Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano

Similar documents
Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs

The Fukushima Daiichi Nuclear Power Station Accident

The Spanish Involvement

The 4th Progress Report

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned

Analysis of the Fukushima Daiichi Nuclear Accident by Severe Accident Analysis Code SAMPSON

Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP

OVERVIEW AND OUTCOMES OF BENCHMARK STUDY OF THE ACCIDENT AT THE FUKUSHIMA DAIICHI NPS (OECD/NEA BSAF PROJECT)

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

The Effect of Fukushima. Research Activities in CIEMAT. Severe Accidents

Fukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011

Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami

Outline of the Fukushima Daiichi Accident. Lessons Learned and Safety Enhancements

Examination into the reactor pressure increase after forced depressurization at Unit-2, using a thermal-hydraulic code

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D

Findings from the latest analyses using MAAP5

Overview of Fukushima accident. Nov. 9, 2011 Orland, Florida

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Contents of Summary. 1. Introduction

Information on Status of Nuclear Power Plants in Fukushima

Contents of summary. 1. Introduction

Information on Status of Nuclear Power Plants in Fukushima

F, 3 Toyokaiji Building, Nishi-Shimbashi, Minato-ku, Tokyo , Japan Published: March 2016

Symposium on Risk Integrated Engineering January 21, 2019, Takeda Hall, The Univ. Tokyo Researches on Severe Accident and Risk Engineering

Modeling and Analysis of In-Vessel Melt Retention and Ex-Vessel Corium Cooling in the U. S.

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations

Information on Status of Nuclear Power Plants in Fukushima

INTRODUCTION IN FUKUSHIMA WATER LEAK PROBLEM

Information on Status of Nuclear Power Plants in Fukushima

Fukushima Dai-ichi. Short overview of 11 March 2011 accidents and considerations. 3 rd EMUG Meeting ENEA Bologna April 2011

Information on Status of Nuclear Power Plants in Fukushima

Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka

Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization)

Recommendations are based on validity of above assumptions.

Phenomena Identification in Severe Accident Sequence and Safety Issues for Severe Accident Management of Light Water Reactors

Fundamental Research Program for Removal of Fuel Debris

A Study of Fukushima Nuclear Power Plant Accidents by the Viewpoint of PSA

IMPORTANT SEVERE ACCIDENT RESEARCH ISSUES AFTER ACCIDENT AT FUKUSHIMA DAIICHI NUCLEAR POWER STATION

EXTENDED LOSS OF AC POWER (ELAP) ANALYSIS OF KUOSHENG BWR/6 USING MELCOR2.1/SNAP

Fukushima Daiichi NPP Accident

State of the Art and Challenges in Level-2 Probabilistic Safety Assessment for New and Channel Type Reactors in India Abstract

Thermal Hydraulics of Severe Accidents (TERMOSAN)

Information on Status of Nuclear Power Plants in Fukushima

Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning

Tohoku Pacific Earthquake and the seismic damage to the NPSs

Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCO Digest Version

The Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations

SAFETY ENHANCEMENT TECHNOLOGY DEVELOPMENT WITH COLLABORATIVE INTERNATIONAL ACTIVITY

Accident Progression & Source Term Analysis

Tohoku Pacific Earthquake and the seismic damage to the NPSs

Severe Accident Progression Without Operator Action

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident

The Fukushima Daiichi Incident

Information on Status of Nuclear Power Plants in Fukushima

THE FUKUSHIMA ACCIDENT: CAUSES, RESULTS AND IMPLICATIONS FOR EUROPE

Inventory estimation of 137 Cs in radioactive wastes generated from contaminated water treatment system in Fukushima Daiichi Nuclear Power Station

24 MARCH :00 UTC. Incident and Emergency Centre

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya

UK ABWR - NEW NPP DESIGN FOR UK

Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station

1) Order of accident progress and provisional expedient (chronological sequence)

Introduction to Level 2 PSA

Evaluation of a Containment Failure Frequency Considering Mitigation Accident Managements for a Japanese PWR Plant *

FIRST RESULTS OF THE SIMULATIONS OF FUKUSHIMA-DAIICHI UNIT 3 ACCIDENT FOR AN ASSESSMENT OF THE APPLICABILITY AND THE CAPABILITY OF THE CODE ATHLET-CD

Information on Status of Nuclear Power Plants in Fukushima

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis

The Fukushima Daiichi Incident Dr. Matthias Braun - 19 May p.1

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Source Terms Issues and Implications on the Nuclear Reactor Safety

NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

The Fukushima Daiichi Incident Dr. Matthias Braun - 16 November p.1

Information on Status of Nuclear Power Plants in Fukushima

Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

Effect of Nuclear Reactor Accidents on Modern Nuclear Power Plant Design Eric P. Loewen, Ph.D. Past President American Nuclear Society

Information on Status of Nuclear Power Plants in Fukushima

Effects of Source Term on Off-site Consequence in LOCA Sequence in a Typical PWR

Fukushima Daiichi Disaster. Facts and lessons learned. July Takashi Shoji Programme Director of WANO

METHODOLOGY USING MELCOR2.1/SNAP TO ESTABLISH AN SBO MODEL OF CHINSHAN BWR/4 NUCLEAR POWER PLANT

Summary on Fukushima Related Activities in Japan

Great East Japan Earthquake and the seismic damage to the NPSs

Development of SAMG Verification and Validation for Kashiwazaki-Kariwa(KK) Nuclear Power Station

Deconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery?

LABGENE CONTAINMENT FAILURE MODES AND EFFECTS ANALYSIS

Progress Report No. 1. December 13, Tokyo Electric Power Company, Inc.

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues

Fukushima Dai-Ichi Nuclear Accident Analysis. How much do we know? After Fukushima Dai-ichi Nuclear Accident: Don t let a crisis go to waste

BENCHMARK STUDY OF THE ACCIDENT AT THE FUKUSHIMA DAIICHI NPS BEST ESTIMATE CASE COMPARISON

Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident

The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station

Great East Japan Earthquake and the seismic damage to the NPSs

The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station

Summary SUMMARY. Contents of Summary

Severe accidents management in PWRs

Transcription:

Side Event of IAEA General Conference Severe Accident Analyses of Fukushima-Daiich Units 1 to 3 Harutaka Hoshi and Masashi Hirano Japan Nuclear Energy Safety Organization (JNES) September 17, 2012 Side Event by Government of Japan at 56th IAEA General Conference, Sep 17, 2012 1 Contents 1. Background 2. Accident Progression at Unit 1 3. Accident Progression at Unit 3 4. Hydrogen Explosions at Units 1 and 3 5. Source Terms 6. Environmental Consequences 7. Summary 2 1

1. Background The SA progression analyses done by TEPCO and JNES were reported to the IAEA Ministerial Conference in June 2011. Since then, the analyses have been continuously improved by taking into account new information on, such as: Operation of isolation condensers, RCIC, venting system, etc. Leakage / Failure of primary pressure boundary and containment, etc. However, it is still difficult to predict when and how much molten core fell into containment mainly due to large uncertainty in injection water flow rate into the core. Very recently, a preliminary analysis of migration and deposition of radioactive materials in the environment by using the radioactive release rates calculated by the SA progression analysis. 3 2. Accident Progression at Unit 1 Major improvements: In the previous analysis, leakage from primary pressure boundary due to over-temperature was not considered. Therefore, the primary system depressurization took place at the timing of lower head failure (melt through). In the present analysis, the leakage due to over-temperature was considered. Similarly, the leakage due to over-temperature was considered at the top-head flange of the containment (PCV). 4 2

Unit 1 RPV Pressure in Previous Analysis (June 2011) Plant records Reactor pressure vessel (RPV) lower head failed and RPV pressure rapidly decreased. In this calculation, leakage due to overtemperature was not considered. Therefore, the primary pressure boundary remained intact although it s temperature exceeded 720K. This was unrealistic. Reference: Nuclear Emergency Response Headquarters Government of Japan, "Report of Japanese Government to the IAEA Ministerial Conference on Nuclear Safety - The Accident at TEPCO's Fukushima Nuclear Power Stations -," June 2011 5 Assumption of leakage from primary pressure boundary due to over-temperature In the present analysis, it is presumed that the leakage took place: At the flange of safety relief valve (SRV) when it s temperature exceeded 720K, At the in-core instrumentation tubes when the peak cladding temperature (PCT) exceeded 1000K. SRV flange ~720 K SRM/IRM dry tube TIP dry tube SRV SRM/IRM, TIP PCT > 1000 K S/C SRM: Source Range Monitor IRM: Intermediate Range Monitor TIP: Traversing In-Core Probe Reference: http://www.tepco.co.jp/en/nu/fukushima-np/images/handouts_120312_04-e.pdf 6 3

