Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Similar documents
SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

Accelerated Bridge Construction (ABC) National Status

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

PUBLIC INFORMATION MEETING June 24, 2015

Zinc Rich Paint in a Pigeon Rich Environment

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Boeing North Bridge in Washington State

Specification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010

Project Overview. Wilson Boulevard over Route 50 Bridge Rehabilitation. Get Involved. Public Information Meeting. Contact Information

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

LRFD Bridge Design Manual Changes

Design of the IL 127 Kaskaskia River Bridge Illinois Transportation and Highway Engineering Conference February 24, 2015 University of Illinois at

Cumberland Viaduct Rehabilitation Project Contract No. AL R Presenter Bob Bofinger MDSHA Office of Structures

Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

John James Audubon Bridge

Bonner Bridge Replacement Update:

Northeast Bridge Preservation Partnership Meeting

Bridge Preservation Beyond the Short Term

7 Bridges in 74 Days. NC 12 Detour

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE

REHABILITATION PACKAGE 4-a

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Ironton Russell Bridge Project

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION

I-70 over SR 121 Bridge Slide Construction and Engineering

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction

Accelerated Bridge Construction Award

Oatman Highway at Sacramento Wash Crossing Federal Aid No. 000-MMO-0(216)T ADOT Project No MO MMO T C

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Accelerated and Innovative Bridge Construction In Washington State

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

Red Wing Bridge Alternates

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

Structural Lightweight Concrete for Accelerated Bridge Construction

Strain Gauge Balancing of the Lea Joyner

PHASING CONSIDERATIONS FOR BRIDGES

John James Audubon Bridge. Introduction

Get In, Get Out, Stay Out!

Conceptual Design Report

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Michael Lewis Director, Rhode Island Department of Transportation

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions

MISENER DAM. Site Number LYNN STREET, PORT DOVER km N of Highway 6

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY

Rehabilitation Design and Construction for the US 190 Mississippi River Bridge Cleaning, Painting, and Repair Project

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

NEWINGTON-DOVER WELCOME

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

BRIDGE MAINTENACE EMERGENCY PROJECTS

US 36 Truss Bridge Rehabilitation Schedule-Critical Deadline Met with Teamwork and Innovation

I-74 over the Mississippi River

CHEF MENTEUR BRIDGE REPLACEMENT

2016 ACEC/PA ANNUAL MEETING

SOUTH MEDFORD INTERCHANGE BRIDGES

System Preservation in Louisiana

LYNNVILLE ROAD BRIDGE. Site Number D00027 LYNNVILLE ROAD, CONCESSION 11, WINDHAM. 2.3km W of Highway 24

Load Rating of a Steel Composite Girder Bridge

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer

PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE

Ellis Powell, PE NCDOT State Construction Engineer

Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013

ABC Techniques for Rapid Bridge Replacement. Bala Sivakumar HNTB Corporation. Purdue Road School 2017

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

Presenter: Contributing Authors: Guy C. Nelson PE, SE TEG Engineering, LLC Structural Engineer

Ironton Russell Bridge Project

Rapid Repair Materials and Construction Rapid Bridge Repair Workshop Holiday Inn Tanglewood-Roanoke, Virginia May 21 and 22, 2009

SEISMIC DESIGN AND RETROFIT OF BRIDGES ON MISSOURI S EARTHQUAKE PRIORITY ROUTES

Replacing the Aging US 52 Mississippi River Bridge

In Service Replacement of Box Girder Bottom Slab

Economical Design / Case Studies

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation

BRIDGE CONSTRUCTION APPROACHES

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

Highway Bridge Structure Components

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 69J13 RAILROAD STREET OVER STORM SEWER CITY OF DULUTH

Society of Women Engineers Region H Conference

STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE

The Pennsylvania Rapid Bridge Replacement Project

Ironton Russell Bridge Project

MOVABLE SPAN BRIDGES. Bridge of Lions, St. Augustine, Florida

Baseline Document Change Announcement

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

Experiences and Practices: Bridge Moves. Presentation Outline

RESILIENT INFRASTRUCTURE June 1 4, 2016

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce

Bridge Economy & Life Cycle Costs of Steel & Concrete Bridges

HALLS RIVER BRIDGE REPLACEMENT

STGEC Pre-Bid Load Testing for the Mobile River Bridge and Bayway Public Private Partnership (P3) Project

Ontario Structure Inspection Manual Inspection Form Structure Number: 12

BRANT - NORFOLK TOWNLINE ROAD

Transcription:

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Presentation Outline Project History Project Scope Construction Alternatives Plan Development Contractor s Methodology Current Project Status

Project History Site Information West Monroe, LA LA 3249 (Well Road) over I-20 Well Road Overpass Truck Stop

Project History Site Information High Average Daily Traffic (ADT) I-20 41,300 ADT LA 3249 (Well Road) 18,700 ADT High truck traffic

Project History Existing Bridge Built in 1963 4 Simple Span Composite Steel Plate Girder Bridge (55 ft 70 ft 85 ft 50 ft) Lightweight concrete deck

Project History Bridge Condition Deck Deterioration

Project History Deck Deterioration

Project History Deck Deterioration

Project History Bridge Condition Bearing Corrosion

Project History Bearing Corrosion (Cont.)

