SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five
|
|
- Stella Cain
- 5 years ago
- Views:
Transcription
1 SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five
2 Project Overview Location SR 600 / US 92, Volusia County FPN: , Kepler Road (Start) FPN: , Tomoka River (End)
3 Overall Project Overview Rehab Project Only (4.5 miles), MP 2.7 to MP 7.2 Rehab and Reconstruction Project with Test Site (8.2 miles), MP 7.2 to MP 15.4 SR 600 / US RT 92 in Volusia County
4 Reconstruction Project Overview WB Raised Section: MP 9.2 to 11.1 (1.9 miles) Test Site : MP 9.42 to 9.57 (0.15 miles/793 ft) Test Site
5 Project History WB Lanes Constructed in 1940 s EB Lanes Constructed in 1970 s Shoulders Const. approx 1997 WB Lanes Flooded MP 9.0 to MP 10.5 (TBWMA to W. of Red John Dr) Test Section Located at MP 9.42 Numerous Individual Slab Failures
6 Show me the # s Clean/Seal Joints 364,603 LF Clean/Seal Random Cracks 3,804 LF Removal Existing Concrete Pavement 64,576 SY Plain Cement Pavement ,534 SY Concrete Pavement Slab Replacement 9,703 CY Grinding Concrete Pavement 299,503 SY Original Contract Amount $13,651, Original Contract Time 680 Days
7 Floodplain Zone A Elevation Not Determined
8 Drainage Investigations 25 Yr Flood Stage Elevations (MP 8.5 MP 12.3)
9 Existing Typical Section Crowned 12-18
10 Existing Typical Section MP 9.0 MP 10.5 WB Lanes Lower than EB 12 to 18
11 Pre-Construction Issues Lanes showing significant distress Never had true major rehabilitation (mostly localized slab replacements) WB Lanes experienced overtopping during significant storm events Ride quality deterioration
12 Causes of Pavement Distress Age (Loadings/67 yrs) Surface/Ground Water Fluctuations Weak Soils Slab Configuration (untied, 11ft x 20 ft) Joint Deficiencies (dowel corrosion, joint faulting, joint width, joint sealant) Differential Loading (slab length, edge stress/narrow lane, untied slabs, joint faulting/impact loading)
13 Typical Lane Pavement Distress
14 Pavement Rehabilitation Methods CONCRETE REHABILITATION Slab Replacements, Joint Reseal, Diamond Grind Finish NEW CONCRETE OVERLAY ON RAISED PROFILE Crushed Concrete Sub-base (recycled slabs) 2 Asphalt Overlay of the Crushed Concrete Sub Base Doweled Cast in Place Concrete Pavement NEW PRECAST POST-TENSIONED SLABS OVERLAY ON UNDISTURBED EXITING ROAD Undisturbed Existing Concrete Road Variable Asphaltic Overlay (platform) Precast Post-tensioned Concrete Pavement Diamond Grind finish
15 Pavement Rehabilitation Methods PPCS TEST on Raised Profile Area 793 ft of WB Lanes Build on top of existing slabs (undisturbed) 2 minimum asphalt layer (working platform, cross slope correction) Positive Drainage (non-erodible base, edge drain) Diamond Grind Finish
16 PPCS &Roadbed Draft Design
17 Key Design Considerations Roadbed or Road Foundation Model Fast Paced Construction Do Nothing to existing slabs regardless of condition Use Conventional Materials/Methods Widen with Minimal Effort but Maximum Benefits Upgrade Lane Widths Cross Slope Correction Non Erodible Base Model for Easy MOT & Construction Operations Stable Working Platform
18 Key Design Considerations For PPCS Components Minimize Field Assembly Difficulty Post Placement Poured Joints vrs Epoxy During Placement Stay within Asphalt Specs Tolerances Minimize Surface Irregularities External Bolsters Diamond Grinding Post Tension System Independent Operation
19 PPCS & Roadbed Final Design
20 Roadbed Components (Foundation)
21 Local Prestress Producer Dura-Stress, Inc. Leesburg, FL Florida Department of Transportation (FDOT) approved prestress plant (PCP )
22 Roles and Responsibilities Dura-Stress provides Quality Control (QC) FDOT in-house & consultants provide Quality Assurance (QA)
23 Plans & Shop Drawings Required concrete strength 5500 psi Reinforcing steel ASTM A615, Grade 60 Pre-stressing strand ASTM A416, Grade 270
24 Specified Tolerances Dimensions pre-pour and post-pour Range from 1/16 to ¼ (very tight)
25 Controlled Environment Indoor building