Potential Leak locations of Mark-I Type Containment It is presumed that a leakage took place at the top head flange or machine hatch when it s temperature exceeded 620K. Unit 1 Unit 3 Causes and Countermeasures:The Accident at TEPCO s Fukushima NPS, Masaya Yasui, NISA/METI, March, 2012 7 Unit 1 RPV Pressure in Present Analysis: Results became more realistic. Plant records Depressurization due to leakage In the present analysis, RPV lower head failed after RPV depressurized. Leakage occurred at primary pressure boundary. RPV Lower head failed. 8 4

Unit 1 PCV Pressure in Present Analysis: Better agreement was obtained. Increase in PCV pressure due to steam and hydrogen leaked from RPV 2nd vent also succeeded partially Plant records PCV leakage started due to over temperature 1st vent partially succeeded 9 Molten Core Concrete Interaction (MCCI) JNES performed cross-checking of the calculation done by TEPCO. The assumption applied by TEPCO: It is assumed that the whole molten fuel fell into containment in Unit 1. RPV PCV Sump Pit Drywell Floor 130º Concrete Molten Fuel Sump Pit http://www.tepco.co.jp/en/nu/fukushimanp/images/handouts_111130_08-e.pdf Outer Wall Inside Wall Inner Skirt Model for distribution of molten fuel on drywell floor The amount of molten fuel in a sump pit is determined according to this distribution. 10 5

Ablation Profile: It was confirmed that both results were consistent PCV Wall Conservative By TEPCO MAAP(DECOMP): 0.65 m 0.65m 1.02m 1.2m 1.45m 0.81m Corium 0.65m 0.65m Ablation Front Y (m) Less conservative By JNES COCO Code horizontal: 0.45 m vertical: 0.38 m 1.0 0.5 0.0-0.5 Corium 0.38 m 0.45 m 1.02m -1.0-1.5-1.0-0.5 0.0 0.5 1.0 1.5 X (m) It is difficult to evaluate the amount of molten fuel that fell into the containment at present. It is expected that useful information be obtained through R&D at the Fukushima site for further assessment of MCCI. 11 3. Accident Progression at Unit 3 Major Improvements In the previous analysis, large decrease in primary pressure just after starting HPCI could not be reproduced. It was reported from TEPCO that HPCI injection flow rate was reduced by using the test line. In the present analysis, this was taken into consideration. Also, agreement with the plant data was poor on the containment pressure. In the present analysis, thermal stratification is presumed to take place at suppression chamber (S/C). Operation of containment spray was also considered based on the information from TEPCO. 12 6

Unit 3 RPV and PCV Pressures in Previous Analysis: Results show significant differences from plant records Significant difference after RCIC stopped and HPCI started Significant difference during RCIC operation Plant records RCIC stopped HPCI started Ref.: Nuclear Emergency Response Headquarters Government of Japan, "Report of Japanese Government to the IAEA Ministerial Conference on Nuclear Safety - The Accident at TEPCO's Fukushima Nuclear Power Stations -," June 2011 13 HPCI Operation Using Test Line In the present analysis, the HPCI operation using the test line was modeled. Large steam flow to HPCI turbine caused rapid decrease in RPV pressure. Steam flow to HPCI turbine Test line Water flow back to CST Water flow to RPV http://www.tepco.co.jp/en/nu/fukushima-np/images/handouts_120312_04-e.pdf 14 7

Major Assumptions: In order to simulate the thermal stratification at suppression chamber (S/C), the S/C was modeled by two volumes, upper and lower parts, in the present MELCOR analysis. A CFD (computational fluid dynamics) analysis was done to estimate the temperature difference between the upper and lower part of S/C (~20K). Modeling in CFD analysis Operation of containment spray: Flow rate of S/C and D/W spray: 50 m 3 /h Temperature distribution after 20 hour operation of RCIC Thermal Stratification 15 RPV and PCV Pressures in the Present analysis: Results were significantly improved Unit 3 Venting repeated several times RPV depressurization just after start of HPCI Operation of containment spray was simulated. Plant records Thermal stratification is presumed at S/C. 16 8

