PGE s 2013 Integrated Resource Plan

Similar documents
,QWHJUDWHG 5HVRXUFH 3ODQ

INTEGRATED RESOURCE PLAN

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016

2009 Integrated Resource Plan. PNUCC Board of Directors Meeting. January 7, Copyright 2010 Portland General Electric. All Rights Reserved.

Northwest Power and Conservation Council

Zero Net Carbon Portfolio Analysis

Integrated Resource Plan NOVEMBER EXECUTIVE SUMMARY

Idaho Power s Transmission System. Greg Travis Nov. 8, 2018

2015 PSE IRP EXECUTIVE SUMMARY

Pacific Northwest Low Carbon Scenario Analysis

Investor Presentation. August 2013

2015 PSE IRP EXECUTIVE SUMMARY

Analysis Regional Portfolio Model Results. Conservation Resources Advisory Committee September 2, 2015

Scenarios Proposed for Testing

2011 IRP Public Input Meeting. December 15, Pacific Power Rocky Mountain Power PacifiCorp Energy

100% Fossil Free Electricity. June 27, 2018

Appendix 13. Renewable Energy Market Potential

RESOURCE PLAN DECISIONS

Boardman to Hemingway Transmission Line Project

Pacific Northwest Low Carbon Scenario Analysis

PacifiCorp s 2017 Integrated Resource Plan Update. Public Utility Commission of Oregon Public Meeting - July 3, 2018

Draft 7 th Plan Scenarios Proposed for Testing

Briefing Paper for the SageCon Partners Estimates of Oregon Renewable Development through 2025

Wells Fargo 11 th Annual Pipeline, MLP, and Energy Symposium. New York City December 5, 2012

Pacific Northwest Low Carbon Scenario Analysis

Energy Storage at PGE. Regional Dynamics

2011 Integrated Resource Plan

Pacific Northwest Low Carbon Scenario Analysis

January 26, We have attached a summary of the Boardman plan from the PGE website for additional background.

Selected Findings from Scenario and Sensitivity Analysis Conducted To Date. August 6, 2015

Williams Capital Group West Coast Utilities Seminar. March 19-20, 2014

2017 IRP Update. Proposed Long Term Resource Strategy Proposed Conservation

INTEGRATED RESOURCE PLAN

Integrated Resource Planning at Tacoma Power. Ahlmahz Negash EE 500E Energy & Environment Seminar University of Washington

2012 Utilities Forum - Baltimore

The Future of CSP: Dispatchable Solar Power

CHAPTER 3: RESOURCE STRATEGY

January 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND:

Pacific Northwest Low Carbon Scenario Analysis

August 22, 2014 FIRE ISLAND WIND

Pacific Northwest Low Carbon Scenario Analysis

Analysis of Beyond the Fence Solutions When the Fence Surrounds Four States

Table 10.1 DRAFT IRP Action Plan

December 5, SUBJECT: Briefing on Public Generating Pool Decarbonization Study. Therese Hampton, Public Generating Pool, Arne Olsen, E3

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE

2017 IRP Advisory Group. July 21, 2017 IRPAG

INTEGRATED RESOURCE PLAN

MEMORANDUM. January 6, Power Committee. Maury Galbraith. Draft Sixth Plan Electricity Price Forecasts

Regional Resource Adequacy Studies

The Seventh Power Plan The Proposed Mix of Generation Resources and Strategies for the Region

Pacific Northwest Low Carbon Scenario Analysis

Eugene Water & Electric Board. The Future of Utilities in the Pacific Northwest

Western Energy Imbalance Market and Regional Initiatives

Hetch Hetchy Integrated Resource Plan Commission Meeting May 23, 2017

Appendix C. Regulatory Compliance Matrix DRAFT 2018 OR IRP

July 5, 2018 MEMORANDUM. Power Committee. John Ollis, Power System Analyst. SUBJECT: Wholesale Electricity Price Forecast BACKGROUND:

Review of BC Hydro s Alternatives Assessment Methodology

Investor Presentation

IRP Advisory Group 2017 IRP Kick Off

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J.

