircraft tire-pavement interaction No IRI models for airfields Adapted an IRI deterioration model from roadways Aircraft are only on pavement for ~30 min/flight Limited and short-sighted accounting for combustion of JP-8 Significant amount of fuel consumption is take-off and cruising (no tire pavement interaction!!) Fuel burn intensity for short vs. long flights 25