PIPEJACKING AND MICR OTUNNELLIN G. James C. Thomson, C. Eng., Eur. Ing. Chairman Jasoo Consultancy Group London- Geneva- Washington DC

Similar documents
PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

Pipe Jacking. Japan Sewage Works Association

Experts in tunneling with Tunnel Boring Machines

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

Trenchless Pipeline Crossings

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

An introduction to. pipe jacking

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Tel: Neil: Tony: Website:

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

WARNING DO NOT BID ON THIS PROJECT

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

1.0 Micro Tunnelling An overview

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Concrete Pipe Jacking

TBM Selection and Specification

Introduction to Tunnel Construction

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

CC1602 Microtunneling

Design Data 4. Jacking Concrete Pipe

Design Data 4M. Jacking Concrete Pipe

APPENDIX: C. Stormwater and Wastewater Construction Specification. Tauranga City Council

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward


E-Power Pipe : A new trenchless method for underground cable installation

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

The new Standard DWA-A 125E. Pipe jacking and related techniques. published in German and English by

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

Trenchless Technology

A number of abbreviations and technical terms have been used in this guideline:

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

ITEM 432 TUNNEL CONSTRUCTION

Mechanised Shield Tunnelling

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

Lesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

Grouting Bilfinger Spezialtiefbau GmbH

Prof. Eng. Daniele PEILA

Design, Specification and Selection of Concrete Jacking Pipes Who Decides? What Really Matters?

Agenda for Today s Workshop

Concrete Pipe Jacking

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Dahlia Ponds Tunnel Project. Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless

MEMORANDUM TO THE INDUSTRY

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Sewerage Code WSA Addendum PART 4 - CONSTRUCTION

Hardrock Tunnel Boring Machines

TRENCHLESS TECHNOLOGY SYSTEMS

IPC Company & DPI Presentation. February 2017

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

Venice Pumping Plant Dual Force Main Project Draft EIR

SITE INVESTIGATION. Foundation Engineering

Horizontal Directional Drilling

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring

Cost Estimating Framework

Scottish Water has recently commenced the first phase of construction on a 120m investment project designed

Wastewater Capital Projects Management Standard Construction Specification

Pipe Jacking. Progress is built on ideas.

Draft. Not yet Approved TABLE OF CONTENTS. Page

SECTION BORING AND/OR JACKING PIPE

2 Technology of closed-face tunnelling machines

February 7, Purpose. Background. the BDCP. needs the project. Discussion. Facilities 1. plants) 1, October 1, 2013,

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

SPECIFICATION : BORING AND JACKING

Gravity Sewerage Code of Australia WSA

Performance review of a pipe jacking project in Hong Kong

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

Compaction and Jet Grouting

Pipe Express - Ideal for pipeline installations in environmentally sensitive areas.

QUANTIFYING THE EFFECTS OF LUBRICATION ON JACKING FORCES

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

Exploring Critical Factors Affecting upon Micro-tunnelling Equipment Productivity

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

Assessment of Pipeline Installation Using the Eliminator: a New Guided Boring Machine. Mahmood Ranjbar

Transcription:

PIPEJACKING AND MICR OTUNNELLIN G By James C. Thomson, C. Eng., Eur. Ing. Chairman Jasoo Consultancy Group London- Geneva- Washington DC m BLACKIE ACADEMIC & PROFESSIONAL An lmp""t cl Chapman & Hall London Glasgow Weinheim New York Tokyo Melbourne Madras

Contents Development of trenchless tecbnology 1.1 Recent growth of trenchless technology l 1.1.1 Categories of trenchless technology 2 1.2 Defining pipejacking and microtunnelling 3 1.2.1 Pipejacking 3 1.2.2 Microtunnelling 6 1.3 A historical perspective 6 1.3.1 Pipejacking 6 1..3.2 Microtunnelling 13 2 Pipejacking and microtunnelling methods 15 2.1 Elements of pipe jacking 15 2.1.1 The face 15 2.1.2 Theline 17 2.1.3 The jacking pit 20 2.1.4 Top side- surface equipment 22 2.2 Applications of pipejacking and microturu:elling 23 2.2.1 Line instaliation 23 2.2.2 Installation of ducts 26 2.2.3 Crossings 28 2.2.4 Pipe excavation techniques 29 2.3 Advantages and limitations of pipejacking an d microtunnelling 30 2.3.1 Working in a wide range of soil conditions 31 2.3.2 Minimising damage to property and existing services 31 2.3.3 Minimising disruption to the public an d the environment 32 2.3.4 Safe working for operati ves and public safety 32 2.3.5 lnstalling to owner' s satisfaction 33 2.3.5 Providing a cost-effective solution 34 3 Equipmeot: shields and tunnel boring machines 35 3.1 lntroduction 35 3.2 Classc-s of equipment 35 3.2.1 Conventional (open) shields 36 3.2.2 Compressed-air shields 40 3.2.3 Auger-type shields 41 3.2.4 Pressure chamber shields 41 3.2.5 Design and constr uction of shields 47 3.3 Spoil cutting 48 3.3.1 Manualexcavation 48 3.3.2 Partially-mechanised excavation 48 3.3.3 Rotary cutting arms and wheels 50 l