4. Hydrogen Explosions at Units 1 and 3 Analysis was done with FLUENT, a CFD code, for hydrogen transport and mixing, and AUTODYN for structural analysis of detonation. Major Assumptions: In Unit 1, Hydrogen of 400 kg was released to the top floor (5F) of reactor building (R/B) and ignited there. In Unit 3, Hydrogen of 1000kg was released to the first floor (1F) of R/B and ignited there. 17 Hydrogen Explosion at Unit 1 Analysis well reproduced the observed explosion: Explosion developed horizontally. Walls and roofs of top floor (5F) were largely damaged and debris scattered around R/B. Web site: Fukushima Central Television Web site: TEPCO Potential location of leakage: top head flange of PCV ignition point [kpa] [m/s] t = 100 (ms) t = 10 (ms) 圧力コンター図 t = 20 (ms) (10~100ms) t = 100 (ms) Propagation of detonation pressure in Unit 1 Detonation analysis with AUTODYN: 18 9

Hydrogen Explosion at Unit 3 Analysis well reproduced the observed explosion: Explosion developed vertically. Walls and roofs of top floor (5F) were largely damaged. Adjacent low building was also damaged. Locally high dose rate was detected at 1st floor. Potential location of leakage: device hatch [kpa] ignition point Web site: Fukushima Central Television The top of a two-story building next to the R/B have also been [m/s] damaged. Web site: TEPCO t = 5 (ms) t = 35 (ms) t = 100 (ms) Propagation of detonation pressure in Unit 3 Detonation analysis with AUTODYN: 19 5. Source Terms The radioactive release rates obtained in the present analysis with MELCOR were compared with onsite monitoring data. The total amounts of releases were also evaluated by several other organizations: TEPCO, JAEA, JAMSTEC and CREEPI applied inverse analysis which evaluated the source terms from the monitoring data and meteorological data. 20 10

Comparison between Release Rates Calculated with MELCORE and Onsite Monitoring Data: Release timings are relatively in good agreement with the monitoring data 1st Vent (Unit 1) 2nd Vent (Unit 1) Vent (Unit 3) From Unit 2 PCV leakage (Unit 1) 21 Amount of Releases Evaluated in Several Organizations: Results are reasonably consistent with each other Organiza tion Amount of Releases (PBq) I-131 Cs-134 Cs-137 JNES 250-340 8.3-15 7.3-13 TEPCO 500 10 10 JAEA 120-9 JAMSTEC 9.7 5.5-5.7 Duration Mar. 11-Mar. 17 Mar.12-May 6 Mar.21-May 6 To the ocean CRIEPI 11 3.5 3.6 Mar. 26-Sep. 30 To the ocean Inverse analysis from monitoring data Severe accident progression analysis Land side only Sea side only (1 PBq = 10 15 Bq) 22 11

6. Environmental Consequences Very recently, JAEA conducted preliminary environmental consequence analysis with the OSCAAR* code developed by JAEA for level 3 PSA. The measured meteorological data were used. The source terms calculated by MELCOR, shown in Slide 21, were used. *: T. Homma, et al, Uncertainty and sensitivity studies with the probabilistic accident consequence assessment code OSCAAR, Nuclear Engineering and Technology, 37(3), 245-258 (2005). Calculation (Bq/m 2 ) Calculated concentrations of Cs-137 in soil are in good agreement with the measured data Measured data (Bq/m 2 ) Correlation between measured data and calculation (Cs-137 concentration in soil) 23 Preliminary Environmental Consequence Analysis by JAEA/JNES Concentration of Cs-137 in soil Environmental consequence analysis by JAEA (OSCAAR) using the source terms by JNES (MELCOR) Monitoring data by MEXT (October to Novemer, 2011) http://radioactivity.mext.go.jp/ja/contents/5000 /4901/24/1910_1216.pdf 24 12

7. Summary Regarding SA progression including source terms, most of the phenomena that took place during the accident have become reasonably well understood by efforts made by various organizations. It is still difficult to predict when and how much molten fuel fell into the containment. On this point, it is expected that new information / data will be obtained through R&D activities at the Fukushima site for decommissioning. New attempts, such as environmental consequence analysis with using the source terms calculated by SA progression analysis, are expected to be able to obtain better understanding. 25 Acronyms AM : Accident Management D/W : Dry Well HPCI : High Pressure Coolant Injection IRM : Intermediate Range Monitor MCCI : Molten Core Concrete Interaction R/B : Reactor Building PCV : Primary Containment Vessel RCIC : Reactor Core Isolation Cooling System RPV : Reactor Pressure Vessel SA : Severe Accident S/C : Suppression Chamber (Suppression Pool) Organization CRIEPI : Central Research Institute of Electric Power Industry JAEA : Japan Atomic Energy Agency JAMSTEC : Japan Agency for Marine-Earth Science and Technology TEPCO : Tokyo Electric Power Company 26 13