Ironton Russell Bridge Project

Similar documents
Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer

Bonner Bridge Replacement Update:

Tilikum Crossing Transit Bridge. Portland, OR

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE

2016 ACEC/PA ANNUAL MEETING

LRFD Bridge Design Manual Changes

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Economical Design / Case Studies

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS, CENTER FOR ENVIRONMENTAL EXCELLENCE, HISTORIC BRIDGES COMMUNITY OF PRACTICE

Red Wing Bridge Alternates

Final Estimates Level 2

Results you can rely on

I-94/I-69 Interchange Bridge Construction

ABC, FHWA SHRP2 R04: Project update, lessons learned. Finn Hubbard, Fish & Associates Inc. SHRP2 ABC/PBES Implementation Technical Lead

Dan Carrier Parsons Brinckerhoff Project Manager Cooper River Bridge Charleston, South Carolina

Accelerated Bridge Construction in USA

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal

MILTON-MADISON BRIDGE REPLACEMENT

Lesner Bridge Replacement

MICHIGAN DEPARTMENT OF TRANSPORTATION BRIDGE DESIGN GUIDES TABLE OF CONTENTS

I-345 Feasibility Study Public Meeting

ABRAHAM LINCOLN BRIDGE

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

STRUCTURES INSPECTION SELF STUDY TRAINING COURSE PART ONE

Short Span Steel Bridges

Pueblo's New 4th street

I2-0 LIST OF ACTIVE SSDs

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

7 Bridges in 74 Days. NC 12 Detour

Lesner Bridge Replacement

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

PHASING CONSIDERATIONS FOR BRIDGES

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS

EGCE 406: Bridge Design

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS

John James Audubon Bridge

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

ABC Technology and Steel Bridges

ASCE STRUCTURAL ENGINEERING CONFERENCE. Ames Iowa

Get In, Get Out, Stay Out!

John James Audubon Bridge. Introduction

Dulles Corridor Metrorail Project

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION

Class Topics & Objectives

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

PLANNING AND DESIGN PARAMETERS BRIDGE STRUCTURES. Engr. Ericson Mammag Feasibility Study Preparation CHARM2 Project

IMUA ANNUAL PRESENTATION 2013

PennDOT e-notification No. 13

Accelerated Bridge Construction Award

EXODERMIC DEXKS AND STEEL BRIDGES

A NEW STEEL ARCH BRIDGE FOR THE US 52 MISSISSIPPI RIVER CROSSING

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

Safe, innovative, quality construction since Riding on the Strength

3.0 TEMPORARY DETOUR BRIDGES

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - WILKIN COUNTY

Specification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

Society of Women Engineers Region H Conference

Presented by: Taya Retterer BRG Webinar July 30, 2012

New Jersey Turnpike Authority

John A. Roebling Bridge Rehabilitation History

UPDATED 04 OCT 07. Following are sample questionnaires to be used to collect information from owners of affected facilities.

SOUTH MEDFORD INTERCHANGE BRIDGES

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

Fort (M-85) Street Bascule Bridge

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

Accelerated Bridge Construction (ABC) National Status

RESILIENT INFRASTRUCTURE June 1 4, 2016

OHIO S CONCRETE BRIDGES

Jeffrey D. Knueppel, P.E. General Manager. Robert L. Lund, Jr., P.E. Assistant General Manager EM&C

Highway Bridge Structure Components

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)

Alberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.

Construction and design features of the Bridge over the Danube River. Bulgaria

Cumberland Viaduct Rehabilitation Project Contract No. AL R Presenter Bob Bofinger MDSHA Office of Structures

Traffic Technical Memorandum: Hickman Road over Tuolumne River Bridge Replacement Project, Stanislaus County (BRLO-5938(199))

JFK Airport Light Rail Transit System

DESIGN AND LAUNCHING OF A REDUNDANT TRUSS OVER RAILROAD YARD

Corrosion Resistant Reinforcing Steel (CRR)

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY, CITY OF MOORHEAD

Inventory Inspection and Load Rating of a Complex Segmental Concrete Bridge. Presented by Matthew J. Lengyel, PE, SE

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

The bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge.

Transcription:

Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E.

Project Overview The Ironton Russell Bridge Project entails the construction of a cast in place concrete cable stayed bridge over the Ohio River with structural steel approaches connecting the towns of Ironton, Ohio and Russell, Kentucky. The bridge will provide two 12-ft driving lanes and two 4 ft shoulders; a driving lane and shoulder in each direction. Span lengths for the approaches vary widely as they cross numerous (6) rail lines, the Ohio River levee and city streets. On the Kentucky side the spans are 140-ft and 235-ft; in Ohio the spans are 110-ft, 144-ft, 186-ft and 144-ft. The approach bridges are founded on small diameter drilled shafts (Kentucky) or steel pile (Ohio). The main span unit consists of three spans; two flanking spans at 370-ft and the center span of 900-ft. The main span unit is supported by two CIP, 316-ft tall, diamond shaped towers, founded on large diameter drilled shafts with rock sockets. When completed, the 900-ft main span will be the longest span the Ohio DOT has built. The contract value for construction of the new structure and removal of the existing is $81,266,742.05, with Brayman Construction Corporation the low bidder. Recent Construction Highlights - Main Span Kentucky Back Span & Tower 3: A picture taken from the existing bridge shows the partially completed back span false work between Pier 2 and Tower 3. The Tower 3 formwork for Segment 3 remains in place while the recently placed concrete is curing. In the distance the AK Steel mill can be seen. Page 1 of 8