CO~ TE :"TS 3.3.4 Full facc machines 51 3.3.5 Crushing heads 53 3.3.6 Rock heads 54 3.4 Shield location, guidancc and monitoring 55 3.4.1 Location 55 3.4.2 Guidancc 60 3.4.3 Monitoring additional inionnation 61 4 Pipejacking: line, drh'e pit, top side 62 4.1 Spoil removal 62 4.1.1 Wheeled systerns 62 4.1.2 Bel t an d c ha in conveyors 64 4.1.3 Positive displacement pumps 64 4.1.4 Pumped sluny 64 4.1.5 Screw conveyors 66 4.1.6 Vacuum extraction 67 4.2 Jacking equipment 67 4.2.1 Jacking rigs 67 4.2.2 Intermedia te jacking stations (I]Ss) 70 4.3 Top side: surface equipment 73 4.3.1 Spoil handling and disposal 73 4.3.2 Pipe and other materia! handling 75 4.3.3 Power supplies: air, hydraulic and electric 76 5 Equipment: microtunnelling 77 5.1 Classifying rnicrotunnelling equipment 77 5.2 Pilot-bore microtunnelling 78 5.2.1 Stage one, the pilot bore 78 5.2.2 Stage two, enlarging the bore 81 5.3 Auger-bore microtunnelling 83 5.3.1 Drive types 83 5.3.2 Head variations 85 5.3.3 Line installa ti o n 89 5.3.4 Equipment manufacturers and suppliers 90 5.4 Pressure balance microtunnelling equipment 91 5.4.1 Water balance machines 92 5.4.2 Bentonite slurry machines 94 5.4.3 Earth pressure balance machines 95 5.4.4 Manufacturers and suppliers % 5.5 Displacement methods of rnicrotunnelling % 5.6 Microtunnellers for on-line replacement 97 5.7 Microtunnellers for house connections 98 5.8 Site equipment 100 6 Design concepts 102 6.1 Role of client, engineer and contractor 102 6.1.1 Traditional approaches to design 102 6.1.2 Global trends 102 6.1.3 The changing nature of work 103 6.1.4 lntegrated design 103 6.2 Conceptual design for sewer installation 104 6.2.1 Line installation: alignment, gradient and depth 104 6.2.2 Subsurface considerations 107 6.2.3 Construction considerations 107 6.2.4 Traffic, social and environmental considerations 108 6.3 Location of crossings 109

\ 0:-.ITEl\ TS Xl 6.3 l Planning and design 109 6 3.2 lnvestigation 109 6.3.3 Crossing waterways 109 7 Subsurface and site investigation 111 7 l Subsurface investigation III 7. 1.1 Cost of investigation 112 7. 1.2 Borehole sampling and laboratory testing 112 7. 1.3 Borehole and field testing 114 7. 1.4 ln-situ test methods 11 5 7. 1.5 Geophysical techniques 117 7. 1.6 Jnfonnation from testing 118 7.2 Site investigation 120 72 1 Types of investigation 120 7.2.2 Points of conflict with Wldergrolllld structures 121 8 Design: permaneot works 123 8. l Pipes an.d pipe c~nnections 123 8.1.1 Requirements for jacking pipes 123 8. 1.2 Concrete pipes 124 8. 1.3 Glass-reinforced plastic pipes (GRP) 129 8.1.4 Asbestos cement pipes 132 8. 1.5 Clay pipes 133 8. 1.6 Plastìc pìpes 135 8. 1.7 Ductile iron - pressure applications 135 8.2 Slructural design principles and methods 137 8.2.1 Principles of pipe analysis 137 8.2.2 Loads on buried pipes in service 142 8.2.3 Design of pipes 146 8.3 Protective linings and coatings 148 8.3. 1 Plastic sheet linings 148 8.3.2 Composite pipes 148 8.4 Pennanent access shafts 149 8.5 Sewer connections 150 8.5.1 Direct connections oflaterals 150 8.5.2 Connection via shafts 151 8.6 lnstauation of a pipe within a sleeve 153 8.6. 1 Differences in practice 153 8.6.2 Filling the annular space 155 8.6.3 Cable instauation 155 9 Design: cboice of metbod 156 9.1 Types of fa il ure 156 9.2 Thcory offace stability 157 9.2.1 Factors influencing face stabijity 157 9.2.2 Stability of granular soils 160 9.3 GroWld deformatioo 165 9.4 Contro! offace stability 170 9.4.1 Ground treatment 171 9.4.2 Cboosing a shield or TBM 172 9.5 Rock 176 lo Temporary work design: tbe line 178 l O. l Jacking loads 178 10.1.1 F ace resistance 179