26 Forms Allowed wood face for smooth finish
27 Prestressing 31.0 kips per strand planned Measured and Recorded Bed Jack
28 Reinforcing Placement Inspected before concrete placement Chair Block
29 Post-Tension Ductwork Inspected before concrete placement Plastic Duct Block Wood (Keep Shape During Concrete Placement)
30 Concrete Production Dura-Stress provides concrete on-site FDOT Approved central mix batch plant (11-013) Use FDOT approved materials (i.e. cement, aggregates, etc.) FDOT inspects concrete batch plant quarterly Concrete transported short distance by Tucker built
31 Concrete Testing QC- every 50 CY or each day (plastic properties & strength) QA randomly test once for every four QC tests On-site Approved Laboratory (P11-013)
32 Concrete Placement Good slump & aggregate distribution
33 Concrete Finishing Meet tight tolerances
34 Concrete Finishing Medium broom finish Broom
35 Curing Blankets Ideal environment out of weather
36 Transfer to Storage Placed on flat bed truck in building
37 Storage
38 Loading & Shipping
39 Successes Partnering between producer, contractor, FDOT & FHWA Knowledgeable QC and QA staff at plant Using local approved producer Controlled environment for concrete and tight tolerances
40 Roadbed Components (Widening)
41 Roadbed Components (Working Surface)
42 Road Surface Components (PPCS)
43 Grouting of the PPCS
44 Full Width Construction
45 Box Culvert Cross Section
46 Box Culvert Replacement with Light Aggregate Fill
47 Slab Removal
48 Concrete Slab Removal
49 Drill for Dowel Bar Placement
50 Two Part Epoxy for Dowel Bars
51 Chairs for Larger Slab Replacements
52 6 Slab Ready for Concrete
53 Reinforced Concrete Slabs
54 Concrete Placement
55 Placing and Screeding of Slabs
56 Saw and Sealing of Expansion Joints
57 Final Component (Grinding)
58 Questions???
District Five Concrete Pavement Update: 2010
District Five Concrete Pavement Update: 2010 FTBA/FDOT Construction Conference Roger C. Schmitt, P.E. Orlando February 2010 Continuously Reinforced Concrete Pavement Constructed din 1968 I 95 Project Brevard
More informationEvaluation of Concrete Pavement Repair Using Precast Technology in Virginia
April 24, 2009,St. Louis, MO Evaluation of Concrete Pavement Repair Using Precast Technology in Virginia Shabbir Hossain Research Scientist Celik Ozyildirim Principal Research Scientist A partnership of
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS
More informationConcrete Pavement: Concrete Pavement Basics. Basic Components of a Concrete Pavement. Concrete Pavement Types. Jointed Plain
Concrete Pavement: PCCP Repair & Rehabilitation Applications, Options & Performance Concrete Pavement Basics Purdue Road School March 25, 2003 Basic Components of a Concrete Pavement Surface smoothness
More informationPRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW
Indiana DOT Precast Concrete Pavement Forum Indianapolis, Indiana August 11, 2016 PRECAST CONCRETE PAVEMENT PRACTICES OVERVIEW Shiraz Tayabji, stayabji@gmail.com Applied Research Associates, Inc. (ARA)
More informationHAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003
HAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003 Reviewed and accepted by FHWA on September 29, 2003 Note: Guidelines was revised on to correct
More information-Buried Treasure- Finding Innovative Solutions by Looking Beneath the Surface
-Buried Treasure- Finding Innovative Solutions by Looking Beneath the Surface WHAT IS A TREASURE? --TREASURE-- A Quantity of Precious Metals, Gems, or other Valuable Objects NATIONAL TREASURE ROADWAY --WHAT
More informationLong-Life. Life Concrete Pavements. Virginia Concrete Conference March 10, 2006 Richmond, VA. Kurt D. Smith, P.E. Applied Pavement Technology, Inc.
Long-Life Life Concrete Pavements Virginia Concrete Conference March 10, 2006 Richmond, VA Kurt D. Smith, P.E. Applied Pavement Technology, Inc. Presentation Outline! Background! Goals and Features! Components
More information2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.
JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine
More information5 Concrete Placement
5 Concrete Placement Testing Entrained Air Slump Strength Water/Cementitious Ratio Mixing Placing Concrete Compressive Test Specimens Curing De-Tensioning Multiple Strand Release Single Strand Release
More informationSECTION MISCELLANEOUS CAST-IN-PLACE CONCRETE
SECTION 033053- MISCELLANEOUS CAST-IN-PLACE CONCRETE PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
More informationB. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.
SECTION 1400 - CONCRETE PAVEMENT 1401 SCOPE. This section governs the furnishing of all labor, equipment, tools, and materials and the performance of all work necessary to construct concrete pavement.
More informationConcrete ete Pavement s Ultra Thin Overlay
Concrete Pavement s e Ultra Thin Overlay Larry Scofield, P.E. IGGA 1 Big Preservation Funding, Funding, Funding 1. Decline in Buying Power 2. Increase in Consumption (wear) 3. Decline in Revenue Generation
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS
Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...
More informationIntegrated Pavement Solutions
Integrated Pavement Solutions 1 Product Solutions for Every Paving Need Application Solution Mainline highways Commercial airports General aviation airports PCC pavement Heavy-duty industrial Concrete
More informationDesign and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation
Design and Construction of Concrete Overlays By: James K. Cable, P.E. Cable Concrete Consultation PCC OVERLAY AGENDA Current design & construction features What is needed in a PCC overlay set of plans?
More informationSECTION PAVEMENT STRUCTURE ANALYSIS
MATERIALS PAVEMENT DESIGN 540.02.01 540.01 General SECTION 540.00 PAVEMENT STRUCTURE ANALYSIS 540.01.01 An engineering report covering life cycle cost analysis of the pavement structure shall be made for
More informationSECTION RIGID PAVEMENT
SECTION 02750 PART 1 GENERAL RIGID PAVEMENT 1.1 SUMMARY A. Section Includes: 1. Concrete sidewalks. 2. Concrete stair steps. 3. Concrete integral curbs gutters. 4. Concrete parking areas and roads. B.
More informationMANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:
MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL EFFECTIVE DATE: OCTOBER 14, 2011 200.07 Contractor Quality Control - is replaced with the following: (a) (b) (c) Scope: These requirements
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES
Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle
More information21 PAVEMENTS General Administrative Requirements Standards Personnel Certification
21 PAVEMENTS 21.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with all Project pavements. The permanent pavement structure for all Project roadways is
More informationTHE LOS ANGELES SH 101 REHABILITATION USING PRECAST CONCRETE PANELS
Louisiana Transportation Conference Baton Rouge, LA March 2, 2016 THE LOS ANGELES SH 101 REHABILITATION USING PRECAST CONCRETE PANELS FHWA Precast Concrete Pavement Implementation Team Shiraz Tayabji,
More informationSection CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.
PART 1 GENERAL 1.01 SUMMARY A. This Section includes the following: Section 02775 1. Reinforced concrete sidewalks. 2. Wheelchair Ramps. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete
More informationConcrete Pavement Preservation Partial Depth Repairs
Concrete Pavement Preservation Partial Depth Repairs National Concrete Pavement Technology Center North Dakota Ready Mix and Concrete Products Association Dan Frentress P.E. IGGA 1 Partial-Depth Repair
More informationThis specification refers to the following standards, specifications, or publications:
PRECAST CONCRETE SLAB REPAIR - Item No. Special Provision No 363S01 February 2013 Amendment to OPSS 363, April 2008 OPSS 363, Construction Specification for Repairing Rigid Pavement with Precast Concrete
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More informationCHAPTER B TABLE OF CONTENTS
July 2006 Page B-1 CHAPTER B TABLE OF CONTENTS B.00 Introduction B.01 Definitions B.02 Maintenance Levels B.03 Definition of Traveled Way B.04 Policy for Performing Roadbed Maintenance Work B.05 Surface
More informationPROJECT CONTRIBUTORS
PROJECT CONTRIBUTORS PERVIOUS CONCRETE Making the Impossible Possible Construction of the I-81 Exit 140 Park-n-Ride in Salem, VA Travis Higgs, P.E. VDOT Salem Materials Exit 140 Park-n-Ride location The
More information(D) Surface Slope Bituminous patch in front of the truncated domes must not exceed 5% measured perpendicular to the flow line or edge of roadway.
Last Revision by CO Special Provisions: 09/14/18 Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2018-143 ((2360) PLANT MIXED ASPHALT PAVEMENT (MSCR)) when using this writeup.
