VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No.

Similar documents
VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No.

Beckett Bridge PD& E Study Elected Officials Kick-Off Meeting

MOVABLE SPAN BRIDGES. Bridge of Lions, St. Augustine, Florida

Red Wing Bridge Alternates

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

SAN ANTONIO STREET BRIDGE AT COMAL RIVER. Open House

Raritan River Bridge Replacement. Public Information Session September 2016

Pinellas Bayway Bridge Replacement

2-2 ALTERNATIVES CONSIDERED AND ELIMINATED

Bridge Preservation Beyond the Short Term

LOCATION HYDRAULIC REPORT

REHABILITATION PACKAGE 4-a

Clear Creek Road (PM 1.82 & 0.25) Bridge Replacement Projects. Public Meeting, Wednesday, November 20, 2013 Pleasant Valley Middle School

Engineering & Capital Improvements. Shore Acres Civic Association August 21 st, 2017

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Fore River Bridge Replacement Project. Spanning the Weymouth Fore River between Quincy and Weymouth, Massachusetts. Highway

Bridge Replacement Study (Phase 1)

Foundation Strengthening Of Bascule Piers At The Bridge Of Lions

Federal Highway Administration s Role in Bridge Preservation. Anwar S. Ahmad 1

9 Conclusion. 9.1 Introduction

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting

Conceptual Design Report

PROGRAMMATIC SECTION 4(f) EVALUATION

6 th STREET VIADUCT SIESMIC IMPROVEMENT PROJECT

US 36 Truss Bridge Rehabilitation Schedule-Critical Deadline Met with Teamwork and Innovation

WELCOME The Walk Bridge Project CTDOT Project No

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions

PUBLIC INFORMATION MEETING June 24, 2015

SECTION 4(f) EVALUATION ALASKA RAILROAD MOODY TUNNEL REMOVAL FEDERAL TRANSIT ADMINISTRATION U.S. Department of Transportation

NJTPA 2014 Local Concept Development Study Hudson & Essex Counties Clay Street Bridge over the Passaic River. Public Information Center

MILTON-MADISON BRIDGE REPLACEMENT

Executive Summary. ES-1 Introduction. ES-2 Background

US 278 East Bound and West Bound. MacKay Creek and Skull Creek. Cursory Above Water and Underwater Investigation Of. Over

STRUCTURE AND BRIDGE DIVISION

Evaluation of Rehabilitation Alternatives for the Cedar Avenue Bridge

Indiana ABC Experience

Cochran Mill Road Bridge over Tuscarora Creek

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

Pensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

Review of Plans and Specs from a Constructability Perspective

PIER PROTECTION (VEHICLE COLLISION) September 13, 2018

Florida Department of Transportation District Four KICK-OFF MEETING. I-95 at Southern Boulevard (SR 80) Project Development and Environment Study

I-395 Reconstruction. Project Advisory Group Meeting A1. PRESENTATION November 15, 2011

MAINTAINING CHARACTER, IMPROVING SAFETY OREGON S STEALTH RAIL PROGRAM

Chapter 4 Bridge Program Drawings

Figure 28 Ocean Drive Improvements and Middle Thorofare Bridge Replacement Alternatives Comparison Matrix

ERRATA SHEET RECORDING AND CODING GUIDE FOR THE STRUCTURE INVENTORY AND APPRAISAL OF THE NATION=S BRIDGES REPORT NO. FHWA-PD , DECEMBER 1995

Feasibility Assessment Study

State of New Jersey NEW JERSEY DEPARTMENT OF TRANSPORTATION 1035 PARKWAY AVENUE P.O. Box 600 TRENTON, NEW JERSEY

103rd Annual T.H.E. Conference February 28 & March 1, 2017 University of Illinois at Urbana-Champaign. Planning and Design. of IL-104 BRIDGE OVER