Tower 3(KY) Segment 4: Rebar for Tower 3 Segment 4 is installed as Rob Baker (Figg) counts the individual bars and verifies their location. (right). Tower 3 (KY) Bridge Health Monitoring: Shown tied to the rebar in Tower 3 Segment 4 is a vibrating wire strain gauge. This sensor along with others in the Towers and in the superstructure will be used to collect scientific measurements of predetermined design and maintenance parameters throughout the life of the structure. (Left) Page 2 of 8

Tower 4 (OH) Footing Cell: The downstream half of the Tower 4 footing cell walls have been cast. Crews are currently forming the upstream half of the walls (above). Water stopping seals have been cast in the construction joints to prevent water from entering the cell once it is submerged and de watered (right). Page 3 of 8

Recent Construction Highlights Approaches Kentucky Approach: Setting of the Kentucky approach steel girders was completed in early September. Using the turn-of-thenut method Ironworkers tighten the 372 bolts that make up a single connection (above). The span from the Kentucky abutment to Pier 1 is currently being formed for the cast in place deck (left). Page 4 of 8

Scheduled Actual Select Milestone Events (Schedule Update 13) Date Date Notice to Proceed 3Feb12 Open Bridge to Traffic 25Apr16 End Project 2Feb17 Ohio Approach Set Structural Steel Ohio Approach Complete Deck Concrete Ohio Approach Main Span Cast KY Tower Footing Cast OH Tower Footing Cast First KY Tower Section Cast Last KY Tower Section Cast First OH Tower Section Cast Last OH Tower Section Complete KY Back span Complete OH Back span Set form traveler KY Tower Set form traveler OH Tower Main span Closure Pour Kentucky Approach Set Structural Steel Kentucky Approach Complete Deck Concrete KY Approach 21Jan14 8Apr14 17Dec13 3Jul14 29Jan14 26Feb15 21Jan14 18Sep14 11Sep14 19May15 30Nov15 4Nov13 10May13 14June13 6Sept13 % Complete ($) Paid $32.6M/Total $81.5M 40.0% % Complete (Time) Day 575 of 1795 32.0% Bridge and Roadway Summary At Tower 3 (KY), Segment 3 was cast on September 16, 2013. Work for Segment 4 is ongoing and placement is expected in the next week. Work at the Pier #2 (KY) integral cap is completed placement 4 of 4 was made on September 12, 2013. At Tower 4(OH), construction of the pre cast tub is ongoing. The bottom soffit of the tub is cast and in place around the drilled shaft casings. The first half of the vertical walls of the tub were cast on September 20, 2013. The second half of the tub walls will be cast in the next two weeks. Carr concrete continues offsite pre casting of the back span floor beams. Currently 26 of the 52 beams have been completed. All Ohio approach substructure elements are complete except for the forward Abutment (OH). Steel girder erection for the Ohio approach is scheduled for late fall 13. Work at the Ohio approach continues to focus on the street improvements. Second Street remains closed. Sub contractor Boone-Coleman continues work on approach embankment and MSE wall construction. All Kentucky approach substructure elements are completed. Steel girder erection is 100% complete. Forming of the deck for the first placement is underway. Page 5 of 8

Tower 3 (KY) Progress thru 10/1/13 Page 6 of 8

Substructure Progress Chart thru 10/1/13 Kentucky Approach Ohio Approach Rear (KY) Abutment % complete Pier 6 % complete Drilled shafts 12 of 12 100 Pile Installed 24 of 24 100 Footing 7 of 7 100 Footing 100 Backwall 2 of 2 100 Stem 100 Wing walls 6 of 6 100 Cap 100 Pier 1 Pier 7 Drilled shafts 3 of 3 100 Pile Installed 24 of 24 100 Footing 100 Footing 100 Stem 100 Stem 100 Cap 100 Cap 100 Main Span Pier 2 Pier 8 Drilled shafts 6 of 6 100 Pile Installed 27 of 27 100 Footing 100 Footing 100 Pier Segment 3 of 3 100 Stem 100 Diaphragm Segment 4 of 4 100 Cap 100 Pier 3 (Ky Tower) Forward (OH) Abutment Drilled shafts 6 of 6 100 Pile Installed 22 of 22 100 Footing 100 Footing 0 Tower Segments 3 of 18 16 Backwall 0 of 2 0 Wingwalls 0 of 2 0 Pier 4 (OH Tower) Drilled shafts 6 of 6 100 Footing 0 Tower Segments 0 of 18 0 Pier 5 Drilled shafts 4 of 4 100 Footing 100 Pier Segments 2 of 2 100 Diaphragm Segment 1 of 4 25 Page 7 of 8

Superstructure Progress Chart thru 10/1/13 Precast Floorbeams # cast % cast 52 pieces total 42 of 52 81 Precast Anchorblocks # cast % cast 108 pieces total 6 of 108 6 Main Span Unit % complete Kentucky Back span Segments 0 of 12 0 Ohio Back span Segments 0 of 12 0 Kentucky Cantilever Segments 0 of 15 0 Ohio Cantilever Segments 0 of 15 0 Kentucky Approach % complete Girders Fabricated 24 of 24 100 Girders Erected 24 of 24 100 Deck Castings 0 of 3 0 Ohio Approach % complete Girders Fabricated 35 of 35 100 Girders Erected 0 of 35 0 Deck Castings 0 of 4 0 Page 8 of 8