More informationThis drawing. is preliminary. and not for. construction or. implementation. purposes. project number 170 END VIEW DESIGN STRENGTHS: PLAN
project number 70 Reference Line 2-0" Reference 3 -" 6-0" 6-0" 3 -" Line Box Culvert Roadway Finished Channel -0" -0" E VIEW 20-0" Riprap 0-0" Riprap Outlet Invert El 87.0 Sta 233+00.00 Inlet Invert El
More information50-Year Concrete Pavements
2018 FDOT- FTBA Construction Conference 50-Year Concrete Pavements Jamshid Armaghani, Ph.D., P.E. Global Sustainable Solutions Jamshid@bellsouth.net Tunnels are designed for 150 years. Bridges are designed
More informationSlab Replacement in Urban Areas
Slab Replacement in Urban Areas High-Early-Strength Concrete Craig Hennings, Executive Director Southwest Concrete Pavement Association Aug 29 2012 California Many Urban Areas 50,000 Lane Miles 16,000
More informationInspection of Concrete Part 2
Inspection of Concrete Part 2 JOINTING IN SLABS, DRIVES, WALKS HOT WEATHER COLD WEATHER Steve Waalkes, P.E. Dir. of Engineering W. Mich. Jointing Why do we joint? Reinforcement Types of Joints Sawing &
More informationCONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS
More informationLIFE CYCLE COST ANALYSIS FOR USE OF PRECAST PRESTRESSED CONCRETE SLABS IN REPAIR OF CONCRETE PAVEMENT
International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 11, November 2018, pp. 1479 1490, Article ID: IJCIET_09_11_143 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=11
More informationA.2.a Random Riprap... Table
3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide
More informationSPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013
SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR
More informationEvaluation and Selection Guide of Method of Repair for Routine
Evaluation and Selection Guide of Method of Repair for Routine Maintenance For TxDOT Maintenance Engineers Product 0-5821-P3 Project 0-5821 Project Title: Develop Guidelines for Routine Maintenance of
More informationCONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 360 NOVEMBER 2015 CONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE TABLE OF CONTENTS 360.01 SCOPE 360.02 REFERENCES
More informationFlorida DOT efforts toward improving Post Tension Durability
Florida DOT efforts toward improving Post Tension Durability By William Nickas 1 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 1 of 73 Post-Tensioning Strategies Enhanced PT Systems
More informationWebinar on: Concrete Overlay Design Details and Joints. Dale S. Harrington P.E. March 5, 2015
Webinar on: Concrete Overlay Design Details and Joints Dale S. Harrington P.E. March 5, 2015 System of Concrete Overlays Concrete Overlays Bonded Overlay System Unbonded Overlay System Concrete Pavements
More informationConstruction and Materials Tips
Construction and Materials Tips Utilizing Slot Stitching for Longitudinal Joint Separation Repair Background Published by the Construction and Bridge Divisions November 2013 Many miles of Continuously
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 PRECAST CONCRETE PIPE 10.1.1 General This section covers material requirements,
More informationChapter 1: INTRODUCTION
Chapter 1: INTRODUCTION Figure 1.1. Photo of deteriorated concrete pavement. Pavement Repair: A Worldwide Necessity The need for rapid repair and replacement of concrete pavement is evident in every large
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS
More informationVDOT MECHANSTIC EMPIRICAL PAVEMENT DESIGN (MEPDG) IMPLEMENTATION
VDOT MECHANSTIC EMPIRICAL PAVEMENT DESIGN (MEPDG) IMPLEMENTATION 2018 Virginia Concrete Conference Richmond, Virginia Girum Merine, PE Senior Pavement Engineer, VDOT Material Division March 2, 2018 Presentation
More informationPAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE
PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE Quality Assurance is not Quality Control Quality control is Contractors responsibility during construction. Quality Assurance