40TH AVENUE NE BRIDGE REPLACEMENT

NEW MEXICO LAND OF ENCHANTMENT

BRIDGE INSPECTION REPORT

Walk Bridge Replacement Project

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017

MICHIGAN DEPARTMENT OF TRANSPORTATION

Ontario Structure Inspection Manual Inspection Form Structure Number: 12

Oklahoma Department of Transportation Environmental Programs Division Office Fax

MICHIGAN DEPARTMENT OF TRANSPORTATION

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

Zinc Rich Paint in a Pigeon Rich Environment

Austin Avenue Bridges Project Walking Tour Agenda

Red Wing Bridge Project. City Council Meeting August 26, 2013

Footbridge Reconstruction Workshop #2

INSPECTION AND REPAIR OF THE DETERIORATED RT.72 MANAHAWKIN BAY BRIDGE

Gasparilla Island Swing Bridge Replacement

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

FHWA Emergency Relief Program. Emergency Relief Program

FINAL Rehabilitation and Replacement Strategy Analysis Report

April 19, 2017 Vicente Valeza, P.E. NOVA District Senior Structural Engineer (703)

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

Alder Drive / Blair Road Bridge Replacement Projects

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

PLANNING BOARD HEARING Miami Shores Village Town Hall Council Chambers NE 2 nd Avenue Miami Shores Hearing Date April 24, 2014

Fairfax Bridge Rehabilitation Program - Bridge Preventive Maintenance Program. January 29, 2014

6 93 Corridor TUNNEL CROSS SECTION 42.0' 24.0' WITH 21.0' WITHOUT 1.5' 6.0' 12.0' 12.0' 6.0' 4.0' 0.5' CLEARANCE ENVELOPE (36' W x 16.

2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER

January 2015 v 2.0. (Revised April 2016)

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

Public Information Meeting Information Packet: Childress Drive Bridge over South Utoy Creek June 29, 2016

Chicago. Crossing. A new Chicago bridge takes over the duties of a former Centurion.

Winona Bridge Work Package #6. Options Overview

Executive Summary S-1 INTRODUCTION

December 28, John Fleming, Division Head, Environmental Division

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

CHITTENDEN COUNTY REGIONAL PLANNING COMMISSION Winooski/Burlington, US RTs 2 & 7 Bridge Scoping Study ADVISORY COMMITTEE MEETING NO.

Movable Bridge Maintenance and Preservation

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

How to Review SI&A Data

HUNT STREET BRIDGE. Site Number HUNT STREET, SIMCOE. 0.2 km North of Highway 3

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION

Public Meeting. Draft Environmental Impact Statement (EIS) and Section 106 Consultation. Preferred Alternative Selection November 29, 2018

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6

Bonner Bridge Replacement Update:

Unionport Bridge Replacement Design Twin Single Leaf Bascules

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

BRIDGE STANDARD PLANS AND SPECIAL DETAILS ADAM LANCASTER, P.E. FEB. 27, 2018

Transcription:

VENETIAN CAUSEWAY (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE FM No. 422713-2-22-01 Efficient Transportation Decision Making (ETDM): 12756 Project Advisory Group (PAG) Meeting No. 2 February 24, 2015 Florida Department of Transportation - District 6 1

Project Team PROJECT MANAGER Dat Huynh, PE CONSULTANT PROJECT MANAGER: Enrique Rick Crooks, PE 2

Agenda PD&E Process and Status Purpose of Project Advisory Group (PAG) Meeting #2 Study Parameters Alternatives Matrix and Flowchart No-Build Alternatives Build Alternatives Other Considerations Summary 3

PD&E Process and Status Public Involvement Engineering Analysis Environmental Analysis Public Kickoff Meeting Data Collection: Engineering, Environmental, Historic Resources Environmental Analysis PAG Meetings CRC Meetings Newsletters One on One Meetings Agency Meetings No Build Rehabilitation Alternatives Select Viable Rehabilitation Alternatives Build Replacement Alternatives Select Viable Replacement Alternatives Environmental Documents Alt. Public Workshop Select Recommended Alternative Public Hearing Value Engineering Final Documents for Federal Highway Administration Approval Completed or In-Progress Future Steps 4

Purpose of PAG 2 The purpose of the PAG is to ensure that the range of stakeholder views regarding possible improvements to the Venetian Causeway is clearly understood and fully considered by the project team. Alternatives being considered as part of the study will be presented for input. The presentation will address the ability of the alternatives to safely carry traffic, pedestrians and bicyclists. The possible impacts of the different alternatives on the environment, historic resources, aesthetics and the public will also be presented. 5

