PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

Similar documents
Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Project Scope Management

Planning & Scheduling

Project Time Management

Developing a Project Plan

Global Project Management, LLC

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Scheduling. Adapted from John Musser

Week 5 Project Work Plan

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

Constructing Networks

IST 302 : Project Time Management

Cambridge International AS & A Level Computer Science

6 PROJECT TIME MANAGEMENT

Time Management PLANNING

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Time has the least. amount of flexibility; Schedule issues are the main reason for

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

Views and Layouts for Program Management

Software Project Management

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Project Time Management

Week 5 Project Work Plan

Calculating and Using Float

Week 5 Project Work Plan

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

Calculating and Using Float

Project Management in Practice Fifth Edition

Project Forecast Survey Results Good Scheduling Practices June 2016

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

PLANNING & SCHEDULING

Estimating Project Schedule-Time and Cost

Team Member Application

PMP Exam Preparation Course Project Time Management

Week 5 Project Work Plan

Project Time Management

Project Management THE MANAGERIAL PROCESS

Artificial Intelligence

Embarking new Project

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Estimating and Scheduling

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

LONG INTERNATIONAL. Robin K. Long, PMP

THE PMP EXAM PREP COURSE

Scheduling Resources and Costs

davidbaileyfcca finance development consultancy Leadership Skills for Service Redesign Leadership Skills for Service Redesign 17 January 2018

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

CE2353-CONSTRUCTION PLANNING & SCHEDULING

Information Technology Project Management, Seventh Edition

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Chapter 7 at a Glance

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Links, Lags and Ladders - the subtleties of overlapping tasks -

PROJECT TIME MANAGEMENT

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

Sample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda

Project Management Techniques

Organization of Software Projects

ConstructionOnline Scheduling Getting Started Guide. ConstructionOnline is presented by UDA Technologies

Imagine this: If you create a hundred tasks and leave their default constraints

Project Management. Term Project. Conveyor Belt Project

Principles of Planning for IT Projects

Lessons Learned Schedule Updating and Maintenance using Primavera P6

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Chapter 3 Managing Systems Projects

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak

Project Management. Time and Resources DPLE 157

P6 Instructors Sample Presentation

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

CHAPTER 1. Basic Concepts on Planning and Scheduling

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Dr. Richard Jerz rjerz.com

Resource-constrained project scheduling using Relationship Diagramming Method (RDM)

The Basics 7. Introduction 8 Project Management 9 What s New? 10 Version Comparison 12 The Gantt Chart 14 Getting Help 15 Summary 16

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

Work Analysis and Design

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

Retained Logic and Progress Override in Primavera P6

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

Software Process and Management

The Project Planning Process Group

Understanding Import & Export with NetPoint 4.2

Project Management PSGLE 122. Time and Resources

Introduction to Project Management

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

4/28/2016. Presented for Boston College Employee Development Office April 6, 2016 by Denise M. Guérin, JD, MS-PPM, PMP. Q&A from Session #2

Project Scheduling with GanttProject. EGR 386w

Managing Complexity in the Face of Uncertainty

Construction Planning and Scheduling

An evaluation of the time constrained and resource constrained scheduling features of commercially available project management software

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification

An Oracle White Paper June Using Relationship Diagrams to Enhance the Critical Path Method of Project Scheduling

Project Management Glossary of Terms

Transcription:

PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS with FF PDM PDM 3 PDM C. Can be time scaled with software D. Natural progression from the bar chart, easier to understand E. Disadvantage: unable to tell what part of an activity is related to another Finish to Start (FS) A. Most common for scheduling B. Succeeding activity cannot start until the preceding activity has been completed C. Three (3) possible forms using 1. Zero Lag most common. Positive Lag used for concrete to gain strength 3. Negative Lag - sometimes called LEAD PDM 4 PDM 5 Finish to Start (FS) (cont.) 3. Negative Lag succeeding activity can begin before preceding activities have been completed CAUTION Forward pass calculation could vary substantially between a F-S relationship with a (1) lag and a S-S relationship with a + lag Start to Start (SS) A. Draw activities one above the other B. Activities with SS with zero lag start concurrently C. Can use positive LAG D. Do not use negative LAG with SS very difficult to understand E. CAUTION Do NOT use alone, use in combo with FF, or will create errors in the critical path calculations!! PDM 6 PDM 7 1