More informationCHAPTER 2. Restricted Residential ½ Street** Design Speed 25 MPH 25 MPH 25 MPH 25 MPH 40 MPH 50 MPH 55 MPH
CHAPTER 2 201 ROADS 201.1 General This section is to assist the designer in determining what is needed for the design of roads in public rights-of-way. For these standards, the terms used are: Restricted
More information550 Surface Treatments
Table of Contents 550 Surface Treatments... 550-1 550.1 Introduction... 550-1 551 Crack Sealing... 550-1 551.1 Project Selection... 550-1 551.2 Design Considerations... 550-1 552 Chip Sealing... 550-2
More informationCement Modified Recycled Base
Supplemental Technical Specification for Cement Modified Recycled Base SCDOT Designation: SC-M-306 (01/18) 1.0 DESCRIPTION 1.1 This section contains specifications for the materials, equipment, construction,
More informationUS-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer
US-131 Over the Muskegon River Corey Rogers, P.E. Bridge Construction Engineer NB and SB US-131 Each bridge is a three-span, 580 foot long, cast-in-place, post-tensioned concrete box girder structure resting
More informationUNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:
SECTION 321610 - CURBING PART 1 - GENERAL 1.1 DESCRIPTION A. This Section specifies requirements for furnishing and installing all types of curbing including the following: granite curb, concrete and bituminous
More information2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT
2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT SECTION 501 PORTLAND CEMENT CONCRETE PAVEMENT 501.01 GENERAL. This item consists of constructing a concrete pavement (with or without reinforcement)
More informationConcrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay
Overlays February 22, 2012 ACPA Pennsylvania Chapter Overlays John M. Becker, P.E. ACPA Penn Chapter February 22, 2012 One of 25 state paving associations affiliated with ACPA National Comprised of approximately
More informationBITUMEN-SET PRECAST CONCRETE PAVING SLABS
SECTION 32 14 13.16 BITUMEN-SET PRECAST CONCRETE PAVING SLABS (1995 MasterFormat Section 02784) NOTE: This guide specification is the U.S. for concrete paving slabs adhered with a neoprene mastic to a
More informationConnecticut PCP Bus Pad Replacement Project. Steve Norton
Connecticut PCP Bus Pad Replacement Project Steve Norton Presentation Overview Need for Rapid Pavement Repair Solutions Project Selection Project Details and Fabrication Construction Sequence Panel Installation
More informationCONSTRUCTION CONFERENCE
CONSTRUCTION CONFERENCE - 2010 Concrete Paving Session February 23, 2010 Greg Schiess 1 2 3 CHANGE 4 TOPICS OF DISCUSSION Implementation of the new Design Guide and related software Pavement Type Selection
More informationPavement Surface Evaluation and Rating. Manual RATING RATING RATING PASER RATING. Concrete Roads
PASER MANUAL FOR CONCRETE ROADS PAVEMENT ENGINEERING SERVICES PASER RATING SUNFLOWER VILLAGE HOMES ASSOCIATION 45800 HANFORD ROAD CANTON, MICHIGAN SME Project Number: 074170.00 July 1, 2016 Pavement Surface
More informationTILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:
PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral
More informationSECTION CONCRETE PAVING
PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 13 13 CONCRETE PAVING A. Extent of concrete curbs, walks, and paving as show on drawings B. Earthwork and prepared sub-base C. Concrete and related materials
More information1.02 RELATED WORK: Refer to the following sections for related work:
SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete
More informationSection 502. HMA CRACK TREATMENT
502.01 Section 502. HMA CRACK TREATMENT 502.01. Description. This work consists of treating cracks in Hot Mix Asphalt (HMA) surfaces using either a saw or rout and seal process or an overband process.
More informationHow to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.