Resource and Financial Impact of Clean Line P&E HVDC Delivered Wind Resources for TVA

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions

Proposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

Electricity Markets. Rapid Conference May 17, Mike Rencheck Rencheck Consulting LLC

2016 Integrated Resource Plans. Duke Energy Carolinas and Duke Energy Progress

Investor Presentation March 2016

I 5 Corridor Analysis Phase 1 Report

Preliminary Assumptions for On-Shore Wind Technologies. Gillian Charles GRAC October 2, 2014

Executive Summary PSE Integrated Resource Plan. Contents. Chapter 1: Executive Summary

Meeting the Challenge of Climate Change

New England States Committee on Electricity

The consumer and societal benefits of wind energy in Texas

Elliot Mainzer, BPA. NW Wind Integration Forum SC Meeting June 6, 2011

Utility Integrated Resource Plans (IRPs) are beginning to

Observations on US Renewable Energy Trends

Peninsula Clean Energy could launch a CCE by Fall January October 2015 October 2015 February 2016 March 2016 October 2016

PWP 2015 IRP Update Energy Roadmap Event

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1

The Southwest Intertie Project: Assessment of Potential Benefits

June 5, 2018 MEMORANDUM. Council Members. John Fazio, Senior Systems Analyst. SUBJECT: Briefing on Adequacy Analysis and Report BACKGROUND:

March 7, SUBJECT: Update from Portland General Electric on Their IRP

July 1, SUBJECT: PNUCC presentation: Carbon - a Northwest perspective

Zero Net Carbon Portfolio Analysis

Investor Presentation August 2016

Roadmaps for Demand Response & Storage

2007 Integrated Resource Plan

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON LC66

Investor Presentation. Portland General Electric February 2019

Renewable Integration The California Experience

2011 RFP for All Generation Sources Proposal Conference

2015 Procurement Plan Thermal Resource Specifications

MEMORANDUM. April 2, Council Members. Charlie Black, Power Planning Division Director. Primer and Briefing on Generating Resources

Integrated Resource Planning. Roundtable 17-2 May 10, 2017

MEMORANDUM. March 5, Council Members. Charlie Black, Power Planning Division Director. Primer and Briefing on Generating Resources

The economic benefits of wind energy in the Southwest Power Pool

Resource Assumptions. Future Renewable PPA Prices

Rick Haener September 4th, 2015

Highlights and Key Results

Overview of the Northwest Power and Conservation Council s Power Plan Development Process. Webinar. October 15, Agenda

Transcription:

PGE s 2013 Integrated Resource Plan OPUC Public Meeting 2014 Portland General Electric. All rights reserved.

Today s topics IRP public process Load-resource balance Assumptions and inputs E3 low-carbon portfolio process Flexible capacity analysis Portfolio analysis, results & observations PGE s 2013 IRP Action Plan PGE s next IRP 2

IRP public process Pre- 2013 IRP Apr.- Nov. 2013 Q4 2013 Q1 2014 Worked with E3 and Stakeholders to develop low-carbon portfolios Launched 2013 IRP process 5 public meetings, 3 technical workshops, written responses to questions Issued Draft 2013 IRP for public review November 22, 2013 Comments received January 22, 2014 Mar. 2014 Q2-Q3 2014 Q3-Q4 2014 Filed Final 2013 IRP March 27, 2014 Discovery & comments submitted by Parties (June-August) OPUC Public Meeting to consider comments OPUC Order on 2013 IRP (estimated) 3

PGE Load-Resource Balance Energy position prior to RFP major resources 4

PGE Load-Resource Balance Winter capacity position prior to RFP major resources 5

PGE s 2009 IRP: Acknowledged Action Plan New Energy & Capacity Resource Actions: Acquire new demand-side resources by 2016: All ETO-targeted EE 60 MW of demand response 67 MW of additional dispatchable standby generation Acquire new renewables to meet the 2015 Oregon RPS with physical resources Approximately 101 MWa of new renewable resources Acquire new baseload energy and peaking capacity 300-500 MW high-efficiency combined cycle gas plant Approximately 200 MW of flexible gas capacity resources Peak season capacity resources of up to 350 MW Fuel, Transmission, and Boardman 2020 Plan Actions: New Natural Gas Transportation & Storage Acquire pipeline & storage capacity to meet the fueling requirements of new gas-fired energy and capacity resources, and maintain portfolio flexibility Cascade Crossing Transmission Line Construct new 500 kv transmission line from Boardman to PGE system (conditional acknowledgement) Implement Boardman 2020 Plan Install new emission controls to meet Oregon Regional Haze / BART and Utility Mercury Rule requirements Cease coal-fired operations at Boardman in 2020 6