Study Parameters Purpose and Need for Project The purpose of the proposed project is to examine the potential replacement or rehabilitation of the twelve existing bridges (ten low-level fixed spans and two movable bascules). 6 Bridge No. DOT Bridge # NBI Condition Rating Sufficiency Rating Deficiency FO/SD Appraisal /Present Posted 2011 2014* 2011/2014 2014 Scour/Storm Evaluation Scour Depth Year 1998 100 Year Category 5 Bridge Exist Est. pile 1927 and Renovation 1 874459 32.6 19 FO/SD 5 Tons 26.9 ft 26.9 ft 40-54 ft 2 874460 52 45.9 FO 11 Tons 19.6 ft 29.1 ft 20-28 ft 3 874461 55.5 46 FO 11 Tons 25.0 ft 31 ft 20-28 ft 4 874463 55.5 46 FO 11 Tons 25.0 ft 31 ft 20-28 ft 5 874465 47.9 36.5 FO 11 Tons 19.6 ft 25.9 ft 20-28 ft 6 874466 57.6 48.2 FO 11 Tons 22.6 ft 28.2 ft 20-28 ft 7 874471 55.5 46 FO 11 Tons 22.0 ft 27.3 ft 20-28 ft 8 874472 55.5 46 FO 11 Tons 22.6 ft 28.9 ft 20-28 ft 9 874473 64 48.7 FO 11 Tons 24.2 ft 35.5 ft 20-28 ft 10 874474 57.5 32.1 11 Tons 25.0 ft 30.1 ft 20-28 ft 11 874477 64 41 FO 11 Tons 25.3 ft 31.6 ft 20-28 ft 12 874481 68.1 43.6 16 Tons 15.8 ft 19.4 ft 20-28 ft *Based on FDOT Bridge Information July 1 st 2014 FO= Functionally Obsolete SD= Structural Deficient EST.= Estimated 6

Study Parameters Historic Resource-Venetian Causeway Prudent and Feasible Build Impacts Constructed in 1926 Oldest causeway in Florida Listed on the National Register of Historic Places Listed as Historic in the Cities of Miami and Miami Beach 7

Study Parameters Section 106 of National Historic Preservation Act Cultural Resources Assessment Survey Establish Area of Potential Effect Identify and Document Resources Evaluate Significance according to NRHP Criteria Evaluation of Effects --Determination of Effects Case Study Apply Section 106 Criteria of Effects All Alternatives assessed in terms of their effects to resources Rehabilitation according to the Secretary of Interiors Standards likely No Adverse Effect Replacement Will be Adverse Effect Finding of No Adverse Effect- Processes Concluded Finding of Adverse Effect - Develop MOA and Section 4(f) Programmatic or Individual Statement Documentation 8

Study Parameters Section 106/4(f) Processes Required for Historic Structures Excerpts from FDOT PD&E Manual (Part 2, Chapter 13) 13-2.4.2 Programmatic Section 4(f) Evaluations Under a Programmatic Section 4(f) Evaluation, certain conditions are laid out such that, if a project meets the conditions, it will satisfy the requirements of Section 4(f) that there are no feasible and prudent alternatives and that there has been all possible planning to minimize harm. Alternatives and Findings 1. Do Nothing. The do nothing alternative has been studied and is not feasible and prudent because it does not correct the situation that causes the bridge to be considered structurally deficient and functionally obsolete to the degree where the bridge poses serious and unacceptable safety hazards to the public or places intolerable restriction on transport or travel. 9

Study Parameters Processes Required for Historic Structures Cont d 2. Build a new structure at a different location without affecting the historic integrity of the old bridge, as determined by procedures implementing the National Historic Preservation Act (NHPA). Demonstrate that investigations have been conducted to construct a bridge on a new location or parallel to the old bridge, but this alternative is not feasible and prudent. 3. Rehabilitate the historic bridge without affecting the historic integrity of the structure, as determined by procedures implementing the NHPA. Show that studies have been conducted of the rehabilitation measures, but because the bridge is so structurally or geometrically deficient, it cannot be rehabilitated to meet either the minimum acceptable load requirements or the minimum required capacity of the highway system on which it is located without affecting the historic integrity of the bridge. 10