Project History Bridge Condition Column Bent Spalling

Project History Bridge Load Testing (March 2008) Bridge Diagnostics, Inc. (BDI) performed the testing Determine the structural capacity considering deck deterioration Review the load rating Provide information to assist in determining the best course of action for rehabilitation

Project History Bridge Load Testing

Project History Bridge Load Testing Finite Element Model Calibrated to match the test results The structure was load rated Results The bridge did not need to be load posted An overlay could be applied

Project History Temporary Repairs Quick Set Concrete Patches

Project History Temporary Repairs Asphalt Overlay Recommended by the District to reduce maintenance

Presentation Outline Project History Project Scope Construction Alternatives Plan Development Contractor s Methodology Current Project Status

Project Scope Project created in mid 2008 to perform permanent repairs Funded by State Surplus Aggressive delivery schedule Proposed July 2009 letting

Project Scope Requirements Replace the deck Minimize impacts to businesses and the traveling public Maintain vertical clearance Strengthen substructure if necessary Considerations High ADT Heavy Truck Traffic Future widening

Accelerated Construction

Presentation Outline Project History Project Scope Construction Alternatives Plan Development Contractor s Methodology Current Project Status

Construction Alternatives Accelerated Construction Precast Panel Units

Construction Alternatives Accelerated Construction Precast Panel Units

Construction Alternatives Accelerated Construction Span Replacement

Construction Alternatives Accelerated Construction Span Replacement Self-Propelled Modular Transporters (SPMT s)

Construction Alternatives Accelerated Construction Span Replacement Self-Propelled Modular Transporters (SPMT s)

Construction Alternatives Accelerated Construction Span Replacement Crane

Construction Alternatives Accelerated Construction Recommend span replacement Reduce traffic impacts Limit overall closure period

Presentation Outline Project History Project Scope Construction Alternatives Plan Development Contractor s Methodology Current Project Status

Plan Development Project Initiation Task order was created with Modjeski and Masters (NTP issued July 2008) Design and develop plans for the new steel girder spans with a concrete deck Load rate the repaired bridge Develop plans to strengthen the substructure if necessary Establish constructability Traffic control plan

Plan Development Steel Girder Replacement Spans 28 clear roadway Weathering steel rolled W-shape girders Girders to be composite with deck 7 ½ thick concrete deck Epoxy coated deck steel

Plan Development Steel Girder Spans

Plan Development Bridge Load Rating Existing bridge was designed using the HS-20 truck The rating showed that the substructure required strengthening using LRFR (HL-93 truck)

Plan Development Substructure Strengthening A spread footing was added between the existing pile footings of column bents Drilled shafts were added to the existing end bents

Plan Development Substructure Strengthening Column Bent Spread Footing

Plan Development Substructure Strengthening End Bent Strengthening (Drilled Shafts)

Plan Development Suggested Method of Construction Construct spans in a staging area Move the spans using SPMT s Replace the spans over four consecutive nightly closures from 7:00 PM to 7:00 AM Replace all four spans over a weekend closure beginning at 7:00 PM Friday and re-opening the bridge at 7:00 AM the following Monday

Plan Development Suggested Method of Construction

Plan Development Suggested Method of Construction

Plan Development Suggested Method of Construction

Plan Development Prefabrication Plan Geotechnical assessment Design of temporary supports Settlement analysis and monitoring

Plan Development Movement Plan As-built survey Moving equipment Path of movement Lift point locations Analysis of temporary loads on spans Geotechnical assessment Span monitoring Contingency planning

Plan Development Span Monitoring 10 Elevation reference points per span Monitoring Intervals Before Lift Immediately After Lift As needed through transport to maintain relative elevations Final Position

Plan Development Traffic Control Plan Road Closed Road Closed Temporary Detour

Plan Development Traffic Control Plan Temporary Detour Road

Plan Development Traffic Control Plan Project Site

Plan Development Project was let in December 2009 Engineer s Estimate $3.95 Million Contractor s Bid Price $ 3.17 Million Awarded to Gibson and Associates Work Order issued March 2010

Presentation Outline Project History Project Scope Construction Alternatives Plan Development Contractor s Methodology Current Project Status

Contractor s Methodology Staging area within the interchange Temporary steel pipe trestle SPMT s to move the spans Perform the moves over a weekend closure

Contractor s Methodology Staging Area and Movement Path Staging Area

Contractor s Methodology Temporary Support

Contractor s Methodology Temporary Support

Contractor s Methodology Movement Method

Contractor s Methodology Movement Method

Presentation Outline Project History Project Scope Construction Alternatives Plan Development Contractor s Methodology Current Project Status

Current Project Status Substructure Strengthening

Current Project Status Substructure Strengthening

Current Project Status Substructure Strengthening

Current Project Status Span Construction

Current Project Status Span Movement Span movement plan is currently under review Span movement is tentatively scheduled for early February 2011

The End