PGE s new generation projects Tucannon River Wind Farm 116 Siemens 2.3 MW wind turbine generators (SWT 2.3 108) Capacity: ~267 MW Expected annual energy: ~100 MWa Location: Columbia County, Washington Expected in-service: December 2014 - March 31, 2015 Carty Generating Station High-efficiency, natural gas-fired combined cycle combustion turbine (Mitsubishi M501 GAC) Capacity: ~440 MW Location: Morrow County, Oregon Expected in-service: Mid-year 2016 Port Westward 2 Highly-flexible natural gas-fired power plant (12 Wärtsilä 18.5 MW reciprocating engine-generator sets) Capacity: ~220 MW Location: Columbia County, Oregon Expected in-service: Q1 2015 7

PGE portfolio composition 2014 vs. 2017 2014 Resource Capability (MWa) 2017 Resource Capability (MWa) 8

PGE Load-Resource Balance Energy position with RFP major resources Forecast annual average energy growth = 1.3% 9

PGE Load-Resource Balance Winter capacity position with RFP major resources Peak load includes 6% planning reserves = ~ 220 MW in 2018 Forecast peak demand growth = 1.0% winter 10

Key assumptions and inputs PGE customer demand projection: annual average load growth of approximately 1.3% per year (2014-2033, including effects of EE) Natural gas price: $4.76/MMBtu (real levelized 2013$ for 2014-2033) Wood Mackenzie spring 2013 long-term forecast CO 2 tax: $18/ton (real levelized 2013$ for 2023-2033) Wood Mackenzie spring 2013 long-term forecast In 2023 = $16/ton (nominal$) with 6% real growth PTC and ITC: available through 2022 Wind integration cost: $3.99/MWh (2018$) All portfolios meet physical compliance with Oregon RPS through 2025 All portfolios meet forecast peak winter capacity need (except Market portfolio) 11

Natural gas long-term price forecast Wood Mackenzie spring 2013 (reference, high, low) 12

Carbon futures Range of CO 2 costs modeled Guideline 8: Reference Case should reflect the most likely regulatory compliance future Using Wood Mackenzie s projection of a federal carbon pricing scheme for CO 2 ($18/ton real-levelized 2013$) CO 2 compliance scenarios from current level to the upper reaches of credible proposals Zero Low ($15/ton) Synapse Low ($21/ton) Synapse High ($54/ton) Trigger point CO 2 scenario that alters portfolio selection ($150/ton real-levelized 2013$) 13

Supply-side resource options Life-cycle cost of energy Source: Black & Veatch studies, PGE internal information 14

E3 portfolio process Objectives As an outcome of the 2009 IRP process PGE and a stakeholder group engaged consulting firm E3 to conduct analysis and help develop low carbon portfolios to be evaluated in the 2013 IRP Our IRP includes three lowcarbon candidate portfolios resulting from this process: Incorporate higher levels of EE (beyond ETO) Add renewables in excess of 2025 RPS requirement 15

E3 portfolio process Objectives E3 work also assessed actions to establish a glide path to achieve aggressive future GHG emissions reductions targets for PGE portfolio Implied long-term targets 2020: 15% below 2005 2050: 80% below 2005 Displacement of Colstrip also considered in E3 analysis to meet 2050 emissions reduction target Our Action Plan includes a study of emerging EE w/ ETO 16

Flexible capacity analysis Context Order No. 12-013 requires a forecast of supply of and demand for flexible capacity PGE s approach informed by NW Power and Conservation Council paper in 2012 on the ability of resources to meet ramping requirements Demand & Supply Rapid response resources required for variable energy resource output and short-term load changes Existing hydro resources can ramp up or down over short periods of time Port Westward 2 (PW2) will provide additional ramping capability Dispatchable standby generation can ramp up very quickly Other resources provide some ramping capability, but are less responsive and flexible 17

2015: Flexible capacity supply and demand 60 minutes Within the hour conclusions: Supply is able to meet up-ramp demand in 2015 Flexibility requirements due to additional wind (2015 RPS) are offset by PW 2 Supply is unable to meet all down-ramp demand in 2015 Wind could be feathered to offset this lack of capability 18