Study Parameters Processes Required for Historic Structures Cont d Measures to Minimize Harm For bridges that are to be rehabilitated according to the Secretary of the Interiors Standards, the historic integrity of the bridge is preserved, to the greatest extent possible, consistent with unavoidable transportation needs, safety, and load requirements. For bridges that are to be rehabilitated to the point that the historic integrity is adversely affected or that are to be moved or demolished, the FHWA ensures that, in accordance with the Historic American Engineering Record (HAER) standards, or other suitable means developed through consultation, fully adequate records are made of the bridge. In addition, other mitigation measures will be developed in consultation with the appropriate agencies, such as SHPO, USCG, as well as the Cities, County, residents, and locally affected parties. 11

Study Parameters Hurricane Resistance Low Causeway Bridges o Below Anticipated Storm Surge 100 Year Storm Surge Elevation 8 ft to 12 ft Wave Crests 7 to 8 ft above Storm Surge I-I0 Escambia Bay, FL. - Hurricane Ivan - 2005 12

Study Parameters Hurricane Resistance 100 year Peak Storm Surge Heights o 7.7' (FEMA) to 11.6' (Current Study) o Wave crest is storm surge plus 70% of the maximum wave height. Causeway bridges are mostly below this elevation. Wave Forces o Vertical will be in the 10 to 14 kip/ft range or 500 to 700 kips (250 to 350 tons) per 50 ft span! o Horizontal wave forces will be in the 4 to 6 kip/ft range or 200 to 250 kips (100 to 125 tons) per 50 ft span! (Equivalent to a collision with a barge drifting at approximately half a knot) Location Design Wave Height (ft) Wave Crest Elevation (ft-navd) End Bent 1 9.3 18.1 100-Year Wave Crest Elevation 100-Year Water Surface Elevation 100-Year Water Surface Elevation (storm surge) and the 100-Year Wave Crest Elevations. Pier 2 13.7 21.2 Pier 3 12.9 20.6 End Bent 4 7.5 16.8 13

Study Parameters Vessel Collision Resistance All Causeway Bridges must consider Risk of Vessel Collision West Bascule Bridge over Intracoastal Waterway o o 80 Tug & Barges per Year (each direction) 500 to 600 Other Larger Vessels (each direction) East Bascule Bridge over Tide Relief Channel o Mostly Recreational and Smaller Commercial Craft Only 14

Study Parameters Rehabilitation Parameters Meet current safety standards Maintain National Register of Historic Places listing Minimize environmental impacts Rehabilitation *Service Life 25 years Typical Section improve functionality Structural Capacity meet current standards for: o Load carrying capacity o Foundation stability o Hurricane resistance o Vessel collision resistance Bridge Railings and End Treatments o Preserve historic character o Meet current standards At a minimum, maintain the existing bridge clearances Maintain traffic during construction Maintain utility services during construction * Cathodic Protection will be utilized to decrease future corrosion 15

Study Parameters Rehabilitation Parameters Cathodic Protection (CP) CP is an electrochemical method of corrosion protection that takes advantage of the electrochemical nature of corrosion by transforming a metal into a non-corroding cathode. CP is the only proven technique to decrease the corrosion of reinforcing steel in concrete. 16

Study Parameters Build Alternatives Replacement Parameters Meet current standards and loading requirements Minimize environmental impacts Service Life 75 years Bridge Railings maintain or improve views of the water Seek opportunities to improve the existing bridge clearances. Variances may be required. Maintain traffic during construction Maintain utility services during construction Accommodate high pedestrian and bicycle traffic 17

Alternatives Matrix Alternative 1 Do Nothing 2 Transportation System Management Description Rehabilitation Alternatives 3 Fixed Bridge Rehab w/out Beam Strengthening 4 Fixed Bridge Rehab with Beam Strengthening M1 Bascule Bridge Rehabilitation Typical Section Alternatives 5 Tunnel T1 T2 T3 T4 Replacement Alternatives Venetian Railing Wyoming Railing TL-4 at coping Wyoming Railing TL-3 at curb and Original Venetian Railing at Coping Wyoming Railing TL-3 at curb and Custom Railing at Coping Fixed Bridge Alternatives 6 High Level Fixed Bridge 7 Arched Beams 8 FIB With Arched Fascia (FA) 9 FIB (F) 10 Flat Slab (FS) Movable Bridge Alternatives M2 Swing Bridge M3 M4 M5 Vertical Lift Bridge Double Leaf Bascule Bridge Single Leaf Bascule Bridge NO BUILD B U I L D A L T E R N A T I V E S 18