xii CONTEL'\TS 10.1.2 Une friction loads 182 10.2 Factors inouencing jacking forces 185 10.2.1 Soil stability and ground water 185 10.2.2 Dclays 188 10.2.3 Lubrication 189 10.2.4 Coatings and rnembranes 194 10.2.5 Overcut ratio 1% 10.2.6 Pipe extemal surface 197 10.2.7 Misalignment 198 10.3 Pipe loads 200 10.4 Curved drives 200 11 Drive and reception pits 202 11.1 Dimensions 201 11.1.1 Drive shafts 201 11.1.2 Reception pits 201 11.2 Shaft construction 201 11.2.1 Stable ground and shallow depths 202 11.2.2 Unstable ground and deep shafts 205 11.3 Safe entry and exit from shafts 209 11.3.1 Stabilisation outside the shafts 210 11.3.2 Sealing eyes within the shaft 210 11.3.3 Key issues for entry and exit of shafts 212 11.4 Reaction walls 212 11.4.1 Reaction walls in shafts 212 11.4.2 Reaction structures at ground leve! 214 12 Design: contract documents 216 12.1 Responsibility for documentation 216 12.2 Conditions of contrae! 216 12.2.1 Standard forms 216 12.2.2 Ti me for completion 217 12.2.3 Limitations 217 12.2.4 Allocation of risk 217 12.3 Lega! considerations 219 12.3.1 Sa fety legislation 219 12.3.2 Enviromnental legislation 221 12.4 Specification 222 12.5 Drawings 225 12.6 Bìlls of quantities 225 12.7 Submissions 226 13 Site contro! and supervision 228 13.1 Si te organisation and management 228 13.1.1 Site responsibilities 228 13.1.2 Operator training 229 13.2 Si te works shafts and machines 229 13.2.1 Shafts 229 13.2.2 Machine considerations 230 13.2.3 Set-up efficiency 230 13.2.4 Tumarounds 230 13.2.5 Driving 231 13.2.6 Adding new sections 231 13.2.7 Obstructions 232 13.2.8 Working in rock 233 13.3 Monitoring and contro! 233

CONTE~TS xiii 13.3.1 ContTolling line and leve! 233 13.3.2 Angular deviation 234 13.3.3 Stecring systcms 234 13.4 Safety 235 13.4.1 Man-entry diameters 235 13.4.2 Explosion 236 13.4.3 Vcntilation 236 13.4.4 Lighting and conununications 236 13.4.5 Shaft area 236 13.4.6 Use of chemicals and additives 237 13.4.7 Hazardous spoil 237 14 Economie consideradons 238 14.1 Variability of costs 238 14.2 Project cost appraisal 238 14.2.1 Direct costs 239 14.2.2 [ndirect costs 240 14.2.3 Soci al costs 241 14.2.4 Alternative approaches to social costs 243 14.3 Estimating costs 244 14.4 Key cost factors 245 14.4.1 Pipe 245 14.4.2 Sha.fts and pits 249 14.4.3 Tnsta llation 249 14.5 Budget costs 254 14.6 Costs of crossings 254 14.6.1 Casings 900 nun or less 254 14.6.2 Pipejacking 255 14.7 Comparison with open eu t 256 14.7.1 Traditional open cut sewer installation 256 References 260 Glossary 265 In d ex 270