2020: Flexible capacity supply and demand 60 minutes Conclusions cont d: Supply is insufficient to meet all up-ramp demand in 2020 without additional flexible resources 19

18 candidate portfolios Resource additions through 2025 Energy E3 inspired Capacity contribution 20

36 Futures PGE risk drivers PGE Load Hydro Conditions Capital Costs CO 2 Tax Power Prices Fuel Price Futures Wind CF 21

Portfolio analysis Reference Case cost 22

Portfolio analysis Risk - severity and variability 23

Portfolio analysis LOLP reliability results 24

Portfolio analysis Box and whisker plot Box and whisker plot summarizes the result distributions End points of lines represent best (lowest) and worst (highest) cost outcomes Line space above and below the box represent 25% of outcomes 50% of outcomes within the box X marks the reference case Colored circles are 10 th (blue) and 90 th (orange) percentiles 25

Portfolio analysis Top performers All three portfolios pursue physical RPS compliance in 2020 and 2025 Natural Gas: Add CCCT in 2021 and 2024 Baseload Gas/RPS only: Add CCCT in 2019 and 2021 Diversified Baseload Gas/Wind: Add CCCT in 2019 and 2021 Additional wind in 2017, 2018, 2023 (beyond RPS) 26

PGE CO 2 Profile Total emissions and impact of resource actions Portfolio Actions through 2024 (post Boardman 2020 Plan) reduce projected PGE CO 2 emissions by over 40% (as compared to CO 2 emissions projection absent abatement actions). Projected aggregate CO 2 emissions decline by 20% in 2024 from 2000 levels. Above CO 2 targets (dotted lines) represent various State of Oregon aspirational goals for CO 2 reduction. Boardman coal replaced with Northwest Regional Mix CO 2 profile in 2021 (roughly equal to CCCT). 27

PGE CO 2 Profile Emissions intensity net of resource actions CO 2 intensity of PGE portfolio steadily declining since 2000 projected to achieve nearly 40% reduction by 2024 Boardman coal replaced with Northwest Regional Mix CO 2 profile in 2021 (roughly equal to CCCT). 28

2013 IRP key observations & findings Projected post-rfp PGE portfolio is largely balanced through 2017 (IRP Action Plan horizon) No new supply-side resources proposed in this IRP Natural gas prices remain low & stable Prices projected to increase modestly in the future, but abundant domestic supply is expected to keep prices at relatively low levels Uncertainty regarding regulation of Greenhouse Gas emissions remains Federal agency action is in process; effect on existing plants not yet determined Unclear whether CO 2 costs will be levied on electric generators at either the Federal or State level in the future IRP analysis indicates that high efficiency, natural gas-fired generation (CCCT) currently represents the lowest expected energy cost for future supply-side resource alternatives (based on reference case gas price forecast) Balanced portfolios (combination of EE, renewables, and natural gas-fired generation) generally exhibit the best overall cost and risk performance under uncertain future conditions 29

2013 IRP Action Plan Resource additions through 2017 No new long-term supply-side resources proposed Renew legacy hydro contracts if available and economic Energy efficiency (via ETO): 124 MWa (158 MW total) Dispatchable Standby Generation: additional 23 MW (116 MW total) Demand response: additional 25 MW (45 MW total) Short- and mid-term market purchases & sales to balance portfolio Studies and initiatives to inform PGE s next IRP Review load forecast methodology Assess emerging EE (with ETO) Evaluate distributed generation (solar PV) Continue technical & economic assessment of Boardman biomass Assess dynamic dispatch requirement & capabilities Review new analytical tools for optimizing portfolio commitment and dispatch Assess longer-term gas supply alternatives to address price volatility 30

Major topics of PGE s next IRP Boardman plant replacement (2021) Meeting growing RPS requirements Meeting increased gas fueling needs Future environmental regulations Energy Imbalance Market (EIM) Impact of California solar (the duck chart) Future capacity/flexible resource needs Regional Supply-Demand balance (+2,000 MW of coal retirements) 31

Conclusion Thank you! Brett Sims PGE Director Origination, Structuring & Resource Strategy Brett.Sims@pgn.com 503-464-7255 32