Alternatives Flowchart 19

No-Build Alternatives Alt. 1 - Do Nothing Existing Deficiencies will Remain Continued Deterioration Extensive Periodic Repairs and Maintenance Does not meet purpose and need for project 20

No-Build Alternative Alt. 2 Transportation System Management Enhanced Bus service Facilitate Pedestrians and Bicyclists Existing Deficiencies will remain, but safe bridges required for effective TSM Does not meet purpose and need for project 21

No-Build Alternatives Alternative Corridor Corridor Analysis FDOT PD&E Manual (Part 2, Chapter 13) - Build a new structure at a different location without affecting the historic integrity of the old bridge, as determined by procedures implementing the National Historic Preservation Act (NHPA). Demonstrate that investigations have been conducted to construct a bridge on a new location or parallel to the old bridge (allowing for a one-way couplet), but, for one of the following reasons, this alternative is not feasible and prudent: 1) Terrain - the existing bridge has already been located at the only feasible and prudent site, 2) building a new bridge away from the present site would result in social, economic, or environmental impact of extraordinary magnitude, 3) the new site would not be feasible and prudent where cost and engineering difficulties reach extraordinary magnitude, and 4) It would not be feasible and prudent to preserve the existing bridge, even if a new bridge were to be built at a new location. 22

No-Build Alternatives Alternative Corridor Cont d Does not meet purpose and need for project 23

Summary and Next Steps 24

Rehabilitation Alternatives Alt. 3 - Fixed Bridge Rehab w/out Beam Strengthening 5 foot Sidewalk meets minimum required for ADA 4 foot Shoulder does not meet 5.5 foot shoulder requirement for bike lane Rehabilitation includes: Deck Replacement and Foundation Strengthening 41-10 Overall width to remain Venetian Railing to remain Typical Section 25

Rehabilitation Alternatives Alt. 3 & 4 Foundation Strengthening Repair concrete spalls and cracks Extend Service Life Cathodic protection Footing Encasement Pier Strengthening for wave vulnerability Riprap placement at foundations for scour protection 26

Rehabilitation Alternatives Alt. 3 - Fixed Bridge Rehab w/out Beam Strengthening Plan View Estimated Cost Range: $22 - $25 Million (Does not include cathodic protection) Elevation View Scour Protection 27

Rehabilitation Alternatives Alt. 4 - Fixed Bridge Rehab with Beam Strengthening 5 foot Sidewalk meets minimum required for ADA 4 foot Shoulder does not meet 5.5 foot shoulder requirement for bike lane Rehabilitation includes: Deck Replacement Beam and Foundation Strengthening 41-10 Overall width to remain Venetian Railing to remain Typical Section 28

Rehabilitation Alternatives Alt. 4 - Fixed Bridge Rehab with Beam Strengthening Plan View Estimated Cost Range: $26 - $30 Million (Does not include cathodic protection) Elevation View Scour Protection 29

Rehabilitation Alternatives Alt. M1 - Bascule Bridge Rehabilitation Estimated Cost Range: $8 - $9 Million 30

Summary and Next Steps 31

Replacement Alternatives Excerpts from FDOT PD&E Manual (Part 2, Chapter 6 - Alternatives) 6.1 Overview The alternatives section is the heart of the Environmental Document and should rigorously explore and objectively evaluate alternatives. 6-2.3 Analysis and Documentation The alternatives section of the Environmental Document must address the following discussion points in accordance with 40 CFR 1502.14: 1. Rigorously explore and objectively evaluate all reasonable alternatives (for EISs), and, for alternatives which are being eliminated from detailed study, briefly discuss the reasons for their elimination. 32

Replacement Alternatives Alt. 5 - Tunnel PortMiami Tunnel Tunnel Limits Portal Limits Estimated Cost Range: $160- $200 Million 33

Replacement Alternatives Typical Section Bridge Typical Section Roadway Typical Section 34

Replacement Alternatives Typical Section/ Railing Selection T1 Venetian Railing 47-10 Overall width 35

Replacement Alternative Typical Section/ Railing Selection T1 Venetian Railing - Bascule Span Typical Section Functions as Traffic Barrier and Pedestrian Railing Matches Current Railings on Causeway but with addition of Inserts in Openings 36