1 How to Select the Appropriate Pavement Rehabilitation Option David Rettner, PE American Engineering Testing, Inc. 2 Pavement Rehabilitation Selection Understanding the Problem 3 Pavement Assessment Pavement
More informationI-64 DUNLAP CREEK BRIDGE REHABILITATION JOINTLESS BRIDGES, DECK OVERLAYS, AND CONCRETE MATERIALS
I-64 DUNLAP CREEK BRIDGE REHABILITATION JOINTLESS BRIDGES, DECK OVERLAYS, AND CONCRETE MATERIALS June 8, 2016 Celik Ozyildirim, PhD, PE, Principal Research Scientist, VTRC, Charlottesville, VA Rex Pearce,
More informationFAA AC 150/ H Draft Principal Changes
FAA AC 150/5370-10H Draft Principal Changes 2018 Indiana Chapter ACPA Workshop Indianapolis, IN Gary L. Mitchell, P.E. Vice President American Concrete Pavement Association Credits Doug Johnson and Greg
More informationConcrete Pavement Preservation 2018 TRC Transportation Engineering Conference May 16, 2018 Hot Springs, Arkansas
Concrete Pavement Preservation 2018 TRC Transportation Engineering Conference May 16, 2018 Hot Springs, Arkansas Peter Taylor, PhD., P.E. ptaylor@iastate.edu 1 Outline Service Life Trigger Values Typical
More informationPavement Design. TTP Orientation Seminar 2013
Pavement Design TTP Orientation Seminar 2013 What are Pavements? Engineered structures in contact with the earth's surface built to facilitate movement of people and goods Pedestrians Personal vehicles
More informationSPECIAL PROVISION Concrete Pavement
1995 Metric CSJ s 0902-48-305, etc. SPECIAL PROVISION 360---036 Concrete Pavement For this project, Item 360, Concrete Pavement, of the Standard Specifications, is hereby amended with respect to the clauses
More informationLong-Life and Sustainable Concrete Pavements
Long-Life and Sustainable Concrete Pavements by Mang Tia Professor of Civil Engineering Engineering School of Sustainable Infrastructure and Environment University of Florida Presentation at 3 rd International
More informationAN INNOVATIVE APPROACH TO SMALL BRIDGE REHABILITATION. Peter Marchant ITS Pipetech Pty Ltd, NSW Australia
AN INNOVATIVE APPROACH TO SMALL BRIDGE REHABILITATION Peter Marchant ITS Pipetech Pty Ltd, NSW Australia Introduction Summary Since first construction our principle infrastructure we are witnessing Increasing
More informationCOUNTY OF BEXAR. Curbed Streets. Residential PUBLIC WORKS DEPARTMENT
COUNTY OF BEXAR PUBLIC WORKS DEPARTMENT 233 N. Pecos La Trinidad, Suite 420 San Antonio, Texas 78207-3188 Main 210-335-6700 DRIVEWAY APPROACH SPECIFICATIONS Curbed Streets Residential Applicability: All
More informationConcrete Pavements. How to Get the Biggest Bang for the Buck in Street/Local Road Applications. Brian Killingsworth, PE VP, Pavement Structures NRMCA
Concrete Pavements How to Get the Biggest Bang for the Buck in Street/Local Road Applications Brian Killingsworth, PE VP, Pavement Structures NRMCA 1 1 How to Get the Biggest Bang for the Buck Definitions
More informationPAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS
SECTION 32 14 13.16 PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs used as ballast and/or paving on
More informationDeterioration of Concrete Roads
Deterioration of Concrete Roads Concrete Roads Joint Spalling Punch outs Cracking Faulting Slab failures Riding Quality Models From USA Chile 2 Types of Deterministic Models Absolute (Concrete HDM-4) Predicts
More informationCONCRETE TILE PAVERS
Section 32 14 13 CONCRETE TILE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for the U.S. is for the installation of concrete tile paving units whose thickness are less than the
More informationSection 504. MICRO-SURFACING
504.01 Section 504. MICRO-SURFACING 504.01. Description. This work consists of preparing existing pavement and providing and placing a micro-surfacing mixture. 504.02. Materials. Provide materials in accordance
More informationNOVEMBER THE CONCRETE PAVEMENT UNIVERSITY Alternative Cement Based Pavement Solutions RCC PAVEMENT FOR LOWER VOLUME ROADS
NOVEMBER 29 2018 THE CONCRETE PAVEMENT UNIVERSITY Alternative Cement Based Pavement Solutions Atkinson Blvd Roseville, CA RCC PAVEMENT FOR LOWER VOLUME ROADS ILLINOIS TRANSPORTATION AND HIGHWAY ENGINEERING
More informationStructural Lightweight Concrete for Accelerated Bridge Construction
Structural Lightweight Concrete for Accelerated Bridge Construction AASHTO T-4 Meeting June 28, 2005 Reid W. Castrodale, PhD, PE Carolina Stalite Company ROTARY KILN PRODUCED STRUCTURAL LIGHTWEIGHT AGGREGATE
More informationRehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements
University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt
More informationA. Submittal Procedures: See Article 13 of the General Conditions.