Start to Start (SS) Start-to-start with positive lag A. Draw activities one above the other B. FF with zero lag most common C. Can use positive LAG D. Do not use negative LAG with FF very difficult to understand E. CAUTION Do NOT use FF alone. Use in combo with SS, or it may create errors in the critical path calculations!! Start-to-start with zero lag PDM 8 PDM 9 Can use all three forms of LAG 1. Zero. Positive 3. Negative (not commonly used, confusing) Zero Lag Finish-to finish with zero lag PDM 10 PDM 11 Positive Lag Start to Finish (SF) Not commonly used Not clear as to how to interpret May include LAG 1 PDM 1 PDM 13

Combo SS & FF SS used with FF to prevent errors in calculating the critical path Activities can be partially or completely concurrent Partially concurrent Start of one activity follows start of another by a few days (LAG = +) Completely concurrent Truly simultaneous activities PDM 14 Combo SS & FF Partially Concurrent EXCAVATION CONCRETE EXCAVATION 6 CONCRETE PDM 15 6 Combo SS & FF Completely Concurrent Logic Loops Avoid at ALL costs! Scheduling software will NOT accept Keep logic SIMPLE to avoid logic loops PDM 16 PDM 17 Logic Loops Dangling Activities All Dogs Have Tails EXCAV ALL activities MUST have an activity that follows WITH a logic relationship EXCEPTION Finish Milestone (No Tail) PDM Diagram with three logic loops PDM 18 PDM 19 3

Dangling Activities Scheduling software interprets ALL Dangling Activities as CRITICAL, and therefore on the CRITICAL PATH Primavera P3.1 and Sure Trak 3.0b both show Dangling Activities as CRITICAL (default setting in software-can be shut off at great peril to the scheduler & project manager) PDM 0 (white board examples) (more to follow in class on Monday) PDM 1 Precedence Diagramming Method (PDM) Part Con E 441 P06 PDM Activity Times ES = Early Start Time Earliest time activity can start after completion of predecessors EF = Early Finish Time Earliest time activity can be completed after completion of predecessors and activity in estimated duration LS = Late Start Time Latest time activity can be started without delaying project completion time LF = Late Finish Time Latest time activity can be completed without delaying project completion time PDM 3 Forward Pass ES for first activity is zero. EFACT = ESACT + DurationACT FS: ESACT = EFPRED + LAGARROW FF: EFACT = EFPRED + LAGARROW SS: ES ESACT =ES ESPRED +LAG LAGARROW SF: EFACT = ESPRED + LAGARROW Governing ESACT is the largest trial ES. Governing EFACT is the largest trial EF OR ESACT plus DurationACT, whichever is greater. Backward Pass LF for last activity is project duration. LSACT = LFACT -DurationACT FS: LFACT = LSSUC LAGARROW SS: LSACT = LSSUC LAGARROW FF: LFACT = LFSUC LAGARROW SF: LSACT = LFSUC LAGARROW Governing LFACT is the smallest trial LF. Governing LSACT is the smallest trial LS OR LFACT minus DurationACT, whichever is least. PDM 4 PDM 5 4

Calculating Float Total Float (if zero, activity is critical): TFACT = LFACT ESACT DURATIONACT Free Float FFACT = ESSUC -EFACT Start Float (if zero, start is critical): SFACT = LSACT ESACT Finish Float (if zero, finish is critical): FNFACT = LFACT EFACT If both Start Float and Finish Float are Zero, the entire activity is critical. PDM 6 HW #3 Due: P07 - Friday, Sept. 14 th @ 9:00 AM Chapter 3: problems: 1, 4, 6, 7 (See WebCT for corrections) Redraw on Engineering problems paper, straight lines, professional appearance (photocopies of problems in textbook NOT allowed). REMINDER: P07: Ch. 4-Activity Durations, Friday, 9/14 P08: Ch. 5-Time In Contracts (BRING TEXTBOOK): Monday, 9/17 P09: Scheduling Logic Skills, Assign HW #15, Friday, 9/1 P10: EXAM NO. 1-Chapters 1 4, Monday, Sept. 4 th See WebCT for split classroom assignments PDM 7 In-Class Examples (work example problem) PDM 8 5