Replacement Alternatives Typical Section/ Railing Selection T1 Venetian Railing 37

Replacement Alternatives Typical Section/ Railing Selection T2 Wyoming Railing TL-4 at coping 49-4 Overall width 38

Replacement Alternative Typical Section/ Railing Selection T2 Wyoming Railing TL-4 at coping - Bascule Span Typical Section Functions as Traffic Barrier and Pedestrian Railing Steel Tube Railing with Intermediate Cables Open Design Maximizes Views from Bridge 39

Replacement Alternatives Typical Section/ Railing Selection T2 Wyoming Railing TL-4 at coping 40

Replacement Alternatives Typical Section/ Railing Selection T3 Wyoming Railing TL-3 at curb and Original Venetian Railing at Coping 48-8 Overall width 41

Replacement Alternative Movable Bridges T4 Bascule Span Typical Section Traffic Barrier at Curb provides Separation from Traffic; Improves Safety and Functionality at Movable Span; Permits Use of Lighter/More Open Railings Matches Original Venetian Causeway Railing but with Inserts in Openings 42

Replacement Alternatives Typical Section/ Railing Selection T4 Wyoming Railing TL-3 at curb and Custom Railing at Coping 48-8 Overall width 43

Replacement Alternative Movable Bridges T4 Bascule Span Typical Section Traffic Barrier at Curb provides Separation from Traffic; Improves Safety and Functionality at Movable Span; Permits Use of Lighter/More Open Railings Custom Metal Pedestrian Railing 44

Replacement Alternatives - Typical Section Selection 45

Summary and Next Steps 46

Replacement Alternatives Fixed Bridges Alt. 6 - High Level Fixed Bridge MacArthur Causeway Image: Schener Fotografia High Level Bridge Limits Estimated Cost Range: $52- $56 Million 47

Replacement Alternatives Fixed Bridges Alt. 7 Arch Beam 6.5 ft Sidewalk meets ADA requirements. 1.5 ft Shoulder and 4 ft Bike lane 11 Venetian Railing 47 10 Overall width Typical Section 48

Replacement Alternatives Fixed Bridges Alt. 7 Arch Beam Plan View Estimated Cost Range: $33 - $37 Million Elevation View 49

Replacement Alternatives Fixed Bridges Alt. 7 Arch Beam with Venetian Railing 50

Replacement Alternatives Fixed Bridges Alt. 7 Arch Beam with Wyoming Railing 51

Replacement Alternatives Fixed Bridges Alt. 8 FIB with Arched Fascia (FA) 6.5 ft Sidewalk meets ADA requirements. 1.5 ft Shoulder and 4 ft Bike lane 11 Venetian Railing 47 10 Overall width Typical Section 52

Replacement Alternatives Fixed Bridges Alt. 8 FIB with Arched Fascia (FA) Plan View Estimated Cost Range: $31 - $36 Million Elevation View 53

Replacement Alternatives Fixed Bridges Alt. 9 FIB (F) 6.5 ft Sidewalk meets ADA requirements. 1.5 ft Shoulder and 4 ft Bike lane 11 Venetian Railing 47 10 Overall width Typical Section 54

Replacement Alternatives Fixed Bridges Alt. 9 FIB (F) Plan View Estimated Cost Range: $26 - $32 Million Elevation View 55

Replacement Alternatives Fixed Bridges Alt. 10 Flat Slab (FS) 6.5 ft Sidewalk meets ADA requirements. 1.5 ft Shoulder and 4 ft Bike lane 1-8 Wyoming TL-4 Railing 49 4 Overall Width Typical Section 56

Replacement Alternatives Fixed Bridges Alt. 10 Flat Slab (FS) Plan View Estimated Cost Range: $31 - $34 Million Elevation View 57

Replacement Alternatives Fixed Bridges Alt. 10 Flat Slab (FS) 58

Summary and Next Steps 59

Replacement Alternatives Movable Bridges Alt. M2 Swing Bridge/ Movable Span alternative Advantages: Low Construction Cost Unlimited Vertical Clearance in Open Position Provides two Channels Estimated Cost Range: $23- $25 Million Disadvantages: Hazard to Navigation Pivots toward Approaching Vessels Swing Span More Exposed to Vessel Collision No Direct Access to Swing Span in Open Position Non-Redundant for Maintenance 60