SECTION 321313 - CONCRETE PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Driveways. 2. Roadways. 3. Parking lots. 4. Curbs and gutters. 5. Walks. B. Proposed Substitutions: See Article 2,
More informationSECTION 415 REINFORCING FOR CONCRETE
SECTION 415 REINFORCING FOR CONCRETE Module 5 August 2018 Release 10, Module 5 1 Release 10, August 2018 5-1 415 1 Description Furnish and place steel and fiber reinforced polymer (FRP) reinforcing of
More informationSection REINFORCING STEEL
Section 03210 PART 1 GENERAL 1.01 SUMMARY This Section includes the furnishing and subsequent placing of reinforcing steel, deformed and smooth, chairs, ties, splicing devices, and other reinforcing accessory
More informationSPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit
2004 Specifications CSJ: 0028-09-111 SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 1. Description. Construct cast-in-place segmental concrete box girder superstructure according to the plans,
More informationPrefabricated Grid Reinforced Concrete Bridge Deck Replacement
Prefabricated Grid Reinforced Concrete Bridge Deck Replacement Philip M. Gase, P.E. The Bridge Grid Flooring Manufacturers Association REHABILITATION = PRESERVATION Partial or complete deck replacement
More informationREHABILITATION OF RUNWAY 11/29 AT CFB BAGOTVILLE. Presented by: Marla Hughesman CAPTG Sunday Workshop 12 September 2010
REHABILITATION OF RUNWAY 11/29 AT CFB BAGOTVILLE Presented by: Marla Hughesman CAPTG Sunday Workshop 12 September 2010 CFB BAGOTVILLE Located approximately 400 km NE of Montreal One of the Canadian Forces
More informationSection 603. CONCRETE PAVEMENT RESTORATION
603.02 Section 603. CONCRETE PAVEMENT RESTORATION 603.01. Description. This work consists of restoring concrete pavement including the following: A. Removing and repairing portions of a concrete pavement,
More informationSECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:
PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01
More informationTRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA
HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA 2008/09 $52.0 M 85% SELF-PERFORMED Widen 12 miles of Interstate 10 to six lanes including the reconstruction
More informationIJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 05, 2016 ISSN (online):
IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 05, 2016 ISSN (online): 2321-0613 Normal and Reactive Powder Reinforced Concrete Structures using Epoxy Injection Technique
More informationColumbia Public Schools Shepard Elementary School Classroom Building Addition PWA I 1 CONCRETE REINFORCEMENT ~4 ASSURANCE
B. Supports and accessories for steel reinforcement. 1.02 SECTIONS A. Section 03300- Cast-in-Place Concrete. 1.03 SUBMITTALS A. See Section 01300- Administrative Requirements, for submittal procedures.
More informationSECTION SITE CONCRETE
SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationBONDED CONCRETE OVERLAY ON ASPHALT
BONDED CONCRETE OVERLAY ON ASPHALT SR 151 in Harrison County HAS-151-12.90 PID:98696 Project #160187 Lloyd MacAdam, District 11 Deputy Director Paul Herman, Pavement Engineer Jason Beranek, Project Manager,
More informationVALLECITOS WATER DISTRICT SECTION PRECAST REINFORCED CONCRETE MANHOLES
PART 1 GENERAL 1.1 DESCRIPTION A. This section includes materials, testing, and installation of precast concrete manholes, manhole bases, manhole frames, and covers. 1.2 RELATED WORK SPECIFIED ELSEWHERE
More informationRehabilitation of the Blue Ridge Parkway with FDR and AC Overlay. Michael Walters FHWA EFLHD October 7, 2014
Rehabilitation of the Blue Ridge Parkway with FDR and AC Overlay Michael Walters FHWA EFLHD October 7, 2014 HISTORY Existing pavement on Parkway very deteriorated Repair options were heavy patching and
More informationBOCA Project Suitability, Design and Construction
BOCA Project Suitability, Design and Construction Bonded Concrete Overlay of Asphalt Pavements Mechanistic-Empirical Design Guide (BCOA ME) B C O A University of Pittsburgh Julie M. Vandenbossche, P.E.,
More informationSection 708. PRESTRESSED CONCRETE
708.02 Section 708. PRESTRESSED CONCRETE 708.01. Description. This work consists of manufacturing and erecting prestressed concrete. 708.02. Materials. Provide materials in accordance with the following:
More informationReview of Caltrans Concrete Pavement Sealed and Unsealed Pavement Performance
2010 Review of Caltrans Concrete Pavement Sealed and Unsealed Pavement Performance Field Review Observations On August 24-25, 2010 a joint Caltrans and Industry group met to discuss the state- 0f- the
More informationIntroduction to Pavement Overlays
Introduction to Pavement Overlays Course No: C02-046 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980
More informationMSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS
219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,
More information