Replacement Alternatives Movable Bridges Alt. M3 Vertical Lift Bridge Advantages: Shallower Girders/More Vertical Clearance - Span Lowered Typically Spans Longer Distance o Span Waterway with no Piers in Water o Greater Horizontal Clearance o Improved Navigation Safety Estimated Cost Range: $26 - $29 Million Disadvantages: High Construction Cost Tall Towers (85 to 90 ft) Restricted Vertical Clearance with Span Raised (65 ft) Longer Operating Time Non-Redundant for Maintenance 61

Replacement Alternative Movable Bridges Alt. M4 Movable Span Alternatives M4 Double Leaf & M5 Single Leaf Bascules Advantages: Economical/Low Construction Cost Unlimited Vertical Clearance in Raised Position Shortest Operating Time Most Similar to Existing Bridge Good Maintenance Access Disadvantages: Larger Pier(s) in Waterway M4 - Double Leaf Bascule: Redundant for Maintenance Shallower Girders/More Clearance Two Smaller Piers Symmetric Arrangement M5 -Single Leaf Bascule: Non-Redundant for Maintenance Deeper Girders/Less Clearance One Larger Pier/One Smaller Pier Asymmetric Arrangement Estimated Cost Range: $25- $28 Million 62

Replacement Alternative Movable Bridges Alt. M4 Movable Span Alternatives M4 Double Leaf 63

Replacement Alternative Movable Bridges Alt. M4 Movable Span Alternatives M4 Double Leaf 64

Replacement Alternative Movable Bridges Alt. M5 Movable Span, Single Leaf Bascule Estimated Cost Range: $23- $26 Million 65

Summary and Next Steps 66

Other Considerations Hybrid Alternatives Other Combinations of Alternatives are Possible Different Structural System on the Fixed Bridges than on the Fixed Approach to the Movable Bridge 67

Other Considerations Bridge Clearances (Replacement East Bascule Bridge 10) i. Navigational o Horizontal increase for safety o Vertical higher profile (Vessel study Diagram Impacts of different heights) ii. Benefits of higher vertical profile Higher Profile: Raises Peak Approx. 12 ft Reduces Bridge Openings Approx. 50% Exceeds Recommended Height for Corrosion Protection and Flooding during Coastal Storms Requires Bridge 9 and 11 Replacement Lower Profile: Raises Peak Approx. 8 ft Reduces Bridge Openings Approx. 30% Lowest Recommended Height for Corrosion Protection and Flooding during Coastal Storms Requires Bridge 9 and 11 Modifications 68

Other Considerations Impacts of No-Build vs Build No build results in no environmental impacts Build Alternatives (Rehab. or Replacement) o Similar natural resource impacts for both rehabilitation and replacement. o Potential impact to corals on substructure & scour protection areas o Temporary impacts due to construction methods o Barge Use, water quality, noise, air quality o Minimal threatened & endangered species involvement o Informal Section 7 (of the Endangered Species Act) Consultation with USFWS & NMFS o Retain and improve bicycle and pedestrian access 69

Other Considerations Maintenance of Traffic Individual Bridge Detours Same considerations for Rehabilitation or Replacement as both remove the deck Detours affect one bridge location at a time Construction Duration Public Safety Emergency Services Maintain Utility Services 70

Other Considerations Maintenance of Traffic Temporary Fixed Bridge (at Bridge 10) Used during 1998 rehabilitation 71

Other Considerations Utility Services Maintain services throughout Construction o Approach is dependent on selected MOT concept Different Approach for Rehabilitation and Replacement o Rehabilitation leaves portion of bridge from which utilities are supported Subaqueous Crossings o Phased construction 72

Anticipated Project Schedule Next Steps Alternative s Workshop 73

Stay Informed FDOT Contact Project Manager: Dat Huynh, PE Email: Dat.Huynh@dot.state.fl.us Phone: 305-470-5217 Miami-Dade County Contact Public Information Officer: Gayle Love Email: loveg@miamidade.gov Phone: 305-514-6607 ONLINE Project webpage - Updates posted weekly http://www.fdotmiamidade.com/venetianbridgestudy Efficient Transportation Decision Making (ETDM) https://etdmpub.fla-etat.org/est/ Click on Project Number on left hand menu Type in 12756 Click "Go" or press Enter 74